4
Repair and
Maintenance of Power
Distribution Lines
INTRODUCTION
Repair and maintenance of lines is very important for
uninterrupted supply of electricity. Maintenance is
done primarily twice a year, once before monsoon and
the next is done after monsoon to see if any breakdown
has occurred in the line. Line patrolling, maintaining
ground clearance, replacement of insulators, restringing
of lines, replacement of burnt jumpers, replacement of
damaged conductor, replacement of damaged pole, etc.
are some of the cheeks performed during maintenance.
Proper maintenance of line improves its life drastically.
SESSION 1: PREPARATION FOR REPAIR AND
MAINTENANCE OF POWER DISTRIBUTION LINES
Materials and Accessories used in Power
Distribution
In this section, we will discuss some materials and
accessories used in power distribution.
Poles (Supports)
The poles or supports are classified according to the
material used for it:
y Steel
y Cement
y Wood
Unit-4 .indd 63
11-06-2019 16:20:54
Fig. 4.1 Tubular Poles
Fig. 4.2 RCC Poles
Fig. 4.3 PSC Poles
Steel poles are further classified as follows
Rail Poles: These can be of L shape, rail type
and tubular shape. They are better than R.C.C.
poles, light in weight and cheaper in cost. The
poles are affected by atmospheric moisture,
rains, etc. Hence they are always painted or
coated with chemicals to avoid rusting. These
are normally used for 33kV lines.
Tubular Poles: Tubular poles are either of
swaged section (built up sections) or stripped
single unit type (jointless one casting). The
action of wind pressure is very low because
of their circular section as compared to plain
section R.C.C. poles and can be erected easily
by digging pits of diameter or section slightly
greater than the pole’s diameter. These are
normally used in hilly areas (Fig. 4.1).
Cement poles are further classified as
follows
R.C.C. poles: These poles are made by
reinforcing (i.e. embedding) steel rods into
concrete slabs of pole shaped cylinders. These
poles are of permanent nature, have a long
life, remain unaffected by rain, sunlight, etc.
and are heavy in weight due to the presence of
concrete and steel (Fig. 4.2).
P.S.C. poles: Pre-stressed cement concrete
poles are essentially made of concrete. A
frame of high tensile steel wire is inserted
into a mould and stretched to a certain level.
Galvanised wire is used as earth wire inside
the mould. A right proportion of concrete mix
is poured in the mould and a vibrator is used
to compress the concrete to produce high
strength PSC poles (Fig. 4.3).
Wooden poles
Wooden poles are light in weight and cheap in
comparison to all other types of poles, made
up of wooden beams. These are easily affected
and spoiled by atmosphere, rain water, white
DISTRIBUTION LINEMAN — CLASS XI
64
Unit-4 .indd 64
11-06-2019 16:21:01
ants, soil moisture, etc. Therefore, they are used for
temporary work and are coated with special chemical
for permanent installations. The common impregnating
material (coating) used is Creosote. These poles are
normally used in hilly areas.
As per the CEA (Central Electricity Authority)
Regulations 2010, Relating to Safety and Electric Supply,
Clause 57(2), the supports should have the following
minimum factor of safety as given in Table 4.1.
NOTES
Table 4.1
S.
No.
Types of Supports
Factor of
Safety
1
Metal Supports
1.5
2
Mechanically processed concrete supports
2.0
3.
Hand moulded concrete supports
2.5
4.
Wooden supports
3.0
An Earthing arrangement is provided with a projected
length of 50 mm at both ends of the pole, using 8 S.W.G
G.I. wire embedded in concrete. In actual practice, it
is convenient to use 8m poles for all purposes (instead
of having different sizes) with minor adjustments in
spans, if required. This avoids future replacement
costs, omission or errors by workmen in transportation
and selecting different poles for different locations. The
selection of poles for erection of lines depends on a
number of factors such as:
y Pole strength
y Type and size of conductor
y Maximum wind pressure
y Maximum line tension
y Snowfall
y Presence of fruit farms
y Guarding
y Different crossings like river, road, railway,
telephone lines, etc.
The erection of power distribution lines involves only
erection of different types of poles, such as steel, PSC,
wooden poles, etc.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
65
Unit-4 .indd 65
11-06-2019 16:21:01
Conductors
Fig. 4.4 All Aluminium
Conductors
Fig. 4.5 Aluminium Conductor
Steel Reinforced
Fig. 4.6 All Aluminium Alloy
Conductors
Aluminium conductors of different types and sizes are
used for drawing overhead lines, whether they are LT or
HT lines. These include:
AAC – All Aluminium Conductors: This type of
conductor is made up of one or more strands of hard
drawn 1350 aluminium alloy. The AAC conductors are
used in low and high voltage overhead lines. AAC is used
extensively in urban areas where spans are usually
short but high conductivity is required (Fig. 4.4).
ACSR – Aluminium Conductor Steel Reinforced:
It is a type of high-capacity, high-strength stranded
conductor typically used in overhead power lines. The
outer strands are high-purity aluminium, chosen for
its excellent conductivity, low weight and low cost. The
centre strand is of steel for additional strength to help
support the weight of the conductor (Fig. 4.5).
Reinforced Conductors
AAAC – All Aluminium Alloy Conductors: These
conductors are made out of high strength AluminiumMagnesium-Silicon Alloy. These conductors are
designed to get better strength to weight ratio and offer
improved electrical properties, excellent sag-tension
characteristics and superior corrosion resistance when
compared with ACSR (Fig. 4.6).
Table 4.2 lists various specifications of different
types of conductors used:
7/2.21
485
73
1.071
85
2.
Ant
50
30
7/3.10
852
144
0.544
135
3.
Squirrel
20
13
6/2.211
771
85
1.394
75
1/2.11
Current carrying
capacity at 40°C
above 30°C
ambient temp.
16
Calculated Resistance at 20°C
in ohms/ km
Stranding & wire
diameter in mm
of Aluminium
(mm)
25
Weight of Cond.
kg./km
Equivalent
nominal copper
area (mm2)
Gnat
Breaking load
kg.
Code Name
1.
Nominal
Aluminium Area
(mm2)
S. No.
Stranding & wire
diameter in mm
of steel (mm)
Table 4.2 Specifications of Different Types of Conductors
DISTRIBUTION LINEMAN — CLASS XI
66
Unit-4 .indd 66
11-06-2019 16:21:08
4.
Weasel
30
20
6/2.59
1/2.59
1136
128
0.9289
102
5.
Rabbit
50
30
6/3.35
1/3.35
1850
214
0.5524
150
6.
Racoon
80
48
6/4.09
1/4.09
2746
318
0.3712
202
7.
Dog
100
65
6/4.72
1/4.72
3299
394
0.2792
250
The Gnat and Ant conductors (mentioned in S. No. 1
and 2) are generally used for LT Lines. The other types
of conductors (mentioned from S. No. 3 to 7 are all
ACSR Conductors and are commonly used on 11kv
lines, except Dog conductors. As per CEA Regulations
2010 relating to Safety and Electric Supply, Clause 7,
the minimum factor of safety for conductors have to be
based on their ultimate tensile strength.
Insulators
Pin Type Insulators: These are commonly used on
11 kV Lines. The pins for pin insulators shall have a
stalk length of 135 mm, shank-length of 125 mm and
minimum failing load of 2kN. They should be forged.
The pin type insulator is secured to the cross-arm on
the distribution pole. There is a groove on the upper end
of the insulator for resting the conductor. The conductor
passes through this groove and is bound by the annealed
wire made of the same material as the conductor. Pin
type insulators can be of one part, two parts or three
parts type, depending upon the application voltage. For
example, in 11kV system, one part type insulators are
used where the whole pin insulator is one single piece of
properly shaped porcelain or glass (Fig. 4.7).
Shackle Type Insulators: The shackle insulators are
used in low voltage distribution lines (LT lines). They
are also called spool insulators. These insulators are
used to isolate the live conductor from pole and are
mounted in every pole of electrical line. These insulators
can be mounted either in vertical or horizontal
positions (Fig. 4.8).
There are two types of shackle insulator fittings —
strap type and u-clamp type fittings. Strap type
fittings are for dead-end locations. On the other hand,
u-clamp type fittings are for tangent locations or for
service lines where the load is small. All fittings are to
be galvanised.
REPAIR
AND
MAINTENANCE
OF
Fig. 4.7 Pin Type Insulators
Fig. 4.8 Shackle Type
Insulator
POWER DISTRIBUTION LINES
67
Unit-4 .indd 67
11-06-2019 16:21:09
Fig. 4.9 Disc Type Insulators
Fig. 4.10 Guy Strain Insulator
Disc Type Insulators: In higher voltage, such as beyond
33kV, it becomes uneconomical to use pin insulator
as the size and weight of the insulator becomes more.
Handling and replacing bigger sized single unit insulator
is a difficult task. Suspension insulator was developed
to overcome these difficulties. In suspension insulator,
the number of insulators are connected in a series to
form a string and the line conductor is carried by the
bottom most insulator. Each insulator of a suspension
string is called disc insulator because of its disc-like
shape. Disc insulators are normally used in 11kV lines
for dead-end locations (Fig. 4.9).
Guy Strain Insulators: These are only used for
guy/stay wires. These are designed to work in mechanical
tension or strain, as they are capable to withstand the
pull of a suspended electrical wire or cable. The guy
strain insulators are used in overhead electrical line. The
strain insulator is inserted between stay wire to isolate
the lower portion from electricity. It may also be used
where a wire attaches to a pole or tower, to transmit
the pull of the wire to the support while insulating it
electrically (Fig. 4.10).
Pins for Insulators
Pins for pin insulators have to be of single-piece forged.
All ferrous parts should be galvanized (Fig. 4.11).
Helically formed pin insulator ties used for holding the
conductor on the pin insulator have been standardised
and should conform to the requirements of IS: 120481987. Types and dimensions of pins are as follows:
Table 4.3 Types and Dimensions of Pins
Voltage
(kV)
Fig. 4.11 11 kV GI Forged Pins
for Pin Insulators
Type
Stalk
Length
Shank
Length (mm)
Failing load
minimum kN
33
Large Steel Head
type L 300 N
300
150
10
11
Small Steel Head 165
type S 165P
150
5
Guy Assembly
Guy assembly is needed for dead-end and angular
locations to counter balance the load on the supports
DISTRIBUTION LINEMAN — CLASS XI
68
Unit-4 .indd 68
11-06-2019 16:21:11
due to pulling of the conductors, so that supports remain
straight in vertical position without bending in any
direction. They are also provided at mid-span support
as a protection against the wind load (Fig. 4.12).
G.I. Wire
G.I. wires are used for protective guarding at the crossing
of lines with roads, railway tracks, telecommunication
lines, etc. These have to be of 3.15, 4 and 5 mm sizes.
The wires shall be galvanised with “heavy coating”. G.I.
wires are used in reinforcement of aluminium conductors
in distribution and transmission of electricity. ACSR
wire is used for power fencing as this material is most
suitable for electric conduction (Fig. 4.13).
Fig. 4.12 Guy Assembly
GO Switches
Gang operated switches or GO switches, as they
are commonly called, are switching devices used in
overhead power lines. They are called Gang Operated
as they are operated in a Gang, all three switches
together, using a single mechanism. The gang operated
switches are also called Air Break Switches because air
is used as the breaking medium. These are normally
installed at the pole mounted distribution substation to
isolate the transformer from HT line, so that the HT fuse
replacement could be carried out for the restoration of
supply. The GO switches are used in electrical lines
with voltage of 5 kV. They can be mounted vertically or
horizontally, and can be motorised and operated from a
remote location.
Fig. 4.13 G.I. Wires
11kV Cross-arms
The following types of cross-arms are used for 11kV
Lines:
y V cross-arms for tangent locations with clamps
are widely used in many electrical transmission
lines, for effective and efficient distribution of
power. They have the capacity to bear heavy
electrical fluctuations and voltages (Fig. 4.14).
y Double-channel cross-arm for tension or cut point
locations where D.Ps. are used. The conductors
REPAIR
AND
MAINTENANCE
OF
Fig. 4.14 V Type
Cross-arms
POWER DISTRIBUTION LINES
69
Unit-4 .indd 69
11-06-2019 16:21:15
for the double cross-arm configurations are
suspended from an adjustable tie plate which
connects the two timber cross-arm members
together. The cross-arm can be used to support
up to three conductors, one mounted at the centre
and one mounted one foot from either end of the
cross-arm (Fig. 4.15).
Fig. 4.15 Double-channel Cross-arms
90
65
65
Fig. 4.16 L.T. Cross-arms
y L.T. cross-arms have been standardised for
horizontal as well as vertical formation of
conductor. They have a strong structure and
high sensitivity (Fig. 4.16).
10
L.T. Line Spacers
13
250
Fig. 4.17 Line Spacers
300
Clashing of L.T. conductors in the mid-span very
often takes place due to sag, wind and longer spans
(Fig. 4.17). This results in faults and interruptions.
In order to overcome this problem spacers are
provided. As per REC Construction Standards two
types of spacers are generally used:
y Spiral - made from high quality PVC. They
should be circular with 13 mm diameter.
y Composite - made
from poly-propylene
in a single mould
(except the clamping
pieces). They should
be rectangular strips
of 25 mm × 12 mm
Fig. 4.18 Vertical Line Spacers
dimensions.
DISTRIBUTION LINEMAN — CLASS XI
70
Unit-4 .indd 70
11-06-2019 16:21:17
Tools to be used for distribution line
maintenance
Name
Screwdriver
Function
NOTES
Image
Used to turn, tighten
or remove screws
Screwdriver
Wrenches
Used to allow
rotary motion in
only one direction
and preventing the
motion in opposite
direction,
Used to tighten nuts
of various sizes
Spanner
Used to provide grip
to apply torque for
turning objects such
as nut or a bolt.
A spanner with
variable diameter
to tighten nuts and
bolt of various sizes
Spanner (Top) and
wrench (Bottom)
Survey and Right of Way (ROW)
Survey of the Proposed Route of Line
Initial survey should be carried out for construction of
new lines. During line survey various type of crossings
i.e. highway crossing, railway, river, telephone lines,
E.H.V. lines etc. are to be taken into account. It should
be seen that telephone line should not be parallel to
power line for excessive length. The induction effect
on telephone line will cause disturbance to telephone
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
71
Unit-4 .indd 71
11-06-2019 16:21:19
NOTES
communication and even damage equipment. It is
necessary to obtain the approval of P and T Department
(B.S.N.L.) for route of lines with voltages of 33 KV
and above.
Any crossing should be at right angle i.e. 90 degrees,
which enables to keep a short span and safe clearance.
If possible, highway and railway crossings should be
avoided. Railway authority gives permission for overhead
crossing only for E.H.V. Lines. Low and medium voltage
lines are to be crossed with underground cables.
Before finalising the route, the following parameters
should be kept in mind
1. The shortest route possible.
2. As close as possible to the road for easy
maintenance
and
approach
during
the
construction.
3. Route should be in the direction of possible
future load.
4. Angle points should be less.
The areas to be avoided as far as possible are
(a) Rough and difficult country side
(b) Urban development area
(c) Restricted access for transport vehicles
(d) Abrupt changes in line routes
(e) Difficult crossing — river, railway lines
(f) Proximity to aerodromes
(g) Natural hazards like steep valleys, hills, lakes,
gardens, forests, playgrounds, etc.
The route selected for a distribution line shall be
such that it will give the lowest cost considered over
a period of years, consistent with accessibility for easy
maintenance, etc. This includes many considerations
such as original cost, tree trimming and compensation,
freedom from vehicular damages, future development
and availability for services. Transportation contributes
to a major portion of construction cost. Hence while
finalising the route alignment, it should be ensured that
transportation cost should be as low as possible.
Transport of RCC/PSC poles pose greater problems
as they are generally heavier than other types of
DISTRIBUTION LINEMAN — CLASS XI
72
Unit-4 .indd 72
11-06-2019 16:21:19
supports for the same purpose. The RCC/ PSC poles
are generally stronger on the longer axis than on the
shorter axis. Care should be taken on this aspect while
handling, to prevent excessive stressing of the pole at
the time of transporting. The unloading of poles from
truck or trailer should also be done carefully. Suitable
skid boards must be used and on no account, the
poles should be dropped. Several utilities have special
trucks made with side loading arrangements for pole
transportation or trailers should be used. It is preferable
to provide a chain pulley block with a beam arrangement
in the middle of the truck body to facilitate unloading/
loading of poles. The poles should not be dragged on a
rough surface, but transported in small hand-cart.
NOTES
Detailed Survey
The survey of the overhead lines can be broadly divided
into two heads:
(a) Preliminary ‘Walk Over’ survey
(b) Detailed survey
Having provisionally fixed the route, on the survey
map, a preliminary ‘Walk Over’ survey is carried out,
before conducting the survey with ranging rods. As far
as possible, the line route is taken through areas with
minimum tree growth. If there are alternative routes, all
such routes are investigated for final evaluation of the
most economic route.
Detailed survey can be carried out by the theodolite
and angle points can be fixed and marked with survey
stones. A route map to a scale of 1cm=0.5km can be
prepared showing the various angles, approach roads,
near the line, routes detail of railways, communication
lines, EHT line crossing, river crossing, etc. But this is
not necessary in case of small lines as the local staff
usually is conversant with the topography and therefore
marking of locations aligning the line with ranging rods
is found to be satisfactory.
Right of Way
(a) Once the route of the line is fixed approval has to
be obtained,
(i) from the railway authorities for railway
crossings,
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
73
Unit-4 .indd 73
11-06-2019 16:21:20
NOTES
(ii) from the competent forest authorities for
routing of the line in forest areas, and
(iii) from the state level Power Tele-communication
Coordination Committee (PTCC).
(b) In addition if urban development, airport
and similar other areas fall in the route of the
line, permission has to be obtained from those
departments.
(c) Sometimes private gardens/orchards may fall on
the route and require tree cutting. The details of
trees are to be marked. Compensation is fixed by
revenue authorities and paid to the owner.
Pole Locations
While locating poles on lines, the following general
principles are to be kept in mind:
1. Keep spans uniform in length as far as possible.
2. Locate to have horizontal grade.
3. By locating the poles on high places short poles
can be used and will maintain proper ground
clearance at the middle of the span. In extremely
hilly or mountainous areas, poles are located
on ridges thereby increasing the spans without
greatly increasing the pull on the conductor. This
is possible because the sag can be made very large
by maintaining the required ground clearance.
4. Poles should not be placed along the edges of cuts
or embankment or along the banks of creeks or
streams.
5. Cut-point for a section could be at a length of 1.6
km (except in special cases), where double-pole
structures should be provided to take tension
of the conductors. It may have been already
estimated that 10 supports (locations) are mostly
required for one km length of H.T. line and 15
supports for L.T. line.
Work permit
Rules regarding work permit and important notices/
information:
DISTRIBUTION LINEMAN — CLASS XI
74
Unit-4 .indd 74
11-06-2019 16:21:20
y Unless line-clear permit is issued by an authorised
person, the worker should not climb on pole or
apparatus. No one should go in the vicinity of
bare conductor and work.
y Only shift engineer or operation in-charge is
authorised to issue permit.
y The line-clear permit should only be issued to a
person duly authorised for said work.
y The only competent authority to authorise a
worker is the executive engineer of that division
or superintending engineer. They should issue
authorisation order in writing.
y The permit can only be issued or obtained by those
authorised persons for the work and jurisdiction
as prescribed in the written authorisation order
by the competent authority.
y The written order by the competent authority
should invariably be displayed on the notice
board at the concerned sub-station, power house
and distribution centres in a specific format.
y The consolidated authorisation should be kept at
the office of the concerned superintending engineer.
y The superintending engineer (SE) or chief engineer
(CE) of Circle/Zone can authorise persons other
than stated above such as E.E. (Testing) or testing
staff (or any other person who is competent to
work in the views of concerned SE/CE).
y The area authority should include the names of
such authorised persons in their list. The area
officer should obtain the list of authorised persons
of bulk consumers and area in the vicinity and
also handover his list to them.
y Generally, the line inspector or persons of
equivalent post are authorised for working on H.T.
line/installations. However, division engineer
may authorise the person/persons of lower rank,
if he is confident about his skills.
NOTES
Methods for issuing or obtaining and returning the permit:
y For obtaining line-clear permit, only an
authorised person should apply. He should apply
for line clear permit to the authorised person
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
75
Unit-4 .indd 75
11-06-2019 16:21:20
NOTES
y
y
y
y
y
only and such authority will issue the permit
accordingly.
Where it is not possible to obtain permit in writing
then permit can be obtained on telephone. In such
a case, the permit obtaining authority should
confirm by repeating the matter with permit
issuing authority over phone. The same should be
noted in the permit book by both the persons. The
duplicate copy of line clear permit after cancellation
shall be sent to each other by post or in person as
early as possible for record. This register should
be inspected by area or divisional Officer from time
to time.
The permit book is an important record and should
be preserved properly. The pages of permit book
should be numbered serially. Pages from this
book should not be taken out or torn or used for
any other work. In case any page is torn or taken
out by some person due to any reason, then the
concerned person should sign on the same and
make dated entry in the logbook of sub-station/
power house with signature.
The person, who has taken the permit, should
return it. In case where the permit issuing and
obtaining authority is same, the self-permit
should be taken in his name and cancelled after
completion of work. This procedure should be
followed strictly.
In case the permit is taken in person, same can
be returned on phone.
While issuing or returning permit on phone, the
code words should be used.
Precautions to be taken while issuing permit:
It is the duty of the shift engineer or person issuing
the line clear permit to ensure that the sub-station/
feeder/equipment for which the permit is being issued,
should be made dead, i.e., equipment/ feeder should
be discharged and properly earthed. First, he should
switch off the equipment/feeder as per the instructions
laid down. Thereafter, he should adhere to the following
instructions regarding grounding and locking of
equipment:
DISTRIBUTION LINEMAN — CLASS XI
76
Unit-4 .indd 76
11-06-2019 16:21:20
y Power T/F should be opened (off position) and
locked, at S/stn, respectively.
y Warning boards with following instructions should
be tagged on handles of isolators/breakers:
– Do not charge. Workers are working.
– The line/equipment under permit - Don’t charge.
– Attention - work in progress - Do not charge
the line/equipment.
y The same type of warning boards should be tagged
on handles of control switchgear. The control
circuit fuse of control panel should also be taken
out and kept in the custody of the permit issuing
authority.
NOTES
Duties and Responsibilities of a Distribution
Lineman
When the lineman is entrusted with the responsibility of
construction (erection of lines, distribution substation,
UG/AB cables):
y He shall be responsible for surveying HT lines and
LT lines and report to his superiors any variation
from the original estimates.
y He shall be responsible for executing the
distribution lines and erecting transformers,
underground and AB cables as per technical
standards.
y He shall be responsible for all T and P issued for
execution of work.
y He shall maintain the time rolls and mark the
attendance regularly.
y He shall maintain a register showing the
allocation of work every day and also write in the
same register the progress of work against the
allocation.
y He shall prepare pole schedules, after completing
the work and handover the same to his superiors.
In case he is put in charge of contract work, he shall be
responsible for proper supervision of work and see that
the work is executed as per standards. Materials issued
to the contractor shall properly be accounted:
y He shall maintain a dairy showing the day to day
work done in detail and take the signatures of his
next superiors once in a fortnight.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
77
Unit-4 .indd 77
11-06-2019 16:21:20
NOTES
y He shall be responsible to ensure that the code
of safety rules is followed by him and the staff
working under him. A copy of the said code is
already supplied to him. Any instances where the
staff fails to use safety appliances as per the code
shall be brought to the notice of his superiors
immediately for taking disciplinary action.
y He shall be responsible for upkeep of T and P and
safety appliances supplied to him and keep them
in working order.
The lineman is entrusted with O and M (operation and
maintenance) activities (lines, distribution substation
and UG/AB cables):
y To restore power supply in an area as quickly
as possible or make arrangements for alternate
power supply till power is restored.
y To maintain LT, HT (Low tension, High tension)
lines and equipment under his charge as per the
schedule fixed up, as well as continuity of supply.
y To report any interruption beyond one hour on LT
lines and restoring supply.
y To rectify HT and LT lines by following instructions
from superiors for such rectification.
y To maintain distribution transformers/substations
in his area of jurisdiction covering oil testing,
checking of condition of breather, GO Switch
operation, HT Fuses and LT side protection, earthing
of transformer body, neutral, etc.
y To attend breakdown of HT and LT Lines in a time
bound manner as per performance standards set
by the State Electricity Regulatory Commission.
y To replace damaged transformers in a time bound
manner as per performance standards set by the
State Electricity Regulatory Commission.
y To make proper gradation of fuse in services and
all other places where fuses are used.
y To maintain a register showing the allocation of
work every day and also record the progress of
work against the allocation.
y To supervise work under contract and see that
all maintenance work is carried out as per
maintenance schedule and as per standards.
y To follow the code of safety rules and encourage
the staff working under him to do the same.
y To ensure security of T and P and safety appliances
supplied to him and keep them in working order.
DISTRIBUTION LINEMAN — CLASS XI
78
Unit-4 .indd 78
11-06-2019 16:21:20
NOTES
Check Your Progress
A. Fill in the blanks
1. Rail poles are ______________ than RCC pole.
2. RCC poles are made by ______________ steel rods into
concrete slabs of pole-shaped cylinders.
3. Pin-type insulation are commonly used on ______________
lines.
4. LT cross arms have been standardised for horizontal as
well as ______________ formation of conductors.
B. Multiple choice questions
1. Identify which is not a cement pole:
(a) RCC pole
(b) PSC pole
(c) Wooden pole
(d) Rail pole
2. Pin-type insulators are commonly used on:
(a) 11 KV line
(b) 33 KV line
(c) 15 KV line
(d) None of these
3. GO switches are used as:
(a) Switching devices
(b) Cutout devices
(c) Controlling switches
(d) None of these
4. LT line spacers are provided:
(a) To keep distance between wires
(b) For holding wires
(c) For tying of wires
(d) None of these
C. Match the columns
Group A
Group B
1. Distribution Lineman (a) recruitment of various roles
2. Electricity Act 2003
(b) concerned with grievances
3. DISCOM
(c) construct LT, HT lines
4. Escalation Matrix
(d) allows multiple licensing in
distribution
D. Short answer questions
1.
2.
3.
4.
REPAIR
Why RCC poles are more preferred in erction of lines?
List the factors responsible for selection of poles.
Discuss the role of conductors and their types.
What is the role of Guy strain insulators?
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
79
Unit-4 .indd 79
11-06-2019 16:21:20
SESSION 2: SPECIFIC TERMINOLOGY
DISTRIBUTION LINE
IN
Low Tension (LT) Line and High Tension
(HT) Line
A low-tension line is a low voltage line and a hightension line is a high voltage line. In India LT
supply is of 400 Volts for three-phase connection
and of 230 Volts for single-phase connection. High
tension or HT supply is applicable for bulk power
purchasers who need 11 kilo-Volts or above.
Overhead Line
Fig. 4.19 Pole
Overhead line means any electric supply line
which is placed above ground and in the
open air.
HT and LT lines upto 33 kV are erected on
poles (Fig. 4.19). Extra High Volt i.e., EHV lines
of 66,132, 220 and 440 kV are erected on towers
(Fig. 4.20).
Peak Demand
Fig. 4.20 Tower
It is the maximum load/demand which is
recorded during the peak hours representing
the simultaneous maximum demand of all the
consumers at a particular point. It can be annual
peak load, monthly peak load, weekly peak load
and daily peak load etc. Peak load for a state is recorded
by state load dispatch centre. For different categories of
consumer peak/maximum demand will be recorded by
the consumer energy installed at their premises.
Load Shedding
Load shedding is normally carried out when the power
demand is more than the power availability at a given
point of time to shed excess load on the generating
stations. Load shedding is carried out on priority basis.
Emergency services such as hospitals, fire services,
important government office etc. are left out and load
shedding is carried out phase by phase. Thus the
switching ‘OFF’ of particular feeder (circuit breaker) to
avoid total breakdown due to overload is called shedding.
DISTRIBUTION LINEMAN — CLASS XI
80
Unit-4 .indd 80
11-06-2019 16:21:22
Power system
NOTES
The production of electricity and transmission and
distribution in our houses, factory or piece of work
involves a long process, which consists of operation of
power machines and system network. The whole process
is referred as the ‘Power System” (Fig. 4.21).
Power system can be divided into three broad
sections: generations, transmission and distribution
and utilisation.
Power generation
Generation of power is done through various sources
like thermal, hydro, non conventional as well as nuclear
power station.
In thermal power station use of coal, gas and diesel
is made for generation of power.
Similarly through hydro power station use of water
as well as tidal energy is used for generation of power.
Non conventional energy uses solar, wind, bio fuel as
well as agricultural waste.
Nuclear power station uses nuclear energy to
generate power.
Transmission
Transmission system is used for transmitting the power
for long distances and it consists of transmission lines
and substation at extra high voltage and high voltage.
In transmission system, two substations are connected
at the same voltage.
In transmission, substation consists of transformers,
bus bars, circuit breakers, isolators, protection and
communication equipments and a control room.
Power Distribution System
Power distribution involves distribution of power received
at HV substations to consumers through distribution
system which operates at voltages at 33 KV and below.
A distribution system consists of electrical sub stations,
distribution transformers and distribution lines.
A distribution substation is located near or inside
city/town/village/industrial area. It receives power
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
81
Unit-4 .indd 81
11-06-2019 16:21:22
Fig. 4.21 Power distribution System
Fig. 4.22 HT Line
from a transmission network. The high voltage from the
transmission line is then stepped down by a step-down
transformer to the primary distribution level voltage.
y Primary distribution system: It connects the
transmission system with secondary distribution
network, at 33 kV or 11 kV voltage levels and form
the backbone of the distribution system.
y Secondary distribution system: Supplies power to
consumers at voltages of 415 volts and/ or 240
volts and constitutes the first contact of utility
authorities with the consumers.
y Distribution lines: These include overhead lines
and/or cables. The lines in rural areas are mostly
radial in nature. The lines in city areas are mostly
mesh-like networks often called 'ring mains',
which are used to increase the reliability of supply
and to meet the high density of loads (Fig. 4.22).
Utilisation refers to the process through which the
electricity is put to different uses such as:
y Power for industrial units
y Power for different kinds of household appliances
and gadgets
y Power for communication and electrical traction
y Use in medical equipment, electrolysis, etc.
We can say that the voltage of a local transmission
line is 13,800 volts. This voltage is then lowered even
DISTRIBUTION LINEMAN — CLASS XI
82
Unit-4 .indd 82
11-06-2019 16:21:27
further between 220 and 440 volts for industrial
use and from 120 to 240 volts for commercial and
residential customers.
NOTES
Difference between Transmission and
Distribution Line
Transmission line helps in the movement of electricity
from a power plant or power station to the various
substations whereas the distribution line carries
electricity from the substation to the consumer's end.
In electric power distribution, a service drop is
an overhead electrical line running from a utility
pole, to a customer's building or other premises. It
is the point where electric utilities provide power to
their customers.
Common safety warnings
Power lines are not insulated and one should always
avoid contact with them. It is quite possible for people
to get electrocuted if you touch power lines.
The strongest magnetic fields are usually emitted
from high voltage transmission lines — the power lines
on the big, tall metal towers. To be sure that you are
reducing the exposure levels to 0.5 milli gauss (mG) or
less, a safety distance of 700 feet may be needed. It
could be much less, but sometimes more.
Power lines produce low-to mid-frequency magnetic
fields (EMFs). These types of EMFs are in the nonionizing radiation part of the electromagnetic spectrum,
and are not known to damage DNA or cells directly,
according to the National Cancer Institute.
Is there a safe living distance from power lines?
Hundreds of studies worldwide have shown that living
next to high voltage power lines and other parts of the
power transmission network increases your risk of
cancer and other health problems. The closer you are
the more you are bombarded with dangerous EMFs.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
83
Unit-4 .indd 83
11-06-2019 16:21:27
NOTES
Check your progress
A. Fill in the blanks
1. ____________means any electric supply line which is
placed above ground line and in the open air.
2. HT and LT lines upto __________33 kV are erected on
poles.
3. The voltage of a local transmission line is ___________
volts.
4. Transmission system is used for ____________the power
for long distances.
B. Multiple Choice Question
1. Generation of power is done through various sources
(a) Thermal,
(b) Hydro,
(c) Non conventional as well as nuclear power station
(d) All the above
2. Extra High Volt i.e., EHV lines of ____________ kV are
erected on towers.
(a) 66
(b) 32,
(c) 220 and 440
(d) All the above
3. The strongest magnetic fields are usually emitted from
high voltage transmission lines are __________milli
gauss
(a) 02
(b) 03
(c) 04
(d) 05
4. It is the ____________ load/demand which is recorded
during the peak hours
(a) Minimum
(b) Maximum
(c) Average
(d) None of these
C. Short Answer questions
1.
2.
3.
4.
Differentiate between high and low tension line.
Define peak demand.
Discuss the importance of power distribution system.
Why house should not be made near high transmission
line.
5. Differentiate between transmission and distribution
line.
DISTRIBUTION LINEMAN — CLASS XI
84
Unit-4 .indd 84
11-06-2019 16:21:27
SESSION 3: CONSTRUCTION ACTIVITIES
NOTES
Construction
The construction activity of H.T. lines is divided into
the following:
1. Pit marking, pit digging
2. Erection of supports and concreting
3. Providing of guys to supports
4. Mounting cross-arms, pin and insulators, and
pin binding
5. Paying and stringing of the conductor
6. Jointing of conductors
7. Sagging and tensioning of conductors
8. Crossings
9. Guarding
10. Earthings
11. Testing and commissioning
Pit Marking and Digging Procedure
After surveying, the pole location should be marked
with the peg. The pits should not be too large than
necessary, as otherwise, after erection of the pole and
filing there remains a possibility of tilting of the pole.
For marking the pits, the dimensions of the pit and
the distance from centre of the pits are required. Pits
having a dimension of about 1.2m x 0.6m should be
excavated with its longer axis in the direction of the
line. The planting depth should be about 1/6 length of
the support (1500 mm). Excavation is generally done by
using pickaxe crow bars and shovel. Very hard or rocky
soil may require blasting of rock by small charges of
gun powder, etc.
Erection of Poles and Concreting
After
excavation
of
pits
is
completed,
the
supports/poles to be erected are brought to the pit
location by manual labour or by cart. Then the pole
is erected inside the pit. Erection of poles can be done
by using bipod/wooden horse made of 15 cm G.I. pipe
and 6m long. The distance between the legs should be
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
85
Unit-4 .indd 85
11-06-2019 16:21:27
10 m. The tie wire for attachment of bipod to
the pole is about 6 m long and is made of 7/10
SWG (3.15mm) stay wire and this wire should
be attached to the pole at 8m. The pole is slid
along the line route. The pole is tied with three
ropes. The rope at the bottom prevents the
pole from dragging in the direction of the pull.
To prevent the support from the moving side
from rising, two guy ropes are fixed on both
sides and attached to a temporary anchor. For
Fig. 4.23 Erection of pole
smooth sliding and prefect placement of pole in
the pit, an inclined trench having 15.2 cm (6 in) width
and 10.2 cm (4 in) length may be dug adjacent to the pit
as shown in fig 4.23. A piece of M.S. channel is placed
in an inclined position at the opposite end of the pit for
enabling the pole to slip smoothly inside it. The trench
would facilitate the pole to skid smoothly into the pit
with jerks. The bipod is placed in position and attached
to the pole by means of tie wire. The rope pulley is used
to pull for lifting the poles. When the pole has reached at
an angle of (35° to 40°) the derrick and bottom holding
rope is slowly released. When the pole assumes the
vertical position, the holding ropes should be tightened.
It should be ensured that during the time of erection,
the two men shifting the bipod while raising the pole
when it is free at a 40 degree angle, will also join the
other two men who are holding the rope. The supervisor
should be at a distance, guiding correct position so that
in the event of breaking of rope, if the pole falls, it will
not cause an accident.
Before the pole is put into RCC, padding or
alternatively suitable base plate may be given below the
pole to increase the surface contact between the pole
and the soil. The padding will distribute the density of
the pressure due to weight of the pole on the soil. After
lifting the pole it should be kept in a vertical position
with the help of manila rope of 20/25 diameter, using
the rope as a temporary anchor. The alignment of the
poles should be checked and set right by visual check.
The verticality of the poles are to be checked with a
spirit level. After the pole erection has been completed,
DISTRIBUTION LINEMAN — CLASS XI
86
Unit-4 .indd 86
11-06-2019 16:21:27
and confirming that the verticality and alignments are
all right, earth filling and ramming should be done
(Fig.4.23).
In swamp and special locations, before earth filling,
the poles are to be concreted up to the ground level of
the pit. After poles have been set, the temporary anchors
should be removed.
NOTES
Erection of Double pole (DP) Structure for Angle
Locations
Double pole structures are required in all the angle
locations as well as in the tangent locations. DP is
erected at a distance of every one kilometre as line DP.
For angles of deviations more than 10°, DP structure
should be erected. The pit digging should be done along
the bisection of angle of deviation.
After the poles are erected, the horizontal/cross
bracing should be fitted and the supports should be
held in a vertical position with the help of temporary
guys of Manila rope 20/25 mm diameter. Ensuring that
the poles are held in vertical position (by spirit level) the
concreting of poles with 1:3:6 ratio may be done from
bottom of the pole to the ground level. Before lifting the
pole in the pit, concrete padding of not less than 75
mm thickness may be put up for the distribution of the
loads of the support on the soil or anchor plate should
be used.
Concreting
The concreting mixture 1:3:6 ratios would mean 13 bags
of cement 100 cft of stone and 50 cft of sand. It may be
noted that while preparing the concrete mixture large
quantities of water should not be used as this would
wash away cement and sand.
Table 4.4 General proportions of Concrete Mixer
Material
Proportion
1:3:6
Proportion
1:2:4
Proportion
1:4:8
1.
1×1/4 Stone Metal
100 cft
100 cft
100 cft
2.
Sand
50 cft
50 cft
50 cft
3.
Cement
13 bags
20 bags
10 bags
4.
Water
484 ltr
484 ltr
484 ltr
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
87
Unit-4 .indd 87
11-06-2019 16:21:28
NOTES
11 kV Line
Normally 10 poles are erected within 1 km distance
(average span length 100-105m).
Stays
After the pole erection is over, guying or putting stays
is carried out. The following are different types of stays
used in distribution lines (Fig.4.24).
1. Ordinary Stay
2. ‘A’ Type
3. Self Stay (“B” type)
4. ‘Y’ stay
5. Flying stay
6. Strut
7. Storm guys
Ordinary Stay: This type of stay is generally used. The
size of stay rod, turn buckle and stay wires are to be
used as per the line tension. Generally, for H.T. lines of
19 mm (3/4”) diameter stay rod, 20 mm (5/6”) size eye
bolt, and 7/8 size stay wire are used and for L.T. lines of
15 mm (5/6”) stay rod, 12.5 mm (½”) eyebolt and 7/10
size stay wire are used. Stay insulator shall be used at
a vertical height of 3 meter (10”) from the ground.
‘A’ Type Stay: When the line tension is less and there is
no sufficient space for stay, this type of stay is used. In
cities, many times, there is no sufficient space for stay.
At such places, the stay pit is dug at a short distance
from the pole and hence cannot take adequate tension.
A support angle is fixed to the pole. Arrangement is
available to affix the stay wire to the angle. This is
called “Stay out trigger”. This type of stay looks like
English ‘A’.
Self Stay or ‘B’ Type Stay: When there is no space for
stay, the lower portion of the stay wire is clamped by
stay clamp to the lower portion of the pole. Such type of
stay is called Self stay or ‘B’ type stay.
‘Y’ Type Stay: It is used for supporting guarding cross
arm. It is also used for side brackets.
Flying Stay: When the line is on the roadside and there
is no space for stay, pole piece of sufficient height is
erected at the other side of the road and a stay wire is
DISTRIBUTION LINEMAN — CLASS XI
88
Unit-4 .indd 88
11-06-2019 16:21:28
tied up between pole and pole piece. For giving tension
to the pole piece, stay wire and stay rod are used.
Strut (Stud): When the pole is on the roadside and there
is no space for stay, one pole is used as a support to the
line pole from opposite side of the stay. The support
pole is called “strut”. Strut is fixed to line pole by a
suitable clamp.
Storm Guys: When the line is straight and the distance
from one cut-point to another is more, this type of stay
is used. At mid-pole of the line, two stays at an angle of
600 on both sides are tied up. Such type of stay is called
“Storm Guys”. For angle location, stays are to be given
in such a way that tilting of the pole due to conductor
tension is avoided. Stay insulators are used to obstruct
the leakage current.
Stay Binding: The stay should be linked with pole
earthing and/or neutral wire using G.I. so that leakage
current will pass through earthing or neutral to the
ground. Such binding is called “Stay Binding”.
NOTES
Remember
1. if stay insulator is not provided, 8 S.W.G. G.I. wire
shall be used near the stay clamp and link it to
neutral conductor. The length of G.I. wire should
be sufficient to join the stay wire to neutral of L.T.
line or in case of H.T. line, to the H.T. earthing.
This G.I. wire should be well bound to the earthing
or neutral.
2. stay insulator should not be less than 10 ft from
the ground.
Normal Stay
Self Stay
A Type
Strut Type
Fig. 4.24 Types of stay
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
89
Unit-4 .indd 89
11-06-2019 16:21:28
3. While binding the stay, pole should not be tilted.
4. Thimble is necessary for stay binding. If the
thimble is not available, the portion on stay wire
on eye bolt should be binded properly.
REC construction G4 gives the details of various guys.
The figure 4.25 gives the detail of stay set arrangement
for 11kV/LT Line.
eye point
ture beckle
stay insulator
base pate E
Fig. 4.25 Erection of stay
16.0 6.0 +1.5
65 max
65
45 + 3
90
25 + 1.5
creepage
distance
105 max
45 +1.5
85
Fifteen locations are there within 1 km.
Provision for 9 guy-sets is made with 7/3.15
stay-wire (5.5kg). The turn-buckle M.S. rod of
16 mm diameter concrete quantity at the rate
of 0.2 cm per stay-set should be provided.
Either base pad should be used or additional
provision for base pad-concreting should be
made (Figs. 4.26 and 4.27).
11 kV and LT Stay erection
80 + 6
140
60.0 + 1.5
Guy Strain Insulators
Guy strain insulators are placed to prevent
the lower part of the guy from becoming electrically
energised by a contact of the upper part of the guy when
the conductor snaps and falls on them or due to leakage.
No guy insulator shall be located less than 3.50 meter
(vertical distance) from the ground.
Fig. 4.26 Dimensions of stay
DISTRIBUTION LINEMAN — CLASS XI
90
Unit-4 .indd 90
11-06-2019 16:21:30
Clam
Clam
Stay set Arrangement
Anchor Rod & Plate
Fig. 4.27 Construction of various components of stay
Fixing of Cross-Arms and Top-brackets
After the erection of supports and providing guys, the
cross-arms and top-brackets are to be mounted on the
support with necessary clamps, bolts and nuts. The
practice of fixing the cross-arms a bracket before the
pole erection is also there. In case, these cross-arms
are to be mounted after the pole is erected, the lineman
should climb the pole with necessary tools. The crossarm is then tied to a hand line and pulled up by the
ground man through a pulley, till the cross-arm reaches
the lineman. The ground man should station himself on
one side, so that if any material drops from the top of
the pole, it does not strike him. All the materials should
be lifted or lowered through the hand line, and should
not be dropped.
11 kV ‘V’ cross arm fixing
There are 3 types of porcelain insulators
1. Pin type
2. Strain type
3. Shackle type
REPAIR
AND
MAINTENANCE
OF
22 0 hole
c75*40*5.7 kg/m
Insulators and Bindings
Line conductors are electrically insulated
from each other as well as from the pole
or tower by non-conductors, which we call
‘insulators’.
40 22 0 hole
1070
50*50*6 plate
to be welded
180
holes
310
370
80
310
310
Elevation
29
1070
Plan
Fig. 4.28 11 kV ‘V’ cross arm specification
POWER DISTRIBUTION LINES
91
Unit-4 .indd 91
11-06-2019 16:21:32
The pin type insulators are generally used for straight
stretch of line. The insulator and its pin should be
mechanically strong enough to withstand the resultant
force due to combined effect of wind pressure and weight
of the conductor in the span. The strain insulators are
used at terminal locations or dead-end locations and
at places where the angle of deviation of line is more
than 10°. The shackle type of insulators are used for L.T
Lines (Figs. 4.28 and 4.29).
The pins for insulators are fixed in the holes
provided in the cross-arms and the pole top brackets.
The insulators are mounted in their places over the pins
and tightened. In case of strain or angle supports, where
strain fittings are provided for this purpose, one strap
of the strain fitting is placed over the cross-arm before
placing the bolt in the hole of cross-arms. The nut of the
straps is so tightened that the strap can move freely in
horizontal direction (Fig. 4.30).
For wood
cross-arm
instead
of spring
washers use
two square
washers
50*50*5 Mm.
One on top
and the other
at bottom
Insulator Pin
(Types 65P)
As Per: 2486 Pt.ii
Fig. 4.30 Specification of GI pin
Fig. 4.29 Binding of pin insulator
Tying of Conductor on Pin Insulators
Conductors should occupy such a position on the
insulator so as to produce minimum strain on the
tie wire. The function of the wire is only to hold the
conductor in place on the insulator, leaving the insulator
and pin to take the strain of the conductor.
In straight line, the best practice is to use a top
groove insulator. These insulators will carry grooves on
DISTRIBUTION LINEMAN — CLASS XI
92
Unit-4 .indd 92
11-06-2019 16:21:33
NOTES
145
35
100
140
1
2
4
3
17.5 Ø hole for
16 Ø cotton pin
5
6
7
elevation
end view
Fig. 4.31 Fixing of Disc Insulator
the side as well. When the conductor is placed on the
top groove, the tie wire serves only to keep the conductor
from slipping out (Fig. 4.31).
On corners and angles (below 5 deviations) the
conductor should be placed on the outer side of the
insulators. On the far side of the pole, this pulls the
conductor against the insulator instead of away from
the insulator.
Kind and Size of Tie Wire to be used
In general the tie wire should be the same kind of wire
as the line wire i.e. aluminium tie wire should be used
with aluminium line conductor. The tie should always
be made of soft annealed wire so that it may not be
brittle and injure the line conductor. A tie wire should
never be used for second time. Good practice is to use
number ‘6’ tie wires for line conductor. The length of the
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
93
Unit-4 .indd 93
11-06-2019 16:21:34
NOTES
wire varies from 1m for simple tie of small insulators (LT
pin insulators) to 3 m (33 KV pin insulators).
Rule of Good Tying Practice
1. Use only fully annealed tie wire.
(i) Use that size of tie wire which can be readily
handled, yet one which will provide adequate
strength.
(ii) Use length of tie wire sufficient for making the
complete tie, including an end allowance for
gripping with the hands. The extra length should
be cut from the end if the tie is completed.
(iii) A good tie should:
y Provide a secure binding between line wire
insulators and tie wire.
y Have positive contacts between the line wire
and the tie wire so as to avoid shifting contacts.
y Reinforce line wire in the vicinity of insulator.
(iv) Avoid use of pliers.
(v) Do not use the wire which has been previously
used.
(vi) Do not use hard drawn wires for tying.
2. Good helical accessories are available and can be used.
Conductor Sagging and Erection Stringing
Conductor erection is the most important phase in
construction. The main operations are:
y Transportation of conductor to work site
y Paying and stringing of conductor
y Joining of conductor
y Tensioning and sagging of conductor
The conductor drums are transported to the location.
While transporting, precautions are to be taken so
that the conductor does not get damaged/ injured.
The drum could be mounted on cable drum support,
which generally is made from crow-bar and wooden
slippers for small size conductor drums. The direction
of rotation of the drum has to be according to the
mark in the drum so that the conductor could be
drawn. While drawing the conductor, it should not rub
causing damage. The conductor could be passed over
DISTRIBUTION LINEMAN — CLASS XI
94
Unit-4 .indd 94
11-06-2019 16:21:34
poles on wooden or aluminum snatch block mounted
on the poles for this purpose.
The mid-span jointing is done through compression
crimping or if helical fittings are used the jointing
could be done manually. After completing the jointing,
tensioning operation can be started. The conductor
is pulled through come-along clamps to string the
conductor between the tension locations. Sagging of
conductor has to be in accordance to the Sag Tension
chart. In order to achieve it, it is preferred to pull the
conductor to a tension a little above the theoretical value
so that while transferring it from the snatch blocks to the
pit insulators and to take care of temperature variation
proper sag could be achieved. Sagging for 33/11 kV line
is mostly done by ‘sighting’. A horizontal strip of wood
is fixed below the cross-arm on the pole at the required
sag. The lineman sees from other end and the sag is
adjusted by increasing or decreasing the tension. The
tension clamps could then be finally fixed and conductor
be fixed on pin-insulators. All fittings, accessories
like guys, cross-arms, etc., could be checked as they
crimping sleeve
die
NOTES
crimping tool
center stop
conductor
start crimp
first crimp
second crimp
to crimp
move handles in the direction
a typical complete joint
Fig. 4.32 Crimping of ACSR and AAC conductor
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
95
Unit-4 .indd 95
11-06-2019 16:21:35
NOTES
should not have deformities. Along the overhead line
where the conductor is to be strung, four number of
wheel consisting of wooden circular base provided with
vertical steel rod is placed, which is loaded with the
conductor drums (as required). These conductors, say
three in number are dragged using the ‘come along’ tool
by either labourers, tractor or pulling machine along
the line supports (Fig. 4.32).
This bunch of conductors is lifted up to the cross-arms
by a man on the pole-top using a pulley and rope. And a
handful of other labourers pull the other end of the rope.
Thus, the conductor reaches the cross-arm. A similar
procedure is followed for all the poles before sagging.
Ground Clearance
y Specified clearances are to be maintained at the
lowest point of the span with maximum sag as
per CEA Gazette Notification 2010
y Maximum sag is related to the temperature
y Tension of conductors is to be limited so that
F.O.S. is 2
Keeping all these parameters in view, sag-tension
charts are to be drawn for each conductor size, so that,
while constructing the lines, these charts are referred
for keeping proper sag and tension at the atmospheric
temperature at that time. This will help in maintaining
required clearance.
Maximum Clearance between Supports
The supports are designed to withstand certain working
load. This governs the distance (span) between two
supports. The load on the supports depends upon wind
pressure on conductors, surface area of the support,
fittings etc. The greater the wind pressure zone area
the lesser the span. REC has issued Construction
Standards for span for 11kV and LT Lines for various
wind pressure zones i.e.50 kg/m, 75 kg/m and 100
kg/m. The span for 11kV for 50 kg/m is 107meters and
it gets reduced at higher wind pressure.
DISTRIBUTION LINEMAN — CLASS XI
96
Unit-4 .indd 96
11-06-2019 16:21:35
Table 4.5 11 kV Line—Triangular Configuration (Rec
Construction Standards)
Conductor size
(Normal AI area)
Working
load of
supports
Maximum permissible span in
meters in a wind pressure zone
of
50 kg/m
75 kg/m
100 kg/m
Rabbit ACSR
(equivalent AAAC
7/3.15)
140 kg
107
(107)
67.5
(72)
NR
200 kg
NR
104
(107)
73.5
(78.0)
Weasel ACSR
(equivalent AAAC
7/2.5)
140 kg
107
(107)
87.5
(90)
NR
200 kg
NR
107
(107)
95
(98)
140 kg
107
107
NR
200 kg
NR
107
107
Squirrel
ACSR(equivalent
AAAC 7/2)
NOTES
LT lines (3 phase 4 wire) 8 m supports (3 phase – 4
wire) line vertical formation
(i) Above spans will suit for single phase lines also.
(ii) 3 phase-5 wire lines are required to provide street
lighting in the inhabited areas where spans have
to be limited to get normal intensity of light hence
the details are not given.
Table 4.6 Maximum permissible spans with ACSR,
AAAC and AAC Conductor
Conductor Size
(Normal AI area)
Working
load of
Supports
Maximum permissible span
in meters in a wind pressure
zone of
50kg/m
75kg/m
100kg/m
ACSR Rabbit
(equivalent AAAC
7/3.15)
140 kg
200 kg
99
(103)
NR
(NR)
62.5
(63)
93.5
(98)
NR
(NR)
66.5
(69)
ACSR Weasel
(equivalent AAAC
7/2.5)
140 kg
200 kg
99.5
(107)
NR
(NR)
77.5
(77)
99.5
(107)
NR
(NR)
82.5
(83)
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
97
Unit-4 .indd 97
11-06-2019 16:21:35
ACSR Squirrel
(equivalent AAAC
7/2)
140 kg
200 kg
100.5
(107)
NR
(NR)
91
(91)
100.5
(107.0)
NR
(NR)
97
(99)
AAC (Ant)
140 kg
200 kg
71.5
NR
66.5
67.5
NR
63
AAC (Gnat)
140 kg
200 kg
73
NR
66
66
NR
59.3
Overhead Conductor Stringing
Along the overhead line where the conductor is to be
strung, four wheels consisting of wooden circular
base provided with vertical steel rod are placed, which
are loaded with the conductor drums (as required).
These conductors, say, three in number are dragged
using the ‘come along’ tool by either labourers, tractor
or pulling machine along the line supports.
This bunch of conductors is lifted up to the crossarms by a man on the pole-top using a pulley and rope.
A handful of other labourers pull the other end of the
rope. Thus, the conductor reaches the cross-arm. The
details are shown in figure 4.33. A similar procedure is
followed for all the poles before sagging.
Derrick
Rope
Derrick
Trifor
OR Rully
Bipod
Channel piece
RCC padding base
Fig. 4.33 Derrick Method
DISTRIBUTION LINEMAN — CLASS XI
98
Unit-4 .indd 98
11-06-2019 16:21:35
Sagging and Tensioning
The variation in the atmospheric temperature results in
the increase or decrease of the length of the conductor
of a section. In summer, when temperature is high,
the length increases due to expansion and in winter,
when the temperature is low the length decreases due
to contraction. With increase in length, the conductor
becomes loose, sag increases and tension reduces, while
in winter the sag decreases, tension increases.
NOTES
11 kV Fixing and binding of strain Insulator
Fig. 4.34 Strain Insulator Assembly with Helically Formed Fittings
There are two important factors which affect the sag
and tension:
y Elasticity of the conductor and
y Temperature
Sag is directly proportional to wind pressure load (W)
and inversely proportional to temperature (T). If the
length of the conductor increases due to temperature
increase then sag will increase. This may be the case in
summer, while it may be reverse in winter. The tension
will accordingly decrease or increase.
In order to keep the sag and tension values under
varied working conditions according to the regulations,
Sag-Tension charts are prepared for different spans and
temperatures for ACSR, AAAC and AAC conductor.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
99
Unit-4 .indd 99
11-06-2019 16:21:36
NOTES
160+0.5
50
90
42
packing piece
18
32
12
12
62
52
15
5
10
14
suitable for conductor
up to 11mm diameter
46
packing piece
m-12 u-bolt
Fig. 4.35 11kV Strain Clamp for Ball and Socket type insulator
DISTRIBUTION LINEMAN — CLASS XI
100
Unit-4 .indd 100
11-06-2019 16:21:38
160+0.5
17.5+0.8
90
35
packing piece
18
32
12
8.5 min
62
16.5
8.5 min
160+0.5
15
3
5
10
14
suitable for conductor
up to 11mm diameter
46
packing piece
m-12 u-bolt
Fig. 4.36 Fixing of Disc insulator
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
101
Unit-4 .indd 101
11-06-2019 16:21:40
Conductor Jointing
The length of distribution lines are in kilometers and one
coil of conductor is not able to solve the length problem.
Hence jointing the conductor is necessary.
Another necessity of jointing the conductor is
breaking of the conductor for some reason.
Types of Joints
(1) Britannia, (2) Telephone, (3) Meried Joint, (4) ‘T”
joint, (5) Sleeve joints, (6) Compression joint.
Britannia Joint: This type of joint
is made only on solid conductors
and cannot be made on stranded
conductor. Two conductors of
length 6 inches (150 mm) are
brought in front of each other to
be joined . Then both conductors
should be cleaned to make sure
that they are rust free. If the
conductor is of copper; it should
make good electrical connection.
Fig. 4.37 Britannia Joint
Then ends of both the conductors are bent through half
centimetre and placed on each other. The length of the
contact portion should be minimum 100 mm. This joint
should be bound by 14 mm copper wire as shown in the
figure (Fig. 4.37).
Telephone Joint (Western Union): This joint is used
only for solid conductors. It is used for conductors of
size 8 SWG or higher size. First, they are bent at 100 to
125 mm from the edges and are placed over each other.
Then each one is twisted with another conductor.
Married Joints: This joint is made between copper
conductors having central strand of G.I. wire. This
joint should not be made between Al conductors.
Approximately 175 to 200 mm of conductor strands are
unwound. The G.I. strand of both conductors should
be broken up to a length of 175 mm. Both conductors
should be brought in front of each other and their
strands should be woven with each other. The strand
of one conductor is twisted on another conductor, and
the strand of the other conductor is twisted on the first.
DISTRIBUTION LINEMAN — CLASS XI
102
Unit-4 .indd 102
11-06-2019 16:21:41
Likewise all the strands are twisted and then soldered.
This is used only for small span length (Fig. 4.38).
‘T’ Joint: This joint is made with stranded conductor.
This joint cannot take tension. It is used for jumper or
tapping in sub-station. The conductor strands to be
separated up to 100 mm. Then middle steel strands are
cut. Then it shall be placed to horizontal conductor with
three strands each on either side and shall be twisted
over the horizontal conductor (Fig. 4.39).
Before Jointing
Preparation of ‘T’ Joint
‘T’ Joint After
Completion
After Jointing
Fig. 4.38 Married Joint
Fig. 4.39 ‘T’ Joint
Sleeve Joint: It can be made with any type of aluminium
conductor. Graphite grease is applied over the conductor
and as shown in figure 4.40 two Al sleeves should be
taken. These sleeves should be placed on the conductor
as shown. Sleeves should be twisted by twisting wrench.
This joint is made for L.T., H.T., ACSR, AAC conductor
up to 0.06 cm2 (Fig. 4.40).
Fig. 4.40 Sleeve Joint
Compression Joint: This joint is used for conductors
of more than 0.06 cm2 sizes. For preparing these joints,
two different sleeves are used. There are two holes in
Al sleeve. Rebating is done through these holes. Slide
aluminium sleeves are slid over one conductor. It is slid
until only the working length protrudes. The next step
will be cutting of the aluminium strands for installation
of the steel sleeve. It is measured back from each end
of the conductor and then a distance equal to half the
length of the aluminium sleeve is marked. The cut
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
103
Unit-4 .indd 103
11-06-2019 16:21:42
NOTES
line is then marked. The marked location for cutting
should be taped. The outer strands are cut with a
rotating tool until the layer becomes loose. To prevent
nicking, the core inner layer should not be cut. The wire
in the inner layer is removed by hand. It is extremely
important to note that a small cut on the core should
not be disturbed while cutting the aluminium strands.
If this happens, the ultimate strength of the joint will
be reduced. Repeat the above process with another
conductor. Insert the conductor’s core into the steel
sleeve, making sure that the ends butt solidly against
the center stop. Also, ensure the distance from the end
of the barrel to the aluminium strand. Lubricate the
sleeves with solid lubricating wax. Remove the tape from
the ends of the aluminium strands. Set the steel sleeve
into the compressing tool. Choose a proper size of the
die for steel sleeve. Make initial die compression at the
centre of the steel sleeve. Make compression on both
sides of the centre compression. Overlap successive
compressions by approximately 0.5 inches. Choose
one side and compress it to the end. Repeat the same
process to the other side also. The aluminium sleeve
extrudes beyond the steel sleeve. Remove and clean the
steel sleeve. Now change the die in compressing tool for
the aluminium joint compression. Slide the aluminium
sleeve over the steel sleeve until the end of the barrel
aligns with the marks placed on the conductor. Inject
the filler compound through holes. This filler compound
protects the steel barrel from corrosion, cleans the
strands by removing oxides while compressing. Now
make the initial compression on either side of the
splice beginning at the start mark. Continue making
compressions on one side to the end. Complete the
compression on the other side also. The centre portion
of the splice is not compressed.
Jumpering
Connecting two conductors or wires is called Jumpering.
1. Jumper should not be connected to main
conductor. The jumper should always be
connected by P.G. clamps as shown in Fig 4.41.
DISTRIBUTION LINEMAN — CLASS XI
104
Unit-4 .indd 104
11-06-2019 16:21:42
2. When the jumpers are near metallic portion, all
such jumpers are covered with alkathene pipe.
NOTES
Fig. 4.41 Jumpering
3. Conductor joints are marked on A.C.S.R.
conductor when dispatched. Mid span joint
should be made before stringing because the
steel strand is not kept continuous. Hence it is
necessary to replace the company joint.
4. Care should be taken that mid span joint will not
be less than 40 feet from pole.
5. Every joint should be done carefully.
6. Where conductor strands are cut, repair sleeve is
used.
7. Conductor joint strength should be 95% that of
conductor, and resistance should be that of main
conductor.
Guarding
Guarding is an arrangement provided for the lines, by
which a live conductor, when accidentally broken, is
prevented to come in contact with other electric lines,
telephone or telegraph lines, railway lines, roads, and
persons or animals and carriages moving along the
railway line or road, by providing a sort of cradle below
the main electric line. Immediately after a live conductor
breaks, it first touches this cradle guard of G.I. wires
before going down further. This, in turn, trips the circuit
breakers or H.T./L.T. fuses provided for the H.T./LT.
lines, and the electric power in the conductor or the line
is cut off, and danger to any living object is averted.
Guarding is not required for crossings of 66 kV
and higher voltage lines where the transmission line is
protected by fast acting relay operated circuit breaker
of modern design with a tripping time of even less than
the order of 0.25 seconds from occurrence of fault
to its clearance. For all other crossings, like railway
tele-communication lines and major road crossing
guarding is essential.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
105
Unit-4 .indd 105
11-06-2019 16:21:42
NOTES
The minimum height between any guard wire and
live crossing conductor shall not be less than 1.5 m in
case of a railway crossing (Fig. 4.41).
Types of Guarding
(i) P.V.C. Guarding
(ii) Levice Guarding
P.V.C. Guarding
This is mainly used for L.T. Lines passing through
agriculture field. This is used where formation of line is
vertical. The upper end is tied in shackle bolt and lower
end is tied to the neutral. A G.I. wire frame is prepared
so that there will be horizontal G.I. wire piece at equal
distance below every conductor. The vertical wires of
the frame are insulated with P.V.C. pipe. Even during
conductor swings, it will not be earthed due to P.V.C.
pipe. In case of snapping of conductor, it will make
contact with the G.I. wire and get earthed, resulting
blowing of the fuse (Fig. 4.42).
430 mm
m
50
m
50
G.I. wire
6 S.W.G.
m
m
450 mm
7.5 mm thinck
120
50
wooden
260 batten
conductor
0
21
260
woldage
light
phase
150
20*20
210
neutral
Fig. 4.42 Vertical Type Guarding
There are two types of guarding according to the
formation. A). To use in case of ‘D’ clamps. (B) Direct
shackle type.
Levice Guarding
This is of the following types:
(i) Carpet guarding
(ii) Cradle guarding
(iii) Box type guarding
There are two, three or four guard wire for levice guarding.
These are bound with cross arm. The horizontal laces at
DISTRIBUTION LINEMAN — CLASS XI
106
Unit-4 .indd 106
11-06-2019 16:21:43
a specific distance are tied up to the above wires. This
guarding is used up to 33 KV lines.
(i) Carpet Guarding: The specific length cross arms are
fixed on the poles. Four G.I. wires are used for guard
wire. Lacings are tied up at specific distance. This type
is used for power line crossing or power and telephone
line crossing (Fig. 4.44).
(ii) Cradle Guarding: It consists of 6 guard wire. Four
are on lower side and two on the upper side. Cross lacing
is done from three sides. It is also called Tray guarding.
Even though the conductor while snapping jumps up
drastically, it will not go out of the cradle guarding.
This is used for railway or L.T. to 33 KV guarding
in residential area, for road crossing or along the
road lines (Fig. 4.43).
P
S
P
610
1830
G.I. wire
cross lacing
for 11/22/11 kV lines
line road
P
S
note
crossing 750 mm 3 mtr
along road 750 mm 6 mtr
Fig. 4.43 Cradle Type Guarding
8 or 7/14 S.W.G.
G.I. wire
cross lacing
8.10 or 12 S.W.g. GI wire
for 11/22/11 kV lines
line road
P
crossing 750 mm
along road 750 mm
S
3 mtr
6 mtr
note
Fig. 4.44 Carpet Guarding
(iii) Box Type Guarding: This is used for composite
lines. By fixing cross arms to the lower line, carpet
guarding is done and also for the upper line, the upper
guard wire is fixed to the lower by vertical lacing.
Road crossing and guarding
(a) As far as possible road crossing should be at right
angle, but not less than an angle of 60 degrees.
(b) Cradle guarding is used for road crossing of power
line or along the line.
(c) G.I. wire of 10 W.S.G. for L.T. line and 8 W.S.G for
11 KV to 33 KV lines is used for guarding.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
107
Unit-4 .indd 107
11-06-2019 16:21:44
NOTES
(d) The first lacing should be at a distance of 750 mm
from the pole. Other lacing is tied at a distance of
3 meter from each other.
(e) The vertical distance between conductor and
guarding in mid span should be minimum 610
mm for L.T. and 1220 mm for H.T line.
(f) The vertical distance between L.T. line guarding
cross arm and neutral should be 610 mm (2 ft.)
and the length of cross arms should be 750 mm
(2½’)
(g) The clearance between line and guarding cross
arm for 11 KV, 22 KV and 33 KV line should be
650 mm (2 ¼’), 750 mm (2 ½’) and 840 mm (2 ¾’)
respectively.
(h) There is no need of guarding for lines above 66
KV, as their circuit breakers are sensitive. The
breaker trips when conductor snaps thereby
isolating the line.
Presently, due to electrification of railway-tracks,
11kV and L.T. crossings have to be done through
underground cables.
Special Instructions
(a) Power lines should always be guarded as above.
(b) The distance between guard-wire and telephone
line should be minimum 920 mm.
(c) The telephone crossings for 66 KV and above are
done by Telephone Department. The clearance
between the power line and telephone line shall
be as below :
66 KV and 132 KV - - 2750 mm (9’)
220 KV and 400 KV -- 4575 mm (15’)
Fitting Accessories on H.T./L.T. line
It is essential to fix accessories after pole erection. Line
accessories are of two types.
(a) Conductor accessories
(b) Pole accessories
a. Conductor Accessories
1. Binding Tape: Binding tape is used for binding pin
insulator, shackle or Line insulator to the conductor.
The tape is wound on the conductor. The metal of
binding tape should be same as that of conductor. The
DISTRIBUTION LINEMAN — CLASS XI
108
Unit-4 .indd 108
11-06-2019 16:21:44
first layer is wound along the wire in direction of twist
of wire and second layer is in opposite the twist. The
portion on which the binding wire is to be wound should
be taped 25mm more from either side. This tape is used
for avoiding conductor snapping due to friction.
2. Binding Wire: It is used for binding insulator to the
conductor.
3. P.G. Clamp: It means parallel groove clamp. This
is used for joining jump wire. Line tension cannot be
given on P.G Clamps. Bi-metallic P.G. clamp is made
out of two different metals and the conductor of the
same metal is used in the same type of metal groove of
P.G. Clamp
4. T Clamp: T clamps are used in substation to connect
the jumps and cannot sustain tension.
NOTES
b. Pole accessories
The main pole accessories are cross arms, clamps,
insulators, aluminum bobbins, nuts and bolts, stay
clamp, etc.
Earthing
Earthing shall generally be carried out in accordance
with the requirements of CEA regulations for measures
relating to safety and electricity supply, dated
20th September 2010 and the relevant regulations
of the Electricity Supply Authority concerned and as
the following:
1. All metal supports, fittings etc. shall be permanently
and efficiently earthed. Either a continuous wire
may be run with earthing arrangements at 4
points in 1.609 km or each independent structure
should be efficiently earthed.
2. Similarly at consumer’s premises a suitable
earthing point would be provided. Consumer has
to make arrangement for independent earthing.
3. Sub-stations structures etc. should be provided
with two independent earthing points. This
should be interconnected or matting in the substation area could be laid-down for connecting to
the earth points.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
109
Unit-4 .indd 109
11-06-2019 16:21:44
NOTES
4. For RCC/PCC poles the metal cross-arms and
insulator pins shall be bonded and earthed at
every pole for HT lines and at every 5th pole for
LT lines.
5. All special structures on which switches,
transformers, fuses, etc., are mounted should be
earthed.
6. The supports on either side of the road, railway or
river crossing should be earthed.
7. All supports (metal, RCC/PCC) of both HT and
LT lines passing through inhabited areas, road
crossings and along such other places, where
earthing of all poles is considered desirable from
safety considerations should be earthed.
In special locations, railway and telegraph line
crossings, special structures, etc., pipe/rod earthing
should be done. At other locations the coil earthing may
be adopted. The coil earthing consist of 10m length of
8 SWG G.I. wire compressed into a coil 450 mm length
and 50 mm diameter and buried 1500 mm deep.
Earthing and its types
It is very important to earth the line and electrical
equipment. It will be electrically unsafe without earthing.
The pole/ body of equipment connected solidly to earth
are called earthing.
1. For Electrical supports and equipment
In case of short circuit or leakage, current will pass with
minimum resistance to earth so that maximum current
will flow through effected circuit so that fuse will blow
or circuit breaker to trip. This will isolate the faulty line
or equipment from live circuit.
2. Transformer neutral earthing
(a) The leakage or unbalanced current will have path
with minimum resistance.
(b) Sensitive protecting equipment works properly.
(Earth Fault Relay)
(c) It prevents the lines being charged to excessive
high voltage due to lightening or switching surges.
DISTRIBUTION LINEMAN — CLASS XI
110
Unit-4 .indd 110
11-06-2019 16:21:44
(d) By connecting resistance in the neutral earthing,
fault current is controlled.
(e) It helps for keeping neutral voltage always zero.
NOTES
3. For Lightening Arrestor
The lightening arrestor or earthing, discharges the
lightening charge with very low resistance, which
prevents possible damages to the infrastructure. For
this, very low earth resistance is necessary. This quality
can be achieved by piercing the earth electrode deep in
the ground till the wet soil.
Earth tester measures earth’s resistance and its unit
is ohm.
It is very important to earth the line and electrical
equipment. It will be electrically unsafe without earthing.
The pole/body of the equipment connected solidly to
earth is called earthing.
Methods of Earthing
As per REC Construction Standards there are two types
of earthing:
1. REC Construction Standard J-1 Coil Earthing
(Fig. 4.45)
2. REC Construction standard J-2 Pipe Earthing or
Spike Earthing (Fig. 4.46)
500
GL
200
300
GL
K W 001 W
2500 welding
Fig. 4.46 Pipe Earthing
Notes:
1. All dimensions are in mm
2. Earth terminal should be made of G.I
3. Manufacturing tolerance
4. Clamp is to be welded to spike
5. The whole assembly is to be hot dip galvanised
(BIS: 2629 and 4759)
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
111
Unit-4 .indd 111
11-06-2019 16:21:45
From support 1200
2.5m
APP
600
G
L
300
NQ 8.5 W.O 0.1
wire closely wound
115 turns
Refilled Earth
Charcoal or coke
and salt layers of
300 in alternate
1500
50
Earthing Spiral
spiral earth wire
8 S.W.G G.I
450
350
Fig. 4.45 Coil Earthing
6. All ms (mild steel) parts should be as per BIS:
2062
7. Weight mentioned is for packing and forwarding
purpose only
Earth Resistance
(a) Earth resistance is depended on following factors:
(i) Type of soil
(ii) Temperature of earth
(iii) Humidity in earth
(iv) Minerals in earth
(v) Length of electrode in the earth
(vi) Electrode shape and size
(vii) Distance between two electrodes
(viii) Number of electrodes
DISTRIBUTION LINEMAN — CLASS XI
112
Unit-4 .indd 112
11-06-2019 16:21:45
(b) Maximum earth resistance allowed is as below:
NOTES
(i) Major power station 0.5 ohms
(ii) Major sub-stations 1.0 ohms
(iii) Minor sub-station 2 ohms
(iv) Neutral bushing 0.2 ohms
(v) Service connection 4 ohms
(vi) L.T lightening arrestor 4 ohms
(vii) L.T. pole 5 ohms
(vii) H.T. pole 10 ohms
(viii) Tower 20-30 ohms
If earth’s resistance is more than the above values,
the following treatments can be made for minimising
resistance.
(i) Oxidation on joints should be removed and joints
should be tightened.
(ii) Sufficient water should be poured in earth
electrode.
(iii) Earth electrode of the biggest value should be
used.
(iv) Electrodes should be connected in parallel.
(v) Earth pit of more depth and width-breadth should
be made.
Anti-climbing Devices
In order to prevent unauthorised persons from climbing
any of the supports of HT and LT lines without the aid
of a ladder or special appliances, certain anti-climbing
devices are provided to the supports. Two methods
generally adopted are:
(i) barbed wire binding, for a distance of 30 cm to 40
cm at a height of 3.5 m to 4 m from ground level,
(ii) clamps with protruding spikes at a height of 3 m
to 4 m.
Testing and Commissioning
When the line is ready to energise, it should be thoroughly
inspected in respect of the following.
1. Poles — proper alignment, concerting and muffing.
2. Cross-arms — proper alignment.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
113
Unit-4 .indd 113
11-06-2019 16:21:45
NOTES
3. Binding, clamps and jumpers — To check whether
these are in reach.
4. Conductor and ground wire — Proper sag and to
check whether there are any cuts, etc.
5. Guy — To check whether the Guy wire is tight
and whether the Guy insulators are intact.
Earthing System: In order to check whether the
earthing connections support and the fittings are
intact the following steps should be taken. Measure
earth’s resistance with a earth tester. After the visual
inspection is over and satisfied, the conductor is tested
for continuity/ground, by means of a Megohmmeter
or megger. At the time of testing through the megger,
a person should not climb on the pole or touch the
guarding, conductor, guy wire etc.
1. Before charging any new line, it should be ensured
that the required inspection fee for the new line
is paid to the electrical inspector and approval
obtained from him for charging the line.
2. The line should be energised before the
authorised officer.
3. Before energising any new line, the officer-incharge of the line shall notify to the workmen
that the line is being energised and that it will no
longer be safe to work on line. Acknowledgement
of all the workmen in writing should be taken in
token of having intimated them.
4. Wide publicity should be made in all the localities
through which the line is to be energised will be
passing. It s necessary to Intimate the time and
date of energising and warning the public against
the risk in meddling with the line.
5. The Officer-in-Charge of the line shall personally
satisfy himself that the same is in a fit state
to be energised.
Principle of Operation of Fuse
Heating effect of electric current is used in the operation
of the fuse (Fig. 4.47). Any increase in an electric current
in the circuit results in the increase in the rate of heat
generation which will increase the temperature of the
DISTRIBUTION LINEMAN — CLASS XI
114
Unit-4 .indd 114
11-06-2019 16:21:45
fuse wire. If this temperature happens to be above the
melting point of the material of fuse wire, fuse must
have operated.
Regulators used in distribution system are voltage
regulators which are used to adjust voltage at
distribution end. The step type voltage regulator takes
an incoming voltage that will vary with load conditions
and maintains a constant output voltage. As the loading
increases along the distribution feeder, the voltage will
drop. This reduction in voltage reduces the amount of
power used by the lighting portion of the load. There
are two types of regulators: single phase regulator and
three phase regulator (Fig. 4.48).
Fig. 4.47 Fuse
Auto Re-closer
(a) A Re-closer is a protection device (Fig. 4.49):
– For overhead power lines
– It is a circuit breaker designed to handle fault
currents
– Designed to Re-close on to a fault
Fig. 4.48 Voltage Regulator
Sectionaliser
(a) A Sectionaliser is a load break switch:
– It is used in conjunction with a “re-closer”
or “circuit breaker”.
– It counts the interruption created by a re-closer
during a fault sequence.
Fig. 4.49 Auto Re-closer
Check Your Progress
A. Fill in the blanks
1. Double poll (DP) strutures are required in all the
angle___________
2. In 11 KV lines _____________ poles are erected within
1 km distance.
3. Guy strain insulators are placed to ____________ the
lower part of the guy.
4. Connecting to conductors or wires is called ____________.
5. Cross arms and _____________ are mounted on the
support with ncessary clamps, bolts and nuts.
B. Multiple choice questions
1. Which type of joint is made with Aluminium conductors?
(a) Compression
(b) Meried
(c) Sleeve
(d) Britannia
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
115
Unit-4 .indd 115
11-06-2019 16:21:47
NOTES
2. Which of these is not a type of porcelain insulator?
(a) Pin type
(b) Strain type
(c) Britannia
(d) Shackle type
3. While binding the stay, pole should not be tilted.
(a) False
(b) True
4. The diamond guarding is used for
(a) LT Line
(b) HT Line
(c) Both HT and LT
(d) None of the above
5. Average span of 11 KV line is
(a) 50 meter
(b) 2. 60 meter
(c) 3. 75 meter
(d) 4. 100 meter
B. Short answer questions
1. Discuss the importance of guarding. Explain the types
of guarding.
2. List the factors on which earth's resistance is dependant
3. How do lightening arrestors help in earthing?
4. Explain the types of joints used in conductor jointing.
SESSION 4: DISTRIBUTION LINE MAINTENANCE
The lines and equipment should be inspected by the
competent authority. Following points need to be taken
care of during inspection:
1. For existing substation, the work should be done
as per the layout approval.
2. Statutory clearances have to be ensured, while
inspecting the following crossings:
(a) Railway crossings
(b) P and T crossings
(c) Junctions
(d) Road Crossings
3. Make sure that proper clearance is obtained for
the lines with different voltages operating on the
same support.
4. DPs and cut points should be inspected based on
need and approvals.
5. Adequate safety and clearances should be ensured
while running the lines at domestic colonies.
DISTRIBUTION LINEMAN — CLASS XI
116
Unit-4 .indd 116
11-06-2019 16:21:47
6. There should be appropriate earthing.
7. Any crossing should be at right angles, to
the extent possible.
8. Proper cross arms, extension cross arms
should be ensured as per the requirement.
Maintenance
When an overhead line trips on a sustained fault,
Fig. 4.50 Power Distribution Lines
it should be inspected to find out the nature of
fault such as loose sag, snapping of conductor,
tree branches touching the lines, conductor falling on
cross arms (Fig. 4.50). An improvement with a view to
avoid re-occurrence of such faults in future should be
arranged and carried out soon (Fig. 4.51). Complaints
regarding no current/failure of power supply, voltage
fluctuation, and load shedding and scheduled outages
shall be addressed by the senior
lineman as per the provisions of
the regulations. Problems related to
current such as no current or failure
of power supply in premises could
occur due to various reasons such as:
y Fuse blown out/tripping of
MCB
y Burnt meter
Fig. 4.51 Mitigating Bird Hazards to Overhead Lines
y Broken service line
y Service line snapped from pole
y Fault in distribution mains
y Distribution transformer failure
y Fault in HT system
y Problem in grid (33 kV or 66 kV) substation
y Planned/scheduled/emergency maintenance work
y Load shedding
y Street light complaint
Pre-monsoon Inspection
The inspection carried out with the overhead lines
without supply is called pre-monsoon inspection. It
should be planned in advance with proper tools and
equipment (Figs. 4.52 and 4.53).
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
117
Unit-4 .indd 117
11-06-2019 16:21:48
Pre-monsoon inspection involves the following
1.
2.
3.
4.
5.
6.
7.
8.
Tree cutting should be properly executed.
Sagging of lines should be minimised.
Leaned poles should be rectified.
Lines should be properly aligned by tightening
with proper bolts and nuts.
Earthing should be checked.
Torn insulators/flash over insulators should
be replaced.
Jumpers at cut points should be checked up.
Stay wires should be properly aligned.
Fig. 4.52 Sag in Overhead
Distribution Lines
Fig. 4.53 Inspection of Power
Distribution Lines
11 kV Lines Maintenance
11 kV Lines maintenance is required to minimise
interruptions and improve the efficiency of power supply.
The overhead lines should be inspected periodically
to detect any fault which may lead to break down of
electric supply. When an overhead line trips, it should
be inspected to find out the nature of fault.
Low Tension (LT) Line Maintenance
Fig. 4.54 Low Tension
Distribution Lines (LT)
LT Line (Fig. 4.54) maintenance includes:
1. Alignment of poles
2. Replacement of damaged service wire
3. Removal of bird nests
4. Tree clearance
5. Checking of pole fittings and street light brackets
6. Careful examination of damages to L T conductor
such as black spots on conductor
DISTRIBUTION LINEMAN — CLASS XI
118
Unit-4 .indd 118
11-06-2019 16:21:50
Ground Patrol
The periodic patrolling (not exceeding a month) of
overhead lines at ground level, while, the line is live,
is called ground patrol (pole to pole inspection) poles
maintenance. The following should be checked:
y Leaning of pole (Fig. 4.55)
y Sinking of earth around the pole
y Corrosion of metal at ground level (RSJ Poles)
y Cracks in Pre stressed Cement Concrete Poles
(PSCC).
Cross Arms
The following should be checked while maintaining
cross arms:
y Tilting of cross arms
y Rusting of cross arms
y Bird nest or creeper on cross arm (Fig. 4.56)
Fig. 4.55 Leaning of Pole due
to loose foundation.
Bindings
The looseness and cutting of bindings should be carefully
observed while patrolling.
Broken Conductor
Fig. 4.56 Bird's Nest on Cross Arm
Fig. 4.57 Conductors Distribution System
Conductors
The following should be checked while
maintaining conductors (Fig. 4.57):
y Cut strands, burnt marks and corrosion
y Breakage/Looseness of conductors
y Spotting kites, green creepers on the
conductors
REPAIR
AND
MAINTENANCE
OF
Fig. 4.58 Stay Wire
POWER DISTRIBUTION LINES
119
Unit-4 .indd 119
11-06-2019 16:21:53
Stay Wire
The following should be checked while maintaining
stay wire (Fig. 4.58):
y Corrosion of guy rod and stay wire
y Guy wire tightness
y Creeper on the stay wire
Fig. 4.59 Aeolian Vibration
Causes of Conductor Damage
Aeolian vibration: It is one of the most
important problems in power transmission
lines because it represents the major cause
of fatigue, failure of conductor strands or
of items associated with the support, use
and protection of the conductor during high
wind pressures (Fig. 4.59).
Fig. 4.60 Power Line Galloping
Fig. 4.61 Voltage Balance
Fig. 4.63 Air Break Switches
Fig. 4.62 Voltage Imbalance
Galloping: The high-amplitude, low-frequency
oscillation of overhead power lines is due to wind.
Sway oscillation and gallop tend to short circuit
between lines thus damage is caused due to
arcing. PG clamp maintains equal distance across
the lines by maintaining the sag to protect from
sway oscillation (Fig. 4.60).
DISTRIBUTION LINEMAN — CLASS XI
120
Unit-4 .indd 120
11-06-2019 16:21:54
Unbalance loading: Major line failures are due to
unbalance load when one phase conductor gets
overheated and snapped (melted down) due to excessive
current (Figs. 4.61, 4.62 and 4.63).
Overloading: When a line is loaded beyond the
maximum current carrying capacity the conductor gets
overheated and snapped.
Air Break (AB) switches need maintainance to check:
y Defect in closing of the AB switch
y Missing of the lock
y Damage of earth wire
y Dust accumulation on the insulators
y Blades/contact burnings
11 kV Cable and Cable Boxes
y Proper supporting of cable and cable boxes
y Damage to insulator and compound
leakage from the box
y Intactness of terminal connections with
overhead lines and earthing
Insulator Discs
Due to moisture and dust particles on the surface
of insulator the resistance is reduced. This leads
to flash over marks in case of lightning (Fig. 4.64).
Fig. 4.64 Disc Insulators used in
Power Lines
Causes of Insulator Damage
1. Due to difference in temperatures and
hot and cold season, there is extra stress
on both conductor and insulators of
entire overhead network (Fig. 4.65).
2. During rainy season dust over the
insulator becomes conductive and forms
fine hair crack which further develops to
fretting due to load and lightening.
3. Excessive tightening of PG clamps
causes extra strain to disc insulator, pin
Fig. 4.65 Wire Insulation Damage
insulator and conductor through-out
up to end points and causes tensile
breaks of conductor and abrasion, fatigue on
pin insulators.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
121
Unit-4 .indd 121
11-06-2019 16:21:56
Fig. 4.66 Megger
4. Though lightning arresters (LA) are the most
effective means of protecting electrical lines
against lightning and switching, failure of LA
directly impacts the insulators damage due to
spark.
Line conductors are electrically insulated from each
other as well as from the pole ‘insulators’. The insulator
and its binding should be mechanically strong enough
to withstand the resultant force due to combined
effect of wind pressure and weight of the conductor in
the span.
Material Testing Equipment
Line conductors are electrically insulated from each
other as well as from the pole ‘insulators’. The insulator
and its binding should be mechanically strong enough to
withstand the resultant force due to combined effect of
wind pressure and weight of the conductor in the span.
Proper calibration and working of equipment should
be double checked before using them for testing and
Fig. 4.67 Earth
repair activity (Figs. 4.66, 4.67 and 4.68). In case
tools used in testing are not properly working
and calibrated, then it will not lead to proper
adjustment of equipment which in turn would
result in malfunction of the total connected
system. All the equipment which are meant
for testing and repair activities should be kept
separately from other equipment, and should
be tested for their accuracy and workability
Fig. 4.68 Equipment Calibration
according to defined standards.
Table 4.7: Line Patrol Log Sheet
Item
No.
Points to be checked during
inspection and defects noticed
Location
Nos.
Action
taken for
Rectification
Inspection
Officer’s
Remarks
General
1.
Adequate clearance to conductors
and poles are available from trees,
shrubs, bushes etc.
Yes
No
2.
Vertical and horizontal clearance
from the neighbouring structures
under construction etc., are adequate
Yes
No
DISTRIBUTION LINEMAN — CLASS XI
122
Unit-4 .indd 122
11-06-2019 16:21:59
3.
Any new road, channels, earth
embankment are constructed near or
below the lines reducing clearance
Yes
No
Poles
4.
The pole is leaning and if so
whether stay is required to make it
plumb
Yes
No
5.
Earth around the pole has sunk or
eroded
Yes
No
6.
The metal is corroded at ground level
Yes
No
7.
Any cracks have been developed in
PCC/RCC poles
Yes
No
8.
The pole is intact and free from
mechanical injury due to vehicles
dashing against them
Yes
No
Any bird nest, or creeper observed on
cross arms
Yes
No
10.
The cross arm is tilted
Yes
No
11.
The cross arm is rusted
Yes
No
The bindings/jumpers are cut,
Yes
No
Loose, Charred or Burnt
Yes
No
13.
Visible indications for heating of the
PG clamps are observed
Yes
No
14.
Visible dangers like cut strands, and
burn marks, corrosion etc. observed
Yes
No
15.
The conductors are loose, increasing
the sag
Yes
No
16.
Kites or green creepers are observed
on the conductors
Yes
No
17.
The conductor/ground wire has
sufficient clearance over roads,
rivers, channels, railways and
telecommunication circuits,
haystacks etc.
Yes
No
18.
The guarding and earth, provided for
conductors are intact
Yes
No
Cross Arms
9.
Binding/Clamps/Jumpers
12.
Guys
19.
Corrosion of guy rod and stay wire is
observed
Yes
No
20.
The guy wire is tight
Yes
No
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
123
Unit-4 .indd 123
11-06-2019 16:21:59
21.
The guy insulators provided are
intact
Yes
No
22.
Any green creepers on the stay wire
Yes
No
23.
Guy pits have been washed away/
sunk
Yes
No
24.
The sleeve concreting is in order
Yes
No
AB Switches and Fuse
25.
There is any visual indication for the
defective closing of the switch
Yes
No
26.
The lock is missing
Yes
No
27.
The earth wire is cut or damaged
Yes
No
28.
There is too much of dust
accumulated on the insulators
Yes
No
29.
The blades/contacts/arcing horns
are burnt out or charred
Yes
No
Lightning Arresters
30.
The porcelain is damaged
Yes
No
31.
The line and earth connections are
intact
Yes
No
32.
There is any external indication to
show the lightning arresters have
been punctured
Yes
No
11 kV Cable and Cable Boxes
33.
The cable and cable boxes are
properly supported
Yes
No
34.
The insulators are damaged and
compound leaking from the box
Yes
No
35.
The terminal connection with the
overhead line is intact
Yes
No
36.
The earthing lead from the cable box
is intact
Yes
No
Yes
No
Yes
No
Earthing System
37.
The earthing connections of
the metal supports and fittings
are intact
Schedule of Periodical Routine
Inspection of Lines Lightning
Arresters
38.
The porcelain is damaged
DISTRIBUTION LINEMAN — CLASS XI
124
Unit-4 .indd 124
11-06-2019 16:21:59
39.
The line and earth connections are
intact
Yes
No
40.
There is any external indication to
show the lightning arresters have
been punctured
Yes
No
11 kV Cable and Cable Boxes
41.
The cable and cable boxes are
properly supported
Yes
No
42.
The insulators are damaged and
compound leaking from the box
Yes
No
43.
The terminal connection with the
overhead line is intact
Yes
No
44.
The earthing lead from the cable box
is intact
Yes
No
Schedule of Periodical Routine Inspection of
Lines
The lineman should adhere to the time limits as per the
performance standard prescribed by the State Electricity
Regulatory Commission.
The following table indicates the time standards
as prescribed by the Delhi Electricity Regulatory
Commission (DERC):
Table 4.8 Schedule for Inspection of Lines
Nature of Cause of Power
Supply Failure
Maximum Time Limit for Power Restoration
Fuse blown out or MCB
tripped
• Within three hours for urban areas.
• Within eight hours for rural areas
Service line broken,
snapped from the pole
• Within six hours for urban areas.
• Within 12 hours for rural areas.
Fault in distribution mains
• Temporary supply to be restored within four hours from
alternate source, wherever feasible.
• Rectification of fault and thereafter restoration of normal
power supply within 12 hours.
Distribution transformer
failed/burnt
• Temporary restoration of supply through mobile transformer or
another backup source within eight hours, wherever feasible.
• Replacement of failed transformer within 48 hours.
HT mains failed
• Temporary restoration of power supply within four hours
wherever feasible
• Rectification of fault within 12 hours.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
125
Unit-4 .indd 125
11-06-2019 16:21:59
Problem in grid 33 kV
substation
• Restoration of supply from alternate source, wherever feasible
within six hours.
• Roster load shedding may be carried out to avoid overloading
of alternate source.
• Repair and restoration of supply within 48 hours.
Failure of power
transformer
• Restoration of supply from alternate source, wherever feasible
within six hours.
• Roster load shedding may be carried out to avoid overloading
of alternate source.
• Replacement action to be intimated to the Commission
within 72 hours and replacement of power transformer within
20 days.
Burnt meter
• Restoration of supply by bypassing the burnt meter within six
hours.
• Replacement of burnt meter within three days
Street light complaint
• Restoration within 72 hours.
Check Your Progress
A. Fill in the blanks
1. Resistance opposes ___________ flow and inductance
opposes ___________ flow.
2. Load shedding is normally carried out when the power
___________ is more than the power ___________ at a
given point of time to shed excess load on the generating
station.
3. ___________ is used for cutting, removing insulation,
jointing and twisting the electric wires and cables even
on live line.
4. Bench vice is use to ___________ the object.
5. The flow of current towards an undesired path or
abnormal stoppage of current is termed as a ___________.
B. Multiple choice questions
1. The selection of poles for erection of lines depends on a
number of factors such as:
(a) Distribution of power
(b) Pole strength
(c) Type and size of conductor
(d) wind pressure
(e) All of above
(f) Only (a) and (c)
DISTRIBUTION LINEMAN — CLASS XI
126
Unit-4 .indd 126
11-06-2019 16:21:59
2. What are the causes of insulator damage?
(a) Due to difference in temperatures
(b) Improper calibration
(c) Broken service line
(d) None of the above
3. Current transformers are:
(a) Small transformer
(b) Supply low values of current
(c) Used where the current or voltage is too high
(d) (a) and (c)
(e) (a) and (b)
(f) (a), (b) and (c)
NOTES
C. Match the columns
Group A
Group B
1.
AAC
(a)
high-capacity, high-strength stranded
conductor
2.
ACSR
(b)
made out of high strength AluminumMagnesium-Silicon Alloy
3.
AAAC
(c)
made up of one or more strands of hard
drawn 1350 aluminum alloy
4.
Shackle
Insulator
(d)
mounted axially
D. Short answer questions
1. Why maintenance is important?
2. What maintenance should be done during pre monsoon
inspections?
3. What are the causes of insulation damage?
4. Why material testing equipment is required? Explain
with reasons.
REPAIR
AND
MAINTENANCE
OF
POWER DISTRIBUTION LINES
127
Unit-4 .indd 127
11-06-2019 16:21:59