Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
SlideShare a Scribd company logo
RAB Update - IR Site 25
            March 10, 2011
                     ,




Presenter: Bryce Bartelma, Navy Project Manager

                       1
IR Site 25

IR Site 25 encompasses approximately 230 acres and was constructed for use
   as part of the Moffett Field stormwater management system since 1953.




             AOI-14




     The Navy is coordinating remedial action activities with NASA as they
  prepare to conduct their cleanup activities at Area of Investigation (AOI)-14
                                        2
Pre-
           Pre-Design Investigation of Sediment


•   Conducted pre-design field work in November and December 2010:

     – Site reconnaissance to evaluate location and access points for Remedial
       Action, sensitive species, wetlands, and baseline conditions

     – Surveying – Light Detection and Ranging (LiDAR) with ground truth for a
       topographic survey

     – Collect sediment samples from the top 0.5 feet for chemical analysis and
       top 3 feet for physical analysis using handheld tools and equipment

     – Collect bulk soil samples for a laboratory treatability study




                                         3
LiDAR Land Survey

LiDAR, which uses laser pulses and optical remote sensing, is a state-of-
the-art surveying technique that was conducted by slowly driving around
             y g        q                         y     y       g
the perimeter of IR Site 25. LiDAR is highly accurate and cost effective for
large areas such as IR Site 25. Highly vegetated areas required standard
“ground truth” surveying (with biological monitor observance).




                                    4
Pre-
       Pre-Design Investigation of Sediment

IR Site 25 stormwater typically evaporates completely during the Summer
months, which would’ve allowed for foot access to all sampling locations.
        ,                                                p g




                                   5
Pre-
      Pre-Design Investigation of Sediment

Increased amount of rainfall throughout 2009 and 2010 did not allow IR
Site 25 to fully evaporate, which required a unique sampling approach.
               y    p     ,         q           q      p g pp




                                  6
Air Boat

The air boat is capable of moving across very shallow water (one inch
deep). Utility locators, surveyors, and sediment samplers were shuttled to
each location to complete the pre-design fieldwork .
   hl    ti t          l t th       d i fi ld     k




                                   7
Air Boat Sample Collection


Twenty-eight (28) sediment samples were collected for chemical (PCBs,
pesticides, lead and zinc) analysis (hand auger sample on left) and
eighteen (18) sediment samples were collected for geotechnical analysis
(undisturbed tube on right) to refine the remedial design.




                                   8
Chemical Sample Locations




            9
Physical Sample Locations




            10
Treatability Study

•   In addition to the chemical and geotechnical samples, five (5) bulk soil
    samples were sent to a laboratory for a treatability study. Results of
        p                             y                y     y
    the study will be provided in the Pre-Design Completion Report and will
    recommend a reagent suitable to stabilize metals in soil.
•   Testing three (3) reagents:
          g       ( )    g
     – Terra-Bond™
     – EnviroBlend®
     – ECOBOND®
•   What does this all mean? If
    concentrations of lead in soil are
    g
    greater than or equal to 100
                     q
    mg/kg, that soil will be segregated
    into a separate stockpile for
    additional lab analysis and
    possible mixing with a stabilizing
    agent before disposal.
                                          11
Site 25 Remedial Action Areas
(
(Before Pre-Design Sampling)
        Pre-    g      p g)




              12
Site 25 Remedial Action Areas
                       (
                       (After Pre-Design Sampling)
                              Pre-    g      p g)

•   Pre-design sampling           Removed
    resulted in a >3 acre                   Added
                                  Polygon
    reduction in the overall                Polygon
    areas requiring remedial
    action (total = 31.9 acres)

•   Sample results will be
    presented in a Completion
    Report and will also be
    incorporated into a
    Remedial Design/Remedial
    Action Work Plan
    (RD/RAWP)

•   The RD/RAWP will detail
    the excavation of sediment
    from areas above the
    remedial action objective,
    with field activities
    commencing in
    Summer/Fall 2011
                                       13
Remedial Action Challenges

•   Rainfall/Discharge
•   Heavy Equipment Access
•   Recently Opened Portion of the Bay Trail
•   Special Species
•   Vegetation R
    V    t ti Removal  l




                                  14
Questions?




     15

More Related Content

Moffett RAB Site 25 Update

  • 1. RAB Update - IR Site 25 March 10, 2011 , Presenter: Bryce Bartelma, Navy Project Manager 1
  • 2. IR Site 25 IR Site 25 encompasses approximately 230 acres and was constructed for use as part of the Moffett Field stormwater management system since 1953. AOI-14 The Navy is coordinating remedial action activities with NASA as they prepare to conduct their cleanup activities at Area of Investigation (AOI)-14 2
  • 3. Pre- Pre-Design Investigation of Sediment • Conducted pre-design field work in November and December 2010: – Site reconnaissance to evaluate location and access points for Remedial Action, sensitive species, wetlands, and baseline conditions – Surveying – Light Detection and Ranging (LiDAR) with ground truth for a topographic survey – Collect sediment samples from the top 0.5 feet for chemical analysis and top 3 feet for physical analysis using handheld tools and equipment – Collect bulk soil samples for a laboratory treatability study 3
  • 4. LiDAR Land Survey LiDAR, which uses laser pulses and optical remote sensing, is a state-of- the-art surveying technique that was conducted by slowly driving around y g q y y g the perimeter of IR Site 25. LiDAR is highly accurate and cost effective for large areas such as IR Site 25. Highly vegetated areas required standard “ground truth” surveying (with biological monitor observance). 4
  • 5. Pre- Pre-Design Investigation of Sediment IR Site 25 stormwater typically evaporates completely during the Summer months, which would’ve allowed for foot access to all sampling locations. , p g 5
  • 6. Pre- Pre-Design Investigation of Sediment Increased amount of rainfall throughout 2009 and 2010 did not allow IR Site 25 to fully evaporate, which required a unique sampling approach. y p , q q p g pp 6
  • 7. Air Boat The air boat is capable of moving across very shallow water (one inch deep). Utility locators, surveyors, and sediment samplers were shuttled to each location to complete the pre-design fieldwork . hl ti t l t th d i fi ld k 7
  • 8. Air Boat Sample Collection Twenty-eight (28) sediment samples were collected for chemical (PCBs, pesticides, lead and zinc) analysis (hand auger sample on left) and eighteen (18) sediment samples were collected for geotechnical analysis (undisturbed tube on right) to refine the remedial design. 8
  • 11. Treatability Study • In addition to the chemical and geotechnical samples, five (5) bulk soil samples were sent to a laboratory for a treatability study. Results of p y y y the study will be provided in the Pre-Design Completion Report and will recommend a reagent suitable to stabilize metals in soil. • Testing three (3) reagents: g ( ) g – Terra-Bond™ – EnviroBlend® – ECOBOND® • What does this all mean? If concentrations of lead in soil are g greater than or equal to 100 q mg/kg, that soil will be segregated into a separate stockpile for additional lab analysis and possible mixing with a stabilizing agent before disposal. 11
  • 12. Site 25 Remedial Action Areas ( (Before Pre-Design Sampling) Pre- g p g) 12
  • 13. Site 25 Remedial Action Areas ( (After Pre-Design Sampling) Pre- g p g) • Pre-design sampling Removed resulted in a >3 acre Added Polygon reduction in the overall Polygon areas requiring remedial action (total = 31.9 acres) • Sample results will be presented in a Completion Report and will also be incorporated into a Remedial Design/Remedial Action Work Plan (RD/RAWP) • The RD/RAWP will detail the excavation of sediment from areas above the remedial action objective, with field activities commencing in Summer/Fall 2011 13
  • 14. Remedial Action Challenges • Rainfall/Discharge • Heavy Equipment Access • Recently Opened Portion of the Bay Trail • Special Species • Vegetation R V t ti Removal l 14