Detail of Welder Welding
Detail of Welder Welding
Detail of Welder Welding
PREPARED BY : J. B. PATEL
45o
1F:
2F:
3F:
4F:
PREHEAT TEMPERATURE
Preheating is decided on basis of thickness of material,type of material and process. Reason to preheat: To slow down cooling rate. To reduce Thermal indifference. To control moisture and Hydrogen which will may create problem of crack and porosity. It is measured on base material T thickness from seam.
e.g:If interpass temperature is 275c temp stick available with welder is 250c He can use or not? Answer :Yes
Note :check interpass before starting another consecutive bead.Apply Temperature chalk t:thickness apart from weld seam on Base metal.
Parameter slip :It is a Slip given to welder containing welding parameters to be used during welding . Barcode (LEMF):Ensure Issue of barcode to each welder must be given of that particular seam only. For SMAW/GTAW:Bead Length For SAW/FCAW/GMAW:Travel Speed
Weaving :Allowed 3times diameter of Electrode. e.g : 3.15mm diameter electrode used 3.15x3=9.45mm allowed.
Bead length:It is the length of weld metal deposited on base metal by one single electrode. Dia(length):3(75mm),4(125mm) e.g:
Weaving and Bead length control must be there during welding joints having impact WPS. As more heat input will be there due to crossing above parameter which will leads to coarse grain structure, which is very hard and brittle in nature and at the end it fails in IMPACT TEST.
TEST PLAN
All Joints of jobs have seam no: for NDT identification. From test plan we can able to see each and every stage for NDT of particular seam. Note :move to further stage after completing NDT of above stage. BaaN system is available through we can offer seam for NDT to Inspection.
TEST PLAN
PTC:Production Test Coupon. Mentioned in Drawing and TEST PLAN. It is to be weld along with seam .
TEST PLAN
PTC is only mean to know properties by doing Destructive Testing. Note:Ensure PTC to be welded along with JOB. Failure of PTC is Failure in Job which will leads to cutting of that seam by raising NCR.
WELDING QUALIFICATION
Welder Qualification Qualification done as per ASME SEC IX. ASME SECTION IX:Welding and Brazing Qualification. WML:Welder Master List It is list of Qualified Welders working in organization through which we can get full information of welder.
WELDING QUALIFICATION
WML CONTAINS. a)STAMP NO:It is identification number given to welder. b)NAME:Name of the welder. c)TEST DATE:Date on which welder welded test coupon. d)SPOT CHECK DATE:Date on which spot check was done by L&T person.
WELDING QUALIFICATION
WML cont e) VALIDITY DATE:Date on which welders validity to weld on JOB vanish.Duration is of 6 months from the test date or Spot check date. f) WELDING PROCESS: e.g.SMAW/SAW/GMAW/FCAW etc. g) WPS NO:Welding Procedure Specification followed during welding test coupon. h) POSITION:Position of welding during welding test coupon (Specified above).
WELDING QUALIFICATION
WML cont i) THICKNESS OF TEST COUPON: Pipe or plate thickness to be mentioned that welded during welding test coupon. j) 1st P NO:Parent material no to be specified. k) 2nd P NO:Parent material no to be specified. l) DIAMETER(mm):Diameter of Pipe welded during welding Test coupon. m)1st F NO:Filler no used in welding qualification. n) 2nd F NO:Filler no Qualified with.
WELDING QUALIFICATION
WML cont
o) P NO: P no qualified with. p) POSITION:Position qualified with. q)THICKNESS:Thickness of weld metal qualified with.(GROOVE)/Thickness of base metal qualified with.(OVERLAY). r) DIAMETER(mm):Diameter qualified with. s) INSPECTION AGENCY:Name of inspection agency. t) CONTRACTOR: Name of contractor.
WELDING QUALIFICATION
A Mandatory Requirement from Codes /Stds / Regulations Qualification Tests in accordance with the Applicable Code / Standard / Regulation. Acceptance Criteria of Test Results as per the Code of Construction Qualification Records and Test Results to be Documented
WELDING QUALIFICATION
Qualification Requirements For Equipments to be Made as per ASME Boiler & Pressure Vessel Code
ASME Sec IX + Applicable Design Code (Sec.VIII Div I or II, Sec. I, Sec. III)
WELDING QUALIFICATION
WELDING QUALIFICATION
Ascertain the skill of a welder or a welding operator to Produce defect free/Sound weld Makes A Weld Coupon Using an Approved WPS of a Qualified Procedure. Weld Coupon Undergoes Soundness Test Each Qualified Welder Shall be Assigned by A Unique Welder Number Welders Qualifications Records Are Documented Performance Qualification limited to the essential variables of the Specific Process
WELDING QUALIFICATION
How To Qualify Groove Butt Weld Procedure? 1) Read & Understand ASME Sec. IX - Welding Data - Essential, Non Essential & Supplementary Essential Variables. - Test Requirements - Testing Procedures ASME Sec.II Part C. - Classification of Welding Consumable - Properties of Consumables
WELDING QUALIFICATION
CONT.. 2) Write A Welding Procedure Specification - WPS Provides Direction for A Specific Welding - WPS Shall Include All Essential, Supplementary Essential & Non Essential Variables - WPS Format Available in ASME Sec. IX. - Each WPS Shall be Assigned with A Unique Number.
WELDING QUALIFICATION
CONT 3) Prepare A Test Coupon As Per WPS - Coupon Size: Pair of 300 mm X 150mm Plate Or as Specified in WPS - All Other Details as per Written WPS - Complete the Welding by Reasonably Skilled Welder - All Welding Variables Shall be Used Within the Limit Specified in WPS. - All Variables Actually Used Shall be Documented as Annexure to PQR ( Procedure Qualification Record)
WELDING QUALIFICATION
CONT
4) NDT Of Weld Coupon - Optional X-Ray / Radiograph the Weld Joint ( Not a Code Requirement ) Mark Transverse Tensile & Guided Bends As Per QW461 Eliminate Defective Weld Portion If Any, while Marking the Test Specimens Preserve RT Report & X-Ray Film as Annexure to PQR
WELDING QUALIFICATION
CONT 5) Mechanical Tests Qw 451, Groove Weld. Up to 10 mm Thickness - Root Bend :- 1No - Face Bend :- 2No 10-19 mm Thickness - Side Bend :- 2No - OR Root Bend :- 1No Face Bend :- 1No Over 19mm Thickness - Side Bend :-2No
WELDING QUALIFICATION
Cont 6) Acceptance Criteria for Test Results. Bend Test (Qw 163) - Opening Not More Than 3.2 mm in Any Direction on Convex Surface Within the Weld & HAZ RT(Qw 191.2.2) - Read from code. ASME SEC IX
WELDING QUALIFICATION
Performance limits.(QW452.1b)GROOVE
Thickness t of Weld Metal in the Coupon in mm ( in) All Thickness of Weld metal Qualified
2t
Maximum To Be Welded
WELDING QUALIFICATION
GROOVE POSITIONS :QW461
Sr No.
1 2 3 4 5
Groove Position
1G Flat 2G Horizontal 3G Vertical 4G Over Head 5G
Pipe
Pipe Axis Horizontal in Rotation Pipe Axis Vertical NA NA Pipe Axis Fixed Horizontally Pipe Axis Fixed 45 inclined
Inclination of Axis in
0 -15 0 - 15 80 90 15 - 80 0 - 80 0 -15
6G
NA
+ or - 5
WELDING QUALIFICATION
Position & Dia Limits-: QW461.9
Qualification Test Position & Type of Weld Qualified Plate & Pipe Over 24
F F, H F,V F,O ALL SP & F
Weld
Position
1G 2G 3G 4G 2G, 3G &4G Spcl. Position
Pipe 24
F F&H F F F&H SP & F
Plate Groove
Pipe Groove
WELDING QUALIFICATION
Groove-Weld, Pipe Dia. Limits :QW 452.3
Out Side Dia. Qualified Out Side Dia. Of Test Coupon in mm ( in) Min. Less Than 25 (1) 25 (1) to 73 (2-7/8) Over 73 (2-7/8) Size Welded 25 (1) 73 (2-7/8) Max. Unlimited Unlimited Unlimited
Notes:1) Type & Number of Tests as per QW-452.1 2) 73 mm OD is equivalent to 2-1/2 NB Pipe 3) Welders Qualified on Groove, Are Also Qualified for making Fillets of all Sizes on Any Thickness & Any Pipe Dia.
WELDING QUALIFICATION
OVERLAY QUALIFICATION THICKNESS LIMITS
Thickness t of Base Thickness of Base metal metal in the Coupon in Qualified mm ( in)
Less than 1 in.(25mm)T T qualified to unlimited
1 in.(25mm) to unlimited
WELDING QUALIFICATION
INSTRUCTION DURING WELDING ON JOB
Welder Stamp punch: Stamp to be punch at 3feet OR 900mm interval of welding seam. Where to use punch and where to Engrave. ASME SECTION VIII DIV A. QW:37. Ferrous Non ferrous P >6mm >13mm E <6mm <13mm
WELDING QUALIFICATION
INSTRUCTION DURING WELDING ON JOB
Seam wise welders record to be kept by qualified contractor welding supervisor. Spot checks to be done at particular interval. Discrepancy must be reported to W.E. LEMF.
Welding Electrodes:Storage,Baking & Issue. Done as per procedure HED-HZW-WEL-P-007 Baking of Electrodes and Flux done as per procedure for electrodes Example:LOW HYDROGEN ELECTRODESE70XX E80XX Baking :250-300c for 2-2.5hrs Holding:100-120c till issue
Welding Flux: Normal e.g. UV420TTR FOR CS/LAS -Baking done at 300-325cfor 2 to 2.5hrs -Holding temp 130-170c till issue -Issue shall be held at 130-170c only after baking
WELD CONSUMABLE RELATED Issue: a) SMAW maximum 15nos electrodes at a time. b) SAW flux max 10kg at a time. c) ESSC/SASC flux maximum 25kg at a time. d) Filler wires and strips to be issued as required. Note: Electrodes to be issue in portable oven or vacuum packed condition only.
WELD CONSUMABLE RELATED Return: a) Return each and every weld consumable to issue stores.Dont keep it any where lying. b) Try to recover flux by flux recovery unit and return it to store. c) Stores:If flux particle size to be observed very small or lumps shall be discarded and the matter shall be informed to welding engineering.
Note:If any consumable found in contractors stores than Discrepancy will be given to contractor with penalty.
CS/LAS ELECTRODES
AMPERES VOLTS
e.g.:ENiCrFe3,ENiCrMo3 ELECTRODES `
ELECTRODE DIA AMPERES VOLTS
2.SAW PROCESS
e.g.: CS/LAS/SS/INCONNEL WIRE SPOOLS
AMPERES VOLTS T.Speed(mm/min)
ELECTRODE DIA
3.FCAW PROCESS
e.g. E308L,E309,ENiCrMo3
ELECTRODE DIA AMPERES VOLTS T.Speed(mm/min)
1.2MM(F6/F43)
160-200
20-32
290-400
4.GTAW PROCESS
e.g.ER70S2,ER80SB2.
ELECTRODE DIA AMPERES VOLTS T.Speed(mm/min)
1.6MM 2.4MM
80-110 110-140
10-15 10-15
50 50
55 55 50
1.2MM (F6/F43)
230-270
30-36
400-500
SMAW
CS
FCAW
CS SS
1.2 1.2
ACHIEVABLE WELD DEPOSITION RATE FOR VARIOUS WELDING PROCESSES (Kg PER Arc hour)
PROCESS NOELECTRODES
MATERIAL DIA
(mm)
CURRENT
(Amps) 550-580
DEPOSITIONRATE
(Kg per Arc hour) 6.5
SAW
CS
4.0
TWIN WIRE
SAW TANDEM ESSC
CS
2.4X2 550-580
2.4X2 750 570-600
6.6
8.9 14 22 33 42
CS SS
4.0
70 80 90
1 2 3 1
3.15mm
100-140
100
120 140
2 3 4 1 2 3 1 2 3
4mm
150-180
5mm
200-240
290 290 290 310 300 300 385 390 400 375 385 395 385 400 385 390 400 397 390 390 390 390 385 385 390 390
85 75 75 77 70 67 100 100 90 85 90 75 73 75 105 100 95 95 90 90 150 150 120 120 115 120
180 127 135 108 135 108 145 112.98 110 94.3 120 107.5 175 105 185 111.1 175 116.6 135 95.3 125 83.3 80 64 90 73.9 161 128.8 150 85.7 160 96 145 91.57 135 85.26 145 96.66 155 103.33 240 96 270 108 165 82.5 230 115 170 88.69 185 92.5
89.3 88.9
2.016 2.36
NCRs:NON CONFERMATIVE REPORT. It is defined as deviation from code standards,customer requirements for the job. NCRs can be given on: a)Base metal repair: for Welding please issue repair plan from welding engineering and repair. b)Arc-strike/NDT requirements after touch ups. NDT is must after touch ups(PT/MT) c)Un cleaned weld joints: Weld joints must be cleaned properly
Temporary attachment joints must be welded as per WPS specified in SWP. Buttering: e.g: Buttering must be at least 5mm. LAS buttering on CS moon plates for spiders. NDT to be perform properly on Temp joints to avoid defect in Base metal.
DEFECT MARKING a) Match the RT spot punch to tracing. b) Transfer Defect marking : Mark 100mm on both side of the defect. Start grinding as per marking. Ensure that Grinding must be in Proper direction with help of 100mmreference line marked on both side.
GENERAL /GOOD ENGINEERING PRACTICES As per code, required reinforcement for different thickness required UW:35
material nominal thk mm Less than 2.4 2.4-4.8 4.8-13 13-25 25-51 51-76 76-102 102-127 127 and above max reinforcement category B &C other 2.4 0.8 3.2 1.6 4.0 2.4 4.8 2.4 5.0 3.2 6.0 4.0 6.0 6.0 6.0 6.0 8.0 8.0
1. 2. 3. 4. 5. 6. 7. 8. 9.
GENERAL /GOOD ENGINEERING PRACTICES Importance of removal of slag and interpass cleaning. Cleaning between two consecutive bead should be done properly otherwise Slag inclusion will be there in weld metal which will not be permitted. Run in Run out: It is required as in starting and ending of arc chances of defects like: Pore/Improper bead overlap/Slag is more as there is much more variation in current and arc gap during starting and ending which leads to defects.
DHT :De-hydrogenation heat treatment. It is post heating of the LAS job where weld metal is >50mm to avoid hydrogen cracking in weld metal. It is generally done at 300-350c for 3.5 to 4 hrs.
Overlay to be properly overlap >=50% of bead for proper dilution to achieve chemistry.
DWT :Double welder Technique DOT :Double welding operator technique. Both method to be used for TSR Tray support ring or fillet weld for minimization distortion. L&T qualification requires :fillet welded Fracture test to be done.
GENERAL /GOOD ENGINEERING PRACTICES Categories of Weld Joints. A: All L/S in Nozzle,Dends,Shell,Cones (Hemispherical Dend # Shell) B: All C/S Nozzle# shell,Nozzle #Flange,Corner joints Dends(Ellipsoidal Dend # shell. C: Flange to Forgings D: Nozzle # Shell Lip type(butt)