J&P ENGINEERING GHANA LTD WEEKLY PROGRESS REPORT

Date: 28TH NOVEMBER TO 4TH DECEMBER 2011


REPORT WK.

WK011

WEATHER CONDITION:

Bright/ Sunny

PROJECT: CONSTRUCTION OF 320 TPD PELLET PLANT AT KUMASI FOR ABELLON CLEAN ENERGY
- CIVIL WORKS

PROGRESS AT A GLANCE
PHYSICAL% COMPLETE CURRENT DATE

STATUS OF PROJECT DURATION TO DATE


TIME OUT DAYS SPENT DAYS TOGO % DAYS TO-GO 67% DAYS PHASE ANGLE 0

8%
COMMULATIVE PHYSICAL% COMPLETE

12/5/2011

5:00 PM

86

178

DATE OF FINAL DATE BEGINNING

FINAL DATE ACCORDING TO PROJECT Thursday, Thursday May 31 2012 31,

63%

9/10/2011
Completed (%)

5/31/2012
Previously Completed (%)

Item Scope
1 2 3 4 5 6 7 8 9 Compound Wall-561m Septic Tank Weighbridge & Security Cabins Weighbridge Foundation Main Plant Building Foundation Underground Water Tank Road Works

Start Date

Target Date

Status

20% 17% 6% 1%

64% 70% 6%

30-Sep-11 2-Nov-11 26-Nov-11 3-Dec-11

23-Dec-11 15-Dec-11 20-Jan-12 9-Feb-12

On - Going On - Going On - Going On - Going

Manpower
Labour 1 Direct & Indirect Total Manhours: Hrs 1516 1516 Comm Hrs Equipment 8939 8939 All Kinds
Total Equipment hours:

Major Equipment
Hrs 88 88 Comm Hrs 352.5 352.5

Safety Record y
No 1 2 3 4 No 1 Incident Nature Near Miss Minor Injury Serious Injury Fatality Fqy 0 0 0 0 Comm Fqy Major Material 0 1 1 0 CEMENT(Bg) 8-20mm REBAR(Tn)

Stores Record
Total QTY QTY in Stock Received 37 0.88 0 0 0 0 0 0 0 2584 60 20 30 20 Cumm. QTY Receive 1061 15.22 3084 460 420 132 200

150MM BLOCK(PC) WAWA BOARD(Nr) 2X4" SCANTING(Nr) SAND(M3) 20MM AGGREG.(M3

Lost Time
Cause of Lost Time N/A Time Lost Comm TL

Main Highlights/Comment:
Setting out Main Plant Building commenced Blockwork for West End Wall completed External Audit was carried out

1 0F 1

WKLY R

ID 0

Task Name

Duration

Start

Finish

CONSTRUCTION OF 320TPD PELLET PLANT

104 days Fri 9/30/11 Tue

1 Sep 18, '11 Oct 9, '11 Oct 30, '11 Nov 20, '11 Dec 11, '11 Jan 1, '12 Jan 22, '12 Feb 12, '12 Mar 16 24 2 10 18 26 3 11 19 27 5 13 21 29 6 14 22 30 7 15 23 2 63% 2/14/12

1 46

CONSTRUCTION OF COMPOUND WALL CONSTRUCTION OF SEPTIC TANK(25-30psn capacity)

61 days 32.75 days

Fri 9/30/11 Wed 11/2/11

Wed 12/14/11 Tue 12/13/11

100% 84% 87%

60

CONSTRUCTION OF SECURITY & WEIGHBRIDGE CABINS

37.95 days

Sat 11/26/11

Fri 1/20/12

12%

82

MAIN PLANT BUILDING PAD FOUNDATION

52.25 days

Sat 12/3/11

Tue 2/14/12

1%

Critical Critical Split Critical Progress Task Split Project: CONSTRUCTION OF 320TPD Date: Mon 12/5/11 Task Progress Baseline Baseline Split Baseline Milestone Milestone Summary Progress

Summary Project Summary Critical Split Critical Progress Task Split Task Progress Baseline Baseline Split Baseline Milestone Milestone Page 1

Summary Progress Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Summary

J&PENGINEERINGGHANALTD FINANCIALREPORTFROM20THSEPTEMBERTO19THNOVEMBER2011
MONIESRECEIVED DATE 9/20/2011 9/24/2011 9/26/2011 10/4/2011 10/7/2011 10/17/2011 10/19/2011 10/22/2011 10/29/2011 11/1/2011 11/3/2011 11/14/2011 11/16/2011 11/22/2011 AMOUNT 400.00 500.00 1,200.00 300.00 1,300.00 11,500.00 1,500.00 500.00 350.00 4,000.00 10,500.00 8,700.00 7,500.00 25,000.00 NOTE:DifferenceofGHC2021.19wouldbeexpendedonmaterialsandothersthisweek thereforenotfree EXPENDITURE
Colour Code

Week1 2025sept 281.00 333.40

Week2 Week3 Week4 Week5 Week6 Week7 Week8 Week9 Week10 26spt2Oct 3Oct8Oct 9Oct15Oct 17Oct22Oct 24Oct29Oct 31Oct5Nov 7Nov12Nov 14Nov19Nov 21Nov26Nov 324.10 461.50 1,020.90 12.00 305.10 614.50 100.00 1,993.50 26.00 85.00 38.00 155.00 7,160.00 280.00 20.00 3,704.78 9,009.88 280.00 1,163.00 1,913.00 9,844.40 140.00 878.40 222.50 549.60 50.00 3,775.00 15,375.00 901.50 1,240.75 401.50

Week11 28Nov03Dec 666.50

Total

Overheads SiteSetup DirectLabour Material Equipment,Tool&others IndirectLabour SiteManager'sUpkeep Total:

6,504.85 956.90

900.00 2,450.00 700.00

10,373.28 38,898.28 9,479.50 1,163.00 3,853.00

283.00 897.40

980.00 1,850.60

280.00 1,350.90

280.00 766.10

1,780.00 11,648.00

250.00 1,428.40 13,217.16 3,675.60 11,225.15 20,453.00 4,716.50

71,228.81 71,228.81

73,250.00

DIFFERENCE

2,021.19

MATERIAL

Week11 W k 11 28Nov04Dec RECEIVED ISSUED 60 20 1 4 6

J&PENGINEERINGGHANALTD WEEKLYMATERIALTRACKER QUANTITY TOTAL TOTAL


RECEIVED
10 460 25 420 18 21 10 2 1 2 3 25 1061 132 200 940 473 1270 198 140 175 1 20 3084

ISSUED
10 460 21 139 9 21 10 2 1 2 3 18 1024 132 200 690 473 1270 198 140 175 0 0 3084

BALANCE

UNIT

Wood3X3 WawaBoard(25mm) Wood2X3 Wood2X4 Wood 2X4 2.5"Nails(box) 3"nails(box) 4"Nails(box) Roofingnails(box) 3"Hinges(pairs) 4"Hinges(pairs) Padlocks Roofingsheet Cement Sand 20mmChippings 8mmRebar 10mmRebar 10mm Rebar 12mmRebar BindingWire JuteSack DirtyOil Grease EngineOil 150mmThkBlock

60 20 6 6

30 20

244 30 20

75

75

2584

2584

0 0 4 281 9 0 0 0 0 0 0 7 37 0 0 250 0 0 0 0 0 1 20 0

nr nr nr nr bx bx bx bx pr pr nr nr bg m3 m3 nr nr nr kg nr K.gln bkt lit pc