Handbook On DevelopmentBuilding Works in RailwayProtectionZone PDF
Handbook On DevelopmentBuilding Works in RailwayProtectionZone PDF
Whilst every effort is made to ensure that the information and materials provided are correct, the Land
Transport Authority does not warrant their accuracy, adequacy or completeness and expressly
disclaims liability for any errors or omission in such information and materials.
The information contained herein is to be used only as a reference and is not intended to exempt any
person from otherwise complying with the Rapid Transit System (Development and Building Works in
Railway Protection Zone) Regulations and the Rapid Transit System (Railway Protection, Restricted
Activities) (Amendment) Regulations.
The Land Transport Authority shall in no event be liable for any damages, losses or expenses including
without limitation direct, indirect, special or consequential damage or economic loss arising from any
reliance on the contents of this disc. This exclusion clause shall take effect to the fullest extent
permitted by law.
The Copyright of the contents in this disc is owned by the Land Transport Authority. No part or parts
hereof maybe reproduced, distributed, republished, displayed, broadcast or transmitted in any manner
or by any means or stored in any information retrieval system without the prior written permission of
the Land Transport Authority.
Any unauthorised reproduction or distribution is prohibited. Infringers will face both criminal
prosecution and civil action.
Handbook on
Development &
Building Works
in Railway
Protection Zone
January 2005 Edition
All rights reserved. No part of this publication may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the Development
and Building Control Department, Land Transport Authority.
PREFACE
Contents
Page
Guide to Users of Handbook
1
2
3
4
5
6
Introduction
Structure of handbook
Step-by-step guide
Referencing of code and handbook
Glossary of acronyms
Useful references
1
1
2
3
4
4
1.4
1.5
5
6
6
6
7
7
7
7
7
9
9
9
10
10
Deemed-to-Satisfy Provisions
Chapter 2 Site preparation works
2.1
Mobilisation works
2.1.1 Demarcation of reserve lines
2.1.1.1 Above ground RTS structures
2.1.1.2 Underground RTS structures
2.1.2 Storage of materials
2.1.2.1 Allowable imposed load on RTS structures
2.1.3 Erection of temporary structures
2.1.4 Access under viaduct
11
11
11
13
14
15
16
18
Page
2.2
Demolition works
2.2.1 Method of demolishing buildings
2.2.2 Method of demolishing station structures
2.2.3 Monitoring of vibration levels
19
19
21
23
3.3
24
25
25
27
31
32
32
32
32
33
36
4.2
4.3
4.4
38
38
41
42
51
53
57
57
57
66
68
68
Chapter 5 Instrumentation
5.1
5.2
5.3
5.4
5.5
Introduction
Planning considerations
Criteria for monitoring
5.3.1 Ground and RTS structure monitoring
5.3.2 Structure and track limits
Monitoring of RTS structure
5.4.1 Total movement in any direction (underground RTS)
5.4.2 Differential movement in transverse plane
5.4.3 Differential movement along the track
Monitoring of RTS track
5.5.1 Track distortions
5.5.2 Twist
5.5.3 Vertical dip or peak
70
71
77
77
77
77
77
78
79
79
79
80
81
Page
5.6
5.7
82
82
82
84
90
90
Alternative Solutions
Chapter 6 Alternative Solutions
6.1
6.2
6.3
92
92
93
94
96
97
98
99
100
1.
Introduction
Interpretation of requirements
Application of requirements
Illustrative figures
Tables
Case examples
2.
Structure of handbook
This handbook has been structured in an easy to read manner as shown in the
diagram below:
Deemed-to-Satisfy Provisions
Chapter 2 Site preparation works
Alternative Solutions
Chapter 6 Alternative Solutions
3.
Step-by-step guide
Use
of
down-the-hole
drilling technique (see
Figure 3-7)
Use of percussively driven
concrete piles, steel H-piles,
sheet-piles or timber piles,
etc.
Use of rock chopping
chisels
Use of vibratory method of
installing or extracting
sheetpiles, H-piles or steel
casings (see Figure 3-8)
Helpful illustrative
figures are provided to
aid the user in
understanding the
requirements of the
Code.
Figure 3-6
View of a hydrofaise machine
Above Ground
Structures
Daily
Twice weekly
Daily
Twice weekly
Daily
Nil
(Trice weekly -critical
cases only)
Table 5-1
Typical instrumentation & frequency for construction
activities within the railway protection zone
Case examples
This section discusses three examples of
development sites within the railway
protection zone that have adopted the
alternative solutions approach. They are:
4.
Part
Section
Clause
Clause
Clause
Drawing
Table
Chapter
Section
Paragraph
5.
Glossary of acronyms
QP Qualified Person
6.
Useful references
Chapter 1
Meeting Performance Requirements
Quick preview
The primary consideration in railway protection is publics safety. In this context,
the Code has identified a set of objectives and the performance requirements. The
objectives spell out the basic criteria that need to be satisfied to ensure safety of
the rapid transit systems. To meet these objectives, performance requirements are
spelt out. These provide quantifiable means for architects, engineers and
contractors to work out suitable solutions using the appropriate assessment
methods. This chapter provides further insight into the above objectives,
performance requirements, solutions and assessment methods.
Objectives
Performance requirements
Solutions
Assessment methods
Part II
Diagram 7.1
1.2 Objectives
The objectives (as given in Part II Section 8 of the Code)
define broadly the goals to be fulfilled for the protection of the
railway.
Part II
Clause 7.1(a)
Structural safety
Operational safety
Fire safety
Flood protection
Part II
Clause 7.2
Clause 8.1
Part II
Clause 8.2
Part II
Clause 8.3
Part II
Clause 8.4
Part II
Clause 8.5
Part II
Clause 8.6
1.4 Solutions
In order for designers to provide innovative and creative
solutions which are practical and technically sound, the Code
allows the architects, engineers, contractors, etc. to choose any
of the processes below in developing a solution:
a combination of above
Part II
Clause 7.1
Structural Safety
Operational Safety
Fire Safety
Figure 1-2
Performance provisions applicable to development and building located
adjacent to above ground RTS station and viaduct
Structural Integrity
Operational Safety
Fire Safety
Flood Protection
Figure 1-3
Performance provisions applicable to development and building linked to an
underground RTS station
Part II
Clause 7.3
Verification methods
Expert judgement
Part II
Clause 7.3(a)
Part II
Clause 7.3(b)
Part II
Clause 7.3(d)
Part II
Clause 7.3(d)
10
Chapter 2
Site Preparation Works
Quick preview
In this chapter, we present the salient safety considerations for carrying out
mobilisation and demolition works in the railway protection zone. Acceptable
practice of demarcating RTS reserve lines on site, method of carrying out
mobilisation works, demolition works, etc. are explained with photographs taken
from development sites. These good practices should be considered to ensure the
safety of the railway.
Part II
Clause 9.2.1
Clause 9.2.2
Part II
Clause 9.2.1(a)
11
6m
500x300mm
Red Flag
MRT/
LRT
Viaduct
Pole
(To PEs Design)
450x450mm
Metal signboard
White base with red
wording
1ST RESERVE
Footing
(To PEs Design)
Note: Demarcation poles must not be spaced at more than 15m interval
Figure 2-1
Demarcation details for first reserve line of above ground RTS
Figure 2-2
Provision of first reserve line demarcation on site
12
Min 450mm
1st
Reserve
450mm
Min
Visible
Height
13
Figure 2-4
Prominent display of MRT third reserve on site
Part II
Table 9.1(a)
14
Kentledge
RTS tunnels
under the road
Silos
1s Reserve
Figure 2-5
Placing of heavy equipment, erection of silos, setting up of kentledge, etc. at
the above site arel outside the 1st reserve
Zone of
Influence
RTS Tunnel
6m
6m
Figure 2-6
Allowable imposed load forRTS structures not under the roadway
15
Part II
Clause 9.2.1(b)
Part II
Clause 9.4.5
16
6m
1st Reserve
Non-Combustible
hoarding
Figure 2-7
Non-combustible hoarding located below and within 6m from the edge of
viaduct is constructed using non-combustible material
Figure 2-8
A 2 hours fire rated hoarding for works site within station
17
Temporary
passageway
Closed
passageway
Figure 2-9
A safe and protected temporary passageway is provided during the
construction of a commercial development
Part II
Clause 9.2.1(c)
18
Figure 2-10
Temporary height restriction gantries are provided on both sides of the
viaduct beam
Part II
Clause 9.2.2
Part II
Clause 9.1.4
19
Figure 2-11
Use of a crusher for demolition helps to minimise the impact of vibration
20
Part II
Table 9.1.4
Part II
Clause 9.4.4.3
Figure 2-12
Stitch coring method for cutting wall panels helps to minimise vibration and
noise levels
21
Figure 2-13
Use of a diamond saw for cutting station structure helps to minimise
vibration and noise levels
Figure 2-14
Use of a diamond wire saw for cutting station structure helps to minimise
vibration and noise levels
22
Figure 2-15
Use of a hydro-jet for demolition helps to minimise dust, fire hazard,
vibration and noise levels
23
Chapter 3
Substructure Works
Quick preview
This chapter discusses the considerations for carrying out excavation and
construction of substructure works in the railway protection zone. Requirements
relating to the set back of these substructures from the RTS structures, acceptable
method of construction in the railway protection zone, etc. are illustrated with
sketches and photographs.
Part II
Clause 9.1
Clause 9.3.1
For footings and rafts within the 1st reserve, the following
requirements must be complied with:
Part II
Table 9.1(a)
24
MRT
Column
Footing
Figure 3-1
Footing constructed next toMRT column
Construction method
Part II
Clause 9.1
Clause 9.3.2
Part II
Table 9.3.2
25
First Reserve
3m
clear
6m clear
RTS Tunnels
Figure 3-2
Above pile configuration may be considered on case-by-case basis
26
Part II
Table 9.3.2
Table 9.1(b)
Figure 3-3
Pile installation by augering method
27
Figure 3-4
Pile installation by oscillatory method
Figure 3-5
Sheetpile installation by a silent piler
28
Figure 3-6
View of a hydrofaise machine
Use of percussively driven concrete piles, steel Hpiles, sheet-piles or timber piles, etc.
Part II
Clause 9.1.4
29
Figure 3-7
Pile installation by down-the-hole drilling technique
Figure 3-8
View of a vibro-hammer
30
3.2.3 Debonding
To prevent any load transfer, load bearing piles (except those
supporting light structures) located within the zone of influence
of the underground (see Figure 3-9) and transition RTS
structures are to be debonded.
Part II
Clause 9.3.3
LTA/DBC/CPRP/001
LTA/DBC/CPRP/002
LTA/DBC/CPRP/008
LTA/DBC/CPRP/009
1st
reserve
2nd
reserve
Double Casing
Debonding
3m
clear
6m
clear
Single Casing
Debonding
45 deg
allow
tolerance
RTS Tunnels
construction
tolerance
Figure 3-9
Care must be taken to protect the debonding membranes from any damage
during installation
31
Debonding
membrane
Spacer
Figure 3-10
Spacer provided to prevent the debonding membranes from any damage
during installation
Part II
Clause 9.3.4
Table 9.3.4
Part II
Clause 9.1
Clause 9.3.7
32
33
Strut
Figure 3-11
Struts and bracing help to minimise ground movement due to excavation
34
Excavation in
compartment
Figure 3-12
Carrying out excavation in small compartments helps to minimise ground
movement
Earth Face
Grout piles seal up the gaps
Figure 3-13
Grout piles can be used to seal up any gaps in temporary earth retaining
wall
35
Part II
Clause 9.1
Clause 9.3.6
36
Part II
Clause 9.1.4
Break-in
Construction
Shaft
TBM
Treated poor
ground
Figure 3-14
Precautions to be taken during tunnelling works
37
Chapter 4
Building Works
Quick preview
In this chapter, technical requirements relating to the carrying out of building works
in the railway protection zone are highlighted. Four scenarios are considered,
namely, a building adjacent to an above ground RTS structures, a building below a
RTS viaduct, a building over a trainway and a building that interfaces or integrates
with the RTS station.
Building setback
Part II
Clause 9.1
Clause 9.4.1
6m clearance; or
Part II
Clause 9.4.1.1(a)
38
Part II
Clause 9.4.1.1
Diagram 9.4.1.1(a)
Note: X must comply with the distance stipulated in the Fire Code
Figure 4-1
Separation distance - viaduct outside development boundary
Part II
Clause 9.4.1.1
Diagram 9.4.1.1(b)
Note: Y must comply with the distance stipulated in the Fire Code or at least 6m
from the outermost edge of viaduct
Figure 4-2
Separation distance viaduct within development boundary
39
Part II
Clause 9.4.1.1
Diagram 9.4.1.1(c)
Note: X must comply with the distance stipulated in the Fire Code
Figure 4-3
Separation distance station outside development boundary
Part II
Clause 9.4.1.1
Diagram 9.4.1.1(d)
Note: Y must comply with the distance stipulated in the Fire Code or at least 6m
whichever is greater
Figure 4-4
Separation distance entrance (without habitable room) within development
boundary
40
Part II
Clause 9.4.1.1
Diagram 9.4.1.1(e)
Note:
Z1 & Z2 must comply with the distance stipulated in the Fire Code.
Z1 + Z2 must be at least 6m
Figure 4-5
Separation distance - station entrance (with habitable room) within development
boundary
Part II
Clause 9.4.1.1(b)
41
Figure 4-6
A multi-storey car park with faade opening facing the viaduct is provided with
a protective screen
Figure 4-7
A multi-storey car park with faade opening facing the viaduct is provided with
a protective screen
Part II
Clause 9.4.2.2.1(a)
Part II
Clause 9.4.2.2.1(b)
42
Provide 2-hour fire rated wall and roof within 6m from the
edge of the viaduct. The fire rated wall must meet the criteria
of stability, integrity and insulation. If sprinkler protection is
provided, the fire resistance rating can be reduced to at least 1
hour (see Figure 4-8). There must be no opening on the firerated roof. For windows and other openings on the fire-rated
walls, 2-hour fire rated doors or shutters must be provided.
Part II
Clause 9.4.2.2.1(c)
Part II
Clause 9.4.2.2.1(d)
Part II
Clause 9.4.2.2.1(e)
Part II
Clause 9.4.2.2.1(f)
Part II
Clause 9.4.2.2.1(h)
Part II
Clause 9.4.2.2.2(a)
Part II
Clause 9.4.2.2.2(b)
Part II
Clause 9.4.2.2.2(c)
Part II
Clause
9.4.2.2.2(d),(e)
Part II
Clause 9.4.2.2.3(a)
Part II
Clause 9.4.2.2.1(g)
Part II
Clause 9.4.2.2.3(b)
43
Figure 4-8
Fire separation for building under RTS viaduct
Figure 4-9(a)
Provision of sprinkler for building under RTS viaduct
44
Figure 4-9(b)
Provision of sprinkler for building under RTS viaduct
Note: Where sprinkler is provided in a building, the sprinkler systems
flow switch can be allowed to activate the fire alarm system. In such case,
detector(s) may be omitted in sprinkler protected areas.
Figure 4-10
Provision of automatic fire alarm system for building under RTS viaduct
45
Figure 4-11
High fire hazard material is prohibited within building
under RTS viaduct
Figure 4-12
Cooking facilities and cooker hood (if any) provided with fire
protection system for building under RTS viaduct
46
Min. 750mm
Figure 4-13
A convenience store located under the viaduct
Figure 4-14
Land below the viaduct can be used to locate shops
47
Figure 4-15
Land below the viaduct can be used to locate a caf
Figure 4-16
Land below the viaduct can be used to locate an eatery
48
Figure 4-17
Land below the viaduct can be used to locate a fitness centre/ station
Figure 4-18
Land below the viaduct can be used to locate a park
49
Figure 4-19
Land below the viaduct can be used to locate a children playground
Figure 4-20
Land below the viaduct can be used to locate a bicycle park
50
Figure 4-21
Land below the viaduct can be used to locate a linkway
Part II
Clause 9.1
Clause 9.4.3.1
51
Figure 4-22
Fire safety requirements for building above and around RTS viaduct
Figure 4-23
View of structures above and around the trainway
52
Part II
Clause 9.1
Clause 9.4.4
Clause 9.4.4.1
53
Figure 4-24
Development integrated with the entrance of an underground RTS station
Figure 4-25
Development integrated with an entrance of an underground RTS station
54
Figure 4-26
Development integrated with an entrance of an underground RTS station
Figure 4-27
Development linked to an underground RTS station
55
Door to
Firemens Staircase
Figure 4-28
Development interfaced with existing RTS fire staircase
Extended
Vent Shaft
Figure 4-29
Building with RTS ventilation shaft extended from the existing one at ground
level
56
Part II
Table 9.1(a)
Part II
Clause 9.4.4.2.1
Clause 9.4.4.2.1(a)
Point of Safety
Figure 4-30
Point of safety is at ground level outside the station entrance
57
Part II
Clause 9.4.4.2.1(b)
Part II
Clause 9.4.4.2.1(c)
External
Corridor
PROPOSED BUILDING
Fire Separation
No
unprotected
opening
>3 m
>3 m
STATION
ENTRANCE
No unprotected
opening
500 mm deep
smoke barrier
Building Line
Figure 4-31
Locations of fire separation, no unprotected opening and smoke barrier at
interface
58
Proposed building
Interface boundary
Sectional View
Figure 4-32
Provision of smoke barrier at interface
Part II
Clause
9.4.4.2.1,(d),(e),(f)
59
Slab Above
Station public
area fire alarm
ITB
S
Link to Station
Passenger Service
Centre by developer
Ceiling
S
Development
immediate zone fire
alarm signal system
Legends
S
Boundary line
RTS Premises
Integrated Development
Smoke Detectors
Interface Terminal Box
(ITB)
Shutter Control Box
Figure 4-33
Typical arrangement for fire shutter at interface of RTS and development
Figure 4-34
Provision of fire-rated shutters at interface of proposed building with an
underground RTS station
60
Figure 4-35
An automatic fire shutter at the interface between a commercial development
and station entrance
Figure 4-36
An automatic fire shutter at the interface between the commercial development
and station entrance
61
Automatic door
Figure 4-37
View of an enclosed entrance at RTS station
Exit capacity must not be less than the existing exit capacity.
Part II
Clause 9.4.4.2.1(g)
62
Existing
Entrance
New
Entrance
Figure 4-38
Provision of a new station entrance at a commercial development
Part II
Clause 9.4.4.2.2
Separation with
fire shutter
Figure 4-39
Building linked to RTS station
63
Fire Separation
CONCOURSE PAID AREA
ANCILLARY
AREA
++
++
++
++
++
SC R
CONCOURSE UNPAID
AREA
Figure 4-40
Location of fire separation between a proposed underground link and an
existing station
Part II
Clause 9.4.4.2.3
64
Door to
Firemens
Stairs
Part II
Clause 9.4.4.2.3(f)
65
Firemens Breeching
inlet and intercom
<18m
Part II
Clause 9.4.5(d)
Part II
Clause 9.4.4.3
Part II
Clause 9.4.4.3(a)
Part II
Clause 9.4.4.3(d)
Part II
Clause 9.4.4.3 (e)
66
Above flood
threshold level
Entrance of
Development Link
to RTS's Station
Figure 4-43
Raised entrance at commercial development linked to RTS station
Swan neck
connection
Flood threshold level
Ground level
Integrated
structure
Sump
Figure 4-44
Swan neck connection for a discharge pipe
67
Part II
Clause 9.4.4.3(c)
Non-combustible temporary
shelter over opening
4.4.1.4 Watertightness
The joint between a proposed building and a RTS station must be
watertight at all time to prevent ingress of water into the station.
At least two levels of defence against water ingress must be
provided at every interface. The waterproofing system provided
must be robust and able to withstand the calculated hydrostatic
pressure and differential movements between the connecting
structures.
Part II
Clause 9.4.4.4
Part II
Clause 9.4.4.5.1
68
Electrical services
protection, etc.
including
power
supply,
lightning
69
Chapter 5
Instrumentation
Quick preview
Instrumentation is an important provision for monitoring the effects of engineering
works. It has to be effective to capture the changes in ground conditions and the
effects on RTS. This will require understanding of the design of the RTS, the
ground conditions in its vicinity and the critical areas to monitor. In this chapter, the
considerations for planning instrumentation proposal are discussed. Key criteria for
monitoring RTS will be explained with examples of typical instrumentation for
monitoring. Some case studies for past development sites within the railway
protection zone are also included to illustrate compliance with the Code for
different situations.
5.1
Introduction
5.1.1
5.1.2
Part II
Section 4
70
5.1.3
5.2
Planning Considerations
5.2.1
Ground conditions
Development proposal
Construction activities
5.2.3
5.2.4
Part II
Clause 4.2
Part II
Clause 4.3
71
5.2.5
5.2.6
20m
INFLUENCE ZONE
Part II
Clause 4.3.8
Clause 4.6.3
20m
MRT tunnels
Development
with basement
construction
Figure 5-1
Influence zone and extent of monitoring
5.2.7
72
5.2.8
5.2.9
5.2.10
5.2.11
5.2.12
5.2.13
Part II
Clause 4.3.3
73
Figure 5-2
Total station in bored tunnel
5.2.14
74
Figure 5-3
Tagging of cables for identification of monitoring company &
development project
5.2.15
GSM
RTS
Monitoring
System
LT
Figure 5-4
Automatic data transmission to LTA's office
75
5.2.16
Prisms
Figure 5-5
Prisms installed in viaduct beam soffit
5.3
5.3.1
5.3.1.1
5.3.2
Part II
Clause 4.3
76
5.3.2.1
5.4
5.4.1
5.4.1.1
Part II
Tables 9.1(b) to
9.1(e)
Part II
Table 9.1(b)
Original position
Shifted position
Inclinometer
(i
d)
x1
y1
A1
m1
m1 = resultant displacement
Figure 5-6
Interpretation of total movement in any direction
5.4.2
5.4.2.1
Part II
Table 9.1(b)
77
Original tunnel
A1
Y-axis
Deformed tunnel
1:1000
1:1000
B1
B
X-axis
Acceptable zone of
movement of point A
Notes:
Point A moves to A1
Point B moves to B1
Figure 5-7
Differential movements in transverse plane
5.4.3
78
1:1000(limit)
A1
Shifted position
B
A
Point A & B - initial positions
Point A1 - new position
Figure 5-8
Differential movement in longitudinal plane
5.5
5.5.1
Track distortions
The allowable track distortions in the Code are
applicable for the rapid transit systems that run on rail
and not for LRT system which has rubber wheels. These
are not absolute values but relative values obtained
before development works and values measured during
the works. Track distortion criteria are dependent on the
bogie spacing of the RTS cabin as shown in Figure 5-9.
Part II
Table 9.1(e)
79
A
B
Figure 5-9
Typical bogie axle spacing of trains used for NSL, EWL and NEL
5.5.2
Twist
80
Figure 5-10
Track twist measurement
5.5.3
Crown of rail
V1 mm
5 m Chord
Average vertical dip = [V 1+V2]/2 (to be < 5mm)
V2 is to be measured in a similar manner from the
crown of the adjacent rail
Figure 5-11
Vertical dip or peak measurement
81
5.5.4
Horizontal versine
Similar to vertical peak or dip, horizontal versine is a
measurement of the change in horizontal curvature over
a 16m chord, the distance between two sets of bogies in
a carriage (see Figure 5-12). Again the average value for
the 2 rails is used. It should be noted that the existing
rail may have a design curvature and monitoring is
checked based on the change in condition before
development work commences.
16m chord
H1
H2
Crown
of rails
Average horizontal versine = [H1+H2]/2 < 6mm)
Figure 5-12
Horizontal verine measured over the centres of 2 sets of bogie
spaced at 16m
5.6
5.6.1
5.6.1.1
5.6.1.2
82
5.6.1.3
Figure 5-13
Layout plan for ground instruments
83
Figure 5-14
Layout plan for tunnel instrument
5.6.2
5.6.2.1
84
5.6.2.2
5.6.2.3
5.6.2.4
85
Figure 5-15
Sectional view of excavation at mid section
86
Figure 5-16
Sectional view of excavation at corners
87
Figure 5-17
Layout plan of ground instruments
88
MRT
tunnels
Figure 5-18
Layout plan of tunnel monitoring
89
5.7
5.7.1
5.7.1.1
5.7.1.2
The
RTS
viaduct
monitoring
and
ground
instrumentation layout plan is shown in Figure 5-19.
Only one inclinometer was installed in the ground.
Piezometers and water standpipes were not necessary as
the final excavation level is higher than the existing
water table.
5.7.1.3
Prism
Tiltmeter
(on column) (on column)
Vibration sensor
(on column)
Inclinometer
(in ground)
Figure 5-19
Instrumentation layout plan
90
Underground, Transition,
Sub-aqueous & At Grade
Structures
Inclinometer
Daily
Twice weekly
Water standpipe
Daily
Twice weekly
Piezometer
Daily
Nil
(Trice weekly -critical cases only)
Extensometer
Daily
Nil
(Trice weekly - critical cases only)
Daily
Nil
(Trice weekly -critical cases only)
Continuous
Nil
(Continuous -critical cases only)
Weekly
Twice weekly
Monthly
Nil
(Monthly -critical cases only)
Monthly
Nil
(Monthly -critical cases only)
Tilt meter
Continuous
Twice weekly
Vibration sensor
Continuous
Continuous
(where applicable)
Weekly
(where applicable)
Weekly
(where applicable)
Ground
Type of Instruments
ATMS
Manual
Survey
Without
ATMS
With
ATMS
Track survey
Crack meter
Note: Ground instruments may be monitored twice weekly for works within MRT 3rd reserve
Table 5-1
Typical instrumentation & frequency for construction activities within the railway protection zone
91
Chapter 6
Alternative Solutions
Quick preview
This final chapter provides you with some suggestions on the process and
methodology for formulating an alternative solution. Three examples of
development sites within the railway protection zone that have successfully
adopted the alternative solutions are presented in this chapter.
Part II
Section 8
Section 9
92
Figure 6-1
Suggested approach for designing an alternative solution
93
94
Ground level
Novena Station
Concourse Level
Platform
Level
Ground level
Novena Station
Concourse Level
Platform
Level
Figure 6-2
Removal of backfill over the station roof and replacement with load from the
retail podium
95
Opening for
underground link
Figure 6-3
An opening created in the wall at concourse level of Bugis Station
96
Ground level
Retaining wall
Existing tunnels
Struts
Excavation
Level
Proposed tunnel
Figure 6-4
Deep excavation adjacent to and tunnelling below existing transit tunnels
97
Increase in
vertical
diam eter
Increase in
horizontal
diam eter
D eform ed shape
O valisation
S quat
Figure 6-5
Tunnel ring deformation
98
Circle joint
Tunnel segmental
lining ring
Circle joint
Tunnel segment
Tunnel segment
step
Figure 6-6
Steps (settlement between rings) at tunnel joints
Circle
joint
Radial
joint
Figure 6-7
Opening of circle joint
Track geometry
99
Crackmeter
Total
Station
Rail
Reflecting
Prism
Vibration
sensor
Settlement cell
Settlement cell
Figure 6-8
Provision of total station, prisms, crack meter, settlement cells and vibration
sensor in the railway tunnel
100
Useful References:
1. The Novena Square. An office cum retail development
over MRT station Structural design and construction
considerations (2000) by Tan Guan & Allan K J Teo, TY
Lin South East Asia Pte Ltd
2. The Novena Square. An office cum retail development
over MRT station (2000) by DP Architects
3. New HDB Centre at Toa Payoh Integration with Toa
Payoh MRT station by Lai Huen Poh, RSP Architects
Planners & Engineers (Pte) Ltd
4. Planning the monitoring required to confirm the movement
and rotation of tunnels and track work due to excavation
and tunnelling by J.N.Shirlaw, S.K.Tham-Lee, F.K.Wong,
L.P.Wong-Ang, D.C.Chen, N.Osborne, & C.G.Tan
101