Avance Proyecto Final 3
Avance Proyecto Final 3
Avance Proyecto Final 3
Facultad de Ingeniería
Integrantes
Docente
Curso
Ica – Perú
2024
INDICE
3
4.6.5. Margen de contingencia ..................................................................................73
4.7. PLAN DE GESTION DE ADQUISICIONES.............................................................75
4.7.1. Criterios de adquisición de recursos humanos ................................................75
4.7.2. Criterios de adquisición de recursos materiales ..............................................76
4.7.3. Criterios de adquisición de maquinarias y equipos ..........................................77
4.7.4. Criterios de Almacenamiento...........................................................................78
4.7.5. Criterios de Transporte ....................................................................................80
4.8. PLAN DE LOS STAKEHOLDERS ...........................................................................81
4.8.1. Identificación de stakeholders .........................................................................81
4.8.2. Análisis de intereses y nivel de compromiso (actual y deseable) ....................83
4.8.3. Estrategias para gestionar stakeholder ...........................................................84
4
I. MARCO TEÓRICO
dentro de la refinería de Petro Perú en Iquitos”, tiene como objetivo permitir el correcto
Este proyecto tendrá un plazo de construcción de 240 días un presupuesto meta de S/.
230 000 000.00 nuevos soles, el terreno disponible es de 250 m2, contará con una
cubierta tipo techo flotante, tendrá una altura de 14m y capacidad de 40 000 barriles
1.2.2. Antecedentes
barriles de hidrocarburos.
1.2.3. El problema
motocicletas, automóviles, entre otros; así mismo ello ha provocado una creciente
demanda de combustible.
5
1.2.4. La solución
N° DE
RIESGO EFECTO
RIESGO
R01
Aumento de los precios de • Incremento del presupuesto
materiales y mano de obra general del proyecto
R03
Cambio en las condiciones del • Alteración en los beneficios del
mercado proyecto
• No se alcanzaría la calidad
No cumplimiento de los deseada.
R05 controles de calidad en el • Defectos que comprometan la
proyecto seguridad del tanque
• Reparaciones costosas y extensas
1.2.6. Alcance
será el producto final entregado ya puesto en marcha y este servirá para abastecer
6
1.2.7. Presupuesto estimado del proyecto
realizarán, se obtiene una estimación financiera que incluye los costos directos del
2.1.1. Título
7
• El tanque poseerá un techo flotante con un diámetro de 30 m
• Poseerá todas sus áreas y servicio para su operación
• Acta de constitución
• Permisos
• Cronograma de actividades
• Presupuesto
• WBS
• Análisis de interesados
• Reportes
Obra finalizada
8
2.1.5. Meta y objetivos del proyecto
almacenamiento óptimos
Iquitos.
almacenamiento.
2.1.6. Stakeholders
Quispe Cabana,
Director Administración Director Financiero
Elías Emanuel
9
2.1.7. Requisitos de alto nivel
Los requisitos tanto del producto como del proyecto son los siguientes:
internacionales de seguridad.
establecidos.
hidrocarburos.
10
2.1.8. Alcance del producto
será el producto final entregado ya puesto en marcha y este servirá para abastecer
FECHA FECHA
NOMBRE DE LA TAREA DURACIÓN
INICIO TOPE
11
Seguridad y Gestión 180 días 04/03/2024 31/08/2024
Los riesgos de alto nivel que se podrían presentar en el transcurso del proyecto
• Accidentes laborales.
• Retraso en el cronograma.
12
2.1.12. Presupuesto y necesidad de recursos
realizarán, se obtiene una estimación financiera que incluye los costos directos
Inclusiones
Exclusiones
Se presenta una lista de entregables y actividades que no se encuentran dentro del alcance
del proyecto:
• Manual de seguridad
• Plan de gestión ambiental
• Actividades de capacitación
13
3.2. DEFINICIÓN DEL ALCANCE
Prestación de servicios
Personal calificado
Reportes
Cronogramas
ETAPA DE DISEÑO
Estudio preliminar
Anteproyecto
14
Se desarrolla un plan detallado del proyecto,
• Planificación del proyecto
incluyendo la descripción del producto a
almacenar, las características del tanque, los • Planos de las especialidades
requeridas
planos del proyecto.
Expediente técnico
• Índice
• Memoria descriptiva
• Estudios básicos
Este documento contiene toda la información • Especificaciones técnicas
técnica y administrativa necesaria para la
• Metrados Cronograma del proyecto
ejecución del proyecto, garantizando su
• Análisis de precios unitarios
cumplimiento con las normas y regulaciones
aplicables. • Relación de insumos
• Presupuesto del proyecto
• Planos
• Anexos
ETAPA DE CONSTRUCCIÓN
Inicio de obra
PUESTA EN MARCHA
ACTIVIDADES DE GESTIÓN
15
• Gestión de alcance
Documentos que presenta los planes de gestión
• Gestión de requisitos
del proyecto
• Gestión de costos Gestión de tiempo
16
3.4. DICCIONARIO DEL EDT/WBS
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
17
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
Descripción Diseño de Techo Flotante
Criterio de Diseño de techo flotante para almacenar gasolina, petróleo y sus derivados
Aceptación evitando la evaporación.
Entregables Planos y especificaciones técnicas.
18
Diseño correctos de planos y especificaciones técnicas, sin necesidad de
Supuestos
correcciones futuras.
Recursos
01 Arquitecto, 1 ingeniero hidráulico y 1 ingeniero mecánico
Asignados
Duración 10 días calendario.
Hitos Diseño de techo flotante.
Costos 5500 soles
Firma del
Director del Rosamaría Nayely Liñán Palomino
Proyecto
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
Descripción Licencias de Construcción
Criterio de
Correcta tramitación de las licencias de construcción.
Aceptación
Entregables Documentación, planos, cortes y especificaciones técnicas.
Supuestos El proyecto y obra cuentan con los requisitos.
Recursos
01 patrocinador
Asignados
Duración 15 días calendario
Hitos Entrega de licencias
Costos 2000 soles
Firma del
Director del Rosamaría Nayely Liñán Palomino
Proyecto
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
19
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
Descripción Plan de seguridad.
Criterio de El plan contemplará y contendrá medidas tanto en el interior como en el
Aceptación exterior de la obra.
Entregables Plan de seguridad.
Supuestos Las especificaciones están bajo normativa actual.
Recursos
01 Arquitecto, 01 ingeniero hidráulico y 01 ingeniero mecánico
Asignados
Duración 15 días calendario.
Hitos Entrega de planes de seguridad.
Costos 4000 soles
Firma del
Director del Rosamaría Nayely Liñán Palomino
Proyecto
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
20
Criterio de
Desarrollo de un plan de costos y recursos a utilizar.
Aceptación
Entregables Entrega de plan de costos.
Supuestos La obra cumple con los requisitos.
Recursos
01 Arquitecto, 01 ingeniero hidráulico y 01 ingeniero mecánico
Asignados
Duración 15 días calendario
Hitos Entrega de plan de costos.
Costos 2000 soles
Firma del
Director del Rosamaría Nayely Liñán Palomino
Proyecto
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
Descripción Plan de Calidad
Criterio de Desarrollo de un plan de calidad que contemple la cantidad de recursos y
Aceptación calidad de cada elemento.
Entregables Entrega de plan de calidad.
Supuestos El plan de calidad garantiza los procesos y productos.
Recursos
01 Arquitecto, 01 ingeniero hidráulico y 01 ingeniero mecánico
Asignados
Duración 20 días calendario.
Hitos Entrega de plan de calidad.
Costos 4000 soles
Firma del
Director del Rosamaría Nayely Liñán Palomino
Proyecto
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
21
Hitos Entrega de plan de tiempo.
Costos 4000 soles
Firma del
Director del Rosamaría Nayely Liñán Palomino
Proyecto
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
Descripción Colocación de armadura.
Criterio de Correcta ejecución y colocación de las armaduras de acero en las
Aceptación cimentaciones.
Entregables Habilitación del acero
Supuestos Ejecución adecuada de la colocación de la armadura.
Recursos
01 ingeniero civil, 01 capataz
Asignados
Duración 25 días calendario.
Hitos Excavación para cimientos.
Costos 32000 soles
Firma del
Director del Rosamaría Nayely Liñán Palomino
Proyecto
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
Descripción Concreto
Criterio de Correcta ejecución y colocación de las armaduras de acero en las
Aceptación cimentaciones.
Entregables Vaciado de concreto.
Supuestos Ejecución adecuada de vaciado de concreto.
Recursos
01 ingeniero civil, 01 capataz
Asignados
Duración 7 días calendario.
Hitos Encofrado y desencofrado de concreto.
Costos 50000 soles
Firma del
Director del Rosamaría Nayely Liñán Palomino
Proyecto
22
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
Descripción Soldadura de Placas
Criterio de
Correcta soldadura en juntas verticales y horizontales.
Aceptación
Entregables Soldadura en las placas.
Supuestos Correcta soldadura de anillos en las palcas.
Recursos
01 ingeniero civil y 01 capataz, 01 soldador
Asignados
Duración 30 días calendario.
Hitos Soldadura placas.
Costos 1 000 000
Firma del
Director del Rosamaría Nayely Liñán Palomino
Proyecto
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
RESPONSABLE
CUENTA ÚLTIMA ACTUALIZACIÓN
(JOSÉ FRANCISCO
CONTROL 21/04/2024
RIOS LEGUA)
Descripción Pruebas de seguridad.
Criterio de Los sistemas de ventilación y contención cumplen con los requisitos de
Aceptación seguridad.
Entregables Sistema activos y en funcionamiento.
Supuestos Los sistemas no presentan ningún problema.
Recursos
01 ingeniero civil ,01 técnico, 01 capataz
Asignados
Duración 10 días calendario.
Hitos Pruebas de seguridad.
Costos 5 000 soles
Firma del
Director del Rosamaría Nayely Liñán Palomino
Proyecto
4.1.1. Fases
24
Se realiza los trabajos
✓ Ingeniero Civil preliminares para dar
✓ Contratista inicio a la obra, se realiza
B Etapa de
general las pruebas y control de
Construcción ✓ Operarios calidad, así mismo los
✓ Especialistas acabados e instalaciones
en seguridad respectivas.
Se realiza la inspección
C final del proyecto para la
Puesta en marcha ✓ Ingeniero Civil
transferencia del producto
✓ Técnicos
al cliente.
Fecha Fase
s ID Descripción del Hito
Límite
A B C D
Término de construcción de
14/06/2024 X
estructuras
Término de instalación de
02/08/2024 X
acabados
25
4.1.3. Principales entregables del plan de hitos
✓ Ingeniero Civil
✓ Ingeniero
Estructural ✓ Planos de estructuras
Anteproyecto aprobado
2 ✓ Ingeniero ✓ Planos eléctricos
por el cliente
Mecánico ✓ Estudio de suelos
✓ Ingeniero
Eléctrico
✓ Memoria descriptiva
✓ Estudios básicos
✓ Especificaciones técnicas
3 Diseño aprobado ✓ Ingeniero Civil ✓ Metrados
✓ Presupuesto de obra
✓ Análisis de costos unitarios
✓ Cronograma de obra
Etapa de diseño
4 ✓ Ingeniero Civil ✓ Expediente técnico
concluida
✓ Ingeniero Civil
✓ Ingeniero
Estructural
✓ Estudios de suelos
5 Inicio de obra ✓ Ingeniero
✓ Control de calidad
Mecánico
✓ Ingeniero
Eléctrico
Firma de acta de
8 ✓ Ingeniero Civil ✓ Acta de recepción final
recepción
26
4.1.4. Cronograma general del proyecto
Las actividades que forman parte de la ruta crítica del proyecto (en complemento
con actividades de gestión al inicio y cierre del proyecto), en cada una de las
fases identificadas son lassiguientes:
27
Fase Actividades
✓ Trabajos preliminares
✓ Fabricación y montaje de tanque
28
4.2. PLAN DE GESTIÓN DE COSTOS
En este punto se detallan los costos unitarios de cada uno de los recursos que serán
empleados en el proyecto:
Recursos humanos
Para el caso de personal administrativo, cada recurso tiene un costo día (el cualestá
29
SP-04 Ingeniero Eléctrico 60 160 9,600.00
SP-05 Dibujante CAD 60 120 7,200.00
Grupo: Equipo de Obra
SP-06 Ingeniero Residente 180 200 36,000.00
SP-07 Supervisor de Obra 180 210 37,800.00
SP-08 Ingeniero Seguridad 180 130 23,400.00
SP-09 Ingeniero Asistente 180 130 23,400.00
SP-10 Maestro de Obra 180 125 22,500.00
SP-11 Jefe de Almacén 180 70 12,600.00
TOTAL (S/.) 248,700.00
este caso, el costo de estos recursos es evaluado por hora (costo hora).
Materiales
Para este proyecto se utilizará el costo del material puesto en obra, debido a que
Uso Costo
ID Nombre del recurso Und Total
Total unidad
MA-01 PLANCHA ASTM A36 2400 X 12000 X 16 27,816.88 KG 2.37 65,926.01
MA-02 PLANCHA ASTM A36 2400 X 12000 X 14 24,339.77 KG 2.37 57,685.25
MA-03 PLANCHA ASTM A36 2400 X 12000 X 12 20,862.66 KG 2.37 49,444.50
MA-04 PLANCHA ASTM A36 2400 X 12000 X 9.5 16,516.27 KG 2.37 39,143.56
MA-05 PLANCHA ASTM A36 2400 X 12000 X 8 13,908.44 KG 2.37 32,963.00
30
MA-06 PLANCHA ASTM A36 2400 X 12000 X 6 20,862.66 KG 2.37 49,444.50
MA-07 ANGULO ASTM A36 3" X 3" X 3/8" 7.69 PZA 123.60 950.48
MA-08 PLANCHA ASTM A36 2400 X 12000 X 8 44,390.70 KG 2.37 105,205.96
MA-09 PLANCHA ASTM A36 2400 X 12000 X 5 37,712.31 KG 2.37 89,378.17
MA-10 PLANCHA ASTM A36 2400 X 12000 X 9 26,147.43 KG 2.37 61,969.41
MA-11 PLANCHA ASTM A36 2400 X 12000 X 15 4,531.55 KG 2.37 10,739.77
MA-12 TUBERIA DE SCH 80, ASM A-53 GB 4" 13.00 PZA 380.60 4,947.80
SELLO MECANICO TECHO FLOTANTE 29000
MA-13 1.00 UND 120,500.00 120,500.00
MM
MA-14 PERFIL C 8" X 18.5 8.46 PZA 347.40 2,939.00
MA-15 TUBERIA SCH 40 ASTM A-53 GB X 1.1/4" 12.11 UND 47.01 569.29
MA-16 TUBERIA SCH 40 ASTM A-53 GB X 1" 9.02 UND 33.74 304.33
PELDAÑO 800 X 200 TIPO GR04 CON 02
MA-17 100.00 UND 72.64 7,264.00
TAPAS VASCULANTES
PINES GUIAS 5/8" X 3" PARA PELDAÑOS
MA-18 200.00 UND 23.60 4,720.00
ESCALER VASCULANTE
SISTEMA CORREDIZO PARA ESCALERA JUEG
MA-19 1.00 15,000.00 15,000.00
VASCULANTE O
PELDAÑO 800 X 200 TIPO GR04 CON 02
MA-20 77.00 UND 59.64 4,592.28
TAPAS LATERALES
MA-21 PLATAFORMA 600 X 800 TIPO GR04 6.00 UND 178.92 1,073.52
MA-22 BARRA LISA 3/4" 14.00 UND 11.27 157.78
MA-23 TUBERIA DE SCH 40, ASTM A-53 GB X 1" 4.10 UND 33.74 138.33
MA-24 TUBERIA DE SCH 40, ASTM A-53 GB X 1.1/4" 4.10 UND 47.01 192.74
MA-25 ANGULO ASTM A36 3" X 3" X 5/16" 1.70 PZA 104.16 177.07
PLANCHA ASTM A36 2400 X 12000 X 6
MA-26 22.61 KG 2.37 53.59
(REFUERZO DE 200 X 200)
MA-27 PLANCHA ESTRIADA 1200 X 2400 X 6 7,053.00 KG 3.01 21,229.53
MA-28 TUBERIA DE SCH 40, ASTM A-53 GB X 1" 33.20 UND 33.74 1,120.17
MA-29 TUBERIA DE SCH 40, ASTM A-53 GB X 1.1/4" 16.00 UND 47.01 752.16
MA-30 ANGULO ASTM A36 3" X 3" X 3/8" 24.00 PZA 123.60 2,966.40
PLANCHA ASTM A36 2400 X 12000 X 6
MA-31 98.00 KG 2.37 232.26
(REFUERZO DE 200 X 200)
MA-32 PLATINA 100 X 6 X 6000 ASTM A36 16.00 UND 45.44 727.04
MA-33 TUBERIA DE SCH 40, ASTM A-53 GB X 1" 0.63 UND 33.74 21.26
MA-34 TUBERIA DE SCH 40, ASTM A-53 GB X 1.1/4" 0.35 UND 153.86 53.85
CODOS 90° - SCH 40 DE RADIO LARGO ANSI
MA-35 1.00 UND 12.61 12.61
B16.9. ASTM 234 4"
CODOS 90° - SCH 40 DE RADIO LARGO ANSI
MA-36 6.00 UND 1.04 6.24
B16.9. ASTM 234 1"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105
MA-37 1.00 UND 34.32 34.32
Gr2 4"
MA-38 PLANCHA ASTM A36 2400 X 12000 X 9.5 57.78 KG 2.37 136.94
PLANCHA ASTM A36 2400 X 12000 X 16
MA-39 136.58 KG 2.37 323.69
(TAPA)
PLANCHA ASTM A36 2400 X 12000 X 16
MA-40 65.54 KG 2.37 155.33
(BRIDA)
PLANCHA ASTM A36 2400 X 12000 X 14
MA-41 124.30 KG 2.37 294.59
(CUELLO)
31
PLANCHA ASTM A36 2400 X 12000 X 14
MA-42 420.66 KG 2.37 996.96
(REFUERZO)
EMPAQUE 1/8" Ø750 INT X Ø820 EXT MM.
MA-43 2.00 UND 439.70 879.40
FIBRA SINTETICA
PERNOS Ø3/4" X 5" UNC EN AGUJERO 7/8" 2
MA-44 56.00 UND 4.23 236.88
CON TUERCAS
MA-45 BARRA LISA ASTM A 36 Ø5/8" 0.23 UND 7.00 1.61
PLANCHA ASTM A36 2400 X 12000 X 16
MA-46 95.51 KG 2.37 226.36
(TAPA)
PLANCHA ASTM A36 2400 X 12000 X 16
MA-47 40.03 KG 2.37 94.87
(BRIDA)
PLANCHA ASTM A36 2400 X 12000 X 14
MA-48 77.68 KG 2.37 184.10
(CUELLO)
PLANCHA ASTM A36 2400 X 12000 X 14
MA-49 316.67 KG 2.37 750.51
(REFUERZO)
EMPAQUE 1/8" Ø750 INT X Ø850 EXT MM
MA-50 1.00 UND 419.25 419.25
FIBRA SINTETICA
MA-51 PERNOS Ø3/4" X 5" UNC EN AGUJERO 7/8" 42.00 UND 4.23 177.66
MA-52 BARRA LISA ASTM A 36 Ø5/8" 0.12 UND 7.00 0.84
BRIDAS WNRF #150 ANSI B16.5 ASTM A105
MA-53 1.00 PZA 23.66 23.66
Gr2 Ø2 1/2"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105
MA-54 3.00 PZA 34.32 102.96
Gr2 Ø2 4"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105
MA-55 2.00 PZA 58.44 116.88
Gr2 Ø2 6"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105
MA-56 2.00 PZA 99.71 199.42
Gr2 Ø2 8"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105
MA-57 1.00 PZA 156.88 156.88
Gr2 Ø2 10"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105
MA-58 1.00 PZA 245.25 245.25
Gr2 Ø2 12"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105
MA-59 1.00 PZA 327.38 327.38
Gr2 Ø2 14"
MA-60 TUBERIA DE SCH 40, ASTM A-53 GB X 2 1/2" 0.10 UND 122.23 12.22
MA-61 TUBERIA DE SCH 40, ASTM A-53 GB X 4" 0.30 UND 153.86 46.16
MA-62 TUBERIA DE SCH 40, ASTM A-53 GB X 6" 0.20 UND 331.11 66.22
MA-63 TUBERIA DE SCH 40, ASTM A-53 GB X 8" 0.10 UND 525.53 52.55
MA-64 TUBERIA DE SCH 40, ASTM A-53 GB X 10" 0.10 UND 767.33 76.73
MA-65 TUBERIA DE SCH 40, ASTM A-53 GB X 12" 0.10 UND 1,030.58 103.06
MA-66 TUBERIA DE SCH 40, ASTM A-53 GB X 14" 0.10 UND 1,324.26 132.43
MA-67 PLANCHA ASTM A36 2400 X 12000 X 12 678.24 KG 2.37 1,607.43
MA-68 TUBERIA DE SCH 80, ASTM A-53 GB X 2 1/2" 2.80 UND 196.17 549.28
MA-69 TUBERIA DE SCH 80, ASTM A-53 GB X 8" 2.80 UND 727.38 2,036.66
TOTAL (S/.) 763,370.38
Maquinaria y equipos
Total Costo
ID Nombre del recurso Total
horas hora
Grupo: Maquinaria
MEH-01 Cargador Frontal 10 250 S/. 2,500.00
MEH-02 Retroexcavadora 15 220 S/. 3,300.00
MEH-03 Volquetes 24 250 S/. 6,000.00
MEH-04 Cisterna 24 300 S/. 7,200.00
MEH-05 Grúa de Carga 12 220 S/. 2,640.00
Grupo: Equipos
MEH-14 Compactadora 36 60 S/. 2,160.00
MEH-15 Vibradora 16 30 S/. 480.00
MEH-16 Mezcladora 24 50 S/. 1,200.00
MEH-17 Máquina de Soldar 48 30 S/. 1,440.00
MEH-18 Grupo Electrógeno 24 40 S/. 960.00
calculado en base a todas las partidas requeridas para el Diseño, Construcción y Puesta
en marcha de la obra y está compuesta principalmente por los costos de manode obra,
ETAPA DE CONSTRUCCIÓN
ACTIVIDADES PRELIMINARES 30,000.00
ADQUISICIÓN DE RECURSOS 800,000.00
SELECCIÓN Y CONTRATACIÓN DE CONTRATISTAS 466,519.94
REVISIÓN DE DISEÑO DEL PROYECTO 8,000.00
PREPARACIÓN DEL TERRENO Y CIMENTACIÓN 35,000.00
FABRICACIÓN Y MONTAJE DEL TANQUE 200,000.00
PRUEBAS Y CONTROL DE CALIDAD 373,215.95
33
ACABADOS 100,000.00
INSTALACIONES 80,000.00
PUESTA EN MARCHA
INSPECCIÓN FINAL DEL PROYECO 2,000.00
PRUEBA DE LOS EQUIPOS 15,000.00
ELABORACIÓN DE DOSSIER DE CALIDAD 5,000.00
TRANSFERENCIA DEL PRODUCTO AL CLIENTE 20,000.00
ACTIVIDADES DE GESTIÓN
ACTIVIDADES DE GESTIÓN DE DISEÑO 2,000.00
ACTIVIDADES DE GESTIÓN DE CONSTRUCCIÓN 2,500.00
SEGUIMIENTO DEL PROYECTO 1,000.00
ACTIVIDADES DE CIERRE 3,000.00
TOTAL (S/.) 2,172,035.89
4.2.3. Gastos
Los gastos del proyecto llegan a S/. 312,200.00 soles, agrupándose de lasiguiente
manera:
GASTOS
GASTOS SUELDO EQUIPO DE PROYECTO 248,700.00
GASTOS OFICINA PRINCIPAL 3,000.00
GASTOS DE COMUNICACIONES 2,500.00
GASTOS DE CAPACITACIÓN 3,000.00
GASTOS DE CALIDAD 15,000.00
GASTOS MATERIALES DE OFICINA 1,500.00
GASTOS SEGURIDAD DE OBRA 10,500.00
GASTOS NEGOCIACIÓN CON SINDICATO 2,000.00
GASTOS DE TRANSPORTE 16,000.00
GASTOS VARIOS 10,000.00
TOTAL (S/.) 312,200.00
Para obtener la línea de base de costes, se debe agregar a la estructura de costesy a los
34
S/. 60,000.00 soles (en el capítulo de riesgos se detalla el cálculo de estemonto). Con
este monto, la línea base de coste del proyecto es de S/. 2,533,735.89 soles.
35
4.2.6. Curva S del proyecto.
36
4.3. PLAN DE GESTIÓN DE CALIDAD
Incrementar la
Porcentaje 𝑡𝑎𝑟𝑒𝑎𝑠 𝑐𝑜𝑚𝑝𝑙𝑒𝑡𝑎𝑑𝑎𝑠 • Seguimiento y control de las
𝑇= eficacia, completando
tarea actividades
3 𝑡𝑎𝑟𝑒𝑎𝑠 𝑡𝑜𝑡𝑎𝑙𝑒𝑠 las actividades en el Cada semana
completada a • Medir el porcentaje de
× 100 cronograma
tiempo avance de la obra
establecido
Mejorar la calidad de
Errores # 𝑑𝑒 𝑒𝑟𝑟𝑜𝑟𝑒𝑠 • Controles de calidad la obra y reducir la Cada 2
4 𝐸=
detectados 𝑡𝑜𝑡𝑎𝑙 𝑑𝑒 𝑎𝑐𝑡𝑖𝑣𝑖𝑑𝑎𝑑𝑒𝑠 • Pruebas de la infraestructura cantidad de errores semanas
detectados en obra
• Elaboración de encuestas Medir y lograr un nivel
Satisfacción
5 𝑆 = 𝑝𝑢𝑛𝑡𝑢𝑎𝑐𝑖𝑜𝑛 𝑒𝑛 𝑒𝑛𝑐𝑢𝑒𝑡𝑎𝑠 • Retroalimentaciones del alto de satisfacción del Cada mes
del cliente
cliente cliente
Métricas de calidad del producto
Frecuencia
Objetivo Métrica Fórmula Procesos involucrados Meta
de medición
Controlar
Cumplimiento de %Avance de obra = (Horas Control de avance obras
efectivamente el
1 cronograma de hombre ganadas / Horas hombre Cumplimiento de plazos de 1 semana
cumplimiento del
avance de obra de línea base) ejecución establecidos.
avance de la obra
Numero de modificaciones
Modificación en Control de modificaciones de Contar con un control
aprobados en la construcción /
2 estructura de estructuras metálicas, instalación de modificaciones en 2 semanas
Numero de modificaciones
metal del acero la estructura
solicitado en la construcción
Suficiencia de
Control de la calidad del producto Cumplir con el
pruebas al Número de pruebas realizadas / Según
3 con la realización de pruebas número de pruebas
tanque de Número de pruebas programadas cronograma
realizadas al proyecto. para el contenedor
almacenamiento
38
Estos son los procedimientos de la constructora que han sido considerados para este
proyecto:
Entregable Procedimientos
Planificación del ISO 9001 Cumplimiento de plazos y Revisión y ajuste periódico Al inicio y en cada
Proyecto presupuesto del plan de trabajo revisión del plan
Antes de la
Gestión de ISO 9001 Cumplimiento de requisitos Evaluación y selección de
contratación y de
Proveedores de calidad proveedores calificados
forma continua
Normativa de gestión de
Desviaciones respecto a la Revisiones periódicas y Semanalmente o
Seguimiento y Control proyectos planificación reportes de avance según planificación
Antes de implementar
ISO 9001 Impacto en el proyecto y Evaluación de cambios y
Control de Cambios cambios y durante el
cumplimiento de plazos comunicación efectiva
proyecto
41
4.3.3. Control de calidad
42
4.3.4. Plan de pruebas y mediciones
actividad debe ser realizada por el equipo de obra junto con el jefe de Calidad,
Estructura
del Tanque Prueba de hermeticidad del tanque Ausencia fugas o filtraciones
Utilización de materiales
2024
Horas
Recurso Ratio Costo Ene Feb Mar Abr May Jun Jul Ago
requeridas
MATERIALES
S/ S/
MATERIALES 6582
300.00 1,974,600.00
PLANCHA ASTM A36 2400 X 12000 X 16 330 0.40 130.35 60 132 138
PLANCHA ASTM A36 2400 X 12000 X 14 330 0.40 130.35 60 132 138
PLANCHA ASTM A36 2400 X 12000 X 12 330 0.40 130.35 60 132 138
PLANCHA ASTM A36 2400 X 12000 X 9.5 330 0.40 130.35 60 132 138
PLANCHA ASTM A36 2400 X 12000 X 8 330 0.40 130.35 60 132 138
PLANCHA ASTM A36 2400 X 12000 X 6 330 0.40 130.35 60 132 138
ANGULO ASTM A36 3" X 3" X 3/8" 60 20.60 1,236.00 60
PLANCHA ASTM A36 2400 X 12000 X 8 210 0.40 82.95 90 60 60
PLANCHA ASTM A36 2400 X 12000 X 5 120 0.40 47.40 60 60
PLANCHA ASTM A36 2400 X 12000 X 9 120 0.40 47.40 60 60
PLANCHA ASTM A36 2400 X 12000 X 15 120 0.40 47.40 60 60
TUBERIA DE SCH 80, ASM A-53 GB 4" 120 63.43 7,612.00 60 60
SELLO MECANICO TECHO FLOTANTE
120 20,083.33 2,410,000.00 60 60
29000 MM
PERFIL C 8" X 18.5 60 57.90 3,474.00 60
TUBERIA SCH 40 ASTM A-53 GB X 1.1/4" 60 7.84 470.10 60
TUBERIA SCH 40 ASTM A-53 GB X 1" 60 5.62 337.40 60
PELDAÑO 800 X 200 TIPO GR04 CON 02
60 12.11 726.40 60
TAPAS VASCULANTES
PINES GUIAS 5/8" X 3" PARA PELDAÑOS
60 3.93 236.00 60
ESCALER VASCULANTE
SISTEMA CORREDIZO PARA ESCALERA
60 2,500.00 150,000.00 60
VASCULANTE
PELDAÑO 800 X 200 TIPO GR04 CON 02
60 9.94 596.40 60
TAPAS LATERALES
PLATAFORMA 600 X 800 TIPO GR04 60 29.82 1,789.20 60
BARRA LISA 3/4" 60 1.88 112.70 60
TUBERIA DE SCH 40, ASTM A-53 GB X 1" 60 5.62 337.40 60
TUBERIA DE SCH 40, ASTM A-53 GB X
60 7.84 470.10 60
1.1/4"
ANGULO ASTM A36 3" X 3" X 5/16" 60 17.36 1,041.60 60
PLANCHA ASTM A36 2400 X 12000 X 6
60 0.40 23.70 60
(REFUERZO DE 200 X 200)
PLANCHA ESTRIADA 1200 X 2400 X 6 120 0.50 60.20 60 60
TUBERIA DE SCH 40, ASTM A-53 GB X 1" 120 5.62 674.80 60 60
TUBERIA DE SCH 40, ASTM A-53 GB X
120 7.84 940.20 60 60
1.1/4"
ANGULO ASTM A36 3" X 3" X 3/8" 120 20.60 2,472.00 60 60
PLANCHA ASTM A36 2400 X 12000 X 6
120 0.40 47.40 60 60
(REFUERZO DE 200 X 200)
PLATINA 100 X 6 X 6000 ASTM A36 120 7.57 908.80 60 60
TUBERIA DE SCH 40, ASTM A-53 GB X 1" 60 5.62 337.40 60
TUBERIA DE SCH 40, ASTM A-53 GB X
60 25.64 1,538.60 60
1.1/4"
CODOS 90° - SCH 40 DE RADIO LARGO
60 2.10 126.10 60
ANSI B16.9. ASTM 234 4"
45
CODOS 90° - SCH 40 DE RADIO LARGO
60 0.17 10.40 60
ANSI B16.9. ASTM 234 1"
BRIDAS WNRF #150 ANSI B16.5 ASTM
60 5.72 343.20 60
A105 Gr2 4"
PLANCHA ASTM A36 2400 X 12000 X 9.5 60 0.40 23.70 60
PLANCHA ASTM A36 2400 X 12000 X 16
48 0.40 18.96 48
(TAPA)
PLANCHA ASTM A36 2400 X 12000 X 16
48 0.40 18.96 48
(BRIDA)
PLANCHA ASTM A36 2400 X 12000 X 14
48 0.40 18.96 48
(CUELLO)
PLANCHA ASTM A36 2400 X 12000 X 14
48 0.40 18.96 48
(REFUERZO)
EMPAQUE 1/8" Ø750 INT X Ø820 EXT
48 73.28 3,517.60 48
MM. FIBRA SINTETICA
PERNOS Ø3/4" X 5" UNC EN AGUJERO
48 0.71 33.84 48
7/8" 2 CON TUERCAS
BARRA LISA ASTM A 36 Ø5/8" 48 1.17 56.00 48
PLANCHA ASTM A36 2400 X 12000 X 16
48 0.40 18.96 48
(TAPA)
PLANCHA ASTM A36 2400 X 12000 X 16
48 0.40 18.96 48
(BRIDA)
PLANCHA ASTM A36 2400 X 12000 X 14
48 0.40 18.96 48
(CUELLO)
PLANCHA ASTM A36 2400 X 12000 X 14
48 0.40 18.96 48
(REFUERZO)
EMPAQUE 1/8" Ø750 INT X Ø850 EXT MM
48 69.88 3,354.00 48
FIBRA SINTETICA
PERNOS Ø3/4" X 5" UNC EN AGUJERO
48 0.71 33.84 48
7/8"
BARRA LISA ASTM A 36 Ø5/8" 48 1.17 56.00 48
46
BRIDAS WNRF #150 ANSI B16.5 ASTM
72 3.94 283.92 72
A105 Gr2 Ø2 1/2"
BRIDAS WNRF #150 ANSI B16.5 ASTM
72 5.72 411.84 72
A105 Gr2 Ø2 4"
BRIDAS WNRF #150 ANSI B16.5 ASTM
72 9.74 701.28 72
A105 Gr2 Ø2 6"
BRIDAS WNRF #150 ANSI B16.5 ASTM
72 16.62 1,196.52 72
A105 Gr2 Ø2 8"
BRIDAS WNRF #150 ANSI B16.5 ASTM
72 26.15 1,882.56 72
A105 Gr2 Ø2 10"
BRIDAS WNRF #150 ANSI B16.5 ASTM
72 40.88 2,943.00 72
A105 Gr2 Ø2 12"
BRIDAS WNRF #150 ANSI B16.5 ASTM
72 54.56 3,928.56 72
A105 Gr2 Ø2 14"
TUBERIA DE SCH 40, ASTM A-53 GB X 2
72 20.37 1,466.76 72
1/2"
TUBERIA DE SCH 40, ASTM A-53 GB X 4" 72 25.64 1,846.32 72
TUBERIA DE SCH 40, ASTM A-53 GB X 6" 72 55.19 3,973.32 72
TUBERIA DE SCH 40, ASTM A-53 GB X 8" 72 87.59 6,306.36 72
TUBERIA DE SCH 40, ASTM A-53 GB X 10" 72 127.89 9,207.96 72
TUBERIA DE SCH 40, ASTM A-53 GB X 12" 72 171.76 12,366.96 72
TUBERIA DE SCH 40, ASTM A-53 GB X 14" 72 220.71 15,891.12 72
PLANCHA ASTM A36 2400 X 12000 X 12 72 0.40 28.44 72
TUBERIA DE SCH 80, ASTM A-53 GB X 2
60 32.70 1,961.70 60
1/2"
TUBERIA DE SCH 80, ASTM A-53 GB X 8" 60 121.23 7,273.80 60
47
4.4.2. Plan de utilización de maquinaria y equipos.
2024
Horas
Recurso Ratio Costo Ene Feb Mar Abr May Jun Jul Ago
requeridas
MAQUINARIA Y EQUIPOS
S/
S/
MAQUINARIA Y EQUIPOS 829 1,240.0
205,300.00
0
Cargador Frontal 220 250.00 55,000.00 80 60 80
Retroexcavadora 184 220.00 40,480.00 76 68 40
Volquetes 200 250.00 50,000.00 74 46 80
Cisterna 129 300.00 38,700.00 59 70
Grúa de Carga 96 220.00 21,120.00 68 28
S/ S/
MAQUINARIA Y EQUIPOS 553
210.00 22,750.00
Compactadora 98 60.00 5,880.00 84 14
Vibradora 44 30.00 1,320.00 12 16 6 10
Mezcladora 71 50.00 3,550.00 7 32 12 20
Máquina de Soldar 160 30.00 4,800.00 132 28
Grupo Electrógeno 180 40.00 7,200.00 132 48
48
4.4.3. Equipo de Trabajo
punto anterior:
Funciones
• Desarrollar diseños detallados y cálculos para las estructuras del tanque de
almacenamiento.
• Seleccionar los materiales estructurales adecuados basándose en el análisis de
resistencia, durabilidad y costo.
• Utilizar software especializado para modelar y simular el comportamiento de las
estructuras.
Supervisar la construcción y montaje de las estructuras, asegurando la conformidad con
los diseños y especificaciones.
50
Requisitos del Rol
✓ Ingeniería Estructural con énfasis en diseño y análisis de
estructuras.
✓ Normativas y regulaciones de construcción y seguridad
Conocimientos
aplicables a tanques de almacenamiento de combustibles.
✓ Métodos de análisis estructural y técnicas de modelado
computacional (SAP2000, ETABS).
✓ Habilidad para realizar cálculos estructurales precisos y
detallados.
✓ Capacidad para trabajar en equipo y coordinar con otros
Habilidades
profesionales del proyecto.
✓ Buena comunicación y habilidades interpersonales para
explicar conceptos técnicos a diversos stakeholders.
✓ Mínimo 5 años de experiencia en el diseño y análisis
estructural, preferentemente en proyectos relacionados con
Experiencia almacenamiento de combustibles o infraestructura similar.
✓ Historial comprobado de diseño de estructuras seguras y
eficientes dentro de los límites de tiempo y presupuesto.
Funciones
• Desarrollar especificaciones y diseños detallados para los sistemas mecánicos,
incluyendo tuberías, bombas y sistemas de ventilación.
• Realizar cálculos de ingeniería para dimensionar y seleccionar equipos mecánicos
adecuados.
• Supervisar la instalación y puesta en marcha de los sistemas mecánicos.
• Realizar inspecciones y pruebas de los sistemas mecánicos para asegurar su
funcionamiento correcto y seguro.
• Mantener registros precisos y documentación técnica de los sistemas mecánicos.
51
✓ Ingeniería Mecánica con especialización en diseño y sistemas
mecánicos.
✓ Normativas y regulaciones para sistemas mecánicos en
Conocimientos
tanques de almacenamiento de combustible.
✓ Técnicas de análisis y diseño de sistemas de bombeo, tuberías
y ventilación.
✓ Habilidad para realizar cálculos precisos y detallados de
sistemas mecánicos.
✓ Competencia en el uso de software de diseño y simulación
Habilidades
mecánica.
✓ Habilidad para identificar y resolver problemas técnicos de
manera efectiva.
✓ Mínimo 5 años de experiencia en diseño y supervisión de
sistemas mecánicos, preferentemente en proyectos
relacionados con almacenamiento de combustibles o
Experiencia
infraestructura similar.
✓ Experiencia en la instalación y puesta en marcha de sistemas
mecánicos complejos.
Funciones
• Desarrollar especificaciones y diseños detallados para los sistemas eléctricos,
incluyendo sistemas de alimentación, control, y comunicación.
• Realizar cálculos de ingeniería para dimensionar y seleccionar equipos eléctricos
adecuados.
• Supervisar la instalación y puesta en marcha de los sistemas eléctricos.
• Realizar inspecciones y pruebas de los sistemas eléctricos para asegurar su
funcionamiento correcto y seguro.
52
✓ Habilidad para realizar cálculos precisos y detallados de
sistemas eléctricos.
✓ Competencia en el uso de software de diseño y simulación
Habilidades
eléctrica.
✓ Habilidad para identificar y resolver problemas técnicos de
manera efectiva.
✓ Mínimo 5 años de experiencia en diseño y supervisión de
sistemas eléctricos, preferentemente en proyectos
relacionados con almacenamiento de combustibles o
Experiencia
infraestructura similar.
✓ Experiencia en la instalación y puesta en marcha de sistemas
eléctricos complejos.
Funciones
• Realizar evaluaciones de riesgos y desarrollar planes de seguridad específicos para el
proyecto.
• Establecer protocolos de respuesta a emergencias y coordinar simulacros de
emergencia.
• Supervisar la correcta implementación de medidas de seguridad durante todas las fases
del proyecto.
• Mantener registros detallados de todas las actividades relacionadas con la seguridad y
elaborar informes para la gerencia.
53
✓ Mínimo 5 años de experiencia en roles de seguridad industrial,
preferentemente en proyectos de construcción y
Experiencia almacenamiento de combustibles.
✓ Experiencia en la implementación de sistemas de gestión de
seguridad y salud ocupacional.
Funciones
• Supervisar la calidad de los materiales y el trabajo realizado para asegurar que cumplan
con los estándares especificados.
• Garantizar el cumplimiento de las normas de seguridad y salud en el sitio.
• Coordinar las entregas de materiales y la logística en el sitio de construcción.
• Gestionar el cronograma del proyecto y asegurar que las etapas del proyecto se
completen a tiempo.
54
NOMBRE DEL ROL
INGENIERO SUPERVISOR
Responsabilidades
• Supervisar las actividades diarias de construcción en el sitio para asegurar el
cumplimiento con los planos, especificaciones y normativas.
• Coordinar con el Ingeniero Residente y otros equipos para asegurar la correcta
ejecución del proyecto.
• Realizar inspecciones periódicas y evaluar la calidad del trabajo realizado.
• Resolver problemas técnicos y logísticos que surjan durante la construcción.
Funciones
• Supervisar la implementación de los procedimientos de seguridad y asegurar el
cumplimiento de las normativas de seguridad en el sitio.
• Revisar y aprobar los trabajos realizados por los contratistas y subcontratistas.
• Coordinar las actividades de construcción y asegurar que se sigan los cronogramas
establecidos.
• Realizar reuniones de seguimiento y coordinación con el equipo de proyecto y
contratistas.
55
NOMBRE DEL ROL
INGENIERO ASISTENTE
Responsabilidades
• Asistir a los ingenieros principales en la planificación, diseño y supervisión del proyecto.
• Ayudar en la recopilación y análisis de datos necesarios para el diseño y construcción.
• Colaborar en la elaboración de informes técnicos y documentación del proyecto.
• Realizar tareas técnicas y administrativas según las necesidades del proyecto.
Funciones
• Asistir en la revisión de planos, especificaciones y documentos técnicos.
• Participar en visitas al sitio para recopilar datos y asegurar que las actividades se
desarrollen conforme a los planes.
• Ayudar en la preparación de cronogramas y seguimiento del progreso del proyecto.
• Apoyar en la implementación de medidas de control de calidad y seguridad en el sitio
de construcción.
56
4.4.5. Cronograma de recursos
2024
Horas
Recurso Ratio Costo Ene Feb Mar Abr May Jun Jul Ago
requeridas
RECURSOS HUMANOS
S/ S/
RECURSOS HUMANOS 1400
28.75 40,250.00
Ingeniero Civil (Jefe de proyecto) 1400 28.75 40,250.00 184 168 168 176 184 160 184 176
RECURSOS HUMANOS S/ S/
1440
78.75 113,400.00
Ingeniero Estructural 360 22.50 8,100.00 184 168 8
Ingeniero Mecánico 360 21.25 7,650.00 184 168 8
Ingeniero Eléctrico 360 20.00 7,200.00 184 168 8
Dibujante CAD 360 15.00 5,400.00 184 168 8
RECURSOS HUMANOS S/ S/
6240
108.13 112,450.00
Ingeniero Residente 1040 25.00 26,000.00 160 176 184 160 184 176
Supervisor de Obra 1040 26.25 27,300.00 160 176 184 160 184 176
Ingeniero Seguridad 1040 16.25 16,900.00 160 176 184 160 184 176
Ingeniero Asistente 1040 16.25 16,900.00 160 176 184 160 184 176
Maestro de Obra 1040 15.63 16,250.00 160 176 184 160 184 176
Jefe de Almacén 1040 8.75 9,100.00 160 176 184 160 184 176
RECURSOS HUMANOS S/ S/
5200
68.21 70,938.40
Capataz 1040 16.62 17,284.80 160 176 184 160 184 176
Operario 1040 14.45 15,028.00 160 176 184 160 184 176
Oficial 1040 11.41 11,866.40 160 176 184 160 184 176
Peón 1040 10.36 10,774.40 160 176 184 160 184 176
Operador de equipo pesado 1040 15.37 15,984.80 160 176 184 160 184 176
MATERIALES
S/
S/
MATERIALES 6582 1,974,600.0
300.00
0
PLANCHA ASTM A36 2400 X 12000 X 16 330 0.40 130.35 60 132 138
PLANCHA ASTM A36 2400 X 12000 X 14 330 0.40 130.35 60 132 138
PLANCHA ASTM A36 2400 X 12000 X 12 330 0.40 130.35 60 132 138
PLANCHA ASTM A36 2400 X 12000 X 9.5 330 0.40 130.35 60 132 138
PLANCHA ASTM A36 2400 X 12000 X 8 330 0.40 130.35 60 132 138
PLANCHA ASTM A36 2400 X 12000 X 6 330 0.40 130.35 60 132 138
ANGULO ASTM A36 3" X 3" X 3/8" 60 20.60 1,236.00 60
PLANCHA ASTM A36 2400 X 12000 X 8 210 0.40 82.95 90 60 60
PLANCHA ASTM A36 2400 X 12000 X 5 120 0.40 47.40 60 60
PLANCHA ASTM A36 2400 X 12000 X 9 120 0.40 47.40 60 60
PLANCHA ASTM A36 2400 X 12000 X 15 120 0.40 47.40 60 60
TUBERIA DE SCH 80, ASM A-53 GB 4" 120 63.43 7,612.00 60 60
SELLO MECANICO TECHO FLOTANTE 29000 MM 20,083.3
120 2,410,000.00 60 60
3
PERFIL C 8" X 18.5 60 57.90 3,474.00 60
TUBERIA SCH 40 ASTM A-53 GB X 1.1/4" 60 7.84 470.10 60
TUBERIA SCH 40 ASTM A-53 GB X 1" 60 5.62 337.40 60
PELDAÑO 800 X 200 TIPO GR04 CON 02 TAPAS
60 12.11 726.40 60
VASCULANTES
PINES GUIAS 5/8" X 3" PARA PELDAÑOS
60 3.93 236.00 60
ESCALER VASCULANTE
SISTEMA CORREDIZO PARA ESCALERA
60 2,500.00 150,000.00 60
VASCULANTE
58
PELDAÑO 800 X 200 TIPO GR04 CON 02 TAPAS
60 9.94 596.40 60
LATERALES
PLATAFORMA 600 X 800 TIPO GR04 60 29.82 1,789.20 60
BARRA LISA 3/4" 60 1.88 112.70 60
TUBERIA DE SCH 40, ASTM A-53 GB X 1" 60 5.62 337.40 60
TUBERIA DE SCH 40, ASTM A-53 GB X 1.1/4" 60 7.84 470.10 60
ANGULO ASTM A36 3" X 3" X 5/16" 60 17.36 1,041.60 60
PLANCHA ASTM A36 2400 X 12000 X 6
60 0.40 23.70 60
(REFUERZO DE 200 X 200)
PLANCHA ESTRIADA 1200 X 2400 X 6 120 0.50 60.20 60 60
TUBERIA DE SCH 40, ASTM A-53 GB X 1" 120 5.62 674.80 60 60
TUBERIA DE SCH 40, ASTM A-53 GB X 1.1/4" 120 7.84 940.20 60 60
ANGULO ASTM A36 3" X 3" X 3/8" 120 20.60 2,472.00 60 60
PLANCHA ASTM A36 2400 X 12000 X 6
120 0.40 47.40 60 60
(REFUERZO DE 200 X 200)
PLATINA 100 X 6 X 6000 ASTM A36 120 7.57 908.80 60 60
TUBERIA DE SCH 40, ASTM A-53 GB X 1" 60 5.62 337.40 60
TUBERIA DE SCH 40, ASTM A-53 GB X 1.1/4" 60 25.64 1,538.60 60
CODOS 90° - SCH 40 DE RADIO LARGO ANSI
60 2.10 126.10 60
B16.9. ASTM 234 4"
CODOS 90° - SCH 40 DE RADIO LARGO ANSI
60 0.17 10.40 60
B16.9. ASTM 234 1"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105 Gr2
60 5.72 343.20 60
4"
PLANCHA ASTM A36 2400 X 12000 X 9.5 60 0.40 23.70 60
PLANCHA ASTM A36 2400 X 12000 X 16 (TAPA) 48 0.40 18.96 48
PLANCHA ASTM A36 2400 X 12000 X 16 (BRIDA) 48 0.40 18.96 48
PLANCHA ASTM A36 2400 X 12000 X 14
48 0.40 18.96 48
(CUELLO)
59
PLANCHA ASTM A36 2400 X 12000 X 14
48 0.40 18.96 48
(REFUERZO)
EMPAQUE 1/8" Ø750 INT X Ø820 EXT MM.
48 73.28 3,517.60 48
FIBRA SINTETICA
PERNOS Ø3/4" X 5" UNC EN AGUJERO 7/8" 2
48 0.71 33.84 48
CON TUERCAS
BARRA LISA ASTM A 36 Ø5/8" 48 1.17 56.00 48
PLANCHA ASTM A36 2400 X 12000 X 16 (TAPA) 48 0.40 18.96 48
PLANCHA ASTM A36 2400 X 12000 X 16 (BRIDA) 48 0.40 18.96 48
PLANCHA ASTM A36 2400 X 12000 X 14
48 0.40 18.96 48
(CUELLO)
PLANCHA ASTM A36 2400 X 12000 X 14
48 0.40 18.96 48
(REFUERZO)
EMPAQUE 1/8" Ø750 INT X Ø850 EXT MM
48 69.88 3,354.00 48
FIBRA SINTETICA
PERNOS Ø3/4" X 5" UNC EN AGUJERO 7/8" 48 0.71 33.84 48
BARRA LISA ASTM A 36 Ø5/8" 48 1.17 56.00 48
BRIDAS WNRF #150 ANSI B16.5 ASTM A105 Gr2
72 3.94 283.92 72
Ø2 1/2"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105 Gr2
72 5.72 411.84 72
Ø2 4"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105 Gr2
72 9.74 701.28 72
Ø2 6"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105 Gr2
72 16.62 1,196.52 72
Ø2 8"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105 Gr2
72 26.15 1,882.56 72
Ø2 10"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105 Gr2
72 40.88 2,943.00 72
Ø2 12"
BRIDAS WNRF #150 ANSI B16.5 ASTM A105 Gr2
72 54.56 3,928.56 72
Ø2 14"
60
TUBERIA DE SCH 40, ASTM A-53 GB X 2 1/2" 72 20.37 1,466.76 72
TUBERIA DE SCH 40, ASTM A-53 GB X 4" 72 25.64 1,846.32 72
TUBERIA DE SCH 40, ASTM A-53 GB X 6" 72 55.19 3,973.32 72
TUBERIA DE SCH 40, ASTM A-53 GB X 8" 72 87.59 6,306.36 72
TUBERIA DE SCH 40, ASTM A-53 GB X 10" 72 127.89 9,207.96 72
TUBERIA DE SCH 40, ASTM A-53 GB X 12" 72 171.76 12,366.96 72
TUBERIA DE SCH 40, ASTM A-53 GB X 14" 72 220.71 15,891.12 72
PLANCHA ASTM A36 2400 X 12000 X 12 72 0.40 28.44 72
TUBERIA DE SCH 80, ASTM A-53 GB X 2 1/2" 60 32.70 1,961.70 60
TUBERIA DE SCH 80, ASTM A-53 GB X 8" 60 121.23 7,273.80 60
MAQUINARIA Y EQUIPOS
MAQUINARIA Y EQUIPOS S/ S/
829
1,240.00 205,300.00
Cargador Frontal 220 250.00 55,000.00 80 60 80
Retroexcavadora 184 220.00 40,480.00 76 68 40
Volquetes 200 250.00 50,000.00 74 46 80
Cisterna 129 300.00 38,700.00 59 70
Grúa de Carga 96 220.00 21,120.00 68 28
MAQUINARIA Y EQUIPOS S/ S/
553
210.00 22,750.00
Compactadora 98 60.00 5,880.00 84 14
Vibradora 44 30.00 1,320.00 12 16 6 10
Mezcladora 71 50.00 3,550.00 7 32 12 20
Máquina de Soldar 160 30.00 4,800.00 132 28
Grupo Electrógeno 180 40.00 7,200.00 132 48
61
4.5. PLAN DE GESTION DE COMUNICACIONES
De esta manera será necesario que plan de gestión sigan los siguientes
lineamientos:
involucrados del proyecto en especial al cliente para que esté al tanto del
proyecto para discutir el avance del proyecto y resolver los problemas que se
hayan presentado
equipo.
Necesidad de Medio de
ID Etapa / Hito Público objetivo Responsable Lugar Frecuencia
comunicación comunicación
Coordinación de
Equipo del
Planificación las actividades y Reuniones Líder de Sala de Inicio de
1 proyecto y
inicial plazos presenciales equipo reunión proyecto
stakeholders
programados
Publicación de
Asistente de
información Señalización en Trabajadores Sitio de Inicio de
2 Inicio de obra supervisor
importante tableros de obra construcción proyecto
de obra
(cronogramas)
Aprobación y
distribución de Mensual o
Revisión de Documentación Ingenieros y Supervisor Oficina de
3 planos y cuando se
planos física contratista de obra proyecto
especificación actualicen
técnicas
Actualización de
informe de Equipo del
Informe de Reuniones Líder de Sala de
4 riegos y proyecto y Quincenal
riegos presenciales equipo reunión
medidas de stakeholders
mitigación
63
Información y
Asistente de
Evaluaciones evaluación de Señalización en Trabajadores Sitio de
5 supervisor Semanal
de seguridad los protocolos tableros de obra construcción
de obra
de seguridad
Ajuste y
Actualización Reuniones Equipo del Líder de Sala de
6 actualizaciones Mensual
de cronograma presenciales proyecto equipo reunión
de cronograma
Visión del
Informe de Documentación Inversionista y Gerente del
8 estado del Oficina central Quincenal
progreso física stakeholders proyecto
proyecto
Resultados de
Inspección de Documentación Equipo de Supervisor Sitio de
9 inspecciones y Mensual
obra física proyecto de obra construcción
auditorias
Tabla 4.1. Matriz de comunicación formal (F) e informal (I) / escrito (E) o hablada (H)
INTERNO EXTERNO
Planificación inicial X
Inicio de obra X X
Revisión de planos X
Informe de riegos X X
Evaluaciones de seguridad X X
Actualización de cronograma X
Informe de progreso X X X
Inspección de obra X
64
4.6. PLAN DE GESTION DE RIESGOS
A continuación, se presenta el listado de los riesgos que han sido identificados para el
65
4.6.2. Análisis de causa y consecuencia de riesgos
Interrupciones en el
Mantenimiento deficiente,
R02 Falla en los equipos trabajo, aumento de
equipos de baja calidad
costos
Deficiencia en la
Personal no capacitado, Filtraciones, fallos
R03 ejecución de las
falta de supervisión estructurales
soldaduras
Falta de integración en
Falta de coordinación, Mal funcionamiento del
R04 los diferentes sistemas
del tanque errores en el diseño tanque, riesgos operativos
66
4.6.3. Valoración de respuesta
Para este punto, se ha desarrollado una matriz de probabilidad impacto; en base a ésta,
alta 61 - 80 % 4 4 8 12 16 20
media 41 - 60 % 3 3 6 9 12 15
baja 21 - 40 % 2 2 4 6 8 10
muy baja 0 - 20 % 1 1 2 3 4 5
1 2 3 4 5
IMPACTO
Para determinar el impacto que puede tener cada uno de los riesgos identificados en el
Escala
Moderado
Muy bajo (1) Bajo (2) (3) Alto (4) Muy alto (5)
Incremento de
Costo costo Incremento Incremento incremento de incremento de
insignificante de costo <1% de costo <3% costo <5% costo >5%
67
Perceptible, Perceptible,
pero se pero se
Se puede
Imperceptible puede puede Hay que
corregir con
corregir sin corregir con rehacer el
Calidad esfuerzo muy
mayor esfuerzo trabajo
significativo
esfuerzo mayor
del impacto (1-5) de cada riesgo como el número entero superior al promedio de los
impactos en cada una de las cuatro restricciones para el análisis, obteniendo los
siguientes resultados:
Falta de entandares de
R01 seguridad en el diseño S/ 10,820.00 0.1 0.05 0.04 Accidentes y
fallos
Escases de Retrasos y
R05 recursos S/ 2,125.00 0.1 0.3 0.05 aumento de
críticos costos
Ineficiencia en la gestión Sobrecostos y
R06 de recursos S/ 2,000.00 0.3 0.2 0.5
ineficiencia
Ineficiente control
R07 S/ 4,231.00 0.1 0.2 0.1 Materiales
de calidad de los defectuosos
materiales
Retrasos en la entrega de
R09 S/ 3,250.00 0.4 0.3 0.5 Paradas en la
materiales y equipos
obra
Falta de mantenimiento en
R10 S/ 5,124.00 0.2 0.1 0.4 Deterioro
la estructura
prematuro
68
Fluctuaciones en el precio Aumento en el
R11 de los equipos y materiales S/ 1,200.00 0.4 0.05 0.2
presupuesto
Prob. Prob.
N° Riesgo Impacto Valoración
(%) (Valor)
Ineficiencia en la gestión de
R06 8 0.2 0.3 0.02
recursos
Retrasos en la entrega de
R09 20 0.6 0.4 0.24
materiales y equipos
69
Falta de mantenimiento en la
R10 13 0.7 0.5 0.04
estructura
Generación de residuos
R12 10 0.4 0.5 0.07
peligrosos
Retrasos en la obtención de
R14 18 0.8 0.6 0.24
permisos
70
4.6.4. Planes de respuesta
Probabilidad
ID Responsable Trigger Estrategia Acciones preventivas Acciones correctivas
Inicial Final
Incidencia de Implementar
Capacitar al personal en Revisar y corregir diseño según
Ingeniero de accidentes estándares de Alta
R01 seguridad laboral estándares de seguridad Baja
Seguridad laborales seguridad en el diseño
Mantenimiento
Jefe de preventivo y Implementar programas de Reparar o reemplazar equipos Media
R02 Falla de equipos Baja
Mantenimiento planificado mantenimiento preventivo defectuosos
Capacitación y
Supervisor de Defectos en las supervisión de Realizar pruebas de soldadura y Rehacer las soldaduras Alta
R03 Soldadura soldaduras certificar soldadores defectuosas Baja
soldadores
Falta de
Coordinación entre Revisar y ajustar diseño para
integración en Media
Ingeniero de equipos de diseño y integración de sistemas Implementar pruebas de
R04 sistemas del Baja
Proyectos construcción integración
tanque
Director de
Ineficiencia en la Capacitación en gestión Implementar herramientas de Reevaluar la asignación de
Recursos
R06 gestión de recursos de recursos gestión de recursos recursos Alta Media
Humanos
71
Jefe de Control Ineficiente control de Establecer Capacitar al personal en control
R07 calidad de los procedimientos de Reinspeccionar materiales y Alta Media
de Calidad de calidad
materiales control de calidad establecer criterios de aceptación
Retrasos en la
entrega de Planificación logística Establecer acuerdos de entrega Coordinar entregas prioritarias y
Coordinador de Alta Media
materiales y adecuada con proveedores alternativas
R09 Logística
equipos
Impacto en la
Coordinador de comunidad por Comunicación y negociación con
Implementar medidas Implementar medidas correctivas Media Baja
Comunidad emisiones de ruido y la comunidad afectada
R13 de mitigación según requerimientos legales
tráfico
72
4.6.5. Margen de contingencia
Para este punto, se ha analizado el impacto de todos los riesgos con una valoración
de nivel medio hacia adelante. El impacto económico de cada uno de estos riesgos
Tabla 4.7. Análisis del impacto económico de los riesgos del proyecto
Incremento S/ 1,568.00
Total S/ 7,524.00
Costo S/ 4,352.00
Incremento S/ 768.00
Total S/ 5,120.00
Escenario: INTERNO
Costo S/ 3,578.00
Incremento S/ 653.00
73
Total S/ 4,231.00
Incremento S/ 874.00
Total S/ 4,124.00
Incremento S/ 826.00
Total S/ 3,250.00
74
4.7. PLAN DE GESTION DE ADQUISICIONES
Este criterio, se enfoca en poder contar con el personal adecuado e idóneo para la
PERSONAL TEMPORAL
CRITERIO DESCRIPCIÓN
75
Se considera la actitud del candidato hacia el trabajo
temporal, su compromiso, capacidad de cumplir con
Responsabilidad en sus
tareas asignadas y mantener un desempeño
actividades temporales
responsable.
76
- Ajustar la selección de materiales al presupuesto del
proyecto sin comprometer la calidad y la seguridad.
- Asegurar que el proveedor pueda suministrar los materiales
en la cantidad y en los plazos requeridos.
- Ajustar la selección de materiales al presupuesto del
proyecto sin comprometer la calidad y la seguridad.
- Realizar un análisis comparativo de costos entre diferentes
Costo
proveedores y materiales, considerando no solo el costo
inicial, sino también los costos de mantenimiento a largo
plazo.
- Considerar el impacto ambiental de los materiales,
favoreciendo aquellos que sean más sostenibles o
Sostenibilidad reciclables.
- Optar por proveedores que practiquen la sostenibilidad en
sus procesos de producción.
- Asegurar que los materiales sean seguros de manejar y que
se proporcionen las instrucciones adecuadas para su uso y
almacenamiento.
Seguridad
- Verificar que los materiales sean compatibles con el tipo de
combustible que se almacenará, evitando reacciones
químicas adversas.
de combustible en la refinería de Petro Perú en Iquitos. Por esto detallaremos los criterios
• Los equipos deben cumplir con las normas de calidad internacionales (ISO, ASME,
77
• Verificar que los proveedores cuenten con las certificaciones y licencias necesarias
• Los costos deben estar alineados con el presupuesto del proyecto, considerando
• Asegurar que los plazos de entrega sean compatibles con el cronograma del
• Asegurarse de que las maquinarias y equipos cuenten con garantías adecuadas que
adquiridos.
Los siguientes criterios proporcionaran una estructura clara para abordar las necesidades
la zona de construcción.
tales como planchas de acero ASTM, barras de acero, tuberías, pernos, etc. Estos
➢ Organización y etiquetado:
obra
78
➢ Almacenamiento seguro
evitar robos, daños o perdidas. De esta manera será necesario implementar medidas
climáticos
De igual manera ser necesario contar con un lugar de almacenamiento para quipos
➢ Control de inventario
Se hará uso de software especializado para la gestión del inventario para llevar un
79
4.7.5. Criterios de Transporte
transporte diseñadas para cumplir despachos en tiempo y forma, al menor costo posible.
más frecuente. Por esto para nuestro proyecto el tipo de transporte a utilizar será
transporte.
transporte.
Asegurarse de que todos los vehículos y métodos de transporte cumplan con las
80
4.8. PLAN DE LOS STAKEHOLDERS
A continuación, se presenta una lista con los principales grupos de personas impactadas
ID Stakeholders Descripción
81
Tabla 4.3. Stakeholders externos del proyecto
ID Stakeholders Descripción
82
4.8.2. Análisis de intereses y nivel de compromiso (actual y deseable)
Nivel de compromiso
Nivel de
ID Stakeholders Intereses
interés Posición Posición
Actual Deseable
Garantizar las Mantener Mantener
Gerente operaciones diarias y cerca y cerca y
I01 Alto
General culminación del gestionar en gestionar en
proyecto mayor grado mayor grado
Asegurar la eficiencia
Ingeniero de Mantener Mantener
I02 del diseño del tanque Alto
diseño informado informado
de almacenamiento
Asegurar la calidad en
Ingeniero de Mantener Mantener
I03 los procesos de Alto
obra informado satisfecho
construcción
Reducir los riegos y
Jefe de Mantener Mantener
I04 prevenir los accidentes Alto
seguridad informado informado
en obra
Aumentar las Monitorear sin
Mantener
I05 Propietarios ganancias del capital Alto mucho
informado
invertido esfuerzo
83
4.8.3. Estrategias para gestionar stakeholder
ID Stakeholders Estrategia
84