252
Int. J. Innovation and Sustainable Development, Vol. 7, No. 3, 2013
Promoting decision making through a Sustainable
Remediation Assessment Matrix (SRAM)
Aspasia Kalomoiri* and Washington Braida
Center for Environmental Systems,
Department of Civil Environmental and Ocean Engineering,
Stevens Institute of Technology,
Castle Point on Hudson,
Hoboken, NJ 07030, USA
Email: akalomoi@stevens.edu
Email: wbraida@stevens.edu
*Corresponding author
Abstract: This paper describes the steps taken in a decision making process
through a Sustainable Remediation Assessment Matrix (SRAM). The
development of the SRAM deals with Complex, Large-scale Interconnected,
Open, and Socio-technical System (CLIOS). For both large and small
contaminated areas, considers potential impacts on neighbouring areas, the
contribution to air emissions from the materials of the proposed project and the
energy to be consumed. Along this line, the research focused on setting up a
model under a systems perspective. A systemigram, from remedial investigation
to project closeout, has been developed. For each stage of the remediation
project, the process to identify stakeholders has been outlined. Moreover, and
as an illustrative example, environmental, social, and economic aspects of
remedial operations have been addressed on a specific case using the US Air
Force Sustainable Remediation Tool (SRT).
Keywords: SRAM; CLIOS; complex large-scale integrated open socio-technical
systems; SRTTM; sustainable remediation tool; TCE; trichloroethylene; PCE;
perchloroethylene; multicriteria analysis; systemigram; MNA; monitoring
natural attenuation; SVE; soil vapour extraction; ISCO; in situ chemical
oxidation; ERD; enhanced reductive dechlorination; ERH; electrical resistive
heating.
Reference to this paper should be made as follows: Kalomoiri, A. and Braida, W.
(2013) ‘Promoting decision making through a Sustainable Remediation
Assessment Matrix (SRAM)’, Int. J. Innovation and Sustainable Development,
Vol. 7, No. 3, pp.252–270.
Biographical notes: Aspasia Kalomoiri is a PhD candidate and a Research
Assistant at the Center for Environmental Systems (CES) at Stevens Institute of
Technology (Hoboken, NJ, USA). Her main research focuses on analysing
complex socio-technological systems that involves life cycle assessment, risk
and uncertainty analysis in sustainable engineering design and construction,
especially in ground water and soil treatment.
Washington Braida is an Associate Professor at the Centre for Environmental
Systems (CES) at Stevens Institute of Technology (Hoboken, NJ, USA).
This paper is a revised and expanded version of a paper entitled ‘A process for
developing a Sustainable Remediation Assessment Matrix (SRAM)’ presented
at the ‘XI International Conference of Protection and Restoration of the
Environment’, Thessaloniki, Greece, 3–6 July 2012.
Copyright © 2013 Inderscience Enterprises Ltd.
Promoting decision making through a SRAM
1
253
Introduction
Sustainable remediation has been defined as the practice of “demonstrating, in terms
of environmental, economic and social indicators, that the benefit of undertaking
remediation is greater than its impact and that the optimum remediation solution is
selected through the use of a balanced decision-making process” (SuRF-UK, 2010). A
related definition covering Green Remediation was advanced by US EPA: “The practice
of considering all environmental effects of remedy implementation and incorporating
options to maximise net environmental benefit of clean-up actions”. As such, the goal of
green and sustainable remediation practices is to minimise the footprint of remediation
and to avoid the transference of risk between environmental media. This can be achieved
by incorporating methods to conserve water, improve water quality, increase energy
efficiency, manage and minimise toxics and waste, and reduce emission of air pollutants
and greenhouse gases during all phases of remediation including investigation, design,
construction, operation, monitoring, and site closure. Moreover, social impacts of any
remedial activity must be considered including the safety of workers and residents, noise
and vibration impacts, ethical procurement and policy compliances. Last, but not least,
under the sustainable remediation umbrella, the economic impacts of remedial activities
need to be considered too. As it can be seen, these two definitions are different in scope:
while SuRF-UK considers remediation activities as part of the broader sustainable
development and considers environmental, social and economic factors, EPA focuses on
the selection of the most environmentally friendly technology to achieve a given
remedial objective, paying less attention to social and/or economic considerations.
This new paradigm has resulted in the need to develop new assessment tools and
metrics such as water intensity (the amount of water necessary to remove one unit mass
of contaminant), soil intensity (the amount of soil displaced or disturbed to remove a unit
mass of contaminant), material intensity (the amount of raw materials extracted,
processed, or disposed per unit mass of contaminant treated), energy efficiency (the
amount of energy needed to remove a unit mass of contaminant), and carbon intensity
(unit mass of CO2 released per unit mass of contaminant). Moreover, since remedial
activities are carried out based upon the objective to reduce risk to potential receptors, a
general metric that takes into account the minimisation of overall input (environmental,
economic and social) per unit of risk reduced, needs also to be developed. This allows the
inclusion in the analysis of remedial activities not based on mass removal. The
interdependence of the many components of a “remedial system” (i.e., environmental
remediation technologies, costs, risks, society, and environment) presents considerable
challenges in the development of a useful framework to guide the implementation of
sustainability principles and to evaluate their success. The main challenge identified in
this paper is to produce assessment tools that are transparent in the input of data and
assumptions that help decision makers to make a balanced decision rather than perform
the assessment per se.
2
Methods
2.1 General
The explosive population growth experienced in the last 100 years resulted in an
increased over exploitation and degradation of land and water resources. As a result,
254
A. Kalomoiri and W. Braida
sustainable reclamation of land and water resources through environmental remediation
is more than ever necessary in order to continuously provide a sustainable quality of life.
Green and sustainable remediation focuses on the “internalities” (remedial objectives,
system performance, costs and environmental impacts local to the remediation site) as
well as the “externalities” (extended environmental, economic, and social impacts) of a
remediation project (Braida and Ogundipe, 2010).
The effectiveness of any tool in assessing sustainability depends on the defined
boundaries of the system. Hence such boundaries need to be inclusive of enough
materials and energy flow streams to accurately portray how truly sustainable the
approach is, yet not to burden the analysis with extraneous information. The SRAM
summarises environmental, economic, and social indicators for sustainability of a given
remedial action plan to support the decision making process. The matrix incorporates
relevant metrics, units of measure and factors for consideration, which are relevant to the
three dimensions of sustainability; environment, economy and society. The SRAM
comprises three columns representing the three dimensions of sustainability and a
variable number of rows depending upon the number of the possible remediation
alternatives for the site.
2.2 A framework for assessing green and sustainable soil and groundwater
clean-up: a theoretical framework approach for SRAM
As we deal with an engineering system, it is necessary to look at the entire contaminated
site from a holistic point of view. The main goal on this framework is to provide a
common methodology in order to analyse such a system regardless the degree of
complexity. The American Cybernetics Society defines system analysis as:
“An approach that applies systems principles to aid a decision-maker with
problems of identifying, reconstructing, optimising and managing a system,
while taking into account multiple objectives, constrains and resources”.
This paper presents the steps towards the development of a matrix to assess sustainable
remediation under a system analysis umbrella, through which the decision makers may
be able to select the most optimum remediation approach satisfying Sustainable
Remediation constrains.
At the end of this section, a ‘systemigram’ is presented which illustrates the overall
picture of the whole decision making process. A systemigram is a very important tool in
the hands of a decision maker, as it provides an overview of the whole process in only
one figure which conveys the project’s information to any category of stakeholders. It is
expected that this can enable stakeholders to understand the steps and the importance of
their contribution in order to finally select the most sustainable remediation method.
Stakeholder identification
Different stakeholders value different aspects of systems performance in different ways,
making decision-making difficult. The stakeholder’s group can include a wide range of
categories such as the following ones:
Federal and state regulators
Local government
Site owner
Responsible parties
255
Promoting decision making through a SRAM
Local residents affected by the site
Residents of neighbouring areas affected by the site remediation actions
Members of environmental organisations, etc.
Those groups can be narrowed down to two major ones, the technical experts and the
public policy group.
Communicate the system boundaries to stakeholders
Stakeholders need to be aware about the system boundaries, including:
Site specifications (site size and location)
Contaminants (hazardous or not)
Remediation time frame / actual risk (how immediate the remediation actions are)
Current situation on site and the nearby areas considering the environment, economy
and the society.
Other constrains pertaining to the specific site
Technical experts most of the time lack the ability to communicate the scientific data to
the public and at this point decision makers roll is to lead the engagement between the
major stakeholders group. The interaction between stakeholders provides a chance for
everyone to understand the scientific analysis process and to agree on the bounds of
uncertainties acceptable for making decisions (Figure 1).
Figure 1
Communicate the system boundaries to stakeholders (see online version for colours)
Stakeholders
must be
communicated
through
desicion-makers
group to
System
boundaries: Site
specifications,
current
Environmental,
Social and
Economic impact
Source: Own illustration
Communicate the Sustainable Remediation Goals to stakeholders
This is an interactive relationship. Decision makers need to inform a principle list of what
the SR goals for the specific contaminated site should be, but on the other hand,
stakeholder’s interaction and opinions could result in a most optimum list on SR goals.
The interconnection is illustrated in Figure 2. Sustainable remediation goals could
include:
Reducing waste production and maximising the recycling and reuse of clean
materials
Reducing the consumption of virgin and non-renewable resources
Minimising energy consumption and greenhouse gas emissions
Improving energy efficiency
Coordinating remediation with green building design
256
A. Kalomoiri and W. Braida
Enhancing ecology and biodiversity during site development
Creating new jobs
Increasing the areas value, etc.
Figure 2
Constructing a more complete list of SR Goals, considering stakeholders needs
(see online version for colours)
Must be cleared
to
Sustainable
Remediation
Goals
Stakeholders
Set the
Source: Own illustration
Categorise and weighting stakeholders importance
Categorise and weighting of stakeholders’ importance is necessary. All stakeholders need
to be heard; however some stakeholders have a greater weighting factor than others. This
is one of the most difficult steps in the whole procedure. Decision makers can prioritise
and weigh the stakeholder’s importance by using a PC (Pairwise Comparison) matrix.
The use of a Pairwise Comparison matrix for the assignment of weights to stakeholders’
views is shown in Table 1.
Table 1
Stakeholders pairwise comparison matrix
S1
S2
S1
1
3
S2
1/3
1
S3
S3
S4
Sm
w2
1
w3
1
…
w4
1
Sm
.
1
Σ1
Σ2
Weighting Factor
w1
S4
SUM
…
Σ3
Σ4
wm
Σm
Where S1, S2… Sm, the stakeholder categories which have been identified at the
stakeholders identification process.
The cells of the matrix presented in Table 1 are filled with numerical values
indicating the relative importance of one stakeholder with respect to others in the same
raw as specified in Table 2. The diagonal is filled with “1s” as each stakeholder is
compared to itself.
After the decision makers complete the matrix, the determination of the weighting
factors is finalised by adding up the figures in each column as represented in
equation (1):
Σi = Σ (α1i+α2i+...αmi),
(1)
The weighting factor for each stakeholder is computed as the ratio of each element from
the first row and the sum for the respective column as presented in equation (1).
257
Promoting decision making through a SRAM
For instance,
Wi = α1i/Σi
(2)
Pairwise comparison matrix measurement scale
Table 2
Intensity of Importance
Definition
1
Equal Importance
3
Moderate Importance
5
Strong Importance
7
Very Strong Importance
9
Extreme Importance
2, 4, 6, 8
Reciprocals of above
For compromises between the above
In comparing elements i and j
If i is 3 compared to j, then j is 1/3 compared to i
System constrains identification
The stakeholders weighting importance, leads to the identification of systems constrain.
System constrains may include:
Remediation time frame
Future use of the site
Local community involvement
Green energy use etc.
System design
Once constrains have been identified the design of the remediation system can be
performed.
Figure 3
System’s design development (see online version for colours)
In order to identify the
Must to
Categorize/weighting
stakeholders
importance
To develop
System
constrains
Decision
makers
System's
design
Source: Own illustration
Sustainability indicators evaluation – Multi-objective analysis implementation
The evaluation of sustainability indicators uses quantitative and qualitative metrics.
Quantitative and qualitative information is processed by applying the Puch matrix
process, multi-objective analysis such as the Analytical Hierarchy Processes (Saaty,
1990) based on pairwise comparisons or Simple Additive Weighting (SAW), depending
upon the accuracy of the data. These approaches have been used to assess sustainability
and to optimise several complex engineering systems.
258
A. Kalomoiri and W. Braida
Uncertainty analysis
In this stage the uncertainty of the variables involved in the decision making process is
assessed and acceptable levels are agreed upon in function of the boundaries of the
system and perhaps time constrains.
Final list of System requirements
The information gathered to this point (e.g. sustainable remediation goals, sustainable
indicators, preliminary design, and acceptable levels of uncertainty) is used to develop
the remedial system requirements and priorities which lead to the selection of the optimal
remedial method. At this point, it is recommended to perform a sensitivity analysis in
order to identify if the top ranking alternative is sensitive to changes in the weights of the
sustainability indicators.
Figure 4
Selection of the Optimum Sustainable Remediation method (see online version
for colours)
Optimum
Remediation
method
In order to
sellect the
Must apply
Sustainability
indicators
Environmental
indicators
Social
Indicators
Economic
Indicators
LCA (SRT,
SiteWise)
Followed by
Multi-Objective
analysis
Addresing
Final list of
Systems
requirments
To enhance
the
Uncertainty
analysis
Source: Own illustration
Once the optimum remediation method has been selected, the design of the site
remediation is performed which leads to the implementation phase of the remedial
project.
Figure 5
Site’s remediation Design and Implementation. Two different opposites’ outcomes after
monitoring implementation (see online version for colours)
Optimum
Remediation
method
To develop
That leads to
Implementation
Site
Remediation
Design
Must apply
SR Goals have been
achieved: leads to
Site closure
Source: Own illustration
Monitoring
SR Goals haven't been
achieved: leads to
Enhancements /
Corrective actions
259
Promoting decision making through a SRAM
During the implementation phase, monitoring is essential, to assess the effectiveness of
the remedial actions with regard to the sustainable remediation objectives. Monitoring
may result to two opposite outcomes:
The first and the most desired one, is that the sustainable remediation goals have been
achieved. That leads to site close out. After the finalisation of remedial activities, post
closure monitoring may be needed for a certain period in order to monitor sustainable
remediation goals. Sampling intensity will depend on the site characteristics.
Sustainable remediation goals have been achieve (see online version for colours)
Figure 6
Site closure
Must continue
Post close
out
Monitoring
SR Goals
Assessment
That will provide the
Source: Own illustration
The second possible outcome is that sustainable remediation goals have not been
achieved or that there is a substantial gap between the projected progress of the project
and the actual progress. In this case, corrective actions need to be identified and
implemented. Before any decision is made, the design team should start over from the
systems requirements and priorities identifications stage and fast move forward to the
other stages as described before in order to select the optimum corrective actions that will
be implemented.
Figure 7
Sustainable remediation goals have not been achieved (see online version for colours)
Should sustain
in the initial
In order to
sellect the
Optimum
Remediation
method
Final list of
Systems
requirments
To develop
That leads to
Implementation
Site
Remediation
Design
Must apply
SR Goals have been
achieved: leads to
Monitoring
Enhancements /
Corrective actions
SR Goals haven't been
achieved: leads to
Site closure
Must continue
Post close
out
Monitoring
That will provide the
SR Goals
Assessment
Source: Own illustration
3
Assembling SRAM
The SRAM is addressed to the decision makers. It is a technical tool that summarises the
information gathered under the system analysis performed and allows the decision maker
to select the most sustainable remediation method.
260
Figure 8
A. Kalomoiri and W. Braida
The overall decision-making process illustration (see online version for colours)
Source: Own illustration
Promoting decision making through a SRAM
261
Figure 9 illustrates the SuRF-US framework to integrate sustainable practices in the
design and implementation of remediation projects.
Figure 9
Linear phase by phase integration of sustainability (SuRF-US: “Framework for
Integrating Sustainability Into Remediation Projects” 2011 US Sustainable Remediation
Forum)
Source: SuRF-US (2011)
At this point, all the process of stakeholder identification, the problem definition, the
potential alternatives, and the list of the criteria that need to be considered for the
evaluation of the alternative remediation, have been considered. The decision matrix
is dependent on the number of the final criteria and the possible alternatives that
has already been identified on the first phase. The process to assemble the SRAM is
described in the following sections.
3.1 Evaluating remedial alternatives based on qualitative criteria
The Pugh method is used to evaluate qualitative criteria. Stakeholder’s involvement is
necessary at this point. Each of the chosen alternatives is compared through the
qualitative criteria and sub criteria that have been selected (see Table 3). The evaluation
is carried out by comparing the selected alternatives against one datum. At a remediation
site, the datum is the current condition.
The scale use is +1, 0 or –1 depending if the alternative is better, similar or worse
than the current condition, respectively. Each of the alternatives will be assessed in the
same way, populating in the Pugh matrix. Then, the total of positives and the total of
negatives are recorded. The overall score will be the summation of the total positives and
the total negative scores. The alternative with the larger positive overall score (comparing
with the datum) is the most desired one. Moreover, most of the times, each criterion
(or sub-criterion on the specific example) has different importance. At this point,
stakeholders can provide a more objective decision as with their contribution, the weights
of each criterion (sub-criterion) will be calculated. The addition of the weighting factors
may result in the selection of a different alternative.
262
A. Kalomoiri and W. Braida
Table 3
Pugh decision matrix
Decision Matrix/Qualitative criteria evaluation
Criteria: Ethical and
equity considerations
Weight
factor
Sub criteria
Alternatives
Scale
Datum
A1
…..
+1
…..
Social justice implementation
–1, 0, 1
0
Ethical operating involved business
–1, 0, 1
0
0
…..
.
+1
…..
.
.
.
…..
.
.
…..
Sub criteria i
–1, 0, 1
0
-1
Aν
…..
Total Positives
Total Negatives
Overall Values
3.2 Evaluating remedial alternatives based on quantitative criteria evaluation
The values of quantitative criteria are calculated from LCA tools. The list of social,
economic and environmental indicators is presented in Table 4 (SuRF-UK, 2010)
Moreover, every indicator has six different criteria and each criterion has as many sub
criteria as the stakeholders identify. An example is presented in Figure 10 for the
environmental indicator.
Table 4
Overarching categories of indicators for sustainability assessment of remediation
options (as identified by SuRF-UK, 2010)
Social Indicators
Environmental Indicators
Economic Indicators
Human health and safety
Impacts on air
Direct economy costs and
benefits
Ethical and equity
considerations
Impacts on soil and ground
conditions
Indirect economy costs and
benefits
Impacts on neighbour
or regions
Impacts on groundwater and
surface waters
Employment and employment
capital
Community involvement
and satisfaction
Impacts on ecology
Inducted costs
Compliance with policy
objectives and strategies
Use of natural resources and
generation of wastes
Life span and project risks
Uncertainty and evidence
Instructiveness
Project flexibility
As explained before, each sub criteria may have a different weighting factor that should
be taken into account at the time of the assessment as shown in the case study discussed
later. The overall score for each alternative is computed by the weighted contribution of
each indicator (criteria and sub criteria).
Wen1
Wen2
Impact on Air
w1
CO2 Emissions
Impacts on Soil and
Groundwater conditions
w1
NOx Emissions
w2
w2
Sub criteria i
Change in physical,
chemical Soil
conditions
Erosion and Soil
stability
w1
wi
Sub criteria i
Release of
Contaminants
Affecting suitability
of water for other
w2
uses
Impacts on Ecology
w1
Sub criteria i
Consequences on
flora
Noise and Vibration
w2 on ecology
.
.
.
wi
Wen5
Wen4
Impact on Groundwater
and Surface waters
.
.
.
.
.
.
wi
Wen3
Use of natural resources
and generation of wastes
w1
Sub criteria i
Generating
renewable energy
by the project
Water abstraction
w2 and disposal
.
.
.
wi
Wen6
Intrusiveness
w1
Risk on flooding
w2
Impacts from
alterations of
landforms
.
.
.
wi
Sub criteria i
.
.
.
wi
Sub criteria i
Promoting decision making through a SRAM
Environmental Indicator
263
Figure 10 Value hierarchy for evaluating SR Alternatives / Fundamental objective: Environmental
Indicator (see online version for colours)
Source: Own illustration
enν
264
A. Kalomoiri and W. Braida
At this point, the process has provided the decision maker with a specific value for each
indicator for each alternative remediation method (enν, sν, ecν). The developed scoring
system (SRAM), will be a 3 x matrix, with 3 columns, representing the sustainability
dimensions (Social, Economic and Environmental) and one row for each individual
alternative.
Figure 11 Hierarchy for evaluating SR Alternatives (see online version for colours)
Goal: Sustainable Remediation
Method
Alternative 2
Alternative ?
.
.
.
.
.
.
.
Alternative 1
Environmental
Indicator
Environmental
Indicator
Environmental
Indicator
Social Indicator
Social Indicator
Social Indicator
Economic Indicator
Economic Indicator
Economic Indicator
Source: Own illustration
Environmental
Social
Economic
Alternative 1
Sustainability Dimensions
Environmental
Social
Economic
Alternative 2
Sustainability Dimensions
.
.
.
.
Alternative v
Environmental
Social
Economic
Sustainability Dimensions
265
Promoting decision making through a SRAM
The SRAM is illustrated as following:
SRAM
Environmental
Social
Economic
Remediation
Alternatives
Sustainability Dimensions
The final score for each alternative will be given from the following summation:
(en
v
s ec )
(3)
where ν is the total number of alternatives being evaluated.
The higher the score, the better the alternative is. For a sustainable remediation
method, the weighing factor for each sustainability dimension should be equal. SRAM
at this point can provide the decision makers with the transparency which allows them
to evaluate the different alternatives according to the stakeholders’ priority along
the sustainability dimensions. If this is the case, applying multi-objective analysis
considering the different weighting factor will provide the decision makers with the
optimum alternative choice.
Moreover, if at this point the weighting factors on the three sustainability dimensions
are not identified, applying sensitivity analysis may help decision makers in finding the
optimum remedial alternative.
4
Results/case study
This section exemplifies the use of SRT in gathering information for the population of
environmental, social and economic matrices. The case study relates to an industrial area
site 4.5 acres large located in the state of New Jersey. It has been estimated that 15,000 to
25,000 pounds of TCE and PCE were released from the annex of a former building into
the subsurface, more than 25 years ago. This discharge has been the source of many soil
and groundwater investigations, interim remedial measures and millions of dollars of
expenditure over the years.
The remedial goals for this site were to remediate PCE and TCE in shallow and deep
soils in the unsaturated zone, below the New Jersey Department of Environmental
Protection Soil Clean Up Criteria; to remediate groundwater to achieve the groundwater
quality standards or background levels; and to remediate and or address vapour intrusion
in on-site and off-site buildings. It can be argued that a sustainability appraisal of the
remedial goals for the site (or even the whole environmental policy regarding clean up
levels) may be granted, but this issue is outside the scope of this work. As such, an
analysis of the data is performed, even though the remedial objective perhaps is not the
most sustainable one.
Ten model runs were completed evaluating five different technologies. The summary
of the outputs are presented in the Table 5. The data were developed by Mr Trevor King
from Langan Engineering.
266
A. Kalomoiri and W. Braida
Table 5
Summary of Sustainability Analysis Results, derived from SRT (Sustainable
Remediation Tool, USA Air Force, 2008) analysis
Alternatives
A1
Technologies
(soil & GW)
A2
Excavation & MNA
A3
A4
A5
SVE (& ISCO
SVE &
ERD
ERH
In situ
In situ
In situ
Sustainability Metrics
Non-Hazardous
Hazardous
CO2 Emissions (tons)
103.8
103.8
470
290
710
Pounds CO2/TCE (lb/lb)
285
285
21,028
8,428
110
Total Energy (KWh)
404,000
404,000
784,000
762,000
3,100,000
Technology Cost ($)
600,000
1,770,000
2,390,000
1,150,000
350,000
Safety/
Accident Risk (lost hrs)
4.05
4.05
13.2
4.2
0.0003
Pounds TCE (lbs)
13.013
13.013
13.013
13.013
13.013
Remediation Time (yrs)
<0.5-5
<0.5-5
<5
<10
<1
Table 6
Criteria been selected
Criteria
Sustainability Metrics
Alternatives
SR Indicator
A1
A2
A3
A4
A5
103.8
103.8
470
290
710
C1 CO2 Emissions (tons)
Environmental
C2 Technology Cost ($)
Economic
Safety/Accident Risk
C3 (lost hours)
Social
4.05
4.05
13.2
4.2
0.0003
Remediation Time
C4 (years)
Social
0.5
0.5
3
5
1
600,000 1,770,000 2,390,000 1,150,000 350,000
Using the data presented in Table 5, the evaluation of the five different alternatives with
respect to the chosen criteria was performed. The remediation time for Excavation &
MNA was estimated in less than 0.5–5 years (0.5 years of excavation and 4.5 years of
MNA), for SVE & ISCO and SVE & ERD remediation times were less than 5 and 10
years, respectively. Among the metrics calculated by the SRT, the ones listed in Table 8
were chosen for the sustainability analysis as they closely match SURF-UK indicators
(Table 4).
In order to find which is the most efficient remediation technology considering
environmental, economic and social indicators, we need to calculate the overall values of
the selected Alternatives. To do so, the first step was to determine the weights for each
output value from LCA implementation for each alternative. Assuming that each
criterion varies linearly and as all of them have negative impact, we use the Simple
Additive Weighting (SAW) (Zarghmi and Szidarovskzky) method to determine the
values. The data was normalised into the interval [0, 1] by using the linear transformation
described in equation (4) (Zarghami and Szidarovszky, 2011):
aij
aij M i
mi M i
(4)
267
Promoting decision making through a SRAM
Where mi and Mi, the computed minimum and maximum values of each criterion, for
i = 1,2,3,4 and j = 1,2,3,4,5 (Table 5), respectively. Results of the transformation are
presented in Table 7.
Normalised overall values for alternatives
Table 7
Criteria
Weights
Alternatives
A1
A2
A3
A4
A5
C1
0.33
1
1
0.396
0.693
0
C2
0.33
0.877
0.338
0
0.608
1
C3
0.23
0.693
0.693
0
0.682
1
C4
0.1
1
1
0.444
0
0.888
Si: Overall Scores for Alternatives
0.879
0.689
0.175
0.586
0.649
Si Normalised Overall Scores for Alternatives
0.294
0.232
0.057
0.198
0.220
Following, the overall scores for alternatives was determined using equation (5)
(Zarghamiand and Szidarovszky, 2011) where wi, are the weight factors for each
criterion. In this regard, a generic approach was used and the same weighting factors,
0.33, were selected for the three sustainability indicators. For C3 and C4 criteria, we use
0.23 and 0.1 respectively, considering that safety has a greater weight than the
technology’s time implementation. Finally, the normalised overall scores for alternatives
were computed, using the equation (6).
Si
Si
n
wi aij
(5)
Si
Si
(6)
i 1
The results in Table 7 suggest that the best choice is the first alternative, as it gives the
smallest weighted average satisfaction value. The alternatives’ ranking that was obtained
from best to the most undesired is as follows:
A1>A2>A5>A4>A3
A sustainable remediation decision tool should be able to guide the user in gathering the
appropriate information and present the associated trade-offs in a manner that allows the
decision maker to reach a conclusion that balances those trade-offs. Furthermore, there
are cases which have specific constrains that also need to be taken into account. Those
constrains might lead the decision maker into an optimum solution which is not the most
sustainable one.
The visual presentation of the Table 7 is displayed in Figure 12. The performance
sensitivity graph shows the relative importance of each of the criteria as bars, and the
relative preference for each alternative with respect to each criterion. The overall
alternative preferences (the normalised overall score) are presented in the foremost right
column. On Figure 12, one can see that alternative A3 performance is worse than
268
A. Kalomoiri and W. Braida
alternatives A1 and A2 for the four criteria analysed and worse than alternatives A4 and
A5 for three of the four criteria. Thus, this alternative cannot affect the total top ranking
even if the criteria weights change. The same can be assumed for alternative A4.
Figure 12 Performance Sensitivity graph under sustainability umbrella (see online version
for colours)
Source: Own illustration, based on Expert Choice software
A sensitivity analysis was performed using Expert Choice software (http://expertchoise.
com), in order to determine the impact of weighting on the ranking of the top
alternatives.
Figure 13 shows that the top ranking is not sensitive to a change in the criteria
weight. In order to place the alternative A5 to the top rank, C2 criterion weighting factor
should be more than 80% (or 0.8 depending on the scale). That automatically reduces the
weighting factors for the rest of the criteria to negligible values (see Figure 13). Thus, A5
could be an optimum solution for a specific contaminated site dealing with harsh budget
constraints, but does not satisfy sustainability criteria.
Figure 13 Performance Sensitivity graph manipulating C2 criterion for changing the top ranking
of alternatives A1 and A5 (see online version for colours)
Source: Own illustration, based on Expert Choice software
Promoting decision making through a SRAM
5
269
Conclusions
Our planet has undergone significant deterioration during the last decades. Today, more
than ever, it is necessary that all human activities be carried out under the framework of
sustainability. Moreover, the demand of decision tools in order to assess sustainability
practices in general and sustainable environmental remediation approaches in particular,
has increased.
An important conclusion from the real case study is that the final decision in the
selection of a remedial approach may change depending upon criteria weights. Thus,
criteria weighting is the most important stage of developing an assessment tool and
stakeholder involvement in this direction is important and very critical in providing an
objective, balanced, and socially acceptable decision that at the same time eliminates
uncertainties.
Acknowledgements
We gratefully acknowledge the QUESTOR Centre for funding the research project “A
Process for Developing a Sustainable Remediation Assessment Matrix (SRAM)”.
Moreover, we would like to like to acknowledge the contributions of Professor Jonathan
Smith from Shell Global Solutions (UK) for his very helpful comments and Mr. Trevor
King from Langan Engineering, who provided the data, used in the evaluation the
different remediation methods by SRT.
References
Braida, W. and Ogundipe, A. (2010) ‘A process for developing a Sustainable Remediation
Assessment Matrix (SRAM)’, Paper presented at the X Protection and Restoration of the
Environment International Conference, 5–9 July 2010, Corfu, Greece.
Expert Choice Software 11.5. Available online at: http://expertchoice.com/ (accessed on 1
November 2012).
Gernot, D., Moritz, O. and Werner, F. (2013) ‘Introducing a goal-oriented sustainability assessment
method to support decision making in contaminated site management’, Journal of
Environmental Science & Policy, Vol. 25, pp.207–217.
Saaty, T. (1990) ‘How to make a decision: the analytic hierarchy process’, European Journal of
Operating Research, Vol. 48, No. 1, pp.9–26.
Sussman, J., Dodder, R., McConnel, J., Mostashari, A. and Sgouridis S. (2007) The CLIOS
Process, A User’s Guide, Massachusetts Institute of Technology.
Scheuermann, K. (2009) ‘Green remediation – estimating the environmental footprint at a
corrective action clean-up, pilot study at Romic East Palo Alto’, Paper presented at the
19th Annual NARPM Training Conference, 2–5 June 2009, Atlanta, Georgia, USA.
Available online at: http://www.epa.gov/region9/waste/romic-eastpaloalto/pdf/Romic-GreenRemediation-Pilot-Study-NARPM.pdf (accessed on June 2011).
SRT (Sustainable Remediation Tool, USA Air Force, 2008). Available online at: http://www.
afcee.af.mil/resources/technologytransfer/programsandinitiatives/sustainableremediation/srt/in
dex.asp (accessed on 3 September 2011).
270
A. Kalomoiri and W. Braida
Sustainable Remediation Forum UK (SuRF-UK) A Framework for Assessing the Sustainability of
Soil and Groundwater Remediation. Available online at: http://www.claire.co.uk/index.
php?option=com_phocadownload&view=file&id=61:initiatives&Itemid=78 (accessed on
March 2010).
Holland, K., Lewis, R., Tripton, K., Karnis, C., Petrovskis, E., Bull, L., Taege, D. and Hook, C.
(2011) ‘Sustainable Remediation Forum US (SuRF-US) (2011) Framework for Integrating
Sustainability Into Remediation Projects’, Willey Online Library, Vol. 21, No. 3, pp.7–38.
Available online at: http://www.sustainableremediation.org/library/guidance-tools-and-otherresources/
Zarghmi, M. and Szidarovskzky, F. (2011) ‘Simple Additive Weighting (SAW)’, Multi-criteria
Analysis – Applications to Water and Environmental Management, Springer-Verlag, Berlin,
Heidelberg, ISBN: 978-3-642-17936-5, pp.26–29.