Integral Bridges
Integral Bridges
Integral Bridges
VOLUME 1
SECTION 3
HIGHWAY STRUCTURES:
APPROVAL PROCEDURES
AND GENERAL DESIGN
GENERAL DESIGN
PART 12
BA 42/96 AMENDMENT NO. 1
THE DESIGN OF INTEGRAL BRIDGES
SUMMARY
This Advice Note provides guidance on the design of
continuous bridges with integral abutments.
INSTRUCTIONS FOR USE
This is an amendment to be incorporated in the Manual.
1.
2.
3.
May 2003
BA 42/96
Amendment No. 1
Summary:
This Advice Note provides guidance on the design of continuous bridges with
integral abutments.
Volume 1 Section 3
Part 12 BA 42/96
Registration of Amendments
REGISTRATION OF AMENDMENTS
Amend
No
May 2003
Page No
Amend
No
Page No
Volume 1 Section 3
Part 12 BA 42/96
Registration of Amendments
REGISTRATION OF AMENDMENTS
Amend
No
Page No
Amend
No
Page No
May 2003
VOLUME 1
SECTION 3
HIGHWAY STRUCTURES:
APPROVAL PROCEDURES
AND GENERAL DESIGN
GENERAL DESIGN
PART 12
BA 42/96 AMENDMENT NO. 1
THE DESIGN OF INTEGRAL BRIDGES
Contents
Chapter
May 2003
1.
Introduction
2.
General
3.
Earth Pressure
4.
References
5.
Enquiries
Volume 1 Section 3
Part 12 BA 42/96
Chapter 1
Introduction
1. INTRODUCTION
1.1 Expansion joints in bridge decks are prone to
leak and allow the ingress of de-icing salts into the
bridge deck and substructure, thereby resulting in
severe durability problems. To overcome these
problems, bridge decks up to 60 metres in length and
with skews not exceeding 30 are generally required to
be continuous over intermediate supports and integral
with their abutments. (See BD 57, DMRB 1.3.7). This
Advice Note covers the design of integral highway
bridges without expansion joints.
1.2 Integral bridges are designed without any
expansion joints between spans or between spans and
abutments. Resistance to longitudinal thermal
movements and braking loads is provided by the
stiffness of the soil abutting the end supports and, in
some cases by the stiffness of the intermediate supports.
ii)
iv)
i)
v)
May 2003
vi)
Frame Abutment
End support for bridge constructed integrally
with the deck and acting as a retaining wall for
adjoining pavement and ground below.
vii)
Granular Backfill
Selected granular material placed adjacent to the
abutment wall and forming the subgrade for the
adjoining pavement construction.
Embedded Abutment
End support for bridge comprising a diaphragm
wall (including contiguous, or secant or sheet
pile walls) with toe embedded in ground below
lower ground surface.
Definitions
1.6 The following are definitions of terms used in the
Advice Note.
Scope
1.3 This Advice Note is applicable to bridges of
steel, concrete and composite construction, including
precast and prestressed concrete, with thermally
induced cyclic movements of each abutment not
exceeding 20mm and skews not exceeding 30.
Abutment
ix)
Integral Bridge
A bridge with integral abutments.
1/1
Chapter 1
Introduction
x)
Volume 1 Section 3
Part 12 BA 42/96
Pavement/Abutment interface
The interface between the pavement construction
and the back face of the abutment.
xi)
Range
Change (of temperature, strain) between extreme
minimum and extreme maximum.
xii)
Stationary Point
The point on a bridge in plan which does not
move when the bridge experiences expansion or
contraction during changes in bridge temperature.
Surfacing
Carriageway or footway wearing course and base
course materials.
Implementation
1.7 This Advice Note should be used forthwith for all
schemes currently being prepared provided that, in the
opinion of the Overseeing Organisation, this would not
result in significant additional expense or delay
progress. Design Organisations should confirm its
application to particular Schemes with the Overseeing
Organisation.
1/2
May 2003
Volume 1 Section 3
Part 12 BA 42/96
Chapter 2
General
2. GENERAL
2.1 Integral bridges should support all the relevant
dead loading and live loading including all longitudinal,
and in the case of structures which are curved in plan,
centrifugal loading, in accordance with BD 37 (DMRB
1.3.14). They should also accommodate the effects of
thermal expansion or contraction without excessive
deformation of the approach pavements.
Types of Integral Construction
2.2 This Advice Note has been drafted for the types
of integral abutment illustrated in Figure 2.1 and
described below:
i)
ii)
iii)
iv)
May 2003
1.0 @ SLS
ii)
2/1
Chapter 2
General
Volume 1 Section 3
Part 12 BA 42/96
Thermal Effects
Piers
steel
(Groups 1 & 2) 0.0006
steel with concrete deck (Group 3) 0.0005
concrete
(Group 4) 0.0004
For the definition of the above-mentioned groups, see
Figure 9 of BD 37 (DMRB 1.3.14). However, the 1.3
factor on the design range of movement at the ultimate
limit state given in Clause 5.4.8.1 of BD 37, should not
be applied to the characteristic thermal strains given
above.
2.11 The above characteristic strains are based on the
following assumptions:
i)
ii)
2/2
May 2003
Volume 1 Section 3
Part 12 BA 42/96
Chapter 2
General
May 2003
2/3
Volume 1 Section 3
Part 12 BA 42/96
Chapter 3
Earth Pressure
3. EARTH PRESSURE
General
3.1 Based on experimental and analytical data the
following design recommendations are made for the
magnitude of lateral earth pressures to be adopted in the
design of integral bridge abutments in the U.K.
Soil Strength and Wall Friction
3.2 An increase of stiffness of granular soil occurs
due to densification of the fill under the thermal cyclic
movements induced by deck expansion. Even if the fill
is placed in loose condition, it will be densified during
the lifetime of the structure (12). Therefore representative
cpeak and peak for the fill material, compacted at the
optimum moisture content to a dry density of 95% of
the maximum dry density determined in accordance
with BS 1377: Part 4(5) using the vibrating hammer
method, should be used throughout the design.
3.3 In a conventional retaining wall, following
BS 8002(4), design tan would then be calculated using
a mobilization factor M = 1.2, on representative
tanpeak and applied to calculate active and at rest
earth pressure coefficients. However, the passive earth
pressure mobilised by a granular backfill on an
abutment of an integral bridge moving towards the
backfill would act in an unfavourable manner. For this
reason, the approach of Eurocode 7(8) Clause 2.4.2 is
adopted in which the factor of M = 1/1.2, i.e. a value of
< 1, is applied to representative tanpeak to determine
design tan for passive earth pressure calculations. The
factor M is applied to the representative value of
tanpeak to allow for variation in the backfill properties
and to ensure that an upper bound value for passive
earth pressure can be determined. Where the source of
the backfill material is known and the upper bound
values of peak have been established, the designer may
justify an increase in the value of M up to unity. When
this is done, site testing must be carried out on the
backfill material to verify its properties remain within
the design upper bound values of peak.
Wall friction should be taken as = design /2.
May 2003
3/1
Chapter 3
Earth Pressure
(b)
Volume 1 Section 3
Part 12 BA 42/96
3/2
May 2003
Volume 1 Section 3
Part 12 BA 42/96
Chapter 3
Earth Pressure
May 2003
3/3
Chapter 3
Earth Pressure
Volume 1 Section 3
Part 12 BA 42/96
Figure 3.2 Earth Pressure Distribution for Full height Embedded Wall Abutments
3/4
May 2003
Volume 1 Section 3
Part 12 BA 42/96
Chapter 4
References
4. REFERENCES
1.
Design Manual for Roads and Bridges
(DMRB): TSO
BD 24 Use of BS 5400: Part 4: 1990. (DMRB 1.3.1)
BD 28 Early Thermal Cracking of Concrete.
(DMRB 1.3)
BD 30 Backfilled Retaining Walls and Bridge
Abutments. (DMRB 2.1)
BD 31 Buried Concrete Box Type Structures.
(DMRB 2.2.12)
BD 33 Expansion Joints for Use in Highway Bridge
Decks. (DMRB 2.3.6)
BD 37 Loads for Highway Bridges. (DMRB 1.3.14)
BD 57 Design for Durability. (DMRB 1.3.7)
BA 26 Expansion joints for use in highway bridge
decks. (DMRB 2.3.7)
BA 57 Design for Durability. (DMBR 1.3.8)
2.
Manual of Contract Documents for Highway
Works (MCHW): TSO
Specification for Highway Works. (MCHW)
3.
British Standard BS 5400: Part 4: 1990. Code of
Practice for the Design of Bridges. BSI
9.
Darley P, D R Carder and G H Alderman (1996).
Seasonal thermal effects on the shallow abutment of an
integral bridge in Glasgow. TRL Project Report 178.
Crowthorne: Transport Research Laboratory.
10. Darley P and G H Alderman (1995).
Measurement of thermal cycle movements on two
portal frame bridges on the M1. TRL Project Report
165. Crowthorne: Transport Research Laboratory.
11. Springman S M, A R M Norrish and C W W Ng
(1996). Cyclic loading of sand behind integral bridge
abutments. TRL Project Report 146. Crowthorne:
Transport Research Laboratory.
12. England G L, Tsang N C M and Bush D I.
Integral Bridges A fundamental approach to the timetemperature loading problem. Thomas Telford, 2000.
13. Darley P, Carder D R and Barker K J. Seasonal
thermal effects over three years on the shallow
abutment of an integral bridge in Glasgow. Transport
Research Laboratory Report 344, 1998.
14. Goh C T. The behaviour of backfill to shallow
abutments of integral bridges. PhD Thesis University of
Birmingham, 2001.
15. Barker K J and Carder D R. Performance of an
integral bridge over M1-A1 Link Road at Bramham
Crossroads. Transport Research Laboratory Report 521,
2001.
4.
British Standard BS 8002: 1994. Code of Practice
for Earth Retaining Structures. BSI
5.
British Standard BS 1377: Part 4: 1990. British
Standard Methods of Test for Soils for Civil
Engineering Purposes; Compaction related tests. BSI
6.
Hambly E C (1991). Bridge Deck Behavior;
2nd ed., E&FN Spon.
7.
Kerisel J and Absi E (1990). Active and Passive
Earth Pressure Tables, Balkema, Rotterdam.
8.
Draft for development DD ENV 1997-1: 1995.
Eurocode 7: Geotechnical design, Part 1.General rules
(together with United Kingdom National Application
Document).
May 2003
4/1
Chapter 5
Enquiries
Volume 1 Section 3
Part 12 BA 42/96
5. ENQUIRIES
All technical enquiries or comments on this Advice Note should be sent in writing as appropriate to:
Divisional Director
Room 913
Sunley Tower
Piccadilly Plaza
Manchester
M1 4BE
Andrew Jones
Divisional Director
J HOWISON
Chief Road Engineer
J R REES
Chief Highway Engineer
Transport Directorate
D OHAGAN
Assistant Director of Engineering
May 2003
5/1