Cronograma de Adquisicion
Cronograma de Adquisicion
Cronograma de Adquisicion
OBRA: CONSTRUCCION DE LOCAL USOS MULTIPLES EN EL ANEXO DE ILUBAYA, DISTRITO DE TORATA, MARISCAL NIETO- MOQUEGUA
EJECUTA: MUNICIPALIDAD DISTRITAL DE TORATA
FECHA: AGOSTO DEL 2010
PRECIO PROGRAMADO
COSTO
ITEM DESCRIPCION UND CANTIDAD UNITARIO PARCIAL S/.
MES 1 MES 2 MES 3 MES 4
S/.
MANO DE OBRA 122,350.91 36,705.27 36,705.27 30,587.73 18,352.64
1.00 TOPOGRAFO hh 11.17 14.82 165.52 49.66 49.66 41.38 24.83
2.00 OPERARIO hh 2,555.44 13.62 34,805.09 10,441.53 10,441.53 8,701.27 5,220.76
3.00 OFICIAL hh 956.62 12.06 11,536.78 3,461.03 3,461.03 2,884.20 1,730.52
4.00 PEON hh 6,964.51 10.89 75,843.52 22,753.06 22,753.06 18,960.88 11,376.53
EQUIPO Y HERRAMIENTAS 15,262.13 11,797.41 1,484.88 1,237.40 742.44
5.00 JALONES he 10.27 15.00 154.03 154.03
6.00 CAMION VOLQUETE 6 X 4 330 HP 10 m3 hm 64.34 90.00 5,790.96 5,790.96
7.00 ANDAMIO METAL TABLAS ALQUILER est 38.15 10.00 381.47 381.47
8.00 ANDAMIO METALICO hm 89.81 10.00 898.09 898.09
9.00 EQUIPO DE PINTURA hm 3.20 10.00 32.00 32.00
10.00 COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP hm 70.20 15.00 1,053.06 1,053.06
11.00 VIBRADOR DE CONCRETO 4 HP 1.35" hm 25.92 15.00 388.80 388.80
12.00 MEZCLADORA DE CONCRETO TAMBOR 18 HP 11 p3 hm 90.84 15.00 1,362.54 1,362.54
13.00 NIVEL TOPOGRAFICO he 5.65 8.00 45.22 45.22
14.00 TEODOLITO hm 9.05 15.00 135.82 135.82
15.00 NIVEL OPTICO hm 4.70 15.00 70.54 70.54
16.00 HERRAMIENTAS MANUALES % 1.00 4,949.60 4,949.60 1,484.88 1,484.88 1,237.40 742.44
MATERIALES 151,314.05 128,432.95 12,555.43 10,325.67 0.00
18.00 ACEITE PARA MOTOR GRADO 30 gal 0.24 45.00 10.97 10.97
19.00 ALAMBRE NEGRO # 16 kg 321.61 7.50 2,412.05 2,412.05
20.00 ALAMBRE NEGRO # 8 kg 84.99 7.50 637.42 637.42
21.00 CLAVOS PARA MADERA CON CABEZA DE 1" kg 0.28 7.20 1.98 1.98
22.00 CLAVOS PARA MADERA CON CABEZA DE 2" kg 8.00 7.50 60.00 60.00
23.00 CLAVOS PARA MADERA CON CABEZA DE 3" kg 72.05 7.50 540.39 540.39
24.00 CLAVOS PARA CEMENTO DE ACERO CON CABEZA DE 3/4" kg 7.87 7.50 59.01 59.01
25.00 ACERO DE REFUERZO fy=4200 GRADO 60 kg 5,730.59 3.50 20,057.06 20,057.06
26.00 ARENA FINA m3 14.44 80.00 1,155.03 1,155.03
27.00 TIERRA DE CHACRA O VEGETAL m3 7.01 15.00 105.20 105.20
28.00 PIEDRA CHANCADA DE 1/2" m3 42.27 70.00 2,958.64 2,958.64
29.00 PIEDRA CHANCADA DE 3/4" m3 2.02 70.00 141.30 141.30
MUNICIPALIDAD DISTRITAL DE TORATA
OBRA: CONSTRUCCION DE LOCAL USOS MULTIPLES EN EL ANEXO DE ILUBAYA, DISTRITO DE TORATA, MARISCAL NIETO- MOQUEGUA
EJECUTA: MUNICIPALIDAD DISTRITAL DE TORATA
FECHA: AGOSTO DEL 2010
PRECIO PROGRAMADO
COSTO
ITEM DESCRIPCION UND CANTIDAD UNITARIO PARCIAL S/.
MES 1 MES 2 MES 3 MES 4
S/.
30.00 PIEDRA DE CANTO RODADO 6" A 8" m3 33.82 45.00 1,522.04 1,522.04
31.00 PIEDRA MEDIANA DE 4" m3 0.54 40.00 21.60 21.60
32.00 PIEDRA MEDIANA DE 6" m3 1.61 60.00 96.66 96.66
33.00 PIEDRA GRANDE m3 8.28 60.00 496.53 496.53
34.00 MATERIAL GRANULAR SELECCIONADO P/FILTROS D=1/2" m3 2.75 70.00 192.57 192.57
35.00 PIEDRA LAJA m2 86.97 80.00 6,957.86 6,957.86
36.00 ARENA GRUESA m3 50.53 70.00 3,537.38 3,537.38
37.00 MATERIAL DE RELLENO m3 7.11 60.00 426.60 426.60
38.00 CONECTOR 1x16mm2 desnudo m 5.00 10.00 50.00 50.00
39.00 CONECTOR ANDERSON u 1.00 100.00 100.00 100.00
40.00 VARILLA DE COBRE al 99% u 1.00 250.00 250.00 250.00
41.00 CABLE TW # 14 AWG 2.5 mm2 m 364.02 1.60 582.43 582.43
42.00 CABLE TW # 12 AWG - 4 mm2 m 131.25 2.60 341.25 341.25
43.00 CONDUCTOR DE COBRE CONCENTRICO TIPO SET DE 2X10MM2. m 10.00 7.50 75.00 75.00
44.00 CONDUCTOR THW 2-1x8.0 mm2 m 16.80 6.00 100.80 100.80
45.00 INODORO TANQUE BAJO NORMAL BLANCO INCLUYE ACCESORIOS u 3.00 250.00 750.00 750.00
46.00 LAVATORIO 23"X17" PARA GRIFERIA 4" BLANCO CON ACCESORIOS u 2.00 195.00 390.00 390.00
47.00 URINARIO PICO BLANCO u 2.00 150.00 300.00 300.00
48.00 LLAVE CORPORATION DE 1/2" u 1.00 16.50 16.50 16.50
49.00 ACCESORIO DE TANQUE SEPTICO glb 1.00 350.00 350.00 350.00
50.00 REGISTRO DE BRONCE DE 4" u 4.00 14.00 56.00 56.00
51.00 TABLERO GABINETE METAL BARRA BRONCE 12 POLOS pza 1.00 220.00 220.00 220.00
52.00 TOMACORRIENTE DOBLE PLANO BAKELITA u 16.00 8.50 136.00 136.00
53.00 INTERRUPTOR TERMOMAGNETICO DE 2 X 40A u 1.00 60.00 60.00 60.00
54.00 INTERRUPTOR TERMOMAGNETICO DE 2 X 20A u 2.00 40.00 80.00 80.00
55.00 INTERRUPTOR TERMOMAGNETICO DE 2 X 15A u 2.00 40.00 80.00 80.00
56.00 INTERRUPTOR BAKELITA X 1 SWITCH u 6.00 8.50 51.00 51.00
57.00 INTERRUPTOR BAKELITA X 2 SWITCH u 1.00 10.00 10.00 10.00
58.00 INTERRUPTOR BAKELITA X 3 SWITCH u 1.00 12.00 12.00 12.00
59.00 CAJA RECTANGULAR GALVANIZADA LIVIANA DE 4" X 2 1/8" u 24.00 3.00 72.00 72.00
60.00 CAJA OCTOGONAL GALVANIZADA LIVIANA 4" X 2 1/8 " u 16.00 4.20 67.20 67.20
61.00 CAJA METALICA PORTAMEDIDOR u 1.00 45.00 45.00 45.00
62.00 FLUORESCENTE RECTO ISPE 1X40 W C/EQ + PANTALLA u 8.00 120.00 960.00 960.00
63.00 FOCO "WS" 150R JOSFEL + LAMPAPRA DE 1OOW u 8.00 3.00 24.00 24.00
64.00 TUBERIA Y ACCESORIOS glb 1.00 350.00 350.00 350.00
MUNICIPALIDAD DISTRITAL DE TORATA
OBRA: CONSTRUCCION DE LOCAL USOS MULTIPLES EN EL ANEXO DE ILUBAYA, DISTRITO DE TORATA, MARISCAL NIETO- MOQUEGUA
EJECUTA: MUNICIPALIDAD DISTRITAL DE TORATA
FECHA: AGOSTO DEL 2010
PRECIO PROGRAMADO
COSTO
ITEM DESCRIPCION UND CANTIDAD UNITARIO PARCIAL S/.
MES 1 MES 2 MES 3 MES 4
S/.
65.00 LADRILLO KING KONG DE ARCILLA 10x14x24cm u 4,698.25 0.85 3,993.51 3,993.51
66.00 LADRILLO PASTELERO 24 X 24 X 3 cm u 2,309.78 0.65 1,501.36 1,501.36
67.00 LADRILLO HUECO 15 X 30 X 30 cm u 1,094.79 2.30 2,518.01 2,518.01
68.00 CEMENTO PORTLAND TIPO I (42.5 kg) bls 1,032.64 22.50 23,234.29 23,234.29
69.00 TUERCA PVC. DE 1/2 P/CONEX. DOMICILIARIA u 1.00 25.00 25.00 25.00
70.00 CINTA AISLANTE rll 5.66 3.50 19.81 19.81
71.00 CINTA TEFLON rll 4.00 3.50 13.99 13.99
72.00 YESO DE 28 Kg bls 31.04 10.00 310.44 310.44
73.00 OCRE ROJO kg 1.75 17.00 29.78 29.78
74.00 THINNER CORRIENTE gal 1.00 17.00 17.00 17.00
75.00 PIZARRA ACRILICA 2.60x1.30 MTS. C/MARCO MADERA CEDRO u 1.00 220.00 220.00 220.00
76.00 ANDAMIOS (DEPOSITO) u 1.00 300.00 300.00 300.00
77.00 SILLAS PLASTICAS u 60.00 25.00 1,500.00 1,500.00
78.00 MESAS PLASTICAS u 60.00 60.00 3,600.00 3,600.00
79.00 CORTINAS u 9.00 300.00 2,700.00 2,700.00
80.00 IMPLEMENTOS DE LIMPIEZA(ESCOBAS, RECOGEDORES, PAPELERAS, PRODUCTOS DE LIMPIEZA glb 1.00 300.00 300.00 300.00
81.00 IMPLEMENTOS DE SEGURIDAD(BOTIQUIN, EXTINTOR) glb 1.00 350.00 350.00 350.00
82.00 ACCESORIOS DIVERSOS u 1.00 75.00 75.00 75.00
83.00 PORCELANA kg 0.48 15.53 7.45 7.45
84.00 PORCELANA BLANCA kg 30.06 7.50 225.45 225.45
85.00 RODOPLAST PARA BORDE DE MAYOLICAS m 30.31 2.00 60.61 60.61
86.00 ADITIVO THOR GEL kg 2.00 70.00 140.00 140.00
87.00 SELLADOR gal 13.48 17.50 235.91 235.91
88.00 SELLADOR ELASTICO DE POLIURETANO tub 28.56 25.00 714.00 714.00
89.00 TRENZA DE CABLE DESNUDO DE 50mm2 m 1.00 100.00 100.00 100.00
90.00 EQUIPO DE SONIDO u 1.00 2,050.00 2,050.00 2,050.00
91.00 COMPUTADORA PENTIUN IV DUAL CORE u 1.00 3,500.00 3,500.00 3,500.00
92.00 IMPRESORA MULTIFUNCIONAL(TAMAÑO PAPEL A-4) u 1.00 400.00 400.00 400.00
93.00 MUEBLE PARA EQUIPO DE COMPUTO TIPO ESCRITORIO DE MELAMINE u 1.00 600.00 600.00 600.00
94.00 PROYECTOR MULTIMEDIA (CAÑON, ECRAN) u 1.00 6,500.00 6,500.00 6,500.00
95.00 LAVADERO ACERO INOXIDABLE 19"X37" CON ESC. P. SAT.CON ACCES. u 1.00 250.00 250.00 250.00
96.00 PEGAMENTO PARA PVC AGUA FORDUIT gal 0.30 90.00 27.43 27.43
97.00 SILICONA u 34.87 15.00 523.06 523.06
98.00 PEGAMENTO PARA TUBERIA PVC gal 1.07 90.00 96.30 96.30
99.00 PEGAMENTO PARA TUBERIA PVC (ELECT.) gal 0.05 60.00 2.85 2.85
MUNICIPALIDAD DISTRITAL DE TORATA
OBRA: CONSTRUCCION DE LOCAL USOS MULTIPLES EN EL ANEXO DE ILUBAYA, DISTRITO DE TORATA, MARISCAL NIETO- MOQUEGUA
EJECUTA: MUNICIPALIDAD DISTRITAL DE TORATA
FECHA: AGOSTO DEL 2010
PRECIO PROGRAMADO
COSTO
ITEM DESCRIPCION UND CANTIDAD UNITARIO PARCIAL S/.
MES 1 MES 2 MES 3 MES 4
S/.
100.00 CINTA BANDIT 3/4" m 1.00 4.00 4.00 4.00
101.00 MEDIDOR ELECTRICO u 1.00 160.00 160.00 160.00
102.00 WINCHA u 0.68 20.00 13.65 13.65
103.00 CAJA DE CEMENTO DE MAMPOSTERIA u 1.00 30.00 30.00 30.00
104.00 CAJA DE CONCRETO C/TAPA PARA AGUA u 1.00 50.00 50.00 50.00
105.00 CAJA DE REGISTRO DE 12"x24" DE C-SP/DESAGUE pza 4.00 12.00 48.00 48.00
106.00 GASOLINA 84 OCTANOS gal 96.70 11.00 1,063.66 1,063.66
107.00 HORMIGON m3 51.54 70.00 3,607.64 3,607.64
108.00 COLA SINTETICA FULLER gal 0.55 60.00 32.83 32.83
109.00 LIJA PARA CONCRETO hja 77.36 2.50 193.40 193.40
110.00 LIJA PARA MADERA u 5.47 2.00 10.94 10.94
111.00 AGUA m3 33.32 3.50 116.61 116.61
112.00 WAYPE INDUSTRIAL kg 3.20 2.50 8.00 8.00
113.00 REFRIGERADORA u 1.00 2,000.00 2,000.00 2,000.00
114.00 COCINA A GAS SEMI INDUSTRIAL 03 HORNILLAS u 1.00 950.00 950.00 950.00
115.00 BALON DE GAS u 1.00 150.00 150.00 150.00
116.00 OLLAS DE ALUMINIO jgo 1.00 2,000.00 2,000.00 2,000.00
117.00 SARTEN u 3.00 80.00 240.00 240.00
118.00 SERVICIO DE PLATOS DE LOZA (HONDOS, TENDIDOS, POSTRE) doc 9.00 25.00 225.00 225.00
119.00 SERVICIO DE JARROS DE LOZA doc 3.00 13.50 40.50 40.50
120.00 SERVICIO DE CUBIERTOS (CUCHARAS, TENEDORES, CUCHILLOS DE MESA) doc 12.00 15.00 180.00 180.00
121.00 UTENSILLOS DE COCINA (CUCHARONES, TASONES, CUCHILLOS DE COCINA) glb 1.00 600.00 600.00 600.00
122.00 THERMOS u 4.00 100.00 400.00 400.00
123.00 LICUADORA u 1.00 313.04 313.04 313.04
124.00 TELEVISOR 21" COLOR u 1.00 1,500.00 1,500.00 1,500.00
125.00 REPRODUCTOR DVD u 1.00 280.00 280.00 280.00
126.00 MICROFONO u 1.00 150.00 150.00 150.00
127.00 INSTALACION DE ACCESORIOS glb 1.00 200.00 200.00 200.00
128.00 INSTALACION DE ACCESORIOS POZO PERCOLADOR glb 1.00 200.00 200.00 200.00
129.00 LIMPIEZA GENERAL DE OBRA mes 1.00 210.00 210.00 210.00
130.00 TAPA METALICA INSPECCION 0.60M X 0.60M u 2.00 80.00 160.00 160.00
131.00 LOSETA CELIMA 20 X 20 cm m2 2.63 45.00 118.13 118.13
132.00 CERAMICO 36 X 36 CM. COLOR TREVISO MARFIL m2 21.51 47.00 1,011.18 1,011.18
133.00 CERAMICO 60 X 60 CM. COLOR TREVISO MARFIL m2 91.36 47.00 4,293.94 4,293.94
134.00 CERAMICO DE 8 X 30 CM. EXTRAFORTE COLOR BLANCO m 41.11 16.00 657.72 657.72
MUNICIPALIDAD DISTRITAL DE TORATA
OBRA: CONSTRUCCION DE LOCAL USOS MULTIPLES EN EL ANEXO DE ILUBAYA, DISTRITO DE TORATA, MARISCAL NIETO- MOQUEGUA
EJECUTA: MUNICIPALIDAD DISTRITAL DE TORATA
FECHA: AGOSTO DEL 2010
PRECIO PROGRAMADO
COSTO
ITEM DESCRIPCION UND CANTIDAD UNITARIO PARCIAL S/.
MES 1 MES 2 MES 3 MES 4
S/.
135.00 CERAMICO DE 27 X 45 CM. COLOR MANHATAN ARENA m2 49.27 27.00 1,330.18 1,330.18
136.00 MADERA TORNILLO p2 2,679.06 5.50 14,734.85 14,734.85
137.00 MADERA CEDRO ( reglas) p2 41.61 10.00 416.14 416.14
138.00 MADERA EUCALIPTO ROLLIZO (p2) p2 324.77 3.50 1,136.68 1,136.68
139.00 ESTACA DE MADERA TORNILLO TRATADA p2 59.73 4.40 262.83 262.83
140.00 TRIPLAY DE 4' X 8' X 19 mm pl 3.27 135.00 441.94 441.94
141.00 TRIPLAY DE 4' X 8' X 4 mm pl 38.40 35.00 1,344.00 1,344.00
142.00 TRIPLAY DE 8 mm m2 8.64 29.51 254.97 254.97
143.00 TRIPLAY DE 6 mm m2 0.20 24.00 4.82 4.82
144.00 MELAMINE DE 18 MM pl 2.49 244.80 610.47 610.47
145.00 MADERA TORNILLO INCLUYE CORTE PARA ENCOFRADO p2 0.52 5.00 2.59 2.59
146.00 TAPA CON MARCO FIERRO FUNDIDO DE DESAGUE 12" X 24" pza 2.00 16.27 32.54 32.54
147.00 PETROLEO DIESSEL # 2 gal 14.10 11.75 165.66 165.66
148.00 GRASA lb 9.35 12.50 116.82 116.82
149.00 PINTURA ESMALTE SINTETICO gal 0.86 35.00 30.18 30.18
150.00 PINTURA LATEX COLOR DURAZNO gal 4.37 45.00 196.84 196.84
151.00 PINTURA LATEX COLOR MELON gal 1.66 45.00 74.62 74.62
152.00 PINTURA LATEX COLOR GRIS PERLA gal 1.67 45.00 75.04 75.04
153.00 PINTURA LATEX COLOR CASTAÑA gal 1.39 45.00 62.74 62.74
154.00 PINTURA LATEX COLOR BLANCO ARENA gal 4.30 45.00 193.66 193.66
155.00 PINTURA LATEX COLOR AMARILLO TROPICAL gal 0.22 45.00 9.83 9.83
156.00 PINTURA LATEX COLOR NEGRO gal 7.71 45.00 346.88 346.88
157.00 PINTURA LATEX COLOR BLANCO gal 6.50 50.00 324.77 324.77
158.00 CALAMINA GALVANIZADA ZINC 24CANALES 1.83 X 1.085 m X 0.6 mm pl 32.00 28.00 896.00 896.00
159.00 POSTE DE CONCRETO H=6 m u 1.00 450.00 450.00 450.00
160.00 UNION UNIVERSAL DE FIERRO GALVANIZADO DE 1/2" u 18.00 8.00 144.00 144.00
161.00 NIPLE DE FIERRO GALVANIZADO DE 1/2" X 1 1/2" u 18.00 3.50 63.00 63.00
162.00 ESCALERA DE GATO u 1.00 180.00 180.00 180.00
163.00 SUMIDERO DE BRONCE DE 2" pza 4.00 6.50 26.00 26.00
164.00 TUBERIA PVC SAP PRESION C-10 C/R. 1/2" X 5m m 39.95 4.00 159.78 159.78
165.00 UNION PVC SAP PARA AGUA CON ROSCA DE 1/2" pza 5.38 2.50 13.44 13.44
166.00 CODO PVC SAP PARA AGUA CON ROSCA DE 1/2" X 90° u 32.00 2.50 80.00 80.00
167.00 CODO PVC SAP 1/2" X 45° C-10 u 2.00 1.50 3.00 3.00
168.00 TEE PVC SAP PARA AGUA CON ROSCA DE 1/2" u 9.00 2.50 22.50 22.50
169.00 TUBERIA PVC SAL PARA DESAGUE DE 2" m 30.55 3.00 91.64 91.64
MUNICIPALIDAD DISTRITAL DE TORATA
OBRA: CONSTRUCCION DE LOCAL USOS MULTIPLES EN EL ANEXO DE ILUBAYA, DISTRITO DE TORATA, MARISCAL NIETO- MOQUEGUA
EJECUTA: MUNICIPALIDAD DISTRITAL DE TORATA
FECHA: AGOSTO DEL 2010
PRECIO PROGRAMADO
COSTO
ITEM DESCRIPCION UND CANTIDAD UNITARIO PARCIAL S/.
MES 1 MES 2 MES 3 MES 4
S/.
170.00 TUBERIA PVC SAL PARA DESAGUE DE 4" m 26.97 4.50 121.36 121.36
171.00 CODO PVC SAL DE 2" X 90° u 10.00 3.50 35.00 35.00
172.00 CODO PVC SAL DE 4" X 90° u 16.00 4.50 72.00 72.00
173.00 TEE SANITARIA SIMPLE PVC SAL DE 4" u 4.00 4.00 16.00 16.00
174.00 TEE SANITARIA SIMPLE CON REDUCCION PVC SAL 4"A 2" u 3.00 5.00 15.00 15.00
175.00 SOMBRERO DE VENTILACION PVC SAL DE 2" u 3.00 4.50 13.50 13.50
176.00 NIPLE PVC SAP DE 1/2" u 1.00 1.20 1.20 1.20
177.00 CODO PVC SAL 2" X 90° pza 9.45 2.00 18.90 18.90
178.00 CODO PVC SAL 4" X 90° pza 4.20 5.00 21.00 21.00
179.00 CODO PVC SAL 4" X 45° pza 1.05 5.00 5.25 5.25
180.00 TEE PVC SAL 4" X 4" pza 6.00 7.50 45.00 45.00
181.00 YEE PVC SAL DE 4" X 2" pza 7.00 5.00 35.00 35.00
182.00 YEE PVC SAL DE 4" X 4" pza 15.00 5.00 75.00 75.00
183.00 REDUCCION PVC SAL 4" X 2" pza 4.00 5.50 22.00 22.00
184.00 TUBO PVC SAP E/C PARA INSTALACIONES ELECTRICAS 1" X 3 m pza 49.95 5.00 249.73 249.73
185.00 TUBO PVC SEL ESPIGA CAMPANA 3/4" X 3.00 m pza 36.00 0.36 12.96 12.96
186.00 TUBERIA PVC SAP PARA INSTALACIONES ELECTRICAS DE 20 mm m 16.00 1.50 24.00 24.00
187.00 CURVA PVC SAP PARA INSTALACIONES ELECTRICAS 3/4" pza 47.46 1.20 56.95 56.95
188.00 UNION PVC SEL 3/4" pza 24.00 0.50 12.00 12.00
189.00 UNION SIMPLE PVC SAP PARA INSTALACIONES ELECTRICAS 20mm pza 32.00 1.20 38.40 38.40
190.00 CONEXION A CAJA PVC SAP 3/4" pza 48.00 0.52 24.96 24.96
191.00 CONEXION A CAJA PVC SAP PARA INSTALACIONES ELECTRICAS 20 mm pza 16.00 1.20 19.20 19.20
192.00 VALVULA COMPUERTA DE BRONCE DE 1/2" u 9.00 22.00 198.00 198.00
193.00 LLAVE DE PASO DE 1/2" u 1.00 16.50 16.50 16.50
194.00 VIDRIO TRANSPARENTE INCOLORO CRUDO MEDIODOBLE p2 244.27 6.50 1,587.77 1,587.77
SERVICIOS- SUBCONTRATOS 29,750.45 990.14 15,940.16 6,075.09 6,745.07
195.00 TRANSPORTE DE MATERIALES A OBRA (FLETE) t 110.42 29.89 3,300.45 990.14 1,155.16 660.09 495.07
196.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIA est 1.00 1,800.00 1,800.00 900.00 900.00
197.00 TALLERES DE CAPACITACION ( MATERIAL DE ESCRITORIO, REFRIGERIOS) est 4.00 1,337.50 5,350.00 5,350.00
198.00 ANALISIS GRANULOMETRICO DE AGREGADOS u 1.00 250.00 250.00 250.00
199.00 DISEÑO DE MEZCLAS DE CONCRETO u 1.00 350.00 350.00 350.00
200.00 ENSAYO DE COMPACTACION DE SUELOS u 1.00 350.00 350.00 350.00
201.00 PRUEBAS DE CALIDAD DE CONCRETO ROTURA u 20.00 15.00 300.00 300.00
202.00 PUERTA DE MADERA TIPO P-1, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 1.00 2,800.00 2,800.00 1,960.00 840.00
203.00 PUERTA DE MADERA TIPO P-2, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 1.00 1,700.00 1,700.00 1,190.00 510.00
MUNICIPALIDAD DISTRITAL DE TORATA
OBRA: CONSTRUCCION DE LOCAL USOS MULTIPLES EN EL ANEXO DE ILUBAYA, DISTRITO DE TORATA, MARISCAL NIETO- MOQUEGUA
EJECUTA: MUNICIPALIDAD DISTRITAL DE TORATA
FECHA: AGOSTO DEL 2010
PRECIO PROGRAMADO
COSTO
ITEM DESCRIPCION UND CANTIDAD UNITARIO PARCIAL S/.
MES 1 MES 2 MES 3 MES 4
S/.
204.00 PUERTA DE MADERA TIPO P-3, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 2.00 1,000.00 2,000.00 1,400.00 600.00
205.00 PUERTA DE MADERA TIPO P-4, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 2.00 1,200.00 2,400.00 1,680.00 720.00
206.00 VENTANA DE MADERA TIPO V-1, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 2.00 600.00 1,200.00 840.00 360.00
207.00 VENTANA DE MADERA TIPO V-2, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 2.00 600.00 1,200.00 840.00 360.00
208.00 VENTANA DE MADERA TIPO V-3, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 1.00 400.00 400.00 280.00 120.00
209.00 VENTANA DE MADERA TIPO V-4, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 1.00 600.00 600.00 420.00 180.00
210.00 PUERTA DE MADERA TIPO P-5, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 3.00 900.00 2,700.00 1,890.00 810.00
211.00 VENTANA DE MADERA TIPO V-5, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 2.00 400.00 800.00 560.00 240.00
212.00 VENTANA DE MADERA TIPO V-6, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 2.00 400.00 800.00 560.00 240.00
213.00 VENTANA DE MADERA TIPO V-7, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 1.00 400.00 400.00 280.00 120.00
214.00 VENTANA DE MADERA TIPO V-8, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 1.00 500.00 500.00 350.00 150.00
215.00 VENTANA DE MADERA TIPO V-9, INCLUYE INSTALACION, ACCESORIOS SEGUN PLANO u 1.00 550.00 550.00 385.00 165.00
TOTALES S/. 318,677.54 177,925.77 66,685.74 48,225.89 25,840.14
PORCENTAJE DE DESEMBOLSO % 55.83% 20.93% 15.13% 8.11%
122,350.91
15,262.13
151,314.05
29,750.45