A STUDY OF THE EFFECTIVENESS OF THE MALAYSIAN
CONSTRUCTION INDUSTRY PAYMENT AND ADJUDICATION ACT
(CIPAA) VIS-À-VIS THE IMPACT OF OVERSEA CONSTRUCTION
PAYMENT LEGISLATIONS ON THEIR RESPECTIVE CONSTRUCTION
INDUSTRIES
CHEANG LI ZHE
A project report submitted in partial fulfilment of the
requirements for the award of Bachelor of Science
(Hons.) Quantity Surveying
Faculty of Engineering and Science
Universiti Tunku Abdul Rahman
Jan 2017
ii
DECLARATION
I hereby declare that this project report is based on my original work except for
citations and quotations which have been duly acknowledged. I also declare that it
has not been previously and concurrently submitted for any other degree or award at
UTAR or other institutions.
Signature
:
Name
: CHEANG LI ZHE
ID No.
: 1203599
Date
: 25.4.2017
iii
APPROVAL FOR SUBMISSION
I certify that this project report entitled “A STUDY OF THE EFFECTIVENESS
OF THE MALAYSIAN CIPA ACT VIS-À-VIS THE IMPACT OF OVERSEA
CONSTRUCTION PAYMENT LEGISLATIONS ON THEIR RESPECTIVE
CONSTRUCTION INDUSTRIES” was prepared by CHEANG LI ZHE has met
the required standard for submission in partial fulfilment of the requirements for the
award of Bachelor of Science (Hons.) Quantity Surveying at Universiti Tunku Abdul
Rahman.
Approved by,
Signature
:
Supervisor
: Sr. Chang Khong Thong
Date
: 25.4.2017
iv
The copyright of this report belongs to the author under the terms of the
copyright Act 1987 as qualified by Intellectual Property Policy of Universiti Tunku
Abdul Rahman. Due acknowledgement shall always be made of the use of any
material contained in, or derived from, this report.
© 2017, Cheang Li Zhe. All right reserved.
v
ACKNOWLEDGEMENTS
I would like to express my gratitude to my research supervisor, Sr. Chang Khong
Thong for his invaluable advice, guidance and his enormous patience throughout the
development of the research.
In addition, I would also like to express my gratitude to my loving parents
and friends who had helped and given me encouragement when facing with
difficulties in completing this study. Furthermore, the responses from the
respondents are much appreciated as this study would not be successful if it was not
for them.
vi
A STUDY OF THE EFFECTIVENESS OF THE MALAYSIAN
CONSTRUCTION INDUSTRY PAYMENT AND ADJUDICATION ACT
(CIPAA) VIS-À-VIS THE IMPACT OF OVERSEA CONSTRUCTION
PAYMENT LEGISLATIONS ON THEIR RESPECTIVE CONSTRUCTION
INDUSTRIES.
ABSTRACT
The problems of cash flow in the construction industry is a common phenomenon. It
happens anywhere and Malaysia is no exception. The main purpose of this research
is to study the effectiveness of Construction Industry Payment and Adjudication Act
(CIPAA) by investigating whether it has eased the problems of cash flow in the
construction industry. Since construction industry plays a pivotal role in national
economic, its problems need to be rectified as soon as possible. CIPAA is enacted as
a solution to this problem. However, whether CIPAA has served its purpose remains
a question. This study intends to look into this question. A questionnaire survey was
conducted to solicit the opinions or feedbacks from main contractors, consultant QS
and subcontractors. 35 respondents took part in the survey. This study found that
cash flow has become smoother since CIPAA was introduced. However, conditional
payment and problem of timeliness in paying remain. Also, most of the construction
industry players are satisfied with the duration of CIPAA. Furthermore, CIPAA is
considered as a relatively affordable and speedy dispute resolution mechanism when
compared to arbitration or litigation, given a rating of 4 out of 5, overall. Issues on
breach of natural justice and jurisdiction problems of adjudicators are found to be the
concern of the industry players. It is also learnt that the construction industry
stakeholders think that it is fair to have adjudication reply with no further ground for
respondent to response to that reply. The power to award adjudication cost given to
adjudicator is seen as a deterrent towards CIPAA, especially to small and medium-
vii
sized company. Extension of coverage of CIPAA to oral and “partly oral, partly
written” construction contracts and adjudication review are sought after.
viii
TABLE OF CONTENTS
DECLARATION
ii
APPROVAL FOR SUBMISSION
iii
ACKNOWLEDGEMENTS
v
ABSTRACT
vi
TABLE OF CONTENTS
viii
LIST OF TABLES
xiii
LIST OF FIGURES
xiv
LIST OF APPENDICES
xxi
CHAPTER
1
2
INTRODUCTION
22
1.1
Background
22
1.2
Problem Statement
23
1.3
Aims and Objectives
25
1.4
Research Scope
25
1.5
Research Justification
26
1.6
Research Methodology
26
1.7
Chapter Organisation
26
LITERATURE REVIEW
28
2.1
Payment Dilemma in Construction Industry
28
2.2
The Importance of Timely Payment and thus Cash Flow in
Construction Industry
29
2.3
30
Overview of CIPAA Implementation
ix
2.4
2.5
2.6
2.7
2.3.1
Registered Matters
30
2.3.2
Registered Matters by Months
31
2.3.3
Registered Matters by States
32
2.3.4
Claimant Statistics
33
2.3.5
Respondent Statistics
34
2.3.6
Types of Adjudication Disputes
35
2.3.7
Decisions Released
36
2.3.8
Claimed Amount
38
2.3.9
Government Related Adjudication Proceedings
40
2.3.10
Number of Adjudicator Empanelled by States
41
2.3.11
Referral of Disputes Decided Under CIPAA to
Arbitration or Court
42
2.3.12
42
General Court Stand and Court Case
Introduction to Adjudication in United Kingdom
43
2.4.1
Adjudication in UK
44
2.4.2
Adjudication Statistics
45
Introduction to Adjudication in Singapore
48
2.5.1
Adjudication in Singapore
50
2.5.2
Enforcement Mechanism
51
2.5.3
Adjudication Statistic
51
Introduction to Adjudication in Australia
55
2.6.1
Adjudication in New South Wales
55
2.6.2
New South Wales (Statistics)
56
2.6.3
Queensland (Statistics)
59
Main Features of CIPAA
61
2.7.1
Make Conditional Payment Void
61
2.7.2
Securing Direct Payment from Principal
61
2.7.3
Suspension or Reduce the Rate of Progress of the
Works 61
2.8
Shortcomings of CIPAA
62
2.8.1
Jurisdiction of the Adjudicator Is Not Made Clear 62
2.8.2
Does Not Address Whether the New Adjudication
Regime Could Apply to Contracts Entered into Before 15
April 2014
62
x
2.8.3
Intentional Delay by Uncooperative Defendant
2.8.4
Relatively
Long
Adjudication
Response
Relatively Short Adjudication Reply
3
and
63
METHODOLOGY
65
3.1
Research Strategy
65
3.1.1
Quantitative Research
65
3.1.2
Qualitative Research
65
3.2
4
63
Approaches to Data Collection
66
3.2.1
Fieldwork Research
66
3.2.2
Desk Study Research
66
3.3
Research Design
67
3.4
Data Analysis Method
68
3.4.1
Descriptive Statistics Method
68
3.4.2
Inferential Statistics Method
68
RESULTS AND DISCUSSION
4.1
69
The View of General Respondents and CIPAA Participants
Towards The Implementation of CIPAA
4.1.1
Percentage
of
CIPAA
69
Participants
to
All
Respondents
70
4.1.2
Cash Flow
71
4.1.3
Eradication of Conditional Payment
72
4.1.4
Adjudicator's Inquisitional Role
73
4.1.5
Reliable Dispute Resolution Mechanism
74
4.1.6
The Adjudicators Empanelled by KLRCA
75
4.1.7
Relatively Speedy Process Compared to Arbitration
or Litigation
4.1.8
76
Relatively Affordable Compared to Arbitration or
Litigation
77
4.1.9
Dispute Resolution of CIPAA
78
4.1.10
The
Duration
of
Initiation
of
Adjudication,
Appointment of Adjudicator and Adjudication Proceedings 79
xi
4.1.11
4.2
Relatively Long Period of CIPAA When Compared
with Other Similar Legislations
81
4.1.12
Preferred Remedy
82
4.1.13
Improvements Felt in Malaysia
85
4.1.14
Power to Award Adjudication Cost
88
4.1.15
Adjudication Reply
89
4.1.16
Reach of CIPAA
90
4.1.17
Issues
of
Breach
of
Natural
Justice
and
Adjudicator’s Jurisdiction Problem
91
4.1.18
Adjudication Review
92
4.1.19
Rating of CIPAA
93
The View of Main Contractors, QS Consultants and
Subcontractors Respectively Towards The Implementation of CIPAA
94
4.2.1
Percentage of Each Party Involved in CIPAA
94
4.2.2
Cash Flow
95
4.2.3
Eradication of Conditional Payment
97
4.2.4
Adjudicator's Inquisitional Role
99
4.2.5
Reliable Dispute Resolution Mechanism
101
4.2.6
The Adjudicators Empanelled by KLRCA
103
4.2.7
Relatively Speedy Process Compared to Arbitration
or Litigation
4.2.8
105
Relatively Affordable Compared to Arbitration or
Litigation
107
4.2.9
Dispute Resolution of CIPAA
109
4.2.10
The
Duration
of
Initiation
of
Adjudication,
Appointment of Adjudicator and Adjudication Proceedings
111
4.2.11
Relatively Long Period of CIPAA When Compared
with Other Similar Legislations
114
4.2.12
Preferred Remedy
116
4.2.13
Improvements Felt in Malaysia
122
4.2.14
Power to Award Adjudication Cost
128
4.2.15
Adjudication Reply
130
xii
5
4.2.16
Reach of CIPAA
4.2.17
Issues
of
Breach
132
of
Natural
Justice
and
Adjudicator’s Jurisdiction Problem
134
4.2.18
Adjudication Review
136
4.2.19
Rating of CIPAA
138
CONCLUSION AND RECOMMENDATIONS
140
5.1
Introduction
140
5.2
Findings
141
5.3
Research Limitations
142
5.4
Research Contribution to Malaysian Construction Industry
143
5.5
Recommendation for Further Research
144
REFERENCES
145
APPENDICES
151
xiii
LIST OF TABLES
TABLE
TITLE
PAGE
Table 2.3.1.1: Total Registered Matters (3years)
30
Table 2.3.5.1: Payment Response
34
Table 2.3.7.1: Decisions Released
36
Table 2.3.7.2: Decisions Released In Favour of Claimant or
Respondent
36
Table 2.3.9.1: Government Related Adjudication Proceedings
40
Table 2.3.10.1: Malaysian Adjudicators Empanelled by State
41
Table 2.3.11.1: Concurrent Referral of Decided Adjudication
Proceedings
42
Table 2.4.2.1: Adjudications by All Reporting Adjudicator
Nominating Bodies (ANB)
45
Table 2.4.2.2: Sources of Appointment of Adjudicators
47
Table
2.4.2.3: Comparison of Successful
Adjudication’s Decisions
Parties
in
47
Table 2.5.3.1: The Number of Applications for Adjudication
51
Table 2.5.3.2: Categories of Claimants against Respondents
52
Table 2.5.3.3: Disputed and Adjudicated Amounts
53
Table 2.5.3.4: Number of Review Applications
54
Table 2.5.3.5: Categories of Claimants against Respondents
54
xiv
LIST OF FIGURES
FIGURE
TITLE
PAGE
Figure 2.3.1.1: Registered Matters from 14.4.2014 to
15.4.2015 (Term Based)
30
Figure 2.3.2.1: Registered Matters from 15.4.2014 to
15.4.2016 (Month Based)
31
Figure 2.3.3.1: Registered Matters from 15.4.2014 to
15.4.2016 (State Based)
32
Figure 2.3.4.1: Claimant Statistics from 15.4.2014 to 15.4.2016
33
Figure 2.3.4.2: Claimant Statistics from 15.4.2014 to 15.4.2016
(Term Based)
33
Figure 2.3.5.1: Respondent Statistics from 15.4.2014 to
15.4.2016
34
Figure 2.3.6.1: Type of Adjudication Disputes
35
Figure 2.3.7.1: Decision Released In Favour of Claimant and
Respondent
37
Figure 2.3.8.1: Claimed Amount
38
Figure 2.3.8.2: Number of Disputes by Range of Claim
Amount
39
Figure 2.4.2.1: Growth Rate in Adjudication Referrals in
United Kingdom
46
Figure 2.6.2.1: Number of adjudication applications by
payment claim value range 2014/15
56
Figure 2.6.2.2: Total claimed and adjudicated amounts
2014/15
57
Figure 2.6.2.3: Claimant Type 2014/15
57
xv
Figure 2.6.2.4: Respondent Type 2014/15
58
Figure 2.6.3.1: Percentage of Claimant Type Year to Date
59
Figure 2.6.3.2: Percentage of Respondent Type Year to Date
59
Figure 2.6.3.3: Application Lodged by Region Year to Date
60
Figure 2.6.3.4: Percentage of Claimants Receiving Full Claim
Amount
60
Figure 4.1.1.1: Percentage of CIPAA Participants to All
Respondents
70
Figure 4.1.2.1: Cash flow
71
Figure 4.1.2.2: CIPAA Participants: Cash flow
71
Figure 4.1.3.1: Eradication of Conditional Payment
72
Figure
4.1.3.2: CIPAA Participant:
Conditional Payment
Eradication
of
72
Figure 4.1.4.1: Adjudicator's inquisitional role
Figure
4.1.4.2:
CIPAA
Participant:
inquisitional role
73
Adjudicator's
73
Figure 4.1.5.1: Reliable dispute resolution mechanism
Figure
4.1.5.2: CIPAA Participant:
resolution mechanism
Reliable
74
dispute
74
Figure 4.1.6.1: The adjudicators empanelled by KLRCA
Figure
4.1.6.2: CIPAA Participant:
empanelled by KLRCA
The
75
adjudicators
75
Figure 4.1.7.1: Relatively speedy process
76
Figure 4.1.7.2: CIPAA Participant: Relatively speedy process
76
Figure 4.1.8.1: Relatively affordable
77
Figure 4.1.8.2: CIPAA Participant: Relatively affordable
77
Figure 4.1.9.1: Dispute resolution of CIPAA
78
Figure 4.1.9.2: CIPAA Participant: Dispute resolution of
CIPAA
78
xvi
Figure 4.1.10.1: Duration of initiation of adjudication
79
Figure 4.1.10.2: Duration of appointment of adjudicator
80
Figure 4.1.10.3: Duration of adjudication proceedings
80
Figure 4.1.11.1: Relatively long period of CIPAA
81
Figure 4.1.11.2: CIPAA Participant: Relatively long period of
CIPAA
81
Figure 4.1.12.1: First choice among three remedies available
82
Figure 4.1.12.2: CIPAA Participant: First choice among three
remedies available
82
Figure 4.1.12.3: Second choice among three remedies
available
83
Figure 4.1.12.4: CIPAA Participant: Second choice among
three remedies available
83
Figure 4.1.12.5: Last choice among three remedies available
84
Figure 4.1.12.6: CIPAA Participant: Last choice among three
remedies available
84
Figure 4.1.13.1: Timeliness in paying
85
Figure 4.1.13.2: CIPAA Participant: Timeliness in paying
85
Figure 4.1.13.3: Certainty in obtaining payment
86
Figure 4.1.13.4: CIPAA Participant: Certainty in obtaining
payment
86
Figure 4.1.13.5: Improvement in willingness of main
contractors to seek amicable settlement with
sub-contractors
87
Figure
4.1.13.6: CIPAA Participant: Improvement in
willingness of main contractors to seek amicable
settlement with sub-contractors
87
Figure 4.1.14.1: Power to award adjudication cost
88
Figure 4.1.14.2: CIPAA Participant: Power to award
adjudication cost
88
Figure 4.1.15.1: Adjudication reply
89
xvii
Figure 4.1.15.2: CIPAA Participant: Adjudication reply
89
Figure 4.1.16.1: Reach of CIPAA
90
Figure 4.1.16.2: CIPAA Participant: Reach of CIPAA
90
Figure 4.1.17.1: Issues within CIPAA
91
Figure 4.1.17.2: CIPAA Participant: Issues within CIPAA
91
Figure 4.1.18.1: Adjudication Review
92
Figure 4.1.18.2: CIPAA Participant: Adjudication Review
92
Figure 4.1.19.1: Rating of CIPAA
93
Figure 4.1.19.2: CIPAA Participant: Rating of CIPAA
93
Figure 4.2.1.1: Percentage of each party involved in CIPAA
94
Figure 4.2.2.1: Main Contractor: Cash flow
95
Figure 4.2.2.2: QS Consultant: Cash flow
95
Figure 4.2.2.3: Subcontractor: Cash flow
96
Figure 4.2.3.1: Main Contractor: Eradication of conditional
payment
97
Figure 4.2.3.2: QS Consultant: Eradication of conditional
payment
97
Figure 4.2.3.3: Subcontractor: Eradication of conditional
payment
98
Figure 4.2.4.1: Main Contractor: Adjudicator's inquisitional
role
99
Figure 4.2.4.2: QS Consultant: Adjudicator's inquisitional
role
99
Figure 4.2.4.3: Subcontractor: Adjudicator's inquisitional
role
100
Figure 4.2.5.1: Main Contractor: Reliable dispute resolution
mechanism
101
Figure 4.2.5.2: QS Consultant: Reliable dispute resolution
mechanism
101
xviii
Figure 4.2.5.3: Subcontractor: Reliable dispute resolution
mechanism
Figure
4.2.6.1: Main Contractor:
empanelled by KLRCA
The
102
adjudicators
103
Figure 4.2.6.2: QS Consultant: The adjudicators empanelled
by KLRCA
103
Figure 4.2.6.3: Subcontractor: The adjudicators empanelled
by KLRCA
104
Figure 4.2.7.1: Main Contractor: Relatively speedy process
105
Figure 4.2.7.2: QS Consultant: Relatively speedy process
105
Figure 4.2.7.3: Subcontractor: Relatively speedy process
106
Figure 4.2.8.1: Main Contractor: Relatively affordable
107
Figure 4.2.8.2: QS Consultant: Relatively affordable
107
Figure 4.2.8.3: Subcontractor: Relatively affordable
108
Figure 4.2.9.1: Main Contractor: Dispute resolution of
CIPAA
109
Figure 4.2.9.2: QS Consultant: Dispute resolution of CIPAA
109
Figure 4.2.9.3: Subcontractor: Dispute resolution of CIPAA
110
Figure 4.2.10.1: Main Contractor: Duration of initiation of
adjudication
111
Figure 4.2.10.2: Main Contractor: Duration of appointment
of adjudicator
112
Figure 4.2.10.3: Main Contractor: Duration of adjudication
proceedings
112
Figure 4.2.10.4: Consultant QS: Duration of initiation of
adjudication, appointment of adjudicator and
adjudication proceedings
113
Figure 4.2.11.1: Main Contractor: Relatively long period of
CIPAA
114
Figure 4.2.11.2: Consultant QS: Relatively long period of
CIPAA
114
xix
Figure 4.2.11.3: Subcontractor: Relatively long period of
CIPAA
115
Figure 4.2.12.1: Main Contractor: First choice among three
remedies available
116
Figure 4.2.12.2: Consultant QS: First choice among three
remedies available
116
Figure 4.2.12.3: Subcontractor: First choice among three
remedies available
117
Figure 4.2.12.4: Main Contractor: Second choice among three
remedies available
118
Figure 4.2.12.5: Consultant QS: Second choice among three
remedies available
118
Figure 4.2.12.6: Subcontractor: Second choice among three
remedies available
119
Figure 4.2.12.7: Main Contractor: Third choice among three
remedies available
120
Figure 4.2.12.8: Consultant QS: Third choice among three
remedies available
120
Figure 4.2.12.9: Subcontractor: Third choice among three
remedies available
121
Figure 4.2.13.1: Main Contractor: Timeliness in paying
122
Figure 4.2.13.2: Consultant QS: Timeliness in paying
122
Figure 4.2.13.3: Subcontractor: Timeliness in paying
123
Figure 4.2.13.4: Main Contractor: Certainty in obtaining
payment
124
Figure 4.2.13.5: Consultant QS: Certainty in obtaining
payment
124
Figure 4.2.13.6: Subcontractor: Certainty in obtaining
payment
125
Figure 4.2.13.7: Main Contractor: Willingness of main
contractors to seek amicable settlement with
sub-contractors
126
xx
Figure 4.2.13.8: Consultant QS: Willingness of main
contractors to seek amicable settlement with
sub-contractors
Figure
Figure
126
4.2.13.9: Subcontractor: Willingness of main
contractors to seek amicable settlement with
sub-contractors
127
4.2.14.1: Main Contractor:
adjudication cost
128
Power
to
award
Figure 4.2.14.2: Consultant QS: Power to award adjudication
cost
128
Figure 4.2.14.3: Subcontractor: Power to award adjudication
cost
129
Figure 4.2.15.1: Main Contractor: Adjudication reply
130
Figure 4.2.15.2: Consultant QS: Adjudication reply
130
Figure 4.2.15.3: Subcontractor: Adjudication reply
131
Figure 4.2.16.1: Main Contractor: Reach of CIPAA
132
Figure 4.2.16.2: QS Consultant: Reach of CIPAA
132
Figure 4.2.16.3: Subcontractor: Reach of CIPAA
133
Figure 4.2.17.1: Main Contractor: Issues within CIPAA
134
Figure 4.2.17.2: Consultant QS: Issues within CIPAA
134
Figure 4.2.17.3: Subcontractor: Issues within CIPAA
135
Figure 4.2.18.1: Main Contractor: Adjudication review
136
Figure 4.2.18.2: Consultant QS: Adjudication review
136
Figure 4.2.18.3: Subcontractor: Adjudication review
137
Figure 4.2.19.1: Main Contractor: Rating of CIPAA
138
Figure 4.2.19.2: Consultant QS: Rating of CIPAA
138
Figure 4.2.19.3: Subcontractor: Rating of CIPAA
139
xxi
LIST OF APPENDICES
APPENDIX
APPENDIX A: Questionnaire
TITLE
PAGE
151
22
CHAPTER 1
1 INTRODUCTION
1.1
Background
During the late 1980s, in United Kingdom, the volume of construction work has been
cut down significantly. As the volume of work plummeted, there was an increase in
competition, resulting in longer payment period and underpayment in subcontracting
sector. Sir Michael Latham was then asked to address this issue. He came out with a
report known as the Latham Report, suggesting the adoption of adjudication within
context of contract. His recommendation was adopted and statutory adjudication was
enacted as a fast-track mean to resolve all payment disputes arising under
construction contract.
According to Glasgow Caledonian University Adjudication Reporting Centre
(2012), from nil in early 2002, nominations of adjudicators have grown to over 2,000
per year. Besides, since the advent of adjudication, the Technology and Construction
Court experiences a trimming in the volume of its work and the number of
arbitrations has also been reduced to almost nil. Until April 2012, there are 20,878
cases of adjudication reported (ARC, 2012). It was a huge success. Viewing its
successful implementation, various countries then follow suit. Among them are
Australia (in the states of New South Wales, Southern Australia, Queensland,
Victoria, Tasmania, Western Australia, Northern Territory, and Australia Capital
Territory), New Zealand, Singapore, Malaysia and Ireland.
23
In conjunction with the 10th Malaysia Plan, The Construction Industry
Payment and Adjudication Act 2012 was gazetted on 22 June 2012 and enforced on
15 April 2014. Its main objectives are to facilitate payments so that they are regular
and timely, provide adjudication for rapid dispute resolution and provide solution for
payment recovery.
This Act is enforceable on every written contract related to construction work
taken place in Malaysia, wholly or partly. It includes government construction
contract. However, this Act is not enforceable on contract involved by a lay person
for constructing building which is not more than three storeys high and solely meant
for his occupation (Gould, n.d.). Clause 40 would be the only possible way out. It
enables Minister for Works to exempt anyone and any works which is considered
necessary.
1.2
Problem Statement
In 2014, while Malaysian national gross domestic product (GDP) was at 6%,
construction industry grew at a promising and encouraging 11.8%, indicating that the
construction sector is one of the main contributing factors to national GDP (CIDB,
2015). This is further supported by Raza Ali, Mohd Shahir, Zulkipli (2014) who
found that there is a strong positive correlation between construction sector and
national economic growth. Hence, to maximise national growth, due attention should
be given to this contributing sector. Any problems encountered should be addressed
as soon as possible and as best as possible.
Payment and cashflow problems has plagued construction industry for some
times (Azman, et al., 2014). Cashflow is often referred to as lifeblood in construction
industry. According to Karib, Shaffii and Nor (2008), the ease of cash flow is a must
in delivering a successful project. “Regular financial injection is essential to make
sure the contractor is able to proceed work diligently” statement further stresses the
importance of cashflow in construction industry (Hasmori, Ismail and Said, 2012;
Judi and Mohamd Sabli, 2010). Noushad Ali Naseem Ameer Ali (2006) contends
24
that consistent timely payment is very crucial as programmed cash flow is
complimentary to a business, especially to construction industry. In addition, a
timely payment is said to be very important since a longer payment period, has to be
planned and factored in in the very beginning. Otherwise, it would have a ripple
effect on other activities.
Notwithstanding its significance, studies done by Hasmori et al. (2012) and
Ye and Abdul Rahman (2010) found that clients delayed payments, delayed in
returning retention monies and wilful withholding of the payment to contractor for
their own financial advantages. Judi and Rashid (2010) are of the opinion that project
delay, minimized profitability and even liquidation of companies could be due to
irregular and untimely payment. It was proved right when more than 16,000 class F
contractors faced bankruptcy issues pertaining to late or non-payments from their
umbrella contractors in 2005 (Suhaini, 2005).
Construction Industry Payment and Adjudication Act (CIPAA) was enacted
to address this payment issue. To date, CIPAA has been in operation for almost 3
years. Now, the questions are “Has CIPAA addressed cashflow problem as it was
intended to? “. Is it effective and efficient enough? If it is not, is there a mean to
improve it further? If yes, how so? Another interesting question to look into will be
“How has CIPAA performed in comparison to other similar legislations in other
countries?”
Considering the pivotal role the construction industry plays in economic
growth of Malaysia, these questions have to be answered. This study will look into
these questions and answers them accordingly.
25
1.3
Research Question
1. Has CIPAA addressed cashflow problem as it was intended to?
2. What construction industry stakeholders think of the effectiveness and
efficiency of CIPAA?
3. What are the improvements on CIPAA that the construction industry
stakeholders are seeking?
4. How has CIPAA performed compared to similar payment legislations?
1.4
Aims and Objectives
The objectives of this study are
1. To investigate whether CIPAA has addressed the cashflow problems in the
construction industry as it was intended to.
2. To get to know how the construction industry stakeholders think of the
effectiveness and efficiency of CIPAA.
3. To get the insight of how CIPAA could be further improved.
4. To compare the effectiveness of similar payment legislations.
1.5
Research Scope
The respondents will be construction industry stakeholders that are currently working
in Malaysia. 35 questionnaires will be given out. Among them, 15 will be given to
main contractors and QS consultant firms respectively. Another 5 will be given to
subcontractors.
26
1.6
Research Justification
Through this study, the performance of CIPAA in addressing cashflow problems in
construction industry in Malaysia could be determined. Moreover, the valuable
insights of how CIPAA could be further ameliorated from these “insiders” could be
obtained. Furthermore, how CIPAA stands in compared to similar payment
legislations in other countries could be ascertained. Since construction industry has a
considerable economic multiplier effect, these questions could not afford to go
unanswered.
1.7
Research Methodology
This research will be conducted by using quantitative method. 35 questionnaires
were received. The respondents will be main contractors, subcontractors and
consultant QS that are currently working in Malaysia. More importantly, these
respondents will be randomly selected for the purpose of this research.
1.8
Chapter Organisation
This study comprises five chapters which are introduction, literature review, research
methodology, result and discussion as well as conclusion. They are further described
as follow:
• Chapter 1 – Introduction. This chapter comprises study background,
problem statement, aim and objectives, research scope, research justification,
research methodology and chapter organisation.
• Chapter 2 – Literature Review. This chapter is based on content from others
works. It reviews the payment dilemma, the importance of timely payment and thus
27
cashflow in construction industry, current status of CIPAA and similar legislations in
other countries.
• Chapter 3 – Research Methodology. This chapter presents on the research
method, data collection method, questionnaire design and data analysis. Basically, it
tells how this research will be conducted.
• Chapter 4 – Results and Discussions. The findings from questionnaires are
tabulated and analysed.
• Chapter 5 – Conclusion. This chapter will conclude the findings. Other than
that, recommendations will be given.
28
CHAPTER 2
2 LITERATURE REVIEW
2.1
Payment Dilemma in Construction Industry
Payment and cashflow issues are aged affair that infiltrate construction industry in
Malaysia. (Azman, et al., 2014). It has a potential to create negative chain effect on
other parties. A delayed payment by a party could affect the entire payment supply
chain. For example, a late payment from an employer will cause sub-contractors and
suppliers to receive late payment from the main contractor (Mohamad et al., 2012).
Worst comes to worst, late payment could affect financial performance of a
contractor, leading to bankruptcy (Ab. Halim, et al., 2010). To add insult to injury,
this issue does not just extend to construction industry stakeholders. It affects the
third party purchasers as well. And, this will be the nightmare not just for the
purchasers but also the government (Tan, 2011).
Some of the main factors are namely, late certification, client's poor financial
management, bad culture, underpayment by the client and 'pay when paid' clauses in
contracts (Che Munaaim, Mohd Danuri and Abdul-Rahman, 2012). Among them is
conditional payment clause. This type of clause is outlawed by Section 13(1) of the
NZ Construction Contracts Act 2002. So does all the similar legislations in other
countries including Malaysia. The negative implication of such clauses is that subcontractors may finish up not being paid although they do their part and are not in
breach of contract (Ameer Ali, 2006). Besides that, Cannon and Gibson (2014) are of
the opinion that such clauses has been the primary cause to the insolvency of the
supply chain, causing the parties further down the chain to be out of business.
29
2.2
The Importance of Timely Payment and thus Cash Flow in
Construction Industry
“Cashflow is the life blood of the building industry”. Lord Denning makes this
statement starting with Dawnays vs Minter (1971) and finishing with Modern
Engineering vs Gilbert Ash (1973). This statement clearly indicates how significant
cashflow and on-time payment are towards the construction industry. For most
contractors, payment certificate could be their one and only source of income while
they are funding the whole of the building operation, including paying for wages of
workers, materials and subcontractors, which will turn out to be a considerable sum.
Therefore, full and timely payment is very important as they depend on it to run their
business effectively (Walker and Wilkie, 2002). Seeing its importance, frictions are
likely to arise resulting from untimely and underpayment, stirring working
relationship on site and causing unnecessary strain. This is counterproductive since it
wastes money, directly or indirectly, and may require to refer the disputes to
arbitration or the court. Hence, proper cashflow distribution throughout the supply
chain is not just a desirable attribute but a must for the proper operation of contracts
(Cunningham, 2013).
30
2.3
Overview of CIPAA Implementation
2.3.1
Registered Matters
Figure 2.3.1.1: Registered Matters from 14.4.2014 to 15.4.2015 (Term Based)
Table 2.3.1.1: Total Registered Matters (3years)
The sudden spike in the number of cases can be attributed to the success of
the CIPAA legislation, efficient administrative mechanism, support from the
judiciary and overall awareness among the industry players. It is anticipated that a
total of over 350 matters will be registered with the KLRCA in 2016 (KLRCA, 2016).
31
2.3.2
Registered Matters by Months
Figure 2.3.2.1: Registered Matters from 15.4.2014 to 15.4.2016 (Month Based)
One thing is obvious, the average number of cases on a monthly basis is on
the rise. There is a growth of 150% when compared to 2014-2015 statistics,
reflecting the success of the reach of adjudication among construction industry
players. It is also a sign of the faith reposed in CIPAA and a testament to its success
(KLRCA, 2016).
32
2.3.3
Registered Matters by States
Figure 2.3.3.1: Registered Matters from 15.4.2014 to 15.4.2016 (State Based)
The bar chart above shows a spread of CIPAA over different states. It is a
positive trend which indicates the reach of awareness of CIPAA in different states.
Most of all, the statistic is promising and is indicative of the expanding reach of
CIPAA (KLRCA, 2016).
33
2.3.4
Claimant Statistics
Figure 2.3.4.1: Claimant Statistics from 15.4.2014 to 15.4.2016
Figure 2.3.4.2: Claimant Statistics from 15.4.2014 to 15.4.2016 (Term Based)
Sub-contractor and main contractor continue to be the main claimant under
CIPAA. Nevertheless, there is a marginal rise of consultants as claimant at 7.9%
compared to previous year of 6%. It is anticipated that this trend will continue
(KLRCA, 2016).
34
2.3.5
Respondent Statistics
Figure 2.3.5.1: Respondent Statistics from 15.4.2014 to 15.4.2016
Table 2.3.5.1: Payment Response
According to KLRCA (2016), main contractors and employers are the
majority of respondents. There is an increase of payment respondent filed by the
respondents from 23.8% to 35.7, showing gradual active participation in the
proceedings. Observations of the Court in relation to Section 6 of CIPAA in the case
of View Esteem Sdn Bhd v Bina Puri Holdings Sdn Bhd could be one of the factors.
Even though in obiter, the Court indicated that if the respondents did not file its
payment response, he is not entitled to raise set off or counterclaims. The trend of
increase is expected to continue.
35
2.3.6
Types of Adjudication Disputes
Figure 2.3.6.1: Type of Adjudication Disputes
According to KLRCA (2016), interim payment and final account are the most
commonly referred disputes under CIPAA, making up for the majority of disputes at
52.9% and 21.65% respectively. Interim payment disputes experience a profound
increase. A surge in cases for interim payment and final account shows the effective
use of CIPAA by sub-contractors and contractors in resolving cash flow disputes
before completion of the works.
36
2.3.7
Decisions Released
Table 2.3.7.1: Decisions Released
According to KLRCA (2016), out of 138 adjudication decisions rendered, 70
have been in favour of the claimant and full claim has been granted, while 55
decisions have had partial claims being granted. Only 13 cases have been dismissed
so far. Some of the grounds to dismiss the claims were procedural non-compliance
such as invalid payment claim or notice of adjudication and the matters falling
outside the ambit of CIPAA. The cases involving dismissal of claims are not
alarming in number and are seen to be in compliance with the provisions of CIPAA.
Table 2.3.7.2: Decisions Released In Favour of Claimant or Respondent
37
Figure 2.3.7.1: Decision Released In Favour of Claimant and Respondent
The trend of a majority of decisions rendered are in favour of claimant
continues. Nonetheless, the figure of 97% in 2014-2015 has dropped to 86% in 20152016. Case dismissals because of procedural non-compliance is one of the causes
resulting in the decrease (KLRCA, 2016).
38
2.3.8
Claimed Amount
Figure 2.3.8.1: Claimed Amount
The significant difference of claimed amount shows the wide reach and
extent of the application of CIPAA. The considerable increase of highest claim
amount is indicative of a rise in trend of high value adjudication disputes being
referred. A total claimed amount of around RM1, 400,000,000.00 is indicative of the
growing popularity and success of CIPAA. It is anticipated that more and more
parties will resort to CIPAA, regardless of the claim amount (KLRCA, 2016).
39
Figure 2.3.8.2: Number of Disputes by Range of Claim Amount
It is observed that a majority of the cases were filed with payment claims
either up to RM150, 000 or between the range of RM300, 000 and RM800, 000. The
trend is anticipated to continue with an increase in cases filed with other payment
ranges as well (KLRCA, 2016).
40
2.3.9
Government Related Adjudication Proceedings
Table 2.3.9.1: Government Related Adjudication Proceedings
According to KLRCA (2016), the presence of these figures is an encouraging
sign of growth of CIPAA in Malaysia, establishing its expansion both in public and
private sectors.
41
2.3.10
Number of Adjudicator Empanelled by States
Table 2.3.10.1: Malaysian Adjudicators Empanelled by State
As reflected in Table 6, Kuala Lumpur WP and Selangor have the highest
concentration of empanelled adjudicators. This trend remains the same as last year
indicating the stronghold on CIPAA of the industrialized capital city (KLRCA, 2016).
42
2.3.11
Referral of Disputes Decided Under CIPAA to Arbitration or Court
Table 2.3.11.1: Concurrent Referral of Decided Adjudication Proceedings
It indicates the binding-but-not-final nature of adjudication and the awareness
among parties of further redressals available to them. The successful party will still
proceed to enforce the decision as provided for under Part IV of the act anyway,
irrespective of whether the another party refers the matter to arbitration or litigation
or not.
2.3.12
General Court Stand and Court Case
As experience has shown in the UK, the successful applications to set aside
adjudicator’s decision will be few and the court will favour the enforcement of
awards.
In Mudajaya Corporation Berhad v Leighton Contractors (Malaysia) Sdn
Bhd (2015) 10 MLJ 745, there is an argument on the application of the exemptions
afforded to Government Contracts under the CIPAA (Exemption) Order 2014.
Mudajaya argued that the sub-contract with Leighton necessarily fell within the First
Schedule of the Exemption Order although it was being constructed by private
parties, the power plant in question was actually in control and regulation of the
Government. However, the High Court reasoned that subparagraph 2(1) of the
Exemption Order clearly exempted a construction contract that is a “Government
construction contract”. It decided in favour of Leighton stating that keeping with the
language of the provision, the Government must necessarily be a party to the
43
construction contract in question. All other contracts do not fall within the
Exemption Order.
In Econpile (M) Sdn Bhd and IRDK Ventures Sdn Bhd, the issue is on the
effect of Section 19(5) of CIPAA – whether an adjudication decision delivered
within time but released to the parties only after the payment of outstanding GST
was made for the KLRCA’s Administrative Fee is void. Judge YA Tuan Lee Swee
Seng held that the adjudication decision was validly made, delivered and released to
the parties, based on the rationale that the release of the adjudication decision to the
parties soon after confirmation that the GST of the adjudication authority, the
KLRCA, had been paid was consistent and in compliance with the KLRCA Standard
Terms of Appointment of the Adjudicator as provided for under Schedule II of the
KLRCA Adjudication Rules and Procedure which are contractually agreed by the
parties when receiving the Adjudicator’s Notice of Acceptance of Appointment
(Form 6).
2.4
Introduction to Adjudication in United Kingdom
Statutory adjudication is introduced with the enactment of Housing Grants,
Construction and Regeneration Act of 1996. It came into force on first of May 1998.
It is born to solve payment issues that have plagued the UK construction industry for
a long time, causing countless contractors, big or small, to become insolvent.
The early application of adjudication is faced with the question of
enforcement and followed by procedural clarifications and finally jurisdictional
challenges (Gould and Linneman, 2008). In Epping Electrical 2007 and Aveat
Heating 2007, His Honor Judge Havery QC confirmed that adjudication decisions
given outside the 28-day time frame is invalid. However, in Cubitt Building &
Interiors v. Fleetglade 2006, it was decided that a decision reached within the agreed
period but not delivered in time is valid, given that it could be shown that the
decision was communicated forthwith.
44
With adjudication proceeding available, Technology and Construction Court
experienced a considerable drop in its workload. Besides, construction disputes, even
complex ones, can be dealt with in a much shorter time frame.
According to Milligan, Cattanach and Jackson (2015), parties and their
representatives are increasingly aggressive and bullish towards adjudication as the
parties have grown accustomed to the practice. Their aim is pretty straightforward; to
influence the adjudicators’ decisions. This is alarming as it could have affected the
impartially and independence of the adjudicators (Bingham, 2002). Conducting
training for adjudicators is one of the remedies provided in this report so that
adjudicators manage to remain in control in the face of intimidation or discourtesy.
Another solution is that all appointing bodies in each respective jurisdiction work
jointly in order to formulate a uniform code of conduct to be issued to both parties
upon appointment of an adjudicator (Milligan, Cattanach and Jackson, 2015).
2.4.1
Adjudication in UK
After the crystallisation of a dispute, claimant may serve a notice of its intention to
refer the dispute to adjudication to the defendant. That notice must identify the
dispute and has the remedy sought after set out. The claimant is required to serve his
or her statement of case, in other words, ‘Referral’ to the defendant within 7 days of
the issuance of notice. If referral, which consists of detailed explanation of the
dispute and its supporting documents, is not served within that specified period, the
adjudication will be void.
Appointment of an adjudicator also has to be done within that 7 days of the
issuance of notice. It can either be an adjudicator agreed and named in the contract or
randomly chosen by a nominating body. A small fee will usually be charged for the
service. After the appointment of an adjudicator, a timetable will be set out by the
adjudicator to facilitate issuance of response to the Referral, reply to that response
and finally rejoinder to that reply.
45
Nonetheless, the adjudicator may only allow one submission by each party.
Without the adjudicator’s permission, any submissions will be ‘unsolicited’. Those
submissions cannot be ignored, though. Different weightage will be given to them
depending on when they are issued within the established timetable.
Within 28 days of Referral, the decision has to be made. However, if both
parties agree, it can be extended to 42 days. Like other similar legislations, it is
binding but not final. It can be toppled through arbitration or litigation.
2.4.2
Adjudication Statistics
Table 2.4.2.1: Adjudications by All Reporting Adjudicator Nominating Bodies
(ANB)
46
The adjudication referral has stayed at around 1500 cases starting from year 7 and
was expected to stay around that. However, because of the economic recession, the
number of referral dropped. In year 18, it returned to that level again, reflecting
economic recovery and a positive sign of stability in the construction industry (CDR,
2016).
Figure 2.4.2.1: Growth Rate in Adjudication Referrals in United Kingdom
Kennedy (2008) found that the appointments of adjudicator away from ANBs
to direct appointment between years 5 to 8 could be due to the fees to be paid to
ANBs for making nominations and the desire to have control over the quality of the
adjudicator. A fee of around £150 to £500 will be charged to the parties for
nominating the adjudicator if they refer to ANBs for appointment. Other than that,
both parties could be concerned over the quality of the adjudicator and thus the
quality of the decisions. Therefore, some parties specify a certain professional
background and qualification the adjudicator must have, for example, postgraduate
qualification in law, to the ANBs before the appointment. Some even appoint the
adjudicators directly, knowing their professional background and qualities well.
47
Table 2.4.2.2: Sources of Appointment of Adjudicators
Obviously, appointment through an ANB is the major source of appointment.
It remained at 90.7% at year 14 and increased to 96% in the following year. In year
16, it dropped to 93.5%. The other mean are through agreement of the parties and
named in the contract. Appointment through agreement of the parties accounts for
2.9% in year 15 and increased to 4.2% in the following year, while appointment of
an adjudicator through named in the contract accounts for 1.1% in year 15 and
increased to 2.3% in year 16.
Payment remains the most referred disputes until year 16, falling to close
second, behind final account disputes. At the same time, the variety of nature of
disputes referred hikes (CDR, 2014).
Consistent with the previous years, the sub-contractor against main contractor
disputes remains the majority of disputes referred, followed by main contractor
against employer and then by sub-sub-contractor against sub-contractor (CDR, 2014).
Table 2.4.2.3: Comparison of Successful Parties in Adjudication’s Decisions
48
According to CDR (2014), claimant remains the most-likely-to-succeed party
although its successful rate has been falling. Respondent successful rate has
decreased from 17% in year 13 to 13% in year 16 as well. Split decision, however,
has been on the rise.
Dancaster (2008) found that not much cases are taken further after
adjudication decisions. Nevertheless, the number of adjudicators’ decisions being put
aside has elevated. The factors that are causing this are breach of natural justice and
adjudicator’s jurisdiction issues. Walls (2004) opines that natural justice is way more
difficult to deal with than a challenge to an adjudicator’s jurisdiction. It is suggested
that adjudicators should be adapted to be more proficient in their understanding of
law (Kennedy, 2008).
One of the grounds to set aside the adjudicators’ decisions is he or she
answers the wrong question. Another ground relates to the time when adjudication is
commenced. Adjudication can only commence if a dispute has “crystallized”. If
there is none, there can be no adjudication and any decision made will be treated as
void.
2.5
Introduction to Adjudication in Singapore
The Building and Construction Industry Security of Payment (SOP) Act 2004
introduces adjudication into Singapore. The Singapore regime is the seventh of its
kind around the world, taking after the precedent regimes in the United Kingdom,
Australia (in the states of New South Wales, Queensland, Victoria, and Western
Australia) and New Zealand. The objectives of the Act are to make sure that the
party is entitled to payment for works carried out or goods or services provided;
rights of the party to suspend work or suspend supply of materials in the event of
default payment, outlawing conditional payment in the contract and nullify any
provisions of contract contrary to the Act (Lim, Leong, & Ng, 2010). The Act
provides a framework for statutory adjudication and preserved the right of the
contractual parties to refer any dispute arising from the contract to adjudication at
49
any time (Cheng, 2005). The adjudication arrangement in Singapore is closest to the
regime in New South Wales (Teo, 2008), which focused on payment disputes,
whereas the adjudication regime in UK focused on disputes on a much wider scope
(Chan, 2006).
One of the outstanding features includes the shortest timeframe the world has
ever seen, that is, 14 days from the commencement of adjudication. It is to live up to
the objective of speeding up payment and facilitating cashflow (Teo, 2008). Another
interesting feature is that it allows the aggrieved party to seek a review of the
adjudication decision by a new adjudicator or a panel of adjudicators. Other than that,
‘dispute settlement period’ is introduced to enable early exchange of information
between the parties that may enhance the prospect of settlement. In addition, the
claimant must serve a ‘notice of intention’ to respondent in order to apply for
adjudication. Similar to UK and New South Wales, there is an ‘authorized
nominating body’.
Since it came into effect on 1 April 2005, myriads of improvement has taken
place. One of them is timeliness of the main contractors in making payment. Besides,
since then, there is more certainty in receiving payment which is due. Main
contractors too have become more willing to settle payment with the subcontractors
amicably. Consequently, subcontractors are more willing to enter into contract with
main contractors who have not been dealt with before as they have more confidence
with the act coming into force. The subcontractors are also becoming more
professional in preparing their payment claims (BCA, 2006).
According to Langdon and Seah (2013), there is a shift towards when
adjudication applications are filed. Adjudication applications are often filed just prior
to the commencement of a long holiday when offices, both adjudicator and
respondent, are closed and staff involved are away. It will surely be a disadvantage to
the respondent. It is suggested that changes to the provisions of the Act to be made to
account for circumstances like this. Another limitation of the Act is that if the
claimant becomes insolvent while review on the adjudication determination is carried
out, the adjudicated amount paid may not be reimbursable as Sec.18(3) necessitates
50
the adjudicated amount to be paid to the claimant prior to the commencement of a
review (Chan, 2006).
2.5.1
Adjudication in Singapore
Anyone who has any written contract and has executed construction work in
Singapore or supplied goods or services relating to such construction work is eligible
to make a ‘payment claim’. Nevertheless, some established formalities have to be
followed. Anyone receiving a ‘payment claim’ is required to write a ’payment
response’ within the prescribed period. The respondent may agree to pay the claimed
amount or to pay partially or not to pay at all. However, if the respondent is not
paying the full amount, reasons for doing so have to be given in the payment
response. Anything not set out in the payment response cannot be raised during
adjudication. Like payment claim, some established formalities have to be complied
with. Dispute settlement period, which is the period of 7 days after the date when the
payment response is due to be provided, is where the parties could seek clarification
from one another regarding the issue. In the meantime, amendment of payment
response could take place. Respondent could even submit one if none has been
provided before. If no settlement is reached during that conflict-resolving period,
claimant may take it to adjudication.
‘Notice of intention’ to refer to adjudication must be served by the claimant
before adjudication can take place. Then, lodging of adjudication application with the
one and only ‘authorized nominating body’, namely, Singapore Mediation Center
(SMC), could take place. After receiving adjudication application from SMC,
adjudication response must be lodged by the respondent within 7 days. Then the
adjudicator comes in picture. The adjudicator is required to make an adjudication
determination within (a) 14 days from the initiation of adjudication (b) 7days in the
case of no payment response has been submitted.
The adjudication determination is binding but it is not final. If one is not
happy with that decision, he or she could seek a review from a different adjudicator
51
or a panel of adjudicators, provided that the application for review is lodged within 7
days after adjudication determination has been served and the adjudicated amount
exceeds the amount set out in the payment response by a prescribed amount. Prior to
applying for review, full adjudicated amount is required to be paid so as to ensure its
objective of facilitating cashflow is not compromised. Other alternative ways will be
through arbitration or litigation.
2.5.2
Enforcement Mechanism
Respondent has to pay the adjudicated amount within 7 days after adjudication
determination is served. Else, claimant may suspend the execution of construction
works or the supply of goods or services. In the event where claimant is a supplier of
goods, he or she may exercise a lien on any unpaid yet supplied unfixed goods.
Lastly, claimant may enforce the adjudication determination as a judgement debt
through court.
2.5.3
Adjudication Statistic
Table 2.5.3.1: The Number of Applications for Adjudication
52
According to Building and Construction Authority (2013), there were 999
cases of adjudication from its inception to the date of reporting. Out of 999, 531
applications have been determined. Among them, 519 have been in favour of the
claimant and only a small fraction, that is, 12 have been decided otherwise. In other
words, the successful rate for claimant is 97.7%, and that of respondent is only 2.3%.
Table 2.5.3.2: Categories of Claimants against Respondents
Like UK, cases of sub-contractor claiming against main contractor were the
majority of the disputes referred, followed by main contractor v developer and
subsequently by sub-subcontractor claiming against subcontractor. Out of 531
applications, the cases of subcontractor claiming against main contractor were 342,
amounting to 64.4%. Whereas, the cases for main contractor v developer was 85,
tantamount to 16%. The number of cases for sub-subcontractor was 75, equivalent to
14.1%. It was followed by consultant v developer and supplier v developer,
amounting to 4.5% and 0.9% respectively (BCA, 2013).
53
Table 2.5.3.3: Disputed and Adjudicated Amounts
Till 2013, the total disputed amounts have reached $909,999,862.23. The
maximum disputed amount for a case is $116,251,933.51, while the minimum is
$4900. The total adjudicated amount stands at $391,810,475.27. The maximum
adjudicated amount is $30,071,968.64, whereas the minimum is $0 (BCA, 2013).
According to Building and Construction Authority (2013), 302 cases,
tantamount to 56.9%, have 90 to 100% of claimed amount as adjudicated amount. In
other words, more than half of the adjudicated amount is of the similar value as
claimed amount. Only 22.4% of adjudicated amount is less than half of the claimed
amount.
54
Table 2.5.3.4: Number of Review Applications
Table 2.5.3.5: Categories of Claimants against Respondents
Out of 17 review applications, 10 was determined in favour of respondent and
7 in favour of claimant, tantamount to 58.8% and 41.2% respectively. In plain
English, respondents have a higher successful rate in review application. In terms of
review application, sub-contractor claiming against main contractor still remains the
majority of the cases (61.5%), just like adjudication application. Whereas, main
contractor v developer cases account for 23.1%. Sub-subcontractor v subcontractor
and consultant v developer cases account for 7.7% each.
55
2.6
Introduction to Adjudication in Australia
2.6.1
Adjudication in New South Wales
Adjudication in New South Wales (NSW) under Building and Construction Industry
Security of Payment Act 1999 is the fourth regime of its kind, following United
Kingdom, Scotland and Northern Ireland. It came into effect on 26 March 2000. Its
aim, like other similar legislations, is to facilitate cashflow in construction industry,
particular in NSW. It is applicable to construction contracts in NSW, where a party
undertakes to execute ‘construction work’ or to supply ‘related goods and services’
for the other party.
The mechanism begins with the claimant making payment claim against the
respondent. The latter may provide a ‘payment schedule’ within 10 business days of
the issuance of the payment claim. The payment schedule must contain concrete
reasons for not paying the claimed amount fully or not paying at all. If the
respondent does not provide the claimant with payment schedule, he becomes liable
to pay the claimed amount fully. When the payment due date comes, the claimant
could recover it through a court or through adjudication. If claimant chooses
adjudication, then the claimant have to submit an adjudication application to the
Authorised Nominating Authority (ANA) and the respondent within the time
prescribed in the Act. An independent adjudicator will then be appointed by the
ANA. The respondent may then lodge an adjudication response to the adjudicator
prior to adjudication determination by the adjudicator. The prescribed timeline of the
Act has to be complied with strictly. Else, the rights of the parties that would
otherwise be available under the Act will be lost.
If the adjudicator decides in favour of the claimant, the claimant may file the
adjudication determination in a court and get automatic judgement for the
adjudicated amount. If the respondent is unhappy with the outcome and wishes to set
aside the adjudication determination, he or she could apply to the court. In the
meantime, the unpaid portion of the adjudicated amount has to be paid as security
pending the outcome of the court proceeding. Other than that, the Act allows
claimant to suspend work pending payment. Besides, claimant could exercise a lien
56
over unfixed plant or materials supplied by him to the extent of the unpaid amount of
the progress claim.
2.6.2
New South Wales (Statistics)
Figure 2.6.2.1: Number of adjudication applications by payment claim value
range 2014/15
72% of the total number of determinations were made for claims for less than
$100,000. In these particular cases, adjudicators awarded, roughly, 87% of the
claimed amount; 61% of claimants being given the full claimed amount. 18% of the
total number of determinations were made for claims for $100,000 to less than
$500,000. In these particular cases, adjudicators awarded, roughly, 66% of the
claimed amount; 20% of claimants being granted the full claimed amount. 10% of
the total number of determinations released were made for claims for $500,000 or
greater. In these particular cases, adjudicators awarded, roughly, 43% of the claimed
amount; 4% of claimants being conferred the full claimed amount (Fair Trading,
2015).
57
Figure 2.6.2.2: Total claimed and adjudicated amounts 2014/15
Roughly, claimants were awarded 44% of the amount claimed (Fair Trading,
2015).
Figure 2.6.2.3: Claimant Type 2014/15
58
Figure 2.6.2.4: Respondent Type 2014/15
Contractors and subcontractors are the main claimants. Whereas, most
common profile of the respondent are head contractors and clients (Fair Trading,
2015).
Claimant has a high successful rate of over 90% in the adjudication process.
In term of being awarded full amount of payment claim, subcontractor is more
successful than main contractor (Uher and Brand, 2005).
59
2.6.3
Queensland (Statistics)
Figure 2.6.3.1: Percentage of Claimant Type Year to Date
Unsurprisingly, subcontractors were the majority of the claimant, tantamount
to 66.83%, followed by contractors who were accounted for 21.29%. Head
contractors come next, accounting for 5.94% (BCIPA, 2014).
Figure 2.6.3.2: Percentage of Respondent Type Year to Date
According to Building and Construction Industry Payment Agency (2014),
50% of respondents were contractors, while client accounts for 26.73%. Head
contractor, on the other hand, accounts for 19.31%.
60
Figure 2.6.3.3: Application Lodged by Region Year to Date
Brisbane tops the list, accounting for almost half the applications lodged, that
is, 49.01%.It was then followed by Gold Coast, Mackay, Toowoomba etc (BCIPA,
2014).
Figure 2.6.3.4: Percentage of Claimants Receiving Full Claim Amount
According to Building and Construction Industry Payment Agency (2014),
80.95% of claimant received full claim amount when the claim amount was lesser
than $5000. 70.59% of claimant received full amount when the claim amount ranged
between $5000 to $9999. There is a downwards trend of claimants receiving full
claim amount as the claim amount increases.
61
2.7
Main Features of CIPAA
2.7.1
Make Conditional Payment Void
Section 35 of CIPAA expressly prohibits conditional payment. Section 35(2) sets out
the condition to which a payment is considered as conditional payment. However,
the scope of S35 conditional payment clauses – whether the conditional payment
clauses are limited to the two types set out in Section 35(2) and whether these stated
conditional payment clauses are exhaustive are brought to court. The Judge held that
this proposition may not have been the will of the Parliament when CIPAA was
enacted – where Section 35(1) states that “Any conditional payment provision…” ,
would deem the provision a more expansive interpretation that would accord with the
purpose of CIPAA. It was held that Section 35 does not have to be interpreted
exhaustively. Based on the factual circumstances of their contractual dispute, parties
may be able to proof that any contractual obligation might be considered a
‘conditional payment provision’, although their current scenario may not specifically
fall under the scopes as stipulated in Section 35(2).
2.7.2
Securing Direct Payment from Principal
CIPAA permits the subcontractor to request direct payment of the adjudicated
amount from the employer. And, in accordance with it, the employer has obligations
to pay for it. Subcontractor could rely on it to recover the adjudicated amount from
the employer where it has a decision against the main contractor who has failed to
pay.
2.7.3
Suspension or Reduce the Rate of Progress of the Works
The winning party will have the right to suspend or reduce the rate of progress of the
works if there is an underpayment of the adjudicated amount as decided, provided
62
that written notice has been given to the losing party, indicating his intention to do so.
If this happens, the winning party will entitle a reasonable extension of time and is
able to claim for any loss and expense resulted from the suspension or reduction of
the rate of progress of the works.
2.8
Shortcomings of CIPAA
2.8.1
Jurisdiction of the Adjudicator Is Not Made Clear
Like UK, jurisdiction of the adjudicator is often complex and controversial.
Redworth Construction Limited v Brookdale Healthcare Limted (2006) EWHC1994
and Harlow & Milner Ltd v Mrs Linda Teasdale (2006) EWHC 1708 both had
jurisdiction as a key issue.
2.8.2
Does Not Address Whether the New Adjudication Regime Could Apply
to Contracts Entered into Before 15 April 2014
CIPAA does not make clear whether the new adjudication regime could apply to
contracts entered into before 15 April 2014. On this matter, KLRCA, the sole
adjudicating body, has confirmed that it welcome construction disputes, regardless of
whether the contract is entered into before or after that date (Cannon and Gibson,
2014).
And, this issue is brought before the High Court and later the Court of Appeal.
In UDA Holdings Berhad v Bisraya Construction Sdn Bhd & Anor. And Capitol
Avenue Development Sdn Bhd v Bauer (Malaysia) Sdn Bhd (2015) 11 MLJ 499, the
High Court is of the opinion that the intention of the Parliament in enacting the
CIPAA was to provide a remedy to all construction contracts and payment claims
made, regardless of when they might have been made. The Court of Appeal later
upheld the High Court’s decision on appeal, suggesting that CIPAA could be given
63
retrospective effect to extend its application to payment disputes and their underlying
contracts that arose before 15 April 2014. The necessary implication of these
judgements is that parties can validly bring claims under the CIPAA so long as they
are not time barred under the relevant limitation legislations and satisfy other
requirements of the Act.
2.8.3
Intentional Delay by Uncooperative Defendant
Since the clock does not start ticking for the date of the adjudication response or the
eventual decision till the adjudicator is nominated, it is likely for the uncooperative
defendant to drag either the selection of adjudicator or appointment of adjudicator by
disagreeing with the terms and fees of adjudicator in the early period or wait for the
last minute to submit the adjudication response even if it has been completed. Worst
comes to worst, these three events could happen all together at a single adjudication
process (Cannon and Gibson, 2014)
2.8.4
Relatively
Long
Adjudication
Response
and
Relatively
Short
Adjudication Reply
According to Cannon and Gibson (2014), the responding party will have up to 6
weeks to prepare its adjudication response. Unlike Malaysia, the adjudications
carried out in the UK, Singapore or Australia do not have such luxury, having only
between 7 to 14 days to respond.
Unlike UK, Singapore, Australia and New Zealand regimes which exclude
the bringing of defences of set-off or counterclaims which have not been raised
before, there are no such restrictions in Malaysia. In fact, there are no restrictions on
what could be included in the adjudication response at all. Hence, nothing is
preventing a defendant from using these 6 weeks to compile something surprising to
surprise the claimant. Thoroughly new contra-charges could be raised, leaving room
64
for tremendously strategic behaviour by the respondent, considering there are only 5
days for claimant to serve the adjudication reply from receipt of the adjudication
response. The probability for the claimant to be overwhelmed by the surprising
multiple lever arch files response is greater than it is supposed to be (Cannon and
Gibson, 2014).
65
CHAPTER 3
3 METHODOLOGY
3.1
Research Strategy
Research strategy can be divided into 2 types, which are, ‘quantitative research’ and
‘qualitative research’. The aim of the study as well as the type and availability of the
information will determine which type of research to adopt (Naoum, 2013).
3.1.1
Quantitative Research
Quantitative research is ‘objective’ in nature. Quantitative data are not abstract; they
are hard and reliable; they are measurements of tangible, countable, sensate features
of the world (Bouma and Atkinson, 1995).
3.1.2
Qualitative Research
Qualitative research, however, is ‘subjective’ in nature. It emphasises on meanings,
experiences, description and so on (Naoum, 2013). According to Gupta and Gupta
(2011), it concerns with subjective assessment of attitudes, opinions and behaviour.
Krysik and Finn (2010) is of the opinion that qualitative research is holistic in its
approach and the data collected tend to be rich in narrative descriptions. Focus group
66
interviews and projective techniques are some of the techniques used (Gupta and Gupta,
2011).
3.2
Approaches to Data Collection
According to Naoum (2013), the approach to be adopted for carrying out of the study
depends very much on the nature of the investigation and the type of data and
information that are required and available. There are 2 approaches to data collection;
they are fieldwork and desk study.
3.2.1
Fieldwork Research
Naoum (2013) finds these three approaches especially practical:
1. Survey approach – Data can be collected from a relatively large number of
respondents in a relatively short time. The findings will then be generalized.
2. Case study approach – It provides an in-depth analysis of a specific problem.
However, the findings cannot be generalized.
3. Problem-solving approach – It reviews the current situation, identifies the
problem, gets involved in introducing some changes to enhance the situation
and evaluates the implication of the changes.
3.2.2
Desk Study Research
Secondary data can be stored in 2 formats, namely, statistical and descriptive.
Statistical format refers to official statistics which are collected by the government
related bodies. Descriptive format, on the other hand, refers to analysing and
appraising the contents of an archival document (Naoum, 2013). According to
67
Kumar (2011), secondary sources offer second-hand data. However, none of the data
collection method provides absolute information, be it a primary sources or be it a
secondary sources.
3.3
Research Design
This study will adopt survey questionnaire. In fact, this method is used extensively
by various parties, namely, private individuals, research workers, private and public
organisations and even by governments (Kothari, 2004). It is suitable to be adopted
for descriptive and analytical surveys whose aim is clear enough to be explained in a
few paragraphs, so as to figure out facts and opinions on what is happening (Naoum,
2013). According to Creswell (2014), it provides a quantitative or numeric
description of trends, attitudes or opinions of a population by studying a sample of
that population. The survey would be a structured survey with closed-ended
questions. Mail, telephone, internet, personal interviews or group administration have
been identified as ways to data collection (Fowler, 2009). Among these, the survey
questionnaire will be sent via mail and face-to-face meeting. Only 35 questionnaires
will be analysed; 15 from quantity surveying firm, 15 from main contractors, 5 from
sub-contractors due to time constraint in analysing the data and difficulties in finding
respondents. Of course, a larger sample will promise a more accurate and reliable
current situations or views. However, this size of sample is believed to be able to
reflect the current situations or views already. This survey will be cross-sectional,
meaning the data will be collected at one point of the time only.
68
3.4
Data Analysis Method
3.4.1
Descriptive Statistics Method
Serving a general overview of the results is what descriptive statistics method does.
It is known as the simplest method of analysis as it will either analyse the responses
in percentages or actual numbers (Naoum, 2013). Put simply, it describes what the
data shows, presenting quantitative descriptions in manageable form (Social research
methods, n.d.). It can be used even when there is no direct relationship between 2
variables.
3.4.2
Inferential Statistics Method
Drawing conclusion which is extended beyond immediate data is what inferential
statistics method does. Inferences are made from the data to more general situations
(Social research methods, n.d.). In other words, inferential statistics are techniques
allowing generalizations about the populations to be made where the samples were
drawn. Hence, it is crucial that the sample accurately represents the targeted
population (Laerd, n.d.).
69
CHAPTER 4
4 RESULTS AND DISCUSSION
4.1
The View of General Respondents and CIPAA Participants Towards
The Implementation of CIPAA
This section will discuss about the view of general respondents and the view of
respondents who have taken part in CIPAA before separately towards the
implementation of CIPAA. Every answer given by the respondents for every
question in the questionnaire is tabulated and the general views of the main
contractors, QS consultants and subcontractor combined and those CIPAA
respondents are projected out in the form of pie charts.
70
4.1.1
Percentage of CIPAA Participants to All Respondents
Figure 4.1.1.1: Percentage of CIPAA Participants to All Respondents
After coming into existence for just 3 years, CIPAA respondents have almost
reached one quarter of the total respondent. That means for every four people, one of
them has taken part in CIPAA before. It is reflective of the confidence and faith the
construction industry stakeholders have in CIPAA.
71
4.1.2
Cash Flow
Figure 4.1.2.1: Cash flow
Figure 4.1.2.2: CIPAA Participants: Cash flow
71% of respondent agrees that the cash flow is smoother since CIPAA is
introduced, even though with varying degree (some agree some strongly agree).
Whereas, CIPAA participants agree to that statement with an even higher percentage
of 75%. This is certainly a testament to its success.
72
4.1.3
Eradication of Conditional Payment
Figure 4.1.3.1: Eradication of Conditional Payment
Figure 4.1.3.2: CIPAA Participant: Eradication of Conditional Payment
Only 49% of respondent opines that conditional payment is eradicated after
CIPAA is introduced, whereas 75% of CIPAA participant thinks so with 13%
disagreeing to that statement. Since outlawing conditional payment is one of the most
important features of CIPAA, the low agreeing rate that conditional payment is
eliminated should be examined.
73
4.1.4
Adjudicator's Inquisitional Role
Figure 4.1.4.1: Adjudicator's inquisitional role
Figure 4.1.4.2: CIPAA Participant: Adjudicator's inquisitional role
Majority of respondents and CIPAA respondents think that adjudicator's
inquisitional role plays an important role in ensuring successful resolved of disputes.
74
4.1.5
Reliable Dispute Resolution Mechanism
Figure 4.1.5.1: Reliable dispute resolution mechanism
Figure 4.1.5.2: CIPAA Participant: Reliable dispute resolution mechanism
A majority of 71% respondents (some agree some strongly agree) agree that
CIPAA is a reliable dispute resolution mechanism. Even a higher approval rate is
seen when it comes to CIPAA participants. 26% of undecided respondents may be
due to unfamiliarity with CIPAA and it is believed that the approval rate will be
increasing as they familiarise with CIPAA.
75
4.1.6
The Adjudicators Empanelled by KLRCA
Figure 4.1.6.1: The adjudicators empanelled by KLRCA
Figure 4.1.6.2: CIPAA Participant: The adjudicators empanelled by KLRCA
It comes as no surprise as majority of respondents choose “neutral” when
asked whether the adjudicators empanelled by KLRCA since only a quarter of them
involved in CIPAA before. However, it does come as a surprise when majority of
CIPAA participants feel the same, taking a middle stand.
76
4.1.7
Relatively Speedy Process Compared to Arbitration or Litigation
Figure 4.1.7.1: Relatively speedy process
Figure 4.1.7.2: CIPAA Participant: Relatively speedy process
Most of the respondents and CIPAA participants are of the opinion that
CIPAA is a relatively speedy process when compared to arbitration or litigation with
CIPAA participants’ approval rate as high as 87% (some agree some strongly agree),
fulfilling one of the very objectives of CIPAA of providing a mechanism for speedy
dispute resolution.
77
4.1.8
Relatively Affordable Compared to Arbitration or Litigation
Figure 4.1.8.1: Relatively affordable
Figure 4.1.8.2: CIPAA Participant: Relatively affordable
Majority of respondents and CIPAA participants agree to the statement that
the cost of adjudication is relatively low compared to arbitration or litigation.
78
4.1.9
Dispute Resolution of CIPAA
Figure 4.1.9.1: Dispute resolution of CIPAA
Figure 4.1.9.2: CIPAA Participant: Dispute resolution of CIPAA
91% of respondent agrees to the statement stating dispute resolution provided
under CIPAA is fast enough. The approval rate of CIPAA participants is, however,
100%, showing great satisfaction towards the duration of CIPAA.
79
4.1.10
The
Duration
of
Initiation
of
Adjudication,
Appointment
of
Adjudicator and Adjudication Proceedings
Undoubtedly, there will be some respondents who are of the opinion that dispute
resolution under CIPAA is not fast enough. Since CIPAA’s main attraction is its
speedy dispute resolution, when stakeholders are questioning about its very essence,
their opinions and suggestions need to be heard. Towards that end, a question of
which part of CIPAA should be shortened is set.
The respondents who have answered “No” in Section 4.1.10, will be asked
which part of CIPAA, in their opinion, should be shortened. As there are not much
respondents who answered “No”, please bear in mind that the percentage generated
in this section is based on a very small sample. Since there was no CIPAA
participant who answered “No”, there will be no analysis for this part.
Figure 4.1.10.1: Duration of initiation of adjudication
A majority of respondents think that the duration of initiation of adjudication,
where non-paying party responds to payment claim, should be shortened.
80
Figure 4.1.10.2: Duration of appointment of adjudicator
A majority of respondents think that the duration of appointment of
adjudicator, should not be shortened. It may be due to the parties want to be certain
that the adjudicator appointed has certain qualifications and has no conflict of
interest so that his decision will be convincing, at least for the parties.
(c)Should the duration of
adjudication proceedings be
shortened?
33%
67%
Yes
No
Figure 4.1.10.3: Duration of adjudication proceedings
Most of them think that the duration of adjudication proceedings should be
shortened.
81
4.1.11
Relatively Long Period of CIPAA When Compared with Other Similar
Legislations
Figure 4.1.11.1: Relatively long period of CIPAA
Figure 4.1.11.2: CIPAA Participant: Relatively long period of CIPAA
Majority of respondents think that the duration of CIPAA is good enough.
Whereas, 100% of CIPAA participants feel the same, in line with Section 4.1.9,
where 100% of them agree that dispute resolution provided under CIPAA is fast
enough.
82
4.1.12
Preferred Remedy
Figure 4.1.12.1: First choice among three remedies available
Figure 4.1.12.2: CIPAA Participant: First choice among three remedies
available
Most respondents and CIPAA participants will secure direct payment from
principal if they have not received payment after adjudication determination is served
in their favour. It is reflective of non-aggressive behaviour of Malaysian construction
industry stakeholders.
83
Figure 4.1.12.3: Second choice among three remedies available
Figure 4.1.12.4: CIPAA Participant: Second choice among three remedies
available
The second choice most respondents chooses is to slow down the works.
Same goes to CIPAA participants.
84
Figure 4.1.12.5: Last choice among three remedies available
Figure 4.1.12.6: CIPAA Participant: Last choice among three remedies
available
Given the less aggressive behaviour of Malaysian construction industry
stakeholders, suspension of works is their last choice. It is a healthy trend as most of
the industry players still view ‘completion of project’ their first priority even when
they are treated unfairly.
85
4.1.13
Improvements Felt in Malaysia
Figure 4.1.13.1: Timeliness in paying
Figure 4.1.13.2: CIPAA Participant: Timeliness in paying
Sadly, a majority of respondents do not think that there is any improvement
in timeliness in paying in Malaysia since CIPAA is introduced. While, only 50% of
CIPAA respondents feel the improvement. As facilitating regular and timely
payment is one of the reasons why CIPAA is introduced, this situation needs to be
studied.
86
Figure 4.1.13.3: Certainty in obtaining payment
Figure 4.1.13.4: CIPAA Participant: Certainty in obtaining payment
Only 49% of respondent feel that there is any improvement in certainty in
obtaining payment in Malaysia since the introduction of CIPAA. Whereas, CIPAA
participants, in overall, stay neutral on this matter. Further research on why this
happens should be done.
87
Figure 4.1.13.5: Improvement in willingness of main contractors to seek
amicable settlement with sub-contractors
Figure 4.1.13.6: CIPAA Participant: Improvement in willingness of main
contractors to seek amicable settlement with sub-contractors
A majority of respondents feel that there is improvement in willingness of
main contractors to seek amicable settlement with sub-contractors, while CIPAA
participants stay undecided on this matter.
88
4.1.14
Power to Award Adjudication Cost
Figure 4.1.14.1: Power to award adjudication cost
Figure 4.1.14.2: CIPAA Participant: Power to award adjudication cost
Majority of respondents and CIPAA participant opine that the power to award
adjudication cost given to adjudicators will discourage the application of
adjudication, particularly to small and medium-sized company, who are already
financially stretched. Measures have to be taken to prevent this from happening.
89
4.1.15
Adjudication Reply
Figure 4.1.15.1: Adjudication reply
Figure 4.1.15.2: CIPAA Participant: Adjudication reply
Majority of respondents and CIPAA participants think that it is fair to have
adjudication reply with no further ground for respondent to response to that reply.
90
4.1.16
Reach of CIPAA
Figure 4.1.16.1: Reach of CIPAA
Figure 4.1.16.2: CIPAA Participant: Reach of CIPAA
Majority of respondents are of the opinion that CIPAA should extend its
reach to cover all types of construction contracts, be it written, oral or partly written
and partly oral, whereas only 50% of CIPAA participants think so.
91
4.1.17
Issues of Breach of Natural Justice and Adjudicator’s Jurisdiction
Problem
Figure 4.1.17.1: Issues within CIPAA
Figure 4.1.17.2: CIPAA Participant: Issues within CIPAA
Most of the respondents, especially CIPAA participants, show serious
concerns towards the issues of breach of natural justice and adjudicator's jurisdiction
problem. One of the possible solutions is constantly providing training and workshop
to the adjudicators so that these predicament can be minimized.
92
4.1.18
Adjudication Review
Figure 4.1.18.1: Adjudication Review
Figure 4.1.18.2: CIPAA Participant: Adjudication Review
Majority of the respondents, especially CIPAA participants, are of the
opinion that CIPAA should have adjudication review. It is indicative of the parties’
wish for a fairer and more transparent mechanism.
93
4.1.19
Rating of CIPAA
Figure 4.1.19.1: Rating of CIPAA
Figure 4.1.19.2: CIPAA Participant: Rating of CIPAA
Majority of respondents and CIPAA participants rate CIPAA four out of five,
which is later given a description as good. It is reflective of the parties’ faith reposed
in CIPAA.
94
4.2
The View of Main Contractors, QS Consultants and Subcontractors
Respectively Towards The Implementation of CIPAA
This section will discuss about the view of main contractors, QS consultants and
subcontractors respectively towards the implementation of CIPAA. Every answer
given by the respondents for every question in the questionnaire is tabulated and the
general views of the main contractors, QS consultants and subcontractor are
projected out in the form of bar charts and pie charts.
4.2.1
Percentage of Each Party Involved in CIPAA
Figure 4.2.1.1: Percentage of each party involved in CIPAA
40% of subcontractor respondent has taken part in CIPAA before, be it as a
claimant or a respondent. 33.3% of main contractor respondent and only a small
fraction of 6.7% of QS consultant respondent have been involved in CIPAA before.
Subcontractor is the mostly CIPAA involved party in this study, followed by main
contractor and lastly QS consultant. This is in line with the KLRCA report stating
subcontractor is the most common profile of the claimant in CIPAA, ensued by main
contractor and eventually consultant. This trend could be attributed to the fact that
the lower the parties down the construction chain, the more they are being pressured
95
financially, not getting paid. In addition, it is reflective of the reach of CIPAA among
subcontractors, main contractors and QS consultants.
4.2.2
Cash Flow
Figure 4.2.2.1: Main Contractor: Cash flow
Figure 4.2.2.2: QS Consultant: Cash flow
96
Figure 4.2.2.3: Subcontractor: Cash flow
Majority of respondents, be it main contractor, consultant QS or
subcontractor, think that CIPAA has eased the cash flow in the construction industry,
although with different intensities.
97
4.2.3
Eradication of Conditional Payment
MAIN CONTRACTOR: CONDITIONAL
PAYMENT IS ERADICATED AFTER CIPAA IS
INTRODUCED
Strongly agree
Agree
Undecided
Disagree
Strongly disagree
0%7%
20%
27%
46%
Figure 4.2.3.1: Main Contractor: Eradication of conditional payment
Figure 4.2.3.2: QS Consultant: Eradication of conditional payment
98
Figure 4.2.3.3: Subcontractor: Eradication of conditional payment
A majority of main contractor and QS consultant agrees that conditional
payment is eradicated after CIPAA is introduced, although not with a lopsided result
that it is supposed to be. Whereas, only 40% of subcontractor respondent agrees with
the statement. While outlawing conditional payment is one of the primary objectives
of CIPAA, this area is indeed worthy of special note and attention. Parties concerned
should look into this “situation” seriously and think of ways to ensure conditional
payment is eradicated thoroughly.
99
4.2.4
Adjudicator's Inquisitional Role
Figure 4.2.4.1: Main Contractor: Adjudicator's inquisitional role
Figure 4.2.4.2: QS Consultant: Adjudicator's inquisitional role
100
Figure 4.2.4.3: Subcontractor: Adjudicator's inquisitional role
Majority of main contractor, QS Consultant and subcontractor respondents
agree that adjudicator's inquisitional role plays an important role in ensuring
successful resolved of disputes.
101
4.2.5
Reliable Dispute Resolution Mechanism
Figure 4.2.5.1: Main Contractor: Reliable dispute resolution mechanism
Figure 4.2.5.2: QS Consultant: Reliable dispute resolution mechanism
102
Figure 4.2.5.3: Subcontractor: Reliable dispute resolution mechanism
Majority of main contractor, QS Consultant and subcontractor respondents
agrees that CIPAA is a reliable dispute resolution mechanism. 60% of main
contractor respondent is of the opinion that CIPAA is a reliable dispute resolution
mechanism. 80% of QS Consultant respondent and subcontractor respondent feels
the same.
103
4.2.6
The Adjudicators Empanelled by KLRCA
Figure 4.2.6.1: Main Contractor: The adjudicators empanelled by KLRCA
Figure 4.2.6.2: QS Consultant: The adjudicators empanelled by KLRCA
104
Figure 4.2.6.3: Subcontractor: The adjudicators empanelled by KLRCA
A majority of 67% of main contractor respondent and QS Consultant take a
middle stand when asked whether the adjudicator empanelled by KLRCA is
knowledgeable enough, neither agree nor disagree. While, in subcontractor side,
similarly, 60% of subcontractor respondent chooses neutral when asked whether the
adjudicator empanelled by KLRCA is knowledgeable enough.
The large undeciding groups of respondents may be attributed to the lack of
experience in CIPAA. Since CIPAA has just been introduced in 2014, there are not
much parties that have been involved in CIPAA before. Therefore, being not familiar
with CIPAA, the respondents are likely to choose “undecided choice”.
105
4.2.7
Relatively Speedy Process Compared to Arbitration or Litigation
Figure 4.2.7.1: Main Contractor: Relatively speedy process
Figure 4.2.7.2: QS Consultant: Relatively speedy process
106
Figure 4.2.7.3: Subcontractor: Relatively speedy process
73% of main contractor respondent and QS Consultant respondent thinks of
adjudication as a relatively speedy process compared to arbitration or litigation.
However, only 40% of subcontractor respondent feels the same.
107
4.2.8
Relatively Affordable Compared to Arbitration or Litigation
Figure 4.2.8.1: Main Contractor: Relatively affordable
Figure 4.2.8.2: QS Consultant: Relatively affordable
108
Figure 4.2.8.3: Subcontractor: Relatively affordable
Majority of main contractor, QS Consultant and subcontractor respondents
agree that the cost of adjudication is relatively low compared to arbitration or
litigation.
109
4.2.9
Dispute Resolution of CIPAA
Figure 4.2.9.1: Main Contractor: Dispute resolution of CIPAA
Figure 4.2.9.2: QS Consultant: Dispute resolution of CIPAA
110
Figure 4.2.9.3: Subcontractor: Dispute resolution of CIPAA
87% of main contractor respondent agrees that dispute resolution provided
under CIPAA is fast enough, whereas 93% of QS Consultant agrees to the statement.
Every subcontractor respondent taking part in this study agrees to the statement. This
unanimous high rating given by various stakeholders can be attributed to the efficient
administrative mechanism of CIPAA and, of course, the success of CIPAA
legislation.
111
4.2.10
The
Duration
of
Initiation
of
Adjudication,
Appointment
of
Adjudicator and Adjudication Proceedings
Certainly, there will be some respondents are of the opinion that dispute resolution
under CIPAA is not fast enough. Since CIPAA’s main attraction is its speedy dispute
resolution, when stakeholders are questioning about its very essence, their opinions
and suggestions need to be heard. To that end, a question of which part of CIPAA
should be shortened is set.
The respondents who have answered “No” in Section 4.2.10, will be asked
which part of CIPAA, in their opinion, should be shortened. As there are not much
respondents who answered “No”, please bear in mind that the percentage generated
in this section is based on a very small sample.
Figure 4.2.10.1: Main Contractor: Duration of initiation of adjudication
112
Figure 4.2.10.2: Main Contractor: Duration of appointment of adjudicator
Figure 4.2.10.3: Main Contractor: Duration of adjudication proceedings
113
Figure 4.2.10.4: Consultant QS: Duration of initiation of adjudication,
appointment of adjudicator and adjudication proceedings
50% of main contractor respondent, who has answered “No” in Section 4.2.9,
thinks that the duration of initiation of adjudication should be shortened. However,
none of them opines that the duration of appointment of adjudicator should be
shortened. While, 50% of them are of the opinion that the duration of adjudication
proceedings should be shortened. On the consultant QS side, the consultant QS
respondent, who has answered “No”, thinks that every phase of CIPAA, be it
duration of initiation of adjudication, appointment of adjudicator or adjudication
proceedings, should be shortened.
114
4.2.11
Relatively Long Period of CIPAA When Compared with Other Similar
Legislations
Figure 4.2.11.1: Main Contractor: Relatively long period of CIPAA
Figure 4.2.11.2: Consultant QS: Relatively long period of CIPAA
115
Figure 4.2.11.3: Subcontractor: Relatively long period of CIPAA
When compared to other similar legislations, the process of CIPAA is
relatively longer. When asked to compare, majority of main contractor, consultant
QS and subcontractor respondents think that the duration of CIPAA is good enough.
In other words, most of the respondents are satisfied with the duration of CIPAA.
116
4.2.12
Preferred Remedy
Figure 4.2.12.1: Main Contractor: First choice among three remedies available
(A)CONSULTANT QS: IF YOU HAVE NOT
RECEIVED PAYMENT AFTER ADJUDICATION
DETERMINATION IS SERVED IN YOUR FAVOR,
WHAT WOULD BE YOUR FIRST CHOICE
AMONG THREE REMEDIES AVAILABLE?
Slow down the works
Secure direct payment from principal
14%
Suspend the works
22%
64%
Figure 4.2.12.2: Consultant QS: First choice among three remedies available
117
Figure 4.2.12.3: Subcontractor: First choice among three remedies available
A majority of main contractor respondent and consultant QS respondent
would prefer “secure direct payment from principal” over other choices. A majority
of subcontractor, however, would slow down the works if they have not received
payment after adjudication determination is served in their favour.
118
Figure 4.2.12.4: Main Contractor: Second choice among three remedies
available
Figure 4.2.12.5: Consultant QS: Second choice among three remedies available
119
Figure 4.2.12.6: Subcontractor: Second choice among three remedies available
It is interesting to note that an equal amount of 46% of main contractor
respondent chooses “secure direct payment from principal” and “slow down the
works” as their second choice. Nevertheless, since “secure direct payment from
principal” is their first choice, so “slow down the works” option will be the second.
Consultant QS also feels the same, choosing “slow down the works” as their second
choice. Similar to main contractor situation, an equal amount of 40% of
subcontractor respondent chooses “suspend the works” and “slow down the works”
as their second choice. As “slow down the works” is their first choice, “suspend the
works” remedy will be their second.
120
Figure 4.2.12.7: Main Contractor: Third choice among three remedies available
Figure 4.2.12.8: Consultant QS: Third choice among three remedies available
121
Figure 4.2.12.9: Subcontractor: Third choice among three remedies available
“Suspend the works” will be the last choice among three remedies available
for main contractor and consultant QS. As “suspend the works” is subcontractor’s
second choice, “secure direct payment from principal” would be their last choice.
122
4.2.13
Improvements Felt in Malaysia
Figure 4.2.13.1: Main Contractor: Timeliness in paying
Figure 4.2.13.2: Consultant QS: Timeliness in paying
123
Figure 4.2.13.3: Subcontractor: Timeliness in paying
Sadly, only a majority of main contractor respondent thinks that timeliness in
paying in Malaysia has improved since CIPAA is introduced. Majority of consultant
QS and subcontractor respondents do not feel the same.
124
Figure 4.2.13.4: Main Contractor: Certainty in obtaining payment
Figure 4.2.13.5: Consultant QS: Certainty in obtaining payment
125
Figure 4.2.13.6: Subcontractor: Certainty in obtaining payment
Majority of main contractor and subcontractor respondents do not think that
there is any improvement in certainty in obtaining payment in Malaysia since the
introduction of CIPAA. However, majority of consultant QS feel otherwise.
126
Figure 4.2.13.7: Main Contractor: Willingness of main contractors to seek
amicable settlement with sub-contractors
Figure 4.2.13.8: Consultant QS: Willingness of main contractors to seek
amicable settlement with sub-contractors
127
Figure 4.2.13.9: Subcontractor: Willingness of main contractors to seek
amicable settlement with sub-contractors
Majority of respondents, be it main contractor, consultant QS and
subcontractor, unanimously think that there is an improvement in willingness of
main contractors to seek amicable settlement with sub-contractors since CIPAA is
introduced. It is a positive trend in which construction industry stakeholders are
seeking - rebalancing of power. With CIPAA in power, subcontractors are no longer
a prey, who used to suffer financially due to stuck cash flow.
128
4.2.14
Power to Award Adjudication Cost
MAIN CONTRACTOR: DO YOU THINK THE
POWER TO AWARD ADJUDICATION COST
GIVEN TO ADJUDICATORS WILL
DISCOURAGE THE APPLICATION OF
ADJUDICATION, PARTICULARLY TO SMALL…
Yes
No
27%
73%
Figure 4.2.14.1: Main Contractor: Power to award adjudication cost
Figure 4.2.14.2: Consultant QS: Power to award adjudication cost
129
Figure 4.2.14.3: Subcontractor: Power to award adjudication cost
Majority of main contractor, consultant QS and subcontractor respondents are
of the opinion that the power to award adjudication cost given to adjudicators will
discourage the application of adjudication, particularly to small and medium-sized
company. The power of awarding adjudication cost given by CIPAA to adjudicators
may deter small and medium-sized company to refer their disputes to CIPAA
because if the adjudicators find that the claimants are partly at fault too and may
award part of adjudication cost to the financially drained claimants. This area is
indeed worthy of attention.
130
4.2.15
Adjudication Reply
Figure 4.2.15.1: Main Contractor: Adjudication reply
Figure 4.2.15.2: Consultant QS: Adjudication reply
131
Figure 4.2.15.3: Subcontractor: Adjudication reply
Majority of main contractor and consultant QS respondents opine that it is
fair to have adjudication reply with no further ground for respondent to response to
that reply. However, majority of subcontractor respondents think that it is unfair and
there should be another reply to that reply. It is interesting to see subcontractors, who
are down the construction chain, feel that this mechanism that is to their advantages,
is unfair and think that there should be another reply to that reply.
132
4.2.16
Reach of CIPAA
Figure 4.2.16.1: Main Contractor: Reach of CIPAA
Figure 4.2.16.2: QS Consultant: Reach of CIPAA
133
Figure 4.2.16.3: Subcontractor: Reach of CIPAA
Majority of main contractor, consultant QS and subcontractor respondents
hope that CIPAA could extend its reach to cover all types of construction contracts,
be it written, oral or partly written and partly oral, just like in New South Wales.
134
4.2.17
Issues of Breach of Natural Justice and Adjudicator’s Jurisdiction
Problem
Figure 4.2.17.1: Main Contractor: Issues within CIPAA
Figure 4.2.17.2: Consultant QS: Issues within CIPAA
135
Figure 4.2.17.3: Subcontractor: Issues within CIPAA
Majority of main contractor, consultant QS and subcontractor respondents
collectively think that issues on breach of natural justice and adjudicator’s
jurisdiction problem affect the effectiveness of CIPAA. This indicates that various
parties show serious concerns towards issues of breach of natural justice and
adjudicator’s jurisdiction problems.
136
4.2.18
Adjudication Review
Figure 4.2.18.1: Main Contractor: Adjudication review
Figure 4.2.18.2: Consultant QS: Adjudication review
137
Figure 4.2.18.3: Subcontractor: Adjudication review
87% of main contractor respondent and 100 % of Consultant QS and
subcontractor respondent wishes that CIPAA to have adjudication review. These
high percentage of approval for adjudication review from various groups indicates
that the parties are seeking a fairer and more transparent adjudication determination.
138
4.2.19
Rating of CIPAA
Figure 4.2.19.1: Main Contractor: Rating of CIPAA
Figure 4.2.19.2: Consultant QS: Rating of CIPAA
139
Figure 4.2.19.3: Subcontractor: Rating of CIPAA
Majority of main contractor and consultant QS respondents rate CIPAA 4 out
of 5, which is later given a description as good. However, a majority of subcontractor
respondents rate CIPAA 3 out of 5, which is later given a description as average.
140
CHAPTER 5
5 CONCLUSION AND RECOMMENDATIONS
5.1
Introduction
Basically, this chapter summarizes the findings found in this study. Of course, the
findings lead back to the objectives of this research which are:
1. To investigate whether CIPAA has addressed the cashflow problems in
the construction industry as it was intended to.
2. To get to know how the construction industry stakeholders think of the
effectiveness and efficiency of CIPAA.
3. To get the insight of how CIPAA could be further improved by studying
similar payment legislations in other countries.
Research limitations faced will also be discussed in this chapter. Besides, the
contributions of this research to the construction industry will be looked into.
Last but not least, there are suggestions for further research.
141
5.2
Findings
Majority of respondents feel that cashflow has become smoother since CIPAA is
introduced. However, not so much for the conditional payment problems.
Surprisingly, majority of respondents except main contractors do not think that
timeliness in paying has improved although CIPAA is in power.
91% of respondents and 100% of CIPAA respondents opine that dispute
resolution provided under CIPAA is fast enough, showing great satisfaction towards
the duration of CIPAA. The majority of the other 9% who thinks otherwise is of the
opinion that the duration of initiation of adjudication and adjudication proceedings
but not the duration of appointment of adjudicator should be shortened. It may be due
to the parties want to be certain that the adjudicator appointed has certain
qualifications and has no conflict of interest so that his decision will be convincing. It
comes as no surprise as most of the respondents think that adjudication under CIPAA
is a relatively speedy and affordable dispute resolution mechanism when compared
to arbitration or litigation. However, the respondents do show their concern towards
issues on breach of natural justice and jurisdiction problems of adjudicators, which
may render the adjudication results not enforceable. In general, the performance of
CIPAA is given 4 out of 5, indicating a sign of faith various parties have reposed in
CIPAA. It is further strengthened when 88% of CIPAA participants think that
CIPAA is reliable.
Most of the respondents think that it is fair to have adjudication reply with no
further ground for respondent to response to that reply. Nevertheless, subcontractor
respondents find that is unfair and think that there should be another reply to that
reply, like what has been practiced in UK. Majority of respondents wish that CIPAA
could extend its reach to cover all types of construction contracts, be it written, oral
or partly written and partly oral, just like in New South Wales. Many feel that the
power to award adjudication cost given to adjudicator will discourage the application
of CIPAA, particularly to small and medium-sized company. 94% of respondent
wishes that CIPAA to have adjudication review. These high percentage of approval
for adjudication review is reflective that the various parties are seeking a fairer and
more transparent adjudication determination.
142
Compared to UK claimant’s successful rate of 50%, CIPAA has a much
higher claimant’s successful rate of over 90% as in New South Wales. Although
CIPAA successful rate is still behind Singapore claimant’s successful rate of 97.7%,
CIPAA is considered to be quite effective. Like UK, Singapore and Queensland, the
trend of the most common profile of the claimant continues to be the subcontractor,
followed by main contractor. However, in New South Wales, contractor is the main
claimant, ensued by subcontractor.
5.3
Research Limitations
There are some research limitations throughout the execution of this research. One of
them is small sample size. Most of the questionnaires sent out through email have
never made their way back, hence, resulting in small sample size.
Initially, this research is further divided into 4 parts, which are main
contractors, consultant QS and subcontractors as well as suppliers. However, since
none of the supplier has responded, its scope has decreased to 3. Furthermore, for the
subcontractor part, this study has only managed to capture 5 respondents, again due
to low response rate. Hence, for the subcontractor part, the results may not be as
accurate as that of main contractors and consultant QS, which have a sample size of
15 respectively.
Lastly, since CIPAA has just been enforced for 3 years, most of the
construction industry players have not been involved in CIPAA before and are not
familiar with it yet. Hence, the data captured will not be that accurate. It can be seen
through the choosing ‘undecided’ or ‘neutral’ choices frequently.
143
5.4
Research Contribution to Malaysian Construction Industry
Through the execution of this research, it is learnt that most of the construction
industry players are aware of CIPAA, be it main contractors, subcontractors or
consultant QS, and admitted that CIPAA has eased the cash flow in the construction
industry. However, conditional payment still prevails despite the introduction of
CIPAA. The timeliness in paying still has room for improvement. Since outlawing
conditional payment and facilitating timely payment are one of the most important
features of CIPAA, KLRCA and the relevant authorities should look into this
predicament seriously and think of ways to ensure that conditional payment is
eradicated thoroughly and industry players get paid timely so that the very objective
of introduction of CIPAA is achieved.
It is also learnt that the industry players are happy about the duration of
CIPAA, even though it is relatively longer compared to similar legislations.
Moreover, the study shows that most of the respondents are concerned towards issues
of breach of natural justice and adjudicator's jurisdiction problem which may render
the adjudication determination unenforceable. Hence, KLRCA should be constantly
providing training and workshop regarding to that matters to minimise the
occurrence of such matters so that the effectiveness of CIPAA is not questioned.
KLRCA and relevant authorities could consider to extend CIPAA’s reach to
cover all types of construction contracts, be it written, oral or partly written and
partly oral. Moreover, many of the respondents are also seeking CIPAA to have
adjudication review. Perhaps KLRCA could consider their suggestion. Of course, it
is easier said than done. But at least it is what can be drawn from this study.
144
5.5
Recommendation for Further Research
The following potential topics are recommended for further research:
(a) A study on the effects of CIPAA on conditional payment.
(b) A study on the effects of CIPAA on timeliness in paying.
(c) A study on the issues on breach of natural justice and jurisdiction problems of
adjudicators towards the implementation of CIPAA.
(d) A study on the practicability of CIPAA to extend its reach to cover all types of
construction contracts, be it written, oral or partly written and partly oral.
(e) A study on the power to award adjudication cost of adjudicator towards the
implementation of CIPAA.
(f) A study on the practicability of CIPAA to have adjudication review.
(g) A study on the understanding of construction industry players towards CIPAA.
145
REFERENCES
Ameer Ali, N.A.N., 2006. A ‘Construction Industry Payment And Adjudication Act’:
Reducing Payment-Default And Increasing Dispute Resolution Efficiency In
Construction.
[online]
Available
at:
<http://www.mbam.org.my/mbam/images/MBJ4Q06(pdf)/CS_ACTpt2.pdf>
[Accessed 20 June 2016].
Ameer Ali, N.A.N., no date. A ‘Construction Industry Payment And Adjudication
Act’: Reducing Payment-Default and Increasing Dispute Resolution Efficiency in
Construction.
[online]
Available
at:
<http://www.cicqs.com/main/files/PaymentAct_Article_Part1%5B1%5D.pdf>
[Accessed 20 June 2016].
Azman, M.N.A., Dzulkalnine, N., Abd Hamid, Z. and Wai Beng, K., 2014. Payment
issue in Malaysian construction industry: Contractors’ perspective. Jurnal Teknologi,
[online]
Available
at:
<https://www.researchgate.net/publication/265208786_Payment_Issue_in_Malaysia
n_Construction_Industry_Contractors%27_Perspective?enrichId=rgreqbd37c26c79bee8be08b7c9f595ed6f30XXX&enrichSource=Y292ZXJQYWdlOzI2NTIwODc4NjtBUzoxNDE1MjcwODI4
Njg3MzZAMTQxMDc1NDA5NDkyNw%3D%3D&el=1_x_2> [Accessed 17 July
2016]
Building and Construction Authority, 2013. Adjudication Review Statistics. [online]
BCA.
Available
<https://www.bca.gov.sg/securitypayment/adjudication_review_statistics.html>
[Accessed 8 July 2016]
at:
146
Building and Construction Authority, 2013. Security of payment legislation,
adjudication
[Online]
statistics.
Available
at:
<https://www.bca.gov.sg/securitypayment/adjudication_review_statistics.html>
[Accessed 2 July 2016].
Building and Construction Industry Payments Agency, 2014. Adjudication Statistics.
[pdf] BCIPA. Available at: <http://www.qbcc.qld.gov.au/get-help-getting-paidbcipa/overview> [Accessed 10 July 2016]
Cannon, S. and Gibson, S., 2014. Adjudication of construction disputes in Malaysia
A
new
approach
to
dispute
resolution.
Available
at:
<https://www.eversheds.com/documents/services/construction/adjudicationconstruction-disputes-malaysia.pdf> [Accessed 25 June 2016].
Chan, C.F., 2006. Security of payment Legislation—Case of a blunt but practical and
equitable instrument. Journal of Professional Issues in Engineering Education and
Practice, 132(3), pp. 248–257. doi: 10.1061/(asce)1052-3928(2006)132:3(248).
Available
at:
<http://eds.a.ebscohost.com.libezp.utar.edu.my/eds/pdfviewer/pdfviewer?sid=ce7819
59-a988-4ec0-98a6-d1fe2404f575%40sessionmgr4008&vid=2&hid=4102>
[Accessed 7 January 2017]
Che Munaaim, M.E., Mohd Danuri, M.S. and Abdul-Rahman, H., 2012. Is Late Or
Non-Payment A Significant Problem To Malaysian Contractors? Journal of Design
and
Built
Environment.
[e-journal]
Available
at:
<http://e-
journal.um.edu.my/public/article-view.php?id=2622> [Accessed 18 July 2016]
Cheng, S.C., 2005. Adjudication in Asia and Australasia. In: Society of Construction
Arbitrators
Annual
Conference.
13
-
15
May
2005.
Available
at
<https://www.constructionarbitrators.org/sites/default/files/local/browser/documents/
adjudicationinAsia%26Australasia.pdf> [Accessed 19 December 2016]
147
Construction Industry Development Board, 2014. 2014 Annual Report. [pdf] Kuala
Lumpur,
Malaysia:
CIDB.
Available
at:
<
http://www.cidb.gov.my/cidbv4/images/pdf/2016/FA%20CIDB%20Annual%20Rep
ort%202014_Publish.pdf> [Accessed 15 July 2016].
Construction Industry Development Board, no date. The Proposed Enactment of
Construction Industry Payment and Adjudication Act (CIPAA). [online]. Available at:
<http://www.cidb.gov.my/cidbv4/index.php?option=com_content&view=article&id=
79:cipaa&catid=35:maklumat-awam&Itemid=179&lang=en> [Accessed 20 June
2016].
Creswell, J.W., 2014. Research design: Qualitative, quantitative, and mixed methods
approaches. 4th edn. Thousand Oaks: SAGE Publications.
Cunningham, T., 2013. Will The Construction Contracts Bill Improve Subcontractor
Cash Flow? [pdf] Ireland: Dublin Institute of Technology. Available at:
<http://arrow.dit.ie/cgi/viewcontent.cgi?article=1009&context=beschreoth>
[Accessed 15 July 2016]
Dancaster, C., 2008. Construction adjudication in the United Kingdom: Past, present,
and future. Journal of Professional Issues in Engineering Education and Practice,
[e-journal] 134(2), pp. 204–208. Available through: Universiti Tunku Abdul Rahman
Library website [Accessed 20 July 2016].
Fair Trading, 2015. Adjudication in New South Wales Annual Report 2014/15. [pdf]
Available
at:
<http://www.fairtrading.nsw.gov.au/biz_res/ftweb/pdfs/Tradespeople/Adjudication_a
nnual_report_2014_2015.pdf> [Accessed 1 Jan 2017]
Gould,
N.,
no
date.
Adjudication
in
Malaysia.
[online]
Available
at:
<http://www.fenwickelliott.com/files/nick_gould_-_adjudication_in_malaysia.pdf>
[Accessed 24 June 2016].
148
Gould, N. and Linneman, C., 2008. Ten years on: Review of Adjudication in the
United Kingdom. Available through: University Tunku Abdul Rahman Library
website [Accessed 6 February 2017].
Gupta, M. and Gupta, D., 2011. Research Methodology. New Delhi: Eastern
Economy Edition.
Kennedy, P., 2008. Evolution of statutory adjudication as a form of dispute
resolution in the U.K. Construction industry. Journal of Professional Issues in
Engineering Education and Practice, [e-journal] 134(2), pp. 214–219. Available
through: University Tunku Abdul Rahman Library website [Accessed 20 July 2016].
Khan, R.A., Liew, M.S. and Ghazali, Z.B., 2014. Malaysian construction sector and
Malaysia vision 2020: Developed nation status. Procedia - Social and Behavioral
Sciences, [e-journal] 109, pp. 507–513. Available through: Universiti Tunku Abdul
Rahman Library website [Accessed 20 July 2016].
Kothari, C.R., 2009. Research methodology: Methods and techniques. 2nd edn. New
Delhi: New Age International (P) Ltd., Publishers.
Kuala Lumpur Regional Center for Arbitration, 2016. CIPAA Conference Gaining
Strength
2016.
Available
at:
<http://klrca.org/wp-
content/uploads/2016/05/ConferenceBooklet-18th-May.pdf> [Accessed 25 June
2016].
Kuala Lumpur Regional Center for Arbitration, 2016. Construction Industry Payment
and Adjudication Act 2012. Available at: <http://klrca.org/cipaa/> [Accessed 8 July
2016].
Kumar, R., 2011. Research methodology: A step-by-step guide for beginners. 3rd edn.
United Kingdom: SAGE Publications.
Laerd, n.d.. Descriptive and Inferential Statistics. [online] Available at: <
https://statistics.laerd.com/statistical-guides/descriptive-inferential-statistics.php>
[Accessed 1 April 2017].
149
Lim, J. M., Leong, J., and Ng, C. C., 2010. Building and Construction Industry
Security of Payment (SOP) Act. Available at:
<http://www.bca.gov.sg/SecurityPayment/others/SOP_briefing_slides.pdf>
[Accessed 27 November 2016].
Milligan, J.L. and Cattanach, L.H., 2014. Report No.13. [pdf] Glasgow Business
Park:
Construction
Dispute
Resolution.
Available
at:
<http://www.cdr.uk.com/documents/FINALREPORT13.pdf> [Accessed 8 July 2016]
Milligan, J.L. and Cattanach, L.H., 2016. Report No.15. [pdf] Glasgow Business
Park:
Construction
Dispute
Resolution.
Available
at:
<https://www.adjudication.org/sites/default/files/Report%2015.pdf> [Accessed 12
February 2016]
Naoum, S.G., 2013. Dissertation research and writing for construction students. 3rd
edn. New York: Routledge.
Royal Institution of Chartered Surveyor, 2015. The extent and impact of intimidation
in UK statutory adjudication. [pdf] Sydney, Australia: RICS. Available at:
<https://www.adjudication.org/sites/default/files/The%20Extent%20and%20Impact
%20of%20Intimidation%20in%20UK%20Statutory%20Adjudication.pdf>
[Accessed 13 February 2017].
Seah, C.M., 2013. Security of Payment Act – Bane or Boon? A Langdon & Seah
Consultancy
Information
Sheet,
13(2).
[online]
Available
at:
<http://studylib.net/doc/8182524/security-of-payment-act-%E2%80%93-bane-orboon%3F> [Accessed 20 February 2017].
Social Research Methods, n.d.. Research methods knowledge base. [online]
Available at: < https://www.socialresearchmethods.net/kb/statdesc.php> [Accessed 1
April 2017].
Tan, T.H., 2011. Sustainability and housing provision in Malaysia. Journal of
Strategic Innovation and Sustainability, Vol. 7 No. 1, pp. 62-71.
150
Walker, I and Wilkie, R, 2002. Commercial Management in Construction, Blackwell
Science, Oxford.
Teo, J.P., 2008. Adjudication: Singapore Perspective. Journal of Professional Issues
in
Engineering
Education
and
Practice,
134(2),
pp.
224–230.
doi:
10.1061/(asce)1052-3928(2008)134:2(224). Available through: Universiti Tunku
Abdul Rahman Library website [Accessed 7 January 2017].
Uher, T.E. and Brand, M.C., 2005. Analysis of adjudication determinations made
under security of payment legislation in New South Wales. International Journal of
Project Management, 23(6), pp. 474–482. doi: 10.1016/j.ijproman.2005.05.002.
Available through: Universiti Tunku Abdul Rahman Library website [Accessed 15
December 2017]
151
APPENDICES
APPENDIX A: Questionnaire
Dear valued respondent(s),
I am a final year student pursuing Bachelor of Science (Hons) Quantity Surveying at
Lee Kong Chian Faculty of Engineering & Science, Sg Long Campus, University
Tunku Abdul Rahman, Malaysia. For my final year project, I am conducting a
research on “A Study of The Effectiveness of The Malaysian CIPAA Act vis-à-vis
The Impact of Oversea Construction Payment Legislations on Their Respective
Construction Industries”. This research paper is under the supervision of Sr. Chang
Khong Thong.
This questionnaire consists of three sections:
Section A: Respondent's particulars.
Section B: Survey on the application of CIPAA.
Section C: Suggestion on improvement that can be made.
Your kind assistance is absolutely vital to the success of this study. I shall be grateful
if you could spare about 10 to 15 minutes of your valuable time in filling up the
questionnaire.
I assure you that the information collected from you will be kept confidential and
used only for my research work. If you have any queries or comments regarding this
survey or interested in knowing the findings, please do not hesitate to contact the
undersigned at 017-4858521 or lzcheang@hotmail.com.
Thank you for your cooperation.
152
Section A – Respondent’s Particular
1. Role in construction industry
□ QS Firm
□ Main Contractor
□ Sub-contractor
□ Supplier
2. Years of involvement in construction industry
□ 0-5 years
□ 6-10 years
□ 11-20 years
□ More than 20 years
3. No of times involved in CIPAA matters, be it as a claimant or a respondent
□ 0
□ 1-5
□ 6-10
□ 11-15
□ 16-20
□ More than 20 times
1.
2.
3.
4.
5.
6.
7.
Since the introduction of CIPAA, payment
systems have changed to meet the new
requirements and cash flow is smoother than
ever.
Conditional payment is eradicated after CIPAA
is introduced.
Adjudication’s inquisitional role plays an
important role in ensuring successful resolved of
disputes.
CIPAA is a reliable dispute resolution
mechanism.
The adjudicator empaneled by KLRCA is
knowledgeable enough.
Adjudication is a relatively speedy process
compared to arbitration or litigation.
The cost of adjudication is relatively low
compared to arbitration or litigation.
disagree
Strongly
Disagree
Neutral
Agree
Statement
Strongly agree
Section B - Survey on the application of CIPAA
153
Section C – Suggestion on improvement that can be made.
1.
“Dispute resolution provided under CIPAA is fast enough.” Do you agree
with this statement? If your answer is no, then proceed to question 2.
Otherwise, just skip question 2.
A. Yes
B. No
2. Which part of the adjudication, in your opinion, should be shortened? You
may tick as many as you think relevant.
□ Initiation of adjudication where non-paying party responds to payment
claim
□ Appointment of adjudicator
□ Adjudication proceedings
3. How do you find adjudication reply? Do you think it is fair to have
adjudication reply with no further ground for respondent to response to that
reply?
A. Yes, it is fair
B. No, it is not fair but it is alright as it is part of the price to be paid in
exchange for speed
C. No, there should be another reply to that reply
4. In New South Wales, all types of construction contracts, be it written, oral or
partly written and partly oral are subjected to the Act. However, CIPAA is
only applicable to written construction contracts. Do you think CIPAA should
extend its reach to cover it all?
A. Yes
B. No
5. In UK, Ireland and Malaysia, adjudicators are given the power to award
adjudication cost. Do you think this will discourage the application of
adjudication, particularly to small and medium-sized company?
A. Yes
B. No
6. In other countries, the time frame allowed in similar legislations are much
shorter compared to CIPAA to facilitate faster cash flow. How do you think?
This question differs from question 1 in the sense that it requires you to think
relatively (as compared to other similar legislations).
A. Good enough
B. Shorten further
154
7. There are cases where breach of natural justice and jurisdiction problems of an
adjudicator rendered the adjudication results not enforceable. Will you think
these kind of situation affect the effectiveness of CIPAA and make you to
reconsider to pursue under CIPAA?
A. Yes
B. No
8. If you have not received payment after adjudication determination is served in
your favor, what remedy would you choose? Please rank the choice from
1(first choice) to 3(third choice).
□ Suspend the works
□ Slow down the works
□ Secure direct payment from principal
9. Upon the application of adjudication in Singapore, numerous improvements
have been felt. Do you think there is any improvement in Malaysia as in
Singapore? You may tick as many as you think relevant.
□ Timeliness in paying
□ Greater certainty in obtaining payment
□ Greater willingness of main contractors to seek amicable settlement with
sub- contractors to avoid adjudication
10. In Singapore, there is an adjudication review available. Would you suggest
CIPAA to follow suit?
A. Yes
B. No
11. How would you rate effectiveness of CIPAA [from 1(lowest) to 5(highest)]?
A. 1
B. 2
C. 3
D. 4
E. 5
END OF QUESTIONNAIRE