Pole Slip Protection
Pole Slip Protection
Case studies
B. Pavlov
NEK, EAD
Bulgaria
I. INTRODUCTION
Significant changes of load as well as faults and
their clearance in power systems often result in
electromechanical oscillations, which generally do
not affect the system stability. Major disturbances
might on the other hand cause bigger oscillations,
which can influence unwanted operation of different
protection functions and in the most severe cases loss
of synchronism (out-of-step or so called pole slip
conditions) between generator groups located in
different subsystems.
In the paper we concentrate on so called
asynchronous operation of power systems, which
may characterize the operation of individual
generating units as well as their groups (power plants)
connected in parallel with the power system or even
the operation of two interconnected power systems.
The asynchronous mode of operation is
characterized by deep active and reactive power
oscillations with time limited constant excitation of
synchronous machines. It produces important
disturbances to the power system operating
parameters, to the quality parameters of delivered
electrical power, causes severe electric and mechanic
D. Paunescu, F. Lazar
Transelectrica
Romania
1
Bulgaria represented by NEK EAD and Romania represented
by Transelectrica are regular UCTE members from 08 May 2003.
239
PSP 2004
Case studies
EL
ER
Q() - left generator
4000
L= const
R= f(t)
ZSL
2000
ZSR
ZL
REL
P()
0
40
80
K increasing
2000
1000
SR
X
Q =
X
+
E
X
2
L
80
120
160
200
240
280
320
360
3000
deg
sin( )
(2)
cos ( ) +
Reactive power at k = 0.8 to 1.2
Here is
40
2000
E E
1000
X
X
SL
1 + k 2 k cos ( )
2
k = E
E
(3)
(4)
k = E
4000
K increasing
3000
Q(k) [Mvar]
P=
360
3000
E E
320
Power [MW]
280
deg
SL
240
6000
200
4000
160
Q() - at B bus
2000
120
E
2000
1000
40
80
120
160
200
240
280
320
360
1000
deg
.
240
PSP 2004
Case studies
B. Equal area criterion
So far only active and reactive power flow
depending on generator angle and k factor have been
observed. The first part of a so called P() powerangle characteristic as presented in Figure 2 serves
also as a basis for the dynamic system stability
studies, based on a known equal area criterion (Figure
5).
We consider the right side generator (see Figure 1)
as an infinitely strong power system. The left side
generator supplies during normal operating conditions
active power, which is equal to the mechanical power
Pmech of a turbine. The angle between the generator
when
I
REL
E E
E e
E e
(5)
1.2
U
Adec
Asm
0.8
REL
P [pu]
Z
0.4
REL
Aacc
I
REL
(6)
SL
U
I
REL
= Z + Z
SL
acc
60
eqv
mech
REL
30
90
deg
120
150
180
impedance points
k = E
1
1 k e
j (
(7)
Z
SL
and ( Z
+ Z
SR
) . This point is
acc
acc
P ( )
between the
Pmech
= E e
PSP 2004
Case studies
systems.
called
120
60
k=0.9
150
30
k=0.8
k=1.0
180
0
0
500
1500 []
1000
k=1.2
210
330
k=1.1
240
300
270
U [V]
600
800
1000
1200
1400
1600
1800
2000
1200
1400
1600
1800
2000
on
impedance
Z t
oscillation
50
400
based
100
200
A. Oscillation detection
measurement
Z t
90
50
100
t [ms]
4
200
400
600
800
1000
EXT
I [A]
jX
INT
OSC
&
t [ms]
Figure 8:
Z t
detection
Oscillation OSC is detected if the impedance
measured in relay point needs to enter the internal
boundary INT with time delay longer than the time
delay t set on time measuring element after it has
entered the external boundary EXT. It should be noted
that the time element needs an adaptive time delay,
which must be for consecutive slips shorter than the
initial time delay for the first slip. This is of outmost
importance in order to distinguish between fast
consecutive slips and slowly developing faults, which
appear for example in series compensated networks or
during slowly developing earth faults (e.g. when the
fault develops over an ice coat around the phase
conductor).
PSP 2004
Case studies
B. Oscillation detection
measurement
based
on
U.cos()
U REL cos ( ) = E cos
2
(8)
UREL
EL
Figure 10: UCTE and area included in systemwide disturbance 11 September 2001
ER
/2
E L = ER = E
243
PSP 2004
Case studies
120
1600
100
1400
1200
80
P [MW]
Z(-85ms)
Z(-185ms)
Z(-285ms)
Z(-385ms)
Z(-485ms)
Z(-35ms)
Z(-135ms)
Z(-235ms)
Z(-535ms)
Z(-335ms)
Z(-435ms)
Z(0sec)
200
0
0
120
48
44
46
42
40
38
36
32
34
30
26
28
24
22
16
18
20
14
-200
12
100
10
80
60
R [ohm]
2
4
40
20
-10
T = 1.7 sec
fs = 0.59 Hz
= 2.12.3%
> 3%
400
-2
20
600
-6
-4
40
800
-8
jX [ohm]
1000
60
Time, sec
P[MW]
1040
dP2/dt2=0 MW/s
1030
1020
1010
1000
990
980
970
960
950
-600
-500
-400
-300
t[ms]
-200
-100
PSP 2004
Case studies
80
60
BG
jX, Ohm
40
Kozloduy
20
Tantareni
-20
-40
-120
RO
-100
-80
-60
-40
-20
20
40
60
80
100
120
R, Ohm
Figure 14: Impedance trajectory as seen by pole slip protection in Tantareni S/S after a three-phase fault at
Kozloduy S/S
245
PSP 2004
Case studies
must detect oscillations caused by faults and similar
big changes in power system as well as oscillations,
which appear during emergent system operating
conditions.
It is recommended to implement pole slip
protection independently on distance protection of the
same power line. This way both protection functions
will operate with their optimal settings and
functionality for line fault conditions (distance
protection) as well as for the wider system
disturbances (pole slip protection). Simultaneous use
of specific distance protection zones for the purposes
of pole slip protection in general does not provide the
optimal solution, because the settings required for one
and another functionality contradict each other.
Measured impedance changes very fast from prefault load conditions (-120 + j25) ohm to impedance
marking the end of protected line (Kozloduy). Fault
clearance also presents fast change in measured
impedance to approximately (0 + j25) ohm. Here
starts slower movement of impedance in
anticlockwise direction and exits the impedance
measuring area completely. The oscillation would
continue further on and even change its direction to
the clockwise one, if it would be permitted to continue
without any action from the installed pole slip
protection.
Measured impedance trajectory enters the external
impedance boundary again at approximately (-17 +
j60) ohm and with time delay longer than 40 ms (set
value) also the inner impedance boundary at (-17 +
j40) ohm.
This is sufficient condition for protection to
declare system oscillation. Big generation units
behind line ends do not permit long oscillations with
more than one slip.
The pole slip protection is for this reason set to
trip the corresponding circuit breaker even before the
complete slip really appears, in this case when the
measured impedance reaches the left incoming
tripping line at approximately (-5 + j28) ohm.
The operating characteristic of the pole slip
protection applied provides a possibility to control the
tripping conditions with respect to the phase angle
between EMFs of power generators in both
subsystems. This prevents additional stresses of
primary equipment. It also provides remote back-up
possibilities for swings with their ECO behind the
remote ends of the protected line (see the area around
the Kozloduy S/S in Figure 14).
VII. REFERENCES
1. Y G Painthankar, 2000, Transmission Network
Protection Theory and Practice
2. ABB Manual 1MRK 506 074, 06-2001
3. F. Ilar: Innovations in the Detection of Power
Swings in Electrical Networks, 1986, ABB document
CH-ES 35-30.10E
VIII. BIOGRAPHIES
Janez Zakonjek (Janez.Zakonjsek@se.ab.com)
obtained his Master Degree in Power Engineering
1977 at University of Ljubljana, Slovenia. Since than
he has been working in the field of power system
protection, firstly in ISKRA, Slovenia and since 1991
in ABB Sweden. His main interest is protection of
complex network configurations. Currently he holds a
position of senior application specialist in ABB
Automation Technologies, Sweden. He is a member
of different international organizations and currently a
convener of CIGR working group for protection of
series compensated networks.
Bozhidar Pavlov (Bpavlov@ndc.bg) has M.Sc.
Degree in Electrical Engineering from the Sofia
Technical University, Bulgaria. Since his graduation
he has been working for the Bulgarian National
Electric Company. From 1983 to 1987 he was a NEK
representative at the Central Dispatching Office of
IPS (Prague) as a relay protection engineer. After his
return to NEK he became a transmission planning
engineer and currently he is the Head of the
Transmission Planning and System Analyses
Department at the National Dispatching Center of
Bulgaria. International activities: Member of the
UCTE WG Operation & Security; Acting secretary of
the Technical Committee UCTE/Romania-Bulgaria.
Doru Mircea Paunescu
VI. CONCLUSIONS
Asynchronous operating conditions are a fact in
modern power systems and should be eliminated as
fast as possible in order to keep their stronger parts in
normal operation. Introduction of pole slip protection
on tie lines proved to be one of the best solutions.
This requires comprehensive stability studies under
different operating conditions and in many cases also
excellent cooperation of experts from different
utilities, and even different countries.
Impedance and its time derivative measurement
provide in a moment still the best information on
system oscillations and possible asynchronous run of
their parts.
Operating characteristics of applied pole slip
protection devices must secure correct operation
under different system operating conditions. They
246
PSP 2004
Case studies
(DPaunescu@transelectrica.ro)
received
his
Master Degree in power engineering 1967 from
Electrical Department of Cluj Technical University in
Cluj Romania. He joined IRE Bucharest as an
electrical engineer immediately after studies and
worked between 1970 and 1974 as an Expert Engineer
in the Bucharest Area Dispatch center. In 1974 he
joined as an Expert Engineer the Ministry of Energy.
Mr. Paunescu worked between 1982 and 1990 as a
Head of Protection & Automation Department in the
Dispatch Center of the East European Power System
in Prague. He headed the Protection & Automation
Department within the National Dispatch Center of
Romania between 1990 and 2000, when he was
appointed to his current position: Chief Inspector of
247
PSP 2004
Case studies
APPENDIX
Simplified operating scheme of a system on Balkan Peninsula 11 September 2001 at the event of major
disturbence
Drmno
400 kV
Djerdap
400 kV
Portile de Fler
400 kV
(300MW)
(850MW)
250MW
(250MW)
850MW
(300MW)
OPEN LINE
(100MW)
(1100MW)
150MW
1000MW
450MW
Slatina
400 kV
0MW
OPEN LINE
(1000MW)
RO
Urechesti
400 kV
1000MW
(450MW)
Tantareni
400 kV
(0MW)
(300MW)
1400MW
(150MW)
CONNECTED
NETWORK
150MW
1000MW
400MW
Isaccea
400 kV
Kozloduy
400 kV
OPEN LINE
100MW
YU
CONNECTED
NETWORK
(150MW)
Bor
400 kV
(300MW)
1150MW
Dobrudja
400 kV
CONNECTED
NETWORK
Sofia West
400 kV
Chervena Mogila
400 kV
Blagoevgrad
400 kV
BG
GR
248
Thessaloniki
400 kV