Four Storey School 303.14 Days Tue 2/27/18 Fri 4/26/19 97,712,945.11
Four Storey School 303.14 Days Tue 2/27/18 Fri 4/26/19 97,712,945.11
Four Storey School 303.14 Days Tue 2/27/18 Fri 4/26/19 97,712,945.11
Page 1
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
10 Submit shop 2 wks Fri 3/2/18 Thu 8 Steel Erection Contractor ₱80,000.00
drawings and 3/15/18 Management
order long lead
items - steel
11 Submit shop 2 wks Mon Fri 3/30/18 7 Roofing Contractor ₱80,000.00
drawings and 3/19/18 Management
order long lead
items - roofing
12 Submit shop 2 wks Mon Fri 3/30/18 7 Plumbing Contractor ₱80,000.00
drawings and 3/19/18 Management
order long lead
items - plumbing
13 Submit shop 2 wks Mon Fri 3/30/18 7 Electric Contractor ₱80,000.00
drawings and 3/19/18 Management
order long lead
items - electric
14 Detail, fabricate 12 wks Fri Thu 6/7/18 10 Steel Erection Contractor ₱480,000.00
and deliver steel 3/16/18 Management[50%],Steel
Erection Contractor[50%]
Page 2
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
17 Install temporary 2 days Thu Fri 3/2/18 2 Plumbing ₱86,698.00 Plumb
water service 3/1/18 Contractor,GATE
VALVE[1],PVC
ELBOW[1],PVC PIPE
18 Set up site office 3 days Mon Wed 16,172"[1],PVC
Labor CrewPIPE 3"[1],PVC ₱12,120.00 Lab
3/5/18 3/7/18 1[10%],General Manager
19 Set line and grade 3 days Thu Mon 18 Survey Crew,Labor Crew 3 ₱5,400.00 S
benchmarks 3/8/18 3/12/18
20 Prepare site - lay 5 days Tue Mon 19 Site Grading Contractor ₱40,000.00
down yard and 3/13/18 3/19/18
temporary fencing
Page 3
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
25 Perform final site 1 wk Wed Wed 24 Site Grading ₱54,000.00 S
grading 3/7/18 3/14/18 Contractor,Engineer
26 Erect building 1 wk Wed Wed 25 Survey Crew,Engineer ₱21,000.00
batter boards and 3/14/18 3/21/18
layout building
32 Set reinforcing and 2 days Wed Fri 5/4/18 31 Rough Carpenter ₱6,400.00
anchor bolts 5/2/18 Crew,Engineer
Page 4
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
33 Pour column piers 3 days Fri 5/4/18 Wed 32 Concrete ₱59,400.00
and foundations 5/9/18 Crew,Backfilling/Disposal[1],Engineer
34 Cure piers and 7 days Wed Fri 5/18/18 33 Labor Crew ₱19,880.00
foundations 5/9/18 1[10%],Engineer
35 Strip wall forms 2 days Tue Wed Labor Crew ₱5,680.00 Labor C
2/27/18 2/28/18 1[10%],Engineer
36 Strip column piers 4 days Fri Thu 34 Labor Crew 1,Engineer ₱12,800.00
and foundation 5/18/18 5/24/18
forms
37 Steel Erection 45 days Fri 6/8/18 Thu 8/9/18 ₱20,539,917.20
38 Erect steel 2 wks Fri 6/8/18 Thu 36,14Steel Erection ₱6,624,619.20
columns, beams 6/21/18 Contractor,WIDE FLANGE
and joist - 1st and w6 x 20 x 20' - FOR
2nd floors BEAMS[1],WIDE FLANGE
39 Erect steel 2 wks Fri w8 x 24
Thu 7/5/18 38 Steel x 20' - FOR
Erection ₱6,913,649.00
columns, beams 6/22/18 Contractor,WIDE FLANGE
and joist - 3rd w6 x 20 x 20' - FOR
floor and roof BEAMS[1],WIDE FLANGE
40 Install 2 wks Fri w8 x 24
Thu 7/5/18 38 Steel x 20' - FOR
Erection ₱60,000.00
miscellaneous iron 6/22/18 Contractor[75%]
and bracing - 1st
and 2nd floors
Page 5
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
41 Install 2 wks Fri 7/6/18 Thu 39 Steel Erection ₱6,893,649.00
miscellaneous iron 7/19/18 Contractor[75%],WIDE
and bracing - 3rd FLANGE w6 x 20 x 20' -
floor and roof FOR BEAMS[1],WIDE
42 Install stairs and 2 wks Fri Thu 8/2/18 41 FLANGE w8 x 24 x 20' -
Steel Erection ₱40,000.00
miscellaneous iron 7/20/18 Contractor[50%]
railing
43 Touch-up paint on 1 wk Fri 8/3/18 Thu 8/9/18 42 Steel Erection ₱8,000.00
steel Contractor[20%]
44 Form and Pour 76.64 days Fri Mon ₱18,803,861.74
Concrete - Floors 6/22/18 10/8/18
and Roof
45 Form 2nd floor 7 days Fri Mon 43,12,13,38
Rough Carpenter ₱3,287,758.00
including all floor 8/10/18 8/20/18 Crew,Labor Crew
openings 1[20%],Formworks/Scaffoldings
for
Beams[1],Formworks/Scaffoldings
46 Install rebar and 7 days Fri Mon 38 for Columns[1],Floor
Labor Crew Slab ₱57,484.00
in-floor utilities 6/22/18 7/2/18 1[33%],Plumbing
(including Contractor[33%],Electric
mechanical, Contractor[33%],Engineer
electrical,
plumbing)
47 Pour 2nd floor slab 5 days Tue Mon 46,45Concrete Crew,CONCRETE ₱2,517,305.00
8/21/18 8/27/18 POURING PER
FLOOR[1],#16 G.I TIE
Task Inactive Summary External Tasks
Page 6
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
48 Cure 2nd floor slab 7 days Tue Wed 47 Labor Crew ₱19,880.00
8/28/18 9/5/18 1[10%],Engineer
49 Strip forms from 3 days Thu Mon 48 Labor Crew ₱2,741,792.00
2nd floor slab 9/6/18 9/10/18 1,Formworks/Scaffoldings
for
Beams[1],Formworks/Scaffoldings
50 Form 3rd floor 7 days Thu Fri 9/14/18 48 for Columns[1],Floor
Rough Carpenter Slab ₱21,560.00
including all floor 9/6/18 Crew[50%],Labor Crew
openings 1[20%],Engineer
51 Install rebar and 7 days Thu Fri 9/14/18 48 Labor Crew ₱57,484.00
in-floor utilities 9/6/18 1[33%],Plumbing
(including Contractor[33%],Electric
mechanical, Contractor[33%],Engineer
electrical,
plumbing)
52 Pour 3rd floor slab 2 days Mon Tue 51,50Concrete Crew,CONCRETE ₱2,507,705.00
9/17/18 9/18/18 POURING PER
53 Cure 3rd floor slab 0.64 days Wed Wed FLOOR[1],#16
52 Labor Crew G.I TIE ₱1,807.27
9/19/18 9/19/18 1[10%],Engineer
54 Strip forms from 1 day Wed Thu 53 Labor Crew 1,Floor Slab ₱2,735,392.00
3rd floor slab 9/19/18 9/20/18 Forms[1],Formworks/Scaffoldings
for
Beams[1],Formworks/Scaffoldings
for Columns[1],Engineer
Page 7
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
55 Form roof slab 3 days Wed Mon 53 Rough Carpenter ₱542,446.00
including all floor 9/19/18 9/24/18 Crew,Labor Crew
openings 1[20%],#16 G.I TIE
WIRES[1],10mm Ø 6m
reinforced steel
56 Install rebar and 3 days Wed Mon bar[1],Engineer
53 Labor Crew ₱24,636.00
in-floor utilities 9/19/18 9/24/18 1[33%],Plumbing
(including Contractor[33%],Electric
mechanical, Contractor[33%],Engineer
electrical,
plumbing)
57 Pour roof slab 2 days Mon Wed 56,55Concrete Crew,Engineer ₱6,400.00
9/24/18 9/26/18
58 Cure roof slab 7 days Wed Fri 10/5/18 57 Labor Crew ₱19,880.00
9/26/18 1[10%],Engineer
59 Strip forms from 1 day Fri Mon 58 Labor Crew 1,Engineer ₱3,200.00
roof slab 10/5/18 10/8/18
Page 8
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
63 Install rebar and 1.99 days Tue Wed 49 Labor Crew ₱16,341.47
in-floor utilities 9/11/18 9/12/18 1[33%],Plumbing
Contractor[33%],Electric
Contractor[33%],Engineer
64 Pour 1st floor slab 2 days Tue Wed 60,63,61,62
Concrete Crew,CONCRETE ₱1,975,099.00
9/18/18 9/19/18 POURING PER
FLOOR[1],Engineer
65 Cure 1st floor slab 7 days Thu Fri 9/28/18 64 Labor Crew ₱19,880.00
9/20/18 1[10%],Engineer
66 Strip forms from 3 days Mon Wed 65 Labor Crew 1,Engineer ₱9,600.00
1st floor slab 10/1/18 10/3/18
Page 9
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
71 Lay masonry at 1 wk Fri Thu 40,41Masonry ₱1,566,356.00
core, mechanical, 7/20/18 7/26/18 Contractor,10mm Ø 6m
and toilets reinforced steel
bar[1],CEMENT
MORTAR[1],CHB 6 1000
72 Install exterior 2.5 wks Mon Thu psi[1],Labor Crew 1,Labor
68 Masonry ₱135,000.00
masonry work 10/15/18 11/1/18 Contractor,Engineer
73 Install tile in toilet 1 wk Thu Wed 70 Tile Contractor,Engineer ₱54,000.00
rooms 10/18/18 10/24/18
74 Clean masonry 1 wk Thu Thu 72 Masonry ₱34,000.00
11/1/18 11/8/18 Contractor[50%],Engineer
75 Clean toilet room 1 wk Thu Wed 73 Tile ₱34,000.00
tile 10/25/18 10/31/18 Contractor[50%],Engineer
76 Roofing 28 days Thu Tue ₱1,212,097.00
11/1/18 12/11/18
77 Install flashing at 3 days Thu Tue 72 Roofing Contractor, PLAIN ₱871,840.00
parapet walls 11/1/18 11/6/18 G.I STRAP 2' X 3'
PURLIN[1],#16 G.I TIE
WIRES[1],ANCHOR
78 Pour lightweight 3 days Tue BOLTS[1],BOTTOM
Fri 11/9/18 11,77Roofing Contractor,Labor ₱33,600.00
concrete roof fill 11/6/18 Crew 2,Engineer
Page 10
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
80 Spread stone 4 days Wed Tue 79 Roofing ₱43,200.00
ballast on 11/21/18 11/27/18 Contractor,Engineer
seamless roof
81 Set rooftop 2 wks Tue Tue 80 LEAD ₱229,857.00
equipment 11/27/18 12/11/18 WASHERS[1],RIVETS[1],Roofing
82 Window wall and 60 days Thu Thu Contractor,Roofing ₱5,663,864.00
store front closures 11/1/18 1/24/19
83 Install window 5 wks Thu Thu 72 Window Contractor,W1 ₱3,893,200.00
wall aluminum and 11/1/18 12/6/18 CASEMENT WINDOW
glass 2.45 X 1.9 m[1],W2
CASEMENT WINDOW
3.45 X 1.9 m[1],W3
84 Install interior stud 5 wks Thu Thu CASEMENT
83 Drywall WINDOW 3.4
Contractor ₱200,000.00
walls and drywall 12/6/18 1/10/19
Page 11
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
88 Paint walls and 2 wks Thu Thu 2/7/19 85 Painting ₱6,248,092.00
woodwork 1/24/19 Contractor,ACRYLIC
89 Install conduit at 1.5 wks Thu Mon LATEX PAINT
83 Electric Contractor,Labor ₱63,000.00
ceiling plenum 12/6/18 12/17/18 Crew 2
space
90 Install duct in 3 wks Thu Thu 84,89Labor Crew 3 ₱6,000.00
ceiling plenum 1/10/19 1/31/19
space
91 Install ceiling grid 2 wks Thu Thu 84,90Drywall Contractor ₱80,000.00
1/31/19 2/14/19
92 Install ceiling tile 2 wks Thu Thu 91 Drywall Contractor,60 x ₱7,085,062.00
2/14/19 2/28/19 60 cm (16' X 16')
CERAMIC FLOOR TILES[1]
Page 12
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
97 Plumbing 75 days Thu Thu ₱1,104,614.00
11/8/18 2/21/19
98 Rough-in plumbing 4 wks Thu Thu 1/3/19 83 Plumbing Contractor ₱160,000.00
in drywall walls 12/6/18
99 Tie-in fire line riser 2 wks Thu Thu 74 Plumbing Contractor ₱80,000.00
and set valves 11/8/18 11/22/18
Page 13
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
112 Remove debris 4 days Thu Wed 94,93,95,96,101,108,92,111
Labor Crew 1 ₱1,600.00
from building and 3/7/19 3/13/19
do final clean-up
Page 14
ID Task Task Name Duration Start Finish Predecessors
Resource Names Cost
Mode
January February Mar
120 Issue final 1 day Tue Wed 118 Project Manager ₱2,800.00
completion 4/23/19 4/24/19
documents
including
warranties
121 Issue final request 1 day Thu Fri 4/26/19 119,120
Project ₱2,904.00
for payment 4/25/19 Manager[33%],Accounting[33%],General
Manager[33%]
Page 15
2018
March April May June July August September October November December January
General Manager,Engineer
Project Manager[25%],Scheduler,Engineer
Project Manager[50%],Procurement[50%],Engineer
Project Manager[50%],Procurement[50%]
Accounting
Page 16
2018
March April May June July August September October November December January
Steel Erection Contractor Management
Page 17
2018
March April May June July August September October November December January
Plumbing Contractor,GATE VALVE[1],PVC ELBOW[1],PVC PIPE 2"[1],PVC PIPE 3"[1],PVC PIPE 4"[1],PVC TEE 2"[1],PVC TEE 3"[1],PVC TEE 4"[1]
Plumbing Contractor,Engineer
Page 18
2018
March April May June July August September October November December January
Site Grading Contractor,Engineer
Survey Crew,Engineer
Page 19
2018
March April May June July August September October November December January
Concrete Crew,Backfilling/Disposal[1],Engineer
Page 20
2018
March April May June July August September October November December January
Steel Erection Contractor[75%],WIDE FLANGE w6 x 20 x 20' - FOR BEAMS[1],WIDE FLAN
Page 21
2018
March April May June July August September October November December January
Labor Crew 1[10%],Engineer
Page 22
2018
March April May June July August September October November December January
Rough Carpenter Crew,Labor Crew 1[20%],#16 G.I TIE WIR
Concrete Crew,Engineer
Page 23
2018
March April May June July August September October November December January
Labor Crew 1[33%],Plumbing Contractor[33%],Electric Contrac
Page 24
2018
March April May June July August September October November December January
Masonry Contractor,10mm Ø 6m reinforced steel bar[1],CEMENT MORTAR[1],CHB 6
Masonry Contractor,Engineer
Tile Contractor,Engineer
Masonry Contractor[50%],Engineer
Tile Contractor[50%],Engineer
Page 25
2018
March April May June July August September October November December January
Roofing Contractor,Engineer
LEAD WASHERS[1],RIV
Window Contractor,W1
Drywall C
Fin
Window Contractor
Page 26
2018
March April May June July August September October November December January
Electric Contractor,
Page 27
2018
March April May June July August September October November December January
Plumbing C
Plumbing Contractor
Pl
Tile C
Til
Page 28
2018
March April May June July August September October November December January
Page 29
2018
March April May June July August September October November December January
Page 30
2019
January February March April May June July August September October November
Page 31
2019
January February March April May June July August September October November
Page 32
2019
January February March April May June July August September October November
TEE 4"[1]
Page 33
2019
January February March April May June July August September October November
Page 34
2019
January February March April May June July August September October November
Page 35
2019
January February March April May June July August September October November
EAMS[1],WIDE FLANGE w8 x 24 x 20' - FOR COLUMNS[1],Formworks/Scaffoldings for Beams[1],Formworks/Scaffoldings for Columns[1],GUSSET PLATE[1]
s/Scaffoldings for Beams[1],Formworks/Scaffoldings for Columns[1],Floor Slab Forms[1],10mm Ø 6m reinforced steel bar[1],#16 G.I TIE WIRES[1],Engineer
ineer
Page 36
2019
January February March April May June July August September October November
[20%],Engineer
3%],Electric Contractor[33%],Engineer
Page 37
2019
January February March April May June July August September October November
20%],#16 G.I TIE WIRES[1],10mm Ø 6m reinforced steel bar[1],Engineer
tor[33%],Electric Contractor[33%],Engineer
PIPE 2"[1],PVC PIPE 3"[1],PVC PIPE 4"[1],PVC TEE 2"[1],PVC TEE 3"[1],PVC TEE 4"[1],TEFLON TAPE[1],Engineer
Page 38
2019
January February March April May June July August September October November
3%],Electric Contractor[33%],Engineer
R FLOOR[1],Engineer
ew 1,Engineer
Page 39
2019
January February March April May June July August September October November
MORTAR[1],CHB 6 1000 psi[1],Labor Crew 1,Labor Crew 2,Engineer
Engineer
or[50%],Engineer
,Engineer
r, PLAIN G.I STRAP 2' X 3' PURLIN[1],#16 G.I TIE WIRES[1],ANCHOR BOLTS[1],BOTTOM CHORD- L 38 X 38 X 6[1],Roofing Contractor Management,Rough Car
Page 40
2019
January February March April May June July August September October November
Contractor,Engineer
AD WASHERS[1],RIVETS[1],Roofing Contractor,Roofing Contractor Management,Rough Carpenter Crew,GI SHEET 50 mm THICK[1],GI SHEET- FOR GUTTER[1]
dow Contractor,W1 CASEMENT WINDOW 2.45 X 1.9 m[1],W2 CASEMENT WINDOW 3.45 X 1.9 m[1],W3 CASEMENT WINDOW 3.4 x 3.2 m[1],W4 BATH WINDO
Drywall Contractor
Finish Carpenter Crew,D1 DOUBLE CASEMENT 2.95m x 2.3m[1],D2 BATHROOM DOOR- SINGLE CASEMENT 1.1 x 2.1[1],D3 CLASSROOM DOO
ntractor
Page 41
2019
January February March April May June July August September October November
Painting Contractor,ACRYLIC LATEX PAINT PRIMER[1],ADHESIVE[1],NEUTRALIZER AND WATER SOLUTION[1],BOTTOM CHORD- L 38 X
Labor Crew 3
Drywall Contractor
Painting Contractor,ACRYLIC LATEX PAINT PRIMER[1],GLOSS LATEX PAINT FINAL COATING[1],NEUTRALIZER AND WATER SO
Carpet Contractor
Landscape Contractor
Page 42
2019
January February March April May June July August September October November
Plumbing Contractor
Contractor
Plumbing Contractor,BRASS FAUCET[1],Frap Pull Down Sprayer Kitchen Sink [1],GATE VALVE[1],Lavatory Sink[1],POZZI/LAV PVE-4090 BASIN
Plumbing Contractor
Tile Contractor,60 x 60 cm (16' X 16') CERAMIC FLOOR TILES[1],ADHESIVE[1],NEUTRALIZER AND WATER SOLUTION[1]
Tile Contractor[50%]
Page 43
2019
January February March April May June July August September October November
Labor Crew 1
Superintendent
Superintendent[50%],Project Manager[50%],Architect
Project Manager[50%],Superintendent[50%]
Project Manager
Page 44
2019
January February March April May June July August September October November
Project Manager
Page 45
2020
December January February March April May June July August September October
Page 46
2020
December January February March April May June July August September October
Page 47
2020
December January February March April May June July August September October
Page 48
2020
December January February March April May June July August September October
Page 49
2020
December January February March April May June July August September October
Page 50
2020
December January February March April May June July August September October
Page 51
2020
December January February March April May June July August September October
Page 52
2020
December January February March April May June July August September October
Page 53
2020
December January February March April May June July August September October
Page 54
2020
December January February March April May June July August September October
Page 55
2020
December January February March April May June July August September October
Page 56
2020
December January February March April May June July August September October
- L 38 X 38 X 6[1],BRASS FAUCET[1],GLOSS LATEX PAINT FINAL COATING[1],Labor Crew 1
ATER SOLUTION[1]
Page 57
2020
December January February March April May June July August September October
Page 58
2020
December January February March April May June July August September October
Page 59
2020
December January February March April May June July August September October
Page 60
2021
November December January February March April May June July August September
Page 61
2021
November December January February March April May June July August September
Page 62
2021
November December January February March April May June July August September
Page 63
2021
November December January February March April May June July August September
Page 64
2021
November December January February March April May June July August September
Page 65
2021
November December January February March April May June July August September
Page 66
2021
November December January February March April May June July August September
Page 67
2021
November December January February March April May June July August September
Page 68
2021
November December January February March April May June July August September
Page 69
2021
November December January February March April May June July August September
Page 70
2021
November December January February March April May June July August September
Page 71
2021
November December January February March April May June July August September
Page 72
2021
November December January February March April May June July August September