10. PROJECT SCHEDULE PLANNING
ADRIENNE WATT
Table of
Contents
In order to develop our schedule, we first need to define the activities, sequence them in the right order, estimate the
resources needed, and estimate the time it will take to complete the tasks.
DEFINING ACTIVITIES
The activity definition process is a further breakdown of the work package elements of the WBS. It documents the specific
activities needed to fulfill the deliverables detailed in the WBS. These activities are not the deliverables themselves but the
individual units of work that must be completed to fulfill the deliverables. Activity definition uses everything we already
know about the project to divide the work into activities that can be estimated. You might want to look at all the lessons
learned from similar projects your company has done to get a good idea of what you need to do on the current one.
Expert judgment in the form of project team members with prior experience developing project scope statements and WBS
can help you define activities. If you are asked to manage a project in a new domain, you might also use experts in
that particular field to help define tasks so you can understand what activities are going to be involved. You may want
to create an activity list and then have the expert review it and suggest changes. Alternatively, you could involve the expert
from the very beginning and ask to have an activity definition conversation with him or her before even making your first
draft of the list.
Sometimes you start a project without knowing a lot about the work that you’ll be doing later. Rolling-wave planning lets
you plan and schedule only the portion that you know enough about to plan well. When you don’t know enough about a
project, you can use placeholders for the unknown portions until you know more. These are extra items that are put at high
levels in the WBS to allow you to plan for the unknown.
A CASE STUDY
Susan and Steve have decided to tie the knot, but they don’t have much time to plan their wedding. They want the big day
to be unforgettable. They want to invite many people and provide a great time. They’ve always dreamed of a June
wedding, but it’s already January. Just thinking about all of the details involved is overwhelming. Susan has been dreaming
of the big day since she was 12, but it seems that there’s so little time for all the tasks to be completed. When they were
choosing the paper for the invitations, the couple realized that they needed help.
Susan:
Steve, we need some help.
Steve
Don’t worry. My sister’s wedding
planner was great. Let me give her a
call. [Steve calls the wedding planner
Sally.]
Wedding
Planner
Hello Susan and Steve.
Steve
We want everything to be perfect.
Susan
There is so much to do! Invitations,
food, guests, and music.
Steve
Oh no, we haven’t even booked a
place!
Susan
And it has to be done right. We can’t
print the invitations until we have the
menu planned. We can’t do the
seating arrangements until we have
the RSVPs. We aren’t sure what kind
of band to get for the reception, or
should it be a DJ? We’re just
overwhelmed.
Steve
My sister said you really saved her
wedding. I know she gave you over a
year to plan.
Steve
But I’ve always dreamed of a June
wedding, and I’m not willing to give
that up. I know it’s late, but Sally can
you help us?
Wedding
Planner
Take it easy, guys. I’ve got it under
control. We’ve a lot of people and
activities to get under control. You
guys really should have called six
months ago, but we’ll still make this
wedding happen on time.
Much work has to be done before June. First, Sally figures out what work needs to be done. She starts to put together a todo list:
Invitations
Flowers
Wedding cake
Dinner menu
Band
Since many different people are involved in the making of the wedding, it takes much planning to coordinate all the work
in the right order by the right people at the right time. Initially, Sally was worried that she didn’t have enough time to make
sure that everything would be done properly. However, she knew that she had some powerful time management tools on
her side when she took the job, and these tools would help her to synchronize all the required tasks.
To get started, Sally arranged all the activities in a work breakdown structure. The next exercise presents part of the WBS
Sally made for the wedding.
WBS EXERCISE (SOLUTION FOLLOWS)
Arrange the following activities into the WBS (Figure 10.1) to show how the work items decompose into activities.
Shop for shoes
Create guest list
Have the tailoring and fitting done
Shop for dress
Find caterer
Cater the wedding
Wait for RSVPs
Mail the invitations
Finalize the menu
Print the invitations
Choose the bouquet
Figure 10.1: Work breakdown structure (WBS) based on project
phase.
Illustration from Barron & Barron Project Management for
Scientists and Engineers, http://cnx.org/content/col11120/1.4/
Solution to Exercise: Figure 10.2
Figure 10.2: Work breakdown structure (WBS) based on project
phase – solution.
Illustration from Barron & Barron Project Management for
Scientists and Engineers, http://cnx.org/content/col11120/1.4/
ACTIVITY LIST
Now that the activity definitions for the work packages have been completed, the next task is to complete the activity list.
The project activity list is a list of everything that needs to be done to complete your project, including all the activities that
must be accomplished to deliver each work package. Next you want to define the activity attributes. Here’s where the
description of each activity is kept. It includes all the information you need to figure out plus the order of the work. Any
predecessor activities, successor activities, or constraints should be listed in the attributes along with descriptions and any
other information about resources or time that you need for planning. The three main kinds of predecessors are finish-tostart (FS), start-to-start (SS), and finish-to-finish (FF). The most common kind of predecessor is the finish-to-start. It means
that one task needs to be completed before another one can start. When you think of predecessors, this is what you usually
think of; one thing needs to end before the next can begin. It’s called finish-to-start because the first activity’s finish leads
into the second activity’s start (Figure 10.3).
Figure 10.3: An example of a finish-to-start (FS) predecessor.
Illustration from Barron & Barron Project Management for
Scientists and Engineers, http://cnx.org/content/col11120/1.4/
The start-to-start predecessor is a little less common, but sometimes you need to coordinate activities so they begin at the
same time (Figure 10.4).
Figure 10.4: An example of a start-to-start (SS)
predecessor.
Illustration from Barron & Barron Project
Management for Scientists and Engineers,
http://cnx.org/content/col11120/1.4/
The finish-to-finish predecessor shows activities that finish at the same time (Figure 10.5).
Figure 10.5: An example of a finish-to-finish (FF) predecessor.
Illustration from Barron & Barron Project Management for Scientists
and Engineers, http://cnx.org/content/col11120/1.4/
It is possible to have start-to-finish (SF) predecessors. This happens when activities require that another task be started
before the successor task can finish. An example might be that the musicians cannot finish playing until the guests have
started leaving the ceremony. In addition, there are some particular types of predecessors that must be considered.
EXTERNAL PREDECESSORS
Sometimes your project will depend on things outside the work you’re doing. For the wedding, we are depending on the
wedding party before us to be out of the reception hall in time for us to decorate. The decoration of the reception hall then
depends on that as an external predecessor.
DISCRETIONARY PREDECESSORS
These are usually process- or procedure-driven or best-practice techniques based on past experience. In the wedding
example, Steve and Susan want the bridesmaids to arrive at the reception before the couple arrives. There’s no necessity; it
is just a matter of preference.
MANDATORY PREDECESSORS
You can’t address an invitation that hasn’t been printed yet. So printing invitations is a mandatory predecessor for
addressing them. Mandatory predecessors are the kinds that have to exist just because of the nature of the work.
LEADS AND LAGS
Sometimes you need to give some extra time between activities. Lag time is when you purposefully put a delay between
the predecessor task and the successor. For example, when the bride and her father dance, the others wait awhile before
they join them (Figure 10.6).
Figure 10.6: A lag means making sure that one task
waits a while before it gets started.
Illustration from Barron & Barron Project Management
for Scientists and Engineers,
http://cnx.org/content/col11120/1.4/
Lead time is when you give a successor task some time to get started before the predecessor finishes (Figure 10.7). So you
might want the caterer preparing dessert an hour before everybody is eating dinner.
Figure 10.7: A lead is when you let a task get
started before its predecessor is done.
Illustration from Barron & Barron Project
Management for Scientists and Engineers,
http://cnx.org/content/col11120/1.4/
MILESTONES
All of the important checkpoints of your project are tracked as milestones. Some of them could be listed in your contract as
requirements of successful completion; some could just be significant points in the project that you want to keep track of.
The milestone list needs to let everyone know which milestones are required and which are not.
Some milestones for Susan and Steve’s wedding might be:
Invitations sent
Menu finalized
Location booked
Bridesmaids’ dresses fitted
As you figure out which activities will need to be done, you may realize that the scope needs to change. When that
happens, you need to create a change request and send it through the change control system.
Some things that could go wrong:
Wedding planner
We just got the programs back from the printer and they’re all wrong.
Steve
The quartet cancelled. They had another wedding that day.
Susan
Aunt Jane is supposed to sing at the service, but after what happened at her uncle’s
funeral, I think I want someone else to do it.
Steve
Should we really have a pan flute player? I’m beginning to think it might be overkill.
Susan
Apparently! Maybe we should hold off on printing the invitations until these things are
worked out.
Wedding Planner
OK, let’s think about exactly how we want to do this. I think we need to be sure about
how we want the service to go before we do any more printing.
THE ACTIVITY SEQUENCING PROCESS
Now that we know what we have to do to make the wedding a success, we need to focus on the order of the work. Sally sat
down with all of the activities she had defined for the wedding and decided to figure out exactly how they needed to
happen. That’s where she used the activity sequencing process.
The activity attribute list Sally created had most of the predecessors and successors necessary written in it. This is where
she thought of what comes first, second, third, etc. Sally’s milestone list had major pieces of work written down, and there
were a couple of changes to the scope she had discovered along the way that were approved and ready to go.
Example milestone list: Steve and Susan had asked that the invitations be printed at least three months in advance to be sure that
everyone had time to RSVP. That’s a milestone on Sally’s list.
Example change request: When Sally realized that Steve and Susan were going to need another limo to take the bridesmaids to the
reception hall, she put that change through change control, including running everything by Susan’s mother, and it was approved.
CREATING THE GANTT CHART
A Gantt chart is a type of bar chart, developed by Henry Gantt, that illustrates a project schedule. Gantt charts are easy to
read and are commonly used to display schedule activities. These charts display the start and finish dates of the terminal
elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown
structure of the project. Some Gantt charts also show the dependency relationships (i.e., precedence network) between
activities.
Gantt charts show all the key stages of a project and their duration as a bar chart, with the time scale across the top. The
key stages are placed on the bar chart in sequence, starting in the top left corner and ending in the bottom right corner
(Figure 10.8). A Gantt chart can be drawn quickly and easily and is often the first tool a project manager uses to provide a
rough estimate of the time that it will take to complete the key tasks. Sometimes it is useful to start with the target deadline
for completion of the whole project, because it is soon apparent if the time scale is too short or unnecessarily long. The
detailed Gantt chart is usually constructed after the main objectives have been determined.
Figure 10.8 Gantt chart for directory production – source:
http://labspace.open.ac.uk/mod/resource/view.php?id=451673
In this example in Figure 10.8, key stage K (Organize distribution) starts at week 23 so that its end point coincides with key
stage L (Distribute directory). However, K could begin as early as week 17, as soon as key stage J is completed. Key stage
K is therefore said to have “slack.” Key stage H (Agree print contract) has been placed to end at week 12. However, it
could end as late as week 22, because key stage I (Print directory) does not begin until week 23. Key stage H is therefore
said to have “float.” Float time can be indicated on the chart by adding a line ahead of the bar to the latest possible end
point. Slack and float show you where there is flexibility in the schedule, and this can be useful when you need to gain time
once the project is up and running.
You can add other information to a Gantt chart, for example:
Milestones could be indicated by using a symbol such as a diamond or triangle.
Project meetings could be indicated by another symbol such as a circle.
Reviews of progress could be indicated by a square.
For a complex project, you may decide to produce a separate Gantt chart for each of the key stages. If you do this shortly
before each key stage begins, you will be able to take any last-minute eventualities into account. These charts provide a
useful tool for monitoring and control as the project progresses.
Gantt charts are relatively easy to draw by hand, but this doesn’t offer the same level of flexibility during monitoring that
you would get from a software package. Various programs are available to assist project managers in scheduling and
control. Once the data have been entered, a program helps you to work on “what if” scenarios, showing what might happen
if a key stage is delayed or speeded up. This is more difficult if you are working manually.
CREATING THE NETWORK DIAGRAM
Many project managers use network diagrams when scheduling a project. The network diagram is a way to visualize the
interrelationships of project activities. Network diagrams provide a graphical view of the tasks and how they relate to one
another. The tasks in the network are the work packages of the WBS. All of the WBS tasks must be included in the
network because they have to be accounted for in the schedule. Leaving even one task out of the network could change the
overall schedule duration, estimated costs, and resource allocation commitments.
The first step is to arrange the tasks from your WBS into a sequence. Some tasks can be accomplished at any time
throughout the project where other tasks depend on input from another task or are constrained by time or resources.
Figure 10.9: The relationship between the work breakdown
structure (WBS) and the network diagram.
Illustration from Barron & Barron Project Management for
Scientists and Engineers, http://cnx.org/content/col11120/1.4/
The WBS is not a schedule, but it is the basis for it. The network diagram is a schedule but is used primarily to identify key
scheduling information that ultimately goes into user-friendly schedule formats, such as milestone and Gantt charts.
The network diagram provides important information to the project team. It provides information about how the tasks are
related (Figure 10.9), where the risk points are in the schedule, how long it will take as currently planned to finish the
project, and when each task needs to begin and end.
In our wedding planner example, Sally would look for relationships between tasks and determine what can be done in
parallel and what activities need to wait for others to complete. As an example, Figure 10.10 shows how the activities
involved in producing the invitations depend on one another. Showing the activities in rectangles and their relationships as
arrows is called a precedence diagramming method (PDM). This kind of diagram is also called an activity-on-node (AON)
diagram.
Another way to show how tasks relate is with the activity-on-arrow (AOA) diagram. Although AON is more commonly
used and is supported by all project management programs, PERT is the best-known AOA-type diagram and is the
historical basis of all network diagramming. The main difference is the AOA diagram is traditionally drawn using circles as
the nodes, with nodes representing the beginning and ending points of the arrows or tasks. In the AOA network, the arrows
represent the activities or tasks (Figure 10.11).
Figure 10.10: An example of an activity on node (AON) diagram.
Illustration from Barron & Barron Project Management for
Scientists and Engineers, http://cnx.org/content/col11120/1.4/
All network diagrams have the advantages of showing task interdependencies, start and end times, and the critical path (the
longest path through the network) but the AOA network diagram has some disadvantages that limit the use of the method.
Figure 10.11: An example of an activity arrow (AOA) network
diagram.
Illustration from Barron & Barron Project Management for
Scientists and Engineers, http://cnx.org/content/col11120/1.4/
The three major disadvantages of the AOA method are:
The AOA network can only show finish-to-start relationships. It is not possible to show lead and lag except by adding
or subtracting time, which makes project tracking difficult.
There are instances when dummy activities can occur in an AOA network. Dummy activities are activities that show
the dependency of one task on other tasks but for other than technical reasons. For example, one task may depend on
another because it would be more cost effective to use the same resources for the two; otherwise the two tasks could be
accomplished in parallel. Dummy activities do not have durations associated with them. They simply show that a task
has some kind of dependence on another task.
AOA diagrams are not as widely used as AON diagrams simply because the latter are somewhat simpler to use, and all
project management software programs can accommodate AON networks, whereas not all can accommodate AOA
networks.
THE CRITICAL PATH
The critical path describes the sequence of tasks that would enable the project to be completed in the shortest possible time.
It is based on the idea that some tasks must be completed before others can begin. A critical path diagram is a useful tool
for scheduling dependencies and controlling a project. In order to identify the critical path, the length of time that each task
will take must be calculated.
Let’s take a look at an example. The length of time in weeks for each key stage is estimated:
Key stage
Estimated time in weeks
A
Secure funds
0
B
Negotiate with other
agencies
4
C
Form advisory group
4
D
Establish data
collection plan
6
E
Collect data
4
F
Write directory text
4
G
Identify printer
2
H
Agree print contract
2
I
Print directory
4
J
Agree distribution plan
12
K
Organize distribution
4
L
Distribute directory
2
Table 10.1 Stages of the Critical Path
Source: http://labspace.open.ac.uk/mod/resource/view.php?id=451674
We have given the key stage “Secure funds” an estimated time of zero weeks because the project cannot start without the
availability of some funding, although estimates would provide detail at a later stage. The stages can now be lined up to
produce a network diagram that shows that there are three paths from start to finish and that the lines making up each path
have a minimum duration (Figure 10.12).
If we now trace each of the possible paths to “Distribute directory” (the finishing point), taking dependencies into account,
the route that has the longest duration is known as the critical path. This is the minimum time in which it will be possible to
complete the project.
Figure 10.12: Critical Path Diagram
In this example, the critical path is A–B–C–D–E–F–I–L, and the earliest completion date for the project is the sum of the
estimated times for all the stages on the critical path – 28 weeks – from the point of securing the funding. All the key stages
on the critical path must be completed on time if the project is to be finished on schedule.
If the projected total time is much longer than the project sponsor’s expectations, you will need to renegotiate the time
scale. Mapping the critical path helps to identify the activities that need to be monitored most closely.
ATTRIBUTION
This chapter of Project Management is a derivative copy of Project Management by Merrie Barron and Andrew Barron
licensed under Creative Commons Attribution 3.0 Unported, Gantt Chart by Wikipedia licensed under Creative Commons
Attribution-ShareAlike 3.0 Unported and Planning a Project by OpenLearn Labspace under Creative Commons
Attribution 3.0 Unported.
10.
10. Project
Project Schedule
Schedule Planning
Planning by
by Adrienne Watt is
is licensed
licensed under
under aa Creative
Creative Commons
Commons Attribution
Attribution 4.0
4.0 International
International License
License,,
exc
exceepptt wwhheere
re ootthheerrwwiissee nnootteedd..
This textbook is available for free at open.bccampus.ca