LRT DEPOT Building Works - B0R0 - 190716: 473 Days Sat 6/1/19 Wed 12/23/20 Renovation of Administration Building

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 18

Duration

Task Name (Working) Start Finish


LRT DEPOT Building
Works_B0R0_190716 642 days Sat 6/1/19 Wed 7/21/21
RENOVATION OF ADMINISTRATION
BUILDING 473 days Sat 6/1/19 Wed 12/23/20

Project Milestone 473 days Sat 6/1/19 Wed 12/23/20


Notice to Proceed (NTP) 1 day Sat 6/1/19 Sat 6/1/19

Work Permit (Right of Access to the Site) 6 days Mon 6/10/19 Mon 6/17/19

Site Mobilization 0 days Thu 6/13/19 Thu 6/13/19

Building Permit Application 0 days Sat 8/10/19 Sat 8/10/19

Building Permit Approval 0 days Sat 9/14/19 Sat 9/14/19

Completion of Renovation Works 0 days Wed 12/23/20 Wed 12/23/20

Building Permit Preparation 81 days Mon 6/10/19 Sat 9/14/19

Site Structural Investigation 17 days Mon 6/10/19 Sat 6/29/19

Design Drawing Development 33 days Tue 7/2/19 Thu 8/8/19

Architectural & MEP Drawings 51 days Mon 6/10/19 Thu 8/8/19

Building Permit Application 0 days Sat 8/10/19 Sat 8/10/19

Building Official Assessment 27 days Mon 8/12/19 Fri 9/13/19

Building Permit Approval 0 days Sat 9/14/19 Sat 9/14/19

Design Works 59 days Sat 8/10/19 Sat 10/19/19

Structural Drawings 59 days Sat 8/10/19 Sat 10/19/19

Architectural & MEP Drawings 36 days Sat 8/10/19 Mon 9/23/19

For Construction Drawings 0 days Tue 9/24/19 Tue 9/24/19

Procurement 159 days Mon 8/5/19 Sat 2/15/20

Demolition Works 47 days Mon 8/5/19 Mon 9/30/19

Internal Finishing 87 days Mon 8/5/19 Sat 11/16/19

MEP Works 88 days Mon 9/2/19 Sat 12/14/19

Metal Roof 99 days Tue 10/1/19 Fri 1/31/20

External Finishing 101 days Mon 9/16/19 Sat 1/18/20


Miscellaneous RC Works 85 days Sat 11/2/19 Sat 2/15/20

ADMINSTRATION BUILDING RENOVATION 430 days Tue 7/23/19 Wed 12/23/20

Temporary Facilities Set-up 22 days Tue 7/23/19 Fri 8/16/19

Dismantling of Temporary Facilities 31 days Mon 12/23/19 Sat 2/1/20

Area 1 & 2 303 days Wed 7/31/19 Mon 8/3/20


Preparation of New Area for Client Transfer
at Area 3 38 days Wed 7/31/19 Sat 9/14/19
MEP Adjustments of Electrical Power and
other Utilities Prior to Demolition 37 days Thu 8/15/19 Sat 9/28/19
Clearing Works at Area 1 & 2 for Handing
Over by Client 87 days Mon 9/30/19 Thu 1/16/20
Installation of Board Up / Temporary
Partition Enclosing Area 1 & 2 27 days Tue 10/1/19 Thu 10/31/19

First Floor At Area 1 & 2 184 days Thu 12/19/19 Fri 7/31/20

Demolition Works 50 days Thu 12/19/19 Thu 2/20/20


Demolition of Existing CHB Partition
(including opening requirements) 17 days Sat 2/1/20 Thu 2/20/20

Demolition of Existing Drywall Partition 2 days Thu 12/19/19 Fri 12/20/19


Removal of Existing Ceiling Board and
Frame 7 days Sat 12/21/19 Fri 1/3/20
Re-adjustment / Removal of Existing
MEP Facilities 14 days Sat 1/4/20 Mon 1/20/20

Removal of Existing Floor Finishing 16 days Tue 1/21/20 Fri 2/7/20

Structural and Architectural Repair 65 days Sat 2/15/20 Tue 5/5/20

Masonry Works 36 days Mon 3/2/20 Wed 4/15/20

CHB Work 26 days Mon 3/2/20 Tue 3/31/20

Plastering Work 24 days Mon 3/16/20 Wed 4/15/20


Installation of New Door and Windows
Frame 17 days Wed 5/6/20 Mon 5/25/20

Mechanical and Electrical Works 90 days Wed 4/15/20 Thu 7/30/20

Electrical Works 90 days Wed 4/15/20 Thu 7/30/20

Lighting / Power System 77 days Wed 4/15/20 Wed 7/15/20

Mechanical Secondary Power 77 days Wed 4/15/20 Wed 7/15/20

Telephone / Lan System 90 days Wed 4/15/20 Thu 7/30/20

Fire Alarm System 90 days Wed 4/15/20 Thu 7/30/20


CCTV System 90 days Wed 4/15/20 Thu 7/30/20

Security Access Control System 90 days Wed 4/15/20 Thu 7/30/20

Mechanical Works 77 days Wed 4/15/20 Wed 7/15/20

Airconditioning System 77 days Wed 4/15/20 Wed 7/15/20

Ventillation System 77 days Wed 4/15/20 Wed 7/15/20

Fire Protection 77 days Wed 4/15/20 Wed 7/15/20

Ceiling Works 38 days Sat 5/16/20 Tue 6/30/20

Floor Finishing Works 17 days Mon 6/1/20 Sat 6/20/20

Internal Painting of CHB Plastered Wall 59 days Thu 4/16/20 Thu 6/25/20
Installation of Door and Window Panels
including its Accessories 13 days Sat 5/16/20 Sat 5/30/20
Installation of Tables and Chairs for Area
1&2 26 days Fri 6/26/20 Sat 7/25/20
Installation of Temporary Partition for
Partial Handing Over 5 days Mon 7/27/20 Fri 7/31/20

Second Floor At Area 1 & 2 187 days Mon 12/16/19 Fri 7/31/20

Demolition Works 57 days Mon 12/16/19 Tue 2/25/20


Client Handing Over of Area 2 (Server
Room) 0 days Thu 1/16/20 Thu 1/16/20
Demolition of Existing CHB Partition
(including opening requirements) 14 days Mon 2/10/20 Tue 2/25/20

Demolition of Existing Drywall Partition 6 days Mon 12/16/19 Sat 12/21/19


Removal of Existing Ceiling Board and
Frame 7 days Mon 12/23/19 Sat 1/4/20
Re-adjustment / Removal of Existing
MEP Facilities 11 days Mon 1/6/20 Fri 1/17/20

Removal of Existing Floor Finishing 17 days Sat 1/18/20 Thu 2/6/20

Structural and Architectural Repair 57 days Tue 2/25/20 Tue 5/5/20


Repainting / Rehabilitation of Existing
Steel Structure 58 days Thu 3/5/20 Fri 5/15/20

Masonry Works 36 days Mon 3/2/20 Wed 4/15/20

Installation of New Door's Frame 5 days Wed 4/1/20 Mon 4/6/20


Installation of New Aluminum Window
Frames 17 days Wed 5/6/20 Mon 5/25/20
Installation of Dry Wall Structural Support
and Frame 13 days Thu 4/16/20 Thu 4/30/20

Installation of Drywall Board 13 days Sat 4/25/20 Mon 5/11/20


Mechanical and Electrical Works 90 days Thu 4/16/20 Fri 7/31/20

Electrical Works 90 days Thu 4/16/20 Fri 7/31/20

Mechanical Works 77 days Thu 4/16/20 Thu 7/16/20

Ceiling Works 63 days Thu 4/16/20 Tue 6/30/20

Floor Finishing Works 17 days Mon 6/1/20 Sat 6/20/20

Internal Painting of CHB Plastered Wall 59 days Thu 4/16/20 Thu 6/25/20
Installation of Door and Window Panels
including its Accessories 13 days Sat 5/16/20 Sat 5/30/20
Installation of Tables and Chairs for Area
1&2 23 days Tue 6/30/20 Sat 7/25/20
Installation of Temporary Partition for
Partial Handing Over 5 days Mon 7/27/20 Fri 7/31/20

Roof Level At Area 1 & 2 109 days Mon 1/6/20 Fri 5/15/20

Roofing Replacement 109 days Mon 1/6/20 Fri 5/15/20

Exterior Finishing Area 1 & 2, 1F and 2F 187 days Mon 12/16/19 Fri 7/31/20

Punchlisting Works 27 days Tue 6/30/20 Thu 7/30/20

Handing Over of Area 1& 2, 1F and 2F 0 days Fri 7/31/20 Fri 7/31/20
Moving Office Furniture / Stuffs from
Area 3, 1F to 2F to Area 1 & 2, 1F and 2F 2 days Sat 8/1/20 Mon 8/3/20

Area 3 265 days Wed 2/5/20 Thu 12/17/20

First Floor Area 3 116 days Mon 8/3/20 Thu 12/17/20

Demolition Works 41 days Mon 8/3/20 Sat 9/19/20


Desk Transfer and Clearing of Area 3
For Handing Over - by Client 13 days Mon 8/3/20 Mon 8/17/20

Demolition of Existing CHB Partition


and Vault (including opening requirements) 20 days Sat 8/15/20 Tue 9/8/20

Demolition of Existing Drywall Partition 4 days Sat 8/15/20 Wed 8/19/20


Removal of Existing Ceiling Board and
Frame 8 days Thu 8/20/20 Sat 8/29/20
Re-adjustment / Removal of Existing
MEP Facilities 9 days Mon 8/31/20 Wed 9/9/20

Removal of Existing Floor Finishing 9 days Thu 9/10/20 Sat 9/19/20

Structural and Architectural Repair 39 days Thu 9/10/20 Sat 10/24/20

Masonry Works 17 days Thu 9/10/20 Tue 9/29/20


Installation of New Door and Windows
Frame 9 days Sat 9/19/20 Tue 9/29/20
Mechanical and Electrical Works 65 days Wed 9/30/20 Tue 12/15/20

Electrical Works 64 days Wed 9/30/20 Mon 12/14/20

Lighting / Power System 60 days Wed 9/30/20 Wed 12/9/20

Mechanical Secondary Power 60 days Wed 9/30/20 Wed 12/9/20

Telephone / Lan System 60 days Wed 9/30/20 Wed 12/9/20

Fire Alarm System 64 days Wed 9/30/20 Mon 12/14/20

CCTV System 64 days Wed 9/30/20 Mon 12/14/20

Security Access Control System 64 days Wed 9/30/20 Mon 12/14/20

Mechanical Works 65 days Wed 9/30/20 Tue 12/15/20

Airconditioning System 65 days Wed 9/30/20 Tue 12/15/20

Ventillation System 65 days Wed 9/30/20 Tue 12/15/20

Fire Protection 65 days Wed 9/30/20 Tue 12/15/20

Ceiling Works 36 days Sat 10/31/20 Sat 12/12/20

Floor Finishing Works 17 days Mon 11/16/20 Sat 12/5/20

Internal Painting of CHB Plastered Wall 61 days Wed 9/30/20 Thu 12/10/20
Installation of Door and Window Panels
including its Accessories 12 days Sat 11/28/20 Sat 12/12/20
Installation of Tables and Chairs for Area
3 6 days Fri 12/11/20 Thu 12/17/20

Toilet A3 , 1F Construction 83 days Fri 9/11/20 Thu 12/17/20

Earthworks 2 days Fri 9/11/20 Sat 9/12/20

Reinforced Concrete Works 14 days Mon 9/14/20 Tue 9/29/20


Steel Rafter Installation including
Purilins and Accessories 3 days Wed 9/30/20 Fri 10/2/20
Installation of Roofing with Wire Mesh
and Insulation 3 days Sat 10/3/20 Tue 10/6/20

CHB including Wall Footing at 1F 12 days Wed 10/7/20 Tue 10/20/20

Installation of New Door Frames 4 days Thu 10/15/20 Mon 10/19/20


Installation of New Aluminum Window
Frames 2 days Sat 11/28/20 Tue 12/1/20

Plastering Works 4 days Thu 11/26/20 Tue 12/1/20

Wall Tiling Works 30 days Wed 11/4/20 Wed 12/9/20


Mechanical and Electrical Works 33 days Thu 10/29/20 Mon 12/7/20

Electrical Works 21 days Thu 10/29/20 Sat 11/21/20

Lighting / Power System 21 days Thu 10/29/20 Sat 11/21/20

Fire Alarm System 21 days Thu 10/29/20 Sat 11/21/20

Mechanical Works 33 days Thu 10/29/20 Mon 12/7/20

Plumbing and Sanitary 33 days Thu 10/29/20 Mon 12/7/20

Ceiling Works 6 days Wed 11/11/20 Tue 11/17/20

Waterproofing Works 4 days Tue 11/17/20 Fri 11/20/20

Painting of Walls and Ceiling 4 days Sat 11/21/20 Wed 11/25/20

Floor Tiles Installation 4 days Thu 11/26/20 Tue 12/1/20


Installation of Door and Window Panels
including its Accessories 4 days Wed 12/2/20 Sat 12/5/20

Installation of Toilet Partition 5 days Tue 12/8/20 Sat 12/12/20


Dismantling of Board-up and Temporary
Partition 5 days Sat 12/12/20 Thu 12/17/20

Second Floor At Area 3 265 days Wed 2/5/20 Thu 12/17/20

Demolition Works 47 days Mon 8/3/20 Sat 9/26/20


Desk Transfer and Clearing of Area 3
For Handing Over - by Client 13 days Mon 8/3/20 Mon 8/17/20
Demolition of Existing CHB Partition
(including opening requirements) 12 days Tue 8/18/20 Tue 9/1/20

Demolition of Existing Drywall Partition 4 days Tue 8/18/20 Sat 8/22/20


Demolition of Suspended Slab at Vault
Area 5 days Fri 9/11/20 Wed 9/16/20
Removal of Existing Ceiling Board and
Frame 9 days Wed 9/2/20 Fri 9/11/20
Re-adjustment / Removal of Existing
MEP Facilities 8 days Sat 9/12/20 Mon 9/21/20

Removal of Existing Floor Finishing 10 days Wed 9/16/20 Sat 9/26/20

Structural and Architectural Repair 39 days Sat 9/12/20 Tue 10/27/20


Repainting / Rehabilitation of Existing
Steel Structure 13 days Sat 9/12/20 Sat 9/26/20

Masonry Works 17 days Sat 9/12/20 Thu 10/1/20


Installation of New Door and Windows
Frame 10 days Mon 9/21/20 Thu 10/1/20
Installation of Dry Wall Structural Support
and Frame 14 days Thu 10/29/20 Fri 11/13/20
Installation of Drywall Board 13 days Sat 11/14/20 Sat 11/28/20

Mechanical and Electrical Works 82 days Sat 9/12/20 Thu 12/17/20

Electrical Works 82 days Sat 9/12/20 Thu 12/17/20

Lighting / Power System 82 days Sat 9/12/20 Thu 12/17/20

Mechanical Secondary Power 82 days Sat 9/12/20 Thu 12/17/20

Telephone / Lan System 82 days Sat 9/12/20 Thu 12/17/20

Fire Alarm System 82 days Sat 9/12/20 Thu 12/17/20

CCTV System 82 days Sat 9/12/20 Thu 12/17/20

Security Access Control System 82 days Sat 9/12/20 Thu 12/17/20

Mechanical Works 59 days Sat 9/12/20 Thu 11/19/20

Airconditioning System 59 days Sat 9/12/20 Thu 11/19/20

Ventillation System 59 days Sat 9/12/20 Thu 11/19/20

Fire Protection 59 days Sat 9/12/20 Thu 11/19/20

Ceiling Works 76 days Wed 9/16/20 Mon 12/14/20

Floor Finishing Works 14 days Tue 11/10/20 Wed 11/25/20

Painting of Walls 52 days Thu 10/15/20 Tue 12/15/20


Installation of Door and Window Panels
including its Accessories 12 days Fri 12/4/20 Thu 12/17/20

Toilet A3 , 2F Construction 84 days Thu 9/10/20 Thu 12/17/20

Mechanical and Electrical Works 47 days Thu 9/10/20 Tue 11/3/20

Electrical Works 42 days Thu 9/10/20 Wed 10/28/20

Lighting / Power System 40 days Thu 9/10/20 Mon 10/26/20

Fire Alarm System 40 days Sat 9/12/20 Wed 10/28/20

Mechanical Works 45 days Sat 9/12/20 Tue 11/3/20

Plumbing and Sanitary 45 days Sat 9/12/20 Tue 11/3/20

Wall Tiling Works 9 days Sat 9/26/20 Tue 10/6/20

Ceiling Works 9 days Fri 10/9/20 Mon 10/19/20

Waterproofing Works 3 days Tue 10/20/20 Thu 10/22/20


Floor Tiles Installation 5 days Fri 10/23/20 Wed 10/28/20

Installation of Toilet Fixtures 4 days Thu 10/29/20 Mon 11/2/20


Installation of Tables and Chairs at Area
3 8 days Sat 12/5/20 Mon 12/14/20
Dismantling of Board-up and Temporary
Partition 6 days Fri 12/11/20 Thu 12/17/20

Roof Level At Area 3 58 days Fri 9/11/20 Tue 11/17/20

Roofing Replacement 58 days Fri 9/11/20 Tue 11/17/20

Exterior Finishing Area 3, 1F and 2F 100 days Tue 8/18/20 Mon 12/14/20

Punchlisting Works 15 days Tue 12/1/20 Thu 12/17/20

Lobby, Stairs and Entry Porch 100 days Sat 8/15/20 Fri 12/11/20
Removal of Existing Ceiling Board and
Frame 4 days Sat 8/15/20 Wed 8/19/20
Re-adjustment / Removal of Existing
MEP Facilities 4 days Thu 8/20/20 Tue 8/25/20

Removal of Existing Floor Finishing 5 days Wed 11/18/20 Mon 11/23/20

Structural and Architectural Repair 10 days Sat 9/5/20 Wed 9/16/20

Waterproofing Works 7 days Thu 9/17/20 Thu 9/24/20

Mechanical and Electrical Works 52 days Fri 9/25/20 Tue 11/24/20

Electrical Works 52 days Fri 9/25/20 Tue 11/24/20

Lighting / Power System 45 days Fri 9/25/20 Mon 11/16/20

Mechanical Secondary Power 45 days Fri 9/25/20 Mon 11/16/20

Telephone / Lan System 52 days Fri 9/25/20 Tue 11/24/20

Fire Alarm System 52 days Fri 9/25/20 Tue 11/24/20

CCTV System 52 days Fri 9/25/20 Tue 11/24/20

Security Access Control System 52 days Fri 9/25/20 Tue 11/24/20

Mechanical Works 52 days Fri 9/25/20 Tue 11/24/20

Airconditioning System 52 days Fri 9/25/20 Tue 11/24/20

Ventillation System 52 days Fri 9/25/20 Tue 11/24/20

Fire Protection 52 days Fri 9/25/20 Tue 11/24/20

Ceiling Works 36 days Fri 9/25/20 Thu 11/5/20


Installation of Handrail including
Accessories 5 days Wed 11/11/20 Mon 11/16/20

Install Aluminum Frame and Glass 5 days Wed 11/11/20 Mon 11/16/20

Painting of Walls and Ceiling 5 days Fri 11/6/20 Wed 11/11/20

Floor Finishing Works 8 days Tue 11/17/20 Wed 11/25/20

Main Entrance Door Replacement 5 days Wed 11/25/20 Tue 12/1/20

Installation of Guard Counter Top 9 days Wed 12/2/20 Fri 12/11/20

Roof Level Lobby 17 days Mon 9/7/20 Fri 9/25/20

Roofing Replacement 17 days Mon 9/7/20 Fri 9/25/20

Main Toilet 265 days Wed 2/5/20 Thu 12/17/20

Ground Floor 207 days Wed 2/5/20 Fri 10/9/20


Installation of Board Up / Temporary
Partition Enclosure 5 days Wed 2/5/20 Mon 2/10/20
Dismantling of Toilet Partition and
Fixtures 5 days Tue 2/11/20 Sat 2/15/20

Dismantling of Ceiling 4 days Mon 2/17/20 Thu 2/20/20


Re-adjustment / Removal of Existing
MEP Facilities 5 days Fri 2/21/20 Wed 2/26/20

Dismantling of Floor Tilea 3 days Thu 2/27/20 Sat 2/29/20

Dismantling of Wall Tiles 8 days Mon 3/2/20 Tue 3/10/20


Perform Structural Retrofitting Activity
Above Ceiling 4 days Wed 3/11/20 Sat 3/14/20

Mechanical and Electrical Works 24 days Mon 3/16/20 Wed 4/15/20

Mechanical and Electrical Works 171 days Mon 3/16/20 Wed 10/7/20

Electrical Works 30 days Thu 9/3/20 Wed 10/7/20

Lighting / Power System 30 days Thu 9/3/20 Wed 10/7/20

Fire Alarm System 30 days Thu 9/3/20 Wed 10/7/20

Mechanical Works 171 days Mon 3/16/20 Wed 10/7/20

Plumbing and Sanitary 74 days Mon 3/16/20 Mon 6/15/20

Ventillation System 30 days Thu 9/3/20 Wed 10/7/20

Restoration of Slab on Grade 2 days Thu 4/16/20 Fri 4/17/20

Installation of New Wall Tiles 14 days Sat 4/18/20 Tue 5/5/20


Ceiling Works 8 days Thu 10/1/20 Fri 10/9/20

Waterproofing Works 9 days Wed 5/6/20 Fri 5/15/20

Floor Tiles Installation 14 days Sat 5/16/20 Mon 6/1/20


Installation of Toilet Fixtures and
Accessories 11 days Tue 6/2/20 Mon 6/15/20

Installation of Toilet Partition 13 days Tue 6/16/20 Tue 6/30/20

Wall Painting 8 days Wed 7/1/20 Thu 7/9/20

Dismantling of Board-up and Partition 5 days Fri 7/10/20 Wed 7/15/20


Installation of LRTA Staff Safety
Access from Area 1 & 2 14 days Thu 7/16/20 Fri 7/31/20

Second Floor 105 days Sat 8/15/20 Thu 12/17/20


Dismantling of Toilet Partiiton and
Fixtures 5 days Sat 8/15/20 Thu 8/20/20

Dismantling of Ceiling 3 days Sat 8/22/20 Tue 8/25/20


Re-adjustment / Removal of Existing
MEP Facilities 5 days Wed 8/26/20 Mon 8/31/20

Dismantling of Wall Tiles 5 days Tue 9/1/20 Sat 9/5/20

Dismantling of Floor Tilea 4 days Mon 9/7/20 Thu 9/10/20


Perform Structural Retrofitting Activity
Above Ceiling 4 days Fri 9/11/20 Tue 9/15/20

Mechanical and Electrical Works 72 days Sat 8/15/20 Sat 11/7/20

Electrical Works 43 days Sat 8/15/20 Mon 10/5/20

Lighting / Power System 43 days Sat 8/15/20 Mon 10/5/20

Fire Alarm System 43 days Sat 8/15/20 Mon 10/5/20

Mechanical Works 72 days Sat 8/15/20 Sat 11/7/20

Plumbing and Sanitary 50 days Fri 9/11/20 Sat 11/7/20

Ventillation System 23 days Sat 8/15/20 Fri 9/11/20

Installation of New Wall Tiles 9 days Mon 9/28/20 Wed 10/7/20

Ceiling Works 11 days Fri 9/11/20 Wed 9/23/20

Waterproofing Works 10 days Tue 10/6/20 Fri 10/16/20

Floor Tiles Installation 15 days Sat 10/17/20 Tue 11/3/20


Installation of Toilet Fixtures and
Accessories 12 days Wed 11/4/20 Tue 11/17/20
Installation of Toilet Partition 13 days Wed 11/18/20 Thu 12/3/20

Wall Painting 8 days Fri 12/4/20 Sat 12/12/20

Dismantling of Board-up and Partition 4 days Mon 12/14/20 Thu 12/17/20

External Works 245 days Thu 3/5/20 Wed 12/23/20

Temporary Septic Tank 44 days Tue 3/10/20 Mon 5/4/20

New Septic Tank Construction 39 days Sat 8/15/20 Wed 9/30/20

PWD Ramp Construction 234 days Mon 3/9/20 Mon 12/14/20


Client Handing Over (Removal of PLDT
Fiber Optic Cables) 0 days Mon 3/9/20 Mon 3/9/20

Earthworks 23 days Tue 5/5/20 Sat 5/30/20

Reinforced Concrete Works 52 days Mon 6/1/20 Fri 7/31/20


Steel Rafter Installation including Purilins
and Accessories 25 days Sat 8/1/20 Mon 8/31/20
Installation of roofing with Wire Mesh and
Insulation 14 days Tue 9/1/20 Wed 9/16/20

Demolition of Ramp Opening at 2F 11 days Tue 8/4/20 Sat 8/15/20


CHB and Plastering Works including Wall
Footing 40 days Wed 7/1/20 Sat 8/15/20

Electrical Works 61 days Thu 8/20/20 Fri 10/30/20

Lighting / Power System 61 days Thu 8/20/20 Fri 10/30/20

Fire Alarm System 61 days Thu 8/20/20 Fri 10/30/20

Ceiling Works inside the Ramps 17 days Fri 9/11/20 Wed 9/30/20

Painting of Walls and Ceiling 17 days Thu 10/1/20 Tue 10/20/20


Installation of Handrail including
Accessories 23 days Wed 10/21/20 Mon 11/16/20

Floor Finishing Works 23 days Tue 11/17/20 Mon 12/14/20

Removal of Board-up at Ramp Openings 5 days Sat 12/12/20 Thu 12/17/20

Fire Exit Stair 245 days Thu 3/5/20 Wed 12/23/20

Area 1 & 2 118 days Thu 3/5/20 Sat 7/25/20

Area 3 109 days Mon 8/17/20 Wed 12/23/20


External Mechanical and Electrical
Works 142 days Wed 4/15/20 Wed 9/30/20

External Electrical Works 74 days Wed 4/15/20 Sat 7/11/20


Power Incoming Underground Ductbank
and Manholes 74 days Wed 4/15/20 Sat 7/11/20

External Mechanical Works 142 days Wed 4/15/20 Wed 9/30/20


EXTENSION OF EXISTING BACLARAN
DEPOT 574 days Mon 6/3/19 Mon 5/3/21

Project Milestone 529 days Mon 6/24/19 Thu 3/25/21

Permit Application 102 days Mon 6/3/19 Wed 10/2/19

Design Works 117 days Tue 7/2/19 Mon 11/18/19

Procurement 315 days Mon 9/16/19 Thu 10/1/20

Construction Works 475 days Mon 9/30/19 Mon 5/3/21

Temporary Facilities Set-up 50 days Thu 10/3/19 Mon 12/2/19

Dismantling of Temporary Facilities 24 days Wed 3/31/21 Mon 5/3/21

Building and Facilities 447 days Mon 9/30/19 Thu 3/25/21


B01 Light and Heavy Maintenance
Workshop 447 days Mon 9/30/19 Thu 3/25/21

Design Review 42 days Mon 9/30/19 Mon 11/18/19


Pre- Construction Tasks of Bored Piling
Works 115 days Thu 10/3/19 Fri 2/21/20

Bored Piling Works 79 days Mon 2/24/20 Fri 5/29/20

Excavation 24 days Fri 4/24/20 Fri 5/22/20

Backfill & Compaction 66 days Tue 6/23/20 Tue 9/8/20

Reinforced Concrete Works 122 days Fri 5/8/20 Tue 9/29/20

Zone 1 66 days Fri 5/8/20 Fri 7/24/20

Zone 2 68 days Fri 5/29/20 Mon 8/17/20

Zone 3 68 days Sat 6/20/20 Tue 9/8/20

Zone 4 68 days Sat 7/11/20 Tue 9/29/20

Steel Structure Works 108 days Wed 7/8/20 Wed 11/11/20

Zone 1 68 days Wed 7/8/20 Fri 9/25/20

Zone 2 72 days Wed 7/22/20 Wed 10/14/20

Zone 3 72 days Wed 8/5/20 Wed 10/28/20

Zone 4 72 days Wed 8/19/20 Wed 11/11/20


Overhead Crane Installation 30 days Thu 9/10/20 Wed 10/14/20

Roofing 48 days Tue 10/13/20 Tue 12/8/20

Exterior Finishing Works 91 days Thu 9/10/20 Mon 12/28/20

Maintenance Area 166 days Wed 8/5/20 Mon 2/22/21

Interior Finishing Works 104 days Fri 10/16/20 Sat 2/20/21

MEPF WORKS 166 days Wed 8/5/20 Mon 2/22/21

Ventillation System 45 days Mon 11/16/20 Wed 1/13/21

Fire Protection System 66 days Mon 11/2/20 Sat 1/23/21

Plumbing and Sanitary Works 136 days Wed 8/5/20 Mon 1/18/21

Compressor System 45 days Mon 11/16/20 Wed 1/13/21

Feeder Line 80 days Sat 10/31/20 Mon 2/8/21

Lighting System 66 days Tue 11/17/20 Mon 2/8/21

Small Power System 66 days Tue 11/17/20 Mon 2/8/21

FDAS 66 days Tue 11/17/20 Mon 2/8/21

Telephone System 66 days Tue 11/17/20 Mon 2/8/21


Lightning Protection/ Grounding
System 56 days Mon 11/23/20 Tue 2/2/21
Duct Bank from Substation to Light /
Heavy Maintenance 0 days Sat 8/8/20 Sat 8/8/20

Internal Testing and Commisioning 12 days Mon 2/8/21 Sat 2/20/21

Electrical Power On 0 days Mon 2/22/21 Mon 2/22/21


EPC Contractor Access to
Mainternace Area 0 days Mon 2/22/21 Mon 2/22/21

Office Area 203 days Fri 7/24/20 Thu 3/25/21

Interior Finishing Works 111 days Wed 11/4/20 Fri 3/19/21

MEPF WORKS 203 days Fri 7/24/20 Thu 3/25/21

Ventillation System 101 days Wed 11/4/20 Mon 3/8/21

Fire Protection System 101 days Wed 11/4/20 Mon 3/8/21

Plumbing and Sanitary Works 187 days Fri 7/24/20 Sat 3/6/21

Feeder Line 90 days Fri 11/6/20 Thu 2/25/21


Lighting System 90 days Sat 11/14/20 Fri 3/5/21

Small Power System 90 days Sat 11/14/20 Fri 3/5/21

FDAS 80 days Sat 11/28/20 Mon 3/8/21

Telephone System 75 days Sat 12/5/20 Mon 3/8/21


Lightning Protection/ Grounding
System 75 days Sat 12/5/20 Mon 3/8/21

Overall Testing and Commissioning 15 days Tue 3/9/21 Thu 3/25/21

B02 Substation 388 days Mon 9/30/19 Fri 1/15/21

Design Review 42 days Mon 9/30/19 Mon 11/18/19

Bore Pling Works and Earthworks 116 days Mon 2/24/20 Mon 7/13/20

Reinforced Concrete Works 96 days Mon 5/11/20 Tue 9/1/20

Exterior Finishing 89 days Wed 7/29/20 Tue 11/10/20

Interior Finishing 95 days Mon 9/21/20 Fri 1/15/21

MEPF WORKS 167 days Sat 6/27/20 Fri 1/15/21

Ventillation System 47 days Tue 10/27/20 Mon 12/21/20

Fire Protection System 11 days Mon 1/4/21 Fri 1/15/21

Plumbing and Sanitary Works 163 days Sat 6/27/20 Mon 1/11/21

Feeder Line 85 days Thu 8/27/20 Fri 12/4/20

Lighting System 60 days Thu 9/17/20 Wed 11/25/20

Small Power System 60 days Thu 9/17/20 Wed 11/25/20

FDAS 60 days Thu 9/17/20 Wed 11/25/20

Telephone System 60 days Thu 9/17/20 Wed 11/25/20

Lightning Protection/ Grounding System 60 days Thu 10/1/20 Thu 12/10/20

B03 Motor Pool 373 days Mon 9/30/19 Wed 12/23/20

Design Review 42 days Mon 9/30/19 Mon 11/18/19

Earthworks 54 days Wed 6/24/20 Wed 8/26/20

Reinforced Concrete Works 105 days Wed 7/1/20 Sat 10/31/20

Exterior Finishing 57 days Fri 9/11/20 Mon 11/16/20


Interior Finishing 60 days Sat 10/10/20 Sat 12/19/20

MEPF WORKS 68 days Mon 10/5/20 Wed 12/23/20

AC System 25 days Sat 10/31/20 Sat 11/28/20

Ventillation System 25 days Sat 10/31/20 Sat 11/28/20

Fire Protection System 46 days Mon 10/5/20 Thu 11/26/20

Plumbing and Sanitary Works 44 days Thu 10/8/20 Fri 11/27/20

Feeder Line 68 days Mon 10/5/20 Wed 12/23/20

Lighting System 35 days Mon 10/12/20 Fri 11/20/20

Small Power System 35 days Mon 10/12/20 Fri 11/20/20

FDAS 35 days Mon 10/19/20 Fri 11/27/20

Telephone System 35 days Mon 10/19/20 Fri 11/27/20

Lightning Protection/ Grounding System 35 days Mon 10/19/20 Fri 11/27/20

B04 Material Storage 395 days Mon 9/30/19 Sat 1/23/21

Design Review 42 days Mon 9/30/19 Mon 11/18/19

Earthworks 54 days Tue 7/7/20 Tue 9/8/20

Reinforced Concrete Works 105 days Tue 7/14/20 Fri 11/13/20

Exterior Finishing 64 days Thu 9/24/20 Tue 12/8/20

Interior Finishing 67 days Sat 10/31/20 Sat 1/23/21

MEPF WORKS 109 days Mon 8/24/20 Mon 1/4/21

AC and Ventillation System 25 days Tue 12/1/20 Mon 1/4/21

Fire Protection System 46 days Sat 10/17/20 Thu 12/10/20

Plumbing and Sanitary Works 94 days Mon 8/24/20 Fri 12/11/20

Feeder Line 35 days Sat 10/17/20 Thu 11/26/20

Lighting System 35 days Sat 10/24/20 Fri 12/4/20

Small Power System 35 days Sat 10/24/20 Fri 12/4/20

FDAS 35 days Sat 10/31/20 Fri 12/11/20

Telephone System 35 days Sat 10/31/20 Fri 12/11/20


Lightning Protection/ Grounding System 35 days Sat 10/31/20 Fri 12/11/20

B05 Guard House 433 days Mon 9/30/19 Tue 3/9/21

Design Review 42 days Mon 9/30/19 Mon 11/18/19

Earthworks 27 days Tue 11/17/20 Fri 12/18/20

Reinforced Concrete Works 66 days Tue 11/24/20 Mon 2/15/21

Exterior Finishing 36 days Thu 1/14/21 Wed 2/24/21

Interior Finishing 34 days Thu 1/28/21 Mon 3/8/21

MEPF WORKS 58 days Tue 12/29/20 Tue 3/9/21

Fire Protection System 10 days Sat 2/6/21 Wed 2/17/21

Plumbing and Sanitary Works 44 days Tue 12/29/20 Sat 2/20/21

Feeder Line 15 days Sat 2/6/21 Tue 2/23/21

Lighting System 15 days Sat 2/13/21 Tue 3/2/21

Small Power System 15 days Sat 2/13/21 Tue 3/2/21

FDAS 15 days Sat 2/20/21 Tue 3/9/21

Telephone System 15 days Sat 2/20/21 Tue 3/9/21

Lightning Protection/ Grounding System 15 days Sat 2/20/21 Tue 3/9/21


B06 & B07 Waste and Hazardous Material
Storage 395 days Mon 9/30/19 Sat 1/23/21

Design Review 42 days Mon 9/30/19 Mon 11/18/19

Earthworks 53 days Thu 7/9/20 Wed 9/9/20

Reinforced Concrete Works 104 days Thu 7/16/20 Sat 11/14/20

Exterior Finishing 64 days Thu 9/24/20 Tue 12/8/20

Interior Finishing 67 days Sat 10/31/20 Sat 1/23/21

MEPF WORKS 108 days Tue 8/25/20 Mon 1/4/21

Ventillation System 25 days Tue 12/1/20 Mon 1/4/21

Fire Protection System 46 days Mon 10/19/20 Fri 12/11/20

Plumbing and Sanitary Works 94 days Tue 8/25/20 Sat 12/12/20

Feeder Line 35 days Mon 10/19/20 Fri 11/27/20


Lighting System 35 days Mon 10/26/20 Sat 12/5/20

Small Power System 35 days Mon 10/26/20 Sat 12/5/20

FDAS 35 days Mon 11/2/20 Sat 12/12/20

Telephone System 35 days Mon 11/2/20 Sat 12/12/20

Lightning Protection/ Grounding System 35 days Mon 11/2/20 Sat 12/12/20

B08 Switch Room 317 days Mon 9/30/19 Sat 10/17/20

Design Review 42 days Mon 9/30/19 Mon 11/18/19

Earthworks 30 days Wed 6/24/20 Tue 7/28/20

Reinforced Concrete Works 75 days Wed 7/1/20 Sat 9/26/20

Exterior Finishing 32 days Wed 8/26/20 Thu 10/1/20

Interior Finishing 32 days Fri 9/11/20 Sat 10/17/20

MEPF WORKS 59 days Fri 8/7/20 Thu 10/15/20

Fire Protection System 10 days Fri 9/18/20 Tue 9/29/20

Plumbing and Sanitary Works 44 days Fri 8/7/20 Mon 9/28/20

Feeder Line 15 days Fri 9/18/20 Mon 10/5/20

Lighting System 15 days Fri 9/25/20 Mon 10/12/20

Small Power System 15 days Fri 9/25/20 Mon 10/12/20

FDAS 15 days Tue 9/29/20 Thu 10/15/20

Telephone System 15 days Tue 9/29/20 Thu 10/15/20

Lightning Protection/ Grounding System 15 days Tue 9/29/20 Thu 10/15/20

B09 IME Storage 317 days Mon 9/30/19 Sat 10/17/20

Design Review 42 days Mon 9/30/19 Mon 11/18/19

Earthworks 46 days Mon 4/27/20 Sat 6/20/20

Reinforced Concrete Works 111 days Sat 5/9/20 Thu 9/17/20

Exterior Finishing 46 days Sat 8/1/20 Thu 9/24/20

Interior Finishing 44 days Fri 8/28/20 Sat 10/17/20

MEPF WORKS 79 days Thu 7/9/20 Fri 10/9/20


Fire Protection System 10 days Fri 9/4/20 Tue 9/15/20

Plumbing and Sanitary Works 44 days Thu 7/9/20 Sat 8/29/20

Feeder Line 22 days Fri 9/4/20 Tue 9/29/20

Lighting System 22 days Fri 9/11/20 Tue 10/6/20

Small Power System 22 days Fri 9/11/20 Tue 10/6/20

FDAS 22 days Tue 9/15/20 Fri 10/9/20

Telephone System 22 days Tue 9/15/20 Fri 10/9/20

Lightning Protection/ Grounding System 22 days Tue 9/15/20 Fri 10/9/20

NEW SATELLITE DEPOT AT ZAPOTE 641 days Mon 6/3/19 Wed 7/21/21