CHECK LIST FOR AUTOCLAVED AERATED CONCRETE BLOCK MASONRY


QA/446 A
Name Of Site :Name Of Sub Contractor

Sr.

DATE:-

Particulars

Before AAC Masonry Check

Availability of material

Line out rechecked.

Cleaning work area off loose material / concrete.

Hacking of concrete complete.

Proper stocking of AAC blocks.

Pre -Wetting of AAC Block slightly before use

Door, Window frames if any to be erected in position.

Door / Window frame plumb checked.

Provision of staging by as per approved material

10

Cutting tools & Equipments available on site.

II

During AAC Masonry Check

AAC block work using approved polymer Mortar. (Fixoblock or


eqvt.)

Availability of tray for mixing of mortar.

Yes

No

Water should add for mixing the Mortar by adding 30% water or
as per manufacturer specification.

Dry mixing in tray to be ensured before water addition.

5.

Consumption of mortar within 1/2 hour after addition of water.

Check for dimensional accuracy (Room size and diagonals etc)

Check for door / window opening sizes.

Provision for path / sill /holdfast.

Clearing dead mortar and AAC block to location of disposal.

10

Check for plumb / line / level of masonry.

11

Check for plumb! Line! Level of doors, windows.

12

Fixoblock or eqvt. Mortar buttered on Autoclaved Aerated


Blocks by using Patra for uniform coverage.

13

Fixoblock or eqvt. Mortar buttered on Autoclaved Aerated


Blocks by using Patra & after that makes the surface rough to
achieve strong Bonding.

14

Inside face of the Masonry unit should be buttered with mortar


before next unit laid on it.

15

Top layer of the Masonry unit should be provided by cutting


required height of the AAC block.

16

Chiseling done on Masonry unit by using approved cutting tools


& equipments.

17

Vertical & horizontal Joints should be maximum 3mm or


manufacturer specification for AAC block work.

III

After Masonry Check

Joints gap filled with polymer mortar on both side & beam
bottom portion.

Identification & date provided for each day element.

Remark

Site Engineer

Q.A. Engineer

Contractors Engineer