                      Scrum for the enterprise
                               Mário André Araújo
                              mario.araujo@outsystems.com
Scrum Meeting Lisbon 2010 By Mario Andre Araujo
Agenda
• Why listen to OutSystems?
• Challenges when delivering for the Enterprise
  1.   Deal with fixed price projects
  2.   Where’s the Product Owner?
  3.   Dealing with immature teams
  4.   Handling distributed teams
Let’s look at OutSystems
Software Houses            IT Consulting Shops

• Make and sell software   • Implement and deploy IT
  products                   solutions
   – SalesForce               – Professional Services
   – Alert                    – Staffing firms
   – Adobe                    – Independent consultants




                                                          Source: Wikipedia
R&D

                           +
• Software House
• Several scrum teams
  – Over 2,000,000 lines of code
  – 100,000 lines of code per developer
  – 6185 installations
Professional Services
• IT Consultancy Shop
                                   If it’s bold, it must
                                       be important



• Delivered over 600 enterprise
  agile projects
• 128 customers
• 16 industries
  – Banking, Telecom, Insurance,
    HealthCare,…
• 51 implementation partners
Agenda
• About OutSystems
• Challenges when delivering for the enterprise
  1.   Deal with fixed price projects
                                        Let’s focus!

  2.   Where’s the Product Owner?
  3.   Dealing with immature teams
  4.   Handling distributed teams
1. Deal with fixed price projects


    1. The budgeting
         process
1. Deal with fixed price projects
• Guess what?
  – The Product Owner is not available.
  – The team is not available.
  – The customer has to know:
                                            It’s about
     • How much will it cost?             predictability


     • When will it be released?
1. Deal with fixed price projects
                       Step 1
                   Create high level
                     user stories




          Step 3                      Step 2
      Calculate effort             Size the user
     and release plan                 stories
1. Deal with fixed price projects
                                2. Size




1. Scope
                                  3. Release
                                     Plan
1. Deal with fixed price projects
• Supply chain management
  – Budgeting effort: 1 day
  – 150 days, 12 weeks
• Business support to a start-up
  – Budgeting effort: 2 days
  – 250 days, 16 weeks
• Insolvency services management
  – Budgeting effort: 3 days
  – 875 days, 36 weeks
Agenda
• About OutSystems
• Challenges when delivering for the enterprise
  1.   Deal with fixed price projects
                                        Let’s focus!

  2.   Where’s the Product Owner?
  3.   Dealing with immature teams
  4.   Handling distributed teams
WHERE’S
                       THE PRODUCT
                         OWNER?




Source: http://media.photobucket.com/image/Where%252527s%20waldo/premium2125/waldo.jpg
2. Where’s the Product Owner?
Business Sponsor
    –   Provides the vision of the overall solution
    –   Agrees and approves business timelines                         –   Ensure the vision is
                                                                           executed by the team
    –   Empower the Business Manager to act in
                                                                       –   Agrees and approves
        behalf of the organization in bringing about                       business timelines
        a successful project                                           –   Owns the product backlog
Business Manager                                       Product Owner   –   PO is empowered to
                                                                           prioritize
    –   Provides guidance in the overall scope of                      –   PO has direct contact with
        the project                                                        the team
    –   Reviews the features, stories, and estimates                   –   PO has direct contact with
        and provide input                                                  stakeholders

    –   Ensures that the Key Business Users are
        available for the Budgeting stage
Key Business User
    –   Works with the Engagement Manager and
        IT Business Analyst to identify and detail
        the user stories
    –   Involves other users as necessary to clarify
        the business requirements
    –   Confirms the features and stories
2. Where’s the Product Owner?
Business Sponsor
    –   Provides the vision of the overall solution
    –   Agrees and approves business timelines                         –   Ensure the vision is
                                                                           executed by the team
    –   Empower the Business Manager to act in
                                                                       –   Agrees and approves
        behalf of the organization in bringing about                       business timelines
        a successful project                                           –   Owns the product backlog
Business Manager                                       Product Owner   –   PO is empowered to
                                                                           prioritize
    –   Provides guidance in the overall scope of                      –   PO has direct contact with
        the project                                                        the team
    –   Reviews the features, stories, and estimates                   –   PO has direct contact with
        and provide input                                                  stakeholders

    –   Ensures that the Key Business Users are
        available for the Budgeting stage
Key Business User
    –   Works with the Engagement Manager and
        IT Business Analyst to identify and detail
        the user stories
    –   Involves other users as necessary to clarify
        the business requirements
    –   Confirms the features and stories
WHERE’S
                            THE PRODUCT
                              OWNER?
PO




     Source: http://media.photobucket.com/image/Where%252527s%20waldo/premium2125/waldo.jpg
Agenda
• About OutSystems
• Challenges when delivering for the enterprise
  1.   Deal with fixed price projects
                                        Let’s focus!

  2.   Where’s the Product Owner?
  3.   Dealing with immature teams
  4.   Handling distributed teams
3. Dealing with immature teams
          Team   Individual
3. Dealing with immature teams
• Team evolution towards self-management:
    – Stage 1: the typical hierarchical structure
    – Stage 2: the leader is a team coordinator/coach
    – Stage 3: members coached to take on more leadership
      tasks
    – Stage 4: the team assumes most of the duties previously
      reserved for the group manager
    – Stage 5: The group manager is a resource for the team



                                                    Source: http://www.saferpak.com/teamwork_articles/ensuring_success.pdf
Zawacki, R. A. and C. A. Norman. "Successful Self-Directed Teams and Planned Change: A Lot in Common." OD Practitioner
3. Dealing with immature teams
• Dreyfus model of skill acquisition
  –   Beginner
  –   Advanced Beginner
  –   Competent
  –   Proficient
  –   Expert        Secret sauce for
                      Agile Teams
3. Dealing with immature teams
           Team           Individual

                           Start from
           Coaching        tasks and
          towards exit      move to
                             stories

                          Technology
         It’s my way or
                           with fast
          the highway
                           ramp-up
Agenda
• About OutSystems
• Challenges when delivering for the enterprise
  1.   Deal with fixed price projects
                                        Let’s focus!

  2.   Where’s the Product Owner?
  3.   Dealing with immature teams
  4.   Handling distributed teams
New York                               fly.com
                GMT -4
                e.g. 14:00
                                                Lisbon
                Customer Product                GMT
                Managers                        e.g. 18:00

                                                Integrations team




                                   Lisbon
San Francisco                      GMT
GMT -8                             e.g. 18:00
e.g. 10:00
                                   Web development team
Customer IT                        OutSystems PO
OutSystems PO                      7 team members
4. Handling distributed teams
• Duration
   –   32 weeks
   –   Number of Sprints: 14
   –   Demos and retrospectives at the end of Sprint
   –   250 change requests (using Agile Platform Embedded Change Technology)
   –   4 week tuning sprint & 4 versions released during tuning
• Team
   –   1 Business Sponsor
   –   1 Business Analyst
   –   2 Product Owners
   –   1 Scrum Master
   –   6 Developers
   –   7 Key users
4. Handling distributed teams
• Challenges
  – Globally distributed stakeholders
     • Time zones
  – Feedback
     • Get feedback from all stakeholders
     • Make that feedback available to process
     • Make it easy to give and process that feedback
  – Getting consensus and avoiding entropy
     • Arbitration of all stakeholders
     • OutSystems PO is a facilitator
  – Communication
     • Where’s the team board?
Thank you



     www.outsystems.com

   mario.araujo@outsystems.com

More Related Content

Scrum Meeting Lisbon 2010 By Mario Andre Araujo

  • 1. http://scrumpt.com/ Scrum for the enterprise Mário André Araújo mario.araujo@outsystems.com
  • 3. Agenda • Why listen to OutSystems? • Challenges when delivering for the Enterprise 1. Deal with fixed price projects 2. Where’s the Product Owner? 3. Dealing with immature teams 4. Handling distributed teams
  • 4. Let’s look at OutSystems Software Houses IT Consulting Shops • Make and sell software • Implement and deploy IT products solutions – SalesForce – Professional Services – Alert – Staffing firms – Adobe – Independent consultants Source: Wikipedia
  • 5. R&D + • Software House • Several scrum teams – Over 2,000,000 lines of code – 100,000 lines of code per developer – 6185 installations
  • 6. Professional Services • IT Consultancy Shop If it’s bold, it must be important • Delivered over 600 enterprise agile projects • 128 customers • 16 industries – Banking, Telecom, Insurance, HealthCare,… • 51 implementation partners
  • 7. Agenda • About OutSystems • Challenges when delivering for the enterprise 1. Deal with fixed price projects Let’s focus! 2. Where’s the Product Owner? 3. Dealing with immature teams 4. Handling distributed teams
  • 8. 1. Deal with fixed price projects 1. The budgeting process
  • 9. 1. Deal with fixed price projects • Guess what? – The Product Owner is not available. – The team is not available. – The customer has to know: It’s about • How much will it cost? predictability • When will it be released?
  • 10. 1. Deal with fixed price projects Step 1 Create high level user stories Step 3 Step 2 Calculate effort Size the user and release plan stories
  • 11. 1. Deal with fixed price projects 2. Size 1. Scope 3. Release Plan
  • 12. 1. Deal with fixed price projects • Supply chain management – Budgeting effort: 1 day – 150 days, 12 weeks • Business support to a start-up – Budgeting effort: 2 days – 250 days, 16 weeks • Insolvency services management – Budgeting effort: 3 days – 875 days, 36 weeks
  • 13. Agenda • About OutSystems • Challenges when delivering for the enterprise 1. Deal with fixed price projects Let’s focus! 2. Where’s the Product Owner? 3. Dealing with immature teams 4. Handling distributed teams
  • 14. WHERE’S THE PRODUCT OWNER? Source: http://media.photobucket.com/image/Where%252527s%20waldo/premium2125/waldo.jpg
  • 15. 2. Where’s the Product Owner? Business Sponsor – Provides the vision of the overall solution – Agrees and approves business timelines – Ensure the vision is executed by the team – Empower the Business Manager to act in – Agrees and approves behalf of the organization in bringing about business timelines a successful project – Owns the product backlog Business Manager Product Owner – PO is empowered to prioritize – Provides guidance in the overall scope of – PO has direct contact with the project the team – Reviews the features, stories, and estimates – PO has direct contact with and provide input stakeholders – Ensures that the Key Business Users are available for the Budgeting stage Key Business User – Works with the Engagement Manager and IT Business Analyst to identify and detail the user stories – Involves other users as necessary to clarify the business requirements – Confirms the features and stories
  • 16. 2. Where’s the Product Owner? Business Sponsor – Provides the vision of the overall solution – Agrees and approves business timelines – Ensure the vision is executed by the team – Empower the Business Manager to act in – Agrees and approves behalf of the organization in bringing about business timelines a successful project – Owns the product backlog Business Manager Product Owner – PO is empowered to prioritize – Provides guidance in the overall scope of – PO has direct contact with the project the team – Reviews the features, stories, and estimates – PO has direct contact with and provide input stakeholders – Ensures that the Key Business Users are available for the Budgeting stage Key Business User – Works with the Engagement Manager and IT Business Analyst to identify and detail the user stories – Involves other users as necessary to clarify the business requirements – Confirms the features and stories
  • 17. WHERE’S THE PRODUCT OWNER? PO Source: http://media.photobucket.com/image/Where%252527s%20waldo/premium2125/waldo.jpg
  • 18. Agenda • About OutSystems • Challenges when delivering for the enterprise 1. Deal with fixed price projects Let’s focus! 2. Where’s the Product Owner? 3. Dealing with immature teams 4. Handling distributed teams
  • 19. 3. Dealing with immature teams Team Individual
  • 20. 3. Dealing with immature teams • Team evolution towards self-management: – Stage 1: the typical hierarchical structure – Stage 2: the leader is a team coordinator/coach – Stage 3: members coached to take on more leadership tasks – Stage 4: the team assumes most of the duties previously reserved for the group manager – Stage 5: The group manager is a resource for the team Source: http://www.saferpak.com/teamwork_articles/ensuring_success.pdf Zawacki, R. A. and C. A. Norman. "Successful Self-Directed Teams and Planned Change: A Lot in Common." OD Practitioner
  • 21. 3. Dealing with immature teams • Dreyfus model of skill acquisition – Beginner – Advanced Beginner – Competent – Proficient – Expert Secret sauce for Agile Teams
  • 22. 3. Dealing with immature teams Team Individual Start from Coaching tasks and towards exit move to stories Technology It’s my way or with fast the highway ramp-up
  • 23. Agenda • About OutSystems • Challenges when delivering for the enterprise 1. Deal with fixed price projects Let’s focus! 2. Where’s the Product Owner? 3. Dealing with immature teams 4. Handling distributed teams
  • 24. New York fly.com GMT -4 e.g. 14:00 Lisbon Customer Product GMT Managers e.g. 18:00 Integrations team Lisbon San Francisco GMT GMT -8 e.g. 18:00 e.g. 10:00 Web development team Customer IT OutSystems PO OutSystems PO 7 team members
  • 25. 4. Handling distributed teams • Duration – 32 weeks – Number of Sprints: 14 – Demos and retrospectives at the end of Sprint – 250 change requests (using Agile Platform Embedded Change Technology) – 4 week tuning sprint & 4 versions released during tuning • Team – 1 Business Sponsor – 1 Business Analyst – 2 Product Owners – 1 Scrum Master – 6 Developers – 7 Key users
  • 26. 4. Handling distributed teams • Challenges – Globally distributed stakeholders • Time zones – Feedback • Get feedback from all stakeholders • Make that feedback available to process • Make it easy to give and process that feedback – Getting consensus and avoiding entropy • Arbitration of all stakeholders • OutSystems PO is a facilitator – Communication • Where’s the team board?
  • 27. Thank you www.outsystems.com mario.araujo@outsystems.com