Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Fitting Loss Calculation

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 6
At a glance
Powered by AI
The document discusses how installing turning vanes in duct elbows can reduce pressure drop and save energy.

Installing turning vanes in duct elbows reduces the pressure drop compared to elbows without vanes. This is because vanes help guide the airflow through the turn with less turbulence.

Installing turning vanes reduces the static pressure in the duct, which lowers the fan horsepower needed. This saves fan energy and leads to annual energy cost savings.

HPCBS

High Performance Commercial Building Systems

Commissioning Guide for Air Handling Systems


Calculation Of Energy Savings through Improved Fitting Design

Calculating Fitting Pressure loss for high velocity ducts


Assumptions:

V =4, 005 p velocity


Therefore:
2
pvelocity = V
4, 005
V = Velocity in feet per minute
4,005 = A units conversion constant
pvelocity = Velocity pressure in inches water column

( )

p fitting =C o p velocity
Where:
p fitting =Fitting pressure loss in inches water column
Co =Local loss coefficient
pvelocity =Velocity pressure in inches water column, usually ( but not always)
based on entering velocity
Flow rate =
Designer's target design friction rate =

20,000 cfm
0.10 inches w.c. per 100 ft. of duct

Duct height =

24 inches

Duct width =

60 inches

Velocity =

2,000 fpm

oss coefficient for a mitered elbow with no turning vanes =

1.03 (from ASHRAE Handbook, fitting CR3-6)

Loss coefficient for a mitered elbow with turning vanes =

0.11 (From ASHRAE Handbook, fitting CR3-9)

Calculation:
Velocity pressure =

0.25 in.w.c.

Loss for the elbow with no turning vanes =

0.26 in.w.c.

Loss for the elbow with turning vanes =

0.03 in.w.c.

Difference (avoided pressure drop if vanes are installed) =

0.23 in.w.c.

File name = 271666934.xls, Page 1 of 6 of Sheet High Velocity loss Printed on 05/27/2015 at 15:37:00
Calculations are subject to user assumptions and inputs. PIER, LBNL, and PECI assume no responsibility for their application.

HPCBS

High Performance Commercial Building Systems

Functional Testing Guide for Air Handling Systems


Appendix D.2.5 Example 3 - Savings Associated with an Improved Duct Fitting Design at a Riser Connection

Assumptions:

QNew
QOld

( )

PNew = POld

Where:
PNew =The static pressure at the new flow condition to be evaluated .
POld = The static pressure at the old or original flow condition, usually the design condition.
Q New = The flow at the new flow condition to be evaluated .
Q Old = The flow at the old or original flow condition, usually the design condition.

Horsepower=

QPSaved
6, 356 FanStaticMotor

Where:
Horsepower=The horsepower saved at the terminals of the motor ( includes motor efficiency losses)
Q= The flow rate which is experiencing the reduction in static pressure in cubic feet per minute (cfm)
PSaved = The static pressure reduction associated with the improvement in inches water column (in . w. c .)
6, 356= A units conversion constant
FanStatic = The fan static efficiency
Motor= The motor efficiency
Savings associated with having the turning vanes =
System flow rate =

0.23 inches w.c.


20,000 cfm

Calculation:
Horsepower savings to be used for the energy calculation based on the reduced flow rate
Flow rate =
Static pressure reduction =
Assumed fan efficiency =
Assumed motor efficiency =

20,000 cfm
0.23 in.w.c.
75% (estimated)
89% (from energy efficient motor performance data in file)

Fan horse power reduction =

1.09 hp.

kW =

0.81 kW

File name = 271666934.xls,


Calculations are subject to the assumptions and inputs. PIER, LBNL, and PECI assume no responsibility thier application and use.

HPCBS

High PerformanceCommercial Building Systems

Functional Testing Guide for Air Handling


Systems
Appendix D.2.5 Example 3 - Savings Associated with an Improved Duct Fitting Design at a Riser Connection

Assumptions:
Constant volume system operation
Current system operating hours =
Operating hours after the first year =
Current electrical rate =
kW savings per hour at design flow =

2,860 hr/yr (5 days at 10 hr./day and 1 day at 5 hr./day, 52 wk/yr)


8,760 hr/yr
$0.0900 $/kWh
0.81 per hour (from previous calculation)

Calculation:
Annual savings at current operating schedule =
=
Annual savings at future operating schedule =
=

2,321 kWh
$209 per year
7,108 kWh
$640 per year

File name = 271666934.xls,


Calculations are subject to the assumptions and inputs. PIER, LBNL, and PECI assume no responsibility thier application and use.

HPCBS

High PerformanceCommercial Building Systems

Functional Testing Guide for Air Handling Systems


Appendix D.2.5 Example 3 - Savings Associated with an Improved Duct Fitting Design at a Riser Connection

Assumptions:

V =4, 005 p velocity


Therefore:
2
V
pvelocity =
4, 005
V = Velocity in feet per minute
4,005 = A units conversion constant
pvelocity = Velocity pressure in inches water column

( )

p fitting =C o p velocity
Where:
p fitting =Fitting pressure loss in inches water column
Co =Local loss coefficient
pvelocity =Velocity pressure in inches water column, usually ( but not always)
based on entering velocity
Flow rate =
Designer's target design friction rate =

350 cfm
0.10 inches w.c. per 100 ft. of duct

Duct height =

6 inches

Duct width =

12 inches

Velocity =

700 fpm

oss coefficient for a mitered elbow with no turning vanes =

1.03 (from ASHRAE Handbook, fitting CR3-6)

Loss coefficient for a mitered elbow with turning vanes =

0.11 (From ASHRAE Handbook, fitting CR3-9)

Calculation:
Velocity pressure =

0.031 in.w.c.

Loss for the elbow with no turning vanes =

0.031 in.w.c.

Loss for the elbow with turning vanes =

0.003 in.w.c.

Difference (avoided pressure drop if vanes are installed) =

0.028 in.w.c.

File name = 271666934.xls,


Calculations are subject to the assumptions and inputs. PIER, LBNL, and PECI assume no responsibility thier application and use.

HPCBS

High PerformanceCommercial Building Systems

Functional Testing Guide for Air Handling Systems


Appendix D.2.5 Example 3 - Savings Associated with an Improved Duct Fitting Design at a Riser Connection

Assumptions:

Q New
Q Old

( )

PNew = POld

Where:
PNew =The static pressure at the new flow condition to be evaluated .
POld = The static pressure at the old or original flow condition, usually the design condition.
QNew = The flow at the new flow condition to be evaluated .
QOld = The flow at the old or original flow condition, usually the design condition.

Horsepower=

QPSaved
6, 356 FanStatic Motor

Where:
Horsepower=The horsepower saved at the terminals of the motor ( includes motor efficiency losses)
Q= The flow rate which is experiencing the reduction in static pressure in cubic feet per minute (cfm)
PSaved = The static pressure reduction associated with the improvement in inches water column (in . w. c .)
6, 356= A units conversion constant
FanStatic = The fan static efficiency
Motor = The motor efficiency

Savings associated with having the turning vanes =


System flow rate =

0.028 inches w.c.


350 cfm

Calculation:
Horsepower savings to be used for the energy calculation based on the reduced flow rate
Flow rate =
Static pressure reduction =
Assumed fan efficiency =
Assumed motor efficiency =

350 cfm
0.028 in.w.c.
75% (estimated)
89% (from energy efficient motor performance data in file)

Fan horse power reduction =

0.002 hp.

kW =

0.002 kW

File name = 271666934.xls,


Calculations are subject to the assumptions and inputs. PIER, LBNL, and PECI assume no responsibility thier application and use.

HPCBS

High PerformanceCommercial Building Systems

Functional Testing Guide for Air Handling


Systems
Appendix D.2.5 Example 3 - Savings Associated with an Improved Duct Fitting Design at a Riser Connection

Assumptions:
Constant volume system operation
Current system operating hours =
Operating hours after the first year =
Current electrical rate =
kW savings per hour at design flow =

2,860 hr/yr (5 days at 10 hr./day and 1 day at 5 hr./day, 52 wk/yr)


8,760 hr/yr
$0.0900 $/kWh
0.002 per hour (from previous calculation)

Calculation:
Annual savings at current operating schedule =
=
Annual savings at future operating schedule =
=

5 kWh
$0.45 per year
15 kWh
$1.37 per year

File name = 271666934.xls,


Calculations are subject to the assumptions and inputs. PIER, LBNL, and PECI assume no responsibility thier application and use.

You might also like