Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
SlideShare a Scribd company logo
Former NAS Moffett Field


Site 25 Remedial Action Update
         Bryce Bartelma, PG
      Salient Federal Solutions
             supporting
       Navy BRAC PMO West

        November 29, 2012
           RAB Meeting
IR Site 25

IR Site 25 encompasses approximately 230 acres and was constructed for use
   as part of the Moffett Field storm water management system since 1953




           AOI-14




     The Navy is coordinating remedial action activities with NASA as they
  prepare to conduct their cleanup activities at Area of Investigation (AOI)-14
                                        2
Remedial Design and
                 Remedial Action Work Plan


• Final Remedial Design
  and Remedial Action
  Work Plan (RD/RAWP)
  distributed on March 30

• Removal of over 32,500
  cubic yards of sediment
  from nearly 32 acres

• Planned excavation
  depths of 0.5 – 1.5 feet
  below ground surface

• Restore vegetated
  areas with pickleweed
  and other native grass
                             3
Temporarily Re-route
Storm Water & WATS effluent




                 Storm Water
                 Settling Vault



                     Catch Basin




             4
August 2012 Conditions at IR Site 25




                  5
Biological Observations at Site 25

                 NESTING
•   Alameda Song Sparrow
•   Western Harrier
•   Mockingbird, marsh wren, bushtit and
    killdeer
                OBSERVED
•   Harvest Mice (unidentified subspecies)
•   Deer Mice & Voles
•   California Least Tern (in flight)
•   Black Rail (vocalizing)
•   Fox, jackrabbit, and gopher snake

             NOT OBSERVED
•   Western Pond Turtle (WPT)
•   Western Snowy Plover
•   California Clapper Rail                  6
Biological Protection Measures



                     PROTECTION MEASURES

                   1. Visually inspect/clear vegetation
                      prior to removal
                   2. Hand remove pickleweed
                   3. Silt fencing along access points
                      and suitable habitat areas
                   4. Continuous biological
                      monitoring
                   5. Coordination with CDFG and
                      USFWS



               7
Sediment Excavations


        •       Planned excavation depths of 0.5 – 1.5
                feet below ground surface
        •       Field surveying to verify dig depths
        •       Grid confirmation sampling




            8
Over-excavations


      •       Several samples confirmed additional
              over-excavation was required
      •       Primarily in Eastern Diked Marsh (EDM)
      •       Depths of up to 5 feet below ground
              surface (EDM) encountered groundwater




          9
IR Site 25 Remedial Action Facts


•   Excavation depths of 0.5 to 5.0
    feet below ground surface
•   36,390 cubic yards of sediment
    from nearly 32 acres
•   19,500 linear feet of biological silt
    fencing
•   Utilized up to 14 biologists
•   Bypassed 15,724,800 gallons of
    WATS and storm water
•   236 confirmation samples
•   173 days with up to 40 workers
    (over 23,502 hours) on site
•   2,173 truck loads of sediment
    transported to landfill
                                            10
Aerial Imagery




       11
Aerial Imagery




       12
Vegetation Restoration


•   All vegetation areas removed
    during Remedial Action will be
    restored (excludes EDM and                  Pickleweed
    inundated mud flats)                        Salicornia
                                                virginica
•   Two types of hydroseed palettes
    (High Salt Marsh and Transitional
    Upland) will be used with
    majority of seeds including
    pickleweed and saltgrass

•   Minimum of two years monitoring             Saltgrass
    and maintenance                             Distichlis
                                                spicata
•   Options for irrigation services and
    additional hydroseeding/plantings


                                          13
Schedule



• Sediment Excavations and
  Disposal
  Completed
• Vegetation Restoration
  Nov./Dec. 2012
• Vegetation Monitoring
  Ongoing
• Submit Remedial Action
  Completion Report
  Spring 2013



                                 14
Questions?




          Point of Contact:

           Scott Anderson
   BRAC Environmental Coordinator
           (619) 532-0938
     scott.d.anderson@navy.mil




     15

More Related Content

Site 25 rab nov 29 2012

  • 1. Former NAS Moffett Field Site 25 Remedial Action Update Bryce Bartelma, PG Salient Federal Solutions supporting Navy BRAC PMO West November 29, 2012 RAB Meeting
  • 2. IR Site 25 IR Site 25 encompasses approximately 230 acres and was constructed for use as part of the Moffett Field storm water management system since 1953 AOI-14 The Navy is coordinating remedial action activities with NASA as they prepare to conduct their cleanup activities at Area of Investigation (AOI)-14 2
  • 3. Remedial Design and Remedial Action Work Plan • Final Remedial Design and Remedial Action Work Plan (RD/RAWP) distributed on March 30 • Removal of over 32,500 cubic yards of sediment from nearly 32 acres • Planned excavation depths of 0.5 – 1.5 feet below ground surface • Restore vegetated areas with pickleweed and other native grass 3
  • 4. Temporarily Re-route Storm Water & WATS effluent Storm Water Settling Vault Catch Basin 4
  • 5. August 2012 Conditions at IR Site 25 5
  • 6. Biological Observations at Site 25 NESTING • Alameda Song Sparrow • Western Harrier • Mockingbird, marsh wren, bushtit and killdeer OBSERVED • Harvest Mice (unidentified subspecies) • Deer Mice & Voles • California Least Tern (in flight) • Black Rail (vocalizing) • Fox, jackrabbit, and gopher snake NOT OBSERVED • Western Pond Turtle (WPT) • Western Snowy Plover • California Clapper Rail 6
  • 7. Biological Protection Measures PROTECTION MEASURES 1. Visually inspect/clear vegetation prior to removal 2. Hand remove pickleweed 3. Silt fencing along access points and suitable habitat areas 4. Continuous biological monitoring 5. Coordination with CDFG and USFWS 7
  • 8. Sediment Excavations • Planned excavation depths of 0.5 – 1.5 feet below ground surface • Field surveying to verify dig depths • Grid confirmation sampling 8
  • 9. Over-excavations • Several samples confirmed additional over-excavation was required • Primarily in Eastern Diked Marsh (EDM) • Depths of up to 5 feet below ground surface (EDM) encountered groundwater 9
  • 10. IR Site 25 Remedial Action Facts • Excavation depths of 0.5 to 5.0 feet below ground surface • 36,390 cubic yards of sediment from nearly 32 acres • 19,500 linear feet of biological silt fencing • Utilized up to 14 biologists • Bypassed 15,724,800 gallons of WATS and storm water • 236 confirmation samples • 173 days with up to 40 workers (over 23,502 hours) on site • 2,173 truck loads of sediment transported to landfill 10
  • 13. Vegetation Restoration • All vegetation areas removed during Remedial Action will be restored (excludes EDM and Pickleweed inundated mud flats) Salicornia virginica • Two types of hydroseed palettes (High Salt Marsh and Transitional Upland) will be used with majority of seeds including pickleweed and saltgrass • Minimum of two years monitoring Saltgrass and maintenance Distichlis spicata • Options for irrigation services and additional hydroseeding/plantings 13
  • 14. Schedule • Sediment Excavations and Disposal Completed • Vegetation Restoration Nov./Dec. 2012 • Vegetation Monitoring Ongoing • Submit Remedial Action Completion Report Spring 2013 14
  • 15. Questions? Point of Contact: Scott Anderson BRAC Environmental Coordinator (619) 532-0938 scott.d.anderson@navy.mil 15