Fidic Letters by Consultantt
Fidic Letters by Consultantt
Fidic Letters by Consultantt
Engineer
The clause to be delegated might be some or all of the fifty clause where the Engineer is
referred to. Delegation should not normally be considered in respect of clause
41,44,48,62,63,65,67, and 69.
Engineer
The clause to be revoked may be some or all of the clauses previously
delegated.
To
The Contractor
Dear Sir
Notice of Dissatisfaction with an instruction issued by the Engineers
Representative
We write to acknowledge receipt of your letter dated concerning
an instruction No . Given by my Representative and concerning
Whilst your expression of dissatisfaction has been noted I confirm the instruction as
issued and give this response pursuant to Clause 2.3(b) of the conditions.
Yours faithfully
Engineer
The engineers response may also be to withdraw the instruction or to
vary it by issuing further instructions.
4- Consent to Sub-let
Date..
To
The Contractor
Dear Sir
Consent to Sub-let
Further to your letter dated seeking permission to subcontract certain
elements of the work we are writing to give our consent pursuant to Clause 4.1 of
the Conditions for the following items of works to be subcontracted.
Item of work
Company
Yours faithfully
Engineer
Regardless of the above consents the Contractor will be fully responsible
for any defaults of the Subcontractor as if they were caused by the
contractor himself and it would be prudent for the Engineer to draw
attention to this fact.
5- Clarification of Ambiguity
Date..
To
The Contractor
Dear Sir
Clarification of Ambiguity
We thank you for your letter dated drawing our attention to the
difference between the description in the Bill of Quantities item .. and
specification item page number ..
This is agreed and pursuant to Clause 5.2 of the Conditions we hereby instruct you
to .
Yours faithfully
Engineer
The Engineer may of course not accept that there is any ambiguity and will then
write to give a clarification if necessary and to instruct the Contractor to proceed
with the works as specified.
Date..
To
The Contractor
Dear Sir
Notice of delay in the issue of information
We thank you for your letter dated and issued pursuant to Clause 6.3 of
the conditions in which you have claimed that non receipt of information is causing
you delay and additional cost to the works.
We have examined your program for the works which illustrates that the
information referred to is not yet required and your actual progress on site is not
such as to reasonably require such information to be available.
Under these circumstances we are unable to accept that your notice is a valid one.
Yours faithfully
Engineer
Should the contractors notice be regarded as valid the Engineer is required to
confirm this and determine the extension of time which should be granted and the
amount of extra cost if any which should be added to the Contract Price.
Date..
To
The Contractor
Dear Sir
Notice of not Foreseeable Physical Obstructions or Conditions
We acknowledge receipt of your letter dated .. giving notice pursuant to
clause 12.2 of the Conditions of the encountering of physical obstructions in the
form of ..which in your opinion were not foreseeable by an experienced
Contractor.
We have carefully examined the information which was made available to you at
the tender stage namely ..and have to advice you that we consider the
matter to be one which was wholly foreseeable pursuant to Clause 12 of the
conditions and have therefore to reject your notice and claim for an extension of
time and additional cost.
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Notice of Not Foreseeable Physical Obstruction or Conditions
I acknowledge receipt of your letter dated . Giving notice pursuant to
Clause 12.2 of the conditions of the encountering of physical obstructions in the
form of ..which in your opinion were not foreseeable by an experienced
contractor.
I have examined the facts put forward by you and after my consultations with you
and the Employer I have determined pursuant to Clause 12.2 that the extension of
time to which you are entitled under Clause 44 shall be and the amount of
the costs to be added to the contract price shall be ..
Yours faithfully
Engineer
9- Program to be submitted
Date..
To
The Contractor
Dear Sir
Program to be submitted
We are writing to draw you attention to the requirement pursuant to Clause 14.1 of
the Conditions to submit within the time stated in part II of the conditions a
program for the works together with a method statement setting out a general
description of the arrangements and methods which you are proposing for the
execution of the works.
The form and method of program presentation required is that set out in the tender
documentation but should you require any further clarification please do not
hesitate to contact me.
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Setting out
We refer to your letter dated in which you advice us of an error in setting
out and construction as a result of incorrect data on our drawing No ..
We therefore require you to rectify this error and pursuant to Clause 17.11 have
determined that the amount of shall be added to the Contract price in
accordance with Clause 52 of the Conditions.
Yours faithfully
Engineer
The Contractor is required to rectify any error, if required to do so by the
Engineer, at his own cost unless the error is based on incorrect
information or data supplied in writing by the Engineer.
11- Fossils
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Fossils
Thank you for your letter dated .. advising of the discovery on site of
Following my consultation with you and the Employer, I have determined pursuant
to Clause 27.1 that the extension of time to which you shall be entitled under
Clause 44 of the conditions will be . And the amount of the costs to
be added to the Contract Price will be
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Notification of damage arising from the transport of materials or plant
Thank you for your letter dated .. enclosing details of a claim received
from the roads (or bridges) Authority.
As provided for in Clause 30.3 it is my opinion that the claim received from the
Authority is due to your failure to comply with the obligations under Clause 30.1
Following my discussions with you and the Employer I have determined that the
sum recoverable from you as a result of your failure will be . And the
amount will be deducted by the Employer from sums which may become due to
you.
Yours faithfully
Engineer
Engineer
Date..
To
The Contractor
Dear Sir
Returns of labor and Contractors Equipment
As previously advised, I require you to provide weekly returns of staff, labor and
plant employed on the Works and in the format discussed with you.
These returns are to cover the whole of your own resources and also those of
approved subcontractors and are requested pursuant to Clause 35.1 of the
Conditions.
Yours faithfully
Engineer
To
The Contractor
(Copy to Employer)
Dear Sir
Cost of Tests not provided for
I refer to your letter dated .. confirming that testing has been carried out in
accordance with my instruction No .
As these tests were not provided for in the Contract I have, after examination of
records and consultations with you and the Employer determined pursuant to
Clause 44 will be . And the amount of the costs which shall be added to the
Contract price will be ..
Yours faithfully
Engineer
To
The Contractor
Dear Sir
Dates for Inspection and Testing
Following our agreement on the time and place for the inspection and/or testing of
the .. I am now writing pursuant to Clause 37.3 to give you the required
notice (not less than 24 hrs) of my intention to carry out the inspection/or attend
the tests.
Yours faithfully
Engineer
The Contractor
Dear Sir
Independent Inspection
I am unable to provide the specialized equipment for the inspection and testing of
.
I am therefore in accordance with Clause 37.5 writing to give you notice that I have
delegated this responsibility to an independent inspector whose duties and
scope of authority will be.
This appointment will become effective on the
Yours faithfully
Engineer
Not less than 14 days notice is to be given
The Contractor
(Copy to Employer)
Dear Sir
Uncovering and making openings.
I refer to my instruction to you to uncover .. (Or make an opening
through) pursuant to Clause 38.2 of the Conditions.
As the work has been found to have been executed in accordance with the Contract
I have after due consultation with you and the Employer determined that
..representing your costs in respect of such uncovering (or making
openings) reinstating and making good the same shall be added to the contract
price.
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Default of Contractor in compliance
I refer to my instruction and adted
We have agreed that the materials referred to were not in accordance with the
Contract and that you are in default by not removing these within the time
specified.
I have therefore after consultationn with you and the Employer determined
pursuant to Clause 39.2 that the costs which the Employer shall be entitled to
recover from you and which may be deducted by the employer from any monies
due or to become due to you shall be ..
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Yours faithfully
Engineer
Date..
To
The Contractor
Dear Sir
Commencement of Works
In accordance with Clause 41.1 of the Conditions I hereby give you notice to
commence the works as soon, as is reasonably possible.
You are required to proceed with the works with due expedition and without delay.
For the purposes of the Contract the Commencement Date will be the receipt by
you of this notice.
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Thank you for your letter dated advising that you have suffered delay
and incurred costs from the failure on the part of the Employer to give possession
of Site Area
This has arisen due to factors beyond the Employers control and the matter has
now been resolved.
Following my consultations with you and the Employer I have determined pursuant
to Clause 42.2 that the extension of time to which you are entitled under Clause 44
shall be .. And that the amount of cost to be added to the Contract Price is
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
I refer to your letter dated . And issued pursuant to Clause 44.2 (a) of
the Conditions advising of the following event .. which was such as to
fairly entitle you to an extension of time for completion of the works.
After my consultation with you and the employer, I have determined pursuant to
Clause 44.1 that the extension of time to which you shall be entitled will be
.. in respect of the following event
Yours faithfully
Engineer
Date..
To
The Contractor
Dear Sir
Rate of Progress
Having considered these I give you notice that for reasons, which do not entitle you
to an extension of time, the rate of progress of the works (or any Section) is in my
opinion too slow to comply with the time for completion.
You are therefore required to take such steps as are necessary, subject to my
consent to expedite progress so as to comply with the time for completion.
This notice is given as required by Clause 46.1 of the conditions and it should be
noted that you shall not be entitled to any additional payment for taking such
steps.
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Rate of Progress
Further to my letter to you dated .. Requiring you to take such steps as
are necessary to expedite progress I must advice you that the measures consented
to will involve additional supervision costs.
Following my consultation with you and the Employer regarding these I have
determined pursuant to Clause 46.1 that the additional supervision costs which
shall be recoverable from you by the Employer and may be deducted by the
Employer from monies due or to become due to you amount to ..
Yours faithfully
Engineer
Dear Sir
Taking-Over Certificate
We are in agreement with the above and hereby certify that in our opinion the
works were substantially completed in accordance with the contract on
Yours faithfully
Engineer
The engineer shall also notify the contractor of any defects in the works
affecting substantial completion that may appear after such instructions
and before completion of the works specified therein.
The Contractor
Dear Sir
Taking-Over Certificate
We write pursuant to Clause 48.1 of the conditions to give you notice that the
following items of defect have appeared in the works:
Item 1 ..
Item 2 ..
These have appeared since instructions were issued to you specifying all the work
which in our opinion was required to be done before the issue of a Taking-Over
Certificate.
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
1. .
2. .
3. .
Have been substantially completed and have satisfactory passed any tests on
completion prescribed by the contract on ..
By the issue of this certificate you are now deemed to have undertaken to complete
with due expedition any outstanding work in the parts of the permanent works
listed above during the defects liability period.
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
It has been agreed that the following items of work . Carried out
after the expiration of the defects liability period are attributable to fair wear and
tear.
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Following your failure to carry out our instructions to remedy defects, we have after
consultation with you and the Employer, determined pursuant to Clause 49.4 of the
Conditions that the costs which the Employer shall be entitled to recover from you
and which may be deducted by the Employer from any monies that are or will
become due to you are ..
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Contractor to Search
We have therefore after consultation with you and the Employer determined
pursuant to Clause 50.1 of the Conditions that the amount in respect of the costs of
the search carried out by you to be added to the contract price is
Yours faithfully
Engineer
32- Variations
Date..
To
The Contractor
Dear Sir
Variations
You are hereby instructed to carry out the works listed in the attached variation
Order which is issued pursuant to Clause 51.1 of the Conditions.
The effect, if any, of these variations shall be valued in accordance with Clause 52.
Yours faithfully
Engineer
Clause 52.1, 52.2 and 52.3 require that the Engineer gives notice to the Contractor that after consultation with
both the Contractor and the Employer suitable rates or prices have been agreed and in the event of non
agreement the Engineer will determine the rates or price or such sums are to be added to the Contract Price.
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Payment of Claims
Having received from you detailed particulars of the amounts claimed and the
grounds upon which your claim is based we have pursuant to Clause 53.5 of the
Conditions determined that the amount in respect of your Claim No. to
which you are entitled to have included in interim payment Certificate No.
will be .
Yours faithfully
Engineer
Date..
To
The Contractors Authorized Agent
Dear Sir
Works to be measured
In accordance with Clause 56.1 of the Conditions we give notice of our requirement
for the following parts of the work to be measured:
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
In accordance with Clause 58.1 of the conditions we have determined that the
amounts to which you are entitled in respect of the work, supply or contingencies
to which the following provisional sums relate are as follows:
.
..
Amount determined:
Yours faithfully
Engineer
Date..
To
(Copy to Contract and Employer)
Dear Sir
We certify that pursuant to Clause 59.5 of the Conditions the contract has failed to
provide reasonable proof that payment, less retention, included in previous
certificates due to .. a nominated subcontractor has been paid or
discharged, and has failed to satisfy us in writing that he has reasonable cause for
withholding or refusing to make such payments or to produce to us reasonable
proof that he has so informed the above named nominated Subcontractor in
writing.
Yours faithfully
Engineer
Date..
To
The Employer
(Copy to Contractor)
Dear Sir
___________________________
..
.
_____________________________
Yours faithfully
Engineer
Date..
To
The Employer
(Copy to Contractor)
Dear Sir
We have pleasure in certifying pursuant to Clause 62.1 of the Conditions that the
date on which the Contractor has completed his obligations to execute and
complete the works and remedy any defects therein to our satisfaction was
.
Yours faithfully
Engineer
Date..
To
The Employer
(Copy to Contractor)
Dear Sir
Default of Contractor
We hereby certify in accordance with Clause 63.1 of the Conditions that in our
opinion the Contractor has
Engineer
Date..
To
(Copy to Employer and Contractor)
Dear Sir
We hereby certify in accordance with Clause 63.3 of the Conditions that at the time
of the Employers entry upon the site and termination of your employment the
amount which had been reasonably earned by you or which reasonably accrue to
you in respect of work than actually done by you under the contract was
. And that the value of any unused or partially used materials, any
contractors Equipment and Temporary works is .
Yours faithfully
Engineer
Date..
To
(Copy to Employer and Contractor)
Dear Sir
We hereby certify that the sum due to the Contractor upon the due completion of
the contract amounts to after the deduction of the Employers
costs stated above.
Yours faithfully
Engineer
Should there be a balance of monies due to the Employer then this is payable on demand.
The Employer shall not be liable to pay the Contractor any further monies until the expiration of the defects liability
period when this certificate should be issued.
Date..
To
Copy to Contractor
Dear Sir
We write to give you notice pursuant to Clause 64.1 of the Conditions that an event
of emergency has occurred in connection with the works and in the nature of
This will in our opinion necessitate urgent remedial action by you for the safety of
the works.
Yours faithfully
Engineer
Should the contractor be unable or unwilling at once to do such work the Employer shall be entitled to employ
others.
If such work was, in the opinion of the Engineer, work for which the Contractor was liable then the Engineer shall
after due consultation with the Employer and the Contractor determine the amount which shall be recoverable
from the Contractor.
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
Now that the damage to the works has been rectified we have pursuant to Clause
65.3 of the Conditions determined that .. Should be added to the
contract price in accordance with Clause 52
Yours faithfully
Engineer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
After our consultation with you and the Employer, we have determined pursuant to
Clause 65.5 that the amount of your costs which shall be added to the contract
price will be
Yours faithfully
Engineer
Date..
To
The Contractor
Dear Sir
Outbreak of War
I am writing to give notice pursuant to Clause 65.5 that due to the outbreak of war
which has materially affected the execution of the works I am with immediate
effect terminating your contract.
Yours faithfully
Employer
Date..
To
The Contractor
(Copy to Employer)
Dear Sir
The provisions of the Clause shall apply and once we have all the appropriate
information we shall after due consultation with you and the Employer determine
any sums which are payable.
Yours faithfully
Engineer