Progress at A Glance: Status of Project Duration To Date
Progress at A Glance: Status of Project Duration To Date
Progress at A Glance: Status of Project Duration To Date
WK011
WEATHER CONDITION:
Bright/ Sunny
PROJECT: CONSTRUCTION OF 320 TPD PELLET PLANT AT KUMASI FOR ABELLON CLEAN ENERGY
- CIVIL WORKS
PROGRESS AT A GLANCE
PHYSICAL% COMPLETE CURRENT DATE
8%
COMMULATIVE PHYSICAL% COMPLETE
12/5/2011
5:00 PM
86
178
63%
9/10/2011
Completed (%)
5/31/2012
Previously Completed (%)
Item Scope
1 2 3 4 5 6 7 8 9 Compound Wall-561m Septic Tank Weighbridge & Security Cabins Weighbridge Foundation Main Plant Building Foundation Underground Water Tank Road Works
Start Date
Target Date
Status
20% 17% 6% 1%
64% 70% 6%
Manpower
Labour 1 Direct & Indirect Total Manhours: Hrs 1516 1516 Comm Hrs Equipment 8939 8939 All Kinds
Total Equipment hours:
Major Equipment
Hrs 88 88 Comm Hrs 352.5 352.5
Safety Record y
No 1 2 3 4 No 1 Incident Nature Near Miss Minor Injury Serious Injury Fatality Fqy 0 0 0 0 Comm Fqy Major Material 0 1 1 0 CEMENT(Bg) 8-20mm REBAR(Tn)
Stores Record
Total QTY QTY in Stock Received 37 0.88 0 0 0 0 0 0 0 2584 60 20 30 20 Cumm. QTY Receive 1061 15.22 3084 460 420 132 200
Lost Time
Cause of Lost Time N/A Time Lost Comm TL
Main Highlights/Comment:
Setting out Main Plant Building commenced Blockwork for West End Wall completed External Audit was carried out
1 0F 1
WKLY R
ID 0
Task Name
Duration
Start
Finish
1 Sep 18, '11 Oct 9, '11 Oct 30, '11 Nov 20, '11 Dec 11, '11 Jan 1, '12 Jan 22, '12 Feb 12, '12 Mar 16 24 2 10 18 26 3 11 19 27 5 13 21 29 6 14 22 30 7 15 23 2 63% 2/14/12
1 46
60
37.95 days
Sat 11/26/11
Fri 1/20/12
12%
82
52.25 days
Sat 12/3/11
Tue 2/14/12
1%
Critical Critical Split Critical Progress Task Split Project: CONSTRUCTION OF 320TPD Date: Mon 12/5/11 Task Progress Baseline Baseline Split Baseline Milestone Milestone Summary Progress
Summary Project Summary Critical Split Critical Progress Task Split Task Progress Baseline Baseline Split Baseline Milestone Milestone Page 1
Summary Progress Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Summary
J&PENGINEERINGGHANALTD FINANCIALREPORTFROM20THSEPTEMBERTO19THNOVEMBER2011
MONIESRECEIVED DATE 9/20/2011 9/24/2011 9/26/2011 10/4/2011 10/7/2011 10/17/2011 10/19/2011 10/22/2011 10/29/2011 11/1/2011 11/3/2011 11/14/2011 11/16/2011 11/22/2011 AMOUNT 400.00 500.00 1,200.00 300.00 1,300.00 11,500.00 1,500.00 500.00 350.00 4,000.00 10,500.00 8,700.00 7,500.00 25,000.00 NOTE:DifferenceofGHC2021.19wouldbeexpendedonmaterialsandothersthisweek thereforenotfree EXPENDITURE
Colour Code
Week2 Week3 Week4 Week5 Week6 Week7 Week8 Week9 Week10 26spt2Oct 3Oct8Oct 9Oct15Oct 17Oct22Oct 24Oct29Oct 31Oct5Nov 7Nov12Nov 14Nov19Nov 21Nov26Nov 324.10 461.50 1,020.90 12.00 305.10 614.50 100.00 1,993.50 26.00 85.00 38.00 155.00 7,160.00 280.00 20.00 3,704.78 9,009.88 280.00 1,163.00 1,913.00 9,844.40 140.00 878.40 222.50 549.60 50.00 3,775.00 15,375.00 901.50 1,240.75 401.50
Total
6,504.85 956.90
283.00 897.40
980.00 1,850.60
280.00 1,350.90
280.00 766.10
1,780.00 11,648.00
71,228.81 71,228.81
73,250.00
DIFFERENCE
2,021.19
MATERIAL
ISSUED
10 460 21 139 9 21 10 2 1 2 3 18 1024 132 200 690 473 1270 198 140 175 0 0 3084
BALANCE
UNIT
Wood3X3 WawaBoard(25mm) Wood2X3 Wood2X4 Wood 2X4 2.5"Nails(box) 3"nails(box) 4"Nails(box) Roofingnails(box) 3"Hinges(pairs) 4"Hinges(pairs) Padlocks Roofingsheet Cement Sand 20mmChippings 8mmRebar 10mmRebar 10mm Rebar 12mmRebar BindingWire JuteSack DirtyOil Grease EngineOil 150mmThkBlock
60 20 6 6
30 20
244 30 20
75
75
2584
2584
0 0 4 281 9 0 0 0 0 0 0 7 37 0 0 250 0 0 0 0 0 1 20 0