Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
SlideShare a Scribd company logo

1

Engineer
Mohamed Esmat Abdelrazek
PMP
Project Management
professional

2

PMP CertificatePMBOK 4th Edition

3

PMP certificate requirements

4

Project Framework & initiation

5

?What is a project
Temporary endeavor undertaken to create a uniqe service or
product or result
Temporary: means definite beginning and definite end
Uniqe :different design, different location , different
circumstance …etc
Progressive elaboration:
“continuously improving and detailing a plan as more detailed and
specific information and more accurate estimates become
available as the project progresses,

6

operationproject
1-temporary 1-permenant
2-unique 2-repetitive
VS
example example
Constructing a building Production line

7

?What is Project Management
the application of
knowledge, skills, tools,
and techniques to
project activities to
meet the project
requirements

8

Project manager
Personal skills performance
knowledge

9

:Who is Stakeholder ?
Stakeholders are the people involved in or
affected by project activities

10

• stakeholders
- Customer (owner)
- Sponsor
- consultant
- Consumer (doctors)
- Government authorities
- Suppliers
- Project team
Hospital Construction Project

11

Project constraints:
-Scope
-Time
-Cost
-quality
-risk
-Resource
SCOPE
Triple Constraints

12

CHARACTERISTICS OF PROJECT LIFE CYCLE
• Cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the project
draws to a close.

13

Stakeholder influences, risk, and uncertainty, are greatest at the start of the project. These factors decrease over
the life of the project.
The cost of changes and correcting errors typically increases substantially as the project approaches
completion.

14

Project Management Process Groups
Mapped to the Plan-Do-Check-Act Cycle

15

- The Process Groups are seldom either discrete or one-time events; they are
overlapping activities that occur throughout the project.

16

Process Interactions
•Inputs
• Document s or
documentable items
that will be acted
upon
Tools &
Techniques
Mechanisms applied to
inputs to create output
Outputs
Document s or documentable
items that are a result of a
process

17

•Process Groups & Knowledge Areas Mapping
Knowledge Area
Process
Initiating Planning Executing Monitoring & Control Closing
Integration Develop
Project
Charter
Develop Project Management
Plan
Direct and Manage Project
Execution
Monitor and Control Project
Work
Perform Integrated Change
Control
Close Project
Scope Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope
Time Define Activities
Sequence Activities
Estimate Activities Resources
Estimate Activities Duration
Develop Schedule
Control Schedule
Cost Estimate Costs
Determine Budget
Control Costs
Quality Plan Quality Perform Quality Assurance Perform Quality Control
Human
Resource
Develop Human Resources Plan Acquire Project Team
Develop Project Team
Manage Project Team
Communication Identify
Stakeholders
Plan Communications Distribute Information
Manage Stakeholders
Expectations
Report Performance
Risk Plan Risk Management
Identify Risk
Perform Qualitative Risk Analysis
Perform Quantitative Risk
Analysis
Plan Risk Response
Monitor and Control Risks
Procurement Plan Procurements Conduct Procurements Administer Procurements Close
Procurements

18

• Projects are means of
– Achieving organization’s strategic plan.
• Projects are result of one or more of the
following :
Market demand
Strategic opportunity/business need
Legal requirements
Ecological Impacts
Social need
Projects and Strategic Planning

19

Project
management
program
management
portfolio
management
Organization
strategy
ORGANIZATIONAL STRATEGIC HIERARCHY

20

:ManagementProgram
Group of related Projects in a coordinated way
to obtain benefits and control
:Portfolio Management
collection of projects or programs and other
work that are grouped together to facilitate
effective management of that work to meet
strategic business objectives

21

Project Management Office (PMO)
* A department that centralizes the management of projects.
Roles of PMO
•Project Support: Provide project management guidance to project
managers in business units.
•Project Management Process/Methodology: Develop and implement
a consistent and standardized process.
•Training: Conduct training programs or collect requirements for an
outside company
A primary function of a PMO is to support project managers in a variety of ways

22

Thank you

More Related Content

Session 1 PMP 4th edition

  • 4. Project Framework & initiation
  • 5. ?What is a project Temporary endeavor undertaken to create a uniqe service or product or result Temporary: means definite beginning and definite end Uniqe :different design, different location , different circumstance …etc Progressive elaboration: “continuously improving and detailing a plan as more detailed and specific information and more accurate estimates become available as the project progresses,
  • 6. operationproject 1-temporary 1-permenant 2-unique 2-repetitive VS example example Constructing a building Production line
  • 7. ?What is Project Management the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements
  • 8. Project manager Personal skills performance knowledge
  • 9. :Who is Stakeholder ? Stakeholders are the people involved in or affected by project activities
  • 10. • stakeholders - Customer (owner) - Sponsor - consultant - Consumer (doctors) - Government authorities - Suppliers - Project team Hospital Construction Project
  • 12. CHARACTERISTICS OF PROJECT LIFE CYCLE • Cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the project draws to a close.
  • 13. Stakeholder influences, risk, and uncertainty, are greatest at the start of the project. These factors decrease over the life of the project. The cost of changes and correcting errors typically increases substantially as the project approaches completion.
  • 14. Project Management Process Groups Mapped to the Plan-Do-Check-Act Cycle
  • 15. - The Process Groups are seldom either discrete or one-time events; they are overlapping activities that occur throughout the project.
  • 16. Process Interactions •Inputs • Document s or documentable items that will be acted upon Tools & Techniques Mechanisms applied to inputs to create output Outputs Document s or documentable items that are a result of a process
  • 17. •Process Groups & Knowledge Areas Mapping Knowledge Area Process Initiating Planning Executing Monitoring & Control Closing Integration Develop Project Charter Develop Project Management Plan Direct and Manage Project Execution Monitor and Control Project Work Perform Integrated Change Control Close Project Scope Collect Requirements Define Scope Create WBS Verify Scope Control Scope Time Define Activities Sequence Activities Estimate Activities Resources Estimate Activities Duration Develop Schedule Control Schedule Cost Estimate Costs Determine Budget Control Costs Quality Plan Quality Perform Quality Assurance Perform Quality Control Human Resource Develop Human Resources Plan Acquire Project Team Develop Project Team Manage Project Team Communication Identify Stakeholders Plan Communications Distribute Information Manage Stakeholders Expectations Report Performance Risk Plan Risk Management Identify Risk Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Response Monitor and Control Risks Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurements
  • 18. • Projects are means of – Achieving organization’s strategic plan. • Projects are result of one or more of the following : Market demand Strategic opportunity/business need Legal requirements Ecological Impacts Social need Projects and Strategic Planning
  • 20. :ManagementProgram Group of related Projects in a coordinated way to obtain benefits and control :Portfolio Management collection of projects or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives
  • 21. Project Management Office (PMO) * A department that centralizes the management of projects. Roles of PMO •Project Support: Provide project management guidance to project managers in business units. •Project Management Process/Methodology: Develop and implement a consistent and standardized process. •Training: Conduct training programs or collect requirements for an outside company A primary function of a PMO is to support project managers in a variety of ways