132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
CHAPTER 7: ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
IMPLEMENTATION SCHEDULE- SOCIAL MANAGEMENT PLAN
Table 1: Social Management Plan
Activity /
Issues
Potential
Impacts
Proposed Management / Mitigation
Measures
Parameter to be
monitored
Measurement &
frequency
Implementation
Schedule
Action taken
Typical “general impacts” during “pre-construction phase” and corresponding mitigation measures for transmission and distribution projects.
Securing
for
land
substations
Loss of land, Use of government land for
assets
and
substations as far as possible
income;
Careful site selection to avoid existing
Change
in
settlements and sensitive locations
social status
Careful selection of site to avoid
encroachment of socially, culturally
Social
and archaeological sensitive areas
Inequities
(e.g. sacred groves, graveyards,
religious worship place, monuments
etc.)
As no involuntary land acquisition
is taking place, the provisions of
RFCTLARRA, 2013 will not be
triggered in the case of Package 5
Location of Social
Inequities
overhead
line
and
towers
Land documents
At time of On f i l i n g o f l a n d
land securing requisition by utility
Consultation with local Once
authorities/ autonomous
councils and land owners
Before
starting
construction of the
substations
Consultation
Women
Before
starting
construction of the
substations
with Once
Stakeholder
Consultations with prior
notice conducted with a
minimum
of
15-20
persons per consultation.
Careful route selection to avoid Consultation with local Once
existing settlements and sensitive
authorities/ autonomous
locations
councils, land owners and
Transmission lines in Package 5 largely
women on location of
crosses over farm land. Ensure women
line
overhead
towers/poles/ laying of
receive compensation for RoW, and
damage to crops, trees etc. in
underground distribution
cases where land rights are with
line & alignment and
women
design
At time of detailed
survey for route
alignment
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Damage
to Careful selection of site and route Consultation with local Once
alignment to avoid encroachment of
authorities/ autonomous
socially
/
culturally
socially, culturally and archaeological
councils and land owners
sensitive areas (e.g. sacred groves,
on location of overhead
sensitive and
historical sites
graveyards, religious worship place,
line towers/poles/ laying
of
underground
monuments etc.)
distribution
line
&
alignment and design
At time of detailed
survey for route
alignment
Loss
of Use existing tower or footings Payment of damages / Quarterly till Prior to the start of
agricultural
wherever possible.
compensation.
process
is construction
production/
completed
Compensation is paid
Payment for crop and tree damages
in
change
for: Land coming in
during
construction
and
cropping
corridor of width of Right
compensation for tower footing
pattern
of Way, Land under the
Compensation for RoW Corridor
tower footing, Damage to
trees and crops, and
Damage to constructed
structure
Refer to Compensation
Plan
for
Temporary
Damage in Annexure 2
Interference
with
communicatio
n n channel
Proposed projects which involve lines PTCC Approval
over 132kV to get approval from
Power
&
Telecommunication
Coordination Committee (PTCC)
before commission
Once
Encroachme The proposed projects sites that have Encroachers
and Once,
with
squatters to be notified
periodic
nts
and
presence of encroachers and
that the land is for public
monitoring
presence of
squatters to be notified for eviction
purpose
and
to
be
given
Squatters
and harvest of any standing crop.
adequate
time
for
removal of standing
crops /assets
At time of detailed
survey
for
route
alignment
At time of detailed
survey for route
alignment,
with
periodic monitoring
till
construction
phase.
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Constructio
n
of
substation
and laying
of lines
Impact
on
worker health
and safety –
possibility of
electrification,
falling
from
height,
and
exposure
to
magnetic
fields
Impact
on community
and
health
safety due to
exposure
electric
to
currents,
hazardous
materials,
electromagnet
ic fields etc.
Contractor should follow defined
protocols for health & safety
Electric Safety Officer to be
appointed
Safety manger to be deployed during
construction
Construction camps should have
adequate sanitation / safety facilities
Safety equipment should be provided
to workers
Sign-boarding of hazardous areas /
materials should be done
Presence of documented Daily
for
health & safety protocols
safety
Safety manger present at
equipment
site during construction
Weekly
for
other
Use of safety equipment
by workers
measures
Presence of signboards
at appropriate locations
Adequate sanitation /
safety
standards
at
camps
During
construction
Refer the Annexure 2:
Labour Management
Plan
Display danger signs at appropriate Signboards / instructions Weekly
for During Construction
locations
are
displayed
at
signboards
appropriate places
Display boards with precautions to be
Monthly
for
adopted by consumers, owners, Use of insulated wires in
compensatio
occupiers, electrical contractors,
congested areas
n
electric workmen and suppliers
Compensation is paid
Display
of
instructions
for
resuscitation of persons suffering
from electric shock.
Use of insulated wires in highly
congested residential areas
Compensation is paid to nondepartmental persons in the case of
fatal accidents due to electrocution.
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Safety
Construction sites are properly lit
and security Minimize blockage of access roads
concerns of
women and
other
population
around
the
construction
site
Site is adequately lit at Weekly
night
Access roads are usable
Violation
labour
standards
Labour laws are being Monthly
followed
of Contractor should follow labour
standards as per applicable laws
such as minimum wages, equal pay
for equal work, no child labour etc.
Provision of welfare measures such
as canteens, first aid facilities,
housing
accommodation
for
workers near the work place etc.
Operation Impact on worker
and
health and safety
maintenanc – possibility of
e
of electrocution,
substations falling from height,
and
and exposure to
maintenanc magnetic fields
e of lines
Welfare
available
facilities are
Safety equipment should be provided Use of safety equipment Weekly
to workers
by workers
Sign boarding of hazardous areas / Presence of signboards
materials should be done
at appropriate locations
Careful design
Adequate sanitation /
Safety awareness
safety standards
Emergency planning
Sanitation and medical facilities
During construction
During
Construction
Refer
the
Annexure 2:
Labour
Management
Plan
During running of
the substation
Refer the Annexure
2:
Labour
Management Plan
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Impact
on
community health
and safety due to
exposure
to
electric current
Display danger signs at appropriate Signboards / instructions Weekly
for During running of the
locations
signboards
substation
are
displayed
at
appropriate places
Display boards with precautions to be
Monthly
for
adopted by consumers, owners, Compensation is paid
compensatio
occupiers, electrical contractors,
n
electric workmen and suppliers
Display
of
instructions
for
resuscitation of persons suffering
from electric shock.
Compensation is paid to nondepartmental persons in the case of
fatal accidents due to electrocution.
Implementation Schedule- Environmental Management Plan
Table 2: Environment Management Plan
Project stage - anticipated
Environmental issues and
impacts
Proposed mitigation measure
Parameter to be
monitored
Institutional Responsibility
Implementation
Action taken
Pre-construction Phase (Planning and Design)
Planning Phase Impacts
Impacts due to
Project Location
Selection of route for the transmission lines and sites for
sub- stations need to avoid the environmentally sensitive
areas like wildlife sanctuaries, national parks, reserved
forest area, historical and cultural sites, or private land to
the extent possible.
Location
of
substations and
line alignment
Avoided wildlife sanctuaries,
Field Staff national parks, reserved forest
(AE
and area,
historical and cultural
ADE)
sites, or private land to the
extent possible
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Loss of property and
impact on habitation
The alignment of proposed new sub-stations,
transmission lines to be finalized after detailed physical
survey.
The line routing will be finalized avoiding existing
settlements such as cities, villages, houses, huts,
buildings, fruit bearing trees or any other existing
settlement directly related with the livelihood of people.
Route
alignment
of
transmission
lines
Field Staff Maximum possible extent
and avoided
cities,
villages,
(AE
ADE)
houses, huts, buildings, fruit
bearing trees or any other
existing settlement directly
related with the livelihood of
people
Encroachment
on
Sites / Structures of
into Cultural, Historical
or
Archaeological
Importance
In the proposed project, preliminary selection of sites for
sub- stations and route alignment of transmission lines to
be ensured, no encroachment into cultural / religious
structures.
Route
alignment
of
transmission
lines
Field Staff
(AE
and
ADE)
Maximum possible extent
avoided
Cutting of trees and
damage to vegetation
Alignment of sub-stations and route of lines to be finalized
to avoid or minimize the cutting and removal of trees
Field Staff
(AE
and
ADE)
Pruning of branches of trees wherever possible
Alignment of
lines.
and
layout of substations
Route itself covers minimal
tree cutting are, trees are
allowed to grow up to 5.0 mtr
height.
Trees allowed growing up to a height within the ROW by
maintaining adequate clearance between the top of tree
and the conductor as per the regulations. Ensure record
keeping of trees in the area and trees to be felled.
Field Staff (AE
and ADE)
The
Route
of
the
Transmission line doesn’t
Encroach into precious
ecological areas
Field Staff (AE
and ADE)
The line doesn’t enter in to
forest area, bird guards
used.
Encroachment into precious
ecological areas
Afforestation plan
Avoid encroachment into National Park, Wildlife Sanctuaries, Location of subReserved Forest and other ecologically sensitive area by stations and line
alignment
careful site and alignment selection
Minimize the need by using existing towers, tall towers and
ROW, wherever possible Obtain statutory clearances from
the Government
Blockage of Wildlife Passage
Avoid Blockage of Wildlife Passage by careful site and
alignment selection and addition of deflectors need to
propose to minimize the avian collision risks with power
Lines.
Place bird guards on towers if in line of bird migratory paths
Location of line
alignment
Location of bird
guards on towers
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Impact on Aesthetic Value
Ensure the design of the system should not have any impact
on visual aesthetics.
Design of sub-stations Field Staff (AE
and alignment of lines and ADE)
Necessary steps taken
Loss of Property Value and
Livelihood
Finalize the alignment to minimize impact on livelihood to
neighboring communities. Compensation for loss of crops
and livelihood
Design of sub-stations Field Staff (AE
and alignment of lines and ADE)
Minimized the impact on
livelihood Compensation for
loss of crops and livelihood
arranged
Interference with other utilities Seek clearance prior to construction from National Highways
and traffic
authority wherever necessary
Clearances obtained
Plan and implement the mitigating measures for the induced
voltage Consultation with the public and implementation of
traffic management plan
Implementation of
traffic management
plan
Transformers designed with oil spill containment systems,
and purpose-built oil, lubricant and fuel storage system,
complete with spill cleanup equipment. The transformers
specifications will be selected as per internationally adopted
standards
Specifications of
equipment
Field Staff (AE
and ADE)
Prior clearances obtained
Design Impacts
Escape of polluting materials
EE
Transformers / capacitors should be free from
polychlorinated biphenyl (PCBs) Transformers / other
equipment should not contain any chemical causing GHG
emission.
Noise and vibration of
equipment
Sub-stations sited and designed to ensure noise will not be a Design document Bid
nuisance Equipment should comply with Indian and document
International standard Generators complying with MoEF
standard shall be purchased
EE
Explosion/fire hazards
Site selection for transmission lines and substations are
ensured away from oil/gas pipelines and other sites with
potential for creating explosions or fires.
EE
Design documents of
sub-stations
and
alignment of lines
Ensured away from oil & gas
pipelines
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Construction Phase
Impact on air quality
Spraying of water in construction sites and on exposed earth
surfaces and stock piles of sand and other construction
materials,
Construction site
Contractor
Water sprinklers
Tarpaulins used
used,
Ambient air quality
Covering of transportation vehicles with tarpaulins Training of monitoring
for
equipment operators and drivers in fuel efficiency and anti- suspended particulate
matter and respirable
idling can effectively reduce the air emissions.
suspended solid
Equipment and vehicles used at construction site shall
comply with the norms and standards prescribed by the
Environment (Protection) Act 1986.
Monitoring of ambient air at major construction sites
Impact due to underground Signposts along the way of underground cabling should be
cabling
well displayed
Alignment
of Contractor
underground cabling
Doesn’t arise as the line was
Over Head EHT Line
To reduce the EMF from underground cable, it can be
shielded with specific metal alloys.
Deep rooted trees to be avoided in the areas of underground
cabling network to avoid interference with duct banks.
Mowing with heavy-duty power equipment is used to control
growth of ground covers and prevent the establishment of
trees and shrubs in the right-of-way. Herbicides and mowing,
should be used to control fast-growing weedy species.
Impact due to blasting of rocks If spacing and weight are within acceptable ranges the
ground vibrations and noise can be controlled by controlling
delay interval and charge/delay.
The airborne dust suppression measure like water sprinklers
should be used to ensure that the airborne dust is within the
permissible limits. Use of excessive explosives should be
avoided and proper blast parameter to be selected to control
fly rocks.
Locals must be informed in advance to avoid blasting sites.
Construction site
Contractor
& Control Blasting adopted
local panchayat
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Silt run off from construction
activities
Develop and implement Construction Site Management Plan
to cover site preparation to minimize clearance to adjoining
vegetation and natural resources; protection of unstable soil
surface from high velocity runoff with interception drains and
stabilization; proper siting and protection of construction
materials; construction wastes disposal practice etc.
Implementation of
Construction Site
Management Plan
Contractor
All procedures Adopted
Erosion Hazards due to
Inadequate Provision for
Resurfacing of Exposed Area
Excavated materials need to be used for re-filling after
construction work is over and remaining materials will be
disposed as per the regulation.
Implementation of
Construction Site
Management Plan
Contractor
Excess
Earth
was
disposed as per the local
regulations
Nuisance to Neighboring
Community from Construction
Activities including Noise,
Health and Safety, Blockage
of Access Roads
The vehicles, plants machineries used for construction to
comply with the statutory norms.
Monitoring of sound Contractor
levels at construction
sit, Health and Safety,
Noisy construction works such as piling, concrete mixing, Blockage of Access
mechanical compaction, etc., will be carried out only during Roads
daytime (between 0600 hours to 2200 hours. All vehicles and
equipment used in construction shall be fitted with exhaust
silences.
No road access was
blocked to general public.
Sound levels monitored to
maintain in limits
During routine servicing operations, the effectiveness of
exhaust silencers shall be checked and if found to be
defective shall be replaced.
Monitoring of sound levels at construction sites Develop and
implement Construction Site Management Plan covering the
above
Impact from work in flood
prone areas
Precautions to avoid blocking of drainage path by construction
activities Avoid storing materials, chemicals and other items
of work in areas where those can be washed away by the
floods.
Stocking of materials
and
construction
activities
Contractor
blocking of drainage path
avoided
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Adopt water-saving construction practices and conduct
Impact on water environment training of construction workers to minimize the discharge
and ground water level
of wastewater. Ensure that pollution of natural
watercourses, ponds, tanks and reservoirs is avoided.
Prevent the Waste water produced in construction from
entering directly into streams, water bodies or the irrigation
systems.
NOC from Ground water board for borewell
Construction site
Contractor
Conducted
awareness
programs on water saving
and waste water disposal
and accordingly steps
taken
Implementation of
health and safety
measures
Contractor
Provided
to
all
workers
safety
goggles,
helmets,
masks, boots, etc,
arranged health and
safety
training
sessions
Oil and fuel spills from construction equipment will be
minimized by good O&M practices. Vehicles /machinery and
equipment serving and maintenance work shall be carried out
only in designated locations /service stations.
The cans and containers of oil and lubricants to be provided
with spill trays to contain the spills
Public and Workers Safety
during Construction Phase
Comply with requirements for the safety of the workmen as
per the existing national /state /local regulations.
Contractor to prepare and implement a health and safety
plan.
Supply all necessary safety appliances such as safety
goggles, helmets, masks, boots, etc., to the workers and
staff. Contractor to arrange for health and safety training
sessions
Comply with all regulations regarding safe scaffolding,
ladders, working platforms, gangway, stairwells, excavations,
trenches and safe movement of the workers and staff.
Adequate precautions will be taken to prevent danger of
electrocuting from electrical equipment and power supply
lines including distribution boards, transformers, etc.
Measures such as danger signboards, danger /red lights,
fencing and lights will be provided to protect the public and
workers. All electric power driven machines to be used in the
construction shall be free from defect, be properly maintained
and kept in good working order
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Disturbed Farming Activity
Construction activities on cropping land will be timed within
one month of harvest wherever possible.
Timing of start of
construction
Contractor
Construction
activities
minimized for one month
and crop compensation
paid
Clearing of trees and
vegetation
Contractor
Route
itself
covers
minimal tree cutting area,
trees are allowed to grow
up to 5.0 mtr height.
Necessary compensation
arranged to the concerned
.
Compensation for crop damage, if any
Impact on Flora and Fauna
Marking of vegetation to be removed prior to clearance
Strict control on clearing activities to ensure minimal
clearance.
Trees allowed growing up to a height within the ROW by
maintaining adequate clearance between the top of tree and
the conductor as per the regulations.
Disposal of cleared
vegetation
as
approved by the
statutory authorities
If cutting of trees is unavoidable, then obtain appropriate Compensatory
regulatory approvals Compensatory afforestation at the rate afforestation
of twice the trees cut/removed Felled trees and other cleared
or pruned vegetation to be disposed of as authorized by the
statutory bodies.
Avoid Blockage of Wildlife Passage by careful site and
alignment selection and addition of deflectors need to
propose to minimize the avian collision risks with power
Lines.
Operation and Maintenance (O&M) Phase
Oil Spillage during Operation
and Maintenance
Sub-station transformers to be located within secure and
impervious bunded areas with a storage capacity of at least
100% of the capacity of oil in transformers and associated
reserve tanks.
Oil traps will be provided to reclaim the oil from the storm
water drained from the bunded area.
Sub-station bunding
132 KV SS KOTHAPALLI ALONG WITH CONNECTED LINE FROM 132 KV SS NOONEGUNDLA PALLI IN CHITTOOR DISTRICT
Management of Solid Waste
Generated
Replaced equipment i.e. transformers, capacitors,
conductors, meters, batteries, transformer oil and other
electrical equipment to be collected and disposed of through
registered recycling/reprocessing units or handed over to
the manufacturers/dealers as per the provisions of the
Hazardous Waste (Management and Handling) Rules1989
and the Batteries (Management and Handling) Rules, 2001.
Disposal of wastes
Obtain statutory clearances for disposal of wastes
Staff/workers health and
safety during operations
Adequate precautions to prevent danger of electrocuting from Health and safety
electrical equipment and power supply lines including practices
distribution boards, transformers, etc. Measures such as
danger signboards, danger/red lights, fencing and lights will be
provided to protect the staff and workers
All workers employed in hazardous activities shall be provided
with necessary protective gear At every workplace, first aid kit
shall be readily available including an adequate supply of
sterilized dressing materials, medicines and appliances in
accordance with the regulations All workers and staff will be
given training/awareness programs on safety measures to be
followed during the operation and maintenance of the system.
Operations and maintenance
staff
skills
less
than
acceptable
Exposure to electromagnetic
interference
Adequate training in O&M to all relevant staff of sub-stations
Posting of Staff
and transmission line maintenance crews. O&M manuals and
standard operating practices (SOP) will be prepared Regular
training will be given to all relevant staff and maintenance No of training
crews to operate the system in accordance with the manuals conducted
and SOPs.
Transmission line design to comply with the limits of
electromagnetic interference from overhead power lines
Ground clearance