Creating Task List in MS Project 2007
Creating Task List in MS Project 2007
Internet.
Check a project plans overall duration.
type Site Work and then press the enter key on your keyboard.
ID number
The default start date is the same as the project start date.
Excel?
From Microsoft Office Project Help: Click Open. In the Files of type box, click the file type you want to import data
from.
Click Open. Follow the instructions in the Import Wizard to import the data you
Workbooks (.xls)
Browse to the Microsoft Excel file, select it, and click Open.
10
11
choices are:
As a new project Append data to the active project Merge the data into the active project
Try appending.
12
13
tasks, so choose Tasks. Also, under Microsoft Office Excel Options, check off Import includes headers. And click Next.
14
15
header named Name in your Excel file with the field named Name in Project, which is the Task Name field in the Gantt chart.
16
17
or months.
Lets say that youve set up your project calendar with working
time defined as 8:00am through 5:00pm, with a one-hour lunch break, Monday through Friday.
If you estimate that a task will take 16 hours of working time,
18
complete?
The overall duration of a project is the difference between the
earliest start date and the latest finish date of its tasks.
A tasks duration and elapsed time are not necessarily the
same.
Working time and non-working time. Task relationships.
19
20
time. Like wait for concrete to cure or wait for paint to dry.
No ones on the clock during it. The next task after it is dependent upon its completion, though. Use the abbreviation ed, so 2ed is 2 elapsed days.
21
22
weeks, months:
Go to the Tools menu > Options
23
24
25
26
27
28
Milestone
29
30
values. Theyre derived, or rolled-up from the subtasks contained within the summary task.
Top-down and bottom-up planning
31
32
33
34
Summary Task
35
example, the task of Formwork must be completed before the task of Concreting can occur. These two tasks have a finish-tostart relationship (also called a link or dependency) that has two aspects:
The second task must occur later than the first task; this is a sequence. The second task can occur only if the first task is completed; this is a
dependency.
36
tasks. Likewise, any task can be a successor to one or more predecessor tasks.
37
Finish-to-start The finish date of the (FS) predecessor task determines the start date of the successor task. Start-to-start (SS) The start date of the predecessor task determines the start date of the successor task.
Pouring and leveling of concrete should occur simultaneously. SS dependencies generally occur because you want the work of two tasks to overlap.. Tasks that require specific equipment must end when the equipment rental ends. This type of relationship is rarely used.
Finish-tofinish (FF)
The finish date of the predecessor task determines the finish date of the successor task.
Start-to-finish The start date of the predecessor (SF) task determines the finish date of the successor task.
38
39
Highlight two tasks, and then on the Edit menu, click Link Tasks.
40
You can link summary tasks to each other. You can also link tasks right in the Gantt chart.
41
42
43
44
45
46
Project menu > Task Notes Right-click the task name, and choose Task Notes Screen tips
47
48
49
button.
Lets look at the current finish date and the current duration.
50
thing.
51
occurrence.
Task links, or relationships, cause the start or end of one task to affect the start
or end of another task. A common task relationship is a finish-to-start relationship in which the completion of one task controls the start of another task.
In Project, phases of a schedule are represented as summary tasks. You can document additional details using task notes and create hyperlinks to
the Internet.
The Project Information dialog box (Project menu) is an excellent way to
observe the key values of a project plan, such as its scheduled finish date and duration.
52
The original project plan, saved for later comparison. The baseline includes the planned start and finish dates of tasks and assignments and their planned costs. Each Microsoft Project file can have at most one baseline.
53
with the lowest-level tasks before organizing them into broad phases.
Top-down Planning: Developing a project plan by identifying
the highest-level phases or summary tasks before breaking them into lower-level components or subtasks.
Deliverable: The final product, service, or event a project is
intended to create.
54
A link between a predecessor task and a successor task. A dependency controls the start or finish of one task relative to the start or finish of the other task. The most common dependency is finish-to-start, in which the finish date of the predecessor task determines the start date of the successor task.
each task in a project. In the Entry table, the Task ID appears in the far left column.
55
to complete a task.
Elapsed Duration: The total length of working and
Chart view.
Field: The lowest-level information about a task, resource, or
56
Microsoft Project. The Gantt Chart view consists of a table (the Entry table by default) on the left side and a graphical bar chart on the right side.
Link: A logical relationship between tasks that controls
sequence and dependency. In the Gantt Chart and Network Diagram views, links appear as lines between tasks.
57
task
or
tasks
(predecessor),
called
Successor
task.
58
the project or imposed upon the project. In Microsoft Project, milestones are normally represented as tasks with zero duration.
Sequence: The chronological order in which tasks occur. A
sequence is ordered from left to right in most views that include a time scale, for example, the Gantt Chart view.
59
visually indicated by a link line. The types of relationships include finish-to-start, start-to-start, finish-to-finish, and startto-finish. Also known as a link, a logical relationship, a task dependency, or a precedence relationship.
60
on the screen and then clicking the right mouse button. Shortcut menus contain only the commands that apply to the item to which you are pointing.
Summary task: A task that is made up of and summarizes
the subtasks below it. In Microsoft Project, phases of project work are represented by summary tasks.
61
62