Four Seasons Hotel Bahrain

Activity ID

Activity Name

Duration Start

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
15-Sep-14

359 09-Jun-13 A
Project: B4S-20 B4S - Revised Programm...
Programme REV D
- 19-11-13 - AOF --- DO NOT TOUCH

CONTRACT
General
Key Milestones
Key Milestone
No DISP
CGEKM140

Duration of execution without FFE

280 03-Oct-13 A

15-Sep-14

280 03-Oct-13 A

15-Sep-14

280
280
280
271

15-Sep-14
15-Sep-14
15-Sep-14
15-Sep-14

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

GEWCO140

HV cable connection - EDD

22-Dec-13

GEWCO130

Power On

04-Jan-14

GEWCO120

Chilled water pipes connection - Dalkia

18-Jan-14

GEWCO160

Irrigation connection

01-Feb-14

GEWCO100

Sewage connection

01-Apr-14

GEWCO150

Water supply connection

01-Apr-14

CGEKM160

Remove Temporary Causeway

CGEKM150

Completion date

Summary

18 26-Aug-14
0

15-Sep-14
15-Sep-14

287 03-Oct-13 A

02-Sep-14

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

12-Aug-14
12-Aug-14
12-Aug-14
17-Apr-14

MEP first fix Tower

260
260
260
161

CSUTO170

PCC Facade Tower

180 03-Oct-13 A

30-Apr-14

CSUTO160

Finishings Tower

225 03-Oct-13 A

12-Aug-14

CSUTO180

Masonry Tower

102 03-Oct-13 A

30-Mar-14

CSUTO190

Curtain Wall Tower

115 06-Oct-13 A

29-Mar-14

CSUTO150

MEP Final Fix Tower

219 20-Nov-13

02-Aug-14

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

05-Aug-14
05-Aug-14
05-Aug-14
01-Apr-14

Tower
Summary
No DISP
CSUTO120

Facade Podium

263
263
263
168

CSUPO130

MEP first fix Podium

151 03-Oct-13 A

29-Apr-14

CSUPO120

Masonry Podium

56 03-Oct-13 A

14-Dec-13

CSUPO150

Finishes Podium

222 20-Nov-13

05-Aug-14

CSUPO160

MEP Final Fix Podium

166 19-Jan-14

30-Jul-14

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

14-Aug-14
14-Aug-14
14-Aug-14
18-Dec-13

East Podium
Summary
No DISP
CSUPO140

Concrete Structure Podium

271
271
271
41

CSUPO230

MEP first fix Podium

106 03-Oct-13 A

22-Mar-14

CSUPO220

Masonry Podium

79 03-Oct-13 A

13-Feb-14

CSUPO260

Facades Podium

119 10-Dec-13

27-Apr-14

CSUPO240

Finishes Podium

208 16-Dec-13

14-Aug-14

CSUPO250

MEP Final Fix Podium

139 02-Mar-14

10-Aug-14

MEP first fix Car park

287
287
287
180

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

02-Sep-14
02-Sep-14
02-Sep-14
11-Jun-14

CSUCP170

Masonry Car Park

111 03-Oct-13 A

23-Mar-14

CSUCP160

Finishings Car Park

211 31-Dec-13

02-Sep-14

West Podium
Summary
No DISP
CSUPO200

Car Park
Summary
No DISP
CSUCP120

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 1 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

CSUCP150

MEP Final Fix Car Park

Duration Start

122 06-Mar-14

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

GENERAL

62 23-Jun-14

15-Sep-14

Mobilization

62 23-Jun-14

15-Sep-14

Demobilization manpower

62
62
62
61

23-Jun-14
23-Jun-14
23-Jun-14
23-Jun-14*

15-Sep-14
15-Sep-14
15-Sep-14
14-Sep-14

Demobilization Site installation

25 18-Aug-14

15-Sep-14

54 24-Jul-14

15-Sep-14

54 24-Jul-14
54 24-Jul-14
54 24-Jul-14
0

15-Sep-14
15-Sep-14
15-Sep-14
24-Jul-14

Demobilization
Demobilization
No DISP
GMODO100
GMODO110

Finishes - external works

FS Occupance Schedule ( Turnover Timeline )


General
No Sub Locat
No DISP
GFSGE130

Telephone Switch/PABX ( with Life Safety Systems )

0
0
0
0

GFSGE100

Administration offices ( with Life Safety Systems )

24-Jul-14

GFSGE110

Maintenance/Engineering ( with Life Safety Systemsn )

24-Jul-14

GFSGE120

Central Plant ( with Life Safety Systems )

24-Jul-14

GFSGE140

Computer Room and Wiring Closets supporting occupie...

24-Jul-14

GFSGE150

Elevators S1 & S2 ( with Life Safety Systems )

24-Jul-14

GFSGE160

Loading Dock ( with Life Safety Systems )

24-Jul-14

GFSGE180

Vehice/Pedestrian Access Paths

24-Jul-14

GFSGE190

Site Lighting

24-Jul-14

GFSGE200

First two guestroom floors ( with Life Safety Systems )

24-Jul-14

GFSGE210

Receiving/Storage ( with Life Safety ASystems )

24-Jul-14

GFSGE220

Houskeeping/Laundry/Valet ( with Life Safety Systems )

24-Jul-14

GFSGE230

Staff Cafeteria ( with Life Safety Systems )

24-Jul-14

GFSGE240

Security Room and Systems ( with Life Safety Systems )

24-Jul-14

GFSGE250

Ballroom ( with Life Safety Systems )

24-Jul-14

GFSGE260

Main Kitchen

04-Aug-14

GFSGE270

Kitchen Storage

04-Aug-14

GFSGE280

Meeting Rooms

04-Aug-14

GFSGE290

Circulation/Pre-function

04-Aug-14

GFSGE360

Spa Fitness Facilities and pools

04-Aug-14

GFSGE310

Casual Dining Restaurant

05-Aug-14

GFSGE300

Front Desk

09-Aug-14

GFSGE330

Front Offices

11-Aug-14

GFSGE320

Speciality Restaurants

11-Aug-14

GFSGE340

Staff Locker Rooms

18-Aug-14

GFSGE350

Pool

01-Sep-14

GFSGE370

Banquet Kitchen

01-Sep-14

GFSGE410

Last two guestroom floors

01-Sep-14

GFSGE420

Retail

01-Sep-14

GFSGE380

Lobby Lounge/Bar

08-Sep-14

GFSGE390

Elevators - Guest

15-Sep-14

GFSGE400

Signage

15-Sep-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 2 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
26-Jul-14

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

External works
Summary
No DISP
CSUEX110

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

TESTING & COMMISSIONING


Tower

15-Sep-14
15-Sep-14
15-Sep-14
15-Sep-14
14-Aug-14

HVAC System

230 08-Dec-13*

15-Sep-14

COTOW590

Fire Fighting System

207 15-Dec-13*

26-Aug-14

COTOW600

Plumbing System

191 30-Dec-13*

23-Aug-14

COTOW640

Chiller Commissioning

190 30-Dec-13*

21-Aug-14

COTOW680

Building Maintenance Units

18 23-Feb-14*

15-Mar-14

COTOW610

ELV System

154 01-Mar-14*

08-Sep-14

COTOW620

Lightning Protection

90 01-Mar-14*

12-Jun-14

COTOW630

Earthing System

90 01-Mar-14*

12-Jun-14

COTOW570

LPG System

57 08-Mar-14*

12-May-14

COTOW660

Schindler Lifts

113 24-Mar-14*

14-Aug-14

COTOW580

Kitchen System

84 10-May-14*

27-Aug-14

COTOW650

Aircraft Warning Lights

49 13-May-14*

13-Jul-14

COTOW670

Basco - Kitchen

24 02-Jun-14*

29-Jun-14

279 03-Oct-13 A

14-Sep-14

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

14-Sep-14
14-Sep-14
14-Sep-14
26-May-14

Power On

279
279
279
160

COEP570

LPG System

149 03-Oct-13 A

14-May-14

COEP590

Fire Fighting System

238 03-Oct-13 A

04-Sep-14

COEP560

HVAC System

213 11-Dec-13*

30-Aug-14

COEP600

Plumbing System

222 14-Dec-13*

11-Sep-14

COEP610

ELV System

194 19-Jan-14*

14-Sep-14

COEP620

Lightning Protection

106 01-Mar-14*

03-Jul-14

COEP630

Earthing System

106 01-Mar-14*

03-Jul-14

COEP580

Kitchen System

36 05-May-14*

15-Jun-14

COEP660

Wotec - Laundry

12 07-May-14*

20-May-14

COEP650

Hot Water Boiler

8 11-Jun-14*

19-Jun-14

COEP640

Steam Boiler

13 12-Jun-14*

26-Jun-14

COEP670

Basco - Kitchen

30 17-Jun-14*

02-Aug-14

280 03-Oct-13 A

15-Sep-14
15-Sep-14
15-Sep-14
15-Sep-14
26-Jun-14

West Podium

Power On

280
280
280
169

COWP600

Plumbing System

230 08-Dec-13*

15-Sep-14

COWP590

Fire Fighting System

183 20-Jan-14*

02-Sep-14

COWP610

ELV System

154 01-Mar-14*

08-Sep-14

COWP560

HVAC System

122 31-Mar-14*

01-Sep-14

COWP620

Lightning Protection

70 01-Apr-14*

21-Jun-14

COWP630

Earthing System

70 01-Apr-14*

21-Jun-14

COWP570

LPG System

22 05-May-14*

29-May-14

No LLocation
No Sub Locat
No DISP
COWP550

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

280 03-Oct-13 A

Power On

No LLocation
No Sub Locat
No DISP
COEP550

Revised Programme Rev. D

280 03-Oct-13 A

COTOW560

East Podium

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
15-Sep-14

Duration Start

280
280
280
232

No LLocation
No Sub Locat
No DISP
COTOW550

Four Seasons Hotel Bahrain

Page 3 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

COWP580

Kitchen System

27 29-May-14*

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
29-Jun-14

COWP640

Barr & Wray - Thermal Cabins

13 10-Jun-14*

24-Jun-14

COWP660

Basco Kitchens

27 25-Jun-14*

07-Aug-14

COWP650

Al Marhoos - Polls

Activity ID

Activity Name

Car Park

Duration Start

24 29-Jun-14*

07-Aug-14

267 03-Oct-13 A

31-Aug-14
31-Aug-14
31-Aug-14
31-Aug-14
22-Apr-14

LPG System

267
267
267
149

COCP600

Plumbing System

188 01-Dec-13*

15-Jul-14

COCP550

Power On

65 15-Feb-14*

30-Apr-14

COCP560

HVAC System

96 20-Feb-14*

11-Jun-14

COCP590

Fire Fighting System

98 15-Mar-14*

10-Jul-14

COCP640

Smoke Ventilation

34 16-Mar-14*

23-Apr-14

COCP580

Kitchen System

36 24-Mar-14*

04-May-14

COCP610

ELV System

120 01-Apr-14*

31-Aug-14

COCP620

Lightning Protection

70 01-Apr-14*

21-Jun-14

COCP630

Earthing System

70 01-Apr-14*

21-Jun-14

COCP650

CO Monitoring System

116 05-Apr-14*

30-Aug-14

251 15-Sep-13 A

12-Aug-14

174 03-Oct-13 A

01-May-14

174
174
174
173

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

01-May-14
01-May-14
01-May-14
01-May-14

No LLocation
No Sub Locat
No DISP
COCP570

TOWER
Pre-cast Concrete Facades

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

West Core
Facades
No DISP
TFAGE220

West Pier Outer Wall ( Wall 1 ) incl Silicone

TFAGE230

West Pier Inner Wall ( Wall 3 - Grd to 10th )

2 03-Oct-13 A

25-Nov-13

TFAGE240

West Pier Inner Wall ( Wall 3 - 10th to 30th )

12 03-Oct-13 A

28-Nov-13

TFAGE250

West Pier Inner Wall ( Wall 3 - 30th to 42nd )

35 03-Oct-13 A

27-Nov-13

TFAGE260

West Pier Inner Wall ( Wall 3 - 42nd to Parapet)

18 03-Nov-13 A

25-Nov-13

TFAGE310

West Pier Wall ( Wall 3 - 42nd to Parapet) Silicone

9 26-Nov-13

07-Dec-13

TFAGE330

Remove Scaffold ( Wall 3 - 42nd to Parapet)

9 08-Dec-13

17-Dec-13

TFAGE300

West Pier Wall ( Wall 3 - to 42nd ) after RMD

24 29-Dec-13

26-Jan-14

TFAGE280

Remove Mast climbers ( Wall 3 - 30th to 42nd )

24 27-Jan-14

23-Feb-14

TFAGE350

Remove Mast climbers & PPC infill ( Wall 1 )

24 05-Apr-14

01-May-14

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

30-Apr-14
30-Apr-14
30-Apr-14
30-Apr-14

East Pier Inner Wall ( Wall 4 - Grd to 10th )

2 03-Oct-13 A

26-Nov-13

East Pier Inner Wall ( Wall 4 - 30h to 42nd )

24 03-Oct-13 A

24-Nov-13

TFAGE210

East Pier Inner Wall ( Wall 4 - 42nd to Parapet)

18 09-Nov-13 A

30-Nov-13

TFAGE190

East Pier Inner Wall ( Wall 4 - 10th to 30th )

21 06-Oct-13 A

15-Dec-13

TFAGE320

East Pier Wall ( Wall 4 - 42nd to Parapet) Silicone

9 30-Nov-13

11-Dec-13

TFAGE340

Remove scaffold ( Wall 4 - 42nd to Parapet)

9 11-Dec-13

22-Dec-13

TFAGE290

East Pier Wall ( Wall 4 - to 42nd ) after RMD

24 29-Dec-13

26-Jan-14

TFAGE270

Remove Mast climbers ( Wall 4 - 30th to 42nd)

24 27-Jan-14

23-Feb-14

TFAGE360

Remove Mast climbers & PPC infill ( Wall 6 )

East Core
Facades
No DISP
TFAGE170

East Pier Outer Wall ( Wall 6 ) incl Silicone

TFAGE180
TFAGE200

Pier Curatin Wall


West Core

173
173
173
173

24 03-Apr-14

30-Apr-14

114 16-Nov-13

29-Mar-14

89 16-Nov-13

27-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 4 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

North West L-20 to L-47 ( 3 frames )

TCWGE280

South West L-19 to L-47

28 17-Nov-13

19-Dec-13

TCWGE400

Remove West Core Hoist

18 07-Dec-13

26-Dec-13

TCWGE360

North West L-1 to L-39 ( 3 frames )

12 06-Feb-14*

20-Feb-14

TCWGE370

North West L-40 to L-47 ( 3 frames )

6 20-Feb-14*

27-Feb-14

East Core
Curtain Wall
No DISP
TCWGE290

North East L-1 to L-6 ( 3 frames )

85
85
85
3

19-Dec-13
19-Dec-13
19-Dec-13
19-Dec-13

29-Mar-14
29-Mar-14
29-Mar-14
23-Dec-13

TCWGE300

North East L-7 to L-10 ( 3 frames )

2 23-Dec-13

25-Dec-13

TCWGE310

South East L-2 to L-10

6 25-Dec-13

01-Jan-14

TCWGE320

North East L-11 to L-30 ( 3 frames )

14 01-Jan-14*

18-Jan-14

TCWGE330

South East L-11 to L-30

14 01-Jan-14

18-Jan-14

TCWGE340

North East L-31 to L-47 ( 3 frames )

17 18-Jan-14

06-Feb-14

TCWGE350

South East L-31 to L-47

17 18-Jan-14

06-Feb-14

TCWGE410

Remove East Core Hoist

18 16-Feb-14

08-Mar-14

TCWGE390

North East L-1 to L-47 ( 3 frames )

18 09-Mar-14

29-Mar-14

98 16-Nov-13

09-Mar-14

98
98
98
12

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

09-Mar-14
09-Mar-14
09-Mar-14
28-Nov-13

Tower Crane & Hoist removal


No LLocation
No Sub Locat
No DISP
TCWGE430

TC1 Removal

TCWGE420

TC 2 Removal

MEP Risers
Lifts
General
Finishes
No DISP
T+31GE400

Lifts & mach inst + tests PE 5 & 6 Lev 31

T+31GE410

ID Fitout PE 5 & 6

T+31GE430

ID Fitout PE 3 & 4

12 24-Feb-14

09-Mar-14

117 16-Nov-13

01-Apr-14

237 03-Oct-13 A

22-Jul-14

237
237
237
145

22-Jul-14
22-Jul-14
22-Jul-14
06-Mar-14

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

30 08-Mar-14

10-Apr-14

30 10-Jun-14

22-Jul-14
23-Jun-14
23-Jun-14
19-May-14

Lifts & mach inst + tests PE1-2 Lev 47

219 03-Oct-13 A
219 03-Oct-13 A
172 03-Oct-13 A

T+47GE130

Lifts & mach inst + tests SE 1 & 2 Lev 47

160 03-Oct-13 A

15-Feb-14

T+47GE680

Lifts & mach inst + tests SE 3 + 4 Lev 47

182 03-Oct-13 A

24-Apr-14

T+31GE290

Lifts & mach inst + tests PE7-8 Ground Floor

71 11-Dec-13*

04-Mar-14

T+31GE420

ID Fitout PE7-8

30 05-Mar-14

08-Apr-14

T+47GE720

ID Fitout PE1-2

30 20-May-14

23-Jun-14

66 22-Feb-14

08-May-14
08-May-14
08-May-14
08-May-14
27-Feb-14

General
No DISP
T+47GE120

Linen Chute

Delivery to site

66
66
66
6

TGLCGE440

Install Chute tube

54 01-Mar-14

01-May-14

TGLCGE450

Fix door hopper

12 19-Apr-14

01-May-14

TGLCGE460

Test & Commission

General
Finishes
No DISP
TGLCGE430

22-Feb-14
22-Feb-14
22-Feb-14
22-Feb-14*

6 03-May-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 5 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
27-Feb-14
27-Feb-14
19-Dec-13

89 16-Nov-13
89 16-Nov-13
29 16-Nov-13*

Curtain Wall
No DISP
TCWGE270

Four Seasons Hotel Bahrain

08-May-14
Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Stair Finishes
West Core
Finishes
Install LL to Lv 05
TCWGE470
Paint walls & soffit
TCWGE480

RMX_01 to floor & treads

TCWGE500

Install Doors

TCWGE490

Install FHC

Install Lv 06 to Lv 10
TCWGE550
Paint walls & soffit

18-Jan-14
18-Jan-14
01-Feb-14
01-Feb-14

26-Jul-14
26-Jul-14
08-Mar-14
06-Feb-14

15 08-Feb-14

24-Feb-14

5 25-Feb-14

02-Mar-14

5 03-Mar-14

08-Mar-14

40 08-Feb-14
6 08-Feb-14

25-Mar-14
13-Feb-14

15 25-Feb-14

13-Mar-14

Install Doors

5 15-Mar-14

19-Mar-14

TCWGE590

Install FHC

5 20-Mar-14

25-Mar-14

49 15-Feb-14
6 15-Feb-14

12-Apr-14
20-Feb-14

TCWGE650

RMX_01 to floor & treads

15 15-Mar-14

31-Mar-14

TCWGE660

Install Doors

5 01-Apr-14

06-Apr-14

TCWGE670

Install FHC

5 07-Apr-14

12-Apr-14

58 22-Feb-14
6 22-Feb-14

29-Apr-14
27-Feb-14

TCWGE730

RMX_01 to floor & treads

15 01-Apr-14

17-Apr-14

TCWGE740

Install Doors

5 19-Apr-14

23-Apr-14

TCWGE750

Install FHC

5 24-Apr-14

29-Apr-14

102 18-Jan-14
12 18-Jan-14

17-May-14
30-Jan-14

6 01-Mar-14

06-Mar-14

14 19-Apr-14

05-May-14

TCWGE790

Paint walls & soffit

TCWGE810

RMX_01 to floor & treads

TCWGE820

Install Doors

5 05-May-14

11-May-14

TCWGE830

Install FHC

5 11-May-14

17-May-14

105 01-Feb-14
12 01-Feb-14

03-Jun-14
13-Feb-14

Install Lv 26 to Lv 30
TCWGE840
Install handrail
TCWGE870

Paint walls & soffit

TCWGE890

RMX_01 to floor & treads

TCWGE900
TCWGE910

6 08-Mar-14

13-Mar-14

15 05-May-14

22-May-14

Install Doors

5 22-May-14

28-May-14

Install FHC

5 28-May-14

03-Jun-14

108 15-Feb-14
12 15-Feb-14

21-Jun-14
27-Feb-14

Install Lv 31 to Lv 35
TCWGE920
Install handrail
TCWGE950

Paint walls & soffit

TCWGE970

RMX_01 to floor & treads

TCWGE980
TCWGE990

6 15-Mar-14

20-Mar-14

15 22-May-14

09-Jun-14

Install Doors

5 09-Jun-14

15-Jun-14

Install FHC

5 15-Jun-14

21-Jun-14

111 01-Mar-14
12 01-Mar-14
0 01-Mar-14

08-Jul-14
13-Mar-14

Install Lv 36 to Lv 41
TCWGE1000
Install handrail
TCWGE1010
Structural clearance
TCWGE1030

Paint walls & soffit

TCWGE1050

RMX_01 to floor & treads

TCWGE1060
TCWGE1070

6 22-Mar-14

27-Mar-14

15 09-Jun-14

26-Jun-14

Install Doors

5 26-Jun-14

02-Jul-14

Install FHC

5 02-Jul-14

08-Jul-14

Install Lv 42 to Lv 48

114 15-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

162
162
31
6

RMX_01 to floor & treads

Install Lv 20 to Lv 25
TCWGE760
Install handrail

Revised Programme Rev. D

216 16-Nov-13

TCWGE580

Install Lv 15 to Lv 20
TCWGE710
Paint walls & soffit

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
26-Jul-14

Duration Start

TCWGE570

Install Lv 11 to Lv 15
TCWGE630
Paint walls & soffit

Four Seasons Hotel Bahrain

Page 6 of 180

26-Jul-14
Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

Install handrail

TCWGE1090

Structural clearance

0 15-Mar-14

TCWGE1110

Paint walls & soffit

6 29-Mar-14

03-Apr-14

TCWGE1130

RMX_01 to floor & treads

15 26-Jun-14

14-Jul-14

TCWGE1140

Install Doors

5 14-Jul-14

20-Jul-14

TCWGE1150

Install FHC

5 20-Jul-14

26-Jul-14

TCEGE480

RMX_01 to floor & treads

TCEGE500
TCEGE490

163
163
31
6

16-Nov-13
16-Nov-13
30-Nov-13
30-Nov-13*

23-Dec-13

Install Doors

5 24-Dec-13

29-Dec-13

Install FHC

5 30-Dec-13

04-Jan-14

40 07-Dec-13
6 07-Dec-13

21-Jan-14
12-Dec-13

15 24-Dec-13

09-Jan-14

5 11-Jan-14

15-Jan-14

TCEGE570

RMX_01 to floor & treads

TCEGE580

Install Doors

TCEGE590

Install FHC

Install Lv 11 to Lv 15
TCEGE630
Paint walls & soffit

5 16-Jan-14

21-Jan-14

49 14-Dec-13
6 14-Dec-13

08-Feb-14
19-Dec-13

TCEGE650

RMX_01 to floor & treads

15 11-Jan-14

27-Jan-14

TCEGE660

Install Doors

5 28-Jan-14

02-Feb-14

TCEGE670

Install FHC

5 03-Feb-14

08-Feb-14

58 21-Dec-13
6 21-Dec-13

25-Feb-14
26-Dec-13

Install Lv 15 to Lv 20
TCEGE710
Paint walls & soffit
TCEGE730

RMX_01 to floor & treads

15 28-Jan-14

13-Feb-14

TCEGE740

Install Doors

5 15-Feb-14

19-Feb-14

TCEGE750

Install FHC

5 20-Feb-14

25-Feb-14

67 28-Dec-13
6 28-Dec-13

15-Mar-14
02-Jan-14

Install Lv 20 to Lv 25
TCEGE790
Paint walls & soffit
TCEGE810

RMX_01 to floor & treads

15 15-Feb-14

03-Mar-14

TCEGE820

Install Doors

5 04-Mar-14

09-Mar-14

TCEGE830

Install FHC

5 10-Mar-14

15-Mar-14

76 04-Jan-14
6 04-Jan-14

01-Apr-14
09-Jan-14

Install Lv 26 to Lv 30
TCEGE870
Paint walls & soffit
TCEGE890

RMX_01 to floor & treads

15 04-Mar-14

20-Mar-14

TCEGE900

Install Doors

5 22-Mar-14

26-Mar-14

TCEGE910

Install FHC

5 27-Mar-14

01-Apr-14

133 16-Nov-13
18 16-Nov-13

19-Apr-14
05-Dec-13

6 11-Jan-14

16-Jan-14

Install Lv 31 to Lv 35
TCEGE920
Install handrail
TCEGE950

Paint walls & soffit

TCEGE970

RMX_01 to floor & treads

15 22-Mar-14

07-Apr-14

TCEGE980

Install Doors

5 08-Apr-14

13-Apr-14

TCEGE990

Install FHC

5 14-Apr-14

19-Apr-14

Install Lv 36 to Lv 41
TCEGE1000
Install handrail
TCEGE1010

Structural clearance

TCEGE1030

Paint walls & soffit

TCEGE1050

RMX_01 to floor & treads

130 07-Dec-13
18 07-Dec-13

06-May-14
26-Dec-13

6 18-Jan-14

23-Jan-14

15 08-Apr-14

24-Apr-14

Remaining Work
Milestone

Data date: 16-Nov-13

0 07-Dec-13

Summary Bar
Critical Remaining Work

Revised Programme Rev. D

24-May-14
24-May-14
04-Jan-14
05-Dec-13

15 07-Dec-13

Install Lv 06 to Lv 10
TCEGE550
Paint walls & soffit

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
27-Mar-14

TCWGE1080

East Core
Finishes
Install LL to Lv 05
TCEGE470
Paint walls & soffit

12 15-Mar-14

Four Seasons Hotel Bahrain

Page 7 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

TCEGE1060

Install Doors

TCEGE1070

Install FHC

Install Lv 42 to Lv 48
TCEGE1080
Install handrail
TCEGE1090

Structural clearance

TCEGE1110

Paint walls & soffit

TCEGE1130

RMX_01 to floor & treads

TCEGE1140

Install Doors

TCEGE1150

Install FHC

Lower level
General
Finishes
No DISP
TL1GE110

Masonry

5 01-May-14

06-May-14
24-May-14
16-Jan-14

0 28-Dec-13
6 25-Jan-14

30-Jan-14

15 26-Apr-14

12-May-14

5 13-May-14

18-May-14

5 19-May-14

24-May-14

224 04-Nov-13 A

05-Aug-14

113
108
108
12

13-Jan-14
13-Jan-14
13-Jan-14
13-Jan-14

24-May-14
18-May-14
18-May-14
26-Jan-14

36 27-Jan-14

09-Mar-14

Marble or ceramic tiles on walls

24 17-Feb-14

16-Mar-14

TL1GE200

Marble or ceramic tiles on floor

42 03-Mar-14

20-Apr-14

TL1GE250

Install door sets

18 17-Mar-14

06-Apr-14

TL1GE210

Gypsum False ceiling

30 31-Mar-14

04-May-14

TL1GE260

Final Painting

12 05-May-14

18-May-14

60 27-Jan-14
60 27-Jan-14
0 27-Jan-14

06-Apr-14
06-Apr-14

TL1GE360

FCU installation

12 27-Jan-14

09-Feb-14

TL1GE390

Duct installation and connections

16 03-Feb-14

20-Feb-14

TL1GE400

CHW piping and valve package installation

15 11-Feb-14

27-Feb-14

TL1GE440

Cable tray & trunking

12 22-Feb-14

06-Mar-14

TL1GE450

Installation of Dampers & Plenums

8 26-Feb-14

06-Mar-14

TL1GE480

Electrical conduiting

12 26-Feb-14

11-Mar-14

TL1GE460

CHW pipe pressure testing

5 01-Mar-14

05-Mar-14

TL1GE470

Condensate drain pipe connection

4 01-Mar-14

04-Mar-14

TL1GE490

CHW pipe insulation

8 06-Mar-14

15-Mar-14

TL1GE500

FP piping

TL1GE510

Cable & Wire pulling

TL1GE520

FP pipe pressure testing

TL1GE530

8 08-Mar-14

16-Mar-14

12 12-Mar-14

25-Mar-14

3 17-Mar-14

19-Mar-14

Cable Termination

10 26-Mar-14

06-Apr-14

Sprinkler installation

54 23-Mar-14
54 23-Mar-14
6 23-Mar-14

24-May-14
24-May-14
29-Mar-14

TL1GE560

Grilles & Diffusers

8 29-Mar-14

06-Apr-14

TL1GE550

Installation of Floor Drains

5 07-Apr-14

12-Apr-14

TL1GE580

Light Fittings

8 11-May-14

19-May-14

TL1GE590

ELV Devices

5 19-May-14

24-May-14

Compacted filling

28
28
28
9

TL1CCT120

MEP in make-up zone

15 07-Nov-13 A

25-Nov-13

TL1CCT130

Slab topping to +5.05

9 26-Nov-13

07-Dec-13

04-Nov-13 A
04-Nov-13 A
04-Nov-13 A
04-Nov-13 A

07-Dec-13
07-Dec-13
07-Dec-13
17-Nov-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

127 28-Dec-13
18 28-Dec-13

Internal & External windows

Tower
Civil Works
No DISP
TL1CCT110

Revised Programme Rev. D

5 26-Apr-14

TL1GE190

MEP Final Fix


No DISP
TL1GE540

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
30-Apr-14

Duration Start

TL1GE180

MEP 1st & 2nd Fix


No DISP
TL1GE340
Access from Structure

Four Seasons Hotel Bahrain

Page 8 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Admin Offices
Finishes
No DISP
TL1MP100

Masonry

Duration Start

131
125
125
30

08-Dec-13
08-Dec-13
08-Dec-13
08-Dec-13

Screed

18 06-Jan-14

26-Jan-14

TL1MP110

Drylined walls

24 20-Jan-14

16-Feb-14

TL1MP140

Acoustic False ceiling grid

12 03-Mar-14

16-Mar-14

TL1MP120

Door sets

18 17-Mar-14

06-Apr-14

TL1MP200

Mist coat to walls

6 17-Mar-14

23-Mar-14

TL1MP510

Wall Covering

18 24-Mar-14

13-Apr-14

TL1MP520

Rubber skirting

12 06-Apr-14

19-Apr-14

TL1MP500

Acoustic tiles

12 13-Apr-14

26-Apr-14

TL1MP530

Carpet

6 27-Apr-14

03-May-14

119 22-Dec-13
57 22-Dec-13
0 22-Dec-13

10-May-14
26-Feb-14

TL1MP250

Drainage Piping

15 22-Dec-13

08-Jan-14

TL1MP260

Drainage Pipe testing

6 09-Jan-14

15-Jan-14

TL1MP450

Water Supply Piping

18 09-Jan-14

29-Jan-14

TL1MP470

Water Supply Pipe insulation

12 27-Jan-14

09-Feb-14

TL1MP460

Water Supply Pipe Pressure Testing

6 30-Jan-14

05-Feb-14

TL1MP300

Condensate drain pipe connection

12 01-Feb-14

13-Feb-14

TL1MP360

FP Piping

12 10-Feb-14

23-Feb-14

TL1MP380

FP pipe pressure testing

MEP Final Fix


TL1MP410
TL1MP400

Installation of Floor Drains

26-Feb-14
10-May-14
20-Feb-14

6 04-May-14

10-May-14

Cable tray & trunking

26-Apr-14
16-Mar-14
09-Feb-14

Electrical conduiting

12 03-Feb-14

16-Feb-14

TL1MP370

Cable & Wire pulling

12 17-Feb-14

02-Mar-14

TL1MP390

Cable Termination

12 03-Mar-14

16-Mar-14

Light Fittings

8 17-Apr-14
8 17-Apr-14

26-Apr-14
26-Apr-14

TL1MP440

ELV Devices

6 17-Apr-14

23-Apr-14

TL1MP490

Wiring Accessories

6 20-Apr-14

26-Apr-14

107 22-Dec-13
49 22-Dec-13
6 22-Dec-13

26-Apr-14
17-Feb-14
28-Dec-13

TL1MP350

MEP Final Fix


TL1MP430

HVAC
1st & 2nd Fix
TL1MP270

Sprinkler installation

6 20-Feb-14
73 15-Feb-14
6 15-Feb-14
77 27-Jan-14
42 27-Jan-14
12 27-Jan-14

ELECTRICAL
1st & 2nd Fix
TL1MP330

FCU installation

TL1MP280

Duct installation and connections

16 29-Dec-13

16-Jan-14

TL1MP290

CHW piping and valve package installation

12 18-Jan-14

30-Jan-14

TL1MP480

Installation and connection to VAV boxes

12 18-Jan-14

30-Jan-14

TL1MP310

CHW pipe pressure testing

6 01-Feb-14

06-Feb-14

TL1MP320

Installation of Dampers & Plenums

9 01-Feb-14

10-Feb-14

TL1MP340

CHW pipe insulation

9 08-Feb-14

17-Feb-14

Grilles & Diffusers

9 16-Apr-14
9 16-Apr-14

26-Apr-14
26-Apr-14

72 29-Dec-13

24-Mar-14

MEP Final Fix


TL1MP420
General
Summary Bar

Remaining Work
Critical Remaining Work
Milestone

Page 9 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-May-14
03-May-14
03-May-14
12-Jan-14

TL1MP540

PLUMBING & FP
1st & 2nd Fix
TL1MP230
Access from Structure

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

HVAC distribution, quip & tests

72 29-Dec-13
30 29-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
24-Mar-14
02-Feb-14

TL1MP160

Heat exchangers, chilled water pumps installation

18 29-Dec-13

19-Jan-14

TL1MP170

Pipes & duct insulation

30 20-Jan-14

23-Feb-14

TL1MP180

Electrical distribution & tests

24 03-Feb-14

02-Mar-14

TL1MP190

Electrical boards

18 17-Feb-14

09-Mar-14

TL1MP210

Testing & commissioning

24 24-Feb-14

23-Mar-14

TL1MP220

Chilled Water Connection

0 24-Mar-14

Activity ID

Activity Name

No DISP
TL1MP150

Restaurant
Finishes
No DISP
TL1RE620

All Design Discrepencies clarified

Duration Start

189 15-Dec-13
189 15-Dec-13
189 15-Dec-13
0

05-Aug-14
05-Aug-14
05-Aug-14
15-Dec-13

TL1RE100

Masonry

18 25-Dec-13

15-Jan-14

TL1RE160

Gypsum walls

24 16-Jan-14

12-Feb-14

TL1RE520

Curtain WAll Frames - South Elevation (11)

14 29-Jan-14

15-Feb-14

TL1RE180

Gypsum False ceiling

36 10-Mar-14

20-Apr-14

TL1RE590

Curtain WAll Glass - South Elevation (11)

4 19-Mar-14

23-Mar-14

TL1RE560

Wood Veneer ceiling

24 24-Mar-14

20-Apr-14

TL1RE490

Decorative metal columns

18 31-Mar-14

20-Apr-14

TL1RE170

Marble on walls

36 05-Apr-14*

15-May-14

TL1RE540

Paint Gypsum ceiling

18 07-Apr-14

27-Apr-14

TL1RE530

Water Feature

18 13-Apr-14*

03-May-14

TL1RE470

Marble floors

36 03-May-14

12-Jun-14

TL1RE500

Feature stairs

24 04-May-14

31-May-14

TL1RE480

Millwork

30 24-May-14

26-Jun-14

TL1RE550

Food Stations

42 24-May-14

17-Jul-14

TL1RE510

Private dining & Dining Screens

18 01-Jun-14*

21-Jun-14

TL1RE570

Wall Covering

12 14-Jun-14

26-Jun-14

TL1RE580

Private dining Finishes

18 22-Jun-14

19-Jul-14

TL1RE220

Painting

18 28-Jun-14

27-Jul-14

TL1RE240

Carpet

MEP 1st & 2nd Fix


No DISP
TL1RE250
Access from Structure

6 30-Jul-14

05-Aug-14

63 25-Dec-13
63 25-Dec-13
0 25-Dec-13

09-Mar-14
09-Mar-14

TL1RE300

Duct installation and connections

18 25-Dec-13

15-Jan-14

TL1RE600

AV Sytem Containment

30 25-Dec-13

29-Jan-14

TL1RE350

Cable tray & trunking

12 05-Jan-14

18-Jan-14

TL1RE370

Electrical conduiting

12 11-Jan-14

23-Jan-14

TL1RE340

Installation of Dampers & Plenums

12 16-Jan-14

29-Jan-14

TL1RE380

FP piping

12 19-Jan-14

01-Feb-14

TL1RE390

Cable & Wire pulling

12 25-Jan-14

06-Feb-14

TL1RE400

FP pipe pressure testing

6 02-Feb-14

08-Feb-14

TL1RE610

Electrical Boards

18 09-Feb-14

01-Mar-14

TL1RE410

Cable Termination

7 02-Mar-14

09-Mar-14

45 28-Apr-14
45 28-Apr-14
6 28-Apr-14

18-Jun-14
18-Jun-14
04-May-14

8 28-Apr-14

06-May-14

12 28-Apr-14

11-May-14

MEP Final Fix


No DISP
TL1RE420

Sprinkler installation

TL1RE440

Grilles & Diffusers

TL1RE450

Light Fittings

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 10 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

TL1RE460

ELV Devices

TL1RE430

Installation of Floor Drains

Computer room
Finishes
No DISP
TL1MP550

West pier hoist removed

18-Jun-14

28-Dec-13
28-Dec-13
28-Dec-13
28-Dec-13

17-Apr-14
17-Apr-14
17-Apr-14
07-Jan-14

TL1MP560

Compacted fill

4 08-Jan-14

12-Jan-14

TL1MP570

Floor slab

6 13-Jan-14

19-Jan-14

TL1MP580

Blockwork

9 20-Jan-14

29-Jan-14

TL1MP590

Screed

3 30-Jan-14

02-Feb-14

TL1MP610

Plaster to walls

6 03-Feb-14

09-Feb-14

TL1MP620

Ceramic tiles to walls

6 23-Mar-14

29-Mar-14

TL1MP630

Acoustic ceiling 1st fix & service tiles

6 30-Mar-14

05-Apr-14

TL1MP640

Mesh fence and gate

6 30-Mar-14

05-Apr-14

TL1MP650

Install doors & Window

6 06-Apr-14

12-Apr-14

TL1MP670

Acoustic ceiling tiles

6 06-Apr-14

12-Apr-14

TL1MP660

Vinyl floor & skirting

4 13-Apr-14

16-Apr-14

TL1MP680

Fire extinguiser cabinet

1 17-Apr-14

17-Apr-14

TL1MP600

Room Complete

17-Apr-14

41 02-Feb-14
41 02-Feb-14
0

22-Mar-14
22-Mar-14
02-Feb-14

TLLBQ1470

Cable Tray and Trunking

8 03-Feb-14

11-Feb-14

TLLBQ1540

Preaction sprinkler system Piping

6 03-Feb-14

09-Feb-14

TLLBQ1580

Piping Installation

10 03-Feb-14

13-Feb-14

TLLBQ1730

MCC Panel & switches

10 03-Feb-14

13-Feb-14

TLLBQ1740

AHU Installation ( 3# )

8 03-Feb-14

11-Feb-14

TLLBQ1560

Sprinkler Pipe drops

3 10-Feb-14

12-Feb-14

TLLBQ1600

Praction sprinkler Pipe Pressure Testing

4 13-Feb-14

17-Feb-14

TLLBQ1530

Duct Installation

9 15-Feb-14

24-Feb-14

TLLBQ1490

Electrical Conduiting

8 15-Feb-14

23-Feb-14

TLLBQ1620

Pipe pressure testing

7 15-Feb-14

22-Feb-14

TLLBQ1640

Pipe insulation

7 18-Feb-14

25-Feb-14

TLLBQ1750

Pipe & valve package connection to AHU's

10 22-Feb-14

04-Mar-14

TLLBQ1500

Lighting & power wiring

6 24-Feb-14

02-Mar-14

TLLBQ1570

Flexible ducts and Plenums

4 25-Feb-14

01-Mar-14

TLLBQ1760

Duct connection to AHU's

12 25-Feb-14

10-Mar-14

TLLBQ1520

ELV cabling

5 03-Mar-14

08-Mar-14

TLLBQ1610

FCU installation & connections ( 2# )

10 05-Mar-14

16-Mar-14

TLLBQ1550

Cable Termination

12 09-Mar-14

22-Mar-14

TLLBQ1770

Dampers & plenum installation

10 11-Mar-14

22-Mar-14
15-Apr-14
15-Apr-14
08-Apr-14

Sprinkler installation

9 06-Apr-14
9 06-Apr-14
3 06-Apr-14

TLLBQ1660

Light Fittings

3 09-Apr-14

12-Apr-14

TLLBQ1680

Wiring Accs.

3 09-Apr-14

12-Apr-14

TLLBQ1670

ELV Devices

3 13-Apr-14

15-Apr-14

Summary Bar
Remaining Work
Milestone

Data date: 16-Nov-13

5 14-Jun-14
95
95
95
0

9 28-Dec-13

Critical Remaining Work

Revised Programme Rev. D

5 10-May-14

Ground Floor suspended slab

MEP Finishes
No DISP
TLLBQ1700

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
14-May-14

Duration Start

TL1MP690

MEP 1st & 2nd Fix


No DISP
TLLBQ1710
Access from structure

Four Seasons Hotel Bahrain

Page 11 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Restrooms
Finishes
No DISP
TLLGE1970

Blockwork to MEP risers - one side

Duration Start

130
127
127
6

08-Dec-13
08-Dec-13
08-Dec-13
08-Dec-13*

Gypsum stud to wall partitions

6 15-Dec-13*

21-Dec-13

TLLGE1800

Blockwork to close MEP risers

9 20-Jan-14*

29-Jan-14

TLLGE1940

Steel frame for vanity units

4 26-Jan-14*

29-Jan-14

TLLGE1900

Stud to block walls & cubicle partitions

6 30-Jan-14*

05-Feb-14

TLLGE1910

MEP drops in walls

4 06-Feb-14*

10-Feb-14

TLLGE1920

Cement board to walls & cubicle partitions

9 11-Feb-14*

20-Feb-14

TLLGE1830

Gypsum ceiling

12 22-Feb-14

06-Mar-14

TLLGE1950

Install corniche

5 08-Mar-14

12-Mar-14

TLLGE1810

Waterproofing

4 13-Mar-14

17-Mar-14

TLLGE1930

Waterproofing Test complete

4 18-Mar-14

22-Mar-14

TLLGE1820

Screed floor

4 23-Mar-14

26-Mar-14

TLLGE1840

Marble to Walls,Floor, cubicles & vanity tops

15 27-Mar-14

13-Apr-14

TLLGE1860

Install Millwork & wall panelling

12 14-Apr-14

27-Apr-14

TLLGE1870

Install doors & frames

4 23-Apr-14

27-Apr-14

TLLGE1880

Wallcoverings

5 28-Apr-14

03-May-14

TLLGE1890

Mirrors

2 04-May-14

05-May-14

24 22-Dec-13
24 22-Dec-13
4 22-Dec-13*

19-Jan-14
19-Jan-14
25-Dec-13

TLLBQ1400

Drainage piping

4 22-Dec-13*

25-Dec-13

TLLBQ1280

Electrical Conduiting

4 26-Dec-13

30-Dec-13

TLLBQ1310

Lighting & power wiring

6 26-Dec-13

02-Jan-14

TLLBQ1410

Drainage pipe testing

3 26-Dec-13*

29-Dec-13

TLLBQ1450

ELV cabling

6 26-Dec-13

02-Jan-14

TLLBQ1290

Duct Installation

5 30-Dec-13

05-Jan-14

TLLBQ1300

FP Piping

4 31-Dec-13

05-Jan-14

TLLBQ1350

Cable Termination

4 04-Jan-14

07-Jan-14

TLLBQ1320

FP Pipe drops

3 06-Jan-14

08-Jan-14

TLLBQ1340

Flexible ducts and Plenums

4 06-Jan-14

09-Jan-14

TLLBQ1330

CHW Piping

4 06-Jan-14

09-Jan-14

TLLBQ1420

Domestic water Piping

6 06-Jan-14

12-Jan-14

TLLBQ1380

FP Pipe Pressure Testing

4 09-Jan-14

13-Jan-14

TLLBQ1360

FCU installation

2 11-Jan-14

12-Jan-14

TLLBQ1370

CHW Pipe pressure testing

3 11-Jan-14

13-Jan-14

TLLBQ1430

Pressure test for Domestic water

3 13-Jan-14

15-Jan-14

TLLBQ1390

CHW Pipe insulation

4 14-Jan-14

18-Jan-14

TLLBQ1440

Insulation to Domestic water

3 16-Jan-14

19-Jan-14

Sanitaryware & connections

22 14-Apr-14
22 14-Apr-14
6 14-Apr-14

08-May-14
08-May-14
20-Apr-14

MEP Finishes
No DISP
TLLBQ1460
TLLBQ1200

Light Fittings

3 04-May-14

06-May-14

TLLBQ1220

ELV Devices

3 04-May-14

06-May-14

TLLBQ1180

Wiring Accs.

3 04-May-14

06-May-14

TLLBQ1190

Sprinkler installation

3 06-May-14

08-May-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 12 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
08-May-14
05-May-14
05-May-14
14-Dec-13

TLLGE1980

MEP 1st & 2nd Fix


No DISP
TLLBQ1270
Cable Tray and Trunking

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

219 16-Nov-13

Ground level
General
MEP Risers
No DISP
T+GGE20

Duration Start

Drainage Riser

77
26
26
10

24-Nov-13
24-Nov-13
24-Nov-13
24-Nov-13*

Rain Water Riser

8 27-Nov-13

07-Dec-13

CD Pipe Riser

8 27-Nov-13

07-Dec-13

T+GGE50

Water Supply Risers

12 30-Nov-13

14-Dec-13

T+GGE60

Electrical Risers

12 03-Dec-13

16-Dec-13

T+GGE70

LPG Riser

6 03-Dec-13

09-Dec-13

T+GGE80

Ducting Risers

14 04-Dec-13

19-Dec-13

T+GGE90

FP Pipe Riser

10 04-Dec-13

15-Dec-13

T+GGE100

CHW Pipe Supply/Return riser

14 09-Dec-13

24-Dec-13

67 07-Dec-13
67 07-Dec-13
10 07-Dec-13

23-Feb-14
23-Feb-14
17-Dec-13

T+GGE300

Water Supply Piping

10 15-Dec-13

25-Dec-13

T+GGE120

Drainage Pipe testing

3 18-Dec-13

21-Dec-13

T+GGE140

Duct installation and connections

12 21-Dec-13

04-Jan-14

T+GGE150

CHW piping and valve package installation

10 25-Dec-13

06-Jan-14

T+GGE310

Water Supply Pipe Pressure testing

3 26-Dec-13

29-Dec-13

T+GGE320

Water Supply Pipe insulation

6 30-Dec-13

06-Jan-14

T+GGE180

Installation of Dampers & Plenums

8 05-Jan-14

13-Jan-14

T+GGE190

Cable tray & trunking

10 05-Jan-14

15-Jan-14

T+GGE170

CHW pipe pressure testing

5 07-Jan-14

12-Jan-14

T+GGE160

Condensate drain pipe connection

4 07-Jan-14

11-Jan-14

T+GGE210

Electrical conduiting

8 11-Jan-14

19-Jan-14

T+GGE200

CHW pipe insulation

8 13-Jan-14

21-Jan-14

T+GGE220

FP piping

8 16-Jan-14

25-Jan-14

T+GGE240

FP pipe pressure testing

3 26-Jan-14

28-Jan-14

T+GGE340

Floor Conduiting & Boxes

7 02-Feb-14

09-Feb-14

T+GGE230

Cable & Wire pulling

6 10-Feb-14

16-Feb-14

T+GGE330

Cable Termination

6 17-Feb-14

23-Feb-14

Lower Scaffold to Porte Cochere

83
83
83
9

TGCCT170

Remove Scaffold to Porte Cochere

12 09-Jan-14

22-Jan-14

TGCCT180

Pre-cast panel installation

12 06-Feb-14

19-Feb-14

West Core
Finishes
No DISP
TGGE330

Masonry

120
120
120
12

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

19-Feb-14
19-Feb-14
19-Feb-14
25-Nov-13

27-Jan-14
27-Jan-14
27-Jan-14
27-Jan-14

15-Jun-14
15-Jun-14
15-Jun-14
09-Feb-14

TGGE340

MEP 1st and 2nd fix

36 27-Jan-14

09-Mar-14

TGGE360

Suspended ceiling

24 10-Mar-14

06-Apr-14

TGGE350

Walll finishes to Madjlis

36 07-Apr-14

18-May-14

TGGE370

Floor finishes to Madjlis

24 19-May-14

15-Jun-14

108 03-Feb-14
108 03-Feb-14

08-Jun-14
08-Jun-14

East Core
Finishes
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 13 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

23-Feb-14
24-Dec-13
24-Dec-13
05-Dec-13

T+GGE40

Tower
Civil Works
No DISP
TGCCT160

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-Aug-14

T+GGE30

MEP 1st & 2nd Fix


No DISP
T+GGE110
Drainage Piping

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

No DISP
TGGE380

Masonry

Duration Start

108 03-Feb-14
12 03-Feb-14

MEP 1st and 2nd fix

36 17-Feb-14

30-Mar-14

TGGE400

Suspended ceiling

24 31-Mar-14

27-Apr-14

TGGE410

Walll finishes

18 28-Apr-14

18-May-14

TGGE420

Floor finishes

18 19-May-14

08-Jun-14

210
162
162
24

26-Nov-13
23-Jan-14
23-Jan-14
23-Jan-14

12-Aug-14
12-Aug-14
12-Aug-14
19-Feb-14

TGEH180

Suspended metal ceiling

24 20-Feb-14

19-Mar-14

TGEH280

Plaster board Ceilings

24 20-Feb-14

19-Mar-14

TGEH290

Timber Ceilings to Alcove, vestibule & reception Ceilings

24 06-Mar-14

02-Apr-14

TGEH170

Marble to walls

30 17-Apr-14*

21-May-14

TGEH250

Marble to floor

24 15-May-14

11-Jun-14

TGEH260

Plaster relieve to walls

30 12-Jun-14

26-Jul-14

TGEH220

Painting

18 06-Jul-14

04-Aug-14

TGEH270

Install front deck incl MEP

9 27-Jul-14

09-Aug-14

TGEH240

Carpet

6 05-Aug-14

12-Aug-14

60 26-Nov-13
60 26-Nov-13
36 26-Nov-13

05-Feb-14
05-Feb-14
08-Jan-14

12 23-Jan-14

05-Feb-14

MEP 1st & 2nd Fix


No DISP
T+GEH220
MEP installation & testing above ceiling
T+GEH40

Duct installation and connections

T+GEH80

Installation of Dampers & Plenums

MEP Final Fix


No DISP
T+GEH230
T+GEH170
Majilis
Finishes
No DISP
TGEH320

MEP final fix to metal ceiling


Grilles & Diffusers

MEP Installation

9 27-Jan-14

05-Feb-14

71 10-Mar-14
71 10-Mar-14
12 10-Mar-14

31-May-14
31-May-14
23-Mar-14

8 22-May-14

31-May-14

132
132
132
30

06-Feb-14
06-Feb-14
06-Feb-14
06-Feb-14

15-Jul-14
15-Jul-14
15-Jul-14
12-Mar-14

TGEH300

Plaster board walls

12 13-Mar-14

26-Mar-14

TGEH310

Plaster board ceilings

18 27-Mar-14

16-Apr-14

TGEH330

Timber ceilings

18 17-Apr-14

07-May-14

TGEH350

Marble floor

18 08-May-14

28-May-14

TGEH340

Timber wall panels

12 29-May-14

11-Jun-14

TGEH360

Millwork

12 26-Jun-14

15-Jul-14

Restrooms
Finishes
No DISP
TGLGE1970

Blockwork to MEP risers - one side

138
135
135
6

28-Dec-13
28-Dec-13
28-Dec-13
28-Dec-13*

07-Jun-14
03-Jun-14
03-Jun-14
04-Jan-14

TGLGE1800

Blockwork to close MEP risers

6 02-Feb-14*

08-Feb-14

TGLGE1900

Stud to block walls

3 05-Feb-14*

08-Feb-14

TGLGE1940

Steel frame for vanity units

3 05-Feb-14*

08-Feb-14

TGLGE1910

MEP drops in walls

2 09-Feb-14*

10-Feb-14

TGLGE1920

Cement board to walls

4 11-Feb-14*

15-Feb-14

TGLGE1960

Stud & board to cubicle partitions

6 11-Feb-14

17-Feb-14

TGLGE1830

Gypsum ceiling

9 16-Feb-14

25-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 14 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
08-Jun-14
16-Feb-14

TGGE390

Ground floor Lobby


Finishes
No DISP
TGEH100
Plaster board walls

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

TGLGE1950

Install corniche

5 26-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
03-Mar-14

TGLGE1810

Waterproofing

4 04-Mar-14

08-Mar-14

TGLGE1930

Waterproofing Test complete

4 09-Mar-14

12-Mar-14

TGLGE1820

Screed floor

4 13-Mar-14

17-Mar-14

TGLGE1840

Marble to Walls,Floor, cubicles & vanity tops

15 19-Apr-14*

05-May-14

TGLGE1860

Install Millwork & wall panelling

12 13-May-14

26-May-14

TGLGE1870

Install doors & frames

4 22-May-14

26-May-14

TGLGE1880

Wallcoverings

5 27-May-14

01-Jun-14

TGLGE1890

Mirrors

2 02-Jun-14

03-Jun-14

24 05-Jan-14
24 05-Jan-14
4 05-Jan-14*

01-Feb-14
01-Feb-14
08-Jan-14

Activity ID

Activity Name

MEP 1st & 2nd Fix


No DISP
TGLBQ1270
Cable Tray and Trunking

Duration Start

TGLBQ1400

Drainage piping

4 05-Jan-14*

08-Jan-14

TGLBQ1280

Electrical Conduiting

4 09-Jan-14

13-Jan-14

TGLBQ1310

Lighting & power wiring

6 09-Jan-14

15-Jan-14

TGLBQ1410

Drainage pipe testing

3 09-Jan-14*

12-Jan-14

TGLBQ1450

ELV cabling

6 09-Jan-14

15-Jan-14

TGLBQ1290

Duct Installation

5 13-Jan-14

18-Jan-14

TGLBQ1300

FP Piping

4 14-Jan-14

18-Jan-14

TGLBQ1350

Cable Termination

4 16-Jan-14

20-Jan-14

TGLBQ1320

FP Pipe drops

3 19-Jan-14

21-Jan-14

TGLBQ1340

Flexible ducts and Plenums

4 19-Jan-14

22-Jan-14

TGLBQ1330

CHW Piping

4 19-Jan-14

22-Jan-14

TGLBQ1420

Domestic water Piping

6 19-Jan-14

25-Jan-14

TGLBQ1380

FP Pipe Pressure Testing

4 22-Jan-14

26-Jan-14

TGLBQ1360

FCU installation

2 23-Jan-14

25-Jan-14

TGLBQ1370

CHW Pipe pressure testing

3 23-Jan-14

26-Jan-14

TGLBQ1430

Pressure test for Domestic water

3 26-Jan-14

28-Jan-14

TGLBQ1390

CHW Pipe insulation

4 27-Jan-14

30-Jan-14

TGLBQ1440

Insulation to Domestic water

3 29-Jan-14

01-Feb-14

Sanitaryware & connections

28 06-May-14
28 06-May-14
6 06-May-14

07-Jun-14
07-Jun-14
12-May-14

MEP Finishes
No DISP
TGLBQ1460
TGLBQ1190

Sprinkler installation

3 04-Jun-14

07-Jun-14

TGLBQ1200

Light Fittings

3 04-Jun-14

07-Jun-14

TGLBQ1220

ELV Devices

3 04-Jun-14

07-Jun-14

TGLBQ1180

Wiring Accs.

3 04-Jun-14

07-Jun-14

Lobby Kitchen & Service Bar


Finishes
No DISP
T+GLA330
Gypsum & cement plaster

171
96
96
15

16-Nov-13
29-Jan-14
29-Jan-14
29-Jan-14

04-Jun-14
20-May-14
20-May-14
15-Feb-14

T+GLA360

Wall ceramic tiles

18 16-Feb-14

08-Mar-14

T+GLA420

Acoustic ceiling first fix & service tiles

12 09-Mar-14

22-Mar-14

T+GLA370

Internal windows

6 16-Mar-14

22-Mar-14

T+GLA400

Ceramic tiles to Floor

24 23-Mar-14

19-Apr-14

T+GLA390

Install doors

6 20-Apr-14

26-Apr-14

T+GLA380

Kitchen equipment

15 20-Apr-14

06-May-14

T+GLA410

Final Painting

12 07-May-14

20-May-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 15 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+GLA430

Acoustic ceiling tiles

T+GLA440

Millwork

T+GGE1390

Complete

MEP 1st & 2nd Fix


No DISP
T+GPSK120
Drainage Piping

Duration Start

6 07-May-14
12 07-May-14
0
56 09-Jan-14
56 09-Jan-14
12 09-Jan-14

15-Mar-14
15-Mar-14
22-Jan-14

12 23-Jan-14

05-Feb-14

FP Piping

12 23-Jan-14

05-Feb-14

T+GPSK140

Drainage Pipe Testing

5 23-Jan-14

28-Jan-14

T+GPSK150

Electrical Conduiting

14 02-Feb-14

17-Feb-14

T+GPSK160

Duct Installation

15 06-Feb-14

23-Feb-14

T+GPSK230

FP Dropper Piping

6 06-Feb-14

12-Feb-14

T+GPSK220

Cabling and Wiring

18 06-Feb-14

26-Feb-14

T+GPSK170

FCU Installation

8 09-Feb-14

18-Feb-14

T+GPSK250

FP Pipe Pressure Testing

7 13-Feb-14

20-Feb-14

T+GPSK180

CHW Piping & valve connection to FCU

10 18-Feb-14

01-Mar-14

T+GPSK240

Flexible ducts

16 24-Feb-14

13-Mar-14

T+GPSK260

Cable Termination

14 27-Feb-14

15-Mar-14

T+GPSK200

CHW Pipe pressure Testing

4 02-Mar-14

05-Mar-14

T+GPSK210

CHW Pipe Insulation

6 05-Mar-14

11-Mar-14

171 16-Nov-13
171 16-Nov-13
6 16-Nov-13

04-Jun-14
04-Jun-14
21-Nov-13

T+GPSK290

Floor Drains

5 23-Mar-14

27-Mar-14

T+GPSK320

Light Fittings

6 21-May-14

27-May-14

T+GPSK310

Grilles and Diffusers

6 21-May-14

27-May-14

T+GPSK300

Wiring Accessories

6 21-May-14

27-May-14

T+GPSK330

ELV Devices

8 27-May-14

04-Jun-14

90 16-Nov-13

02-Mar-14

90
90
90
12

02-Mar-14
02-Mar-14
02-Mar-14
28-Nov-13

General
Finishes
No DISP
T+1GE100

Masonry

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13*

T+1GE490

Gypsum & cement plaster

T+1GE200

Install metal frames & doors

T+1GE210

Painting

6 15-Dec-13

21-Dec-13

6 06-Feb-14

12-Feb-14

18 10-Feb-14

02-Mar-14
31-Dec-13
31-Dec-13

Access from Structure

27 30-Nov-13
27 30-Nov-13
0 30-Nov-13

T+1GE300

Drainage Riser

10 01-Dec-13

12-Dec-13

T+1GE310

Rain Water Riser

8 05-Dec-13

14-Dec-13

T+1GE320

CD Pipe Riser

8 05-Dec-13

14-Dec-13

T+1GE330

Water Supply Risers

12 08-Dec-13

21-Dec-13

T+1GE340

Electrical Risers

12 10-Dec-13

23-Dec-13

T+1GE350

LPG Riser

6 10-Dec-13

16-Dec-13

T+1GE360

Ducting Risers

14 11-Dec-13

26-Dec-13

T+1GE370

FP Pipe Riser

10 11-Dec-13

22-Dec-13

T+1GE380

CHW Pipe Supply/Return riser

14 16-Dec-13

31-Dec-13

54 30-Nov-13

02-Feb-14

MEP Risers
No DISP
T+1GE290

General
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

20-May-14

Cable Tray and Trunking

+01 @ +16.00

Revised Programme Rev. D

20-May-14

T+GPSK190

Sprinkler installation

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
13-May-14

T+GPSK130

MEP Finishes
No DISP
T+GPSK270

Four Seasons Hotel Bahrain

Page 16 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

No DISP
T+1GE400

Elect embeds in masonry

54 30-Nov-13
6 30-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
02-Feb-14
07-Dec-13

T+1GE120

Plumbing & FP distr, tests

24 22-Dec-13

19-Jan-14

T+1GE130

HVAC Duct, pipes distr, FCU & tests

24 22-Dec-13

19-Jan-14

T+1GE140

Electrical distribution LV&LC

24 22-Dec-13

19-Jan-14

T+1GE170

Pb&FF equip (sprinkler heads...)

12 20-Jan-14

02-Feb-14

T+1GE180

HVAC Grilles & diffusers...

12 20-Jan-14

02-Feb-14

T+1GE190

Electr equip, lighting fixt....

12 20-Jan-14

02-Feb-14

192 16-Nov-13

29-Jun-14

192
72
72
36

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

29-Jun-14
09-Feb-14
09-Feb-14
28-Dec-13

Activity ID

Activity Name

+02 @ +24.85
General
Civil Works
No DISP
T+2CCT110

Install Cable net glazing

Duration Start

T+2CCT120

Porte cochere standing seam roof

36 30-Nov-13

12-Jan-14

T+2CCT130

Sub structure for Metal ceiling

24 13-Jan-14

09-Feb-14

166 30-Nov-13
166 30-Nov-13
12 30-Nov-13

12-Jun-14
12-Jun-14
14-Dec-13

Finishes
No DISP
T+2GE100

Masonry to risers

T+2GE650

Screed

12 15-Dec-13

28-Dec-13

T+2GE640

Gypsum walls

24 29-Dec-13

26-Jan-14

T+2GE210

Gypsum False ceiling

24 22-Feb-14

20-Mar-14

T+2GE190

Wall coverings

18 22-Mar-14

10-Apr-14

T+2GE250

Install frames & doors

6 12-Apr-14

17-Apr-14

T+2GE660

Millwork

30 12-Apr-14

15-May-14

T+2GE260

Painting

18 17-May-14

05-Jun-14

T+2GE200

Carpet

6 07-Jun-14

12-Jun-14
22-Jan-14
22-Jan-14

Access from Structure

21 29-Dec-13
21 29-Dec-13
0 29-Dec-13

T+2GE350

Drainage Riser

10 30-Dec-13

11-Jan-14

T+2GE360

Rain Water Riser

8 04-Jan-14

12-Jan-14

T+2GE370

CD Pipe Riser

8 04-Jan-14

12-Jan-14

T+2GE380

Water Supply Risers

8 06-Jan-14

14-Jan-14

T+2GE390

Electrical Risers

8 08-Jan-14

16-Jan-14

T+2GE400

LPG Riser

8 08-Jan-14

16-Jan-14

T+2GE410

Ducting Risers

8 09-Jan-14

18-Jan-14

T+2GE420

FP Pipe Riser

10 09-Jan-14

20-Jan-14

T+2GE430

CHW Pipe Supply/Return riser

8 14-Jan-14

22-Jan-14

40 12-Jan-14
40 12-Jan-14
10 12-Jan-14

26-Feb-14
26-Feb-14
22-Jan-14

MEP Risers
No DISP
T+2GE340

MEP 1st & 2nd Fix


No DISP
T+2GE330
Drainage Piping
T+2GE550

Condensate drain pipe connection

4 13-Jan-14

16-Jan-14

T+2GE450

Duct installation and connections

8 19-Jan-14

27-Jan-14

T+2GE460

CHW piping and valve package installation

10 23-Jan-14

03-Feb-14

T+2GE610

Drainage Pipe testing

3 23-Jan-14

26-Jan-14

T+2GE490

Installation of Dampers & Plenums

8 28-Jan-14

05-Feb-14

T+2GE520

Cable tray & trunking

10 28-Jan-14

08-Feb-14

T+2GE530

Electrical conduiting

8 03-Feb-14

11-Feb-14

T+2GE470

CHW pipe pressure testing

5 04-Feb-14

09-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 17 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+2GE500

FP piping

8 09-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
17-Feb-14

T+2GE480

CHW pipe insulation

8 10-Feb-14

18-Feb-14

T+2GE540

Cable & Wire pulling

6 12-Feb-14

18-Feb-14

T+2GE510

FP pipe pressure testing

3 18-Feb-14

20-Feb-14

T+2GE620

Cable Termination

7 19-Feb-14

26-Feb-14

62 19-Apr-14
62 19-Apr-14
6 19-Apr-14

29-Jun-14
29-Jun-14
24-Apr-14

Activity ID

Activity Name

MEP Final Fix


No DISP
T+2GE560

Sprinkler installation

Duration Start

T+2GE570

Installation of Floor Drains

5 24-Apr-14

29-Apr-14

T+2GE580

Grilles & Diffusers

8 29-Apr-14

07-May-14

T+2GE590

Light Fittings

8 07-Jun-14

15-Jun-14

T+2GE600

ELV Devices

5 12-Jun-14

17-Jun-14

T+2GE630

Clean & Snag

10 18-Jun-14

29-Jun-14

6 15-Dec-13

21-Dec-13

6
6
6
6

15-Dec-13
15-Dec-13
15-Dec-13
15-Dec-13

21-Dec-13
21-Dec-13
21-Dec-13
21-Dec-13

149 22-Dec-13

14-Jun-14

Masonry

149
149
149
6

22-Dec-13
22-Dec-13
22-Dec-13
22-Dec-13

14-Jun-14
14-Jun-14
14-Jun-14
28-Dec-13

T+4GE130

Plumbing & FP distr, tests

100 29-Dec-13

24-Apr-14

T+4GE140

HVAC Duct, pipes distr, FCU & tests

100 29-Dec-13

24-Apr-14

T+4GE150

Electrical distribution LV&LC

100 29-Dec-13

24-Apr-14

T+4GE210

Pb&FF equip (sprinkler heads...)

12 26-Apr-14

08-May-14

T+4GE220

HVAC Grilles & diffusers...

12 26-Apr-14

08-May-14

T+4GE230

Electr equip, lighting fixt....

12 26-Apr-14

08-May-14

T+4GE240

Install metal frames & doors

T+4GE250

Painting

T+4GE260
T+4GE270

+03 @ +27.40
General
Finishes
No DISP
T+2GE110

Masonry

+04 @ +31.20
General
Finishes
No DISP
T+4GE110

6 13-May-14

19-May-14

18 17-May-14

05-Jun-14

Pb&FF tests

6 18-May-14

24-May-14

HVAC tests

6 18-May-14

24-May-14

T+4GE280

Electr tests

6 18-May-14

24-May-14

T+4GE290

Testing & commissioning

6 01-Jun-14

07-Jun-14

T+4GE300

Inspection & snag list

6 08-Jun-14

14-Jun-14

6 29-Dec-13

05-Jan-14

6
6
6
6

29-Dec-13
29-Dec-13
29-Dec-13
29-Dec-13

05-Jan-14
05-Jan-14
05-Jan-14
05-Jan-14

139 06-Jan-14

16-Jun-14

139
117
117
6

06-Jan-14
06-Jan-14
06-Jan-14
06-Jan-14

16-Jun-14
21-May-14
21-May-14
12-Jan-14

+05 @ +35.00
General
Finishes
No DISP
T+4GE320

Masonry

+06 @ +38.8
General
Finishes
No DISP
T+6GE100

Masonry

T+6GE110

Metal doorframes

6 07-Jan-14

13-Jan-14

T+6GE200

Install metal frames & doors

6 15-May-14

21-May-14

133 13-Jan-14

16-Jun-14

General
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 18 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

No DISP
T+6GE120

Plumbing & FP distr, tests

Duration Start

133 13-Jan-14
90 13-Jan-14

HVAC Duct, pipes distr, FCU & tests

90 13-Jan-14

27-Apr-14

T+6GE140

Electrical distribution LV&LC

90 13-Jan-14

27-Apr-14

T+6GE150

Elect embeds in masonry

6 14-Jan-14

20-Jan-14

T+6GE180

HVAC Grilles & diffusers...

12 28-Apr-14

11-May-14

T+6GE190

Electr equip, lighting fixt....

12 28-Apr-14

11-May-14

T+6GE170

Pb&FF equip (sprinkler heads...)

12 28-Apr-14

11-May-14

T+6GE210

Painting

18 19-May-14

08-Jun-14

T+6GE220

Pb&FF tests

6 20-May-14

26-May-14

T+6GE230

HVAC tests

6 20-May-14

26-May-14

T+6GE240

Electr tests

6 20-May-14

26-May-14

T+6GE250

Testing & commissioning

6 03-Jun-14

09-Jun-14

T+6GE260

Inspection & snag list

6 10-Jun-14

16-Jun-14

6 13-Jan-14

19-Jan-14

6
6
6
6

19-Jan-14
19-Jan-14
19-Jan-14
19-Jan-14

General
Finishes
No DISP
T+6GE280

Masonry

+08 @ +46.40
General
Finishes
No DISP
T+8GE100

Masonry

13-Jan-14
13-Jan-14
13-Jan-14
13-Jan-14

139 20-Jan-14

01-Jul-14

139
117
117
6

20-Jan-14
20-Jan-14
20-Jan-14
20-Jan-14

01-Jul-14
04-Jun-14
04-Jun-14
26-Jan-14

T+8GE110

Metal doorframes

6 21-Jan-14

27-Jan-14

T+8GE200

Install metal frames & doors

6 29-May-14

04-Jun-14

133 27-Jan-14
133 27-Jan-14
90 27-Jan-14

01-Jul-14
01-Jul-14
11-May-14

General
No DISP
T+8GE120

Plumbing & FP distr, tests

T+8GE130

HVAC Duct, pipes distr, FCU & tests

90 27-Jan-14

11-May-14

T+8GE140

Electrical distribution LV&LC

90 27-Jan-14

11-May-14

T+8GE150

Elect embeds in masonry

6 28-Jan-14

03-Feb-14

T+8GE170

Pb&FF equip (sprinkler heads...)

12 12-May-14

25-May-14

T+8GE180

HVAC Grilles & diffusers...

12 12-May-14

25-May-14

T+8GE190

Electr equip, lighting fixt....

12 12-May-14

25-May-14

T+8GE210

Painting

18 02-Jun-14

22-Jun-14

T+8GE220

Pb&FF tests

6 03-Jun-14

09-Jun-14

T+8GE230

HVAC tests

6 03-Jun-14

09-Jun-14

T+8GE240

Electr tests

6 03-Jun-14

09-Jun-14

T+8GE250

Testing & commissioning

6 17-Jun-14

23-Jun-14

T+8GE260

Inspection & snag list

6 24-Jun-14

01-Jul-14

6 27-Jan-14

02-Feb-14

6
6
6
6

27-Jan-14
27-Jan-14
27-Jan-14
27-Jan-14

02-Feb-14
02-Feb-14
02-Feb-14
02-Feb-14

115 03-Feb-14

16-Jun-14

72 03-Feb-14
72 03-Feb-14

27-Apr-14
27-Apr-14

+09 @ +50.20
General
Finishes
No DISP
T+9GE280

Masonry

+10 @ +54.00
General
Finishes
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 19 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
16-Jun-14
27-Apr-14

T+6GE130

+07 @ +42.60

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

Masonry

72 03-Feb-14
6 03-Feb-14

T+10GE210

Painting

6 21-Apr-14

27-Apr-14

T+10GE200

Install metal frames & doors

6 21-Apr-14

27-Apr-14
12-Mar-14
12-Mar-14

Access from Structure

27 10-Feb-14
27 10-Feb-14
0 10-Feb-14

T+10GE300

Drainage Riser

10 11-Feb-14

22-Feb-14

T+10GE310

Rain Water Riser

8 15-Feb-14

23-Feb-14

T+10GE320

CD Pipe Riser

8 15-Feb-14

23-Feb-14

T+10GE330

Water Supply Risers

12 17-Feb-14

02-Mar-14

T+10GE340

Electrical Risers

12 19-Feb-14

04-Mar-14

T+10GE360

Ducting Risers

14 20-Feb-14

08-Mar-14

T+10GE370

FP Pipe Riser

10 20-Feb-14

03-Mar-14

T+10GE380

CHW Pipe Supply/Return riser

14 25-Feb-14

12-Mar-14
27-Apr-14
27-Apr-14
06-Apr-14

Plumbing & FP distr, tests

66 10-Feb-14
66 10-Feb-14
48 10-Feb-14

T+10GE130

HVAC Duct, pipes distr, FCU & tests

48 10-Feb-14

06-Apr-14

T+10GE140

Electrical distribution LV&LC

48 10-Feb-14

06-Apr-14

T+10GE150

Elect embeds in masonry

6 10-Feb-14

16-Feb-14

T+10GE170

Pb&FF equip (sprinkler heads...)

12 07-Apr-14

20-Apr-14

T+10GE180

HVAC Grilles & diffusers...

12 07-Apr-14

20-Apr-14

T+10GE190

Electr equip, lighting fixt....

12 07-Apr-14

20-Apr-14

T+10GE260

Inspection & snag list

6 21-Apr-14

27-Apr-14

General
No DISP
T+10GE120

Mechanical Plantroom
Civil Works
No DISP
T+10MP110
Concrete Plinths

115
91
91
4

03-Feb-14
03-Feb-14
03-Feb-14
03-Feb-14

16-Jun-14
19-May-14
19-May-14
06-Feb-14

T+10MP640

RMX01 to plinths

3 24-Feb-14

26-Feb-14

T+10MP120

Metal door with frames

2 18-May-14

19-May-14

91 08-Feb-14
91 08-Feb-14
9 08-Feb-14

24-May-14
24-May-14
17-Feb-14

Finishes
No DISP
T+10MP140
T+10MP200

Painting on walls first coat


Painting on walls & floor

6 18-May-14

24-May-14
29-Mar-14
29-Mar-14

Access from Structure

41 10-Feb-14
41 10-Feb-14
0 10-Feb-14

T+10MP230

Drainage Riser

10 11-Feb-14

22-Feb-14

T+10MP240

Rain Water Riser

8 15-Feb-14

23-Feb-14

T+10MP260

Water Supply Risers

12 17-Feb-14

02-Mar-14

T+10MP280

LPG Riser

18 19-Feb-14

11-Mar-14

T+10MP290

Ducting Risers

14 20-Feb-14

08-Mar-14

T+10MP250

CD Pipe Riser

8 24-Feb-14

04-Mar-14

T+10MP300

FP Pipe Riser

10 04-Mar-14

15-Mar-14

T+10MP270

Electrical Risers

12 05-Mar-14

18-Mar-14

T+10MP310

CHW Pipe Supply/Return riser

14 13-Mar-14

29-Mar-14

85 08-Feb-14
85 08-Feb-14

17-May-14
17-May-14

MEP Risers
No DISP
T+10MP220

MEP 1st & 2nd Fix


No DISP
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 20 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
27-Apr-14
09-Feb-14

No DISP
T+10GE100

MEP Risers
No DISP
T+10GE290

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

14 08-Feb-14

DHW Storage tanks Installation

T+10MP610

Installation of Potable Water Tanks

8 13-Feb-14

22-Feb-14

T+10MP320

Drainage Piping

10 23-Feb-14

05-Mar-14

T+10MP370

FCU Installation

14 23-Feb-14

10-Mar-14

T+10MP360

Installation of Booster Pumps

12 24-Feb-14

09-Mar-14

T+10MP350

Installation of HEX

16 24-Feb-14

13-Mar-14

T+10MP620

Installation of DHW circulating Pumps

8 04-Mar-14

12-Mar-14

T+10MP340

Drainage Pipe Testing

T+10MP430

Duct connection to FCU

T+10MP460

Condensate Drain Pipe connection

T+10MP440

6 06-Mar-14

12-Mar-14

18 11-Mar-14

31-Mar-14

8 11-Mar-14

19-Mar-14

HTW Pipe and valve connections to HEX

21 15-Mar-14

07-Apr-14

T+10MP380

MCC Panels and Switches

21 15-Mar-14

07-Apr-14

T+10MP410

Installation & connection to Pumps

18 15-Mar-14

03-Apr-14

T+10MP390

FP Piping

14 16-Mar-14

31-Mar-14

T+10MP400

Cable Tray & Trunking

21 20-Mar-14

13-Apr-14

T+10MP420

Electrical Containment

18 26-Mar-14

15-Apr-14

T+10MP450

CHW Pipe and valve connections to FCU

18 30-Mar-14

19-Apr-14

T+10MP510

Installation of Dampers and Plenums

12 01-Apr-14

14-Apr-14

T+10MP480

FP Pipe pressure Testing

6 01-Apr-14

07-Apr-14

T+10MP470

Water Supply pipe pressure Testing

8 08-Apr-14

16-Apr-14

T+10MP490

Water Supply Pipe insulation

16 13-Apr-14

30-Apr-14

T+10MP500

Cable & Wire Pulling

21 16-Apr-14

10-May-14

T+10MP520

CHW Pipe Pressure Testing

8 20-Apr-14

28-Apr-14

T+10MP530

CHW Pipe insulation

18 20-Apr-14

10-May-14

T+10MP550

Cable Termination

18 27-Apr-14

17-May-14
16-Jun-14
16-Jun-14
01-Jun-14

Sprinkler Installation

21 24-May-14
21 24-May-14
8 24-May-14

T+10MP560

Light fittings

10 25-May-14

04-Jun-14

T+10MP570

Installation of Floor Drains

4 27-May-14

31-May-14

T+10MP580

FA & SD Devices

8 31-May-14

08-Jun-14

T+10MP600

Grilles & Louvres

+11 @ +59.00
West Core
Electrical/Telecom Room
Finishes
T+11WR26870 RMX - 01 to floor
T+11WR26880 RMX-01 to floor

14 01-Jun-14

16-Jun-14

196 03-Oct-13 A

27-May-14

160
29
9
3

15-Apr-14
04-Jan-14
04-Jan-14
26-Dec-13

03-Oct-13 A
30-Nov-13
24-Dec-13
24-Dec-13

3 31-Dec-13

04-Jan-14

20 30-Nov-13
3 30-Nov-13*

23-Dec-13
03-Dec-13

T+11WR26780 Busbar installation & connection

2 04-Dec-13

05-Dec-13

T+11WR26820 Install IT Panels

2 04-Dec-13

05-Dec-13

T+11WR26830 Install Security Panels

2 04-Dec-13

05-Dec-13

T+11WR26790 Duckwork branch to room

2 07-Dec-13

08-Dec-13

T+11WR26800 Fire alarm cabling

3 09-Dec-13

11-Dec-13

T+11WR26810 Cable terminations

10 12-Dec-13

23-Dec-13

6 24-Dec-13
2 24-Dec-13

30-Dec-13
25-Dec-13

2 26-Dec-13

28-Dec-13

1st & 2nd Fix


T+11WR26770 Electrical Containment

MEP Final Fix


T+11WR26840 Grills & diffusers
T+11WR26850 Fire alarm devices
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 21 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
23-Feb-14

T+10MP330

MEP Final Fix


No DISP
T+10MP590

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+11WR26860 Light fittings

Duration Start

2 29-Dec-13

05-Jan-14
05-Jan-14
17-Nov-13

18 15-Dec-13

05-Jan-14

MEP riser summary


No DISP
T+11WR26080 MEP risers & 1st fix

18 03-Oct-13 A
18 03-Oct-13 A
18 03-Oct-13 A

20-Nov-13
20-Nov-13
20-Nov-13

MEP Risers & First Fix


No DISP
T+11WR26130 DCW / DHW & CCW riser

56 03-Oct-13 A
56 03-Oct-13 A
18 21-Oct-13 A

14-Dec-13
14-Dec-13
01-Dec-13

T+11WR26140 Sanitary riser

18 21-Oct-13 A

04-Dec-13

T+11WR26160 Ductwork - supply, make-up air & extract

18 06-Oct-13 A

19-Nov-13

T+11WR26170 CW supply / return & condensate

18 09-Oct-13 A

17-Nov-13

T+11WR26190 FCU connections

18 16-Nov-13

07-Dec-13

T+11WR26180 Plumbing & san distribution

18 16-Nov-13

07-Dec-13

T+11WR26110 Ductworks risers

18 03-Oct-13 A

19-Nov-13

T+11WR26120 Chilled water & condensate

18 10-Oct-13 A

19-Nov-13

T+11WR26210 Sprinkler pipes ( Not drops ) from corridor

18 20-Nov-13

11-Dec-13

T+11WR26200 Cable tray / trunking

18 20-Nov-13

11-Dec-13

T+11WR26220 Test risers ( 3floors vertically )

18 23-Nov-13

14-Dec-13

T+11WR26070 Close blockwork risers

T+11WR26230 MEP sign off risers (Start)

24-Mar-14
24-Mar-14
18-Dec-13

T+11WR26250 Insulate & board walls

18 05-Jan-14*

25-Jan-14

T+11WR26260 Ceiling 1st fix

18 09-Jan-14

29-Jan-14

T+11WR26270 Wiring

18 14-Jan-14

03-Feb-14

T+11WR26280 MEP drops in ceiling

18 18-Jan-14

06-Feb-14

T+11WR26290 Board ceiling

18 19-Jan-14

08-Feb-14

T+11WR26300 Tape & Joint walls & ceiling

18 23-Jan-14

12-Feb-14

T+11WR26310 Mist coat all dry lining

18 28-Jan-14

17-Feb-14

T+11WR26320 Install cornice

18 30-Jan-14

19-Feb-14

T+11WR26330 Paint ceiling and cornice

18 04-Feb-14

24-Feb-14

T+11WR26340 Wall covering

18 09-Feb-14

01-Mar-14

T+11WR26350 Install furniture

18 13-Feb-14

05-Mar-14

T+11WR26360 MEP terminations in furniture

18 18-Feb-14

10-Mar-14

T+11WR26370 MEP 3rd fix- sockets, cover plates etc

18 25-Feb-14

17-Mar-14

T+11WR26760 Underlay & Carpet

6 18-Mar-14

24-Mar-14

Bathroom
No DISP
T+11WR26380 Stud to block walls

74 22-Dec-13
74 22-Dec-13
18 22-Dec-13

18-Mar-14
18-Mar-14
12-Jan-14

T+11WR26390 Waterproof bathroom

18 24-Dec-13

14-Jan-14

T+11WR26400 Flood test

18 31-Dec-13

21-Jan-14

T+11WR26410 MEP Drops in walls & back boxes

18 11-Jan-14

30-Jan-14

T+11WR26420 Install bath

18 11-Jan-14

30-Jan-14

T+11WR26430 Insulate & board walls

18 13-Jan-14

02-Feb-14

T+11WR26440 Framing & board for bath

18 13-Jan-14

02-Feb-14

T+11WR26450 First fix ceiling

18 15-Jan-14

04-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 22 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

14-Dec-13

99 27-Nov-13
99 27-Nov-13
18 27-Nov-13

Bedroom
No DISP
T+11WR26240 MEP Drops in walls & back boxes

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
30-Dec-13

74 03-Oct-13 A
74 03-Oct-13 A
18 03-Oct-13 A

Finishes - 1st Fix


No DISP
T+11WR26060 Studwork incl noggins

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+11WR26460 MEP drops in ceiling

18 18-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
06-Feb-14

T+11WR26470 2nd fix ceiling incl access panel

18 19-Jan-14

08-Feb-14

T+11WR26480 Install corniche

18 21-Jan-14

10-Feb-14

T+11WR26490 Stone to floors

15 30-Jan-14*

16-Feb-14

T+11WR26500 Stone surround to bath

15 30-Jan-14

16-Feb-14

T+11WR26510 Stone vanity

15 30-Jan-14

16-Feb-14

T+11WR26520 Stone to walls incl niche

15 30-Jan-14

16-Feb-14

T+11WR26530 Casing stone

15 30-Jan-14

16-Feb-14

T+11WR26540 Grout to all stone

15 30-Jan-14

16-Feb-14

T+11WR26550 Glass Partition

18 17-Feb-14

09-Mar-14

T+11WR26560 Install and connect " Free issue " mirror

18 18-Feb-14

10-Mar-14

T+11WR26570 Sanitary ware and accessories

18 20-Feb-14

12-Mar-14

T+11WR26580 MEP connections to bath and basin

18 22-Feb-14

13-Mar-14

T+11WR26590 MEP 3rd fix - switch / socket covers

18 24-Feb-14

16-Mar-14

T+11WR26600 Hang glass doors

18 26-Feb-14

18-Mar-14

Entrance Vestibule & dressing


No DISP
T+11WR26610 MEP drops in walls

37 25-Jan-14
37 25-Jan-14
12 25-Jan-14

08-Mar-14
08-Mar-14
06-Feb-14

T+11WR26620 Board walls

12 28-Jan-14

10-Feb-14

T+11WR26630 Ceiling 1st fix

12 30-Jan-14

12-Feb-14

T+11WR26640 MEP drops in ceiling

12 02-Feb-14

15-Feb-14

T+11WR26650 Board ceiling incl access panel

12 05-Feb-14

18-Feb-14

T+11WR26670 Tape & joint walls & ceilings

12 08-Feb-14

20-Feb-14

T+11WR26680 Mist coat dry lining

12 09-Feb-14

22-Feb-14

T+11WR26700 Stone flooring incl grout

12 10-Feb-14

23-Feb-14

T+11WR26690 Paint ceiling

12 11-Feb-14

24-Feb-14

T+11WR26710 Pocket door to bathroom

12 16-Feb-14

01-Mar-14

T+11WR26720 Entrance door - Temporary

12 16-Feb-14

01-Mar-14

T+11WR26730 Install wardrobe

12 17-Feb-14

02-Mar-14

T+11WR26740 Wall Coverings

12 19-Feb-14

04-Mar-14

T+11WR26750 3rd fix MEP

12 23-Feb-14

08-Mar-14

24 19-Mar-14
24 19-Mar-14
3 19-Mar-14

15-Apr-14
15-Apr-14
22-Mar-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+11GR620
Installation of Flexibles / Plenum
W+11GR640

Sprinkler Drops

Duration Start

3 19-Mar-14

22-Mar-14

W+11GR17360 Gypsum Ceilings

6 23-Mar-14

29-Mar-14

W+11GR17400 Paint Ceiling

4 30-Mar-14

02-Apr-14

W+11GR17390 Millwork

6 03-Apr-14

09-Apr-14

W+11GR17380 Wall Covering & fabric panels

4 06-Apr-14

09-Apr-14

W+11GR660

Light Fittings Installation

2 10-Apr-14

12-Apr-14

W+11GR670

Sprinkler Installation

2 10-Apr-14

12-Apr-14

3 13-Apr-14

15-Apr-14

W+11GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+11ER26060 Studwork incl noggins
T+11ER26070

Close blockwork risers

MEP riser summary

189
74
74
18

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

18 15-Dec-13

05-Jan-14

18 03-Oct-13 A

20-Nov-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

19-May-14
05-Jan-14
05-Jan-14
20-Nov-13

Page 23 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

No DISP
T+11ER26080

MEP risers & 1st fix

MEP Risers & First Fix


No DISP
T+11ER26130 DCW / DHW & CCW riser

16-Dec-13
16-Dec-13
23-Nov-13

18 21-Oct-13 A

04-Dec-13

Ductwork - supply, make-up air & extract

18 06-Oct-13 A

19-Nov-13

T+11ER26170

CW supply / return & condensate

18 16-Nov-13

07-Dec-13

T+11ER26180

Plumbing & san distribution

18 16-Nov-13

07-Dec-13

T+11ER26190

FCU connections

18 20-Nov-13

11-Dec-13

T+11ER26200

Cable tray / trunking

18 20-Nov-13

11-Dec-13

T+11ER26220

Test risers ( 3floors vertically )

18 23-Nov-13

14-Dec-13

T+11ER26210

Sprinkler pipes ( Not drops ) from corridor

18 25-Nov-13

16-Dec-13

T+11ER26230

MEP sign off risers (Start)

0
147 27-Nov-13
147 27-Nov-13
18 27-Nov-13

14-Dec-13
19-May-14
19-May-14
18-Dec-13

T+11ER26250

Insulate & board walls

6 16-Mar-14*

22-Mar-14

T+11ER26260

Ceiling 1st fix

6 20-Mar-14

26-Mar-14

T+11ER26270

Wiring

6 25-Mar-14

31-Mar-14

T+11ER26280

MEP drops in ceiling

6 29-Mar-14

03-Apr-14

T+11ER26290

Board ceiling

6 30-Mar-14

05-Apr-14

T+11ER26300

Tape & Joint walls & ceiling

6 03-Apr-14

09-Apr-14

T+11ER26310

Mist coat all dry lining

6 08-Apr-14

14-Apr-14

T+11ER26320

Install cornice

6 10-Apr-14

16-Apr-14

T+11ER26330

Paint ceiling and cornice

6 15-Apr-14

21-Apr-14

T+11ER26340

Wall covering

6 20-Apr-14

26-Apr-14

T+11ER26350

Install furniture

6 24-Apr-14

30-Apr-14

T+11ER26360

MEP terminations in furniture

6 29-Apr-14

05-May-14

T+11ER26370

MEP 3rd fix- sockets, cover plates etc

6 06-May-14

12-May-14

T+11ER26980

Underlay & Carpet

6 13-May-14

19-May-14

Stud to block walls

77 25-Dec-13
77 25-Dec-13
18 25-Dec-13

25-Mar-14
25-Mar-14
15-Jan-14

T+11ER26390

Waterproof bathroom

18 28-Dec-13

18-Jan-14

T+11ER26400

Flood test

18 05-Jan-14

25-Jan-14

T+11ER26410

MEP Drops in walls & back boxes

18 12-Jan-14

01-Feb-14

T+11ER26420

Install bath

18 14-Jan-14

03-Feb-14

T+11ER26430

Insulate & board walls

18 16-Jan-14

05-Feb-14

T+11ER26440

Framing & board for bath

18 16-Jan-14

05-Feb-14

T+11ER26450

First fix ceiling

18 19-Jan-14

08-Feb-14

T+11ER26460

MEP drops in ceiling

18 21-Jan-14

10-Feb-14

T+11ER26470

2nd fix ceiling incl access panel

18 28-Jan-14

17-Feb-14

T+11ER26480

Install corniche

18 30-Jan-14

19-Feb-14

T+11ER26490

Stone to floors

15 06-Feb-14

23-Feb-14

T+11ER26500

Stone surround to bath

15 06-Feb-14

23-Feb-14

T+11ER26510

Stone vanity

15 06-Feb-14

23-Feb-14

T+11ER26520

Stone to walls incl niche

15 06-Feb-14

23-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

46 06-Oct-13 A
46 06-Oct-13 A
18 21-Oct-13 A

Sanitary riser

Bathroom
No DISP
T+11ER26380

Revised Programme Rev. D

18 03-Oct-13 A
18 03-Oct-13 A

T+11ER26160

MEP Drops in walls & back boxes

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
20-Nov-13
20-Nov-13

Duration Start

T+11ER26140

Bedroom
No DISP
T+11ER26240

Four Seasons Hotel Bahrain

Page 24 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+11ER26530

Casing stone

15 06-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
23-Feb-14

T+11ER26540

Grout to all stone

15 06-Feb-14

23-Feb-14

T+11ER26550

Glass Partition

18 24-Feb-14

16-Mar-14

T+11ER26560

Install and connect " Free issue " mirror

18 25-Feb-14

17-Mar-14

T+11ER26570

Sanitary ware and accessories

18 27-Feb-14

19-Mar-14

T+11ER26580

MEP connections to bath and basin

18 01-Mar-14

20-Mar-14

T+11ER26590

MEP 3rd fix - switch / socket covers

18 03-Mar-14

23-Mar-14

T+11ER26600

Hang glass doors

18 05-Mar-14

25-Mar-14

54 19-Jan-14
54 19-Jan-14
18 19-Jan-14

22-Mar-14
22-Mar-14
08-Feb-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+11ER26610 MEP drops in walls

Duration Start

T+11ER26620

Board walls

18 22-Jan-14

11-Feb-14

T+11ER26630

Ceiling 1st fix

18 25-Jan-14

13-Feb-14

T+11ER26640

MEP drops in ceiling

18 27-Jan-14

16-Feb-14

T+11ER26650

Board ceiling incl access panel

18 30-Jan-14

19-Feb-14

T+11ER26670

Tape & joint walls & ceilings

18 02-Feb-14

22-Feb-14

T+11ER26680

Mist coat dry lining

18 03-Feb-14

23-Feb-14

T+11ER26690

Paint ceiling

18 05-Feb-14

25-Feb-14

T+11ER26700

Stone flooring incl grout

18 17-Feb-14

09-Mar-14

T+11ER26710

Pocket door to bathroom

18 23-Feb-14

15-Mar-14

T+11ER26720

Entrance door - Temporary

18 23-Feb-14

15-Mar-14

T+11ER26730

Install wardrobe

18 24-Feb-14

16-Mar-14

T+11ER26740

Wall Coverings

18 26-Feb-14

18-Mar-14

T+11ER26750

3rd fix MEP

18 02-Mar-14

22-Mar-14

131 16-Nov-13
131 16-Nov-13
3 16-Nov-13

19-Apr-14
19-Apr-14
18-Nov-13

Pier Corridors & Lift Lobby


No DISP
E+11GR640
Sprinkler Drops
E+11GR620

3 23-Mar-14

25-Mar-14

E+11GR17360 Gypsum Ceilings

Installation of Flexibles / Plenum

6 26-Mar-14

01-Apr-14

E+11GR17400 Paint Ceiling

4 02-Apr-14

06-Apr-14

E+11GR17390 Millwork

6 07-Apr-14

13-Apr-14

E+11GR17380 Wall Covering & fabric panels

4 09-Apr-14

13-Apr-14

E+11GR660

Light Fittings Installation

2 14-Apr-14

15-Apr-14

E+11GR670

Sprinkler Installation

2 14-Apr-14

15-Apr-14

3 16-Apr-14

19-Apr-14

E+11GR17410 Underlay & Carpet


East Core - South - JAP Storage
Bedroom
No DISP
T+11ER26760 Studwork incl noggins

68
68
68
6

10-Mar-14
10-Mar-14
10-Mar-14
10-Mar-14

27-May-14
27-May-14
27-May-14
16-Mar-14

T+11ER26840

MEP Drops in walls & back boxes

4 17-Mar-14

20-Mar-14

T+11ER26850

Insulate & board walls

6 22-Mar-14

27-Mar-14

T+11ER26860

Ceiling 1st fix

6 26-Mar-14

01-Apr-14

T+11ER26870

Wiring

4 31-Mar-14

03-Apr-14

T+11ER26880

MEP drops in ceiling

4 03-Apr-14

07-Apr-14

T+11ER26890

Board ceiling

4 05-Apr-14

08-Apr-14

T+11ER26900

Tape & Joint walls & ceiling

4 09-Apr-14

13-Apr-14

T+11ER26910

Mist coat all dry lining

2 14-Apr-14

15-Apr-14

T+11ER26920

Install cornice

4 16-Apr-14

20-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 25 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+11ER26930

Paint ceiling and cornice

4 21-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
24-Apr-14

T+11ER26940

Wall covering

3 26-Apr-14

28-Apr-14

T+11ER26950

Install furniture

6 30-Apr-14

06-May-14

T+11ER26960

MEP terminations in furniture

T+11ER26970

MEP 3rd fix- sockets, cover plates etc

T+11ER26990

Underlay & Carpet

Activity ID

Activity Name

Guestrooms
Bedroom
No DISP
T+11GU1280

Install cornice

Duration Start

4 05-May-14

08-May-14

12 12-May-14

25-May-14

2 26-May-14

27-May-14

114
84
84
6

10-Oct-13 A
22-Oct-13 A
22-Oct-13 A
16-Nov-13

27-Feb-14
26-Jan-14
26-Jan-14
21-Nov-13

T+11GU1310

Install furniture

12 16-Nov-13

28-Nov-13

T+11GU1330

Wall covering

12 22-Oct-13 A

27-Nov-13

T+11GU1320

MEP terminations in furniture

12 20-Nov-13

04-Dec-13

T+11GU1350

MEP 3rd fix- sockets, cover plates etc

12 24-Nov-13

08-Dec-13

T+11GU17310

Underlay & Carpet

12 13-Jan-14*

26-Jan-14
30-Jan-14
30-Jan-14
21-Nov-13

Install cornice

90 10-Oct-13 A
90 10-Oct-13 A
6 16-Nov-13

T+11GU17320

Vanity S/S & mirrors

12 20-Oct-13 A

25-Nov-13

T+11GU1780

Sanitary ware and accessories

12 18-Nov-13

01-Dec-13

T+11GU1540

MEP connections to bath and basin

12 19-Nov-13

03-Dec-13

T+11GU1560

Hang glass doors

12 20-Nov-13

04-Dec-13

T+11GU1550

MEP 3rd fix - switch / socket covers

12 21-Nov-13

05-Dec-13

T+11GU17330

Vanity unit

12 10-Oct-13 A

24-Nov-13

T+11GU1510

Glass Partition

12 10-Oct-13 A

26-Nov-13

T+11GU17340

Wallcovering

12 26-Nov-13

10-Dec-13

T+11GU1530

Install and connect " Free issue " mirror

12 18-Jan-14*

30-Jan-14

66 10-Oct-13 A
66 10-Oct-13 A
12 16-Nov-13

12-Jan-14
12-Jan-14
28-Nov-13

Bathroom
No DISP
T+11GU17130

Entrance Vestibule & dressing


No DISP
T+11GU1640
Mist coat dry lining
T+11GU1660

Paint ceiling

12 18-Nov-13

01-Dec-13

T+11GU1720

Wall Coverings

12 30-Nov-13

14-Dec-13

T+11GU1710

Install wardrobe

12 10-Oct-13 A

07-Dec-13

T+11GU1700

Mirrors

12 08-Dec-13

21-Dec-13

T+11GU1730

3rd fix MEP

12 15-Dec-13

28-Dec-13

T+11GU1690

Pocket door to bathroom

12 29-Dec-13

12-Jan-14

Sprinkler Drops

88 16-Nov-13 A
88 16-Nov-13 A
12 16-Nov-13

27-Feb-14
27-Feb-14
28-Nov-13

T+11GU17360

Gypsum Ceilings

12 16-Nov-13

28-Nov-13

T+11GU17370

T & J Walls & Ceilings

12 30-Nov-13

14-Dec-13

T+11GU17400

Paint Ceiling

12 15-Dec-13

28-Dec-13

T+11GU17390

Millwork

12 29-Dec-13

12-Jan-14

T+11GU620

Installation of Flexibles / Plenum

12 30-Dec-13 A

13-Jan-14

T+11GU17380

Wall Covering

12 13-Jan-14

26-Jan-14

T+11GU17420

Mirrors

12 13-Jan-14

26-Jan-14

T+11GU680

Grilles / Diffuser Installation

12 14-Jan-14

27-Jan-14

T+11GU660

Light Fittings Installation

12 27-Jan-14

09-Feb-14

T+11GU670

Sprinkler Installation

12 28-Jan-14

10-Feb-14

Corridor
No DISP
T+11GU640

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 26 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+11GU690

FA / SD installation

T+11GU17410

Underlay & Carpet

+12 @ +62.80
West Core
Electrical/Telecom Room
Finishes
T+12WR26870 RMX - 01 to floor
T+12WR26880 Permanent door

12 15-Feb-14

27-Feb-14

206 03-Oct-13 A

08-Jun-14

149
29
3
3

16-Apr-14
07-Jan-14
07-Jan-14
07-Jan-14

10-Oct-13 A
04-Dec-13
05-Jan-14
05-Jan-14

07-Jan-14
26-Dec-13
07-Dec-13

T+12WR26780 Busbar installation & connection

2 08-Dec-13

09-Dec-13

T+12WR26820 Install IT Panels

2 08-Dec-13

09-Dec-13

T+12WR26830 Install Security Panels

2 08-Dec-13

09-Dec-13

T+12WR26790 Duckwork branch to room

2 10-Dec-13

11-Dec-13

T+12WR26800 Fire alarm cabling

3 12-Dec-13

15-Dec-13

T+12WR26810 Cable terminations

10 16-Dec-13

26-Dec-13

6 28-Dec-13
2 28-Dec-13

04-Jan-14
29-Dec-13

2 30-Dec-13

31-Dec-13

T+12WR26850 Fire alarm devices


T+12WR26860 Light fittings
Finishes - 1st Fix
No DISP
T+12WR26060 Studwork incl noggins
T+12WR26070 Close blockwork risers

2 02-Jan-14

04-Jan-14

60 21-Oct-13 A
60 21-Oct-13 A
15 21-Oct-13 A

02-Jan-14
02-Jan-14
24-Nov-13

15 16-Dec-13

02-Jan-14

MEP riser summary


No DISP
T+12WR26080 MEP risers & 1st fix

15 21-Oct-13 A
15 21-Oct-13 A
15 21-Oct-13 A

20-Nov-13
20-Nov-13
20-Nov-13

MEP Risers & First Fix


No DISP
T+12WR26130 DCW / DHW & CCW riser

34 10-Oct-13 A
34 10-Oct-13 A
15 10-Oct-13 A

16-Dec-13
16-Dec-13
30-Nov-13

T+12WR26140 Sanitary riser

15 16-Nov-13

03-Dec-13

T+12WR26150 Hang FCU

15 16-Nov-13

03-Dec-13

T+12WR26160 Ductwork - supply, make-up air & extract

15 16-Nov-13

03-Dec-13

T+12WR26170 CW supply / return & condensate

15 19-Nov-13

07-Dec-13

T+12WR26180 Plumbing & san distribution

15 20-Nov-13

08-Dec-13

T+12WR26190 FCU connections

15 24-Nov-13

11-Dec-13

T+12WR26200 Cable tray / trunking

15 25-Nov-13

12-Dec-13

T+12WR26220 Test risers ( 3floors vertically )

15 27-Nov-13

15-Dec-13

T+12WR26210 Sprinkler pipes ( Not drops ) from corridor

15 28-Nov-13

16-Dec-13

T+12WR26230 MEP sign off risers (Start)

22-Feb-14
22-Feb-14
19-Dec-13

T+12WR26250 Insulate & board walls

15 08-Dec-13

24-Dec-13

T+12WR26260 Ceiling 1st fix

15 12-Dec-13

29-Dec-13

T+12WR26270 Wiring

15 17-Dec-13

04-Jan-14

T+12WR26280 MEP drops in ceiling

15 21-Dec-13

07-Jan-14

T+12WR26290 Board ceiling

15 22-Dec-13

08-Jan-14

T+12WR26300 Tape & Joint walls & ceiling

15 26-Dec-13

13-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

15-Dec-13

69 03-Dec-13
69 03-Dec-13
15 03-Dec-13

Bedroom
No DISP
T+12WR26240 MEP Drops in walls & back boxes

Revised Programme Rev. D

12 01-Feb-14

3 05-Jan-14

MEP Final Fix


T+12WR26840 Grills & diffusers

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
13-Feb-14

Duration Start

20 04-Dec-13
3 04-Dec-13

1st & 2nd Fix


T+12WR26890 Electrical Containment

Four Seasons Hotel Bahrain

Page 27 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+12WR26310 Mist coat all dry lining

15 31-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
18-Jan-14

T+12WR26320 Install cornice

15 04-Jan-14

20-Jan-14

T+12WR26330 Paint ceiling and cornice

15 08-Jan-14

25-Jan-14

T+12WR26340 Wall covering

15 13-Jan-14*

29-Jan-14

T+12WR26350 Install furniture

15 18-Jan-14

03-Feb-14

T+12WR26360 MEP terminations in furniture

15 22-Jan-14

08-Feb-14

T+12WR26370 MEP 3rd fix- sockets, cover plates etc

15 29-Jan-14

15-Feb-14

T+12WR26770 Underlay & Carpet

6 16-Feb-14

22-Feb-14

Bathroom
No DISP
T+12WR26380 Stud to block walls

76 23-Dec-13
76 23-Dec-13
15 23-Dec-13

22-Mar-14
22-Mar-14
09-Jan-14

T+12WR26390 Waterproof bathroom

15 25-Dec-13

12-Jan-14

T+12WR26400 Flood test

15 02-Jan-14

19-Jan-14

T+12WR26410 MEP Drops in walls & back boxes

15 12-Jan-14

28-Jan-14

T+12WR26420 Install bath

15 12-Jan-14

28-Jan-14

T+12WR26430 Insulate & board walls

15 14-Jan-14

30-Jan-14

T+12WR26440 Framing & board for bath

15 14-Jan-14

30-Jan-14

T+12WR26450 First fix ceiling

15 16-Jan-14

02-Feb-14

T+12WR26460 MEP drops in ceiling

15 19-Jan-14

04-Feb-14

T+12WR26470 2nd fix ceiling incl access panel

15 20-Jan-14

05-Feb-14

T+12WR26480 Install corniche

15 22-Jan-14

08-Feb-14

T+12WR26490 Stone to floors

15 06-Feb-14

23-Feb-14

T+12WR26500 Stone surround to bath

15 06-Feb-14

23-Feb-14

T+12WR26510 Stone vanity

15 06-Feb-14

23-Feb-14

T+12WR26520 Stone to walls incl niche

15 06-Feb-14

23-Feb-14

T+12WR26530 Casing stone

15 06-Feb-14

23-Feb-14

T+12WR26540 Grout to all stone

15 06-Feb-14

23-Feb-14

T+12WR26550 Glass Partition

15 24-Feb-14

12-Mar-14

T+12WR26560 Install and connect " Free issue " mirror

15 25-Feb-14

13-Mar-14

T+12WR26570 Sanitary ware and accessories

15 27-Feb-14

16-Mar-14

T+12WR26580 MEP connections to bath and basin

15 01-Mar-14

17-Mar-14

T+12WR26590 MEP 3rd fix - switch / socket covers

15 03-Mar-14

19-Mar-14

T+12WR26600 Hang glass doors

15 05-Mar-14

22-Mar-14

Entrance Vestibule & dressing


No DISP
T+12WR26610 MEP drops in walls

48 19-Jan-14
48 19-Jan-14
12 19-Jan-14

15-Mar-14
15-Mar-14
01-Feb-14

T+12WR26620 Board walls

12 22-Jan-14

04-Feb-14

T+12WR26630 Ceiling 1st fix

12 25-Jan-14

06-Feb-14

T+12WR26640 MEP drops in ceiling

12 27-Jan-14

09-Feb-14

T+12WR26650 Board ceiling incl access panel

12 30-Jan-14

12-Feb-14

T+12WR26670 Tape & joint walls & ceilings

12 02-Feb-14

15-Feb-14

T+12WR26680 Mist coat dry lining

12 03-Feb-14

16-Feb-14

T+12WR26690 Paint ceiling

12 05-Feb-14

18-Feb-14

T+12WR26700 Stone flooring incl grout

12 17-Feb-14

02-Mar-14

T+12WR26710 Pocket door to bathroom

12 23-Feb-14

08-Mar-14

T+12WR26720 Entrance door - Temporary

12 23-Feb-14

08-Mar-14

T+12WR26730 Install wardrobe

12 24-Feb-14

09-Mar-14

T+12WR26740 Wall Coverings

12 26-Feb-14

11-Mar-14

Activity ID

Activity Name

Duration Start

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 28 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+12WR26750 3rd fix MEP


Pier Corridors & Lift Lobby
No DISP
W+12GR620
Installation of Flexibles / Plenum
W+12GR640

Sprinkler Drops

16-Apr-14
16-Apr-14
25-Mar-14
25-Mar-14
01-Apr-14

W+12GR17400 Paint Ceiling

2 02-Apr-14

03-Apr-14

W+12GR17390 Millwork

6 05-Apr-14

10-Apr-14

W+12GR17380 Wall Covering & fabric panels

4 07-Apr-14

10-Apr-14

W+12GR660

Light Fittings Installation

2 12-Apr-14

13-Apr-14

W+12GR670

Sprinkler Installation

2 12-Apr-14

13-Apr-14

3 14-Apr-14

16-Apr-14

169
72
72
20

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

26-Apr-14
02-Jan-14
02-Jan-14
19-Nov-13

T+12ER26060

Studwork incl noggins

15 16-Nov-13

03-Dec-13

T+12ER26070

Close blockwork risers

15 16-Dec-13

02-Jan-14

MEP riser summary


No DISP
T+12ER26080 MEP risers & 1st fix

15 12-Oct-13 A
15 12-Oct-13 A
15 12-Oct-13 A

28-Nov-13
28-Nov-13
28-Nov-13

MEP Risers & First Fix


No DISP
T+12ER26130 DCW / DHW & CCW riser

32 15-Oct-13 A
32 15-Oct-13 A
15 19-Oct-13 A

16-Dec-13
16-Dec-13
25-Nov-13

T+12ER26140

Sanitary riser

15 16-Nov-13

03-Dec-13

T+12ER26150

Hang FCU

15 16-Nov-13

03-Dec-13

T+12ER26160

Ductwork - supply, make-up air & extract

15 16-Nov-13

03-Dec-13

T+12ER26120

Chilled water & condensate

15 15-Oct-13 A

20-Nov-13

T+12ER26170

CW supply / return & condensate

15 19-Nov-13

07-Dec-13

T+12ER26180

Plumbing & san distribution

15 20-Nov-13

08-Dec-13

T+12ER26190

FCU connections

15 24-Nov-13

11-Dec-13

T+12ER26200

Cable tray / trunking

15 25-Nov-13

12-Dec-13

T+12ER26220

Test risers ( 3floors vertically )

15 27-Nov-13

15-Dec-13

T+12ER26210

Sprinkler pipes ( Not drops ) from corridor

15 28-Nov-13

16-Dec-13

T+12ER26230

MEP sign off risers (Start)

MEP Drops in walls & back boxes

15-Dec-13

122 03-Dec-13
122 03-Dec-13
15 03-Dec-13

24-Apr-14
24-Apr-14
19-Dec-13

T+12ER26250

Insulate & board walls

15 08-Dec-13

24-Dec-13

T+12ER26260

Ceiling 1st fix

15 12-Dec-13

29-Dec-13

T+12ER26270

Wiring

15 17-Dec-13

04-Jan-14

T+12ER26280

MEP drops in ceiling

15 21-Dec-13

07-Jan-14

T+12ER26290

Board ceiling

15 22-Dec-13

08-Jan-14

T+12ER26300

Tape & Joint walls & ceiling

15 26-Dec-13

13-Jan-14

T+12ER26310

Mist coat all dry lining

15 31-Dec-13

18-Jan-14

T+12ER26320

Install cornice

15 04-Jan-14

20-Jan-14

T+12ER26330

Paint ceiling and cornice

15 08-Jan-14

25-Jan-14

T+12ER26340

Wall covering

T+12ER26350

Install furniture

6 16-Mar-14*
15 20-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

22 23-Mar-14
22 23-Mar-14
3 23-Mar-14
6 26-Mar-14

Bedroom
No DISP
T+12ER26240

Revised Programme Rev. D

12 02-Mar-14

3 23-Mar-14

East Core
Finishes - 1st Fix
No DISP
T+12ER26010 Blockwork to risers ( 2 sides )

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
15-Mar-14

Duration Start

W+12GR17360 Gypsum Ceilings

W+12GR17410 Underlay & Carpet

Four Seasons Hotel Bahrain

Page 29 of 180

22-Mar-14
06-Apr-14
Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+12ER26360

MEP terminations in furniture

15 25-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-Apr-14

T+12ER26370

MEP 3rd fix- sockets, cover plates etc

15 01-Apr-14

17-Apr-14

T+12ER26760

Underlay & Carpet

6 19-Apr-14

24-Apr-14

Stud to block walls

82 23-Dec-13
82 23-Dec-13
15 23-Dec-13

29-Mar-14
29-Mar-14
09-Jan-14

T+12ER26390

Waterproof bathroom

15 25-Dec-13

12-Jan-14

T+12ER26400

Flood test

15 02-Jan-14

19-Jan-14

T+12ER26410

MEP Drops in walls & back boxes

15 12-Jan-14

28-Jan-14

T+12ER26420

Install bath

15 12-Jan-14

28-Jan-14

T+12ER26430

Insulate & board walls

15 14-Jan-14

30-Jan-14

T+12ER26440

Framing & board for bath

15 14-Jan-14

30-Jan-14

T+12ER26450

First fix ceiling

15 16-Jan-14

02-Feb-14

T+12ER26460

MEP drops in ceiling

15 19-Jan-14

04-Feb-14

T+12ER26470

2nd fix ceiling incl access panel

15 20-Jan-14

05-Feb-14

T+12ER26480

Install corniche

15 22-Jan-14

08-Feb-14

T+12ER26490

Stone to floors

15 13-Feb-14

02-Mar-14

T+12ER26500

Stone surround to bath

15 13-Feb-14

02-Mar-14

T+12ER26510

Stone vanity

15 13-Feb-14

02-Mar-14

T+12ER26520

Stone to walls incl niche

15 13-Feb-14

02-Mar-14

T+12ER26530

Casing stone

15 13-Feb-14

02-Mar-14

T+12ER26540

Grout to all stone

15 13-Feb-14

02-Mar-14

T+12ER26550

Glass Partition

15 03-Mar-14

19-Mar-14

T+12ER26560

Install and connect " Free issue " mirror

15 04-Mar-14

20-Mar-14

T+12ER26570

Sanitary ware and accessories

15 06-Mar-14

23-Mar-14

T+12ER26580

MEP connections to bath and basin

15 08-Mar-14

24-Mar-14

T+12ER26590

MEP 3rd fix - switch / socket covers

15 10-Mar-14

26-Mar-14

T+12ER26600

Hang glass doors

15 12-Mar-14

29-Mar-14

57 19-Jan-14
57 19-Jan-14
15 19-Jan-14

25-Mar-14
25-Mar-14
04-Feb-14

Activity ID

Activity Name

Bathroom
No DISP
T+12ER26380

Entrance Vestibule & dressing


No DISP
T+12ER26610 MEP drops in walls

Duration Start

T+12ER26620

Board walls

15 22-Jan-14

08-Feb-14

T+12ER26630

Ceiling 1st fix

15 25-Jan-14

10-Feb-14

T+12ER26640

MEP drops in ceiling

15 27-Jan-14

12-Feb-14

T+12ER26650

Board ceiling incl access panel

15 30-Jan-14

16-Feb-14

T+12ER26660

Door frames

15 02-Feb-14

18-Feb-14

T+12ER26670

Tape & joint walls & ceilings

15 02-Feb-14

18-Feb-14

T+12ER26680

Mist coat dry lining

15 03-Feb-14

19-Feb-14

T+12ER26690

Paint ceiling

15 05-Feb-14

22-Feb-14

T+12ER26700

Stone flooring incl grout

15 24-Feb-14

12-Mar-14

T+12ER26710

Pocket door to bathroom

15 02-Mar-14

18-Mar-14

T+12ER26720

Entrance door - Temporary

15 02-Mar-14

18-Mar-14

T+12ER26730

Install wardrobe

15 03-Mar-14

19-Mar-14

T+12ER26740

Wall Coverings

15 05-Mar-14

22-Mar-14

T+12ER26750

3rd fix MEP

15 09-Mar-14

25-Mar-14

137 16-Nov-13
137 16-Nov-13
3 16-Nov-13

26-Apr-14
26-Apr-14
18-Nov-13

Pier Corridors & Lift Lobby


No DISP
E+12GR640
Sprinkler Drops

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 30 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

3 30-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
01-Apr-14

E+12GR17360 Gypsum Ceilings

6 02-Apr-14

08-Apr-14

E+12GR17400 Paint Ceiling

4 09-Apr-14

13-Apr-14

E+12GR17390 Millwork

6 14-Apr-14

20-Apr-14

E+12GR17380 Wall Covering & fabric panels

4 16-Apr-14

20-Apr-14

E+12GR660

Light Fittings Installation

2 21-Apr-14

22-Apr-14

E+12GR670

Sprinkler Installation

2 21-Apr-14

22-Apr-14

3 23-Apr-14

26-Apr-14

Activity ID

Activity Name

E+12GR620

Installation of Flexibles / Plenum

E+12GR17410 Underlay & Carpet


Guestrooms
Bedroom
No DISP
T+12GU17530

Paint ceiling and cornice

Duration Start

206
88
88
15

03-Oct-13 A
12-Oct-13 A
12-Oct-13 A
12-Oct-13 A

08-Jun-14
05-Feb-14
05-Feb-14
17-Nov-13

T+12GU17540

Wall covering

15 25-Nov-13

12-Dec-13

T+12GU17550

Install furniture

15 30-Nov-13

17-Dec-13

T+12GU17560

MEP terminations in furniture

15 08-Dec-13

24-Dec-13

T+12GU17570

MEP 3rd fix- sockets, cover plates etc

15 26-Dec-13

13-Jan-14

T+12GU17960

Underlay & Carpet

Bathroom
No DISP
T+12GU17730

Casing stone

15 20-Jan-14

05-Feb-14

105 03-Oct-13 A
105 03-Oct-13 A
15 03-Oct-13 A

10-Feb-14
10-Feb-14
17-Nov-13

T+12GU17750

Glass Partition

15 16-Nov-13

03-Dec-13

T+12GU17740

Grout to all stone

15 14-Oct-13 A

27-Nov-13

T+12GU18100

Vanity S/S & mirrors

15 16-Nov-13

03-Dec-13

T+12GU17800

Hang glass doors

15 20-Nov-13

08-Dec-13

T+12GU18110

Vanity Unit

15 13-Oct-13 A

03-Dec-13

T+12GU18120

Wall covering

15 12-Dec-13

29-Dec-13

T+12GU17770

Sanitary ware and accessories

15 23-Dec-13

09-Jan-14

T+12GU17780

MEP connections to bath and basin

15 24-Dec-13

11-Jan-14

T+12GU17790

MEP 3rd fix - switch / socket covers

15 26-Dec-13

13-Jan-14

T+12GU17760

Install and connect " Free issue " mirror

15 25-Jan-14*

10-Feb-14

143 13-Oct-13 A
143 13-Oct-13 A
15 13-Oct-13 A

12-Apr-14
12-Apr-14
20-Nov-13

Entrance Vestibule & dressing


No DISP
T+12GU17890 Paint ceiling
T+12GU17930

Install wardrobe

15 19-Oct-13 A

23-Nov-13

T+12GU17940

Wall Coverings

15 18-Dec-13

05-Jan-14

T+12GU17950

3rd fix MEP

15 26-Dec-13

13-Jan-14

T+12GU17920

Mirrors

15 29-Dec-13

15-Jan-14

T+12GU17910

Pocket door to bathroom

15 26-Mar-14

12-Apr-14

Sprinkler Drops

97 16-Feb-14
97 16-Feb-14
6 16-Feb-14*

08-Jun-14
08-Jun-14
22-Feb-14

6 16-Feb-14*

22-Feb-14

Corridor
No DISP
T+12GU640
T+12GU17360

Gypsum Ceilings

T+12GU680

Grilles / Diffuser Installation

15 23-Feb-14

11-Mar-14

T+12GU17370

T & J Walls & Ceilings

12 23-Feb-14

08-Mar-14

T+12GU17400

Paint Ceiling

15 09-Mar-14

25-Mar-14

T+12GU17390

Millwork

15 26-Mar-14

12-Apr-14

T+12GU17380

Wall Covering

15 13-Apr-14

29-Apr-14

T+12GU17420

Mirrors

15 13-Apr-14

29-Apr-14

T+12GU660

Light Fittings Installation

15 30-Apr-14

17-May-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 31 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+12GU670

Sprinkler Installation

15 30-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
17-May-14

T+12GU690

FA / SD installation

15 05-May-14

21-May-14

T+12GU17410

Underlay & Carpet

15 22-May-14

08-Jun-14

223 08-Oct-13 A

10-Jul-14

154
29
3
3

16-Nov-13
08-Dec-13
08-Jan-14
08-Jan-14

15-May-14
11-Jan-14
11-Jan-14
11-Jan-14

Activity ID

Activity Name

+14 @ +66.60
West Core
Electrical/Telecom Room
Finishes
T+14WR26870 RMX - 01 to floor
T+14WR26880 Permanent door

Duration Start

3 08-Jan-14

11-Jan-14

20 08-Dec-13
3 08-Dec-13

30-Dec-13
10-Dec-13

T+14WR26780 Busbar installation & connection

2 11-Dec-13

12-Dec-13

T+14WR26820 Install IT Panels

2 11-Dec-13

12-Dec-13

T+14WR26830 Install Security Panels

2 11-Dec-13

12-Dec-13

T+14WR26790 Duckwork branch to room

2 14-Dec-13

15-Dec-13

T+14WR26800 Fire alarm cabling

3 16-Dec-13

18-Dec-13

T+14WR26810 Cable terminations

10 19-Dec-13

30-Dec-13

6 31-Dec-13
2 31-Dec-13

07-Jan-14
02-Jan-14

T+14WR26850 Fire alarm devices

2 04-Jan-14

05-Jan-14

T+14WR26860 Light fittings

2 06-Jan-14

07-Jan-14

Finishes - 1st Fix


No DISP
T+14WR26070 Close blockwork risers

17 29-Dec-13
17 29-Dec-13
12 29-Dec-13

18-Jan-14
18-Jan-14
12-Jan-14

T+14WR26060 Studwork incl noggins

12 05-Jan-14*

18-Jan-14

MEP riser summary


No DISP
T+14WR26080 MEP risers & 1st fix

12 16-Nov-13
12 16-Nov-13
12 16-Nov-13

28-Nov-13
28-Nov-13
28-Nov-13

MEP Risers & First Fix


No DISP
T+14WR26110 Ductworks risers

78 16-Nov-13
78 16-Nov-13
12 16-Nov-13

16-Feb-14
16-Feb-14
28-Nov-13

T+14WR26120 Chilled water & condensate Riser

12 23-Nov-13

07-Dec-13

T+14WR26130 DCW / DHW & CCW riser

12 30-Nov-13

14-Dec-13

T+14WR26140 Sanitary riser

12 30-Nov-13

14-Dec-13

T+14WR26220 Test risers ( 3floors vertically )

12 15-Dec-13

28-Dec-13

1st & 2nd Fix


T+14WR26890 Electrical Containment

MEP Final Fix


T+14WR26840 Grills & diffusers

T+14WR26230 MEP sign off risers (Start)

28-Dec-13

T+14WR26150 Hang FCU

12 19-Jan-14

01-Feb-14

T+14WR26160 Ductwork - supply, make-up air & extract

12 19-Jan-14

01-Feb-14

T+14WR26170 CW supply / return & condensate

12 22-Jan-14

04-Feb-14

T+14WR26190 FCU connections

12 27-Jan-14

09-Feb-14

T+14WR26180 Plumbing & san distribution

12 29-Jan-14

11-Feb-14

T+14WR26210 Sprinkler pipes ( Not drops ) from corridor

12 01-Feb-14

13-Feb-14

T+14WR26200 Cable tray / trunking

12 03-Feb-14

16-Feb-14

66 10-Feb-14
66 10-Feb-14
12 10-Feb-14

27-Apr-14
27-Apr-14
23-Feb-14

T+14WR26250 Insulate & board walls

12 15-Feb-14

27-Feb-14

T+14WR26260 Ceiling 1st fix

18 19-Feb-14

11-Mar-14

T+14WR26270 Wiring

12 24-Feb-14

09-Mar-14

Bedroom
No DISP
T+14WR26240 MEP Drops in walls & back boxes

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 32 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+14WR26280 MEP drops in ceiling

12 27-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-Mar-14

T+14WR26290 Board ceiling

12 01-Mar-14

13-Mar-14

T+14WR26300 Tape & Joint walls & ceiling

12 05-Mar-14

18-Mar-14

T+14WR26310 Mist coat all dry lining

12 10-Mar-14

23-Mar-14

T+14WR26320 Install cornice

12 12-Mar-14

25-Mar-14

T+14WR26330 Paint ceiling and cornice

12 17-Mar-14

30-Mar-14

T+14WR26340 Wall covering

12 22-Mar-14

03-Apr-14

T+14WR26350 Install furniture

12 26-Mar-14

08-Apr-14

T+14WR26360 MEP terminations in furniture

12 31-Mar-14

13-Apr-14

T+14WR26370 MEP 3rd fix- sockets, cover plates etc

12 07-Apr-14

20-Apr-14

T+14WR26760 Underlay & Carpet

6 21-Apr-14

27-Apr-14

Bathroom
No DISP
T+14WR26380 Stud to block walls

89 06-Jan-14
89 06-Jan-14
12 06-Jan-14

19-Apr-14
19-Apr-14
19-Jan-14

T+14WR26390 Waterproof bathroom

12 12-Feb-14

25-Feb-14

T+14WR26400 Flood test

12 19-Feb-14

04-Mar-14

T+14WR26410 MEP Drops in walls & back boxes

12 01-Mar-14

13-Mar-14

T+14WR26420 Install bath

12 01-Mar-14

13-Mar-14

T+14WR26430 Insulate & board walls

12 03-Mar-14

16-Mar-14

T+14WR26440 Framing & board for bath

12 03-Mar-14

16-Mar-14

T+14WR26450 First fix ceiling

12 05-Mar-14

18-Mar-14

T+14WR26460 MEP drops in ceiling

12 08-Mar-14

20-Mar-14

T+14WR26470 2nd fix ceiling incl access panel

12 09-Mar-14

22-Mar-14

T+14WR26480 Install corniche

12 11-Mar-14

24-Mar-14

T+14WR26490 Stone to floors

12 13-Mar-14

26-Mar-14

T+14WR26500 Stone surround to bath

12 13-Mar-14

26-Mar-14

T+14WR26510 Stone vanity

12 13-Mar-14

26-Mar-14

T+14WR26520 Stone to walls incl niche

12 13-Mar-14

26-Mar-14

T+14WR26530 Casing stone

12 13-Mar-14

26-Mar-14

T+14WR26540 Grout to all stone

12 13-Mar-14

26-Mar-14

T+14WR26550 Glass Partition

12 27-Mar-14

09-Apr-14

T+14WR26560 Install and connect " Free issue " mirror

12 29-Mar-14

10-Apr-14

T+14WR26570 Sanitary ware and accessories

12 31-Mar-14

13-Apr-14

T+14WR26580 MEP connections to bath and basin

12 01-Apr-14

14-Apr-14

T+14WR26590 MEP 3rd fix - switch / socket covers

12 03-Apr-14

16-Apr-14

T+14WR26600 Hang glass doors

12 06-Apr-14

19-Apr-14

Entrance Vestibule & dressing


No DISP
T+14WR26610 MEP drops in walls

34 08-Mar-14
34 08-Mar-14
12 08-Mar-14

15-Apr-14
15-Apr-14
20-Mar-14

T+14WR26620 Board walls

12 11-Mar-14

24-Mar-14

T+14WR26630 Ceiling 1st fix

12 13-Mar-14

26-Mar-14

T+14WR26640 MEP drops in ceiling

12 16-Mar-14

29-Mar-14

T+14WR26650 Board ceiling incl access panel

12 19-Mar-14

01-Apr-14

T+14WR26700 Stone flooring incl grout

12 20-Mar-14

02-Apr-14

T+14WR26670 Tape & joint walls & ceilings

12 22-Mar-14

03-Apr-14

T+14WR26680 Mist coat dry lining

12 23-Mar-14

05-Apr-14

T+14WR26690 Paint ceiling

12 25-Mar-14

07-Apr-14

T+14WR26710 Pocket door to bathroom

12 26-Mar-14

08-Apr-14

Activity ID

Activity Name

Duration Start

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 33 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+14WR26720 Entrance door - Temporary

12 26-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
08-Apr-14

T+14WR26730 Install wardrobe

12 27-Mar-14

09-Apr-14

T+14WR26740 Wall Coverings

12 30-Mar-14

12-Apr-14

T+14WR26750 3rd fix MEP

12 02-Apr-14

15-Apr-14

22 21-Apr-14
22 21-Apr-14
3 21-Apr-14

15-May-14
15-May-14
23-Apr-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+14GR620
Installation of Flexibles / Plenum
W+14GR640

Sprinkler Drops

Duration Start

3 21-Apr-14

23-Apr-14

W+14GR17360 Gypsum Ceilings

6 24-Apr-14

30-Apr-14

W+14GR17400 Paint Ceiling

2 01-May-14

03-May-14

W+14GR17390 Millwork

6 04-May-14

10-May-14

W+14GR17380 Wall Covering & fabric panels

4 06-May-14

10-May-14

W+14GR660

Light Fittings Installation

2 11-May-14

12-May-14

W+14GR670

Sprinkler Installation

2 11-May-14

12-May-14

3 13-May-14

15-May-14

W+14GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+14ER26070 Close blockwork risers
T+14ER26060

Studwork incl noggins

MEP riser summary


No DISP
T+14ER26080 MEP risers & 1st fix
MEP Risers & First Fix
No DISP
T+14ER26110 Ductworks risers

192
77
77
12

23-Nov-13
22-Dec-13
22-Dec-13
22-Dec-13

10-Jul-14
22-Mar-14
22-Mar-14
05-Jan-14

6 16-Mar-14

22-Mar-14

12 23-Nov-13
12 23-Nov-13
12 23-Nov-13

07-Dec-13
07-Dec-13
07-Dec-13

118 23-Nov-13
118 23-Nov-13
12 23-Nov-13

10-Apr-14
10-Apr-14
07-Dec-13

T+14ER26120

Chilled water & condensate Riser

12 30-Nov-13

14-Dec-13

T+14ER26130

DCW / DHW & CCW riser

12 08-Dec-13

21-Dec-13

T+14ER26140

Sanitary riser

12 08-Dec-13

21-Dec-13

T+14ER26220

Test risers ( 3floors vertically )

12 08-Dec-13

21-Dec-13

T+14ER26230

MEP sign off risers (Start)

21-Dec-13

T+14ER26150

Hang FCU

6 23-Mar-14

29-Mar-14

T+14ER26160

Ductwork - supply, make-up air & extract

6 23-Mar-14

29-Mar-14

T+14ER26170

CW supply / return & condensate

6 26-Mar-14

01-Apr-14

T+14ER26180

Plumbing & san distribution

6 26-Mar-14

01-Apr-14

T+14ER26190

FCU connections

6 31-Mar-14

06-Apr-14

T+14ER26200

Cable tray / trunking

6 31-Mar-14

06-Apr-14

T+14ER26210

Sprinkler pipes ( Not drops ) from corridor

6 05-Apr-14

10-Apr-14

60 07-Apr-14
60 07-Apr-14
6 07-Apr-14

15-Jun-14
15-Jun-14
13-Apr-14

Bedroom
No DISP
T+14ER26240

MEP Drops in walls & back boxes

T+14ER26250

Insulate & board walls

6 12-Apr-14

17-Apr-14

T+14ER26260

Ceiling 1st fix

6 16-Apr-14

22-Apr-14

T+14ER26270

Wiring

6 21-Apr-14

27-Apr-14

T+14ER26280

MEP drops in ceiling

6 24-Apr-14

30-Apr-14

T+14ER26290

Board ceiling

6 26-Apr-14

01-May-14

T+14ER26300

Tape & Joint walls & ceiling

6 30-Apr-14

06-May-14

T+14ER26310

Mist coat all dry lining

6 05-May-14

11-May-14

T+14ER26320

Install cornice

6 07-May-14

13-May-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 34 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+14ER26330

Paint ceiling and cornice

6 12-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
18-May-14

T+14ER26340

Wall covering

6 17-May-14

22-May-14

T+14ER26350

Install furniture

6 21-May-14

27-May-14

T+14ER26360

MEP terminations in furniture

6 26-May-14

01-Jun-14

T+14ER26370

MEP 3rd fix- sockets, cover plates etc

6 02-Jun-14

08-Jun-14

T+14ER27350

Underlay & Carpet

6 09-Jun-14

15-Jun-14
15-May-14
15-May-14
22-Mar-14

Activity ID

Activity Name

Duration Start

Stud to block walls

59 09-Mar-14
59 09-Mar-14
12 09-Mar-14

T+14ER26390

Waterproof bathroom

12 11-Mar-14

24-Mar-14

T+14ER26400

Flood test

12 18-Mar-14

31-Mar-14

T+14ER26410

MEP Drops in walls & back boxes

12 27-Mar-14

09-Apr-14

T+14ER26420

Install bath

12 27-Mar-14

09-Apr-14

T+14ER26430

Insulate & board walls

12 30-Mar-14

12-Apr-14

T+14ER26440

Framing & board for bath

12 30-Mar-14

12-Apr-14

T+14ER26450

First fix ceiling

12 01-Apr-14

14-Apr-14

T+14ER26460

MEP drops in ceiling

12 03-Apr-14

16-Apr-14

T+14ER26470

2nd fix ceiling incl access panel

12 05-Apr-14

17-Apr-14

T+14ER26480

Install corniche

12 07-Apr-14

20-Apr-14

T+14ER26490

Stone to floors

12 09-Apr-14

22-Apr-14

T+14ER26500

Stone surround to bath

12 09-Apr-14

22-Apr-14

T+14ER26510

Stone vanity

12 09-Apr-14

22-Apr-14

T+14ER26520

Stone to walls incl niche

12 09-Apr-14

22-Apr-14

T+14ER26530

Casing stone

12 09-Apr-14

22-Apr-14

T+14ER26540

Grout to all stone

12 09-Apr-14

22-Apr-14

T+14ER26550

Glass Partition

12 23-Apr-14

06-May-14

T+14ER26560

Install and connect " Free issue " mirror

12 24-Apr-14

07-May-14

T+14ER26570

Sanitary ware and accessories

12 27-Apr-14

10-May-14

T+14ER26580

MEP connections to bath and basin

12 28-Apr-14

11-May-14

T+14ER26590

MEP 3rd fix - switch / socket covers

12 30-Apr-14

13-May-14

T+14ER26600

Hang glass doors

12 03-May-14

15-May-14

34 03-Apr-14
34 03-Apr-14
12 03-Apr-14

12-May-14
12-May-14
16-Apr-14

Bathroom
No DISP
T+14ER26380

Entrance Vestibule & dressing


No DISP
T+14ER26610 MEP drops in walls
T+14ER26620

Board walls

12 07-Apr-14

20-Apr-14

T+14ER26630

Ceiling 1st fix

12 09-Apr-14

22-Apr-14

T+14ER26640

MEP drops in ceiling

12 12-Apr-14

24-Apr-14

T+14ER26650

Board ceiling incl access panel

12 15-Apr-14

28-Apr-14

T+14ER26700

Stone flooring incl grout

12 16-Apr-14

29-Apr-14

T+14ER26670

Tape & joint walls & ceilings

12 17-Apr-14

30-Apr-14

T+14ER26680

Mist coat dry lining

12 19-Apr-14

01-May-14

T+14ER26690

Paint ceiling

12 21-Apr-14

04-May-14

T+14ER26710

Pocket door to bathroom

12 22-Apr-14

05-May-14

T+14ER26720

Entrance door - Temporary

12 22-Apr-14

05-May-14

T+14ER26730

Install wardrobe

12 23-Apr-14

06-May-14

T+14ER26740

Wall Coverings

12 26-Apr-14

08-May-14

T+14ER26750

3rd fix MEP

12 29-Apr-14

12-May-14

24 09-Jun-14

10-Jul-14

Pier Corridors & Lift Lobby


Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 35 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

No DISP
E+14GR620
E+14GR640

Installation of Flexibles / Plenum


Sprinkler Drops

Duration Start

24 09-Jun-14
3 09-Jun-14
3 09-Jun-14

11-Jun-14

6 12-Jun-14

18-Jun-14

E+14GR17400 Paint Ceiling

4 19-Jun-14

23-Jun-14

E+14GR17390 Millwork

6 24-Jun-14

01-Jul-14

E+14GR17380 Wall Covering & fabric panels

4 26-Jun-14

01-Jul-14

E+14GR660

Light Fittings Installation

2 03-Jul-14

05-Jul-14

E+14GR670

Sprinkler Installation

2 03-Jul-14

05-Jul-14

3 06-Jul-14

10-Jul-14

East Core - North - JAP Storage


Finishes - 1st Fix
No DISP
T+14ER26760 Studwork incl noggins
MEP Risers & First Fix
No DISP
T+14ER26780 Hang FCU

82
6
6
6

01-Feb-14
01-Feb-14
01-Feb-14
01-Feb-14*

15 08-Feb-14
15 08-Feb-14
4 08-Feb-14

24-Feb-14
24-Feb-14
11-Feb-14

Ductwork - supply, make-up air & extract

6 08-Feb-14

13-Feb-14

T+14ER26800

CW supply / return & condensate

6 11-Feb-14

17-Feb-14

T+14ER26810

Plumbing & san distribution

8 15-Feb-14

23-Feb-14

T+14ER26820

FCU connections

8 16-Feb-14

24-Feb-14

T+14ER26830

Cable tray / trunking

4 19-Feb-14

23-Feb-14

62 24-Feb-14
62 24-Feb-14
4 24-Feb-14

06-May-14
06-May-14
27-Feb-14

MEP Drops in walls & back boxes

T+14ER26850

Insulate & board walls

6 01-Mar-14

06-Mar-14

T+14ER26860

Ceiling 1st fix

6 05-Mar-14

11-Mar-14

T+14ER26870

Wiring

4 10-Mar-14

13-Mar-14

T+14ER26880

MEP drops in ceiling

4 13-Mar-14

17-Mar-14

T+14ER26890

Board ceiling

4 15-Mar-14

18-Mar-14

T+14ER26900

Tape & Joint walls & ceiling

4 19-Mar-14

23-Mar-14

T+14ER26910

Mist coat all dry lining

2 24-Mar-14

25-Mar-14

T+14ER26920

Install cornice

4 26-Mar-14

30-Mar-14

T+14ER26930

Paint ceiling and cornice

4 31-Mar-14

03-Apr-14

T+14ER26940

Wall covering

3 05-Apr-14

07-Apr-14

T+14ER26950

Install furniture

6 09-Apr-14

15-Apr-14

T+14ER26960

MEP terminations in furniture

4 14-Apr-14

17-Apr-14

T+14ER26970

MEP 3rd fix- sockets, cover plates etc

12 21-Apr-14

04-May-14

T+14ER27360

Underlay & Carpet

Bathroom
No DISP
T+14ER26990

Waterproof bathroom

2 05-May-14

06-May-14

46 25-Feb-14
46 25-Feb-14
3 25-Feb-14

19-Apr-14
19-Apr-14
27-Feb-14

T+14ER27000

Cure & Flood test

8 01-Mar-14

09-Mar-14

T+14ER27010

MEP Drops in walls & back boxes

4 05-Mar-14

09-Mar-14

T+14ER27020

Install bath

2 08-Mar-14

09-Mar-14

T+14ER27030

Insulate & board walls

6 10-Mar-14

16-Mar-14

T+14ER27050

First fix ceiling

4 17-Mar-14

20-Mar-14

T+14ER27060

MEP drops in ceiling

4 19-Mar-14

23-Mar-14

T+14ER27070

2nd fix ceiling incl access panel

4 20-Mar-14

24-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 36 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

06-May-14
06-Feb-14
06-Feb-14
06-Feb-14

T+14ER26790

Bedroom
No DISP
T+14ER26840

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-Jul-14
11-Jun-14

E+14GR17360 Gypsum Ceilings

E+14GR17410 Underlay & Carpet

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

Install corniche

3 25-Mar-14

T+14ER27090

Stone to floors

12 27-Mar-14

09-Apr-14

T+14ER27100

Stone surround to bath

12 27-Mar-14

09-Apr-14

T+14ER27110

Stone vanity

12 27-Mar-14

09-Apr-14

T+14ER27120

Stone to walls incl niche

12 27-Mar-14

09-Apr-14

T+14ER27130

Casing stone

12 27-Mar-14

09-Apr-14

T+14ER27140

Grout to all stone

12 27-Mar-14

09-Apr-14

T+14ER27170

Sanitary ware and accessories

5 10-Apr-14

15-Apr-14

T+14ER27180

MEP connections to bath and basin

4 12-Apr-14

15-Apr-14

T+14ER27190

MEP 3rd fix - switch / socket covers

2 14-Apr-14

15-Apr-14

T+14ER27150

Glass Partition

2 16-Apr-14

17-Apr-14

T+14ER27200

Hang glass doors

2 16-Apr-14

17-Apr-14

T+14ER27160

Install and connect " Free issue " mirror

2 17-Apr-14

19-Apr-14

54 24-Feb-14
54 24-Feb-14
4 24-Feb-14

27-Apr-14
27-Apr-14
27-Feb-14

T+14ER27220

Board walls

4 27-Feb-14

03-Mar-14

T+14ER27230

Ceiling 1st fix

3 02-Mar-14

04-Mar-14

T+14ER27240

MEP drops in ceiling

T+14ER27290

Stone flooring incl grout

T+14ER27250

3 04-Mar-14

06-Mar-14

12 27-Mar-14

09-Apr-14

Board ceiling incl access panel

2 10-Apr-14

12-Apr-14

T+14ER27260

Tape & joint walls & ceilings

3 13-Apr-14

15-Apr-14

T+14ER27270

Mist coat dry lining

2 14-Apr-14

15-Apr-14

T+14ER27280

Paint ceiling

2 16-Apr-14

17-Apr-14

T+14ER27300

Pocket door to bathroom

3 19-Apr-14

21-Apr-14

T+14ER27320

Install wardrobe

3 19-Apr-14

21-Apr-14

T+14ER27330

Wall Coverings

2 22-Apr-14

23-Apr-14

T+14ER27310

Mirrors

3 24-Apr-14

27-Apr-14

T+14ER27340

3rd fix MEP

2 24-Apr-14

26-Apr-14

Guestrooms
Bedroom
No DISP
T+14GU17530

Paint ceiling and cornice

147
76
76
12

08-Oct-13 A
20-Oct-13 A
20-Oct-13 A
20-Oct-13 A

Wall covering

12 17-Dec-13

30-Dec-13

T+14GU17550

Install furniture

12 22-Dec-13

05-Jan-14

T+14GU17560

MEP terminations in furniture

12 29-Dec-13

12-Jan-14

T+14GU17570

MEP 3rd fix- sockets, cover plates etc

12 06-Jan-14

19-Jan-14

T+14GU17960

Underlay & Carpet

12 30-Jan-14

12-Feb-14

107 08-Oct-13 A
107 08-Oct-13 A
12 10-Oct-13 A

20-Feb-14
20-Feb-14
30-Nov-13

Stone to floors

T+14GU17700

Stone surround to bath

12 17-Nov-13

30-Nov-13

T+14GU17710

Stone vanity

12 17-Nov-13

30-Nov-13

T+14GU17720

Stone to walls incl niche

12 17-Nov-13

30-Nov-13

T+14GU17730

Casing stone

12 17-Nov-13

30-Nov-13

T+14GU17740

Grout to all stone

12 17-Nov-13

30-Nov-13

T+14GU17970

VAnity S/S & Mirrors

12 19-Nov-13

03-Dec-13

T+14GU17980

VAnity Unit

12 19-Nov-13

03-Dec-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 37 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

08-Apr-14
12-Feb-14
12-Feb-14
24-Nov-13

T+14GU17540

Bathroom
No DISP
T+14GU17690

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
27-Mar-14

T+14ER27080

Entrance Vestibule & dressing


No DISP
T+14ER27210 MEP drops in walls

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+14GU17680

Install corniche

12 08-Oct-13 A

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
25-Nov-13

T+14GU17750

Glass Partition

12 26-Nov-13

10-Dec-13

T+14GU17800

Hang glass doors

12 30-Nov-13

14-Dec-13

T+14GU18120

Wall covering

12 19-Dec-13

02-Jan-14

T+14GU17760

Install and connect " Free issue " mirror

12 04-Feb-14*

17-Feb-14

T+14GU17770

Sanitary ware and accessories

12 04-Feb-14

17-Feb-14

T+14GU17780

MEP connections to bath and basin

12 05-Feb-14

18-Feb-14

T+14GU17790

MEP 3rd fix - switch / socket covers

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+14GU17880 Mist coat dry lining

Duration Start

12 08-Feb-14

20-Feb-14

118 16-Oct-13 A
118 16-Oct-13 A
6 16-Nov-13

26-Mar-14
26-Mar-14
21-Nov-13

T+14GU17900

Stone flooring incl grout

12 16-Oct-13 A

05-Dec-13

T+14GU17870

Tape & joint walls & ceilings

12 20-Oct-13 A

08-Dec-13

T+14GU17890

Paint ceiling

6 07-Dec-13

12-Dec-13

T+14GU17930

Install wardrobe

12 07-Dec-13

19-Dec-13

T+14GU17920

Mirrors

12 21-Dec-13

04-Jan-14

T+14GU17940

Wall Coverings

12 30-Dec-13

13-Jan-14

T+14GU17950

3rd fix MEP

12 05-Jan-14

18-Jan-14

T+14GU17910

Pocket door to bathroom

12 13-Mar-14

26-Mar-14

Installation of Flexibles / Plenum

41 20-Feb-14
41 20-Feb-14
8 20-Feb-14

08-Apr-14
08-Apr-14
01-Mar-14

Corridor
No DISP
T+14GR620
T+14GR640

Sprinkler Drops

6 23-Feb-14

01-Mar-14

T+14GR17360

Gypsum Ceilings

6 23-Feb-14

01-Mar-14

T+14GR680

Grilles / Diffuser Installation

7 02-Mar-14

09-Mar-14

T+14GR17370

T & J Walls & Ceilings

6 02-Mar-14

08-Mar-14

T+14GR17400

Paint Ceiling

4 09-Mar-14

12-Mar-14

T+14GR17390

Millwork

12 13-Mar-14

26-Mar-14

T+14GR17380

Wall Covering

4 27-Mar-14

31-Mar-14

T+14GR17420

Mirrors

3 27-Mar-14

30-Mar-14

T+14GR660

Light Fittings Installation

4 01-Apr-14

05-Apr-14

T+14GR690

FA / SD installation

4 01-Apr-14

05-Apr-14

T+14GR670

Sprinkler Installation

4 01-Apr-14

05-Apr-14

T+14GR17410

Underlay & Carpet

3 06-Apr-14

08-Apr-14

160 19-Oct-13 A

29-Apr-14

132
29
3
3

16-Nov-13
11-Dec-13
12-Jan-14
12-Jan-14

20-Apr-14
14-Jan-14
14-Jan-14
14-Jan-14

+15 @ +70.40
West Core
Electrical/Telecom Room
Finishes
T+15WR26870 RMX - 01 to floor
T+15WR26880 Permanent door

3 12-Jan-14

14-Jan-14

20 11-Dec-13
3 11-Dec-13

04-Jan-14
14-Dec-13

T+15WR26780 Busbar installation & connection

2 15-Dec-13

16-Dec-13

T+15WR26820 Install IT Panels

2 15-Dec-13

16-Dec-13

T+15WR26830 Install Security Panels

2 15-Dec-13

16-Dec-13

T+15WR26790 Duckwork branch to room

2 17-Dec-13

18-Dec-13

T+15WR26800 Fire alarm cabling

3 19-Dec-13

22-Dec-13

T+15WR26810 Cable terminations

10 23-Dec-13

04-Jan-14

6 05-Jan-14

11-Jan-14

1st & 2nd Fix


T+15WR26890 Electrical Containment

MEP Final Fix


Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 38 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+15WR26840 Grills & diffusers

2 05-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
06-Jan-14

T+15WR26850 Fire alarm devices

2 07-Jan-14

08-Jan-14

T+15WR26860 Light fittings

2 09-Jan-14

11-Jan-14

52 16-Nov-13
52 16-Nov-13
12 16-Nov-13*

16-Jan-14
16-Jan-14
28-Nov-13

Activity ID

Activity Name

Finishes - 1st Fix


No DISP
T+15WR26060 Studwork incl noggins
T+15WR26070 Close blockwork risers

Duration Start

12 04-Jan-14

16-Jan-14

MEP riser summary


No DISP
T+15WR26080 MEP risers & 1st fix

12 23-Nov-13
12 23-Nov-13
12 23-Nov-13

07-Dec-13
07-Dec-13
07-Dec-13

MEP Risers & First Fix


No DISP
T+15WR26110 Ductworks risers

35 23-Nov-13
35 23-Nov-13
12 23-Nov-13

04-Jan-14
04-Jan-14
07-Dec-13

T+15WR26120 Chilled water & condensate

12 30-Nov-13

14-Dec-13

T+15WR26130 DCW / DHW & CCW riser

12 08-Dec-13

21-Dec-13

T+15WR26140 Sanitary riser

12 08-Dec-13

21-Dec-13

T+15WR26150 Hang FCU

12 08-Dec-13

21-Dec-13

T+15WR26160 Ductwork - supply, make-up air & extract

12 08-Dec-13

21-Dec-13

T+15WR26170 CW supply / return & condensate

12 11-Dec-13

24-Dec-13

T+15WR26180 Plumbing & san distribution

12 12-Dec-13

25-Dec-13

T+15WR26190 FCU connections

12 16-Dec-13

29-Dec-13

T+15WR26200 Cable tray / trunking

12 17-Dec-13

30-Dec-13

T+15WR26220 Test risers ( 3floors vertically )

12 19-Dec-13

02-Jan-14

T+15WR26210 Sprinkler pipes ( Not drops ) from corridor

12 21-Dec-13

04-Jan-14

T+15WR26230 MEP sign off risers (Start)

02-Jan-14

66 24-Dec-13
66 24-Dec-13
12 24-Dec-13

11-Mar-14
11-Mar-14
07-Jan-14

T+15WR26250 Insulate & board walls

12 29-Dec-13

12-Jan-14

T+15WR26260 Ceiling 1st fix

18 04-Jan-14

23-Jan-14

T+15WR26270 Wiring

12 08-Jan-14

21-Jan-14

T+15WR26280 MEP drops in ceiling

12 12-Jan-14

25-Jan-14

T+15WR26290 Board ceiling

12 13-Jan-14

26-Jan-14

T+15WR26300 Tape & Joint walls & ceiling

12 18-Jan-14

30-Jan-14

T+15WR26310 Mist coat all dry lining

12 22-Jan-14

04-Feb-14

T+15WR26320 Install cornice

12 25-Jan-14

06-Feb-14

T+15WR26330 Paint ceiling and cornice

12 29-Jan-14

11-Feb-14

T+15WR26340 Wall covering

12 03-Feb-14

16-Feb-14

T+15WR26350 Install furniture

12 08-Feb-14

20-Feb-14

T+15WR26360 MEP terminations in furniture

12 12-Feb-14

25-Feb-14

T+15WR26370 MEP 3rd fix- sockets, cover plates etc

Bedroom
No DISP
T+15WR26240 MEP Drops in walls & back boxes

12 19-Feb-14

04-Mar-14

T+15WR26760 Underlay & Carpet

6 05-Mar-14

11-Mar-14

Bathroom
No DISP
T+15WR26380 Stud to block walls

64 11-Jan-14
64 11-Jan-14
12 11-Jan-14

25-Mar-14
25-Mar-14
23-Jan-14

T+15WR26390 Waterproof bathroom

12 13-Jan-14

26-Jan-14

T+15WR26400 Flood test

12 20-Jan-14

02-Feb-14

T+15WR26410 MEP Drops in walls & back boxes

12 29-Jan-14

11-Feb-14

T+15WR26420 Install bath

12 29-Jan-14

11-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 39 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+15WR26430 Insulate & board walls

12 01-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
13-Feb-14

T+15WR26440 Framing & board for bath

12 01-Feb-14

13-Feb-14

T+15WR26450 First fix ceiling

12 03-Feb-14

16-Feb-14

T+15WR26460 MEP drops in ceiling

12 05-Feb-14

18-Feb-14

T+15WR26470 2nd fix ceiling incl access panel

12 06-Feb-14

19-Feb-14

T+15WR26480 Install corniche

12 09-Feb-14

22-Feb-14

T+15WR26490 Stone to floors

12 17-Feb-14

02-Mar-14

T+15WR26500 Stone surround to bath

12 17-Feb-14

02-Mar-14

T+15WR26510 Stone vanity

12 17-Feb-14

02-Mar-14

T+15WR26520 Stone to walls incl niche

12 17-Feb-14

02-Mar-14

T+15WR26530 Casing stone

12 17-Feb-14

02-Mar-14

T+15WR26540 Grout to all stone

12 17-Feb-14

02-Mar-14

T+15WR26550 Glass Partition

12 03-Mar-14

16-Mar-14

T+15WR26560 Install and connect " Free issue " mirror

12 04-Mar-14

17-Mar-14

T+15WR26570 Sanitary ware and accessories

12 06-Mar-14

19-Mar-14

T+15WR26580 MEP connections to bath and basin

12 08-Mar-14

20-Mar-14

T+15WR26590 MEP 3rd fix - switch / socket covers

12 10-Mar-14

23-Mar-14

T+15WR26600 Hang glass doors

12 12-Mar-14

25-Mar-14

Entrance Vestibule & dressing


No DISP
T+15WR26610 MEP drops in walls

39 05-Feb-14
39 05-Feb-14
12 05-Feb-14

22-Mar-14
22-Mar-14
18-Feb-14

T+15WR26620 Board walls

12 09-Feb-14

22-Feb-14

T+15WR26630 Ceiling 1st fix

12 11-Feb-14

24-Feb-14

T+15WR26640 MEP drops in ceiling

12 13-Feb-14

26-Feb-14

T+15WR26650 Board ceiling incl access panel

12 17-Feb-14

02-Mar-14

T+15WR26670 Tape & joint walls & ceilings

12 19-Feb-14

04-Mar-14

T+15WR26680 Mist coat dry lining

12 20-Feb-14

05-Mar-14

T+15WR26690 Paint ceiling

12 23-Feb-14

08-Mar-14

T+15WR26700 Stone flooring incl grout

12 24-Feb-14

09-Mar-14

T+15WR26710 Pocket door to bathroom

12 02-Mar-14

15-Mar-14

T+15WR26720 Entrance door - Temporary

12 02-Mar-14

15-Mar-14

T+15WR26730 Install wardrobe

12 03-Mar-14

16-Mar-14

T+15WR26740 Wall Coverings

12 05-Mar-14

18-Mar-14

T+15WR26750 3rd fix MEP

12 09-Mar-14

22-Mar-14

22 26-Mar-14
22 26-Mar-14
3 26-Mar-14

20-Apr-14
20-Apr-14
29-Mar-14

3 26-Mar-14

29-Mar-14

W+15GR17360 Gypsum Ceilings

6 30-Mar-14

05-Apr-14

W+15GR17400 Paint Ceiling

2 06-Apr-14

07-Apr-14

W+15GR17390 Millwork

6 08-Apr-14

14-Apr-14

W+15GR17380 Wall Covering & fabric panels

4 10-Apr-14

14-Apr-14

W+15GR660

Light Fittings Installation

2 15-Apr-14

16-Apr-14

W+15GR670

Sprinkler Installation

2 15-Apr-14

16-Apr-14

3 17-Apr-14

20-Apr-14

140 19-Oct-13 A
40 16-Nov-13
40 16-Nov-13

29-Apr-14
02-Jan-14
02-Jan-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+15GR620
Installation of Flexibles / Plenum
W+15GR640

Sprinkler Drops

W+15GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP

Duration Start

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 40 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+15ER26060

Studwork incl noggins

12 16-Nov-13*

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
28-Nov-13

T+15ER26070

Close blockwork risers

12 19-Dec-13

02-Jan-14

MEP riser summary


No DISP
T+15ER26080 MEP risers & 1st fix

12 19-Oct-13 A
12 19-Oct-13 A
12 19-Oct-13 A

12-Dec-13
12-Dec-13
12-Dec-13

MEP Risers & First Fix


No DISP
T+15ER26110 Ductworks risers

29 19-Oct-13 A
29 19-Oct-13 A
12 19-Oct-13 A

19-Dec-13
19-Dec-13
23-Nov-13

Activity ID

Activity Name

Duration Start

T+15ER26120

Chilled water & condensate

12 16-Nov-13

28-Nov-13

T+15ER26130

DCW / DHW & CCW riser

12 23-Nov-13

07-Dec-13

T+15ER26140

Sanitary riser

12 23-Nov-13

07-Dec-13

T+15ER26150

Hang FCU

12 23-Nov-13

07-Dec-13

T+15ER26160

Ductwork - supply, make-up air & extract

12 23-Nov-13

07-Dec-13

T+15ER26170

CW supply / return & condensate

12 26-Nov-13

10-Dec-13

T+15ER26180

Plumbing & san distribution

12 27-Nov-13

11-Dec-13

T+15ER26190

FCU connections

12 01-Dec-13

15-Dec-13

T+15ER26200

Cable tray / trunking

12 03-Dec-13

16-Dec-13

T+15ER26220

Test risers ( 3floors vertically )

12 05-Dec-13

18-Dec-13

T+15ER26210

Sprinkler pipes ( Not drops ) from corridor

12 07-Dec-13

19-Dec-13

T+15ER26230

MEP sign off risers (Start)

Bedroom
No DISP
T+15ER26240

MEP Drops in walls & back boxes

18-Dec-13

113 10-Dec-13
113 10-Dec-13
12 10-Dec-13

21-Apr-14
21-Apr-14
23-Dec-13

T+15ER26250

Insulate & board walls

12 15-Dec-13

28-Dec-13

T+15ER26260

Ceiling 1st fix

18 19-Dec-13

09-Jan-14

T+15ER26270

Wiring

12 24-Dec-13

07-Jan-14

T+15ER26280

MEP drops in ceiling

12 28-Dec-13

11-Jan-14

T+15ER26290

Board ceiling

12 29-Dec-13

12-Jan-14

T+15ER26300

Tape & Joint walls & ceiling

12 04-Jan-14

16-Jan-14

T+15ER26310

Mist coat all dry lining

12 08-Jan-14

21-Jan-14

T+15ER26320

Install cornice

12 11-Jan-14

23-Jan-14

T+15ER26330

Paint ceiling and cornice

12 15-Jan-14

28-Jan-14

T+15ER26340

Wall covering

6 16-Mar-14

22-Mar-14

T+15ER26350

Install furniture

12 20-Mar-14

02-Apr-14

T+15ER26360

MEP terminations in furniture

12 25-Mar-14

07-Apr-14

T+15ER26370

MEP 3rd fix- sockets, cover plates etc

12 01-Apr-14

14-Apr-14

T+15ER26760

Underlay & Carpet

6 15-Apr-14

21-Apr-14

Stud to block walls

82 26-Dec-13
82 26-Dec-13
12 26-Dec-13

01-Apr-14
01-Apr-14
09-Jan-14

T+15ER26390

Waterproof bathroom

12 29-Dec-13

12-Jan-14

T+15ER26400

Flood test

12 06-Jan-14

19-Jan-14

T+15ER26410

MEP Drops in walls & back boxes

12 15-Jan-14

28-Jan-14

T+15ER26420

Install bath

12 15-Jan-14

28-Jan-14

T+15ER26430

Insulate & board walls

12 18-Jan-14

30-Jan-14

T+15ER26440

Framing & board for bath

12 18-Jan-14

30-Jan-14

T+15ER26450

First fix ceiling

12 20-Jan-14

02-Feb-14

T+15ER26460

MEP drops in ceiling

12 22-Jan-14

04-Feb-14

T+15ER26470

2nd fix ceiling incl access panel

12 23-Jan-14

05-Feb-14

Bathroom
No DISP
T+15ER26380

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 41 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+15ER26480

Install corniche

12 26-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
08-Feb-14

T+15ER26490

Stone to floors

12 24-Feb-14

09-Mar-14

T+15ER26500

Stone surround to bath

12 24-Feb-14

09-Mar-14

T+15ER26510

Stone vanity

12 24-Feb-14

09-Mar-14

T+15ER26520

Stone to walls incl niche

12 24-Feb-14

09-Mar-14

T+15ER26530

Casing stone

12 24-Feb-14

09-Mar-14

T+15ER26540

Grout to all stone

12 24-Feb-14

09-Mar-14

T+15ER26550

Glass Partition

12 10-Mar-14

23-Mar-14

T+15ER26560

Install and connect " Free issue " mirror

12 11-Mar-14

24-Mar-14

T+15ER26570

Sanitary ware and accessories

12 13-Mar-14

26-Mar-14

T+15ER26580

MEP connections to bath and basin

12 15-Mar-14

27-Mar-14

T+15ER26590

MEP 3rd fix - switch / socket covers

12 17-Mar-14

30-Mar-14

T+15ER26600

Hang glass doors

12 19-Mar-14

01-Apr-14

57 22-Jan-14
57 22-Jan-14
12 22-Jan-14

29-Mar-14
29-Mar-14
04-Feb-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+15ER26610 MEP drops in walls

Duration Start

T+15ER26620

Board walls

12 26-Jan-14

08-Feb-14

T+15ER26630

Ceiling 1st fix

12 28-Jan-14

10-Feb-14

T+15ER26640

MEP drops in ceiling

12 30-Jan-14

12-Feb-14

T+15ER26650

Board ceiling incl access panel

12 03-Feb-14

16-Feb-14

T+15ER26670

Tape & joint walls & ceilings

12 05-Feb-14

18-Feb-14

T+15ER26680

Mist coat dry lining

12 06-Feb-14

19-Feb-14

T+15ER26690

Paint ceiling

12 09-Feb-14

22-Feb-14

T+15ER26700

Stone flooring incl grout

12 03-Mar-14

16-Mar-14

T+15ER26710

Pocket door to bathroom

12 09-Mar-14

22-Mar-14

T+15ER26720

Entrance door - Temporary

12 09-Mar-14

22-Mar-14

T+15ER26730

Install wardrobe

12 10-Mar-14

23-Mar-14

T+15ER26740

Wall Coverings

12 12-Mar-14

25-Mar-14

T+15ER26750

3rd fix MEP

12 16-Mar-14

29-Mar-14

24 02-Apr-14
24 02-Apr-14
3 02-Apr-14

29-Apr-14
29-Apr-14
05-Apr-14

Pier Corridors & Lift Lobby


No DISP
E+15GR620
Installation of Flexibles / Plenum
E+15GR640

3 02-Apr-14

05-Apr-14

E+15GR17360 Gypsum Ceilings

Sprinkler Drops

6 06-Apr-14

12-Apr-14

E+15GR17400 Paint Ceiling

4 13-Apr-14

16-Apr-14

E+15GR17390 Millwork

6 17-Apr-14

23-Apr-14

E+15GR17380 Wall Covering & fabric panels

4 20-Apr-14

23-Apr-14

E+15GR660

Light Fittings Installation

2 24-Apr-14

26-Apr-14

E+15GR670

Sprinkler Installation

2 24-Apr-14

26-Apr-14

3 27-Apr-14

29-Apr-14

E+15GR17410 Underlay & Carpet


Guestrooms
Bedroom
No DISP
T+15GU20160

Paint ceiling and cornice

146
76
76
12

21-Oct-13 A
21-Oct-13 A
21-Oct-13 A
21-Oct-13 A

13-Apr-14
19-Feb-14
19-Feb-14
26-Nov-13

T+15GU20170

Wall covering

12 24-Dec-13

07-Jan-14

T+15GU20180

Install furniture

12 29-Dec-13

12-Jan-14

T+15GU20190

MEP terminations in furniture

12 02-Jan-14

15-Jan-14

T+15GU20200

MEP 3rd fix- sockets, cover plates etc

12 09-Jan-14

22-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 42 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

T+15GU17970

Data date: 16-Nov-13

12 06-Feb-14

02-Mar-14
02-Mar-14
15-Dec-13

Stone to floors

T+15GU21870

Stone surround to bath

12 01-Dec-13

15-Dec-13

T+15GU21880

Stone vanity

12 01-Dec-13

15-Dec-13

T+15GU21890

Stone to walls incl niche

12 01-Dec-13

15-Dec-13

T+15GU21900

Casing stone

12 01-Dec-13

15-Dec-13

T+15GU21910

Grout to all stone

12 09-Dec-13

22-Dec-13

T+15GU21850

Install corniche

12 16-Dec-13

29-Dec-13

T+15GU24670

Vanity S/S & mirrors

12 16-Dec-13

29-Dec-13

T+15GU24680

Vanity Unit

12 16-Dec-13

29-Dec-13

T+15GU21920

Glass Partition

12 23-Dec-13

06-Jan-14

T+15GU21970

Hang glass doors

12 28-Dec-13

11-Jan-14

T+15GU18120

Wall covering

12 04-Jan-14

16-Jan-14

T+15GU21930

Install and connect " Free issue " mirror

12 11-Feb-14*

24-Feb-14

T+15GU21940

Sanitary ware and accessories

12 13-Feb-14

26-Feb-14

T+15GU21950

MEP connections to bath and basin

12 15-Feb-14

27-Feb-14

T+15GU21960

MEP 3rd fix - switch / socket covers

Entrance Vestibule & dressing


No DISP
T+15GU24550 Board ceiling incl access panel

12 17-Feb-14

02-Mar-14

137 21-Oct-13 A
137 21-Oct-13 A
6 21-Oct-13 A

02-Apr-14
02-Apr-14
16-Nov-13

T+15GU24580

Mist coat dry lining

12 16-Nov-13

28-Nov-13

T+15GU24590

Paint ceiling

12 18-Nov-13

01-Dec-13

T+15GU24600

Stone flooring incl grout

12 01-Dec-13

15-Dec-13

T+15GU24630

Install wardrobe

12 09-Dec-13

22-Dec-13

T+15GU24620

Mirrors

12 16-Dec-13

29-Dec-13

T+15GU24650

3rd fix MEP

12 30-Dec-13

13-Jan-14

T+15GU24640

Wall Coverings

12 06-Jan-14

19-Jan-14

T+15GU24610

Pocket door to bathroom

12 20-Mar-14

02-Apr-14

Gypsum Ceilings

37 02-Mar-14
37 02-Mar-14
6 02-Mar-14

13-Apr-14
13-Apr-14
08-Mar-14

T+15GR620

Installation of Flexibles / Plenum

5 09-Mar-14

13-Mar-14

T+15GR640

Sprinkler Drops

6 09-Mar-14

15-Mar-14

T+15GR17370

T & J Walls & Ceilings

6 09-Mar-14

15-Mar-14

T+15GR680

Grilles / Diffuser Installation

7 15-Mar-14

22-Mar-14

T+15GR17400

Paint Ceiling

T+15GR17390

Millwork

T+15GR17380

4 16-Mar-14

19-Mar-14

10 20-Mar-14

31-Mar-14

Wall Covering

4 01-Apr-14

05-Apr-14

T+15GR17420

Mirrors

3 01-Apr-14

03-Apr-14

T+15GR660

Light Fittings Installation

4 06-Apr-14

09-Apr-14

T+15GR690

FA / SD installation

4 06-Apr-14

09-Apr-14

T+15GR670

Sprinkler Installation

4 06-Apr-14

09-Apr-14

T+15GR17410

Underlay & Carpet

3 10-Apr-14

13-Apr-14

174 19-Oct-13 A

22-May-14

154 23-Nov-13
29 15-Dec-13
3 15-Jan-14

22-May-14
18-Jan-14
18-Jan-14

+16 @ +74.20
West Core
Electrical/Telecom Room
Finishes
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Revised Programme Rev. D

Underlay & Carpet

Duration Start

77 01-Dec-13
77 01-Dec-13
12 01-Dec-13*

Corridor
No DISP
T+15GR17360

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
19-Feb-14

Activity Name

Bathroom
No DISP
T+15GU21860

Four Seasons Hotel Bahrain

Page 43 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+16WR26870 RMX - 01 to floor


T+16WR26880 Permanent door

18-Jan-14
07-Jan-14
17-Dec-13

T+16WR26780 Busbar installation & connection

2 18-Dec-13

19-Dec-13

T+16WR26820 Install IT Panels

2 18-Dec-13

19-Dec-13

T+16WR26830 Install Security Panels

2 18-Dec-13

19-Dec-13

T+16WR26790 Duckwork branch to room

2 21-Dec-13

22-Dec-13

T+16WR26800 Fire alarm cabling

3 23-Dec-13

25-Dec-13

T+16WR26810 Cable terminations

10 26-Dec-13

07-Jan-14

6 08-Jan-14
2 08-Jan-14

14-Jan-14
09-Jan-14

T+16WR26850 Fire alarm devices

2 11-Jan-14

12-Jan-14

T+16WR26860 Light fittings

2 13-Jan-14

14-Jan-14

Finishes - 1st Fix


No DISP
T+16WR26060 Studwork incl noggins

52 23-Nov-13
52 23-Nov-13
12 23-Nov-13

23-Jan-14
23-Jan-14
07-Dec-13

T+16WR26070 Close blockwork risers

12 11-Jan-14

23-Jan-14

MEP riser summary


No DISP
T+16WR26080 MEP risers & 1st fix

12 30-Nov-13
12 30-Nov-13
12 30-Nov-13

14-Dec-13
14-Dec-13
14-Dec-13

MEP Risers & First Fix


No DISP
T+16WR26110 Ductworks risers

35 30-Nov-13
35 30-Nov-13
12 30-Nov-13

11-Jan-14
11-Jan-14
14-Dec-13

T+16WR26120 Chilled water & condensate

12 08-Dec-13

21-Dec-13

T+16WR26130 DCW / DHW & CCW riser

12 15-Dec-13

28-Dec-13

T+16WR26140 Sanitary riser

12 15-Dec-13

28-Dec-13

T+16WR26150 Hang FCU

12 15-Dec-13

28-Dec-13

T+16WR26160 Ductwork - supply, make-up air & extract

12 15-Dec-13

28-Dec-13

T+16WR26170 CW supply / return & condensate

12 18-Dec-13

31-Dec-13

T+16WR26180 Plumbing & san distribution

12 19-Dec-13

02-Jan-14

T+16WR26190 FCU connections

12 23-Dec-13

06-Jan-14

T+16WR26200 Cable tray / trunking

12 24-Dec-13

07-Jan-14

T+16WR26220 Test risers ( 3floors vertically )

12 26-Dec-13

09-Jan-14

T+16WR26210 Sprinkler pipes ( Not drops ) from corridor

12 28-Dec-13

11-Jan-14

T+16WR26230 MEP sign off risers (Start)

04-May-14
04-May-14
14-Jan-14

T+16WR26250 Insulate & board walls

12 22-Feb-14

06-Mar-14

T+16WR26260 Ceiling 1st fix

18 26-Feb-14

18-Mar-14

T+16WR26270 Wiring

12 03-Mar-14

16-Mar-14

T+16WR26280 MEP drops in ceiling

12 06-Mar-14

19-Mar-14

T+16WR26290 Board ceiling

12 08-Mar-14

20-Mar-14

T+16WR26300 Tape & Joint walls & ceiling

12 12-Mar-14

25-Mar-14

T+16WR26310 Mist coat all dry lining

12 17-Mar-14

30-Mar-14

T+16WR26320 Install cornice

12 19-Mar-14

01-Apr-14

T+16WR26330 Paint ceiling and cornice

12 24-Mar-14

06-Apr-14

T+16WR26340 Wall covering

12 29-Mar-14

10-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

09-Jan-14

106 31-Dec-13
106 31-Dec-13
12 31-Dec-13

Bedroom
No DISP
T+16WR26240 MEP Drops in walls & back boxes

Revised Programme Rev. D

3 15-Jan-14
3 15-Jan-14

MEP Final Fix


T+16WR26840 Grills & diffusers

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
18-Jan-14

Duration Start

20 15-Dec-13
3 15-Dec-13

1st & 2nd Fix


T+16WR26890 Electrical Containment

Four Seasons Hotel Bahrain

Page 44 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+16WR26350 Install furniture

12 02-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
15-Apr-14

T+16WR26360 MEP terminations in furniture

12 07-Apr-14

20-Apr-14

T+16WR26370 MEP 3rd fix- sockets, cover plates etc

12 14-Apr-14

27-Apr-14

T+16WR26760 Underlay & Carpet

6 28-Apr-14

04-May-14

Bathroom
No DISP
T+16WR26380 Stud to block walls

64 18-Jan-14
64 18-Jan-14
12 18-Jan-14

01-Apr-14
01-Apr-14
30-Jan-14

T+16WR26390 Waterproof bathroom

12 20-Jan-14

02-Feb-14

T+16WR26400 Flood test

12 27-Jan-14

09-Feb-14

T+16WR26410 MEP Drops in walls & back boxes

12 05-Feb-14

18-Feb-14

T+16WR26420 Install bath

12 05-Feb-14

18-Feb-14

T+16WR26430 Insulate & board walls

12 08-Feb-14

20-Feb-14

T+16WR26440 Framing & board for bath

12 08-Feb-14

20-Feb-14

T+16WR26450 First fix ceiling

12 10-Feb-14

23-Feb-14

T+16WR26460 MEP drops in ceiling

12 12-Feb-14

25-Feb-14

T+16WR26470 2nd fix ceiling incl access panel

12 13-Feb-14

26-Feb-14

T+16WR26480 Install corniche

12 16-Feb-14

01-Mar-14

T+16WR26490 Stone to floors

12 24-Feb-14

09-Mar-14

T+16WR26500 Stone surround to bath

12 24-Feb-14

09-Mar-14

T+16WR26510 Stone vanity

12 24-Feb-14

09-Mar-14

T+16WR26520 Stone to walls incl niche

12 24-Feb-14

09-Mar-14

T+16WR26530 Casing stone

12 24-Feb-14

09-Mar-14

T+16WR26540 Grout to all stone

12 24-Feb-14

09-Mar-14

T+16WR26550 Glass Partition

12 10-Mar-14

23-Mar-14

T+16WR26560 Install and connect " Free issue " mirror

12 11-Mar-14

24-Mar-14

T+16WR26570 Sanitary ware and accessories

12 13-Mar-14

26-Mar-14

T+16WR26580 MEP connections to bath and basin

12 15-Mar-14

27-Mar-14

T+16WR26590 MEP 3rd fix - switch / socket covers

12 17-Mar-14

30-Mar-14

T+16WR26600 Hang glass doors

12 19-Mar-14

01-Apr-14

Entrance Vestibule & dressing


No DISP
T+16WR26610 MEP drops in walls

39 12-Feb-14
39 12-Feb-14
12 12-Feb-14

29-Mar-14
29-Mar-14
25-Feb-14

T+16WR26620 Board walls

12 16-Feb-14

01-Mar-14

T+16WR26630 Ceiling 1st fix

12 18-Feb-14

03-Mar-14

T+16WR26640 MEP drops in ceiling

12 20-Feb-14

05-Mar-14

T+16WR26650 Board ceiling incl access panel

12 24-Feb-14

09-Mar-14

T+16WR26670 Tape & joint walls & ceilings

12 26-Feb-14

11-Mar-14

T+16WR26680 Mist coat dry lining

12 27-Feb-14

12-Mar-14

T+16WR26690 Paint ceiling

12 02-Mar-14

15-Mar-14

T+16WR26700 Stone flooring incl grout

12 03-Mar-14

16-Mar-14

T+16WR26710 Pocket door to bathroom

12 09-Mar-14

22-Mar-14

T+16WR26720 Entrance door - Temporary

12 09-Mar-14

22-Mar-14

T+16WR26730 Install wardrobe

12 10-Mar-14

23-Mar-14

T+16WR26740 Wall Coverings

12 12-Mar-14

25-Mar-14

T+16WR26750 3rd fix MEP

12 16-Mar-14

29-Mar-14

22 28-Apr-14
22 28-Apr-14
3 28-Apr-14

22-May-14
22-May-14
30-Apr-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+16GR620
Installation of Flexibles / Plenum

Duration Start

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 45 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

3 28-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
30-Apr-14

W+16GR17360 Gypsum Ceilings

6 01-May-14

07-May-14

W+16GR17400 Paint Ceiling

2 08-May-14

10-May-14

W+16GR17390 Millwork

6 11-May-14

17-May-14

W+16GR17380 Wall Covering & fabric panels

4 13-May-14

17-May-14

W+16GR660

Light Fittings Installation

2 18-May-14

19-May-14

W+16GR670

Sprinkler Installation

2 18-May-14

19-May-14

3 20-May-14

22-May-14

Activity ID

Activity Name

W+16GR640

Sprinkler Drops

W+16GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+16ER26060 Studwork incl noggins
T+16ER26070

Close blockwork risers

Duration Start

140
57
57
12

23-Nov-13
23-Nov-13
23-Nov-13
23-Nov-13

06-May-14
29-Jan-14
29-Jan-14
07-Dec-13

12 16-Jan-14

29-Jan-14

MEP riser summary


No DISP
T+16ER26080 MEP risers & 1st fix

12 07-Dec-13
12 07-Dec-13
12 07-Dec-13

19-Dec-13
19-Dec-13
19-Dec-13

MEP Risers & First Fix


No DISP
T+16ER26110 Ductworks risers

35 07-Dec-13
35 07-Dec-13
12 07-Dec-13

16-Jan-14
16-Jan-14
19-Dec-13

T+16ER26120

Chilled water & condensate

12 14-Dec-13

26-Dec-13

T+16ER26130

DCW / DHW & CCW riser

12 21-Dec-13

04-Jan-14

T+16ER26140

Sanitary riser

12 21-Dec-13

04-Jan-14

T+16ER26150

Hang FCU

12 21-Dec-13

04-Jan-14

T+16ER26160

Ductwork - supply, make-up air & extract

12 21-Dec-13

04-Jan-14

T+16ER26170

CW supply / return & condensate

12 24-Dec-13

07-Jan-14

T+16ER26180

Plumbing & san distribution

12 25-Dec-13

08-Jan-14

T+16ER26190

FCU connections

12 29-Dec-13

12-Jan-14

T+16ER26200

Cable tray / trunking

12 30-Dec-13

13-Jan-14

T+16ER26220

Test risers ( 3floors vertically )

12 02-Jan-14

15-Jan-14

T+16ER26210

Sprinkler pipes ( Not drops ) from corridor

12 04-Jan-14

16-Jan-14

T+16ER26230

MEP sign off risers (Start)

15-Jan-14

MEP Drops in walls & back boxes

66 07-Jan-14
66 07-Jan-14
12 07-Jan-14

T+16ER26250

Insulate & board walls

12 12-Jan-14

25-Jan-14

T+16ER26260

Ceiling 1st fix

18 16-Jan-14

05-Feb-14

T+16ER26270

Wiring

12 21-Jan-14

03-Feb-14

T+16ER26280

MEP drops in ceiling

12 25-Jan-14

06-Feb-14

T+16ER26290

Board ceiling

12 26-Jan-14

08-Feb-14

T+16ER26300

Tape & Joint walls & ceiling

12 30-Jan-14

12-Feb-14

T+16ER26310

Mist coat all dry lining

12 04-Feb-14

17-Feb-14

T+16ER26320

Install cornice

12 06-Feb-14

19-Feb-14

T+16ER26330

Paint ceiling and cornice

12 11-Feb-14

24-Feb-14

T+16ER26340

Wall covering

12 16-Feb-14

01-Mar-14

T+16ER26350

Install furniture

12 20-Feb-14

05-Mar-14

T+16ER26360

MEP terminations in furniture

12 25-Feb-14

10-Mar-14

T+16ER26370

MEP 3rd fix- sockets, cover plates etc

12 04-Mar-14

17-Mar-14

T+16ER26760

Underlay & Carpet

6 18-Mar-14

24-Mar-14

65 23-Jan-14

08-Apr-14

Bedroom
No DISP
T+16ER26240

Bathroom
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 46 of 180

24-Mar-14
24-Mar-14
20-Jan-14

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

Stud to block walls

65 23-Jan-14
12 23-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
08-Apr-14
05-Feb-14

T+16ER26390

Waterproof bathroom

12 26-Jan-14

08-Feb-14

T+16ER26400

Flood test

12 02-Feb-14

15-Feb-14

T+16ER26410

MEP Drops in walls & back boxes

12 09-Feb-14

22-Feb-14

T+16ER26420

Install bath

12 11-Feb-14

24-Feb-14

T+16ER26430

Insulate & board walls

12 13-Feb-14

26-Feb-14

T+16ER26440

Framing & board for bath

12 13-Feb-14

26-Feb-14

T+16ER26450

First fix ceiling

12 16-Feb-14

01-Mar-14

T+16ER26460

MEP drops in ceiling

12 18-Feb-14

03-Mar-14

T+16ER26470

2nd fix ceiling incl access panel

12 19-Feb-14

04-Mar-14

T+16ER26480

Install corniche

12 22-Feb-14

06-Mar-14

T+16ER26490

Stone to floors

12 03-Mar-14

16-Mar-14

T+16ER26500

Stone surround to bath

12 03-Mar-14

16-Mar-14

T+16ER26510

Stone vanity

12 03-Mar-14

16-Mar-14

T+16ER26520

Stone to walls incl niche

12 03-Mar-14

16-Mar-14

T+16ER26530

Casing stone

12 03-Mar-14

16-Mar-14

T+16ER26540

Grout to all stone

12 03-Mar-14

16-Mar-14

T+16ER26550

Glass Partition

12 17-Mar-14

30-Mar-14

T+16ER26560

Install and connect " Free issue " mirror

12 18-Mar-14

31-Mar-14

T+16ER26570

Sanitary ware and accessories

12 20-Mar-14

02-Apr-14

T+16ER26580

MEP connections to bath and basin

12 22-Mar-14

03-Apr-14

T+16ER26590

MEP 3rd fix - switch / socket covers

12 24-Mar-14

06-Apr-14

T+16ER26600

Hang glass doors

12 26-Mar-14

08-Apr-14

42 16-Feb-14
42 16-Feb-14
12 16-Feb-14

05-Apr-14
05-Apr-14
01-Mar-14

Activity ID

Activity Name

No DISP
T+16ER26380

Entrance Vestibule & dressing


No DISP
T+16ER26610 MEP drops in walls

Duration Start

T+16ER26620

Board walls

12 19-Feb-14

04-Mar-14

T+16ER26630

Ceiling 1st fix

12 22-Feb-14

06-Mar-14

T+16ER26640

MEP drops in ceiling

12 24-Feb-14

09-Mar-14

T+16ER26650

Board ceiling incl access panel

12 27-Feb-14

12-Mar-14

T+16ER26670

Tape & joint walls & ceilings

12 02-Mar-14

15-Mar-14

T+16ER26680

Mist coat dry lining

12 03-Mar-14

16-Mar-14

T+16ER26690

Paint ceiling

12 05-Mar-14

18-Mar-14

T+16ER26700

Stone flooring incl grout

12 10-Mar-14

23-Mar-14

T+16ER26710

Pocket door to bathroom

12 16-Mar-14

29-Mar-14

T+16ER26720

Entrance door - Temporary

12 16-Mar-14

29-Mar-14

T+16ER26730

Install wardrobe

12 17-Mar-14

30-Mar-14

T+16ER26740

Wall Coverings

12 19-Mar-14

01-Apr-14

T+16ER26750

3rd fix MEP

12 23-Mar-14

05-Apr-14

24 09-Apr-14
24 09-Apr-14
3 09-Apr-14

06-May-14
06-May-14
12-Apr-14

Pier Corridors & Lift Lobby


No DISP
E+16GR620
Installation of Flexibles / Plenum
E+16GR640

3 09-Apr-14

12-Apr-14

E+16GR17360 Gypsum Ceilings

Sprinkler Drops

6 13-Apr-14

19-Apr-14

E+16GR17400 Paint Ceiling

4 20-Apr-14

23-Apr-14

E+16GR17390 Millwork

6 24-Apr-14

30-Apr-14

E+16GR17380 Wall Covering & fabric panels

4 27-Apr-14

30-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 47 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

E+16GR660

Light Fittings Installation

2 01-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
03-May-14

E+16GR670

Sprinkler Installation

2 01-May-14

03-May-14

3 04-May-14

06-May-14

Activity ID

Activity Name

E+16GR17410 Underlay & Carpet


Guestrooms
Bedroom
No DISP
T+16GU20300

Paint ceiling and cornice

Duration Start

146
93
93
12

19-Oct-13 A
20-Oct-13 A
20-Oct-13 A
20-Oct-13 A

20-Apr-14
26-Feb-14
26-Feb-14
26-Nov-13

T+16GU20310

Wall covering

12 31-Dec-13

14-Jan-14

T+16GU20320

Install furniture

12 06-Jan-14

19-Jan-14

T+16GU20330

MEP terminations in furniture

12 13-Jan-14

26-Jan-14

T+16GU20340

MEP 3rd fix- sockets, cover plates etc

12 16-Jan-14

29-Jan-14

T+16GU17980

Underlay & Carpet

12 13-Feb-14

26-Feb-14
09-Mar-14
09-Mar-14
23-Dec-13

Stone to floors

76 10-Dec-13
76 10-Dec-13
12 10-Dec-13

T+16GU22100

Stone surround to bath

12 10-Dec-13

23-Dec-13

T+16GU22110

Stone vanity

12 10-Dec-13

23-Dec-13

T+16GU22120

Stone to walls incl niche

12 10-Dec-13

23-Dec-13

T+16GU22130

Casing stone

12 10-Dec-13

23-Dec-13

T+16GU22140

Grout to all stone

12 17-Dec-13

30-Dec-13

T+16GU22080

Install corniche

12 24-Dec-13

07-Jan-14

T+16GU24820

Vanity S/S & Mirrors

12 24-Dec-13

07-Jan-14

T+16GU24830

Vanity Unit

12 24-Dec-13

07-Jan-14

T+16GU22150

Glass Partition

12 31-Dec-13

14-Jan-14

T+16GU22200

Hang glass doors

12 06-Jan-14

19-Jan-14

T+16GU18120

Wall covering

12 09-Jan-14

22-Jan-14

T+16GU22160

Install and connect " Free issue " mirror

12 18-Feb-14

03-Mar-14

T+16GU22170

Sanitary ware and accessories

12 20-Feb-14

05-Mar-14

T+16GU22180

MEP connections to bath and basin

12 22-Feb-14

06-Mar-14

T+16GU22190

MEP 3rd fix - switch / socket covers

12 24-Feb-14

09-Mar-14

137 19-Oct-13 A
137 19-Oct-13 A
12 16-Nov-13

09-Apr-14
09-Apr-14
28-Nov-13

6 19-Oct-13 A

17-Nov-13

Bathroom
No DISP
T+16GU22090

Entrance Vestibule & dressing


No DISP
T+16GU24710 Door frames
T+16GU24700

Board ceiling incl access panel

T+16GU24720

Tape & joint walls & ceilings

12 16-Nov-13

28-Nov-13

T+16GU24730

Mist coat dry lining

12 30-Nov-13

14-Dec-13

T+16GU24740

Paint ceiling

12 03-Dec-13

16-Dec-13

T+16GU24750

Stone flooring incl grout

12 10-Dec-13

23-Dec-13

T+16GU24780

Install wardrobe

12 24-Dec-13

07-Jan-14

T+16GU24770

Mirrors

12 08-Jan-14

21-Jan-14

T+16GU24790

Wall Coverings

12 09-Jan-14

22-Jan-14

T+16GU24800

3rd fix MEP

12 22-Jan-14

04-Feb-14

T+16GU24760

Pocket door to bathroom

Corridor
No DISP
T+16GR17350

Gypsum Walls

12 27-Mar-14

09-Apr-14

132 16-Nov-13
132 16-Nov-13
6 16-Nov-13

20-Apr-14
20-Apr-14
21-Nov-13

T+16GR620

Installation of Flexibles / Plenum

8 06-Mar-14

15-Mar-14

T+16GR640

Sprinkler Drops

6 09-Mar-14

15-Mar-14

T+16GR17360

Gypsum Ceilings

6 09-Mar-14

15-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 48 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+16GR680

Grilles / Diffuser Installation

7 16-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
23-Mar-14

T+16GR17370

T & J Walls & Ceilings

6 16-Mar-14

22-Mar-14

T+16GR17400

Paint Ceiling

4 23-Mar-14

26-Mar-14

T+16GR17390

Millwork

10 27-Mar-14

07-Apr-14

T+16GR17380

Wall Covering

4 08-Apr-14

12-Apr-14

T+16GR17420

Mirrors

3 08-Apr-14

10-Apr-14

T+16GR660

Light Fittings Installation

4 13-Apr-14

16-Apr-14

T+16GR690

FA / SD installation

4 13-Apr-14

16-Apr-14

T+16GR670

Sprinkler Installation

4 13-Apr-14

16-Apr-14

T+16GR17410

Underlay & Carpet

3 17-Apr-14

20-Apr-14

185 06-Oct-13 A

14-May-14

136
29
3
3

30-Nov-13
18-Dec-13
19-Jan-14
19-Jan-14

08-May-14
21-Jan-14
21-Jan-14
21-Jan-14

3 19-Jan-14

21-Jan-14

20 18-Dec-13
3 18-Dec-13

11-Jan-14
21-Dec-13

T+17WR26780 Busbar installation & connection

2 22-Dec-13

23-Dec-13

T+17WR26820 Install IT Panels

2 22-Dec-13

23-Dec-13

T+17WR26830 Install Security Panels

2 22-Dec-13

23-Dec-13

T+17WR26790 Duckwork branch to room

2 24-Dec-13

25-Dec-13

T+17WR26800 Fire alarm cabling

3 26-Dec-13

29-Dec-13

T+17WR26810 Cable terminations

10 30-Dec-13

11-Jan-14

6 12-Jan-14
2 12-Jan-14

18-Jan-14
13-Jan-14

2 14-Jan-14

15-Jan-14

Activity ID

Activity Name

+17 @ +78.00
West Core
Electrical/Telecom Room
Finishes
T+17WR26870 RMX - 01 to floor
T+17WR26880 Permanent door
1st & 2nd Fix
T+17WR26890 Electrical Containment

MEP Final Fix


T+17WR26840 Grills & diffusers
T+17WR26850 Fire alarm devices
T+17WR26860 Light fittings

Duration Start

2 16-Jan-14

18-Jan-14

Finishes - 1st Fix


No DISP
T+17WR26060 Studwork incl noggins

52 30-Nov-13
52 30-Nov-13
12 30-Nov-13

30-Jan-14
30-Jan-14
14-Dec-13

T+17WR26070 Close blockwork risers

12 18-Jan-14

30-Jan-14

MEP riser summary


No DISP
T+17WR26080 MEP risers & 1st fix

12 08-Dec-13
12 08-Dec-13
12 08-Dec-13

21-Dec-13
21-Dec-13
21-Dec-13

MEP Risers & First Fix


No DISP
T+17WR26110 Ductworks risers

35 08-Dec-13
35 08-Dec-13
12 08-Dec-13

18-Jan-14
18-Jan-14
21-Dec-13

T+17WR26120 Chilled water & condensate

12 15-Dec-13

28-Dec-13

T+17WR26130 DCW / DHW & CCW riser

12 22-Dec-13

05-Jan-14

T+17WR26140 Sanitary riser

12 22-Dec-13

05-Jan-14

T+17WR26150 Hang FCU

12 22-Dec-13

05-Jan-14

T+17WR26160 Ductwork - supply, make-up air & extract

12 22-Dec-13

05-Jan-14

T+17WR26170 CW supply / return & condensate

12 25-Dec-13

08-Jan-14

T+17WR26180 Plumbing & san distribution

12 26-Dec-13

09-Jan-14

T+17WR26190 FCU connections

12 30-Dec-13

13-Jan-14

T+17WR26200 Cable tray / trunking

12 31-Dec-13

14-Jan-14

T+17WR26220 Test risers ( 3floors vertically )

12 04-Jan-14

16-Jan-14

T+17WR26210 Sprinkler pipes ( Not drops ) from corridor

12 05-Jan-14

18-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 49 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+17WR26230 MEP sign off risers (Start)

Duration Start

03-Apr-14
03-Apr-14
21-Jan-14

T+17WR26250 Insulate & board walls

12 22-Jan-14

04-Feb-14

T+17WR26260 Ceiling 1st fix

18 27-Jan-14

16-Feb-14

T+17WR26270 Wiring

12 01-Feb-14

13-Feb-14

T+17WR26280 MEP drops in ceiling

12 04-Feb-14

17-Feb-14

T+17WR26290 Board ceiling

12 05-Feb-14

18-Feb-14

T+17WR26300 Tape & Joint walls & ceiling

12 10-Feb-14

23-Feb-14

T+17WR26310 Mist coat all dry lining

12 15-Feb-14

27-Feb-14

T+17WR26320 Install cornice

12 17-Feb-14

02-Mar-14

T+17WR26330 Paint ceiling and cornice

12 22-Feb-14

06-Mar-14

T+17WR26340 Wall covering

12 26-Feb-14

11-Mar-14

T+17WR26350 Install furniture

12 03-Mar-14

16-Mar-14

T+17WR26360 MEP terminations in furniture

12 08-Mar-14

20-Mar-14

T+17WR26370 MEP 3rd fix- sockets, cover plates etc

12 15-Mar-14

27-Mar-14

T+17WR26760 Underlay & Carpet

6 29-Mar-14

03-Apr-14

Bathroom
No DISP
T+17WR26380 Stud to block walls

64 25-Jan-14
64 25-Jan-14
12 25-Jan-14

08-Apr-14
08-Apr-14
06-Feb-14

T+17WR26390 Waterproof bathroom

12 27-Jan-14

09-Feb-14

T+17WR26400 Flood test

12 03-Feb-14

16-Feb-14

T+17WR26410 MEP Drops in walls & back boxes

12 12-Feb-14

25-Feb-14

T+17WR26420 Install bath

12 12-Feb-14

25-Feb-14

T+17WR26430 Insulate & board walls

12 15-Feb-14

27-Feb-14

T+17WR26440 Framing & board for bath

12 15-Feb-14

27-Feb-14

T+17WR26450 First fix ceiling

12 17-Feb-14

02-Mar-14

T+17WR26460 MEP drops in ceiling

12 19-Feb-14

04-Mar-14

T+17WR26470 2nd fix ceiling incl access panel

12 20-Feb-14

05-Mar-14

T+17WR26480 Install corniche

12 23-Feb-14

08-Mar-14

T+17WR26490 Stone to floors

12 03-Mar-14

16-Mar-14

T+17WR26500 Stone surround to bath

12 03-Mar-14

16-Mar-14

T+17WR26510 Stone vanity

12 03-Mar-14

16-Mar-14

T+17WR26520 Stone to walls incl niche

12 03-Mar-14

16-Mar-14

T+17WR26530 Casing stone

12 03-Mar-14

16-Mar-14

T+17WR26540 Grout to all stone

12 03-Mar-14

16-Mar-14

T+17WR26550 Glass Partition

12 17-Mar-14

30-Mar-14

T+17WR26560 Install and connect " Free issue " mirror

12 18-Mar-14

31-Mar-14

T+17WR26570 Sanitary ware and accessories

12 20-Mar-14

02-Apr-14

T+17WR26580 MEP connections to bath and basin

12 22-Mar-14

03-Apr-14

T+17WR26590 MEP 3rd fix - switch / socket covers

12 24-Mar-14

06-Apr-14

T+17WR26600 Hang glass doors

12 26-Mar-14

08-Apr-14

Entrance Vestibule & dressing


No DISP
T+17WR26610 MEP drops in walls

39 19-Feb-14
39 19-Feb-14
12 19-Feb-14

05-Apr-14
05-Apr-14
04-Mar-14

T+17WR26620 Board walls

12 23-Feb-14

08-Mar-14

T+17WR26630 Ceiling 1st fix

12 25-Feb-14

10-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 50 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
16-Jan-14

74 08-Jan-14
74 08-Jan-14
12 08-Jan-14

Bedroom
No DISP
T+17WR26240 MEP Drops in walls & back boxes

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+17WR26640 MEP drops in ceiling

12 27-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-Mar-14

T+17WR26650 Board ceiling incl access panel

12 03-Mar-14

16-Mar-14

T+17WR26670 Tape & joint walls & ceilings

12 05-Mar-14

18-Mar-14

T+17WR26680 Mist coat dry lining

12 06-Mar-14

19-Mar-14

T+17WR26690 Paint ceiling

12 09-Mar-14

22-Mar-14

T+17WR26700 Stone flooring incl grout

12 10-Mar-14

23-Mar-14

T+17WR26710 Pocket door to bathroom

12 16-Mar-14

29-Mar-14

T+17WR26720 Entrance door - Temporary

12 16-Mar-14

29-Mar-14

T+17WR26730 Install wardrobe

12 17-Mar-14

30-Mar-14

T+17WR26740 Wall Coverings

12 19-Mar-14

01-Apr-14

T+17WR26750 3rd fix MEP

12 23-Mar-14

05-Apr-14

26 09-Apr-14
26 09-Apr-14
3 09-Apr-14

08-May-14
08-May-14
12-Apr-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+17GR620
Installation of Flexibles / Plenum
W+17GR640

Sprinkler Drops

Duration Start

3 09-Apr-14

12-Apr-14

W+17GR17360 Gypsum Ceilings

6 13-Apr-14

19-Apr-14

W+17GR17400 Paint Ceiling

2 20-Apr-14

21-Apr-14

W+17GR17390 Millwork

6 22-Apr-14

28-Apr-14

W+17GR17380 Wall Covering & fabric panels

4 29-Apr-14

03-May-14

W+17GR660

Light Fittings Installation

2 04-May-14

05-May-14

W+17GR670

Sprinkler Installation

2 04-May-14

05-May-14

3 06-May-14

08-May-14

W+17GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+17ER26020 Blockwork to wall full height

185
107
107
20

06-Oct-13 A
06-Oct-13 A
06-Oct-13 A
06-Oct-13 A

14-May-14
12-Feb-14
12-Feb-14
24-Nov-13

T+17ER26060

Studwork incl noggins

12 30-Nov-13

14-Dec-13

T+17ER26070

Close blockwork risers

12 30-Jan-14

12-Feb-14

MEP riser summary


No DISP
T+17ER26080 MEP risers & 1st fix

12 21-Dec-13
12 21-Dec-13
12 21-Dec-13

04-Jan-14
04-Jan-14
04-Jan-14

MEP Risers & First Fix


No DISP
T+17ER26110 Ductworks risers

35 21-Dec-13
35 21-Dec-13
12 21-Dec-13

30-Jan-14
30-Jan-14
04-Jan-14

T+17ER26120

Chilled water & condensate

12 28-Dec-13

11-Jan-14

T+17ER26130

DCW / DHW & CCW riser

12 05-Jan-14

18-Jan-14

T+17ER26140

Sanitary riser

12 05-Jan-14

18-Jan-14

T+17ER26150

Hang FCU

12 05-Jan-14

18-Jan-14

T+17ER26160

Ductwork - supply, make-up air & extract

12 05-Jan-14

18-Jan-14

T+17ER26170

CW supply / return & condensate

12 08-Jan-14

21-Jan-14

T+17ER26180

Plumbing & san distribution

12 09-Jan-14

22-Jan-14

T+17ER26190

FCU connections

12 13-Jan-14

26-Jan-14

T+17ER26200

Cable tray / trunking

12 14-Jan-14

27-Jan-14

T+17ER26220

Test risers ( 3floors vertically )

12 16-Jan-14

29-Jan-14

T+17ER26210

Sprinkler pipes ( Not drops ) from corridor

12 18-Jan-14

30-Jan-14

T+17ER26230

MEP sign off risers (Start)

Bedroom
No DISP
T+17ER26240

MEP Drops in walls & back boxes

0
80 21-Jan-14
80 21-Jan-14
12 21-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 51 of 180

29-Jan-14
23-Apr-14
23-Apr-14
03-Feb-14
Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+17ER26250

Insulate & board walls

12 04-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
17-Feb-14

T+17ER26260

Ceiling 1st fix

18 09-Feb-14

01-Mar-14

T+17ER26270

Wiring

12 13-Feb-14

26-Feb-14

T+17ER26280

MEP drops in ceiling

12 17-Feb-14

02-Mar-14

T+17ER26290

Board ceiling

12 18-Feb-14

03-Mar-14

T+17ER26300

Tape & Joint walls & ceiling

12 23-Feb-14

08-Mar-14

T+17ER26310

Mist coat all dry lining

12 27-Feb-14

12-Mar-14

T+17ER26320

Install cornice

12 02-Mar-14

15-Mar-14

T+17ER26330

Paint ceiling and cornice

12 06-Mar-14

19-Mar-14

T+17ER26340

Wall covering

12 18-Mar-14

31-Mar-14

T+17ER26350

Install furniture

12 23-Mar-14

05-Apr-14

T+17ER26360

MEP terminations in furniture

12 27-Mar-14

09-Apr-14

T+17ER26370

MEP 3rd fix- sockets, cover plates etc

12 03-Apr-14

16-Apr-14

T+17ER26760

Underlay & Carpet

6 17-Apr-14

23-Apr-14
15-Apr-14
15-Apr-14
19-Feb-14

Activity ID

Activity Name

Duration Start

Stud to block walls

59 06-Feb-14
59 06-Feb-14
12 06-Feb-14

T+17ER26390

Waterproof bathroom

12 09-Feb-14

22-Feb-14

T+17ER26400

Flood test

12 16-Feb-14

01-Mar-14

T+17ER26410

MEP Drops in walls & back boxes

12 25-Feb-14

10-Mar-14

T+17ER26420

Install bath

12 25-Feb-14

10-Mar-14

T+17ER26430

Insulate & board walls

12 27-Feb-14

12-Mar-14

T+17ER26440

Framing & board for bath

12 27-Feb-14

12-Mar-14

T+17ER26450

First fix ceiling

12 02-Mar-14

15-Mar-14

T+17ER26460

MEP drops in ceiling

12 04-Mar-14

17-Mar-14

T+17ER26470

2nd fix ceiling incl access panel

12 05-Mar-14

18-Mar-14

T+17ER26480

Install corniche

12 08-Mar-14

20-Mar-14

T+17ER26490

Stone to floors

12 10-Mar-14

23-Mar-14

T+17ER26500

Stone surround to bath

12 10-Mar-14

23-Mar-14

T+17ER26510

Stone vanity

12 10-Mar-14

23-Mar-14

T+17ER26520

Stone to walls incl niche

12 10-Mar-14

23-Mar-14

T+17ER26530

Casing stone

12 10-Mar-14

23-Mar-14

T+17ER26540

Grout to all stone

12 10-Mar-14

23-Mar-14

T+17ER26550

Glass Partition

12 24-Mar-14

06-Apr-14

T+17ER26560

Install and connect " Free issue " mirror

12 25-Mar-14

07-Apr-14

T+17ER26570

Sanitary ware and accessories

12 27-Mar-14

09-Apr-14

T+17ER26580

MEP connections to bath and basin

12 29-Mar-14

10-Apr-14

T+17ER26590

MEP 3rd fix - switch / socket covers

12 31-Mar-14

13-Apr-14

T+17ER26600

Hang glass doors

12 02-Apr-14

15-Apr-14

34 04-Mar-14
34 04-Mar-14
12 04-Mar-14

12-Apr-14
12-Apr-14
17-Mar-14

Bathroom
No DISP
T+17ER26380

Entrance Vestibule & dressing


No DISP
T+17ER26610 MEP drops in walls
T+17ER26620

Board walls

12 08-Mar-14

20-Mar-14

T+17ER26630

Ceiling 1st fix

12 10-Mar-14

23-Mar-14

T+17ER26640

MEP drops in ceiling

12 12-Mar-14

25-Mar-14

T+17ER26650

Board ceiling incl access panel

12 16-Mar-14

29-Mar-14

T+17ER26700

Stone flooring incl grout

12 17-Mar-14

30-Mar-14

T+17ER26670

Tape & joint walls & ceilings

12 18-Mar-14

31-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 52 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+17ER26680

Mist coat dry lining

12 19-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
01-Apr-14

T+17ER26690

Paint ceiling

12 22-Mar-14

03-Apr-14

T+17ER26710

Pocket door to bathroom

12 23-Mar-14

05-Apr-14

T+17ER26720

Entrance door - Temporary

12 23-Mar-14

05-Apr-14

T+17ER26730

Install wardrobe

12 24-Mar-14

06-Apr-14

T+17ER26740

Wall Coverings

12 26-Mar-14

08-Apr-14

T+17ER26750

3rd fix MEP

12 30-Mar-14

12-Apr-14

24 17-Apr-14
24 17-Apr-14
3 17-Apr-14

14-May-14
14-May-14
20-Apr-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
E+17GR620
Installation of Flexibles / Plenum
E+17GR640

Sprinkler Drops

Duration Start

3 17-Apr-14

20-Apr-14

E+17GR17360 Gypsum Ceilings

6 21-Apr-14

27-Apr-14

E+17GR17400 Paint Ceiling

4 28-Apr-14

01-May-14

E+17GR17390 Millwork

6 03-May-14

08-May-14

E+17GR17380 Wall Covering & fabric panels

4 05-May-14

08-May-14

E+17GR660

Light Fittings Installation

2 10-May-14

11-May-14

E+17GR670

Sprinkler Installation

2 10-May-14

11-May-14

3 12-May-14

14-May-14

E+17GR17410 Underlay & Carpet


Guestrooms
Bedroom
No DISP
T+17GU20410

Tape & Joint walls & ceiling

138
93
93
12

17-Oct-13 A
17-Oct-13 A
17-Oct-13 A
17-Oct-13 A

27-Apr-14
05-Mar-14
05-Mar-14
16-Nov-13

T+17GU20420

Mist coat all dry lining

12 20-Oct-13 A

17-Nov-13

T+17GU20430

Install cornice

12 21-Oct-13 A

24-Nov-13

T+17GU20440

Paint ceiling and cornice

12 16-Nov-13

28-Nov-13

T+17GU20450

Wall covering

12 08-Jan-14

21-Jan-14

T+17GU20460

Install furniture

12 13-Jan-14

26-Jan-14

T+17GU20470

MEP terminations in furniture

12 20-Jan-14

02-Feb-14

T+17GU20480

MEP 3rd fix- sockets, cover plates etc

12 23-Jan-14

05-Feb-14

T+17GU24821

Underlay & Carpet

12 20-Feb-14

05-Mar-14

102 16-Nov-13
102 16-Nov-13
12 16-Nov-13

16-Mar-14
16-Mar-14
28-Nov-13

Bathroom
No DISP
T+17GU22300

2nd fix ceiling incl access panel

T+17GU22250

Install bath

12 16-Nov-13

28-Nov-13

T+17GU22270

Framing & board for bath

12 18-Nov-13

01-Dec-13

T+17GU22310

Install corniche

12 18-Nov-13

01-Dec-13

T+17GU22320

Stone to floors

12 16-Dec-13

29-Dec-13

T+17GU22330

Stone surround to bath

12 16-Dec-13

29-Dec-13

T+17GU22340

Stone vanity

12 16-Dec-13

29-Dec-13

T+17GU22350

Stone to walls incl niche

12 16-Dec-13

29-Dec-13

T+17GU22360

Casing stone

12 16-Dec-13

29-Dec-13

T+17GU22370

Grout to all stone

12 23-Dec-13

06-Jan-14

T+17GU24970

Vanity S/S & Mirrors

12 30-Dec-13

13-Jan-14

T+17GU24980

Vanity Unit

12 30-Dec-13

13-Jan-14

T+17GU22380

Glass Partition

12 07-Jan-14

20-Jan-14

T+17GU22430

Hang glass doors

12 07-Jan-14

20-Jan-14

T+17GU18120

Wall covering

12 16-Jan-14

29-Jan-14

T+17GU22390

Install and connect " Free issue " mirror

12 25-Feb-14

10-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 53 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+17GU22400

Sanitary ware and accessories

12 27-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-Mar-14

T+17GU22410

MEP connections to bath and basin

12 01-Mar-14

13-Mar-14

T+17GU22420

MEP 3rd fix - switch / socket covers

12 03-Mar-14

16-Mar-14

104 16-Dec-13
104 16-Dec-13
12 16-Dec-13

16-Apr-14
16-Apr-14
29-Dec-13

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+17GU24900 Stone flooring incl grout

Duration Start

T+17GU24850

Board ceiling incl access panel

12 30-Dec-13

13-Jan-14

T+17GU24860

Door frames

12 02-Jan-14

15-Jan-14

T+17GU24870

Tape & joint walls & ceilings

12 02-Jan-14

15-Jan-14

T+17GU24880

Mist coat dry lining

12 04-Jan-14

16-Jan-14

T+17GU24890

Paint ceiling

12 06-Jan-14

19-Jan-14

T+17GU24930

Install wardrobe

12 20-Jan-14

02-Feb-14

T+17GU24940

Wall Coverings

12 22-Jan-14

04-Feb-14

T+17GU24920

Mirors

12 27-Jan-14

09-Feb-14

T+17GU24950

3rd fix MEP

12 03-Feb-14

16-Feb-14

T+17GU24910

Pocket door to bathroom

12 03-Apr-14

16-Apr-14

132 23-Nov-13
132 23-Nov-13
6 23-Nov-13

27-Apr-14
27-Apr-14
28-Nov-13

Corridor
No DISP
T+17GR17350

Gypsum Walls

T+17GR620

Installation of Flexibles / Plenum

8 13-Mar-14

22-Mar-14

T+17GR640

Sprinkler Drops

6 16-Mar-14

22-Mar-14

T+17GR17360

Gypsum Ceilings

6 16-Mar-14

22-Mar-14

T+17GR680

Grilles / Diffuser Installation

4 23-Mar-14

26-Mar-14

T+17GR17370

T & J Walls & Ceilings

6 23-Mar-14

29-Mar-14

T+17GR17400

Paint Ceiling

4 30-Mar-14

02-Apr-14

T+17GR17390

Millwork

10 03-Apr-14

14-Apr-14

T+17GR17380

Wall Covering

4 15-Apr-14

19-Apr-14

T+17GR17420

Mirrors

3 15-Apr-14

17-Apr-14

T+17GR660

Light Fittings Installation

4 20-Apr-14

23-Apr-14

T+17GR690

FA / SD installation

4 20-Apr-14

23-Apr-14

T+17GR670

Sprinkler Installation

4 20-Apr-14

23-Apr-14

T+17GR17410

Underlay & Carpet

3 24-Apr-14

27-Apr-14

155 09-Oct-13 A

11-May-14

132
29
3
3

08-Dec-13
22-Dec-13
22-Jan-14
22-Jan-14

11-May-14
25-Jan-14
25-Jan-14
25-Jan-14

3 22-Jan-14

25-Jan-14

20 22-Dec-13
3 22-Dec-13

14-Jan-14
24-Dec-13

T+18WR26780 Busbar installation & connection

2 25-Dec-13

26-Dec-13

T+18WR26820 Install IT Panels

2 25-Dec-13

26-Dec-13

T+18WR26830 Install Security Panels

2 25-Dec-13

26-Dec-13

T+18WR26790 Duckwork branch to room

2 28-Dec-13

29-Dec-13

+18 @ +81.80
West Core
Electrical/Telecom Room
Finishes
T+18WR26870 RMX - 01 to floor
T+18WR26880 Permanent door
1st & 2nd Fix
T+18WR26890 Electrical Containment

T+18WR26800 Fire alarm cabling


T+18WR26810 Cable terminations
MEP Final Fix
T+18WR26840 Grills & diffusers
T+18WR26850 Fire alarm devices

3 30-Dec-13

02-Jan-14

10 04-Jan-14

14-Jan-14

6 15-Jan-14
2 15-Jan-14

21-Jan-14
16-Jan-14

2 18-Jan-14

19-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 54 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+18WR26860 Light fittings

Duration Start

2 20-Jan-14
52 08-Dec-13
52 08-Dec-13
12 08-Dec-13

06-Feb-14
06-Feb-14
21-Dec-13

T+18WR26070 Close blockwork risers

12 25-Jan-14

06-Feb-14

MEP riser summary


No DISP
T+18WR26080 MEP risers & 1st fix

12 15-Dec-13
12 15-Dec-13
12 15-Dec-13

28-Dec-13
28-Dec-13
28-Dec-13

MEP Risers & First Fix


No DISP
T+18WR26110 Ductworks risers

35 15-Dec-13
35 15-Dec-13
12 15-Dec-13

25-Jan-14
25-Jan-14
28-Dec-13

T+18WR26120 Chilled water & condensate

12 22-Dec-13

05-Jan-14

T+18WR26130 DCW / DHW & CCW riser

12 29-Dec-13

12-Jan-14

T+18WR26140 Sanitary riser

12 29-Dec-13

12-Jan-14

T+18WR26150 Hang FCU

12 29-Dec-13

12-Jan-14

T+18WR26160 Ductwork - supply, make-up air & extract

12 29-Dec-13

12-Jan-14

T+18WR26170 CW supply / return & condensate

12 02-Jan-14

15-Jan-14

T+18WR26180 Plumbing & san distribution

12 04-Jan-14

16-Jan-14

T+18WR26190 FCU connections

12 07-Jan-14

20-Jan-14

T+18WR26200 Cable tray / trunking

12 08-Jan-14

21-Jan-14

T+18WR26220 Test risers ( 3floors vertically )

12 11-Jan-14

23-Jan-14

T+18WR26210 Sprinkler pipes ( Not drops ) from corridor

12 12-Jan-14

25-Jan-14

01-Apr-14
01-Apr-14
28-Jan-14

T+18WR26250 Insulate & board walls

12 20-Jan-14

02-Feb-14

T+18WR26260 Ceiling 1st fix

18 25-Jan-14

13-Feb-14

T+18WR26270 Wiring

12 29-Jan-14

11-Feb-14

T+18WR26280 MEP drops in ceiling

12 02-Feb-14

15-Feb-14

T+18WR26290 Board ceiling

12 03-Feb-14

16-Feb-14

T+18WR26300 Tape & Joint walls & ceiling

12 08-Feb-14

20-Feb-14

T+18WR26310 Mist coat all dry lining

12 12-Feb-14

25-Feb-14

T+18WR26320 Install cornice

12 15-Feb-14

27-Feb-14

T+18WR26330 Paint ceiling and cornice

12 19-Feb-14

04-Mar-14

T+18WR26340 Wall covering

12 24-Feb-14

09-Mar-14

T+18WR26350 Install furniture

12 01-Mar-14

13-Mar-14

T+18WR26360 MEP terminations in furniture

12 05-Mar-14

18-Mar-14

T+18WR26370 MEP 3rd fix- sockets, cover plates etc

12 12-Mar-14

25-Mar-14

T+18WR26760 Underlay & Carpet

6 26-Mar-14

01-Apr-14

Bathroom
No DISP
T+18WR26380 Stud to block walls

64 01-Feb-14
64 01-Feb-14
12 01-Feb-14

15-Apr-14
15-Apr-14
13-Feb-14

T+18WR26390 Waterproof bathroom

12 03-Feb-14

16-Feb-14

T+18WR26400 Flood test

12 10-Feb-14

23-Feb-14

T+18WR26410 MEP Drops in walls & back boxes

12 19-Feb-14

04-Mar-14

T+18WR26420 Install bath

12 19-Feb-14

04-Mar-14

T+18WR26430 Insulate & board walls

12 22-Feb-14

06-Mar-14

T+18WR26440 Framing & board for bath

12 22-Feb-14

06-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 55 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

23-Jan-14

66 15-Jan-14
66 15-Jan-14
12 15-Jan-14

Bedroom
No DISP
T+18WR26240 MEP Drops in walls & back boxes

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
21-Jan-14

Finishes - 1st Fix


No DISP
T+18WR26060 Studwork incl noggins

T+18WR26230 MEP sign off risers (Start)

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+18WR26450 First fix ceiling

12 24-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
09-Mar-14

T+18WR26460 MEP drops in ceiling

12 26-Feb-14

11-Mar-14

T+18WR26470 2nd fix ceiling incl access panel

12 27-Feb-14

12-Mar-14

T+18WR26480 Install corniche

12 02-Mar-14

15-Mar-14

T+18WR26490 Stone to floors

12 10-Mar-14

23-Mar-14

T+18WR26500 Stone surround to bath

12 10-Mar-14

23-Mar-14

T+18WR26510 Stone vanity

12 10-Mar-14

23-Mar-14

T+18WR26520 Stone to walls incl niche

12 10-Mar-14

23-Mar-14

T+18WR26530 Casing stone

12 10-Mar-14

23-Mar-14

T+18WR26540 Grout to all stone

12 10-Mar-14

23-Mar-14

T+18WR26550 Glass Partition

12 24-Mar-14

06-Apr-14

T+18WR26560 Install and connect " Free issue " mirror

12 25-Mar-14

07-Apr-14

T+18WR26570 Sanitary ware and accessories

12 27-Mar-14

09-Apr-14

T+18WR26580 MEP connections to bath and basin

12 29-Mar-14

10-Apr-14

T+18WR26590 MEP 3rd fix - switch / socket covers

12 31-Mar-14

13-Apr-14

T+18WR26600 Hang glass doors

12 02-Apr-14

15-Apr-14

Entrance Vestibule & dressing


No DISP
T+18WR26610 MEP drops in walls

39 26-Feb-14
39 26-Feb-14
12 26-Feb-14

12-Apr-14
12-Apr-14
11-Mar-14

T+18WR26620 Board walls

12 02-Mar-14

15-Mar-14

T+18WR26630 Ceiling 1st fix

12 04-Mar-14

17-Mar-14

T+18WR26640 MEP drops in ceiling

12 06-Mar-14

19-Mar-14

T+18WR26650 Board ceiling incl access panel

12 10-Mar-14

23-Mar-14

T+18WR26670 Tape & joint walls & ceilings

12 12-Mar-14

25-Mar-14

T+18WR26680 Mist coat dry lining

12 13-Mar-14

26-Mar-14

T+18WR26690 Paint ceiling

12 16-Mar-14

29-Mar-14

T+18WR26700 Stone flooring incl grout

12 17-Mar-14

30-Mar-14

T+18WR26710 Pocket door to bathroom

12 23-Mar-14

05-Apr-14

T+18WR26720 Entrance door - Temporary

12 23-Mar-14

05-Apr-14

T+18WR26730 Install wardrobe

12 24-Mar-14

06-Apr-14

T+18WR26740 Wall Coverings

12 26-Mar-14

08-Apr-14

T+18WR26750 3rd fix MEP

12 30-Mar-14

12-Apr-14

22 16-Apr-14
22 16-Apr-14
3 16-Apr-14

11-May-14
11-May-14
19-Apr-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+18GR620
Installation of Flexibles / Plenum
W+18GR640

Sprinkler Drops

Duration Start

3 16-Apr-14

19-Apr-14

W+18GR17360 Gypsum Ceilings

6 20-Apr-14

26-Apr-14

W+18GR17400 Paint Ceiling

2 27-Apr-14

28-Apr-14

W+18GR17390 Millwork

6 29-Apr-14

05-May-14

W+18GR17380 Wall Covering & fabric panels

4 01-May-14

05-May-14

W+18GR660

Light Fittings Installation

2 06-May-14

07-May-14

W+18GR670

Sprinkler Installation

2 06-May-14

07-May-14

3 08-May-14

11-May-14

W+18GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+18ER26060 Studwork incl noggins
T+18ER26070

Close blockwork risers

MEP riser summary

127
63
63
12

08-Dec-13
08-Dec-13
08-Dec-13
08-Dec-13

05-May-14
19-Feb-14
19-Feb-14
21-Dec-13

12 06-Feb-14

19-Feb-14

12 28-Dec-13

11-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 56 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

No DISP
T+18ER26080

MEP risers & 1st fix

MEP Risers & First Fix


No DISP
T+18ER26110 Ductworks risers

06-Feb-14
06-Feb-14
11-Jan-14

12 05-Jan-14

18-Jan-14

DCW / DHW & CCW riser

12 12-Jan-14

25-Jan-14

T+18ER26140

Sanitary riser

12 12-Jan-14

25-Jan-14

T+18ER26150

Hang FCU

12 12-Jan-14

25-Jan-14

T+18ER26160

Ductwork - supply, make-up air & extract

12 12-Jan-14

25-Jan-14

T+18ER26170

CW supply / return & condensate

12 15-Jan-14

28-Jan-14

T+18ER26180

Plumbing & san distribution

12 16-Jan-14

29-Jan-14

T+18ER26190

FCU connections

12 20-Jan-14

02-Feb-14

T+18ER26200

Cable tray / trunking

12 21-Jan-14

03-Feb-14

T+18ER26220

Test risers ( 3floors vertically )

12 23-Jan-14

05-Feb-14

T+18ER26210

Sprinkler pipes ( Not drops ) from corridor

12 25-Jan-14

06-Feb-14

T+18ER26230

MEP sign off risers (Start)

05-Feb-14

MEP Drops in walls & back boxes

72 28-Jan-14
72 28-Jan-14
12 28-Jan-14

T+18ER26250

Insulate & board walls

12 02-Feb-14

15-Feb-14

T+18ER26260

Ceiling 1st fix

12 06-Feb-14

19-Feb-14

T+18ER26270

Wiring

12 11-Feb-14

24-Feb-14

T+18ER26280

MEP drops in ceiling

12 15-Feb-14

27-Feb-14

T+18ER26290

Board ceiling

12 16-Feb-14

01-Mar-14

T+18ER26300

Tape & Joint walls & ceiling

12 20-Feb-14

05-Mar-14

T+18ER26310

Mist coat all dry lining

12 25-Feb-14

10-Mar-14

T+18ER26320

Install cornice

12 27-Feb-14

12-Mar-14

T+18ER26330

Paint ceiling and cornice

12 04-Mar-14

17-Mar-14

T+18ER26340

Wall covering

6 16-Mar-14

22-Mar-14

T+18ER26350

Install furniture

12 20-Mar-14

02-Apr-14

T+18ER26360

MEP terminations in furniture

12 25-Mar-14

07-Apr-14

T+18ER26370

MEP 3rd fix- sockets, cover plates etc

12 01-Apr-14

14-Apr-14

T+18ER26760

Underlay & Carpet

6 15-Apr-14

21-Apr-14
21-Apr-14
10-Feb-14

21-Apr-14
22-Apr-14
22-Apr-14
26-Feb-14

Stud to block walls

59 13-Feb-14
59 13-Feb-14
12 13-Feb-14

T+18ER26390

Waterproof bathroom

12 16-Feb-14

01-Mar-14

T+18ER26400

Flood test

12 19-Feb-14

04-Mar-14

T+18ER26410

MEP Drops in walls & back boxes

12 25-Feb-14

10-Mar-14

T+18ER26420

Install bath

12 25-Feb-14

10-Mar-14

T+18ER26430

Insulate & board walls

12 27-Feb-14

12-Mar-14

T+18ER26440

Framing & board for bath

12 27-Feb-14

12-Mar-14

T+18ER26450

First fix ceiling

12 02-Mar-14

15-Mar-14

T+18ER26460

MEP drops in ceiling

12 04-Mar-14

17-Mar-14

T+18ER26470

2nd fix ceiling incl access panel

12 05-Mar-14

18-Mar-14

T+18ER26480

Install corniche

12 08-Mar-14

20-Mar-14

T+18ER26490

Stone to floors

12 17-Mar-14

30-Mar-14

Summary Bar
Remaining Work
Milestone

Data date: 16-Nov-13

35 28-Dec-13
35 28-Dec-13
12 28-Dec-13

Chilled water & condensate

Critical Remaining Work

Revised Programme Rev. D

12 28-Dec-13
12 28-Dec-13

T+18ER26130

Bathroom
No DISP
T+18ER26380

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
11-Jan-14
11-Jan-14

Duration Start

T+18ER26120

Bedroom
No DISP
T+18ER26240

Four Seasons Hotel Bahrain

Page 57 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+18ER26500

Stone surround to bath

12 17-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
30-Mar-14

T+18ER26510

Stone vanity

12 17-Mar-14

30-Mar-14

T+18ER26520

Stone to walls incl niche

12 17-Mar-14

30-Mar-14

T+18ER26530

Casing stone

12 17-Mar-14

30-Mar-14

T+18ER26540

Grout to all stone

12 17-Mar-14

30-Mar-14

T+18ER26550

Glass Partition

12 31-Mar-14

13-Apr-14

T+18ER26560

Install and connect " Free issue " mirror

12 01-Apr-14

14-Apr-14

T+18ER26570

Sanitary ware and accessories

12 03-Apr-14

16-Apr-14

T+18ER26580

MEP connections to bath and basin

12 05-Apr-14

17-Apr-14

T+18ER26590

MEP 3rd fix - switch / socket covers

12 07-Apr-14

20-Apr-14

T+18ER26600

Hang glass doors

12 09-Apr-14

22-Apr-14

46 04-Mar-14
46 04-Mar-14
12 04-Mar-14

26-Apr-14
26-Apr-14
17-Mar-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+18ER26610 MEP drops in walls

Duration Start

T+18ER26620

Board walls

12 08-Mar-14

20-Mar-14

T+18ER26630

Ceiling 1st fix

12 10-Mar-14

23-Mar-14

T+18ER26640

MEP drops in ceiling

12 12-Mar-14

25-Mar-14

T+18ER26650

Board ceiling incl access panel

12 16-Mar-14

29-Mar-14

T+18ER26670

Tape & joint walls & ceilings

12 18-Mar-14

31-Mar-14

T+18ER26680

Mist coat dry lining

12 19-Mar-14

01-Apr-14

T+18ER26690

Paint ceiling

12 22-Mar-14

03-Apr-14

T+18ER26700

Stone flooring incl grout

12 31-Mar-14

13-Apr-14

T+18ER26710

Pocket door to bathroom

12 06-Apr-14

19-Apr-14

T+18ER26720

Entrance door - Temporary

12 06-Apr-14

19-Apr-14

T+18ER26730

Install wardrobe

12 07-Apr-14

20-Apr-14

T+18ER26740

Wall Coverings

12 09-Apr-14

22-Apr-14

T+18ER26750

3rd fix MEP

12 13-Apr-14

26-Apr-14

24 08-Apr-14
24 08-Apr-14
3 08-Apr-14

05-May-14
05-May-14
10-Apr-14

Pier Corridors & Lift Lobby


No DISP
E+18GR620
Installation of Flexibles / Plenum
E+18GR640

3 08-Apr-14

10-Apr-14

E+18GR17360 Gypsum Ceilings

Sprinkler Drops

6 12-Apr-14

17-Apr-14

E+18GR17400 Paint Ceiling

4 19-Apr-14

22-Apr-14

E+18GR17390 Millwork

6 23-Apr-14

29-Apr-14

E+18GR17380 Wall Covering & fabric panels

4 26-Apr-14

29-Apr-14

E+18GR660

Light Fittings Installation

2 30-Apr-14

01-May-14

E+18GR670

Sprinkler Installation

2 30-Apr-14

01-May-14

3 03-May-14

05-May-14

E+18GR17410 Underlay & Carpet


Guestrooms
Bedroom
No DISP
T+18GU20500

Insulate & board walls

149
104
104
12

09-Oct-13 A
09-Oct-13 A
09-Oct-13 A
09-Oct-13 A

04-May-14
12-Mar-14
12-Mar-14
16-Nov-13

T+18GU20550

Tape & Joint walls & ceiling

12 17-Oct-13 A

17-Nov-13

T+18GU20560

Mist coat all dry lining

12 16-Nov-13

28-Nov-13

T+18GU20570

Install cornice

12 18-Nov-13

01-Dec-13

T+18GU20580

Paint ceiling and cornice

12 23-Nov-13

07-Dec-13

T+18GU20590

Wall covering

12 15-Jan-14

28-Jan-14

T+18GU20600

Install furniture

12 20-Jan-14

02-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 58 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+18GU20610

MEP terminations in furniture

12 27-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
09-Feb-14

T+18GU20620

MEP 3rd fix- sockets, cover plates etc

12 03-Feb-14

16-Feb-14

T+18GU24971

Underlay & Carpet

12 27-Feb-14

12-Mar-14

108 16-Nov-13
108 16-Nov-13
12 16-Nov-13

23-Mar-14
23-Mar-14
28-Nov-13

Activity ID

Activity Name

Bathroom
No DISP
T+18GU22500

Framing & board for bath

Duration Start

T+18GU22540

Install corniche

12 16-Nov-13

28-Nov-13

T+18GU22530

2nd fix ceiling incl access panel

12 11-Dec-13

24-Dec-13

T+18GU22550

Stone to floors

12 24-Dec-13

07-Jan-14

T+18GU22560

Stone surround to bath

12 24-Dec-13

07-Jan-14

T+18GU22570

Stone vanity

12 24-Dec-13

07-Jan-14

T+18GU22580

Stone to walls incl niche

12 24-Dec-13

07-Jan-14

T+18GU22590

Casing stone

12 24-Dec-13

07-Jan-14

T+18GU22600

Grout to all stone

12 31-Dec-13

14-Jan-14

T+18GU25120

Vanity S/S & Mirrors

12 08-Jan-14

21-Jan-14

T+18GU25130

Vanity Unit

12 08-Jan-14

21-Jan-14

T+18GU22610

Glass Partition

12 15-Jan-14

28-Jan-14

T+18GU22660

Hang glass doors

12 15-Jan-14

28-Jan-14

T+18GU18120

Wall covering

12 23-Jan-14

05-Feb-14

T+18GU22620

Install and connect " Free issue " mirror

12 04-Mar-14

17-Mar-14

T+18GU22630

Sanitary ware and accessories

12 06-Mar-14

19-Mar-14

T+18GU22640

MEP connections to bath and basin

12 08-Mar-14

20-Mar-14

T+18GU22650

MEP 3rd fix - switch / socket covers

Entrance Vestibule & dressing


No DISP
T+18GU24990 MEP drops in ceiling

12 10-Mar-14

23-Mar-14

130 21-Oct-13 A
130 21-Oct-13 A
12 21-Oct-13 A

23-Apr-14
23-Apr-14
16-Nov-13

T+18GU25050

Stone flooring incl grout

12 24-Dec-13

07-Jan-14

T+18GU25000

Board ceiling incl access panel

12 15-Jan-14

28-Jan-14

T+18GU25020

Tape & joint walls & ceilings

12 18-Jan-14

30-Jan-14

T+18GU25030

Mist coat dry lining

12 19-Jan-14

01-Feb-14

T+18GU25040

Paint ceiling

12 21-Jan-14

03-Feb-14

T+18GU25080

Install wardrobe

12 28-Jan-14

10-Feb-14

T+18GU25090

Wall Coverings

12 30-Jan-14

12-Feb-14

T+18GU25100

3rd fix MEP

12 03-Feb-14

16-Feb-14

T+18GU25070

Mirrors

12 11-Feb-14

24-Feb-14

T+18GU25060

Pocket door to bathroom

12 10-Apr-14

23-Apr-14

132 30-Nov-13
132 30-Nov-13
6 30-Nov-13

04-May-14
04-May-14
07-Dec-13

Corridor
No DISP
T+18GR17350

Gypsum Walls

T+18GR620

Installation of Flexibles / Plenum

8 20-Mar-14

29-Mar-14

T+18GR640

Sprinkler Drops

6 23-Mar-14

29-Mar-14

T+18GR17360

Gypsum Ceilings

6 23-Mar-14

29-Mar-14

T+18GR680

Grilles / Diffuser Installation

4 30-Mar-14

02-Apr-14

T+18GR17370

T & J Walls & Ceilings

6 30-Mar-14

05-Apr-14

T+18GR17400

Paint Ceiling

4 06-Apr-14

09-Apr-14

T+18GR17390

Millwork

10 10-Apr-14

21-Apr-14

T+18GR17380

Wall Covering

4 22-Apr-14

26-Apr-14

T+18GR17420

Mirrors

3 22-Apr-14

24-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 59 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+18GR660

Light Fittings Installation

4 27-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
30-Apr-14

T+18GR690

FA / SD installation

4 27-Apr-14

30-Apr-14

T+18GR670

Sprinkler Installation

4 27-Apr-14

30-Apr-14

T+18GR17410

Underlay & Carpet

Activity ID

Activity Name

+19 @ +85.60
West Core
Electrical/Telecom Room
Finishes
T+19WR26870 RMX - 01 to floor
T+19WR26880 Permanent door

Duration Start

3 01-May-14

04-May-14

176 06-Oct-13 A

14-May-14

120
29
3
3

15-Dec-13
25-Dec-13
26-Jan-14
26-Jan-14

04-May-14
28-Jan-14
28-Jan-14
28-Jan-14

3 26-Jan-14

28-Jan-14

20 25-Dec-13
3 25-Dec-13

18-Jan-14
28-Dec-13

T+19WR26780 Busbar installation & connection

2 29-Dec-13

30-Dec-13

T+19WR26820 Install IT Panels

2 29-Dec-13

30-Dec-13

T+19WR26830 Install Security Panels

2 29-Dec-13

30-Dec-13

T+19WR26790 Duckwork branch to room

2 31-Dec-13

02-Jan-14

T+19WR26800 Fire alarm cabling

3 04-Jan-14

06-Jan-14

T+19WR26810 Cable terminations

10 07-Jan-14

18-Jan-14

6 19-Jan-14
2 19-Jan-14

25-Jan-14
20-Jan-14

T+19WR26850 Fire alarm devices

2 21-Jan-14

22-Jan-14

T+19WR26860 Light fittings

2 23-Jan-14

25-Jan-14

Finishes - 1st Fix


No DISP
T+19WR26060 Studwork incl noggins

52 15-Dec-13
52 15-Dec-13
12 15-Dec-13

13-Feb-14
13-Feb-14
28-Dec-13

T+19WR26070 Close blockwork risers

12 01-Feb-14

13-Feb-14

MEP riser summary


No DISP
T+19WR26080 MEP risers & 1st fix

12 22-Dec-13
12 22-Dec-13
12 22-Dec-13

05-Jan-14
05-Jan-14
05-Jan-14

MEP Risers & First Fix


No DISP
T+19WR26110 Ductworks risers

35 22-Dec-13
35 22-Dec-13
12 22-Dec-13

01-Feb-14
01-Feb-14
05-Jan-14

T+19WR26120 Chilled water & condensate

12 29-Dec-13

12-Jan-14

T+19WR26130 DCW / DHW & CCW riser

12 06-Jan-14

19-Jan-14

T+19WR26140 Sanitary riser

12 06-Jan-14

19-Jan-14

T+19WR26150 Hang FCU

12 06-Jan-14

19-Jan-14

T+19WR26160 Ductwork - supply, make-up air & extract

12 06-Jan-14

19-Jan-14

T+19WR26170 CW supply / return & condensate

12 09-Jan-14

22-Jan-14

T+19WR26180 Plumbing & san distribution

12 11-Jan-14

23-Jan-14

T+19WR26190 FCU connections

12 14-Jan-14

27-Jan-14

T+19WR26200 Cable tray / trunking

12 15-Jan-14

28-Jan-14

T+19WR26220 Test risers ( 3floors vertically )

12 18-Jan-14

30-Jan-14

T+19WR26210 Sprinkler pipes ( Not drops ) from corridor

12 19-Jan-14

01-Feb-14

1st & 2nd Fix


T+19WR26890 Electrical Containment

MEP Final Fix


T+19WR26840 Grills & diffusers

T+19WR26230 MEP sign off risers (Start)

30-Jan-14

66 22-Jan-14
66 22-Jan-14
12 22-Jan-14

08-Apr-14
08-Apr-14
04-Feb-14

T+19WR26250 Insulate & board walls

12 27-Jan-14

09-Feb-14

T+19WR26260 Ceiling 1st fix

18 01-Feb-14

20-Feb-14

Bedroom
No DISP
T+19WR26240 MEP Drops in walls & back boxes

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 60 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+19WR26270 Wiring

12 05-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
18-Feb-14

T+19WR26280 MEP drops in ceiling

12 09-Feb-14

22-Feb-14

T+19WR26290 Board ceiling

12 10-Feb-14

23-Feb-14

T+19WR26300 Tape & Joint walls & ceiling

12 15-Feb-14

27-Feb-14

T+19WR26310 Mist coat all dry lining

12 19-Feb-14

04-Mar-14

T+19WR26320 Install cornice

12 22-Feb-14

06-Mar-14

T+19WR26330 Paint ceiling and cornice

12 26-Feb-14

11-Mar-14

T+19WR26340 Wall covering

12 03-Mar-14

16-Mar-14

T+19WR26350 Install furniture

12 08-Mar-14

20-Mar-14

T+19WR26360 MEP terminations in furniture

12 12-Mar-14

25-Mar-14

T+19WR26370 MEP 3rd fix- sockets, cover plates etc

12 19-Mar-14

01-Apr-14

T+19WR26760 Underlay & Carpet

6 02-Apr-14

08-Apr-14

Bathroom
No DISP
T+19WR26380 Stud to block walls

64 08-Feb-14
64 08-Feb-14
12 08-Feb-14

22-Apr-14
22-Apr-14
20-Feb-14

T+19WR26390 Waterproof bathroom

12 10-Feb-14

23-Feb-14

T+19WR26400 Flood test

12 17-Feb-14

02-Mar-14

T+19WR26410 MEP Drops in walls & back boxes

12 26-Feb-14

11-Mar-14

T+19WR26420 Install bath

12 26-Feb-14

11-Mar-14

T+19WR26430 Insulate & board walls

12 01-Mar-14

13-Mar-14

T+19WR26440 Framing & board for bath

12 01-Mar-14

13-Mar-14

T+19WR26450 First fix ceiling

12 03-Mar-14

16-Mar-14

T+19WR26460 MEP drops in ceiling

12 05-Mar-14

18-Mar-14

T+19WR26470 2nd fix ceiling incl access panel

12 06-Mar-14

19-Mar-14

T+19WR26480 Install corniche

12 09-Mar-14

22-Mar-14

T+19WR26490 Stone to floors

12 17-Mar-14

30-Mar-14

T+19WR26500 Stone surround to bath

12 17-Mar-14

30-Mar-14

T+19WR26510 Stone vanity

12 17-Mar-14

30-Mar-14

T+19WR26520 Stone to walls incl niche

12 17-Mar-14

30-Mar-14

T+19WR26530 Casing stone

12 17-Mar-14

30-Mar-14

T+19WR26540 Grout to all stone

12 17-Mar-14

30-Mar-14

T+19WR26550 Glass Partition

12 31-Mar-14

13-Apr-14

T+19WR26560 Install and connect " Free issue " mirror

12 01-Apr-14

14-Apr-14

T+19WR26570 Sanitary ware and accessories

12 03-Apr-14

16-Apr-14

T+19WR26580 MEP connections to bath and basin

12 05-Apr-14

17-Apr-14

T+19WR26590 MEP 3rd fix - switch / socket covers

12 07-Apr-14

20-Apr-14

T+19WR26600 Hang glass doors

12 09-Apr-14

22-Apr-14

Entrance Vestibule & dressing


No DISP
T+19WR26610 MEP drops in walls

39 05-Mar-14
39 05-Mar-14
12 05-Mar-14

19-Apr-14
19-Apr-14
18-Mar-14

T+19WR26620 Board walls

12 09-Mar-14

22-Mar-14

T+19WR26630 Ceiling 1st fix

12 11-Mar-14

24-Mar-14

T+19WR26640 MEP drops in ceiling

12 13-Mar-14

26-Mar-14

T+19WR26650 Board ceiling incl access panel

12 17-Mar-14

30-Mar-14

T+19WR26670 Tape & joint walls & ceilings

12 19-Mar-14

01-Apr-14

T+19WR26680 Mist coat dry lining

12 20-Mar-14

02-Apr-14

T+19WR26690 Paint ceiling

12 23-Mar-14

05-Apr-14

T+19WR26700 Stone flooring incl grout

12 24-Mar-14

06-Apr-14

Activity ID

Activity Name

Duration Start

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 61 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+19WR26710 Pocket door to bathroom

12 30-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-Apr-14

T+19WR26720 Entrance door - Temporary

12 30-Mar-14

12-Apr-14

T+19WR26730 Install wardrobe

12 31-Mar-14

13-Apr-14

T+19WR26740 Wall Coverings

12 02-Apr-14

15-Apr-14

T+19WR26750 3rd fix MEP

12 06-Apr-14

19-Apr-14

22 09-Apr-14
22 09-Apr-14
3 09-Apr-14

04-May-14
04-May-14
12-Apr-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+19GR620
Installation of Flexibles / Plenum
W+19GR640

Sprinkler Drops

Duration Start

3 09-Apr-14

12-Apr-14

W+19GR17360 Gypsum Ceilings

6 13-Apr-14

19-Apr-14

W+19GR17400 Paint Ceiling

2 20-Apr-14

21-Apr-14

W+19GR17390 Millwork

6 22-Apr-14

28-Apr-14

W+19GR17380 Wall Covering & fabric panels

4 24-Apr-14

28-Apr-14

W+19GR660

Light Fittings Installation

2 29-Apr-14

30-Apr-14

W+19GR670

Sprinkler Installation

2 29-Apr-14

30-Apr-14

3 01-May-14

04-May-14

W+19GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+19ER26060 Studwork incl noggins
T+19ER26070

Close blockwork risers

129
63
63
12

15-Dec-13
15-Dec-13
15-Dec-13
15-Dec-13

14-May-14
26-Feb-14
26-Feb-14
28-Dec-13

12 13-Feb-14

26-Feb-14

MEP riser summary


No DISP
T+19ER26080 MEP risers & 1st fix

12 05-Jan-14
12 05-Jan-14
12 05-Jan-14

18-Jan-14
18-Jan-14
18-Jan-14

MEP Risers & First Fix


No DISP
T+19ER26110 Ductworks risers

35 05-Jan-14
35 05-Jan-14
12 05-Jan-14

13-Feb-14
13-Feb-14
18-Jan-14

T+19ER26120

Chilled water & condensate

12 12-Jan-14

25-Jan-14

T+19ER26130

DCW / DHW & CCW riser

12 19-Jan-14

01-Feb-14

T+19ER26140

Sanitary riser

12 19-Jan-14

01-Feb-14

T+19ER26150

Hang FCU

12 19-Jan-14

01-Feb-14

T+19ER26160

Ductwork - supply, make-up air & extract

12 19-Jan-14

01-Feb-14

T+19ER26170

CW supply / return & condensate

12 22-Jan-14

04-Feb-14

T+19ER26180

Plumbing & san distribution

12 23-Jan-14

05-Feb-14

T+19ER26190

FCU connections

12 27-Jan-14

09-Feb-14

T+19ER26200

Cable tray / trunking

12 28-Jan-14

10-Feb-14

T+19ER26220

Test risers ( 3floors vertically )

12 30-Jan-14

12-Feb-14

T+19ER26210

Sprinkler pipes ( Not drops ) from corridor

12 01-Feb-14

13-Feb-14

T+19ER26230

MEP sign off risers (Start)

12-Feb-14

MEP Drops in walls & back boxes

68 04-Feb-14
68 04-Feb-14
12 04-Feb-14

T+19ER26250

Insulate & board walls

12 11-Feb-14

24-Feb-14

T+19ER26260

Ceiling 1st fix

18 16-Feb-14

08-Mar-14

T+19ER26270

Wiring

12 20-Feb-14

05-Mar-14

T+19ER26280

MEP drops in ceiling

12 24-Feb-14

09-Mar-14

T+19ER26290

Board ceiling

12 25-Feb-14

10-Mar-14

T+19ER26300

Tape & Joint walls & ceiling

12 02-Mar-14

15-Mar-14

T+19ER26310

Mist coat all dry lining

12 06-Mar-14

19-Mar-14

Bedroom
No DISP
T+19ER26240

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 62 of 180

23-Apr-14
23-Apr-14
17-Feb-14

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+19ER26320

Install cornice

12 09-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
22-Mar-14

T+19ER26330

Paint ceiling and cornice

12 13-Mar-14

26-Mar-14

T+19ER26340

Wall covering

6 18-Mar-14

24-Mar-14

T+19ER26350

Install furniture

12 23-Mar-14

05-Apr-14

T+19ER26360

MEP terminations in furniture

12 27-Mar-14

09-Apr-14

T+19ER26370

MEP 3rd fix- sockets, cover plates etc

12 03-Apr-14

16-Apr-14

T+19ER26760

Underlay & Carpet

6 17-Apr-14

23-Apr-14

Stud to block walls

59 20-Feb-14
59 20-Feb-14
12 20-Feb-14

29-Apr-14
29-Apr-14
05-Mar-14

T+19ER26390

Waterproof bathroom

12 23-Feb-14

08-Mar-14

T+19ER26400

Flood test

12 26-Feb-14

11-Mar-14

T+19ER26410

MEP Drops in walls & back boxes

12 08-Mar-14

20-Mar-14

T+19ER26420

Install bath

12 08-Mar-14

20-Mar-14

T+19ER26430

Insulate & board walls

12 10-Mar-14

23-Mar-14

T+19ER26440

Framing & board for bath

12 10-Mar-14

23-Mar-14

T+19ER26450

First fix ceiling

12 12-Mar-14

25-Mar-14

T+19ER26460

MEP drops in ceiling

12 15-Mar-14

27-Mar-14

T+19ER26470

2nd fix ceiling incl access panel

12 16-Mar-14

29-Mar-14

T+19ER26480

Install corniche

12 18-Mar-14

31-Mar-14

T+19ER26490

Stone to floors

12 24-Mar-14

06-Apr-14

T+19ER26500

Stone surround to bath

12 24-Mar-14

06-Apr-14

T+19ER26510

Stone vanity

12 24-Mar-14

06-Apr-14

T+19ER26520

Stone to walls incl niche

12 24-Mar-14

06-Apr-14

T+19ER26530

Casing stone

12 24-Mar-14

06-Apr-14

T+19ER26540

Grout to all stone

12 24-Mar-14

06-Apr-14

T+19ER26550

Glass Partition

12 07-Apr-14

20-Apr-14

T+19ER26560

Install and connect " Free issue " mirror

12 08-Apr-14

21-Apr-14

T+19ER26570

Sanitary ware and accessories

12 10-Apr-14

23-Apr-14

T+19ER26580

MEP connections to bath and basin

12 12-Apr-14

24-Apr-14

T+19ER26590

MEP 3rd fix - switch / socket covers

12 14-Apr-14

27-Apr-14

T+19ER26600

Hang glass doors

12 16-Apr-14

29-Apr-14

37 15-Mar-14
37 15-Mar-14
12 15-Mar-14

26-Apr-14
26-Apr-14
27-Mar-14

Activity ID

Activity Name

Bathroom
No DISP
T+19ER26380

Entrance Vestibule & dressing


No DISP
T+19ER26610 MEP drops in walls

Duration Start

T+19ER26620

Board walls

12 18-Mar-14

31-Mar-14

T+19ER26630

Ceiling 1st fix

12 20-Mar-14

02-Apr-14

T+19ER26640

MEP drops in ceiling

12 23-Mar-14

05-Apr-14

T+19ER26650

Board ceiling incl access panel

12 26-Mar-14

08-Apr-14

T+19ER26670

Tape & joint walls & ceilings

12 29-Mar-14

10-Apr-14

T+19ER26680

Mist coat dry lining

12 30-Mar-14

12-Apr-14

T+19ER26700

Stone flooring incl grout

12 31-Mar-14

13-Apr-14

T+19ER26690

Paint ceiling

12 01-Apr-14

14-Apr-14

T+19ER26710

Pocket door to bathroom

12 06-Apr-14

19-Apr-14

T+19ER26720

Entrance door - Temporary

12 06-Apr-14

19-Apr-14

T+19ER26730

Install wardrobe

12 07-Apr-14

20-Apr-14

T+19ER26740

Wall Coverings

12 09-Apr-14

22-Apr-14

T+19ER26750

3rd fix MEP

12 13-Apr-14

26-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 63 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
E+19GR620
Installation of Flexibles / Plenum
E+19GR640

Sprinkler Drops

Duration Start

24 17-Apr-14
24 17-Apr-14
3 17-Apr-14
3 17-Apr-14

20-Apr-14

6 21-Apr-14

27-Apr-14

E+19GR17400 Paint Ceiling

4 28-Apr-14

01-May-14

E+19GR17390 Millwork

6 03-May-14

08-May-14

E+19GR17380 Wall Covering & fabric panels

4 05-May-14

08-May-14

E+19GR660

Light Fittings Installation

2 10-May-14

11-May-14

E+19GR670

Sprinkler Installation

2 10-May-14

11-May-14

3 12-May-14

14-May-14

E+19GR17410 Underlay & Carpet

Insulate & board walls

173
102
102
12

06-Oct-13 A
13-Oct-13 A
13-Oct-13 A
13-Oct-13 A

11-May-14
16-Mar-14
16-Mar-14
16-Nov-13

T+19GU20680

Board ceiling

12 19-Oct-13 A

16-Nov-13

T+19GU20690

Tape & Joint walls & ceiling

12 21-Oct-13 A

21-Nov-13

T+19GU20700

Mist coat all dry lining

12 16-Nov-13

28-Nov-13

T+19GU20710

Install cornice

12 18-Nov-13

01-Dec-13

T+19GU20720

Paint ceiling and cornice

12 23-Nov-13

07-Dec-13

T+19GU20730

Wall covering

12 29-Jan-14

11-Feb-14

T+19GU20740

Install furniture

12 03-Feb-14

16-Feb-14

T+19GU20750

MEP terminations in furniture

12 10-Feb-14

23-Feb-14

T+19GU20760

MEP 3rd fix- sockets, cover plates etc

12 17-Feb-14

02-Mar-14

T+19GU25121

Underlay & Carpet

12 03-Mar-14

16-Mar-14

131 17-Oct-13 A
131 17-Oct-13 A
12 16-Nov-13

10-Apr-14
10-Apr-14
28-Nov-13

Bathroom
No DISP
T+19GU22740

First fix ceiling

T+19GU22760

2nd fix ceiling incl access panel

12 16-Nov-13

28-Nov-13

T+19GU22730

Framing & board for bath

12 16-Nov-13

28-Nov-13

T+19GU22710

Install bath

12 22-Oct-13 A

21-Nov-13

T+19GU22690

Flood test

12 21-Oct-13 A

20-Nov-13

T+19GU22720

Insulate & board walls

12 17-Oct-13 A

24-Nov-13

T+19GU22750

MEP drops in ceiling

12 28-Oct-13 A

01-Dec-13

T+19GU22770

Install corniche

12 23-Nov-13

07-Dec-13

T+19GU22780

Stone to floors

12 30-Dec-13

13-Jan-14

T+19GU22790

Stone surround to bath

12 30-Dec-13

13-Jan-14

T+19GU22800

Stone vanity

12 30-Dec-13

13-Jan-14

T+19GU22810

Stone to walls incl niche

12 30-Dec-13

13-Jan-14

T+19GU22820

Casing stone

12 30-Dec-13

13-Jan-14

T+19GU22830

Grout to all stone

12 07-Jan-14

20-Jan-14

T+19GU25270

Vanity S/S & Mirrors

12 14-Jan-14

27-Jan-14

T+19GU25280

Vanity Unit

12 14-Jan-14

27-Jan-14

T+19GU22840

Glass Partition

12 21-Jan-14

03-Feb-14

T+19GU22890

Hang glass doors

12 21-Jan-14

03-Feb-14

T+19GU18120

Wall covering

12 06-Feb-14

19-Feb-14

T+19GU22850

Install and connect " Free issue " mirror

12 18-Mar-14

31-Mar-14

T+19GU22860

Sanitary ware and accessories

12 25-Mar-14

07-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 64 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
14-May-14
14-May-14
20-Apr-14

E+19GR17360 Gypsum Ceilings

Guestrooms
Bedroom
No DISP
T+19GU20640

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+19GU22870

MEP connections to bath and basin

T+19GU22880

MEP 3rd fix - switch / socket covers

Entrance Vestibule & dressing


No DISP
T+19GU25110 MEP drops in walls

12 29-Mar-14

10-Apr-14

143 20-Oct-13 A
143 20-Oct-13 A
12 20-Oct-13 A

30-Apr-14
30-Apr-14
21-Nov-13

12 21-Oct-13 A

23-Nov-13

T+19GU25130

Ceiling 1st fix

12 22-Oct-13 A

23-Nov-13

T+19GU25140

MEP drops in ceiling

12 16-Nov-13

28-Nov-13

T+19GU25200

Stone flooring incl grout

12 30-Dec-13

13-Jan-14

T+19GU25150

Board ceiling incl access panel

12 14-Jan-14

27-Jan-14

T+19GU25170

Tape & joint walls & ceilings

12 16-Jan-14

29-Jan-14

T+19GU25180

Mist coat dry lining

18 18-Jan-14

06-Feb-14

T+19GU25190

Paint ceiling

12 20-Jan-14

02-Feb-14

T+19GU25230

Install wardrobe

12 27-Jan-14

09-Feb-14

T+19GU25220

Mirrors

12 03-Feb-14

16-Feb-14

T+19GU25250

3rd fix MEP

12 10-Feb-14

23-Feb-14

T+19GU25240

Wall Coverings

12 15-Feb-14

27-Feb-14

T+19GU25210

Pocket door to bathroom

12 17-Apr-14

30-Apr-14

173 06-Oct-13 A
173 06-Oct-13 A
15 06-Oct-13 A

11-May-14
11-May-14
03-Dec-13

T+19GU600

Duct Installation

12 16-Nov-13

28-Nov-13

T+19GU610

Electrical Containment

12 28-Nov-13

12-Dec-13

T+19GU590

FP Piping

10 30-Nov-13

11-Dec-13

T+19GR17350

Gypsum Walls

6 08-Dec-13

14-Dec-13

T+19GU640

Sprinkler Dropper piping Installation

6 12-Dec-13

18-Dec-13

T+19GU630

Cabling and wire pulling

8 14-Dec-13

22-Dec-13

T+19GR630

Cabling and wire pulling

8 14-Dec-13

22-Dec-13

T+19GU650

FP Pipe Pressure Testing

3 19-Dec-13

22-Dec-13

T+19GR620

Installation of Flexibles / Plenum

8 27-Mar-14

05-Apr-14

T+19GR640

Sprinkler Drops

6 30-Mar-14

05-Apr-14

T+19GR17360

Gypsum Ceilings

6 30-Mar-14

05-Apr-14

T+19GR680

Grilles / Diffuser Installation

4 06-Apr-14

09-Apr-14

T+19GR17370

T & J Walls & Ceilings

6 06-Apr-14

12-Apr-14

T+19GR17400

Paint Ceiling

T+19GR17390

Millwork

T+19GR17380

4 13-Apr-14

16-Apr-14

10 17-Apr-14

28-Apr-14

Wall Covering

4 29-Apr-14

03-May-14

T+19GR17420

Mirrors

3 29-Apr-14

01-May-14

T+19GR660

Light Fittings Installation

4 04-May-14

07-May-14

T+19GR690

FA / SD installation

4 04-May-14

07-May-14

T+19GR670

Sprinkler Installation

4 04-May-14

07-May-14

T+19GR17410

Underlay & Carpet

3 08-May-14

11-May-14

202 03-Oct-13 A

03-Jun-14

126
29
3
3

29-Dec-13
29-Dec-13
29-Jan-14
29-Jan-14

25-May-14
01-Feb-14
01-Feb-14
01-Feb-14

3 29-Jan-14

01-Feb-14

20 29-Dec-13

21-Jan-14

+20 @ +89.40
West Core
Electrical/Telecom Room
Finishes
T+20WR26870 RMX - 01 to floor
T+20WR26880 Permanent door
1st & 2nd Fix
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Revised Programme Rev. D

Data date: 16-Nov-13

12 26-Mar-14

Board walls

Cable Tray / Trunking

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
08-Apr-14

Duration Start

T+19GU25120

Corridor
No DISP
T+19GU580

Four Seasons Hotel Bahrain

Page 65 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+20WR26890 Electrical Containment

3 29-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
31-Dec-13

T+20WR26780 Busbar installation & connection

2 02-Jan-14

04-Jan-14

T+20WR26820 Install IT Panels

2 02-Jan-14

04-Jan-14

T+20WR26830 Install Security Panels

2 02-Jan-14

04-Jan-14

T+20WR26790 Duckwork branch to room

2 05-Jan-14

06-Jan-14

T+20WR26800 Fire alarm cabling

3 07-Jan-14

09-Jan-14

T+20WR26810 Cable terminations

10 11-Jan-14

21-Jan-14

6 22-Jan-14
2 22-Jan-14

28-Jan-14
23-Jan-14

T+20WR26850 Fire alarm devices

2 25-Jan-14

26-Jan-14

T+20WR26860 Light fittings

2 27-Jan-14

28-Jan-14

25 12-Jan-14
25 12-Jan-14
12 12-Jan-14*

09-Feb-14
09-Feb-14
25-Jan-14

12 27-Jan-14

09-Feb-14

MEP riser summary


No DISP
T+20WR26080 MEP risers & 1st fix

12 29-Dec-13
12 29-Dec-13
12 29-Dec-13

12-Jan-14
12-Jan-14
12-Jan-14

MEP Risers & First Fix


No DISP
T+20WR26110 Ductworks risers

48 29-Dec-13
48 29-Dec-13
12 29-Dec-13

23-Feb-14
23-Feb-14
12-Jan-14

T+20WR26120 Chilled water & condensate riser

12 06-Jan-14

19-Jan-14

T+20WR26130 DCW / DHW & CCW riser

12 13-Jan-14

26-Jan-14

T+20WR26140 Sanitary riser

12 13-Jan-14

26-Jan-14

T+20WR26220 Test risers ( 3floors vertically )

12 13-Jan-14

26-Jan-14

T+20WR26150 Hang FCU

12 26-Jan-14

08-Feb-14

T+20WR26160 Ductwork - supply, make-up air & extract

12 26-Jan-14

08-Feb-14

Activity ID

Activity Name

MEP Final Fix


T+20WR26840 Grills & diffusers

Finishes - 1st Fix


No DISP
T+20WR26060 Studwork incl noggins
T+20WR26070 Close blockwork risers

T+20WR26230 MEP sign off risers (Start)

Duration Start

26-Jan-14

T+20WR26170 CW supply / return & condensate

12 29-Jan-14

11-Feb-14

T+20WR26190 FCU connections

12 03-Feb-14

16-Feb-14

T+20WR26180 Plumbing & san distribution

12 05-Feb-14

18-Feb-14

T+20WR26210 Sprinkler pipes ( Not drops ) from corridor

12 08-Feb-14

20-Feb-14

T+20WR26200 Cable tray / trunking

12 10-Feb-14

23-Feb-14

66 17-Feb-14
66 17-Feb-14
12 17-Feb-14

04-May-14
04-May-14
02-Mar-14

T+20WR26250 Insulate & board walls

12 22-Feb-14

06-Mar-14

T+20WR26260 Ceiling 1st fix

18 26-Feb-14

18-Mar-14

T+20WR26270 Wiring

12 03-Mar-14

16-Mar-14

T+20WR26280 MEP drops in ceiling

12 06-Mar-14

19-Mar-14

T+20WR26290 Board ceiling

12 08-Mar-14

20-Mar-14

T+20WR26300 Tape & Joint walls & ceiling

12 12-Mar-14

25-Mar-14

T+20WR26310 Mist coat all dry lining

12 17-Mar-14

30-Mar-14

T+20WR26320 Install cornice

12 19-Mar-14

01-Apr-14

T+20WR26330 Paint ceiling and cornice

12 24-Mar-14

06-Apr-14

T+20WR26340 Wall covering

12 29-Mar-14

10-Apr-14

T+20WR26350 Install furniture

12 02-Apr-14

15-Apr-14

T+20WR26360 MEP terminations in furniture

12 07-Apr-14

20-Apr-14

T+20WR26370 MEP 3rd fix- sockets, cover plates etc

12 14-Apr-14

27-Apr-14

Bedroom
No DISP
T+20WR26240 MEP Drops in walls & back boxes

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 66 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

T+20WR26760 Underlay & Carpet

6 28-Apr-14
93 12-Jan-14
93 12-Jan-14
12 12-Jan-14

29-Apr-14
29-Apr-14
25-Jan-14

T+20WR26390 Waterproof bathroom

12 19-Feb-14

04-Mar-14

T+20WR26400 Flood test

12 26-Feb-14

11-Mar-14

T+20WR26410 MEP Drops in walls & back boxes

12 08-Mar-14

20-Mar-14

T+20WR26420 Install bath

12 08-Mar-14

20-Mar-14

T+20WR26430 Insulate & board walls

12 10-Mar-14

23-Mar-14

T+20WR26440 Framing & board for bath

12 10-Mar-14

23-Mar-14

T+20WR26450 First fix ceiling

12 12-Mar-14

25-Mar-14

T+20WR26460 MEP drops in ceiling

12 15-Mar-14

27-Mar-14

T+20WR26470 2nd fix ceiling incl access panel

12 16-Mar-14

29-Mar-14

T+20WR26480 Install corniche

12 18-Mar-14

31-Mar-14

T+20WR26490 Stone to floors

12 24-Mar-14

06-Apr-14

T+20WR26500 Stone surround to bath

12 24-Mar-14

06-Apr-14

T+20WR26510 Stone vanity

12 24-Mar-14

06-Apr-14

T+20WR26520 Stone to walls incl niche

12 24-Mar-14

06-Apr-14

T+20WR26530 Casing stone

12 24-Mar-14

06-Apr-14

T+20WR26540 Grout to all stone

12 24-Mar-14

06-Apr-14

T+20WR26550 Glass Partition

12 07-Apr-14

20-Apr-14

T+20WR26560 Install and connect " Free issue " mirror

12 08-Apr-14

21-Apr-14

T+20WR26570 Sanitary ware and accessories

12 10-Apr-14

23-Apr-14

T+20WR26580 MEP connections to bath and basin

12 12-Apr-14

24-Apr-14

T+20WR26590 MEP 3rd fix - switch / socket covers

12 14-Apr-14

27-Apr-14

T+20WR26600 Hang glass doors

12 16-Apr-14

29-Apr-14

Entrance Vestibule & dressing


No DISP
T+20WR26610 MEP drops in walls

62 15-Mar-14
62 15-Mar-14
12 15-Mar-14

25-May-14
25-May-14
27-Mar-14

T+20WR26700 Stone flooring incl grout

12 31-Mar-14

13-Apr-14

T+20WR26620 Board walls

12 14-Apr-14

27-Apr-14

T+20WR26630 Ceiling 1st fix

12 16-Apr-14

29-Apr-14

T+20WR26640 MEP drops in ceiling

12 19-Apr-14

01-May-14

T+20WR26650 Board ceiling incl access panel

12 22-Apr-14

05-May-14

T+20WR26670 Tape & joint walls & ceilings

12 24-Apr-14

07-May-14

T+20WR26680 Mist coat dry lining

12 26-Apr-14

08-May-14

T+20WR26690 Paint ceiling

12 28-Apr-14

11-May-14

T+20WR26710 Pocket door to bathroom

12 05-May-14

18-May-14

T+20WR26720 Entrance door - Temporary

12 05-May-14

18-May-14

T+20WR26730 Install wardrobe

12 06-May-14

19-May-14

T+20WR26740 Wall Coverings

12 08-May-14

21-May-14

T+20WR26750 3rd fix MEP

12 12-May-14

25-May-14

20 28-Apr-14
20 28-Apr-14
3 28-Apr-14

20-May-14
20-May-14
30-Apr-14

W+20GR640

Sprinkler Drops

3 28-Apr-14

30-Apr-14

W+20GR17360 Gypsum Ceilings

4 01-May-14

05-May-14

W+20GR17400 Paint Ceiling

2 06-May-14

07-May-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 67 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
04-May-14

Bathroom
No DISP
T+20WR26380 Stud to block walls

Pier Corridors & Lift Lobby


No DISP
W+20GR620
Installation of Flexibles / Plenum

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

W+20GR17390 Millwork

6 08-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
14-May-14

W+20GR17380 Wall Covering & fabric panels

4 11-May-14

14-May-14

W+20GR660

Light Fittings Installation

2 15-May-14

17-May-14

W+20GR670

Sprinkler Installation

2 15-May-14

17-May-14

3 18-May-14

20-May-14

Activity ID

Activity Name

W+20GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+20ER26010 Blockwork to risers ( 2 sides )

Duration Start

202
125
125
20

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

03-Jun-14
05-Mar-14
05-Mar-14
26-Nov-13

T+20ER26020

Blockwork to wall full height

20 03-Oct-13 A

09-Dec-13

T+20ER26060

Studwork incl noggins

12 22-Dec-13

05-Jan-14

T+20ER26070

Close blockwork risers

12 20-Feb-14

05-Mar-14

MEP riser summary


No DISP
T+20ER26080 MEP risers & 1st fix

12 12-Jan-14
12 12-Jan-14
12 12-Jan-14

25-Jan-14
25-Jan-14
25-Jan-14

MEP Risers & First Fix


No DISP
T+20ER26110 Ductworks risers

35 12-Jan-14
35 12-Jan-14
12 12-Jan-14

20-Feb-14
20-Feb-14
25-Jan-14

T+20ER26120

Chilled water & condensate riser

12 19-Jan-14

01-Feb-14

T+20ER26130

DCW / DHW & CCW riser

12 26-Jan-14

08-Feb-14

T+20ER26140

Sanitary riser

12 26-Jan-14

08-Feb-14

T+20ER26150

Hang FCU

12 26-Jan-14

08-Feb-14

T+20ER26160

Ductwork - supply, make-up air & extract

12 26-Jan-14

08-Feb-14

T+20ER26170

CW supply / return & condensate

12 29-Jan-14

11-Feb-14

T+20ER26180

Plumbing & san distribution

12 30-Jan-14

12-Feb-14

T+20ER26190

FCU connections

12 03-Feb-14

16-Feb-14

T+20ER26200

Cable tray / trunking

12 04-Feb-14

17-Feb-14

T+20ER26220

Test risers ( 3floors vertically )

12 06-Feb-14

19-Feb-14

T+20ER26210

Sprinkler pipes ( Not drops ) from corridor

12 08-Feb-14

20-Feb-14

T+20ER26230

MEP sign off risers (Start)

19-Feb-14

MEP Drops in walls & back boxes

68 11-Feb-14
68 11-Feb-14
12 11-Feb-14

30-Apr-14
30-Apr-14
24-Feb-14

T+20ER26250

Insulate & board walls

12 18-Feb-14

03-Mar-14

T+20ER26260

Ceiling 1st fix

18 23-Feb-14

15-Mar-14

T+20ER26270

Wiring

12 27-Feb-14

12-Mar-14

T+20ER26280

MEP drops in ceiling

12 03-Mar-14

16-Mar-14

T+20ER26290

Board ceiling

12 04-Mar-14

17-Mar-14

T+20ER26300

Tape & Joint walls & ceiling

12 09-Mar-14

22-Mar-14

T+20ER26310

Mist coat all dry lining

12 13-Mar-14

26-Mar-14

T+20ER26320

Install cornice

12 16-Mar-14

29-Mar-14

T+20ER26330

Paint ceiling and cornice

12 20-Mar-14

02-Apr-14

T+20ER26340

Wall covering

6 25-Mar-14

31-Mar-14

T+20ER26350

Install furniture

12 30-Mar-14

12-Apr-14

T+20ER26360

MEP terminations in furniture

12 03-Apr-14

16-Apr-14

T+20ER26370

MEP 3rd fix- sockets, cover plates etc

12 10-Apr-14

23-Apr-14

T+20ER26760

Underlay & Carpet

6 24-Apr-14

30-Apr-14

59 27-Feb-14
59 27-Feb-14

06-May-14
06-May-14

Bedroom
No DISP
T+20ER26240

Bathroom
No DISP
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 68 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+20ER26380

Stud to block walls

12 27-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-Mar-14

T+20ER26390

Waterproof bathroom

12 02-Mar-14

15-Mar-14

T+20ER26400

Flood test

12 08-Mar-14

20-Mar-14

T+20ER26410

MEP Drops in walls & back boxes

12 15-Mar-14

27-Mar-14

T+20ER26420

Install bath

12 15-Mar-14

27-Mar-14

T+20ER26430

Insulate & board walls

12 17-Mar-14

30-Mar-14

T+20ER26440

Framing & board for bath

12 17-Mar-14

30-Mar-14

T+20ER26450

First fix ceiling

12 19-Mar-14

01-Apr-14

T+20ER26460

MEP drops in ceiling

12 22-Mar-14

03-Apr-14

T+20ER26470

2nd fix ceiling incl access panel

12 23-Mar-14

05-Apr-14

T+20ER26480

Install corniche

12 25-Mar-14

07-Apr-14

T+20ER26490

Stone to floors

12 31-Mar-14

13-Apr-14

T+20ER26500

Stone surround to bath

12 31-Mar-14

13-Apr-14

T+20ER26510

Stone vanity

12 31-Mar-14

13-Apr-14

T+20ER26520

Stone to walls incl niche

12 31-Mar-14

13-Apr-14

T+20ER26530

Casing stone

12 31-Mar-14

13-Apr-14

T+20ER26540

Grout to all stone

12 31-Mar-14

13-Apr-14

T+20ER26550

Glass Partition

12 14-Apr-14

27-Apr-14

T+20ER26560

Install and connect " Free issue " mirror

12 15-Apr-14

28-Apr-14

T+20ER26570

Sanitary ware and accessories

12 17-Apr-14

30-Apr-14

T+20ER26580

MEP connections to bath and basin

12 19-Apr-14

01-May-14

T+20ER26590

MEP 3rd fix - switch / socket covers

12 21-Apr-14

04-May-14

T+20ER26600

Hang glass doors

12 23-Apr-14

06-May-14

37 22-Mar-14
37 22-Mar-14
12 22-Mar-14

03-May-14
03-May-14
03-Apr-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+20ER26610 MEP drops in walls

Duration Start

T+20ER26620

Board walls

12 25-Mar-14

07-Apr-14

T+20ER26630

Ceiling 1st fix

12 27-Mar-14

09-Apr-14

T+20ER26640

MEP drops in ceiling

12 30-Mar-14

12-Apr-14

T+20ER26650

Board ceiling incl access panel

12 02-Apr-14

15-Apr-14

T+20ER26670

Tape & joint walls & ceilings

12 05-Apr-14

17-Apr-14

T+20ER26680

Mist coat dry lining

12 06-Apr-14

19-Apr-14

T+20ER26700

Stone flooring incl grout

12 07-Apr-14

20-Apr-14

T+20ER26690

Paint ceiling

12 08-Apr-14

21-Apr-14

T+20ER26710

Pocket door to bathroom

12 13-Apr-14

26-Apr-14

T+20ER26720

Entrance door - Temporary

12 13-Apr-14

26-Apr-14

T+20ER26730

Install wardrobe

12 14-Apr-14

27-Apr-14

T+20ER26740

Wall Coverings

12 16-Apr-14

29-Apr-14

T+20ER26750

3rd fix MEP

12 20-Apr-14

03-May-14

24 07-May-14
24 07-May-14
3 07-May-14

03-Jun-14
03-Jun-14
10-May-14

Pier Corridors & Lift Lobby


No DISP
E+20GR620
Installation of Flexibles / Plenum
E+20GR640

3 07-May-14

10-May-14

E+20GR17360 Gypsum Ceilings

Sprinkler Drops

6 11-May-14

17-May-14

E+20GR17400 Paint Ceiling

4 18-May-14

21-May-14

E+20GR17390 Millwork

6 22-May-14

28-May-14

E+20GR17380 Wall Covering & fabric panels

4 25-May-14

28-May-14

E+20GR660

2 29-May-14

31-May-14

Light Fittings Installation

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 69 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

E+20GR670

Sprinkler Installation

E+20GR17410 Underlay & Carpet


Guestrooms
MEP Risers & First Fix
No DISP
T+20GU19250 MEP sign off risers (Start)

03-Jun-14

08-Oct-13 A
08-Oct-13 A
08-Oct-13 A
16-Nov-13

21-May-14
20-Nov-13
20-Nov-13
20-Nov-13

T+20GU19260

FCU connections

12 13-Oct-13 A

19-Nov-13

T+20GU19240

Plumbing & san distribution

18 08-Oct-13 A

19-Nov-13

108 23-Oct-13 A
108 23-Oct-13 A
18 16-Nov-13

23-Mar-14
23-Mar-14
07-Dec-13

T+20GU20780

Insulate & board walls

12 23-Oct-13 A

24-Nov-13

T+20GU20800

Wiring

12 20-Nov-13

04-Dec-13

T+20GU20810

MEP drops in ceiling

12 24-Nov-13

08-Dec-13

T+20GU20820

Board ceiling

12 25-Nov-13

09-Dec-13

T+20GU20830

Tape & Joint walls & ceiling

12 30-Nov-13

14-Dec-13

T+20GU20840

Mist coat all dry lining

12 05-Dec-13

18-Dec-13

T+20GU20850

Install cornice

12 08-Dec-13

21-Dec-13

T+20GU20860

Paint ceiling and cornice

12 12-Dec-13

25-Dec-13

T+20GU20870

Wall covering

12 05-Feb-14

18-Feb-14

T+20GU20880

Install furniture

12 10-Feb-14

23-Feb-14

T+20GU20890

MEP terminations in furniture

12 15-Feb-14

27-Feb-14

T+20GU20900

MEP 3rd fix- sockets, cover plates etc

12 19-Feb-14

04-Mar-14

T+20GU25271

Underlay & Carpet

12 10-Mar-14

23-Mar-14

139 21-Oct-13 A
139 21-Oct-13 A
12 21-Oct-13 A

13-Apr-14
13-Apr-14
16-Nov-13

SS frame to shower & toilet

T+20GU22910

Waterproof bathroom

12 25-Nov-13

09-Dec-13

T+20GU22920

Flood test

12 30-Nov-13

14-Dec-13

T+20GU22930

MEP Drops in walls & back boxes

12 10-Dec-13

23-Dec-13

T+20GU22940

Install bath

12 10-Dec-13

23-Dec-13

T+20GU22950

Insulate & board walls

12 12-Dec-13

25-Dec-13

T+20GU22960

Framing & board for bath

12 12-Dec-13

25-Dec-13

T+20GU22970

First fix ceiling

12 15-Dec-13

28-Dec-13

T+20GU22980

MEP drops in ceiling

12 17-Dec-13

30-Dec-13

T+20GU22990

2nd fix ceiling incl access panel

12 18-Dec-13

31-Dec-13

T+20GU23000

Install corniche

12 21-Dec-13

04-Jan-14

T+20GU23010

Stone to floors

12 08-Jan-14

21-Jan-14

T+20GU23020

Stone surround to bath

12 08-Jan-14

21-Jan-14

T+20GU23030

Stone vanity

12 08-Jan-14

21-Jan-14

T+20GU23040

Stone to walls incl niche

12 08-Jan-14

21-Jan-14

T+20GU23050

Casing stone

12 08-Jan-14

21-Jan-14

T+20GU23060

Grout to all stone

12 15-Jan-14

28-Jan-14

T+20GU25420

Vanity S/S & Mirrors

12 22-Jan-14

04-Feb-14

T+20GU25430

Vanity Unit

12 22-Jan-14

04-Feb-14

T+20GU23070

Glass Partition

12 29-Jan-14

11-Feb-14

T+20GU23120

Hang glass doors

12 29-Jan-14

11-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

3 01-Jun-14
185
26
26
0

18 10-Oct-13 A

Bathroom
No DISP
T+20GU25410

Revised Programme Rev. D

2 29-May-14

CW supply / return & condensate

Ceiling 1st fix

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
31-May-14

Duration Start

T+20GU19230

Bedroom
No DISP
T+20GU20790

Four Seasons Hotel Bahrain

Page 70 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+20GU18120

Wall covering

12 13-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
26-Feb-14

T+20GU23080

Install and connect " Free issue " mirror

12 25-Mar-14

07-Apr-14

T+20GU23090

Sanitary ware and accessories

12 27-Mar-14

09-Apr-14

T+20GU23100

MEP connections to bath and basin

12 29-Mar-14

10-Apr-14

T+20GU23110

MEP 3rd fix - switch / socket covers

12 31-Mar-14

13-Apr-14

129 12-Dec-13
129 12-Dec-13
12 12-Dec-13

12-May-14
12-May-14
25-Dec-13

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+20GU25270 Board walls

Duration Start

T+20GU25280

Ceiling 1st fix

12 15-Dec-13

28-Dec-13

T+20GU25290

MEP drops in ceiling

12 17-Dec-13

30-Dec-13

T+20GU25350

Stone flooring incl grout

12 08-Jan-14

21-Jan-14

T+20GU25300

Board ceiling incl access panel

12 29-Jan-14

11-Feb-14

T+20GU25320

Tape & joint walls & ceilings

12 01-Feb-14

13-Feb-14

T+20GU25330

Mist coat dry lining

12 02-Feb-14

15-Feb-14

T+20GU25340

Paint ceiling

12 04-Feb-14

17-Feb-14

T+20GU25380

Install wardrobe

12 11-Feb-14

24-Feb-14

T+20GU25370

Mirrors

12 18-Feb-14

03-Mar-14

T+20GU25390

Wall Coverings

12 25-Feb-14

10-Mar-14

T+20GU25400

3rd fix MEP

12 04-Mar-14

17-Mar-14

T+20GU25360

Pocket door to bathroom

12 29-Apr-14

12-May-14

144 04-Dec-13
144 04-Dec-13
15 04-Dec-13

21-May-14
21-May-14
21-Dec-13

12 11-Dec-13

24-Dec-13

6 15-Dec-13

21-Dec-13

Corridor
No DISP
T+20GU580

Cable Tray / Trunking

T+20GU600

Duct Installation

T+20GR17350

Gypsum Walls

T+20GU610

Electrical Containment

12 17-Dec-13

30-Dec-13

T+20GU25440

FP Piping

8 25-Dec-13

04-Jan-14

T+20GU630

Cabling and wire pulling

8 31-Dec-13

09-Jan-14

T+20GU640

Sprinkler Drops piping Installation

6 05-Jan-14

11-Jan-14

T+20GU650

FP Pipe Pressure Testing

3 12-Jan-14

14-Jan-14

T+20GR17360

Gypsum Ceilings & corniche

6 06-Apr-14

12-Apr-14

T+20GR620

Installation of Flexibles / Plenum

4 08-Apr-14

12-Apr-14

T+20GR680

Grilles / Diffuser Installation

4 13-Apr-14

16-Apr-14

T+20GR17370

T & J Walls & Ceilings

6 17-Apr-14

23-Apr-14

T+20GR17400

Paint Ceiling

4 24-Apr-14

28-Apr-14

T+20GR17390

Millwork

10 29-Apr-14

10-May-14

T+20GR17420

Mirrors

3 07-May-14

10-May-14

T+20GR17380

Wall Covering

3 11-May-14

13-May-14

T+20GR660

Light Fittings Installation

4 14-May-14

18-May-14

T+20GR690

FA / SD installation

4 14-May-14

18-May-14

T+20GR670

Sprinkler Installation

4 14-May-14

18-May-14

T+20GR17410

Underlay & Carpet

3 19-May-14

21-May-14

196 12-Oct-13 A

10-Jun-14

154
29
3
3

16-Nov-13
02-Jan-14
02-Feb-14
02-Feb-14

15-May-14
04-Feb-14
04-Feb-14
04-Feb-14

3 02-Feb-14

04-Feb-14

20 02-Jan-14

25-Jan-14

+21 @ +93.20
West Core
Electrical/Telecom Room
Finishes
T+21WR26870 RMX - 01 to floor
T+21WR26880 Permanent door
1st & 2nd Fix
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 71 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+21WR26890 Electrical Containment

3 02-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
05-Jan-14

T+21WR26780 Busbar installation & connection

2 06-Jan-14

07-Jan-14

T+21WR26820 Install IT Panels

2 06-Jan-14

07-Jan-14

T+21WR26830 Install Security Panels

2 06-Jan-14

07-Jan-14

T+21WR26790 Duckwork branch to room

2 08-Jan-14

09-Jan-14

T+21WR26800 Fire alarm cabling

3 11-Jan-14

13-Jan-14

T+21WR26810 Cable terminations

10 14-Jan-14

25-Jan-14

6 26-Jan-14
2 26-Jan-14

01-Feb-14
27-Jan-14

T+21WR26850 Fire alarm devices

2 28-Jan-14

29-Jan-14

T+21WR26860 Light fittings

2 30-Jan-14

01-Feb-14

58 22-Dec-13
58 22-Dec-13
12 22-Dec-13*

27-Feb-14
27-Feb-14
05-Jan-14

12 15-Feb-14

27-Feb-14

MEP riser summary


No DISP
T+21WR26080 MEP risers & 1st fix

12 06-Jan-14
12 06-Jan-14
12 06-Jan-14

19-Jan-14
19-Jan-14
19-Jan-14

MEP Risers & First Fix


No DISP
T+21WR26110 Ductworks risers

35 06-Jan-14
35 06-Jan-14
12 06-Jan-14

15-Feb-14
15-Feb-14
19-Jan-14

T+21WR26120 Chilled water & condensate

12 13-Jan-14

26-Jan-14

T+21WR26130 DCW / DHW & CCW riser

12 20-Jan-14

02-Feb-14

T+21WR26140 Sanitary riser

12 20-Jan-14

02-Feb-14

T+21WR26150 Hang FCU

12 20-Jan-14

02-Feb-14

T+21WR26160 Ductwork - supply, make-up air & extract

12 20-Jan-14

02-Feb-14

T+21WR26170 CW supply / return & condensate

12 23-Jan-14

05-Feb-14

T+21WR26180 Plumbing & san distribution

12 25-Jan-14

06-Feb-14

T+21WR26190 FCU connections

12 28-Jan-14

10-Feb-14

T+21WR26200 Cable tray / trunking

12 29-Jan-14

11-Feb-14

T+21WR26220 Test risers ( 3floors vertically )

12 01-Feb-14

13-Feb-14

T+21WR26210 Sprinkler pipes ( Not drops ) from corridor

12 02-Feb-14

15-Feb-14

Activity ID

Activity Name

MEP Final Fix


T+21WR26840 Grills & diffusers

Finishes - 1st Fix


No DISP
T+21WR26060 Studwork incl noggins
T+21WR26070 Close blockwork risers

T+21WR26230 MEP sign off risers (Start)

Duration Start

13-Feb-14

66 05-Feb-14
66 05-Feb-14
12 05-Feb-14

22-Apr-14
22-Apr-14
18-Feb-14

T+21WR26250 Insulate & board walls

12 10-Feb-14

23-Feb-14

T+21WR26260 Ceiling 1st fix

18 15-Feb-14

06-Mar-14

T+21WR26270 Wiring

12 19-Feb-14

04-Mar-14

T+21WR26280 MEP drops in ceiling

12 23-Feb-14

08-Mar-14

T+21WR26290 Board ceiling

12 24-Feb-14

09-Mar-14

T+21WR26300 Tape & Joint walls & ceiling

12 01-Mar-14

13-Mar-14

T+21WR26310 Mist coat all dry lining

12 05-Mar-14

18-Mar-14

T+21WR26320 Install cornice

12 08-Mar-14

20-Mar-14

T+21WR26330 Paint ceiling and cornice

12 12-Mar-14

25-Mar-14

T+21WR26340 Wall covering

12 17-Mar-14

30-Mar-14

T+21WR26350 Install furniture

12 22-Mar-14

03-Apr-14

T+21WR26360 MEP terminations in furniture

12 26-Mar-14

08-Apr-14

T+21WR26370 MEP 3rd fix- sockets, cover plates etc

12 02-Apr-14

15-Apr-14

Bedroom
No DISP
T+21WR26240 MEP Drops in walls & back boxes

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 72 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

T+21WR26760 Underlay & Carpet

6 16-Apr-14
64 22-Feb-14
64 22-Feb-14
12 22-Feb-14

06-May-14
06-May-14
06-Mar-14

T+21WR26390 Waterproof bathroom

12 24-Feb-14

09-Mar-14

T+21WR26400 Flood test

12 03-Mar-14

16-Mar-14

T+21WR26410 MEP Drops in walls & back boxes

12 12-Mar-14

25-Mar-14

T+21WR26420 Install bath

12 12-Mar-14

25-Mar-14

T+21WR26430 Insulate & board walls

12 15-Mar-14

27-Mar-14

T+21WR26440 Framing & board for bath

12 15-Mar-14

27-Mar-14

T+21WR26450 First fix ceiling

12 17-Mar-14

30-Mar-14

T+21WR26460 MEP drops in ceiling

12 19-Mar-14

01-Apr-14

T+21WR26470 2nd fix ceiling incl access panel

12 20-Mar-14

02-Apr-14

T+21WR26480 Install corniche

12 23-Mar-14

05-Apr-14

T+21WR26490 Stone to floors

12 31-Mar-14

13-Apr-14

T+21WR26500 Stone surround to bath

12 31-Mar-14

13-Apr-14

T+21WR26510 Stone vanity

12 31-Mar-14

13-Apr-14

T+21WR26520 Stone to walls incl niche

12 31-Mar-14

13-Apr-14

T+21WR26530 Casing stone

12 31-Mar-14

13-Apr-14

T+21WR26540 Grout to all stone

12 31-Mar-14

13-Apr-14

T+21WR26550 Glass Partition

12 14-Apr-14

27-Apr-14

T+21WR26560 Install and connect " Free issue " mirror

12 15-Apr-14

28-Apr-14

T+21WR26570 Sanitary ware and accessories

12 17-Apr-14

30-Apr-14

T+21WR26580 MEP connections to bath and basin

12 19-Apr-14

01-May-14

T+21WR26590 MEP 3rd fix - switch / socket covers

12 21-Apr-14

04-May-14

T+21WR26600 Hang glass doors

12 23-Apr-14

06-May-14

Entrance Vestibule & dressing


No DISP
T+21WR26610 MEP drops in walls

39 19-Mar-14
39 19-Mar-14
12 19-Mar-14

03-May-14
03-May-14
01-Apr-14

T+21WR26620 Board walls

12 23-Mar-14

05-Apr-14

T+21WR26630 Ceiling 1st fix

12 25-Mar-14

07-Apr-14

T+21WR26640 MEP drops in ceiling

12 27-Mar-14

09-Apr-14

T+21WR26650 Board ceiling incl access panel

12 31-Mar-14

13-Apr-14

T+21WR26670 Tape & joint walls & ceilings

12 02-Apr-14

15-Apr-14

T+21WR26680 Mist coat dry lining

12 03-Apr-14

16-Apr-14

T+21WR26690 Paint ceiling

12 06-Apr-14

19-Apr-14

T+21WR26700 Stone flooring incl grout

12 07-Apr-14

20-Apr-14

T+21WR26710 Pocket door to bathroom

12 13-Apr-14

26-Apr-14

T+21WR26720 Entrance door - Temporary

12 13-Apr-14

26-Apr-14

T+21WR26730 Install wardrobe

12 14-Apr-14

27-Apr-14

T+21WR26740 Wall Coverings

12 16-Apr-14

29-Apr-14

T+21WR26750 3rd fix MEP

12 20-Apr-14

03-May-14

Pier Corridors & Lift Lobby


No DISP
W+21GR17400 Paint Ceiling

154 16-Nov-13
154 16-Nov-13
2 16-Nov-13

15-May-14
15-May-14
17-Nov-13

W+21GR17390 Millwork

6 18-Nov-13

24-Nov-13

W+21GR17380 Wall Covering & fabric panels

4 20-Nov-13

24-Nov-13

W+21GR660

2 25-Nov-13

26-Nov-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 73 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
22-Apr-14

Bathroom
No DISP
T+21WR26380 Stud to block walls

Light Fittings Installation

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

W+21GR620

Installation of Flexibles / Plenum

3 07-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-May-14

W+21GR640

Sprinkler Drops

3 07-May-14

10-May-14

W+21GR670

Sprinkler Installation

2 11-May-14

12-May-14

W+21GR17360 Gypsum Ceilings

4 11-May-14

14-May-14

W+21GR17410 Underlay & Carpet

3 13-May-14

15-May-14

Activity ID

Activity Name

East Core
Finishes - 1st Fix
No DISP
T+21ER26060 Studwork incl noggins
T+21ER26070

Close blockwork risers

Duration Start

140
63
63
12

29-Dec-13
29-Dec-13
29-Dec-13
29-Dec-13

10-Jun-14
12-Mar-14
12-Mar-14
12-Jan-14

12 27-Feb-14

12-Mar-14

MEP riser summary


No DISP
T+21ER26080 MEP risers & 1st fix

12 19-Jan-14
12 19-Jan-14
12 19-Jan-14

01-Feb-14
01-Feb-14
01-Feb-14

MEP Risers & First Fix


No DISP
T+21ER26110 Ductworks risers

35 19-Jan-14
35 19-Jan-14
12 19-Jan-14

27-Feb-14
27-Feb-14
01-Feb-14

T+21ER26120

Chilled water & condensate

12 26-Jan-14

08-Feb-14

T+21ER26130

DCW / DHW & CCW riser

12 02-Feb-14

15-Feb-14

T+21ER26140

Sanitary riser

12 02-Feb-14

15-Feb-14

T+21ER26150

Hang FCU

12 02-Feb-14

15-Feb-14

T+21ER26160

Ductwork - supply, make-up air & extract

12 02-Feb-14

15-Feb-14

T+21ER26170

CW supply / return & condensate

12 05-Feb-14

18-Feb-14

T+21ER26180

Plumbing & san distribution

12 06-Feb-14

19-Feb-14

T+21ER26190

FCU connections

12 10-Feb-14

23-Feb-14

T+21ER26200

Cable tray / trunking

12 11-Feb-14

24-Feb-14

T+21ER26220

Test risers ( 3floors vertically )

12 13-Feb-14

26-Feb-14

T+21ER26210

Sprinkler pipes ( Not drops ) from corridor

12 15-Feb-14

27-Feb-14

T+21ER26230

MEP sign off risers (Start)

26-Feb-14

MEP Drops in walls & back boxes

68 18-Feb-14
68 18-Feb-14
12 18-Feb-14

T+21ER26250

Insulate & board walls

12 23-Feb-14

08-Mar-14

T+21ER26260

Ceiling 1st fix

18 27-Feb-14

19-Mar-14

T+21ER26270

Wiring

12 04-Mar-14

17-Mar-14

T+21ER26280

MEP drops in ceiling

12 08-Mar-14

20-Mar-14

T+21ER26290

Board ceiling

12 09-Mar-14

22-Mar-14

T+21ER26300

Tape & Joint walls & ceiling

12 13-Mar-14

26-Mar-14

T+21ER26310

Mist coat all dry lining

12 18-Mar-14

31-Mar-14

T+21ER26320

Install cornice

12 20-Mar-14

02-Apr-14

T+21ER26330

Paint ceiling and cornice

12 25-Mar-14

07-Apr-14

T+21ER26340

Wall covering

6 01-Apr-14

07-Apr-14

T+21ER26350

Install furniture

12 06-Apr-14

19-Apr-14

T+21ER26360

MEP terminations in furniture

12 10-Apr-14

23-Apr-14

T+21ER26370

MEP 3rd fix- sockets, cover plates etc

12 17-Apr-14

30-Apr-14

T+21ER26760

Underlay & Carpet

6 01-May-14

07-May-14

Stud to block walls

59 06-Mar-14
59 06-Mar-14
12 06-Mar-14

13-May-14
13-May-14
19-Mar-14

Waterproof bathroom

12 09-Mar-14

22-Mar-14

Bedroom
No DISP
T+21ER26240

Bathroom
No DISP
T+21ER26380
T+21ER26390
Summary Bar

Remaining Work
Critical Remaining Work
Milestone

Page 74 of 180

07-May-14
07-May-14
03-Mar-14

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+21ER26400

Flood test

12 16-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
29-Mar-14

T+21ER26410

MEP Drops in walls & back boxes

12 25-Mar-14

07-Apr-14

T+21ER26420

Install bath

12 25-Mar-14

07-Apr-14

T+21ER26430

Insulate & board walls

12 27-Mar-14

09-Apr-14

T+21ER26440

Framing & board for bath

12 27-Mar-14

09-Apr-14

T+21ER26450

First fix ceiling

12 30-Mar-14

12-Apr-14

T+21ER26460

MEP drops in ceiling

12 01-Apr-14

14-Apr-14

T+21ER26470

2nd fix ceiling incl access panel

12 02-Apr-14

15-Apr-14

T+21ER26480

Install corniche

12 05-Apr-14

17-Apr-14

T+21ER26490

Stone to floors

12 07-Apr-14

20-Apr-14

T+21ER26500

Stone surround to bath

12 07-Apr-14

20-Apr-14

T+21ER26510

Stone vanity

12 07-Apr-14

20-Apr-14

T+21ER26520

Stone to walls incl niche

12 07-Apr-14

20-Apr-14

T+21ER26530

Casing stone

12 07-Apr-14

20-Apr-14

T+21ER26540

Grout to all stone

12 07-Apr-14

20-Apr-14

T+21ER26550

Glass Partition

12 21-Apr-14

04-May-14

T+21ER26560

Install and connect " Free issue " mirror

12 22-Apr-14

05-May-14

T+21ER26570

Sanitary ware and accessories

12 24-Apr-14

07-May-14

T+21ER26580

MEP connections to bath and basin

12 26-Apr-14

08-May-14

T+21ER26590

MEP 3rd fix - switch / socket covers

12 28-Apr-14

11-May-14

T+21ER26600

Hang glass doors

12 30-Apr-14

13-May-14

34 01-Apr-14
34 01-Apr-14
12 01-Apr-14

10-May-14
10-May-14
14-Apr-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+21ER26610 MEP drops in walls

Duration Start

T+21ER26620

Board walls

12 05-Apr-14

17-Apr-14

T+21ER26630

Ceiling 1st fix

12 07-Apr-14

20-Apr-14

T+21ER26640

MEP drops in ceiling

12 09-Apr-14

22-Apr-14

T+21ER26650

Board ceiling incl access panel

12 13-Apr-14

26-Apr-14

T+21ER26700

Stone flooring incl grout

12 14-Apr-14

27-Apr-14

T+21ER26670

Tape & joint walls & ceilings

12 15-Apr-14

28-Apr-14

T+21ER26680

Mist coat dry lining

12 16-Apr-14

29-Apr-14

T+21ER26690

Paint ceiling

12 19-Apr-14

01-May-14

T+21ER26710

Pocket door to bathroom

12 20-Apr-14

03-May-14

T+21ER26720

Entrance door - Temporary

12 20-Apr-14

03-May-14

T+21ER26730

Install wardrobe

12 21-Apr-14

04-May-14

T+21ER26740

Wall Coverings

12 23-Apr-14

06-May-14

T+21ER26750

3rd fix MEP

12 27-Apr-14

10-May-14

24 14-May-14
24 14-May-14
3 14-May-14

10-Jun-14
10-Jun-14
17-May-14

Pier Corridors & Lift Lobby


No DISP
E+21GR620
Installation of Flexibles / Plenum
E+21GR640

3 14-May-14

17-May-14

E+21GR17360 Gypsum Ceilings

Sprinkler Drops

6 18-May-14

24-May-14

E+21GR17400 Paint Ceiling

4 25-May-14

28-May-14

E+21GR17390 Millwork

6 29-May-14

04-Jun-14

E+21GR17380 Wall Covering & fabric panels

4 01-Jun-14

04-Jun-14

E+21GR660

Light Fittings Installation

2 05-Jun-14

07-Jun-14

E+21GR670

Sprinkler Installation

2 05-Jun-14

07-Jun-14

3 08-Jun-14

10-Jun-14

E+21GR17410 Underlay & Carpet


Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 75 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Guestrooms
MEP Risers & First Fix
No DISP
T+21GU19350 Ductwork - supply, make-up air & extract
T+21GU19390

FCU connections

T+21GU19410

Sprinkler pipes ( Not drops ) from corridor

T+21GU19370

Plumbing & san distribution

Bedroom
No DISP
T+21GU20910

MEP Drops in walls & back boxes

Duration Start

182
26
26
12

12-Oct-13 A
12-Oct-13 A
12-Oct-13 A
12-Oct-13 A

12 16-Oct-13 A

17-Nov-13

6 16-Nov-13

21-Nov-13

12 13-Oct-13 A

21-Nov-13

126 20-Oct-13 A
126 20-Oct-13 A
12 20-Oct-13 A

27-Mar-14
27-Mar-14
17-Nov-13

Insulate & board walls

12 18-Nov-13

01-Dec-13

T+21GU20930

Ceiling 1st fix

18 23-Nov-13

14-Dec-13

T+21GU20940

Wiring

12 27-Nov-13

11-Dec-13

T+21GU20950

MEP drops in ceiling

12 01-Dec-13

15-Dec-13

T+21GU20960

Board ceiling

12 03-Dec-13

16-Dec-13

T+21GU20970

Tape & Joint walls & ceiling

12 08-Dec-13

21-Dec-13

T+21GU20980

Mist coat all dry lining

12 12-Dec-13

25-Dec-13

T+21GU20990

Install cornice

12 15-Dec-13

28-Dec-13

T+21GU21000

Paint ceiling and cornice

12 19-Dec-13

02-Jan-14

T+21GU21010

Wall covering

12 12-Feb-14

25-Feb-14

T+21GU21020

Install furniture

12 17-Feb-14

02-Mar-14

T+21GU21030

MEP terminations in furniture

12 22-Feb-14

06-Mar-14

T+21GU21040

MEP 3rd fix- sockets, cover plates etc

12 01-Mar-14

13-Mar-14

T+21GU25421

Underlay & Carpet

12 15-Mar-14

27-Mar-14

Stud to block walls

132 16-Nov-13
132 16-Nov-13
12 16-Nov-13

20-Apr-14
20-Apr-14
28-Nov-13

T+21GU25560

SS frame to showr & toilet

12 16-Nov-13

28-Nov-13

T+21GU23140

Waterproof bathroom

12 10-Dec-13

23-Dec-13

T+21GU23150

Flood test

12 17-Dec-13

30-Dec-13

T+21GU23160

MEP Drops in walls & back boxes

12 21-Dec-13

04-Jan-14

T+21GU23170

Install bath

12 21-Dec-13

04-Jan-14

T+21GU23180

Insulate & board walls

12 23-Dec-13

06-Jan-14

T+21GU23190

Framing & board for bath

12 23-Dec-13

06-Jan-14

T+21GU23200

First fix ceiling

12 25-Dec-13

08-Jan-14

T+21GU23210

MEP drops in ceiling

12 28-Dec-13

11-Jan-14

T+21GU23220

2nd fix ceiling incl access panel

12 29-Dec-13

12-Jan-14

T+21GU23230

Install corniche

12 31-Dec-13

14-Jan-14

T+21GU23240

Stone to floors

12 25-Jan-14*

06-Feb-14

T+21GU23250

Stone surround to bath

12 25-Jan-14

06-Feb-14

T+21GU23260

Stone vanity

12 25-Jan-14

06-Feb-14

T+21GU23270

Stone to walls incl niche

12 25-Jan-14

06-Feb-14

T+21GU23280

Casing stone

12 25-Jan-14

06-Feb-14

T+21GU23290

Grout to all stone

12 01-Feb-14

13-Feb-14

T+21GU25570

Vanity S/S & Mirrors

12 08-Feb-14

20-Feb-14

T+21GU25580

Vanity Unit

12 08-Feb-14

20-Feb-14

T+21GU23300

Glass Partition

12 15-Feb-14

27-Feb-14

T+21GU23350

Hang glass doors

12 15-Feb-14

27-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 76 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
25-May-14
21-Nov-13
21-Nov-13
17-Nov-13

T+21GU20920

Bathroom
No DISP
T+21GU23130

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+21GU18120

Wall covering

12 20-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
05-Mar-14

T+21GU23310

Install and connect " Free issue " mirror

12 01-Apr-14*

14-Apr-14

T+21GU23320

Sanitary ware and accessories

12 03-Apr-14

16-Apr-14

T+21GU23330

MEP connections to bath and basin

12 05-Apr-14

17-Apr-14

T+21GU23340

MEP 3rd fix - switch / socket covers

12 07-Apr-14

20-Apr-14

151 18-Nov-13
151 18-Nov-13
12 18-Nov-13

14-May-14
14-May-14
01-Dec-13

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+21GU25410 MEP drops in walls

Duration Start

T+21GU25420

Board walls

12 23-Dec-13

06-Jan-14

T+21GU25430

Ceiling 1st fix

12 25-Dec-13

08-Jan-14

T+21GU25440

MEP drops in ceiling

12 28-Dec-13

11-Jan-14

T+21GU25500

Stone flooring incl grout

12 25-Jan-14

06-Feb-14

T+21GU25450

Board ceiling incl access panel

12 08-Feb-14

20-Feb-14

T+21GU25460

Door frames

12 10-Feb-14

23-Feb-14

T+21GU25470

Tape & joint walls & ceilings

12 10-Feb-14

23-Feb-14

T+21GU25480

Mist coat dry lining

12 11-Feb-14

24-Feb-14

T+21GU25490

Paint ceiling

12 13-Feb-14

26-Feb-14

T+21GU25530

Install wardrobe

12 20-Feb-14

05-Mar-14

T+21GU25540

Wall Coverings

12 23-Feb-14

08-Mar-14

T+21GU25520

Mirrors

12 27-Feb-14

12-Mar-14

T+21GU25550

3rd fix MEP

12 06-Mar-14

19-Mar-14

T+21GU25510

Pocket door to bathroom

12 01-May-14

14-May-14

142 10-Dec-13
142 10-Dec-13
15 10-Dec-13

25-May-14
25-May-14
26-Dec-13

12 17-Dec-13

30-Dec-13

6 22-Dec-13

28-Dec-13

Corridor
No DISP
T+21GU580

Cable Tray / Trunking

T+21GU600

Duct Installation

T+21GR17350

Gypsum Walls

T+21GU610

Electrical Containment

12 23-Dec-13

06-Jan-14

T+21GU590

FP Piping

10 31-Dec-13

12-Jan-14

T+21GU630

Cabling and wire pulling

8 07-Jan-14

15-Jan-14

T+21GR630

Cabling and wire pulling

8 07-Jan-14

15-Jan-14

T+21GU640

Sprinkler Dropper piping Installation

6 13-Jan-14

19-Jan-14

T+21GU650

FP Pipe Pressure Testing

3 20-Jan-14

22-Jan-14

T+21GR17360

Gypsum Ceilings

6 13-Apr-14

19-Apr-14

T+21GR620

Installation of Flexibles / Plenum

4 15-Apr-14

19-Apr-14

T+21GR640

Sprinkler Drops

4 15-Apr-14

19-Apr-14

T+21GR680

Grilles / Diffuser Installation

4 20-Apr-14

23-Apr-14

T+21GR17370

T & J Walls & Ceilings

6 20-Apr-14

26-Apr-14

T+21GR17400

Paint Ceiling

T+21GR17390

Millwork

T+21GR17380

4 27-Apr-14

30-Apr-14

10 01-May-14

12-May-14

Wall Covering

4 13-May-14

17-May-14

T+21GR17420

Mirrors

3 13-May-14

15-May-14

T+21GR660

Light Fittings Installation

4 18-May-14

21-May-14

T+21GR690

FA / SD installation

4 18-May-14

21-May-14

T+21GR670

Sprinkler Installation

4 18-May-14

21-May-14

T+21GR17410

Underlay & Carpet

3 22-May-14

25-May-14

214 16-Sep-13 A

17-Jun-14

136 29-Dec-13

05-Jun-14

+22 @ +97.00
West Core
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 77 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Electrical/Telecom Room
Finishes
T+22WR26870 RMX - 01 to floor
T+22WR26880 Permanent door

Duration Start

29 06-Jan-14
3 05-Feb-14
3 05-Feb-14
3 05-Feb-14

08-Feb-14
28-Jan-14
08-Jan-14

T+22WR26780 Busbar installation & connection

2 09-Jan-14

11-Jan-14

T+22WR26820 Install IT Panels

2 09-Jan-14

11-Jan-14

T+22WR26830 Install Security Panels

2 09-Jan-14

11-Jan-14

T+22WR26790 Duckwork branch to room

2 12-Jan-14

13-Jan-14

T+22WR26800 Fire alarm cabling

3 14-Jan-14

16-Jan-14

T+22WR26810 Cable terminations

10 18-Jan-14

28-Jan-14

6 29-Jan-14
2 29-Jan-14

04-Feb-14
30-Jan-14

T+22WR26850 Fire alarm devices

2 01-Feb-14

02-Feb-14

T+22WR26860 Light fittings

2 03-Feb-14

04-Feb-14

Finishes - 1st Fix


No DISP
T+22WR26060 Studwork incl noggins

58 29-Dec-13
58 29-Dec-13
12 29-Dec-13

06-Mar-14
06-Mar-14
12-Jan-14

T+22WR26070 Close blockwork risers

12 22-Feb-14

06-Mar-14

MEP riser summary


No DISP
T+22WR26080 MEP risers & 1st fix

12 13-Jan-14
12 13-Jan-14
12 13-Jan-14

26-Jan-14
26-Jan-14
26-Jan-14

MEP Risers & First Fix


No DISP
T+22WR26110 Ductworks risers

35 13-Jan-14
35 13-Jan-14
12 13-Jan-14

22-Feb-14
22-Feb-14
26-Jan-14

T+22WR26120 Chilled water & condensate

12 20-Jan-14

02-Feb-14

T+22WR26130 DCW / DHW & CCW riser

12 27-Jan-14

09-Feb-14

T+22WR26140 Sanitary riser

12 27-Jan-14

09-Feb-14

T+22WR26150 Hang FCU

12 27-Jan-14

09-Feb-14

T+22WR26160 Ductwork - supply, make-up air & extract

12 27-Jan-14

09-Feb-14

T+22WR26170 CW supply / return & condensate

12 30-Jan-14

12-Feb-14

T+22WR26180 Plumbing & san distribution

12 01-Feb-14

13-Feb-14

T+22WR26190 FCU connections

12 04-Feb-14

17-Feb-14

T+22WR26200 Cable tray / trunking

12 05-Feb-14

18-Feb-14

T+22WR26220 Test risers ( 3floors vertically )

12 08-Feb-14

20-Feb-14

T+22WR26210 Sprinkler pipes ( Not drops ) from corridor

12 09-Feb-14

22-Feb-14

MEP Final Fix


T+22WR26840 Grills & diffusers

T+22WR26230 MEP sign off risers (Start)

29-Apr-14
29-Apr-14
25-Feb-14

T+22WR26250 Insulate & board walls

12 17-Feb-14

02-Mar-14

T+22WR26260 Ceiling 1st fix

18 22-Feb-14

13-Mar-14

T+22WR26270 Wiring

12 26-Feb-14

11-Mar-14

T+22WR26280 MEP drops in ceiling

12 02-Mar-14

15-Mar-14

T+22WR26290 Board ceiling

12 03-Mar-14

16-Mar-14

T+22WR26300 Tape & Joint walls & ceiling

12 08-Mar-14

20-Mar-14

T+22WR26310 Mist coat all dry lining

12 12-Mar-14

25-Mar-14

T+22WR26320 Install cornice

12 15-Mar-14

27-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 78 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

20-Feb-14

66 12-Feb-14
66 12-Feb-14
12 12-Feb-14

Bedroom
No DISP
T+22WR26240 MEP Drops in walls & back boxes

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
08-Feb-14
08-Feb-14
08-Feb-14

20 06-Jan-14
3 06-Jan-14

1st & 2nd Fix


T+22WR26890 Electrical Containment

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+22WR26330 Paint ceiling and cornice

12 19-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
01-Apr-14

T+22WR26340 Wall covering

12 24-Mar-14

06-Apr-14

T+22WR26350 Install furniture

12 29-Mar-14

10-Apr-14

T+22WR26360 MEP terminations in furniture

12 02-Apr-14

15-Apr-14

T+22WR26370 MEP 3rd fix- sockets, cover plates etc

12 09-Apr-14

22-Apr-14

T+22WR26760 Underlay & Carpet

6 23-Apr-14

29-Apr-14

Bathroom
No DISP
T+22WR26380 Stud to block walls

64 01-Mar-14
64 01-Mar-14
12 01-Mar-14

13-May-14
13-May-14
13-Mar-14

T+22WR26390 Waterproof bathroom

12 03-Mar-14

16-Mar-14

T+22WR26400 Flood test

12 10-Mar-14

23-Mar-14

T+22WR26410 MEP Drops in walls & back boxes

12 19-Mar-14

01-Apr-14

T+22WR26420 Install bath

12 19-Mar-14

01-Apr-14

T+22WR26430 Insulate & board walls

12 22-Mar-14

03-Apr-14

T+22WR26440 Framing & board for bath

12 22-Mar-14

03-Apr-14

T+22WR26450 First fix ceiling

12 24-Mar-14

06-Apr-14

T+22WR26460 MEP drops in ceiling

12 26-Mar-14

08-Apr-14

T+22WR26470 2nd fix ceiling incl access panel

12 27-Mar-14

09-Apr-14

T+22WR26480 Install corniche

12 30-Mar-14

12-Apr-14

T+22WR26490 Stone to floors

12 07-Apr-14

20-Apr-14

T+22WR26500 Stone surround to bath

12 07-Apr-14

20-Apr-14

T+22WR26510 Stone vanity

12 07-Apr-14

20-Apr-14

T+22WR26520 Stone to walls incl niche

12 07-Apr-14

20-Apr-14

T+22WR26530 Casing stone

12 07-Apr-14

20-Apr-14

T+22WR26540 Grout to all stone

12 07-Apr-14

20-Apr-14

T+22WR26550 Glass Partition

12 21-Apr-14

04-May-14

T+22WR26560 Install and connect " Free issue " mirror

12 22-Apr-14

05-May-14

T+22WR26570 Sanitary ware and accessories

12 24-Apr-14

07-May-14

T+22WR26580 MEP connections to bath and basin

12 26-Apr-14

08-May-14

T+22WR26590 MEP 3rd fix - switch / socket covers

12 28-Apr-14

11-May-14

T+22WR26600 Hang glass doors

12 30-Apr-14

13-May-14

Entrance Vestibule & dressing


No DISP
T+22WR26610 MEP drops in walls

39 26-Mar-14
39 26-Mar-14
12 26-Mar-14

10-May-14
10-May-14
08-Apr-14

T+22WR26620 Board walls

12 30-Mar-14

12-Apr-14

T+22WR26630 Ceiling 1st fix

12 01-Apr-14

14-Apr-14

T+22WR26640 MEP drops in ceiling

12 03-Apr-14

16-Apr-14

T+22WR26650 Board ceiling incl access panel

12 07-Apr-14

20-Apr-14

T+22WR26670 Tape & joint walls & ceilings

12 09-Apr-14

22-Apr-14

T+22WR26680 Mist coat dry lining

12 10-Apr-14

23-Apr-14

T+22WR26690 Paint ceiling

12 13-Apr-14

26-Apr-14

T+22WR26700 Stone flooring incl grout

12 14-Apr-14

27-Apr-14

T+22WR26710 Pocket door to bathroom

12 20-Apr-14

03-May-14

T+22WR26720 Entrance door - Temporary

12 20-Apr-14

03-May-14

T+22WR26730 Install wardrobe

12 21-Apr-14

04-May-14

T+22WR26740 Wall Coverings

12 23-Apr-14

06-May-14

T+22WR26750 3rd fix MEP

12 27-Apr-14

10-May-14

20 14-May-14

05-Jun-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby

Duration Start

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 79 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

No DISP
W+22GR620
W+22GR640

Installation of Flexibles / Plenum


Sprinkler Drops

Duration Start

20 14-May-14
3 14-May-14
3 14-May-14

17-May-14

4 18-May-14

21-May-14

W+22GR17400 Paint Ceiling

2 22-May-14

24-May-14

W+22GR17390 Millwork

6 25-May-14

31-May-14

W+22GR17380 Wall Covering & fabric panels

4 27-May-14

31-May-14

W+22GR660

Light Fittings Installation

2 01-Jun-14

02-Jun-14

W+22GR670

Sprinkler Installation

2 01-Jun-14

02-Jun-14

3
214
137
137
20

03-Jun-14
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

05-Jun-14
17-Jun-14
19-Mar-14
19-Mar-14
19-Nov-13

T+22ER26020

Blockwork to wall full height

20 03-Oct-13 A

17-Nov-13

T+22ER26060

Studwork incl noggins

12 06-Jan-14

19-Jan-14

T+22ER26070

Close blockwork risers

12 06-Mar-14

19-Mar-14

MEP riser summary


No DISP
T+22ER26080 MEP risers & 1st fix

12 26-Jan-14
12 26-Jan-14
12 26-Jan-14

08-Feb-14
08-Feb-14
08-Feb-14

MEP Risers & First Fix


No DISP
T+22ER26110 Ductworks risers

35 26-Jan-14
35 26-Jan-14
12 26-Jan-14

06-Mar-14
06-Mar-14
08-Feb-14

T+22ER26120

Chilled water & condensate

12 02-Feb-14

15-Feb-14

T+22ER26130

DCW / DHW & CCW riser

12 09-Feb-14

22-Feb-14

T+22ER26140

Sanitary riser

12 09-Feb-14

22-Feb-14

T+22ER26150

Hang FCU

12 09-Feb-14

22-Feb-14

T+22ER26160

Ductwork - supply, make-up air & extract

12 09-Feb-14

22-Feb-14

T+22ER26170

CW supply / return & condensate

12 12-Feb-14

25-Feb-14

T+22ER26180

Plumbing & san distribution

12 13-Feb-14

26-Feb-14

T+22ER26190

FCU connections

12 17-Feb-14

02-Mar-14

T+22ER26200

Cable tray / trunking

12 18-Feb-14

03-Mar-14

T+22ER26220

Test risers ( 3floors vertically )

12 20-Feb-14

05-Mar-14

T+22ER26210

Sprinkler pipes ( Not drops ) from corridor

12 22-Feb-14

06-Mar-14

T+22ER26230

MEP sign off risers (Start)

MEP Drops in walls & back boxes

T+22ER26250

Insulate & board walls

12 02-Mar-14

15-Mar-14

T+22ER26260

Ceiling 1st fix

18 06-Mar-14

26-Mar-14

T+22ER26270

Wiring

12 11-Mar-14

24-Mar-14

T+22ER26280

MEP drops in ceiling

12 15-Mar-14

27-Mar-14

T+22ER26290

Board ceiling

12 16-Mar-14

29-Mar-14

T+22ER26300

Tape & Joint walls & ceiling

12 20-Mar-14

02-Apr-14

T+22ER26310

Mist coat all dry lining

12 25-Mar-14

07-Apr-14

T+22ER26320

Install cornice

12 27-Mar-14

09-Apr-14

T+22ER26330

Paint ceiling and cornice

12 01-Apr-14

14-Apr-14

T+22ER26340

Wall covering

6 08-Apr-14

14-Apr-14

T+22ER26350

Install furniture

12 13-Apr-14

26-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 80 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

05-Mar-14

68 25-Feb-14
68 25-Feb-14
12 25-Feb-14

Bedroom
No DISP
T+22ER26240

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
05-Jun-14
17-May-14

W+22GR17360 Gypsum Ceilings

W+22GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+22ER26010 Blockwork to risers ( 2 sides )

Four Seasons Hotel Bahrain

14-May-14
14-May-14
10-Mar-14

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+22ER26360

MEP terminations in furniture

12 17-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
30-Apr-14

T+22ER26370

MEP 3rd fix- sockets, cover plates etc

12 24-Apr-14

07-May-14

T+22ER26760

Underlay & Carpet

6 08-May-14

14-May-14

Stud to block walls

59 13-Mar-14
59 13-Mar-14
12 13-Mar-14

20-May-14
20-May-14
26-Mar-14

T+22ER26390

Waterproof bathroom

12 16-Mar-14

29-Mar-14

T+22ER26400

Flood test

12 23-Mar-14

05-Apr-14

T+22ER26410

MEP Drops in walls & back boxes

12 01-Apr-14

14-Apr-14

T+22ER26420

Install bath

12 01-Apr-14

14-Apr-14

T+22ER26430

Insulate & board walls

12 03-Apr-14

16-Apr-14

T+22ER26440

Framing & board for bath

12 03-Apr-14

16-Apr-14

T+22ER26450

First fix ceiling

12 06-Apr-14

19-Apr-14

T+22ER26460

MEP drops in ceiling

12 08-Apr-14

21-Apr-14

T+22ER26470

2nd fix ceiling incl access panel

12 09-Apr-14

22-Apr-14

T+22ER26480

Install corniche

12 12-Apr-14

24-Apr-14

T+22ER26490

Stone to floors

12 14-Apr-14

27-Apr-14

T+22ER26500

Stone surround to bath

12 14-Apr-14

27-Apr-14

T+22ER26510

Stone vanity

12 14-Apr-14

27-Apr-14

T+22ER26520

Stone to walls incl niche

12 14-Apr-14

27-Apr-14

T+22ER26530

Casing stone

12 14-Apr-14

27-Apr-14

T+22ER26540

Grout to all stone

12 14-Apr-14

27-Apr-14

T+22ER26550

Glass Partition

12 28-Apr-14

11-May-14

T+22ER26560

Install and connect " Free issue " mirror

12 29-Apr-14

12-May-14

T+22ER26570

Sanitary ware and accessories

12 01-May-14

14-May-14

T+22ER26580

MEP connections to bath and basin

12 03-May-14

15-May-14

T+22ER26590

MEP 3rd fix - switch / socket covers

12 05-May-14

18-May-14

T+22ER26600

Hang glass doors

12 07-May-14

20-May-14

34 08-Apr-14
34 08-Apr-14
12 08-Apr-14

17-May-14
17-May-14
21-Apr-14

Activity ID

Activity Name

Bathroom
No DISP
T+22ER26380

Entrance Vestibule & dressing


No DISP
T+22ER26610 MEP drops in walls

Duration Start

T+22ER26620

Board walls

12 12-Apr-14

24-Apr-14

T+22ER26630

Ceiling 1st fix

12 14-Apr-14

27-Apr-14

T+22ER26640

MEP drops in ceiling

12 16-Apr-14

29-Apr-14

T+22ER26650

Board ceiling incl access panel

12 20-Apr-14

03-May-14

T+22ER26700

Stone flooring incl grout

12 21-Apr-14

04-May-14

T+22ER26670

Tape & joint walls & ceilings

12 22-Apr-14

05-May-14

T+22ER26680

Mist coat dry lining

12 23-Apr-14

06-May-14

T+22ER26690

Paint ceiling

12 26-Apr-14

08-May-14

T+22ER26710

Pocket door to bathroom

12 27-Apr-14

10-May-14

T+22ER26720

Entrance door - Temporary

12 27-Apr-14

10-May-14

T+22ER26730

Install wardrobe

12 28-Apr-14

11-May-14

T+22ER26740

Wall Coverings

12 30-Apr-14

13-May-14

T+22ER26750

3rd fix MEP

12 04-May-14

17-May-14

24 21-May-14
24 21-May-14
3 21-May-14

17-Jun-14
17-Jun-14
24-May-14

3 21-May-14

24-May-14

Pier Corridors & Lift Lobby


No DISP
E+22GR620
Installation of Flexibles / Plenum
E+22GR640

Sprinkler Drops

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 81 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

E+22GR17360 Gypsum Ceilings

6 25-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
31-May-14

E+22GR17400 Paint Ceiling

4 01-Jun-14

04-Jun-14

E+22GR17390 Millwork

6 05-Jun-14

11-Jun-14

E+22GR17380 Wall Covering & fabric panels

4 08-Jun-14

11-Jun-14

E+22GR660

Light Fittings Installation

2 12-Jun-14

14-Jun-14

E+22GR670

Sprinkler Installation

2 12-Jun-14

14-Jun-14

3 15-Jun-14

17-Jun-14

Activity ID

Activity Name

E+22GR17410 Underlay & Carpet

Duration Start

16-Sep-13 A
16-Nov-13
16-Nov-13
16-Nov-13

01-Jun-14
28-Nov-13
28-Nov-13
28-Nov-13

MEP riser summary


No DISP
T+22GU18360 MEP risers & 1st fix Riser 1

9 16-Sep-13 A
9 16-Sep-13 A
9 16-Sep-13 A

19-Nov-13
19-Nov-13
19-Nov-13

MEP Risers & First Fix


No DISP
T+22GU19450 DCW / DHW & CCW riser

56 23-Sep-13 A
56 23-Sep-13 A
12 14-Oct-13 A

21-Dec-13
21-Dec-13
17-Nov-13

Guestrooms
Finishes - 1st Fix
No DISP
T+22GU17860 Close blockwork risers

200
12
12
12

T+22GU19460

Sanitary riser

12 16-Oct-13 A

19-Nov-13

T+22GU19440

Test risers ( 3floors vertically )

12 20-Oct-13 A

19-Nov-13

T+22GU19510

MEP sign off risers (Start)

T+22GU19430

Chilled water & condensate riser

12 16-Oct-13 A

19-Nov-13

T+22GU19480

Ductwork - supply, make-up air & extract

12 18-Nov-13

01-Dec-13

T+22GU19500

Plumbing & san distribution

18 20-Nov-13

11-Dec-13

T+22GU19490

CW supply / return & condensate

12 03-Dec-13

16-Dec-13

T+22GU19520

FCU connections

12 08-Dec-13

21-Dec-13

T+22GU19540

Sprinkler pipes ( Not drops ) from corridor

18 23-Sep-13 A

17-Dec-13

Bedroom
No DISP
T+22GU21060

Insulate & board walls

0 16-Nov-13

110 03-Dec-13
110 03-Dec-13
12 03-Dec-13

10-Apr-14
10-Apr-14
16-Dec-13

T+22GU21070

Ceiling 1st fix

18 08-Dec-13

28-Dec-13

T+22GU21080

Wiring

12 12-Dec-13

25-Dec-13

T+22GU21090

MEP drops in ceiling

12 16-Dec-13

29-Dec-13

T+22GU21100

Board ceiling

12 17-Dec-13

30-Dec-13

T+22GU21110

Tape & Joint walls & ceiling

12 22-Dec-13

05-Jan-14

T+22GU21120

Mist coat all dry lining

12 26-Dec-13

09-Jan-14

T+22GU21130

Install cornice

12 29-Dec-13

12-Jan-14

T+22GU21140

Paint ceiling and cornice

12 04-Jan-14

16-Jan-14

T+22GU21150

Wall covering

12 26-Feb-14

11-Mar-14

T+22GU21160

Install furniture

12 03-Mar-14

16-Mar-14

T+22GU21170

MEP terminations in furniture

12 08-Mar-14

20-Mar-14

T+22GU21180

MEP 3rd fix- sockets, cover plates etc

12 15-Mar-14

27-Mar-14

T+22GU25571

Underlay & Carpet

Bathroom
No DISP
T+22GU25710

SS frame to shower & toilet

12 29-Mar-14

10-Apr-14

132 23-Nov-13
132 23-Nov-13
12 23-Nov-13

27-Apr-14
27-Apr-14
07-Dec-13

T+22GU23360

Stud to block walls

12 30-Nov-13

14-Dec-13

T+22GU23370

Waterproof bathroom

12 24-Dec-13

07-Jan-14

T+22GU23380

Flood test

12 31-Dec-13

14-Jan-14

T+22GU23390

MEP Drops in walls & back boxes

12 05-Jan-14

18-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 82 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+22GU23400

Install bath

12 05-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
18-Jan-14

T+22GU23410

Insulate & board walls

12 07-Jan-14

20-Jan-14

T+22GU23420

Framing & board for bath

12 07-Jan-14

20-Jan-14

T+22GU23430

First fix ceiling

12 09-Jan-14

22-Jan-14

T+22GU23440

MEP drops in ceiling

12 12-Jan-14

25-Jan-14

T+22GU23450

2nd fix ceiling incl access panel

12 13-Jan-14

26-Jan-14

T+22GU23460

Install corniche

12 15-Jan-14

28-Jan-14

T+22GU23470

Stone to floors

12 01-Feb-14*

13-Feb-14

T+22GU23480

Stone surround to bath

12 01-Feb-14

13-Feb-14

T+22GU23490

Stone vanity

12 01-Feb-14

13-Feb-14

T+22GU23500

Stone to walls incl niche

12 01-Feb-14

13-Feb-14

T+22GU23510

Casing stone

12 01-Feb-14

13-Feb-14

T+22GU23520

Grout to all stone

12 08-Feb-14

20-Feb-14

T+22GU25720

Vanity S/S & Mirrors

12 15-Feb-14

27-Feb-14

T+22GU25730

Vanity Unit

12 15-Feb-14

27-Feb-14

T+22GU23530

Glass Partition

12 22-Feb-14

06-Mar-14

T+22GU23580

Hang glass doors

12 22-Feb-14

06-Mar-14

T+22GU18120

Wall covering

12 06-Mar-14

19-Mar-14

T+22GU23540

Install and connect " Free issue " mirror

12 08-Apr-14

21-Apr-14

T+22GU23550

Sanitary ware and accessories

12 10-Apr-14

23-Apr-14

T+22GU23560

MEP connections to bath and basin

12 12-Apr-14

24-Apr-14

T+22GU23570

MEP 3rd fix - switch / socket covers

12 14-Apr-14

27-Apr-14

114 09-Jan-14
114 09-Jan-14
12 09-Jan-14

21-May-14
21-May-14
22-Jan-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+22GU25560 MEP drops in walls

Duration Start

T+22GU25570

Board walls

12 14-Jan-14

27-Jan-14

T+22GU25650

Stone flooring incl grout

12 01-Feb-14

13-Feb-14

T+22GU25580

Ceiling 1st fix

12 22-Feb-14

06-Mar-14

T+22GU25590

MEP drops in ceiling

12 24-Feb-14

09-Mar-14

T+22GU25600

Board ceiling incl access panel

12 27-Feb-14

12-Mar-14

T+22GU25610

Door frames

12 02-Mar-14

15-Mar-14

T+22GU25620

Tape & joint walls & ceilings

12 02-Mar-14

15-Mar-14

T+22GU25630

Mist coat dry lining

12 03-Mar-14

16-Mar-14

T+22GU25640

Paint ceiling

12 05-Mar-14

18-Mar-14

T+22GU25680

Install wardrobe

12 19-Mar-14

01-Apr-14

T+22GU25690

Wall Coverings

12 22-Mar-14

03-Apr-14

T+22GU25670

Mirrors

12 26-Mar-14

08-Apr-14

T+22GU25700

3rd fix MEP

12 02-Apr-14

15-Apr-14

T+22GU25660

Pocket door to bathroom

12 08-May-14

21-May-14

143 16-Dec-13
143 16-Dec-13
15 16-Dec-13

01-Jun-14
01-Jun-14
02-Jan-14

Corridor
No DISP
T+22GU580

Cable Tray / Trunking

T+22GR17350

Gypsum Walls

6 22-Dec-13

28-Dec-13

T+22GU600

Duct Installation

12 23-Dec-13

06-Jan-14

T+22GU610

Electrical Containment

12 29-Dec-13

12-Jan-14

T+22GU590

FP Piping

10 07-Jan-14

18-Jan-14

T+22GU630

Cabling and wire pulling

8 13-Jan-14

21-Jan-14

T+22GR630

Cabling and wire pulling

8 13-Jan-14

21-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 83 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+22GU640

Sprinkler Dropper piping Installation

6 19-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
25-Jan-14

T+22GU650

FP Pipe Pressure Testing

3 26-Jan-14

28-Jan-14

T+22GR640

Sprinkler Drops

6 20-Apr-14

26-Apr-14

T+22GR17360

Gypsum Ceilings

6 20-Apr-14

26-Apr-14

T+22GR620

Installation of Flexibles / Plenum

4 22-Apr-14

26-Apr-14

T+22GR680

Grilles / Diffuser Installation

4 27-Apr-14

30-Apr-14

T+22GR17370

T & J Walls & Ceilings

6 27-Apr-14

03-May-14

T+22GR17400

Paint Ceiling

T+22GR17390

Millwork

T+22GR17380

Activity ID

Activity Name

Duration Start

4 04-May-14

07-May-14

10 08-May-14

19-May-14

Wall Covering

4 20-May-14

24-May-14

T+22GR17420

Mirrors

3 20-May-14

22-May-14

T+22GR660

Light Fittings Installation

4 25-May-14

28-May-14

T+22GR670

Sprinkler Installation

4 25-May-14

28-May-14

T+22GR17410

Underlay & Carpet

3 29-May-14

01-Jun-14

211 15-Sep-13 A

24-Jun-14

136
29
3
3

06-Jan-14
09-Jan-14
09-Feb-14
09-Feb-14

12-Jun-14
11-Feb-14
11-Feb-14
11-Feb-14

+23 @ +100.80
West Core
Electrical/Telecom Room
Finishes
T+23WR26870 RMX - 01 to floor
T+23WR26880 Permanent door

3 09-Feb-14

11-Feb-14

20 09-Jan-14
3 09-Jan-14

01-Feb-14
12-Jan-14

T+23WR26780 Busbar installation & connection

2 13-Jan-14

14-Jan-14

T+23WR26820 Install IT Panels

2 13-Jan-14

14-Jan-14

T+23WR26830 Install Security Panels

2 13-Jan-14

14-Jan-14

T+23WR26790 Duckwork branch to room

2 15-Jan-14

16-Jan-14

T+23WR26800 Fire alarm cabling

3 18-Jan-14

20-Jan-14

T+23WR26810 Cable terminations

10 21-Jan-14

01-Feb-14

6 02-Feb-14
2 02-Feb-14

08-Feb-14
03-Feb-14

T+23WR26850 Fire alarm devices

2 04-Feb-14

05-Feb-14

T+23WR26860 Light fittings

2 06-Feb-14

08-Feb-14

Finishes - 1st Fix


No DISP
T+23WR26060 Studwork incl noggins

58 06-Jan-14
58 06-Jan-14
12 06-Jan-14

13-Mar-14
13-Mar-14
19-Jan-14

T+23WR26070 Close blockwork risers

1st & 2nd Fix


T+23WR26890 Electrical Containment

MEP Final Fix


T+23WR26840 Grills & diffusers

12 01-Mar-14

13-Mar-14

MEP riser summary


No DISP
T+23WR26080 MEP risers & 1st fix

12 20-Jan-14
12 20-Jan-14
12 20-Jan-14

02-Feb-14
02-Feb-14
02-Feb-14

MEP Risers & First Fix


No DISP
T+23WR26110 Ductworks risers

35 20-Jan-14
35 20-Jan-14
12 20-Jan-14

01-Mar-14
01-Mar-14
02-Feb-14

T+23WR26120 Chilled water & condensate

12 27-Jan-14

09-Feb-14

T+23WR26130 DCW / DHW & CCW riser

12 03-Feb-14

16-Feb-14

T+23WR26140 Sanitary riser

12 03-Feb-14

16-Feb-14

T+23WR26150 Hang FCU

12 03-Feb-14

16-Feb-14

T+23WR26160 Ductwork - supply, make-up air & extract

12 03-Feb-14

16-Feb-14

T+23WR26170 CW supply / return & condensate

12 06-Feb-14

19-Feb-14

T+23WR26180 Plumbing & san distribution

12 08-Feb-14

20-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 84 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+23WR26190 FCU connections

12 11-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
24-Feb-14

T+23WR26200 Cable tray / trunking

12 12-Feb-14

25-Feb-14

T+23WR26220 Test risers ( 3floors vertically )

12 15-Feb-14

27-Feb-14

T+23WR26210 Sprinkler pipes ( Not drops ) from corridor

12 16-Feb-14

01-Mar-14

Activity ID

Activity Name

T+23WR26230 MEP sign off risers (Start)

Duration Start

27-Feb-14

66 19-Feb-14
66 19-Feb-14
12 19-Feb-14

06-May-14
06-May-14
04-Mar-14

T+23WR26250 Insulate & board walls

12 24-Feb-14

09-Mar-14

T+23WR26260 Ceiling 1st fix

18 01-Mar-14

20-Mar-14

T+23WR26270 Wiring

12 05-Mar-14

18-Mar-14

T+23WR26280 MEP drops in ceiling

12 09-Mar-14

22-Mar-14

T+23WR26290 Board ceiling

12 10-Mar-14

23-Mar-14

T+23WR26300 Tape & Joint walls & ceiling

12 15-Mar-14

27-Mar-14

T+23WR26310 Mist coat all dry lining

12 19-Mar-14

01-Apr-14

T+23WR26320 Install cornice

12 22-Mar-14

03-Apr-14

T+23WR26330 Paint ceiling and cornice

12 26-Mar-14

08-Apr-14

T+23WR26340 Wall covering

12 31-Mar-14

13-Apr-14

T+23WR26350 Install furniture

12 05-Apr-14

17-Apr-14

T+23WR26360 MEP terminations in furniture

12 09-Apr-14

22-Apr-14

T+23WR26370 MEP 3rd fix- sockets, cover plates etc

12 16-Apr-14

29-Apr-14

T+23WR26760 Underlay & Carpet

6 30-Apr-14

06-May-14

Bathroom
No DISP
T+23WR26380 Stud to block walls

64 08-Mar-14
64 08-Mar-14
12 08-Mar-14

20-May-14
20-May-14
20-Mar-14

T+23WR26390 Waterproof bathroom

12 10-Mar-14

23-Mar-14

T+23WR26400 Flood test

12 17-Mar-14

30-Mar-14

T+23WR26410 MEP Drops in walls & back boxes

12 26-Mar-14

08-Apr-14

T+23WR26420 Install bath

12 26-Mar-14

08-Apr-14

T+23WR26430 Insulate & board walls

12 29-Mar-14

10-Apr-14

T+23WR26440 Framing & board for bath

12 29-Mar-14

10-Apr-14

T+23WR26450 First fix ceiling

12 31-Mar-14

13-Apr-14

T+23WR26460 MEP drops in ceiling

12 02-Apr-14

15-Apr-14

T+23WR26470 2nd fix ceiling incl access panel

12 03-Apr-14

16-Apr-14

T+23WR26480 Install corniche

12 06-Apr-14

19-Apr-14

T+23WR26490 Stone to floors

12 14-Apr-14

27-Apr-14

T+23WR26500 Stone surround to bath

12 14-Apr-14

27-Apr-14

T+23WR26510 Stone vanity

12 14-Apr-14

27-Apr-14

T+23WR26520 Stone to walls incl niche

12 14-Apr-14

27-Apr-14

T+23WR26530 Casing stone

12 14-Apr-14

27-Apr-14

T+23WR26540 Grout to all stone

12 14-Apr-14

27-Apr-14

T+23WR26550 Glass Partition

12 28-Apr-14

11-May-14

T+23WR26560 Install and connect " Free issue " mirror

12 29-Apr-14

12-May-14

T+23WR26570 Sanitary ware and accessories

12 01-May-14

14-May-14

T+23WR26580 MEP connections to bath and basin

12 03-May-14

15-May-14

T+23WR26590 MEP 3rd fix - switch / socket covers

12 05-May-14

18-May-14

T+23WR26600 Hang glass doors

12 07-May-14

20-May-14

39 02-Apr-14

17-May-14

Bedroom
No DISP
T+23WR26240 MEP Drops in walls & back boxes

Entrance Vestibule & dressing


Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 85 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

39 02-Apr-14
12 02-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
17-May-14
15-Apr-14

T+23WR26620 Board walls

12 06-Apr-14

19-Apr-14

T+23WR26630 Ceiling 1st fix

12 08-Apr-14

21-Apr-14

T+23WR26640 MEP drops in ceiling

12 10-Apr-14

23-Apr-14

T+23WR26650 Board ceiling incl access panel

12 14-Apr-14

27-Apr-14

T+23WR26670 Tape & joint walls & ceilings

12 16-Apr-14

29-Apr-14

T+23WR26680 Mist coat dry lining

12 17-Apr-14

30-Apr-14

T+23WR26690 Paint ceiling

12 20-Apr-14

03-May-14

T+23WR26700 Stone flooring incl grout

12 21-Apr-14

04-May-14

T+23WR26710 Pocket door to bathroom

12 27-Apr-14

10-May-14

T+23WR26720 Entrance door - Temporary

12 27-Apr-14

10-May-14

T+23WR26730 Install wardrobe

12 28-Apr-14

11-May-14

T+23WR26740 Wall Coverings

12 30-Apr-14

13-May-14

T+23WR26750 3rd fix MEP

12 04-May-14

17-May-14

20 21-May-14
20 21-May-14
3 21-May-14

12-Jun-14
12-Jun-14
24-May-14

Activity ID

Activity Name

No DISP
T+23WR26610 MEP drops in walls

Pier Corridors & Lift Lobby


No DISP
W+23GR620
Installation of Flexibles / Plenum
W+23GR640

Sprinkler Drops

Duration Start

3 21-May-14

24-May-14

W+23GR17360 Gypsum Ceilings

4 25-May-14

28-May-14

W+23GR17400 Paint Ceiling

2 29-May-14

31-May-14

W+23GR17390 Millwork

6 01-Jun-14

07-Jun-14

W+23GR17380 Wall Covering & fabric panels

4 03-Jun-14

07-Jun-14

W+23GR660

Light Fittings Installation

2 08-Jun-14

09-Jun-14

W+23GR670

Sprinkler Installation

2 08-Jun-14

09-Jun-14

3 10-Jun-14

12-Jun-14

W+23GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+23ER26060 Studwork incl noggins
T+23ER26070

Close blockwork risers

140
63
63
12

13-Jan-14
13-Jan-14
13-Jan-14
13-Jan-14

24-Jun-14
26-Mar-14
26-Mar-14
26-Jan-14

12 13-Mar-14

26-Mar-14

MEP riser summary


No DISP
T+23ER26080 MEP risers & 1st fix

12 02-Feb-14
12 02-Feb-14
12 02-Feb-14

15-Feb-14
15-Feb-14
15-Feb-14

MEP Risers & First Fix


No DISP
T+23ER26110 Ductworks risers

35 02-Feb-14
35 02-Feb-14
12 02-Feb-14

13-Mar-14
13-Mar-14
15-Feb-14

T+23ER26120

Chilled water & condensate

12 09-Feb-14

22-Feb-14

T+23ER26130

DCW / DHW & CCW riser

12 16-Feb-14

01-Mar-14

T+23ER26140

Sanitary riser

12 16-Feb-14

01-Mar-14

T+23ER26150

Hang FCU

12 16-Feb-14

01-Mar-14

T+23ER26160

Ductwork - supply, make-up air & extract

12 16-Feb-14

01-Mar-14

T+23ER26170

CW supply / return & condensate

12 19-Feb-14

04-Mar-14

T+23ER26180

Plumbing & san distribution

12 20-Feb-14

05-Mar-14

T+23ER26190

FCU connections

12 24-Feb-14

09-Mar-14

T+23ER26200

Cable tray / trunking

12 25-Feb-14

10-Mar-14

T+23ER26220

Test risers ( 3floors vertically )

12 27-Feb-14

12-Mar-14

T+23ER26210

Sprinkler pipes ( Not drops ) from corridor

12 01-Mar-14

13-Mar-14

T+23ER26230

MEP sign off risers (Start)

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 86 of 180

12-Mar-14
Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

MEP Drops in walls & back boxes

T+23ER26250

Insulate & board walls

12 09-Mar-14

22-Mar-14

T+23ER26260

Ceiling 1st fix

18 13-Mar-14

02-Apr-14

T+23ER26270

Wiring

12 18-Mar-14

31-Mar-14

T+23ER26280

MEP drops in ceiling

12 22-Mar-14

03-Apr-14

T+23ER26290

Board ceiling

12 23-Mar-14

05-Apr-14

T+23ER26300

Tape & Joint walls & ceiling

12 27-Mar-14

09-Apr-14

T+23ER26310

Mist coat all dry lining

12 01-Apr-14

14-Apr-14

T+23ER26320

Install cornice

12 03-Apr-14

16-Apr-14

T+23ER26330

Paint ceiling and cornice

12 08-Apr-14

21-Apr-14

T+23ER26340

Wall covering

6 15-Apr-14

21-Apr-14

T+23ER26350

Install furniture

12 20-Apr-14

03-May-14

T+23ER26360

MEP terminations in furniture

12 24-Apr-14

07-May-14

T+23ER26370

MEP 3rd fix- sockets, cover plates etc

12 01-May-14

14-May-14

T+23ER26760

Underlay & Carpet

6 15-May-14

21-May-14
27-May-14
27-May-14
02-Apr-14

Stud to block walls

59 20-Mar-14
59 20-Mar-14
12 20-Mar-14

T+23ER26390

Waterproof bathroom

12 23-Mar-14

05-Apr-14

T+23ER26400

Flood test

12 30-Mar-14

12-Apr-14

T+23ER26410

MEP Drops in walls & back boxes

12 08-Apr-14

21-Apr-14

T+23ER26420

Install bath

12 08-Apr-14

21-Apr-14

T+23ER26430

Insulate & board walls

12 10-Apr-14

23-Apr-14

T+23ER26440

Framing & board for bath

12 10-Apr-14

23-Apr-14

T+23ER26450

First fix ceiling

12 13-Apr-14

26-Apr-14

T+23ER26460

MEP drops in ceiling

12 15-Apr-14

28-Apr-14

T+23ER26470

2nd fix ceiling incl access panel

12 16-Apr-14

29-Apr-14

T+23ER26480

Install corniche

12 19-Apr-14

01-May-14

T+23ER26490

Stone to floors

12 21-Apr-14

04-May-14

T+23ER26500

Stone surround to bath

12 21-Apr-14

04-May-14

T+23ER26510

Stone vanity

12 21-Apr-14

04-May-14

T+23ER26520

Stone to walls incl niche

12 21-Apr-14

04-May-14

T+23ER26530

Casing stone

12 21-Apr-14

04-May-14

T+23ER26540

Grout to all stone

12 21-Apr-14

04-May-14

T+23ER26550

Glass Partition

12 05-May-14

18-May-14

T+23ER26560

Install and connect " Free issue " mirror

12 06-May-14

19-May-14

T+23ER26570

Sanitary ware and accessories

12 08-May-14

21-May-14

T+23ER26580

MEP connections to bath and basin

12 10-May-14

22-May-14

T+23ER26590

MEP 3rd fix - switch / socket covers

12 12-May-14

25-May-14

T+23ER26600

Hang glass doors

12 14-May-14

27-May-14

34 15-Apr-14
34 15-Apr-14
12 15-Apr-14

24-May-14
24-May-14
28-Apr-14

Bathroom
No DISP
T+23ER26380

Entrance Vestibule & dressing


No DISP
T+23ER26610 MEP drops in walls
T+23ER26620

Board walls

12 19-Apr-14

01-May-14

T+23ER26630

Ceiling 1st fix

12 21-Apr-14

04-May-14

T+23ER26640

MEP drops in ceiling

12 23-Apr-14

06-May-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 87 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
21-May-14
21-May-14
17-Mar-14

68 04-Mar-14
68 04-Mar-14
12 04-Mar-14

Bedroom
No DISP
T+23ER26240

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+23ER26650

Board ceiling incl access panel

12 27-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-May-14

T+23ER26700

Stone flooring incl grout

12 28-Apr-14

11-May-14

T+23ER26670

Tape & joint walls & ceilings

12 29-Apr-14

12-May-14

T+23ER26680

Mist coat dry lining

12 30-Apr-14

13-May-14

T+23ER26690

Paint ceiling

12 03-May-14

15-May-14

T+23ER26710

Pocket door to bathroom

12 04-May-14

17-May-14

T+23ER26720

Entrance door - Temporary

12 04-May-14

17-May-14

T+23ER26730

Install wardrobe

12 05-May-14

18-May-14

T+23ER26740

Wall Coverings

12 07-May-14

20-May-14

T+23ER26750

3rd fix MEP

12 11-May-14

24-May-14

24 28-May-14
24 28-May-14
3 28-May-14

24-Jun-14
24-Jun-14
31-May-14

3 28-May-14

31-May-14

E+23GR17360 Gypsum Ceilings

6 01-Jun-14

07-Jun-14

E+23GR17400 Paint Ceiling

4 08-Jun-14

11-Jun-14

E+23GR17390 Millwork

6 12-Jun-14

18-Jun-14

E+23GR17380 Wall Covering & fabric panels

4 15-Jun-14

18-Jun-14

E+23GR660

Light Fittings Installation

2 19-Jun-14

21-Jun-14

E+23GR670

Sprinkler Installation

2 19-Jun-14

21-Jun-14

3 22-Jun-14

24-Jun-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
E+23GR620
Installation of Flexibles / Plenum
E+23GR640

Sprinkler Drops

E+23GR17410 Underlay & Carpet

Duration Start

15-Sep-13 A
23-Nov-13
23-Nov-13
23-Nov-13

08-Jun-14
07-Dec-13
07-Dec-13
07-Dec-13

MEP riser summary


No DISP
T+23GU18390 MEP risers & 1st fix Riser 1

18 13-Oct-13 A
18 13-Oct-13 A
18 13-Oct-13 A

04-Dec-13
04-Dec-13
04-Dec-13

MEP Risers & First Fix


No DISP
T+23GU19580 DCW / DHW & CCW riser

49 15-Sep-13 A
49 15-Sep-13 A
12 20-Oct-13 A

19-Dec-13
19-Dec-13
23-Nov-13

Guestrooms
Finishes - 1st Fix
No DISP
T+23GU17930 Close blockwork risers

197
12
12
12

T+23GU19590

Sanitary riser

12 21-Oct-13 A

23-Nov-13

T+23GU19570

Test risers ( 3floors vertically )

12 16-Nov-13

28-Nov-13

T+23GU19550

Ductworks risers

12 15-Oct-13 A

20-Nov-13

T+23GU19560

Chilled water & condensate riser

12 20-Oct-13 A

23-Nov-13

T+23GU19610

Ductwork - supply, make-up air & extract

12 21-Nov-13

05-Dec-13

T+23GU19640

MEP sign off risers (Start)

T+23GU19620

CW supply / return & condensate

18 24-Nov-13

15-Dec-13

T+23GU19630

Plumbing & san distribution

18 24-Nov-13

15-Dec-13

T+23GU19650

FCU connections

18 28-Nov-13

19-Dec-13

T+23GU19660

Cable tray / trunking

12 01-Dec-13

15-Dec-13

T+23GU19670

Sprinkler pipes ( Not drops ) from corridor

18 15-Sep-13 A

14-Dec-13

Bedroom
No DISP
T+23GU21190

MEP Drops in walls & back boxes

0 23-Nov-13

108 05-Dec-13
108 05-Dec-13
12 05-Dec-13

10-Apr-14
10-Apr-14
18-Dec-13

T+23GU21200

Insulate & board walls

12 10-Dec-13

23-Dec-13

T+23GU21210

Ceiling 1st fix

18 15-Dec-13

05-Jan-14

T+23GU21220

Wiring

12 19-Dec-13

02-Jan-14

T+23GU21230

MEP drops in ceiling

12 23-Dec-13

06-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 88 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+23GU21240

Board ceiling

12 24-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
07-Jan-14

T+23GU21250

Tape & Joint walls & ceiling

12 29-Dec-13

12-Jan-14

T+23GU21260

Mist coat all dry lining

12 04-Jan-14

16-Jan-14

T+23GU21270

Install cornice

12 06-Jan-14

19-Jan-14

T+23GU21280

Paint ceiling and cornice

12 11-Jan-14

23-Jan-14

T+23GU21290

Wall covering

12 05-Mar-14

18-Mar-14

T+23GU21300

Install furniture

12 10-Mar-14

23-Mar-14

T+23GU21310

MEP terminations in furniture

12 15-Mar-14

27-Mar-14

T+23GU21320

MEP 3rd fix- sockets, cover plates etc

12 22-Mar-14

03-Apr-14

T+23GU25721

Underlay & Carpet

12 29-Mar-14

10-Apr-14

132 30-Nov-13
132 30-Nov-13
12 30-Nov-13

04-May-14
04-May-14
14-Dec-13

Activity ID

Activity Name

Bathroom
No DISP
T+23GU25860

SS frame to shower & toilet

Duration Start

T+23GU23590

Stud to block walls

12 08-Dec-13

21-Dec-13

T+23GU23600

Waterproof bathroom

12 08-Jan-14

21-Jan-14

T+23GU23610

Flood test

12 15-Jan-14

28-Jan-14

T+23GU23620

MEP Drops in walls & back boxes

12 19-Jan-14

01-Feb-14

T+23GU23630

Install bath

12 19-Jan-14

01-Feb-14

T+23GU23640

Insulate & board walls

12 21-Jan-14

03-Feb-14

T+23GU23650

Framing & board for bath

12 21-Jan-14

03-Feb-14

T+23GU23660

First fix ceiling

12 23-Jan-14

05-Feb-14

T+23GU23670

MEP drops in ceiling

12 26-Jan-14

08-Feb-14

T+23GU23680

2nd fix ceiling incl access panel

12 27-Jan-14

09-Feb-14

T+23GU23700

Stone to floors

12 08-Feb-14

20-Feb-14

T+23GU23710

Stone surround to bath

12 08-Feb-14

20-Feb-14

T+23GU23720

Stone vanity

12 08-Feb-14

20-Feb-14

T+23GU23730

Stone to walls incl niche

12 08-Feb-14

20-Feb-14

T+23GU23740

Casing stone

12 08-Feb-14

20-Feb-14

T+23GU23750

Grout to all stone

12 15-Feb-14

27-Feb-14

T+23GU23690

Install corniche

12 22-Feb-14

06-Mar-14

T+23GU25870

Vanity S/S & Mirrors

12 01-Mar-14

13-Mar-14

T+23GU25880

Vanity Unit

12 01-Mar-14

13-Mar-14

T+23GU23760

Glass Partition

12 08-Mar-14

20-Mar-14

T+23GU23810

Hang glass doors

12 08-Mar-14

20-Mar-14

T+23GU18120

Wall covering

12 13-Mar-14

26-Mar-14

T+23GU23770

Install and connect " Free issue " mirror

12 15-Apr-14

28-Apr-14

T+23GU23780

Sanitary ware and accessories

12 17-Apr-14

30-Apr-14

T+23GU23790

MEP connections to bath and basin

12 19-Apr-14

01-May-14

T+23GU23800

MEP 3rd fix - switch / socket covers

12 21-Apr-14

04-May-14

95 08-Feb-14
95 08-Feb-14
12 08-Feb-14

28-May-14
28-May-14
20-Feb-14

Entrance Vestibule & dressing


No DISP
T+23GU25800 Stone flooring incl grout
T+23GU25710

MEP drops in walls

12 01-Mar-14

13-Mar-14

T+23GU25720

Board walls

12 04-Mar-14

17-Mar-14

T+23GU25730

Ceiling 1st fix

12 06-Mar-14

19-Mar-14

T+23GU25740

MEP drops in ceiling

12 09-Mar-14

22-Mar-14

T+23GU25750

Board ceiling incl access panel

12 12-Mar-14

25-Mar-14

T+23GU25760

Door frames

12 15-Mar-14

27-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 89 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+23GU25770

Tape & joint walls & ceilings

12 15-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
27-Mar-14

T+23GU25780

Mist coat dry lining

12 16-Mar-14

29-Mar-14

T+23GU25790

Paint ceiling

12 18-Mar-14

31-Mar-14

T+23GU25830

Install wardrobe

12 25-Mar-14

07-Apr-14

T+23GU25840

Wall Coverings

12 27-Mar-14

09-Apr-14

T+23GU25820

Mirrors

12 01-Apr-14

14-Apr-14

T+23GU25850

3rd fix MEP

12 08-Apr-14

21-Apr-14

T+23GU25810

Pocket door to bathroom

Activity ID

Activity Name

Corridor
No DISP
T+23GU580

Cable Tray / Trunking

Duration Start

12 15-May-14

28-May-14

144 22-Dec-13
144 22-Dec-13
15 22-Dec-13

08-Jun-14
08-Jun-14
08-Jan-14

12 29-Dec-13

12-Jan-14

6 29-Dec-13

05-Jan-14

T+23GU600

Duct Installation

T+23GR17350

Gypsum Walls

T+23GU610

Electrical Containment

12 05-Jan-14

18-Jan-14

T+23GU590

FP Piping

10 13-Jan-14

23-Jan-14

T+23GR630

Cabling and wire pulling

8 19-Jan-14

27-Jan-14

T+23GU640

Sprinkler Dropper piping Installation

6 25-Jan-14

30-Jan-14

T+23GU650

FP Pipe Pressure Testing

3 01-Feb-14

03-Feb-14

T+23GU670

Sprinkler Installation

4 04-Feb-14

08-Feb-14

T+23GR640

Sprinkler Drops

6 27-Apr-14

03-May-14

T+23GR17360

Gypsum Ceilings

6 27-Apr-14

03-May-14

T+23GR620

Installation of Flexibles / Plenum

4 29-Apr-14

03-May-14

T+23GR680

Grilles / Diffuser Installation

4 04-May-14

07-May-14

T+23GR17370

T & J Walls & Ceilings

6 04-May-14

10-May-14

T+23GR17400

Paint Ceiling

4 11-May-14

14-May-14

T+23GR17390

Millwork

10 15-May-14

26-May-14

T+23GR17380

Wall Covering

4 27-May-14

31-May-14

T+23GR17420

Mirrors

3 27-May-14

29-May-14

T+23GR660

Light Fittings Installation

4 01-Jun-14

04-Jun-14

T+23GR690

FA / SD installation

4 01-Jun-14

04-Jun-14

T+23GR670

Sprinkler Installation

4 01-Jun-14

04-Jun-14

T+23GR17410

Underlay & Carpet

3 05-Jun-14

08-Jun-14

+24 @ +104.60
West Core
Electrical/Telecom Room
Finishes
T+24WR26870 RMX - 01 to floor
T+24WR26880 Permanent door

194 16-Nov-13

03-Jul-14

186
20
3
3

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

22-Jun-14
09-Dec-13
18-Nov-13
18-Nov-13

3 16-Nov-13

18-Nov-13

20 16-Nov-13
3 16-Nov-13

09-Dec-13
18-Nov-13

T+24WR26780 Busbar installation & connection

2 19-Nov-13

20-Nov-13

T+24WR26820 Install IT Panels

2 19-Nov-13

20-Nov-13

T+24WR26830 Install Security Panels

2 19-Nov-13

20-Nov-13

T+24WR26790 Duckwork branch to room

2 21-Nov-13

23-Nov-13

T+24WR26800 Fire alarm cabling

3 24-Nov-13

26-Nov-13

T+24WR26810 Cable terminations

10 27-Nov-13

09-Dec-13

6 16-Nov-13
2 16-Nov-13

21-Nov-13
17-Nov-13

1st & 2nd Fix


T+24WR26890 Electrical Containment

MEP Final Fix


T+24WR26840 Grills & diffusers

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 90 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+24WR26850 Fire alarm devices


T+24WR26860 Light fittings

21-Nov-13
20-Mar-14
20-Mar-14
26-Jan-14

12 08-Mar-14

20-Mar-14

MEP riser summary


No DISP
T+24GU26080 MEP risers & 1st fix

12 27-Jan-14
12 27-Jan-14
12 27-Jan-14

09-Feb-14
09-Feb-14
09-Feb-14

MEP Risers & First Fix


No DISP
T+24GU26110 Ductworks risers

35 27-Jan-14
35 27-Jan-14
12 27-Jan-14

08-Mar-14
08-Mar-14
09-Feb-14

Close blockwork risers

T+24GU26120

Chilled water & condensate

12 03-Feb-14

16-Feb-14

T+24GU26130

DCW / DHW & CCW riser

12 10-Feb-14

23-Feb-14

T+24GU26140

Sanitary riser

12 10-Feb-14

23-Feb-14

T+24GU26150

Hang FCU

12 10-Feb-14

23-Feb-14

T+24GU26160

Ductwork - supply, make-up air & extract

12 10-Feb-14

23-Feb-14

T+24GU26170

CW supply / return & condensate

12 13-Feb-14

26-Feb-14

T+24GU26180

Plumbing & san distribution

12 15-Feb-14

27-Feb-14

T+24GU26190

FCU connections

12 18-Feb-14

03-Mar-14

T+24GU26200

Cable tray / trunking

12 19-Feb-14

04-Mar-14

T+24GU26220

Test risers ( 3floors vertically )

12 22-Feb-14

06-Mar-14

T+24GU26210

Sprinkler pipes ( Not drops ) from corridor

12 23-Feb-14

08-Mar-14

T+24GU26230

MEP sign off risers (Start)

MEP Drops in walls & back boxes

10-May-14
10-May-14
08-Mar-14

T+24GU26250

Insulate & board walls

12 27-Feb-14

12-Mar-14

T+24GU26260

Ceiling 1st fix

18 04-Mar-14

24-Mar-14

T+24GU26270

Wiring

12 09-Mar-14

22-Mar-14

T+24GU26280

MEP drops in ceiling

12 12-Mar-14

25-Mar-14

T+24GU26290

Board ceiling

12 13-Mar-14

26-Mar-14

T+24GU26300

Tape & Joint walls & ceiling

12 18-Mar-14

31-Mar-14

T+24GU26310

Mist coat all dry lining

12 23-Mar-14

05-Apr-14

T+24GU26320

Install cornice

12 25-Mar-14

07-Apr-14

T+24GU26330

Paint ceiling and cornice

12 30-Mar-14

12-Apr-14

T+24GU26340

Wall covering

12 03-Apr-14

16-Apr-14

T+24GU26350

Install furniture

12 08-Apr-14

21-Apr-14

T+24GU26360

MEP terminations in furniture

12 13-Apr-14

26-Apr-14

T+24GU26370

MEP 3rd fix- sockets, cover plates etc

12 20-Apr-14

03-May-14

T+24GU27530

Underlay & Carpet

6 04-May-14

10-May-14
27-May-14
27-May-14
25-Mar-14

Stud to block walls

66 12-Mar-14
66 12-Mar-14
12 12-Mar-14

T+24GU26390

Waterproof bathroom

12 15-Mar-14

27-Mar-14

T+24GU26400

Flood test

12 29-Mar-14

10-Apr-14

T+24GU26410

MEP Drops in walls & back boxes

12 07-Apr-14

20-Apr-14

T+24GU26420

Install bath

12 07-Apr-14

20-Apr-14

T+24GU26430

Insulate & board walls

12 09-Apr-14

22-Apr-14

Bathroom
No DISP
T+24GU26380

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

06-Mar-14

66 23-Feb-14
66 23-Feb-14
12 23-Feb-14

Bedroom
No DISP
T+24GU26240

Revised Programme Rev. D

2 18-Nov-13
2 20-Nov-13

T+24GU26070

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
19-Nov-13

Duration Start

58 13-Jan-14
58 13-Jan-14
12 13-Jan-14

Finishes - 1st Fix


No DISP
T+24GU26060 Studwork incl noggins

Four Seasons Hotel Bahrain

Page 91 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+24GU26440

Framing & board for bath

12 09-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
22-Apr-14

T+24GU26450

First fix ceiling

12 12-Apr-14

24-Apr-14

T+24GU26460

MEP drops in ceiling

12 14-Apr-14

27-Apr-14

T+24GU26470

2nd fix ceiling incl access panel

12 15-Apr-14

28-Apr-14

T+24GU26480

Install corniche

12 17-Apr-14

30-Apr-14

T+24GU26490

Stone to floors

12 21-Apr-14

04-May-14

T+24GU26500

Stone surround to bath

12 21-Apr-14

04-May-14

T+24GU26510

Stone vanity

12 21-Apr-14

04-May-14

T+24GU26520

Stone to walls incl niche

12 21-Apr-14

04-May-14

T+24GU26530

Casing stone

12 21-Apr-14

04-May-14

T+24GU26540

Grout to all stone

12 21-Apr-14

04-May-14

T+24GU26550

Glass Partition

12 05-May-14

18-May-14

T+24GU26560

Install and connect " Free issue " mirror

12 06-May-14

19-May-14

T+24GU26570

Sanitary ware and accessories

12 08-May-14

21-May-14

T+24GU26580

MEP connections to bath and basin

12 10-May-14

22-May-14

T+24GU26590

MEP 3rd fix - switch / socket covers

12 12-May-14

25-May-14

T+24GU26600

Hang glass doors

12 14-May-14

27-May-14

39 09-Apr-14
39 09-Apr-14
12 09-Apr-14

24-May-14
24-May-14
22-Apr-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+24GU26610 MEP drops in walls

Duration Start

T+24GU26620

Board walls

12 13-Apr-14

26-Apr-14

T+24GU26630

Ceiling 1st fix

12 15-Apr-14

28-Apr-14

T+24GU26640

MEP drops in ceiling

12 17-Apr-14

30-Apr-14

T+24GU26650

Board ceiling incl access panel

12 21-Apr-14

04-May-14

T+24GU26670

Tape & joint walls & ceilings

12 23-Apr-14

06-May-14

T+24GU26680

Mist coat dry lining

12 24-Apr-14

07-May-14

T+24GU26690

Paint ceiling

12 27-Apr-14

10-May-14

T+24GU26700

Stone flooring incl grout

12 28-Apr-14

11-May-14

T+24GU26710

Pocket door to bathroom

12 04-May-14

17-May-14

T+24GU26720

Entrance door - Temporary

12 04-May-14

17-May-14

T+24GU26730

Install wardrobe

12 05-May-14

18-May-14

T+24GU26740

Wall Coverings

12 07-May-14

20-May-14

T+24GU26750

3rd fix MEP

12 11-May-14

24-May-14

22 28-May-14
22 28-May-14
3 28-May-14

22-Jun-14
22-Jun-14
31-May-14

Pier Corridors & Lift Lobby


No DISP
W+24GR620
Installation of Flexibles / Plenum
W+24GR640

3 28-May-14

31-May-14

W+24GR17360 Gypsum Ceilings

Sprinkler Drops

4 01-Jun-14

04-Jun-14

W+24GR17400 Paint Ceiling

4 05-Jun-14

09-Jun-14

W+24GR17390 Millwork

6 10-Jun-14

16-Jun-14

W+24GR17380 Wall Covering & fabric panels

4 12-Jun-14

16-Jun-14

W+24GR660

Light Fittings Installation

2 17-Jun-14

18-Jun-14

W+24GR670

Sprinkler Installation

2 17-Jun-14

18-Jun-14

3 19-Jun-14

22-Jun-14

W+24GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+24GU26810 Studwork incl noggins

140
65
65
12

20-Jan-14
20-Jan-14
20-Jan-14
20-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 92 of 180

03-Jul-14
05-Apr-14
05-Apr-14
02-Feb-14
Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

12 23-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
05-Apr-14

MEP riser summary


No DISP
T+24GU26830 MEP risers & 1st fix

12 09-Feb-14
12 09-Feb-14
12 09-Feb-14

22-Feb-14
22-Feb-14
22-Feb-14

MEP Risers & First Fix


No DISP
T+24GU26850 Ductworks risers

36 09-Feb-14
36 09-Feb-14
12 09-Feb-14

22-Mar-14
22-Mar-14
22-Feb-14

Activity ID

Activity Name

T+24GU26820

Close blockwork risers

Duration Start

T+24GU26860

Chilled water & condensate

12 16-Feb-14

01-Mar-14

T+24GU26870

DCW / DHW & CCW riser

12 23-Feb-14

08-Mar-14

T+24GU26880

Sanitary riser

12 23-Feb-14

08-Mar-14

T+24GU26890

Hang FCU

12 23-Feb-14

08-Mar-14

T+24GU26900

Ductwork - supply, make-up air & extract

12 23-Feb-14

08-Mar-14

T+24GU26910

CW supply / return & condensate

12 26-Feb-14

11-Mar-14

T+24GU26920

Plumbing & san distribution

12 27-Feb-14

12-Mar-14

T+24GU26930

FCU connections

12 03-Mar-14

16-Mar-14

T+24GU26940

Cable tray / trunking

12 04-Mar-14

17-Mar-14

T+24GU26950

Sprinkler pipes ( Not drops ) from corridor

12 08-Mar-14

20-Mar-14

T+24GU26960

Test risers ( 3floors vertically )

12 09-Mar-14

22-Mar-14

T+24GU26970

MEP sign off risers (Start)

22-Mar-14

MEP Drops in walls & back boxes

68 11-Mar-14
68 11-Mar-14
12 11-Mar-14

T+24GU26990

Insulate & board walls

12 16-Mar-14

29-Mar-14

T+24GU27000

Ceiling 1st fix

18 20-Mar-14

09-Apr-14

T+24GU27010

Wiring

12 25-Mar-14

07-Apr-14

T+24GU27020

MEP drops in ceiling

12 29-Mar-14

10-Apr-14

T+24GU27030

Board ceiling

12 30-Mar-14

12-Apr-14

T+24GU27040

Tape & Joint walls & ceiling

12 03-Apr-14

16-Apr-14

T+24GU27050

Mist coat all dry lining

12 08-Apr-14

21-Apr-14

T+24GU27060

Install cornice

12 10-Apr-14

23-Apr-14

T+24GU27070

Paint ceiling and cornice

12 15-Apr-14

28-Apr-14

T+24GU27080

Wall covering

6 22-Apr-14

28-Apr-14

T+24GU27090

Install furniture

12 27-Apr-14

10-May-14

T+24GU27100

MEP terminations in furniture

12 01-May-14

14-May-14

T+24GU27110

MEP 3rd fix- sockets, cover plates etc

12 08-May-14

21-May-14

T+24GU27540

Underlay & Carpet

6 22-May-14

28-May-14
03-Jun-14
03-Jun-14
12-Apr-14

Bedroom
No DISP
T+24GU26980

28-May-14
28-May-14
24-Mar-14

Stud to block walls

57 30-Mar-14
57 30-Mar-14
12 30-Mar-14

T+24GU27130

Waterproof bathroom

12 01-Apr-14

14-Apr-14

T+24GU27140

Flood test

12 15-Apr-14

28-Apr-14

T+24GU27150

MEP Drops in walls & back boxes

12 24-Apr-14

07-May-14

T+24GU27160

Install bath

12 24-Apr-14

07-May-14

T+24GU27170

Insulate & board walls

12 27-Apr-14

10-May-14

T+24GU27180

Framing & board for bath

12 27-Apr-14

10-May-14

T+24GU27230

Stone to floors

12 28-Apr-14

11-May-14

T+24GU27240

Stone surround to bath

12 28-Apr-14

11-May-14

T+24GU27250

Stone vanity

12 28-Apr-14

11-May-14

T+24GU27260

Stone to walls incl niche

12 28-Apr-14

11-May-14

Bathroom
No DISP
T+24GU27120

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 93 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+24GU27270

Casing stone

12 28-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
11-May-14

T+24GU27280

Grout to all stone

12 28-Apr-14

11-May-14

T+24GU27190

First fix ceiling

12 29-Apr-14

12-May-14

T+24GU27200

MEP drops in ceiling

12 01-May-14

14-May-14

T+24GU27210

2nd fix ceiling incl access panel

12 03-May-14

15-May-14

T+24GU27220

Install corniche

12 05-May-14

18-May-14

T+24GU27290

Glass Partition

12 12-May-14

25-May-14

T+24GU27300

Install and connect " Free issue " mirror

12 13-May-14

26-May-14

T+24GU27310

Sanitary ware and accessories

12 15-May-14

28-May-14

T+24GU27320

MEP connections to bath and basin

12 17-May-14

29-May-14

T+24GU27330

MEP 3rd fix - switch / socket covers

12 19-May-14

01-Jun-14

T+24GU27340

Hang glass doors

12 21-May-14

03-Jun-14

27 01-May-14
27 01-May-14
12 01-May-14

01-Jun-14
01-Jun-14
14-May-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+24GU27350 MEP drops in walls

Duration Start

T+24GU27360

Board walls

12 05-May-14

18-May-14

T+24GU27440

Stone flooring incl grout

12 05-May-14

18-May-14

T+24GU27370

Ceiling 1st fix

12 07-May-14

20-May-14

T+24GU27380

MEP drops in ceiling

12 10-May-14

22-May-14

T+24GU27450

Pocket door to bathroom

12 11-May-14

24-May-14

T+24GU27460

Entrance door - Temporary

12 11-May-14

24-May-14

T+24GU27470

Install wardrobe

12 12-May-14

25-May-14

T+24GU27390

Board ceiling incl access panel

12 13-May-14

26-May-14

T+24GU27480

Wall Coverings

12 14-May-14

27-May-14

T+24GU27410

Tape & joint walls & ceilings

12 15-May-14

28-May-14

T+24GU27420

Mist coat dry lining

12 17-May-14

29-May-14

T+24GU27490

3rd fix MEP

12 18-May-14

31-May-14

T+24GU27430

Paint ceiling

12 19-May-14

01-Jun-14

Pier Corridors & Lift Lobby


No DISP
E+24GR620
Installation of Flexibles / Plenum

24 04-Jun-14
24 04-Jun-14
3 04-Jun-14

03-Jul-14
03-Jul-14
07-Jun-14

E+24GR640

3 04-Jun-14

07-Jun-14

E+24GR17360 Gypsum Ceilings

Sprinkler Drops

6 08-Jun-14

14-Jun-14

E+24GR17400 Paint Ceiling

4 15-Jun-14

18-Jun-14

E+24GR17390 Millwork

6 19-Jun-14

25-Jun-14

E+24GR17380 Wall Covering & fabric panels

4 22-Jun-14

25-Jun-14

E+24GR660

Light Fittings Installation

2 26-Jun-14

28-Jun-14

E+24GR670

Sprinkler Installation

2 26-Jun-14

28-Jun-14

3 29-Jun-14

03-Jul-14

E+24GR17410 Underlay & Carpet

27-Nov-13
28-Jan-14
28-Jan-14
28-Jan-14

15-Jun-14
10-Feb-14
10-Feb-14
10-Feb-14

MEP riser summary


No DISP
T+24GU18420 MEP risers & 1st fix Riser 1

18 27-Nov-13
18 27-Nov-13
18 27-Nov-13

18-Dec-13
18-Dec-13
18-Dec-13

MEP Risers & First Fix


No DISP
T+24GU19680 Ductworks risers

51 27-Nov-13
51 27-Nov-13
12 27-Nov-13

27-Jan-14
27-Jan-14
11-Dec-13

Guestrooms
Finishes - 1st Fix
No DISP
T+24GU18000 Close blockwork risers

170
12
12
12

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 94 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+24GU19790

Cable tray / trunking

12 05-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
18-Dec-13

T+24GU19690

Chilled water & condensate risers

12 05-Dec-13

18-Dec-13

T+24GU19710

DCW / DHW & CCW riser

12 12-Dec-13

25-Dec-13

T+24GU19720

Sanitary riser

12 19-Dec-13

02-Jan-14

T+24GU19730

Hang FCU

12 19-Dec-13

02-Jan-14

T+24GU19750

CW supply / return & condensate

12 23-Dec-13

06-Jan-14

T+24GU19780

FCU connections

12 28-Dec-13

11-Jan-14

T+24GU19800

Sprinkler pipes ( Not drops ) from corridor

18 02-Jan-14

22-Jan-14

T+24GU19740

Ductwork - supply, make-up air & extract

18 04-Jan-14

23-Jan-14

T+24GU19760

Plumbing & san distribution

12 04-Jan-14

16-Jan-14

T+24GU19700

Test risers ( 3floors vertically )

12 14-Jan-14

27-Jan-14

T+24GU19770

MEP sign off risers (Start)

Activity ID

Activity Name

Bedroom
No DISP
T+24GU21330

MEP Drops in walls & back boxes

Duration Start

27-Jan-14

110 19-Dec-13
110 19-Dec-13
12 19-Dec-13

27-Apr-14
27-Apr-14
02-Jan-14

T+24GU21340

Insulate & board walls

12 24-Dec-13

07-Jan-14

T+24GU21350

Ceiling 1st fix

18 29-Dec-13

19-Jan-14

T+24GU21360

Wiring

12 04-Jan-14

16-Jan-14

T+24GU21370

MEP drops in ceiling

12 07-Jan-14

20-Jan-14

T+24GU21380

Board ceiling

12 08-Jan-14

21-Jan-14

T+24GU21390

Tape & Joint walls & ceiling

12 13-Jan-14

26-Jan-14

T+24GU21400

Mist coat all dry lining

12 18-Jan-14

30-Jan-14

T+24GU21410

Install cornice

12 20-Jan-14

02-Feb-14

T+24GU21420

Paint ceiling and cornice

12 25-Jan-14

06-Feb-14

T+24GU21430

Wall covering

12 17-Mar-14

30-Mar-14

T+24GU21440

Install furniture

12 22-Mar-14

03-Apr-14

T+24GU21450

MEP terminations in furniture

12 26-Mar-14

08-Apr-14

T+24GU21460

MEP 3rd fix- sockets, cover plates etc

12 31-Mar-14

13-Apr-14

T+24GU25871

Underlay & Carpet

12 14-Apr-14

27-Apr-14

132 08-Dec-13
132 08-Dec-13
12 08-Dec-13

11-May-14
11-May-14
21-Dec-13

Bathroom
No DISP
T+24GU27500

SS frame to shower & toilet

T+24GU23820

Stud to block walls

12 02-Feb-14

15-Feb-14

T+24GU23830

Waterproof bathroom

12 04-Feb-14

17-Feb-14

T+24GU23840

Flood test

12 09-Feb-14

22-Feb-14

T+24GU23930

Stone to floors

12 15-Feb-14

27-Feb-14

T+24GU23940

Stone surround to bath

12 15-Feb-14

27-Feb-14

T+24GU23950

Stone vanity

12 15-Feb-14

27-Feb-14

T+24GU23960

Stone to walls incl niche

12 15-Feb-14

27-Feb-14

T+24GU23970

Casing stone

12 15-Feb-14

27-Feb-14

T+24GU23850

MEP Drops in walls & back boxes

12 18-Feb-14

03-Mar-14

T+24GU23860

Install bath

12 18-Feb-14

03-Mar-14

T+24GU23870

Insulate & board walls

12 20-Feb-14

05-Mar-14

T+24GU23880

Framing & board for bath

12 20-Feb-14

05-Mar-14

T+24GU23980

Grout to all stone

12 22-Feb-14

06-Mar-14

T+24GU23890

First fix ceiling

12 23-Feb-14

08-Mar-14

T+24GU23900

MEP drops in ceiling

12 25-Feb-14

10-Mar-14

T+24GU23910

2nd fix ceiling incl access panel

12 26-Feb-14

11-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 95 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+24GU23920

Install corniche

12 01-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
13-Mar-14

T+24GU27510

Vanity S/S & Mirrors

12 01-Mar-14

13-Mar-14

T+24GU27520

Vanity Unit

12 01-Mar-14

13-Mar-14

T+24GU23990

Glass Partition

12 08-Mar-14

20-Mar-14

T+24GU24040

Hang glass doors

12 08-Mar-14

20-Mar-14

T+24GU18120

Wall covering

12 25-Mar-14

07-Apr-14

T+24GU24000

Install and connect " Free issue " mirror

12 22-Apr-14

05-May-14

T+24GU24010

Sanitary ware and accessories

12 24-Apr-14

07-May-14

T+24GU24020

MEP connections to bath and basin

12 26-Apr-14

08-May-14

T+24GU24030

MEP 3rd fix - switch / socket covers

12 28-Apr-14

11-May-14

95 15-Feb-14
95 15-Feb-14
12 15-Feb-14

04-Jun-14
04-Jun-14
27-Feb-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+24GU25950 Stone flooring incl grout

Duration Start

T+24GU25860

MEP drops in walls

12 20-Feb-14

05-Mar-14

T+24GU25870

Board walls

12 08-Mar-14

20-Mar-14

T+24GU25880

Ceiling 1st fix

12 10-Mar-14

23-Mar-14

T+24GU25890

MEP drops in ceiling

12 12-Mar-14

25-Mar-14

T+24GU25900

Board ceiling incl access panel

12 16-Mar-14

29-Mar-14

T+24GU25910

Door frames

12 18-Mar-14

31-Mar-14

T+24GU25920

Tape & joint walls & ceilings

12 18-Mar-14

31-Mar-14

T+24GU25930

Mist coat dry lining

12 19-Mar-14

01-Apr-14

T+24GU25940

Paint ceiling

12 22-Mar-14

03-Apr-14

T+24GU25980

Install wardrobe

12 29-Mar-14

10-Apr-14

T+24GU25990

Wall Coverings

12 31-Mar-14

13-Apr-14

T+24GU25970

Mirrors

12 05-Apr-14

17-Apr-14

T+24GU26000

3rd fix MEP

12 12-Apr-14

24-Apr-14

T+24GU25960

Pocket door to bathroom

12 22-May-14

04-Jun-14

145 28-Dec-13
145 28-Dec-13
15 28-Dec-13

15-Jun-14
15-Jun-14
14-Jan-14

Corridor
No DISP
T+24GU580

Cable Tray / Trunking

T+24GR17350

Gypsum Walls

6 29-Dec-13

05-Jan-14

T+24GU600

Duct Installation

12 05-Jan-14

18-Jan-14

T+24GU610

Electrical Containment

12 11-Jan-14

23-Jan-14

T+24GU590

FP Piping

10 19-Jan-14

29-Jan-14

T+24GR630

Cabling and wire pulling

8 25-Jan-14

02-Feb-14

T+24GU640

Sprinkler Dropper piping Installation

6 30-Jan-14

05-Feb-14

T+24GU650

FP Pipe Pressure Testing

3 06-Feb-14

09-Feb-14

T+24GR17360

Gypsum Ceilings

6 04-May-14

10-May-14

T+24GR620

Installation of Flexibles / Plenum

4 06-May-14

10-May-14

T+24GR640

Sprinkler Drops

4 06-May-14

10-May-14

T+24GR680

Grilles / Diffuser Installation

4 11-May-14

14-May-14

T+24GR17370

T & J Walls & Ceilings

6 11-May-14

17-May-14

T+24GR17400

Paint Ceiling

T+24GR17390

Millwork

T+24GR17380

4 18-May-14

21-May-14

10 22-May-14

02-Jun-14

Wall Covering

4 03-Jun-14

07-Jun-14

T+24GR17420

Mirrors

3 03-Jun-14

05-Jun-14

T+24GR660

Light Fittings Installation

4 08-Jun-14

11-Jun-14

T+24GR690

FA / SD installation

4 08-Jun-14

11-Jun-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 96 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+24GR670

Sprinkler Installation

T+24GR17410

Underlay & Carpet

+25 @ +108.40
West Core
Electrical/Telecom Room
Finishes
T+25WR26870 RMX - 01 to floor
T+25WR26880 Permanent door

3 12-Jun-14

15-Jun-14

214 19-Oct-13 A

13-Jul-14

187
29
3
3

19-Nov-13
19-Nov-13
21-Dec-13
21-Dec-13

26-Jun-14
23-Dec-13
23-Dec-13
23-Dec-13
23-Dec-13
12-Dec-13
21-Nov-13

T+25WR26780 Busbar installation & connection

2 23-Nov-13

24-Nov-13

T+25WR26820 Install IT Panels

2 23-Nov-13

24-Nov-13

T+25WR26830 Install Security Panels

2 23-Nov-13

24-Nov-13

T+25WR26790 Duckwork branch to room

2 25-Nov-13

26-Nov-13

T+25WR26800 Fire alarm cabling

3 27-Nov-13

30-Nov-13

T+25WR26810 Cable terminations

10 01-Dec-13

12-Dec-13

6 14-Dec-13
2 14-Dec-13

19-Dec-13
15-Dec-13

2 16-Dec-13

17-Dec-13

T+25WR26850 Fire alarm devices


T+25WR26860 Light fittings

2 18-Dec-13

19-Dec-13

Finishes - 1st Fix


No DISP
T+25WR26060 Studwork incl noggins

58 20-Jan-14
58 20-Jan-14
12 20-Jan-14

27-Mar-14
27-Mar-14
02-Feb-14

T+25WR26070 Close blockwork risers

12 15-Mar-14

27-Mar-14

MEP riser summary


No DISP
T+25WR26080 MEP risers & 1st fix

12 03-Feb-14
12 03-Feb-14
12 03-Feb-14

16-Feb-14
16-Feb-14
16-Feb-14

MEP Risers & First Fix


No DISP
T+25WR26110 Ductworks risers

35 03-Feb-14
35 03-Feb-14
12 03-Feb-14

15-Mar-14
15-Mar-14
16-Feb-14

T+25WR26120 Chilled water & condensate

12 10-Feb-14

23-Feb-14

T+25WR26130 DCW / DHW & CCW riser

12 17-Feb-14

02-Mar-14

T+25WR26140 Sanitary riser

12 17-Feb-14

02-Mar-14

T+25WR26150 Hang FCU

12 17-Feb-14

02-Mar-14

T+25WR26160 Ductwork - supply, make-up air & extract

12 17-Feb-14

02-Mar-14

T+25WR26170 CW supply / return & condensate

12 20-Feb-14

05-Mar-14

T+25WR26180 Plumbing & san distribution

12 22-Feb-14

06-Mar-14

T+25WR26190 FCU connections

12 25-Feb-14

10-Mar-14

T+25WR26200 Cable tray / trunking

12 26-Feb-14

11-Mar-14

T+25WR26220 Test risers ( 3floors vertically )

12 01-Mar-14

13-Mar-14

T+25WR26210 Sprinkler pipes ( Not drops ) from corridor

12 02-Mar-14

15-Mar-14

T+25WR26230 MEP sign off risers (Start)

20-May-14
20-May-14
18-Mar-14

T+25WR26250 Insulate & board walls

12 10-Mar-14

23-Mar-14

T+25WR26260 Ceiling 1st fix

18 15-Mar-14

03-Apr-14

T+25WR26270 Wiring

12 19-Mar-14

01-Apr-14

T+25WR26280 MEP drops in ceiling

12 23-Mar-14

05-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

13-Mar-14

66 05-Mar-14
66 05-Mar-14
12 05-Mar-14

Bedroom
No DISP
T+25WR26240 MEP Drops in walls & back boxes

Revised Programme Rev. D

4 08-Jun-14

3 21-Dec-13

MEP Final Fix


T+25WR26840 Grills & diffusers

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
11-Jun-14

Duration Start

20 19-Nov-13
3 19-Nov-13

1st & 2nd Fix


T+25WR26890 Electrical Containment

Four Seasons Hotel Bahrain

Page 97 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+25WR26290 Board ceiling

12 24-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
06-Apr-14

T+25WR26300 Tape & Joint walls & ceiling

12 29-Mar-14

10-Apr-14

T+25WR26310 Mist coat all dry lining

12 02-Apr-14

15-Apr-14

T+25WR26320 Install cornice

12 05-Apr-14

17-Apr-14

T+25WR26330 Paint ceiling and cornice

12 09-Apr-14

22-Apr-14

T+25WR26340 Wall covering

12 14-Apr-14

27-Apr-14

T+25WR26350 Install furniture

12 19-Apr-14

01-May-14

T+25WR26360 MEP terminations in furniture

12 23-Apr-14

06-May-14

T+25WR26370 MEP 3rd fix- sockets, cover plates etc

12 30-Apr-14

13-May-14

Activity ID

Activity Name

Duration Start

T+25WR26760 Underlay & Carpet

6 14-May-14

20-May-14

Bathroom
No DISP
T+25WR26380 Stud to block walls

64 22-Mar-14
64 22-Mar-14
12 22-Mar-14

03-Jun-14
03-Jun-14
03-Apr-14

T+25WR26390 Waterproof bathroom

12 24-Mar-14

06-Apr-14

T+25WR26400 Flood test

12 31-Mar-14

13-Apr-14

T+25WR26410 MEP Drops in walls & back boxes

12 09-Apr-14

22-Apr-14

T+25WR26420 Install bath

12 09-Apr-14

22-Apr-14

T+25WR26430 Insulate & board walls

12 12-Apr-14

24-Apr-14

T+25WR26440 Framing & board for bath

12 12-Apr-14

24-Apr-14

T+25WR26450 First fix ceiling

12 14-Apr-14

27-Apr-14

T+25WR26460 MEP drops in ceiling

12 16-Apr-14

29-Apr-14

T+25WR26470 2nd fix ceiling incl access panel

12 17-Apr-14

30-Apr-14

T+25WR26480 Install corniche

12 20-Apr-14

03-May-14

T+25WR26490 Stone to floors

12 28-Apr-14

11-May-14

T+25WR26500 Stone surround to bath

12 28-Apr-14

11-May-14

T+25WR26510 Stone vanity

12 28-Apr-14

11-May-14

T+25WR26520 Stone to walls incl niche

12 28-Apr-14

11-May-14

T+25WR26530 Casing stone

12 28-Apr-14

11-May-14

T+25WR26540 Grout to all stone

12 28-Apr-14

11-May-14

T+25WR26550 Glass Partition

12 12-May-14

25-May-14

T+25WR26560 Install and connect " Free issue " mirror

12 13-May-14

26-May-14

T+25WR26570 Sanitary ware and accessories

12 15-May-14

28-May-14

T+25WR26580 MEP connections to bath and basin

12 17-May-14

29-May-14

T+25WR26590 MEP 3rd fix - switch / socket covers

12 19-May-14

01-Jun-14

T+25WR26600 Hang glass doors

12 21-May-14

03-Jun-14

Entrance Vestibule & dressing


No DISP
T+25WR26610 MEP drops in walls

40 16-Apr-14
40 16-Apr-14
12 16-Apr-14

01-Jun-14
01-Jun-14
29-Apr-14

T+25WR26620 Board walls

12 20-Apr-14

03-May-14

T+25WR26630 Ceiling 1st fix

12 22-Apr-14

05-May-14

T+25WR26640 MEP drops in ceiling

12 24-Apr-14

07-May-14

T+25WR26650 Board ceiling incl access panel

12 28-Apr-14

11-May-14

T+25WR26670 Tape & joint walls & ceilings

12 30-Apr-14

13-May-14

T+25WR26680 Mist coat dry lining

12 01-May-14

14-May-14

T+25WR26690 Paint ceiling

12 04-May-14

17-May-14

T+25WR26700 Stone flooring incl grout

12 06-May-14

19-May-14

T+25WR26710 Pocket door to bathroom

12 12-May-14

25-May-14

T+25WR26720 Entrance door - Temporary

12 12-May-14

25-May-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 98 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+25WR26730 Install wardrobe

12 13-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
26-May-14

T+25WR26740 Wall Coverings

12 15-May-14

28-May-14

T+25WR26750 3rd fix MEP

12 19-May-14

01-Jun-14

20 04-Jun-14
20 04-Jun-14
3 04-Jun-14

26-Jun-14
26-Jun-14
07-Jun-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+25GR620
Installation of Flexibles / Plenum
W+25GR640

Sprinkler Drops

Duration Start

3 04-Jun-14

07-Jun-14

W+25GR17360 Gypsum Ceilings

4 08-Jun-14

11-Jun-14

W+25GR17400 Paint Ceiling

2 12-Jun-14

14-Jun-14

W+25GR17390 Millwork

6 15-Jun-14

21-Jun-14

W+25GR17380 Wall Covering & fabric panels

4 17-Jun-14

21-Jun-14

W+25GR660

Light Fittings Installation

2 22-Jun-14

23-Jun-14

W+25GR670

Sprinkler Installation

2 22-Jun-14

23-Jun-14

3 24-Jun-14

26-Jun-14

W+25GR17410 Underlay & Carpet

27-Jan-14
27-Jan-14
27-Jan-14
27-Jan-14

13-Jul-14
09-Apr-14
09-Apr-14
09-Feb-14

12 27-Mar-14

09-Apr-14

MEP riser summary


No DISP
T+25ER26080 MEP risers & 1st fix

12 16-Feb-14
12 16-Feb-14
12 16-Feb-14

01-Mar-14
01-Mar-14
01-Mar-14

MEP Risers & First Fix


No DISP
T+25ER26110 Ductworks risers

35 16-Feb-14
35 16-Feb-14
12 16-Feb-14

27-Mar-14
27-Mar-14
01-Mar-14

East Core
Finishes - 1st Fix
No DISP
T+25ER26060 Studwork incl noggins
T+25ER26070

Close blockwork risers

140
63
63
12

T+25ER26120

Chilled water & condensate

12 23-Feb-14

08-Mar-14

T+25ER26130

DCW / DHW & CCW riser

12 02-Mar-14

15-Mar-14

T+25ER26140

Sanitary riser

12 02-Mar-14

15-Mar-14

T+25ER26150

Hang FCU

12 02-Mar-14

15-Mar-14

T+25ER26160

Ductwork - supply, make-up air & extract

12 02-Mar-14

15-Mar-14

T+25ER26170

CW supply / return & condensate

12 05-Mar-14

18-Mar-14

T+25ER26180

Plumbing & san distribution

12 06-Mar-14

19-Mar-14

T+25ER26190

FCU connections

12 10-Mar-14

23-Mar-14

T+25ER26200

Cable tray / trunking

12 11-Mar-14

24-Mar-14

T+25ER26220

Test risers ( 3floors vertically )

12 13-Mar-14

26-Mar-14

T+25ER26210

Sprinkler pipes ( Not drops ) from corridor

12 15-Mar-14

27-Mar-14

T+25ER26230

MEP sign off risers (Start)

26-Mar-14

MEP Drops in walls & back boxes

68 18-Mar-14
68 18-Mar-14
12 18-Mar-14

04-Jun-14
04-Jun-14
31-Mar-14

T+25ER26250

Insulate & board walls

12 23-Mar-14

05-Apr-14

T+25ER26260

Ceiling 1st fix

18 27-Mar-14

16-Apr-14

T+25ER26270

Wiring

12 01-Apr-14

14-Apr-14

T+25ER26280

MEP drops in ceiling

12 05-Apr-14

17-Apr-14

T+25ER26290

Board ceiling

12 06-Apr-14

19-Apr-14

T+25ER26300

Tape & Joint walls & ceiling

12 10-Apr-14

23-Apr-14

T+25ER26310

Mist coat all dry lining

12 15-Apr-14

28-Apr-14

T+25ER26320

Install cornice

12 17-Apr-14

30-Apr-14

T+25ER26330

Paint ceiling and cornice

12 22-Apr-14

05-May-14

Bedroom
No DISP
T+25ER26240

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 99 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

Wall covering

6 29-Apr-14

T+25ER26350

Install furniture

12 04-May-14

17-May-14

T+25ER26360

MEP terminations in furniture

12 08-May-14

21-May-14

T+25ER26370

MEP 3rd fix- sockets, cover plates etc

12 15-May-14

28-May-14

T+25ER26760

Underlay & Carpet

6 29-May-14

04-Jun-14

Stud to block walls

59 03-Apr-14
59 03-Apr-14
12 03-Apr-14

T+25ER26390

Waterproof bathroom

12 06-Apr-14

19-Apr-14

T+25ER26400

Flood test

12 13-Apr-14

26-Apr-14

T+25ER26410

MEP Drops in walls & back boxes

12 22-Apr-14

05-May-14

T+25ER26420

Install bath

12 22-Apr-14

05-May-14

T+25ER26430

Insulate & board walls

12 24-Apr-14

07-May-14

T+25ER26440

Framing & board for bath

12 24-Apr-14

07-May-14

T+25ER26450

First fix ceiling

12 27-Apr-14

10-May-14

T+25ER26460

MEP drops in ceiling

12 29-Apr-14

12-May-14

T+25ER26470

2nd fix ceiling incl access panel

12 30-Apr-14

13-May-14

T+25ER26480

Install corniche

12 03-May-14

15-May-14

T+25ER26490

Stone to floors

12 05-May-14

18-May-14

T+25ER26500

Stone surround to bath

12 05-May-14

18-May-14

T+25ER26510

Stone vanity

12 05-May-14

18-May-14

T+25ER26520

Stone to walls incl niche

12 05-May-14

18-May-14

T+25ER26530

Casing stone

12 05-May-14

18-May-14

T+25ER26540

Grout to all stone

12 05-May-14

18-May-14

T+25ER26550

Glass Partition

12 19-May-14

01-Jun-14

T+25ER26560

Install and connect " Free issue " mirror

12 20-May-14

02-Jun-14

T+25ER26570

Sanitary ware and accessories

12 22-May-14

04-Jun-14

T+25ER26580

MEP connections to bath and basin

12 24-May-14

05-Jun-14

T+25ER26590

MEP 3rd fix - switch / socket covers

12 26-May-14

08-Jun-14

T+25ER26600

Hang glass doors

12 28-May-14

10-Jun-14

34 29-Apr-14
34 29-Apr-14
12 29-Apr-14

07-Jun-14
07-Jun-14
12-May-14

Entrance Vestibule & dressing


No DISP
T+25ER26610 MEP drops in walls

10-Jun-14
10-Jun-14
16-Apr-14

T+25ER26620

Board walls

12 03-May-14

15-May-14

T+25ER26630

Ceiling 1st fix

12 05-May-14

18-May-14

T+25ER26640

MEP drops in ceiling

12 07-May-14

20-May-14

T+25ER26650

Board ceiling incl access panel

12 11-May-14

24-May-14

T+25ER26700

Stone flooring incl grout

12 12-May-14

25-May-14

T+25ER26670

Tape & joint walls & ceilings

12 13-May-14

26-May-14

T+25ER26680

Mist coat dry lining

12 14-May-14

27-May-14

T+25ER26690

Paint ceiling

12 17-May-14

29-May-14

T+25ER26710

Pocket door to bathroom

12 18-May-14

31-May-14

T+25ER26720

Entrance door - Temporary

12 18-May-14

31-May-14

T+25ER26730

Install wardrobe

12 19-May-14

01-Jun-14

T+25ER26740

Wall Coverings

12 21-May-14

03-Jun-14

T+25ER26750

3rd fix MEP

12 25-May-14

07-Jun-14

24 11-Jun-14
24 11-Jun-14

13-Jul-14
13-Jul-14

Pier Corridors & Lift Lobby


No DISP
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 100 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
05-May-14

T+25ER26340

Bathroom
No DISP
T+25ER26380

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

E+25GR620

Installation of Flexibles / Plenum

3 11-Jun-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
14-Jun-14

E+25GR640

Sprinkler Drops

Activity ID

Activity Name

Duration Start

3 11-Jun-14

14-Jun-14

E+25GR17360 Gypsum Ceilings

6 15-Jun-14

21-Jun-14

E+25GR17400 Paint Ceiling

4 22-Jun-14

25-Jun-14

E+25GR17390 Millwork

6 26-Jun-14

05-Jul-14

E+25GR17380 Wall Covering & fabric panels

4 29-Jun-14

05-Jul-14

E+25GR660

Light Fittings Installation

2 06-Jul-14

08-Jul-14

E+25GR670

Sprinkler Installation

2 06-Jul-14

08-Jul-14

3 10-Jul-14

13-Jul-14

E+25GR17410 Underlay & Carpet


Guestrooms
Finishes - 1st Fix
No DISP
T+25GU18060 Studwork to walls incl noggins
T+25GU18070

Close blockwork risers

200
87
87
18

19-Oct-13 A
19-Oct-13 A
19-Oct-13 A
19-Oct-13 A

22-Jun-14
10-Feb-14
10-Feb-14
20-Nov-13

12 28-Jan-14

10-Feb-14

MEP riser summary


No DISP
T+25GU18450 MEP risers & 1st fix Riser 1

18 12-Dec-13
18 12-Dec-13
18 12-Dec-13

02-Jan-14
02-Jan-14
02-Jan-14

MEP Risers & First Fix


No DISP
T+25GU19810 Ductworks risers

41 12-Dec-13
41 12-Dec-13
12 12-Dec-13

29-Jan-14
29-Jan-14
25-Dec-13

T+25GU19820

Chilled water & condensate riser

12 19-Dec-13

02-Jan-14

T+25GU19840

DCW / DHW & CCW riser

12 26-Dec-13

09-Jan-14

T+25GU19850

Sanitary riser

12 26-Dec-13

09-Jan-14

T+25GU19860

Hang FCU

12 26-Dec-13

09-Jan-14

T+25GU19870

Ductwork - supply, make-up air & extract

12 26-Dec-13

09-Jan-14

T+25GU19880

CW supply / return & condensate

12 30-Dec-13

13-Jan-14

T+25GU19890

Plumbing & san distribution

12 31-Dec-13

14-Jan-14

T+25GU19910

FCU connections

12 05-Jan-14

18-Jan-14

T+25GU19920

Cable tray / trunking

12 06-Jan-14

19-Jan-14

T+25GU19930

Sprinkler pipes ( Not drops ) from corridor

18 09-Jan-14

29-Jan-14

T+25GU19830

Test risers ( 3floors vertically )

12 14-Jan-14

27-Jan-14

T+25GU19900

MEP sign off risers (Start)

27-Jan-14

MEP Drops in walls & back boxes

93 09-Jan-14
93 09-Jan-14
12 09-Jan-14

T+25GU21480

Insulate & board walls

12 14-Jan-14

27-Jan-14

T+25GU21490

Ceiling 1st fix

12 19-Jan-14

01-Feb-14

T+25GU21500

Wiring

12 23-Jan-14

05-Feb-14

T+25GU21510

MEP drops in ceiling

12 27-Jan-14

09-Feb-14

T+25GU21520

Board ceiling

12 28-Jan-14

10-Feb-14

T+25GU21530

Tape & Joint walls & ceiling

12 02-Feb-14

15-Feb-14

T+25GU21540

Mist coat all dry lining

12 06-Feb-14

19-Feb-14

T+25GU21550

Install cornice

12 09-Feb-14

22-Feb-14

T+25GU21560

Paint ceiling and cornice

12 13-Feb-14

26-Feb-14

T+25GU21570

Wall covering

12 24-Mar-14

06-Apr-14

T+25GU21580

Install furniture

12 29-Mar-14

10-Apr-14

T+25GU21590

MEP terminations in furniture

12 02-Apr-14

15-Apr-14

T+25GU21600

MEP 3rd fix- sockets, cover plates etc

12 07-Apr-14

20-Apr-14

T+25GU27511

Underlay & Carpet

12 14-Apr-14

27-Apr-14

Bedroom
No DISP
T+25GU21470

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 101 of 180

27-Apr-14
27-Apr-14
22-Jan-14

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Bathroom
No DISP
T+25GU26160

SS frame to shower & toilet

Duration Start

132 15-Dec-13
132 15-Dec-13
12 15-Dec-13

Stud to block walls

12 02-Feb-14

15-Feb-14

T+25GU24060

Waterproof bathroom

12 11-Feb-14

24-Feb-14

T+25GU24070

Flood test

12 16-Feb-14

01-Mar-14

T+25GU24160

Stone to floors

12 22-Feb-14

06-Mar-14

T+25GU24170

Stone surround to bath

12 22-Feb-14

06-Mar-14

T+25GU24180

Stone vanity

12 22-Feb-14

06-Mar-14

T+25GU24190

Stone to walls incl niche

12 22-Feb-14

06-Mar-14

T+25GU24200

Casing stone

12 22-Feb-14

06-Mar-14

T+25GU24080

MEP Drops in walls & back boxes

12 25-Feb-14

10-Mar-14

T+25GU24090

Install bath

12 25-Feb-14

10-Mar-14

T+25GU24100

Insulate & board walls

12 27-Feb-14

12-Mar-14

T+25GU24110

Framing & board for bath

12 27-Feb-14

12-Mar-14

T+25GU24210

Grout to all stone

12 01-Mar-14

13-Mar-14

T+25GU24120

First fix ceiling

12 02-Mar-14

15-Mar-14

T+25GU24130

MEP drops in ceiling

12 04-Mar-14

17-Mar-14

T+25GU24140

2nd fix ceiling incl access panel

12 05-Mar-14

18-Mar-14

T+25GU24150

Install corniche

12 08-Mar-14

20-Mar-14

T+25GU27521

Vanity S/S & Mirrors

12 08-Mar-14

20-Mar-14

T+25GU27531

Vanity Unit

12 08-Mar-14

20-Mar-14

T+25GU24220

Glass Partition

12 15-Mar-14

27-Mar-14

T+25GU24270

Hang glass doors

12 15-Mar-14

27-Mar-14

T+25GU18120

Wall covering

12 01-Apr-14

14-Apr-14

T+25GU24230

Install and connect " Free issue " mirror

12 29-Apr-14

12-May-14

T+25GU24240

Sanitary ware and accessories

12 01-May-14

14-May-14

T+25GU24250

MEP connections to bath and basin

12 03-May-14

15-May-14

T+25GU24260

MEP 3rd fix - switch / socket covers

12 05-May-14

18-May-14

95 22-Feb-14
95 22-Feb-14
12 22-Feb-14

11-Jun-14
11-Jun-14
06-Mar-14

T+25GU26010

MEP drops in walls

12 27-Feb-14

12-Mar-14

T+25GU26020

Board walls

12 08-Mar-14

20-Mar-14

T+25GU26030

Ceiling 1st fix

12 10-Mar-14

23-Mar-14

T+25GU26040

MEP drops in ceiling

12 12-Mar-14

25-Mar-14

T+25GU26050

Board ceiling incl access panel

12 16-Mar-14

29-Mar-14

T+25GU26060

Door frames

12 18-Mar-14

31-Mar-14

T+25GU26070

Tape & joint walls & ceilings

12 18-Mar-14

31-Mar-14

T+25GU26080

Mist coat dry lining

12 19-Mar-14

01-Apr-14

T+25GU26090

Paint ceiling

12 22-Mar-14

03-Apr-14

T+25GU26130

Install wardrobe

12 29-Mar-14

10-Apr-14

T+25GU26140

Wall Coverings

12 31-Mar-14

13-Apr-14

T+25GU26120

Mirrors

12 05-Apr-14

17-Apr-14

T+25GU26150

3rd fix MEP

12 12-Apr-14

24-Apr-14

T+25GU26110

Pocket door to bathroom

12 29-May-14

11-Jun-14

146 04-Jan-14
146 04-Jan-14

22-Jun-14
22-Jun-14

Corridor
No DISP
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 102 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
18-May-14
18-May-14
28-Dec-13

T+25GU24050

Entrance Vestibule & dressing


No DISP
T+25GU26100 Stone flooring incl grout

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

Cable Tray / Trunking

T+25GR17350

Gypsum Walls

6 06-Jan-14

12-Jan-14

T+25GU600

Duct Installation

12 11-Jan-14

23-Jan-14

T+25GU610

Electrical Containment

12 16-Jan-14

29-Jan-14

T+25GU590

FP Piping

10 25-Jan-14

04-Feb-14

T+25GR630

Cabling and wire pulling

8 30-Jan-14

08-Feb-14

T+25GU640

Sprinkler Dropper piping Installation

6 05-Feb-14

11-Feb-14

T+25GU650

FP Pipe Pressure Testing

3 12-Feb-14

15-Feb-14

T+25GR640

Sprinkler Drops

6 11-May-14

17-May-14

T+25GR17360

Gypsum Ceilings

6 11-May-14

17-May-14

T+25GR620

Installation of Flexibles / Plenum

4 13-May-14

17-May-14

T+25GR680

Grilles / Diffuser Installation

4 18-May-14

21-May-14

T+25GR17370

T & J Walls & Ceilings

6 18-May-14

24-May-14

T+25GR17400

Paint Ceiling

4 25-May-14

28-May-14

T+25GR17390

Millwork

10 29-May-14

09-Jun-14

T+25GR17380

Wall Covering

4 10-Jun-14

14-Jun-14

T+25GR17420

Mirrors

3 10-Jun-14

12-Jun-14

T+25GR660

Light Fittings Installation

4 15-Jun-14

18-Jun-14

T+25GR690

FA / SD installation

4 15-Jun-14

18-Jun-14

T+25GR670

Sprinkler Installation

4 15-Jun-14

18-Jun-14

T+25GR17410

Underlay & Carpet

3 19-Jun-14

22-Jun-14

232 10-Oct-13 A

24-Jul-14

225
29
3
3

12-Jul-14
26-Dec-13
26-Dec-13
26-Dec-13

West Core
Electrical/Telecom Room
Finishes
T+26WR26870 RMX - 01 to floor
T+26WR26880 Permanent door

10-Oct-13 A
23-Nov-13
24-Dec-13
24-Dec-13

3 24-Dec-13

26-Dec-13

20 23-Nov-13
3 23-Nov-13

16-Dec-13
25-Nov-13

T+26WR26780 Busbar installation & connection

2 26-Nov-13

27-Nov-13

T+26WR26820 Install IT Panels

2 26-Nov-13

27-Nov-13

T+26WR26830 Install Security Panels

2 26-Nov-13

27-Nov-13

T+26WR26790 Duckwork branch to room

2 28-Nov-13

30-Nov-13

T+26WR26800 Fire alarm cabling

3 01-Dec-13

04-Dec-13

T+26WR26810 Cable terminations

10 05-Dec-13

16-Dec-13

6 17-Dec-13
2 17-Dec-13

23-Dec-13
18-Dec-13

T+26WR26850 Fire alarm devices

2 19-Dec-13

21-Dec-13

T+26WR26860 Light fittings

2 22-Dec-13

23-Dec-13

Finishes - 1st Fix


No DISP
T+26WR26010 Blockwork to risers ( 2 sides )

144 10-Oct-13 A
144 10-Oct-13 A
20 10-Oct-13 A

03-Apr-14
03-Apr-14
19-Nov-13

T+26WR26020 Blockwork to wall full height

20 10-Oct-13 A

26-Nov-13

T+26WR26030 Screed to bedroom area

10 16-Nov-13

26-Nov-13

T+26WR26040 Screed cure

10 19-Nov-13

30-Nov-13

T+26WR26060 Studwork incl noggins

12 27-Jan-14

09-Feb-14

T+26WR26070 Close blockwork risers

12 22-Mar-14

03-Apr-14

12 10-Feb-14
12 10-Feb-14

23-Feb-14
23-Feb-14

1st & 2nd Fix


T+26WR26890 Electrical Containment

MEP Final Fix


T+26WR26840 Grills & diffusers

MEP riser summary


No DISP
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 103 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
20-Jan-14

T+25GU580

+26 @ +112.20

15 04-Jan-14

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

12 10-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
23-Feb-14

35 10-Feb-14
35 10-Feb-14
12 10-Feb-14

22-Mar-14
22-Mar-14
23-Feb-14

T+26WR26120 Chilled water & condensate

12 17-Feb-14

02-Mar-14

T+26WR26130 DCW / DHW & CCW riser

12 24-Feb-14

09-Mar-14

T+26WR26140 Sanitary riser

12 24-Feb-14

09-Mar-14

T+26WR26150 Hang FCU

12 24-Feb-14

09-Mar-14

T+26WR26160 Ductwork - supply, make-up air & extract

12 24-Feb-14

09-Mar-14

T+26WR26170 CW supply / return & condensate

12 27-Feb-14

12-Mar-14

T+26WR26180 Plumbing & san distribution

12 01-Mar-14

13-Mar-14

T+26WR26190 FCU connections

12 04-Mar-14

17-Mar-14

T+26WR26200 Cable tray / trunking

12 05-Mar-14

18-Mar-14

T+26WR26220 Test risers ( 3floors vertically )

12 08-Mar-14

20-Mar-14

T+26WR26210 Sprinkler pipes ( Not drops ) from corridor

12 09-Mar-14

22-Mar-14

Activity ID

Activity Name

T+26WR26080 MEP risers & 1st fix


MEP Risers & First Fix
No DISP
T+26WR26110 Ductworks risers

T+26WR26230 MEP sign off risers (Start)

Duration Start

20-Mar-14

66 12-Mar-14
66 12-Mar-14
12 12-Mar-14

27-May-14
27-May-14
25-Mar-14

T+26WR26250 Insulate & board walls

12 17-Mar-14

30-Mar-14

T+26WR26260 Ceiling 1st fix

18 22-Mar-14

10-Apr-14

T+26WR26270 Wiring

12 26-Mar-14

08-Apr-14

T+26WR26280 MEP drops in ceiling

12 30-Mar-14

12-Apr-14

T+26WR26290 Board ceiling

12 31-Mar-14

13-Apr-14

T+26WR26300 Tape & Joint walls & ceiling

12 05-Apr-14

17-Apr-14

T+26WR26310 Mist coat all dry lining

12 09-Apr-14

22-Apr-14

T+26WR26320 Install cornice

12 12-Apr-14

24-Apr-14

T+26WR26330 Paint ceiling and cornice

12 16-Apr-14

29-Apr-14

T+26WR26340 Wall covering

12 21-Apr-14

04-May-14

T+26WR26350 Install furniture

12 26-Apr-14

08-May-14

T+26WR26360 MEP terminations in furniture

12 30-Apr-14

13-May-14

T+26WR26370 MEP 3rd fix- sockets, cover plates etc

12 07-May-14

20-May-14

T+26WR26760 Underlay & Carpet

6 21-May-14

27-May-14

Bathroom
No DISP
T+26WR26380 Stud to block walls

67 29-Mar-14
67 29-Mar-14
12 29-Mar-14

14-Jun-14
14-Jun-14
10-Apr-14

T+26WR26390 Waterproof bathroom

12 31-Mar-14

13-Apr-14

T+26WR26400 Flood test

12 07-Apr-14

20-Apr-14

T+26WR26410 MEP Drops in walls & back boxes

12 16-Apr-14

29-Apr-14

T+26WR26420 Install bath

12 16-Apr-14

29-Apr-14

T+26WR26430 Insulate & board walls

12 19-Apr-14

01-May-14

T+26WR26440 Framing & board for bath

12 19-Apr-14

01-May-14

T+26WR26450 First fix ceiling

12 21-Apr-14

04-May-14

T+26WR26460 MEP drops in ceiling

12 23-Apr-14

06-May-14

T+26WR26470 2nd fix ceiling incl access panel

12 24-Apr-14

07-May-14

T+26WR26480 Install corniche

12 27-Apr-14

10-May-14

T+26WR26490 Stone to floors

12 05-May-14

18-May-14

T+26WR26500 Stone surround to bath

12 08-May-14

21-May-14

Bedroom
No DISP
T+26WR26240 MEP Drops in walls & back boxes

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 104 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+26WR26510 Stone vanity

12 08-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
21-May-14

T+26WR26520 Stone to walls incl niche

12 08-May-14

21-May-14

T+26WR26530 Casing stone

12 08-May-14

21-May-14

T+26WR26540 Grout to all stone

12 08-May-14

21-May-14

T+26WR26550 Glass Partition

12 22-May-14

04-Jun-14

T+26WR26560 Install and connect " Free issue " mirror

12 24-May-14

05-Jun-14

T+26WR26570 Sanitary ware and accessories

12 26-May-14

08-Jun-14

T+26WR26580 MEP connections to bath and basin

12 27-May-14

09-Jun-14

T+26WR26590 MEP 3rd fix - switch / socket covers

12 29-May-14

11-Jun-14

T+26WR26600 Hang glass doors

12 01-Jun-14

14-Jun-14

Entrance Vestibule & dressing


No DISP
T+26WR26610 MEP drops in walls

42 23-Apr-14
42 23-Apr-14
12 23-Apr-14

10-Jun-14
10-Jun-14
06-May-14

T+26WR26620 Board walls

12 27-Apr-14

10-May-14

T+26WR26630 Ceiling 1st fix

12 29-Apr-14

12-May-14

T+26WR26640 MEP drops in ceiling

12 01-May-14

14-May-14

T+26WR26650 Board ceiling incl access panel

12 05-May-14

18-May-14

T+26WR26670 Tape & joint walls & ceilings

12 07-May-14

20-May-14

T+26WR26680 Mist coat dry lining

12 08-May-14

21-May-14

T+26WR26690 Paint ceiling

12 11-May-14

24-May-14

T+26WR26700 Stone flooring incl grout

12 15-May-14

28-May-14

T+26WR26710 Pocket door to bathroom

12 21-May-14

03-Jun-14

T+26WR26720 Entrance door - Temporary

12 21-May-14

03-Jun-14

T+26WR26730 Install wardrobe

12 22-May-14

04-Jun-14

T+26WR26740 Wall Coverings

12 25-May-14

07-Jun-14

T+26WR26750 3rd fix MEP

12 28-May-14

10-Jun-14

20 15-Jun-14
20 15-Jun-14
3 15-Jun-14

12-Jul-14
12-Jul-14
17-Jun-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+26GR620
Installation of Flexibles / Plenum
W+26GR640

Sprinkler Drops

Duration Start

3 15-Jun-14

17-Jun-14

W+26GR17360 Gypsum Ceilings

4 18-Jun-14

22-Jun-14

W+26GR17400 Paint Ceiling

2 23-Jun-14

24-Jun-14

W+26GR17390 Millwork

6 25-Jun-14

03-Jul-14

W+26GR17380 Wall Covering & fabric panels

4 28-Jun-14

03-Jul-14

W+26GR660

Light Fittings Installation

2 05-Jul-14

06-Jul-14

W+26GR670

Sprinkler Installation

2 05-Jul-14

06-Jul-14

3 08-Jul-14

12-Jul-14

W+26GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+26ER26010 Blockwork to risers ( 2 sides )

206
129
129
20

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

24-Jul-14
16-Apr-14
16-Apr-14
09-Dec-13

T+26ER26020

Blockwork to wall full height

20 16-Nov-13

09-Dec-13

T+26ER26030

Screed to bedroom area

10 27-Nov-13

09-Dec-13

T+26ER26040

Screed cure

10 01-Dec-13

12-Dec-13

T+26ER26060

Studwork incl noggins

12 03-Feb-14

16-Feb-14

T+26ER26070

Close blockwork risers

12 03-Apr-14

16-Apr-14

12 23-Feb-14
12 23-Feb-14
12 23-Feb-14

08-Mar-14
08-Mar-14
08-Mar-14

MEP riser summary


No DISP
T+26ER26080 MEP risers & 1st fix
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 105 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

MEP Risers & First Fix


No DISP
T+26ER26110 Ductworks risers
Chilled water & condensate

12 02-Mar-14

15-Mar-14

DCW / DHW & CCW riser

12 09-Mar-14

22-Mar-14

T+26ER26140

Sanitary riser

12 09-Mar-14

22-Mar-14

T+26ER26150

Hang FCU

12 09-Mar-14

22-Mar-14

T+26ER26160

Ductwork - supply, make-up air & extract

12 09-Mar-14

22-Mar-14

T+26ER26170

CW supply / return & condensate

12 12-Mar-14

25-Mar-14

T+26ER26180

Plumbing & san distribution

12 13-Mar-14

26-Mar-14

T+26ER26190

FCU connections

12 17-Mar-14

30-Mar-14

T+26ER26200

Cable tray / trunking

12 18-Mar-14

31-Mar-14

T+26ER26220

Test risers ( 3floors vertically )

12 20-Mar-14

02-Apr-14

T+26ER26210

Sprinkler pipes ( Not drops ) from corridor

12 22-Mar-14

03-Apr-14

T+26ER26230

MEP sign off risers (Start)

MEP Drops in walls & back boxes

T+26ER26250

Insulate & board walls

12 30-Mar-14

12-Apr-14

T+26ER26260

Ceiling 1st fix

18 03-Apr-14

23-Apr-14

T+26ER26270

Wiring

12 08-Apr-14

21-Apr-14

T+26ER26280

MEP drops in ceiling

12 12-Apr-14

24-Apr-14

T+26ER26290

Board ceiling

12 13-Apr-14

26-Apr-14

T+26ER26300

Tape & Joint walls & ceiling

12 17-Apr-14

30-Apr-14

T+26ER26310

Mist coat all dry lining

12 22-Apr-14

05-May-14

T+26ER26320

Install cornice

12 24-Apr-14

07-May-14

T+26ER26330

Paint ceiling and cornice

12 29-Apr-14

12-May-14

T+26ER26340

Wall covering

6 06-May-14

12-May-14

T+26ER26350

Install furniture

12 11-May-14

24-May-14

T+26ER26360

MEP terminations in furniture

12 15-May-14

28-May-14

T+26ER26370

MEP 3rd fix- sockets, cover plates etc

12 22-May-14

04-Jun-14

T+26ER26760

Underlay & Carpet

6 05-Jun-14

11-Jun-14
11-Jun-14
07-Apr-14

11-Jun-14
17-Jun-14
17-Jun-14
23-Apr-14

Stud to block walls

59 10-Apr-14
59 10-Apr-14
12 10-Apr-14

T+26ER26390

Waterproof bathroom

12 13-Apr-14

26-Apr-14

T+26ER26400

Flood test

12 20-Apr-14

03-May-14

T+26ER26410

MEP Drops in walls & back boxes

12 29-Apr-14

12-May-14

T+26ER26420

Install bath

12 29-Apr-14

12-May-14

T+26ER26430

Insulate & board walls

12 01-May-14

14-May-14

T+26ER26440

Framing & board for bath

12 01-May-14

14-May-14

T+26ER26450

First fix ceiling

12 04-May-14

17-May-14

T+26ER26460

MEP drops in ceiling

12 06-May-14

19-May-14

T+26ER26470

2nd fix ceiling incl access panel

12 07-May-14

20-May-14

T+26ER26480

Install corniche

12 10-May-14

22-May-14

T+26ER26490

Stone to floors

12 12-May-14

25-May-14

T+26ER26500

Stone surround to bath

12 12-May-14

25-May-14

T+26ER26510

Stone vanity

12 12-May-14

25-May-14

Summary Bar
Remaining Work
Milestone

Data date: 16-Nov-13

02-Apr-14

68 25-Mar-14
68 25-Mar-14
12 25-Mar-14

Critical Remaining Work

Revised Programme Rev. D

35 23-Feb-14
35 23-Feb-14
12 23-Feb-14

T+26ER26130

Bathroom
No DISP
T+26ER26380

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
03-Apr-14
03-Apr-14
08-Mar-14

Duration Start

T+26ER26120

Bedroom
No DISP
T+26ER26240

Four Seasons Hotel Bahrain

Page 106 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+26ER26520

Stone to walls incl niche

12 12-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
25-May-14

T+26ER26530

Casing stone

12 12-May-14

25-May-14

T+26ER26540

Grout to all stone

12 12-May-14

25-May-14

T+26ER26550

Glass Partition

12 26-May-14

08-Jun-14

T+26ER26560

Install and connect " Free issue " mirror

12 27-May-14

09-Jun-14

T+26ER26570

Sanitary ware and accessories

12 29-May-14

11-Jun-14

T+26ER26580

MEP connections to bath and basin

12 31-May-14

12-Jun-14

T+26ER26590

MEP 3rd fix - switch / socket covers

12 02-Jun-14

15-Jun-14

T+26ER26600

Hang glass doors

12 04-Jun-14

17-Jun-14

34 06-May-14
34 06-May-14
12 06-May-14

14-Jun-14
14-Jun-14
19-May-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+26ER26610 MEP drops in walls

Duration Start

T+26ER26620

Board walls

12 10-May-14

22-May-14

T+26ER26630

Ceiling 1st fix

12 12-May-14

25-May-14

T+26ER26640

MEP drops in ceiling

12 14-May-14

27-May-14

T+26ER26650

Board ceiling incl access panel

12 18-May-14

31-May-14

T+26ER26700

Stone flooring incl grout

12 19-May-14

01-Jun-14

T+26ER26670

Tape & joint walls & ceilings

12 20-May-14

02-Jun-14

T+26ER26680

Mist coat dry lining

12 21-May-14

03-Jun-14

T+26ER26690

Paint ceiling

12 24-May-14

05-Jun-14

T+26ER26710

Pocket door to bathroom

12 25-May-14

07-Jun-14

T+26ER26720

Entrance door - Temporary

12 25-May-14

07-Jun-14

T+26ER26730

Install wardrobe

12 26-May-14

08-Jun-14

T+26ER26740

Wall Coverings

12 28-May-14

10-Jun-14

T+26ER26750

3rd fix MEP

12 01-Jun-14

14-Jun-14

24 18-Jun-14
24 18-Jun-14
3 18-Jun-14

24-Jul-14
24-Jul-14
21-Jun-14

3 18-Jun-14

21-Jun-14

E+26GR17360 Gypsum Ceilings

6 22-Jun-14

28-Jun-14

E+26GR17400 Paint Ceiling

4 29-Jun-14

05-Jul-14

E+26GR17390 Millwork

6 06-Jul-14

15-Jul-14

E+26GR17380 Wall Covering & fabric panels

4 10-Jul-14

15-Jul-14

E+26GR660

Light Fittings Installation

2 17-Jul-14

19-Jul-14

E+26GR670

Sprinkler Installation

2 17-Jul-14

19-Jul-14

3 20-Jul-14

24-Jul-14

Pier Corridors & Lift Lobby


No DISP
E+26GR620
Installation of Flexibles / Plenum
E+26GR640

Sprinkler Drops

E+26GR17410 Underlay & Carpet


Guestrooms
Finishes - 1st Fix
No DISP
T+26GU18130 Studwork to walls incl noggins
T+26GU18140

Close blockwork risers

192
70
70
18

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

29-Jun-14
06-Feb-14
06-Feb-14
07-Dec-13

9 28-Jan-14

06-Feb-14

MEP riser summary


No DISP
T+26GU18480 MEP risers & 1st fix Riser 1

18 23-Dec-13
18 23-Dec-13
18 23-Dec-13

13-Jan-14
13-Jan-14
13-Jan-14

MEP Risers & First Fix


No DISP
T+26GU19940 Ductworks risers

41 23-Dec-13
41 23-Dec-13
12 23-Dec-13

09-Feb-14
09-Feb-14
06-Jan-14

T+26GU19950

Chilled water & condensate

12 30-Dec-13

13-Jan-14

T+26GU19970

DCW / DHW & CCW riser

12 07-Jan-14

20-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 107 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+26GU19980

Sanitary riser

12 07-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
20-Jan-14

T+26GU19990

Hang FCU

12 07-Jan-14

20-Jan-14

T+26GU20000

Ductwork - supply, make-up air & extract

12 07-Jan-14

20-Jan-14

T+26GU20010

CW supply / return & condensate

12 11-Jan-14

23-Jan-14

T+26GU20020

Plumbing & san distribution

12 12-Jan-14

25-Jan-14

T+26GU19960

Test risers ( 3floors vertically )

12 14-Jan-14

27-Jan-14

T+26GU20040

FCU connections

12 15-Jan-14

28-Jan-14

T+26GU20050

Cable tray / trunking

12 19-Jan-14

01-Feb-14

T+26GU20060

Sprinkler pipes ( Not drops ) from corridor

18 20-Jan-14

09-Feb-14

T+26GU20030

MEP sign off risers (Start)

Activity ID

Activity Name

Bedroom
No DISP
T+26GU21610

MEP Drops in walls & back boxes

Duration Start

27-Jan-14

104 22-Jan-14
104 22-Jan-14
12 22-Jan-14

22-May-14
22-May-14
04-Feb-14

T+26GU21620

Insulate & board walls

12 28-Jan-14

10-Feb-14

T+26GU21630

Ceiling 1st fix

18 02-Feb-14

22-Feb-14

T+26GU21640

Wiring

12 06-Feb-14

19-Feb-14

T+26GU21650

MEP drops in ceiling

12 10-Feb-14

23-Feb-14

T+26GU21660

Board ceiling

12 11-Feb-14

24-Feb-14

T+26GU21670

Tape & Joint walls & ceiling

12 16-Feb-14

01-Mar-14

T+26GU21680

Mist coat all dry lining

12 20-Feb-14

05-Mar-14

T+26GU21690

Install cornice

12 23-Feb-14

08-Mar-14

T+26GU21700

Paint ceiling and cornice

12 27-Feb-14

12-Mar-14

T+26GU21710

Wall covering

12 07-Apr-14

20-Apr-14

T+26GU21720

Install furniture

12 12-Apr-14

24-Apr-14

T+26GU21730

MEP terminations in furniture

12 19-Apr-14

01-May-14

T+26GU21740

MEP 3rd fix- sockets, cover plates etc

12 26-Apr-14

08-May-14

T+26GU27521

Underlay & Carpet

12 10-May-14

22-May-14

132 22-Dec-13
132 22-Dec-13
12 22-Dec-13

25-May-14
25-May-14
05-Jan-14

Bathroom
No DISP
T+26GU26310

SS frame to shower & toilet

T+26GU24280

Stud to block walls

12 02-Feb-14

15-Feb-14

T+26GU24290

Waterproof bathroom

12 18-Feb-14

03-Mar-14

T+26GU24300

Flood test

12 25-Feb-14

10-Mar-14

T+26GU24310

MEP Drops in walls & back boxes

12 01-Mar-14

13-Mar-14

T+26GU24320

Install bath

12 01-Mar-14

13-Mar-14

T+26GU24390

Stone to floors

12 01-Mar-14

13-Mar-14

T+26GU24400

Stone surround to bath

12 01-Mar-14

13-Mar-14

T+26GU24410

Stone vanity

12 01-Mar-14

13-Mar-14

T+26GU24420

Stone to walls incl niche

12 01-Mar-14

13-Mar-14

T+26GU24430

Casing stone

12 01-Mar-14

13-Mar-14

T+26GU24330

Insulate & board walls

12 03-Mar-14

16-Mar-14

T+26GU24340

Framing & board for bath

12 03-Mar-14

16-Mar-14

T+26GU24350

First fix ceiling

12 05-Mar-14

18-Mar-14

T+26GU24440

Grout to all stone

12 08-Mar-14

20-Mar-14

T+26GU24360

MEP drops in ceiling

12 08-Mar-14

20-Mar-14

T+26GU24370

2nd fix ceiling incl access panel

12 09-Mar-14

22-Mar-14

T+26GU24380

Install corniche

12 11-Mar-14

24-Mar-14

T+26GU27531

Vanity S/S & Mirrors

12 15-Mar-14

27-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 108 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+26GU27541

Vanity Units

12 15-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
27-Mar-14

T+26GU24450

Glass Partition

12 22-Mar-14

03-Apr-14

T+26GU24500

Hang glass doors

12 22-Mar-14

03-Apr-14

T+26GU18120

Wall covering

12 15-Apr-14

28-Apr-14

T+26GU24460

Install and connect " Free issue " mirror

12 06-May-14

19-May-14

T+26GU24470

Sanitary ware and accessories

12 08-May-14

21-May-14

T+26GU24480

MEP connections to bath and basin

12 10-May-14

22-May-14

T+26GU24490

MEP 3rd fix - switch / socket covers

12 12-May-14

25-May-14

95 01-Mar-14
95 01-Mar-14
12 01-Mar-14

18-Jun-14
18-Jun-14
13-Mar-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+26GU26250 Stone flooring incl grout

Duration Start

T+26GU26160

MEP drops in walls

12 03-Mar-14

16-Mar-14

T+26GU26170

Board walls

12 06-Mar-14

19-Mar-14

T+26GU26180

Ceiling 1st fix

12 09-Mar-14

22-Mar-14

T+26GU26190

MEP drops in ceiling

12 11-Mar-14

24-Mar-14

T+26GU26200

Board ceiling incl access panel

12 15-Mar-14

27-Mar-14

T+26GU26210

Door frames

12 17-Mar-14

30-Mar-14

T+26GU26220

Tape & joint walls & ceilings

12 17-Mar-14

30-Mar-14

T+26GU26230

Mist coat dry lining

12 18-Mar-14

31-Mar-14

T+26GU26240

Paint ceiling

12 20-Mar-14

02-Apr-14

T+26GU26280

Install wardrobe

12 27-Mar-14

09-Apr-14

T+26GU26290

Wall Coverings

12 30-Mar-14

12-Apr-14

T+26GU26270

Mirrors

12 03-Apr-14

16-Apr-14

T+26GU26300

3rd fix MEP

12 10-Apr-14

23-Apr-14

T+26GU26260

Pocket door to bathroom

12 05-Jun-14

18-Jun-14

150 06-Jan-14
150 06-Jan-14
6 06-Jan-14

29-Jun-14
29-Jun-14
12-Jan-14

Corridor
No DISP
T+26GR17350

Gypsum Walls

T+26GU580

Cable Tray / Trunking

15 09-Jan-14

26-Jan-14

T+26GU600

Duct Installation

12 16-Jan-14

29-Jan-14

T+26GU610

Electrical Containment

12 22-Jan-14

04-Feb-14

T+26GU590

FP Piping

10 30-Jan-14

10-Feb-14

T+26GR630

Cabling and wire pulling

8 05-Feb-14

13-Feb-14

T+26GU640

Sprinkler Dropper piping Installation

6 11-Feb-14

17-Feb-14

T+26GU650

FP Pipe Pressure Testing

3 18-Feb-14

20-Feb-14

T+26GR640

Sprinkler Drops

6 18-May-14

24-May-14

T+26GR17360

Gypsum Ceilings

6 18-May-14

24-May-14

T+26GR620

Installation of Flexibles / Plenum

4 20-May-14

24-May-14

T+26GR680

Grilles / Diffuser Installation

4 25-May-14

28-May-14

T+26GR17370

T & J Walls & Ceilings

6 25-May-14

31-May-14

T+26GR17400

Paint Ceiling

4 01-Jun-14

04-Jun-14

T+26GR17390

Millwork

10 05-Jun-14

16-Jun-14

T+26GR17380

Wall Covering

4 17-Jun-14

21-Jun-14

T+26GR17420

Mirrors

3 17-Jun-14

19-Jun-14

T+26GR660

Light Fittings Installation

4 22-Jun-14

25-Jun-14

T+26GR690

FA / SD installation

4 22-Jun-14

25-Jun-14

T+26GR670

Sprinkler Installation

4 22-Jun-14

25-Jun-14

T+26GR17410

Underlay & Carpet

3 26-Jun-14

29-Jun-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 109 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

+27 @ +116.00
West Core
Electrical/Telecom Room
Finishes
T+27WR26870 RMX - 01 to floor
T+27WR26880 Permanent door

16-Nov-13
26-Nov-13
28-Dec-13
28-Dec-13

17-Jul-14
30-Dec-13
30-Dec-13
30-Dec-13
19-Dec-13
28-Nov-13

T+27WR26780 Busbar installation & connection

2 30-Nov-13

01-Dec-13

T+27WR26820 Install IT Panels

2 30-Nov-13

01-Dec-13

T+27WR26830 Install Security Panels

2 30-Nov-13

01-Dec-13

T+27WR26790 Duckwork branch to room

2 03-Dec-13

04-Dec-13

T+27WR26800 Fire alarm cabling

3 05-Dec-13

08-Dec-13

T+27WR26810 Cable terminations

10 09-Dec-13

19-Dec-13

6 21-Dec-13
2 21-Dec-13

26-Dec-13
22-Dec-13

T+27WR26850 Fire alarm devices

2 23-Dec-13

24-Dec-13

T+27WR26860 Light fittings

2 25-Dec-13

26-Dec-13

Finishes - 1st Fix


No DISP
T+27WR26060 Studwork incl noggins

58 03-Feb-14
58 03-Feb-14
12 03-Feb-14

10-Apr-14
10-Apr-14
16-Feb-14

T+27WR26070 Close blockwork risers

12 29-Mar-14

10-Apr-14

MEP riser summary


No DISP
T+27WR26080 MEP risers & 1st fix

12 17-Feb-14
12 17-Feb-14
12 17-Feb-14

02-Mar-14
02-Mar-14
02-Mar-14

MEP Risers & First Fix


No DISP
T+27WR26110 Ductworks risers

35 17-Feb-14
35 17-Feb-14
12 17-Feb-14

29-Mar-14
29-Mar-14
02-Mar-14

T+27WR26120 Chilled water & condensate

12 24-Feb-14

09-Mar-14

T+27WR26130 DCW / DHW & CCW riser

12 03-Mar-14

16-Mar-14

T+27WR26140 Sanitary riser

12 03-Mar-14

16-Mar-14

T+27WR26150 Hang FCU

12 03-Mar-14

16-Mar-14

T+27WR26160 Ductwork - supply, make-up air & extract

12 03-Mar-14

16-Mar-14

T+27WR26170 CW supply / return & condensate

12 06-Mar-14

19-Mar-14

T+27WR26180 Plumbing & san distribution

12 08-Mar-14

20-Mar-14

T+27WR26190 FCU connections

12 11-Mar-14

24-Mar-14

T+27WR26200 Cable tray / trunking

12 12-Mar-14

25-Mar-14

T+27WR26220 Test risers ( 3floors vertically )

12 15-Mar-14

27-Mar-14

T+27WR26210 Sprinkler pipes ( Not drops ) from corridor

12 16-Mar-14

29-Mar-14

27-Mar-14

170 16-Nov-13
170 16-Nov-13
12 16-Nov-13

03-Jun-14
03-Jun-14
28-Nov-13

T+27WR26240 MEP Drops in walls & back boxes

12 19-Mar-14

01-Apr-14

T+27WR26250 Insulate & board walls

12 24-Mar-14

06-Apr-14

T+27WR26260 Ceiling 1st fix

18 29-Mar-14

17-Apr-14

T+27WR26270 Wiring

12 02-Apr-14

15-Apr-14

T+27WR26280 MEP drops in ceiling

12 06-Apr-14

19-Apr-14

T+27WR26290 Board ceiling

12 07-Apr-14

20-Apr-14

Bedroom
No DISP
T+27WR26760 MEP 3rd fix- sockets, cover plates etc

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

202
29
3
3

30-Dec-13

T+27WR26230 MEP sign off risers (Start)

Revised Programme Rev. D

212 16-Nov-13

3 28-Dec-13

MEP Final Fix


T+27WR26840 Grills & diffusers

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
03-Aug-14

Duration Start

20 26-Nov-13
3 26-Nov-13

1st & 2nd Fix


T+27WR26890 Electrical Containment

Four Seasons Hotel Bahrain

Page 110 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+27WR26300 Tape & Joint walls & ceiling

12 12-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
24-Apr-14

T+27WR26310 Mist coat all dry lining

12 16-Apr-14

29-Apr-14

T+27WR26320 Install cornice

12 19-Apr-14

01-May-14

T+27WR26330 Paint ceiling and cornice

12 23-Apr-14

06-May-14

T+27WR26340 Wall covering

12 28-Apr-14

11-May-14

T+27WR26350 Install furniture

12 03-May-14

15-May-14

T+27WR26360 MEP terminations in furniture

12 07-May-14

20-May-14

T+27WR26370 MEP 3rd fix- sockets, cover plates etc

12 14-May-14

27-May-14

6 28-May-14

03-Jun-14

Activity ID

Activity Name

T+27WR26770 Underlay & Carpet

Duration Start

64 05-Apr-14
64 05-Apr-14
12 05-Apr-14

17-Jun-14
17-Jun-14
17-Apr-14

T+27WR26390 Waterproof bathroom

12 07-Apr-14

20-Apr-14

T+27WR26400 Flood test

12 14-Apr-14

27-Apr-14

T+27WR26410 MEP Drops in walls & back boxes

12 23-Apr-14

06-May-14

T+27WR26420 Install bath

12 23-Apr-14

06-May-14

T+27WR26430 Insulate & board walls

12 26-Apr-14

08-May-14

T+27WR26440 Framing & board for bath

12 26-Apr-14

08-May-14

T+27WR26450 First fix ceiling

12 28-Apr-14

11-May-14

T+27WR26460 MEP drops in ceiling

12 30-Apr-14

13-May-14

T+27WR26470 2nd fix ceiling incl access panel

12 01-May-14

14-May-14

T+27WR26480 Install corniche

12 04-May-14

17-May-14

T+27WR26490 Stone to floors

12 12-May-14

25-May-14

T+27WR26500 Stone surround to bath

12 12-May-14

25-May-14

T+27WR26510 Stone vanity

12 12-May-14

25-May-14

T+27WR26520 Stone to walls incl niche

12 12-May-14

25-May-14

T+27WR26530 Casing stone

12 12-May-14

25-May-14

T+27WR26540 Grout to all stone

12 12-May-14

25-May-14

T+27WR26550 Glass Partition

12 26-May-14

08-Jun-14

T+27WR26560 Install and connect " Free issue " mirror

12 27-May-14

09-Jun-14

T+27WR26570 Sanitary ware and accessories

12 29-May-14

11-Jun-14

T+27WR26580 MEP connections to bath and basin

12 31-May-14

12-Jun-14

T+27WR26590 MEP 3rd fix - switch / socket covers

12 02-Jun-14

15-Jun-14

T+27WR26600 Hang glass doors

12 04-Jun-14

17-Jun-14

Entrance Vestibule & dressing


No DISP
T+27WR26610 MEP drops in walls

39 30-Apr-14
39 30-Apr-14
12 30-Apr-14

14-Jun-14
14-Jun-14
13-May-14

T+27WR26620 Board walls

12 04-May-14

17-May-14

T+27WR26630 Ceiling 1st fix

12 06-May-14

19-May-14

T+27WR26640 MEP drops in ceiling

12 08-May-14

21-May-14

T+27WR26650 Board ceiling incl access panel

12 12-May-14

25-May-14

T+27WR26670 Tape & joint walls & ceilings

12 14-May-14

27-May-14

T+27WR26680 Mist coat dry lining

12 15-May-14

28-May-14

T+27WR26690 Paint ceiling

12 18-May-14

31-May-14

T+27WR26700 Stone flooring incl grout

12 19-May-14

01-Jun-14

T+27WR26710 Pocket door to bathroom

12 25-May-14

07-Jun-14

T+27WR26720 Entrance door - Temporary

12 25-May-14

07-Jun-14

T+27WR26730 Install wardrobe

12 26-May-14

08-Jun-14

Bathroom
No DISP
T+27WR26380 Stud to block walls

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 111 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+27WR26740 Wall Coverings

12 28-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-Jun-14

T+27WR26750 3rd fix MEP

12 01-Jun-14

14-Jun-14

20 18-Jun-14
20 18-Jun-14
3 18-Jun-14

17-Jul-14
17-Jul-14
21-Jun-14

3 18-Jun-14

21-Jun-14

W+27GR17360 Gypsum Ceilings

4 22-Jun-14

25-Jun-14

W+27GR17400 Paint Ceiling

2 26-Jun-14

28-Jun-14

W+27GR17390 Millwork

6 29-Jun-14

08-Jul-14

W+27GR17380 Wall Covering & fabric panels

4 03-Jul-14

08-Jul-14

W+27GR660

Light Fittings Installation

2 10-Jul-14

12-Jul-14

W+27GR670

Sprinkler Installation

2 10-Jul-14

12-Jul-14

3 13-Jul-14

17-Jul-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+27GR620
Installation of Flexibles / Plenum
W+27GR640

Sprinkler Drops

W+27GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+27ER26010 Blockwork to risers ( 2 sides )

Duration Start

212
135
135
20

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

03-Aug-14
23-Apr-14
23-Apr-14
09-Dec-13

T+27ER26020

Blockwork to wall full height

20 16-Nov-13

09-Dec-13

T+27ER26030

Screed to bedroom area

10 27-Nov-13

09-Dec-13

T+27ER26040

Screed cure

10 01-Dec-13

12-Dec-13

T+27ER26060

Studwork incl noggins

12 10-Feb-14

23-Feb-14

T+27ER26070

Close blockwork risers

12 10-Apr-14

23-Apr-14

MEP riser summary


No DISP
T+27ER26080 MEP risers & 1st fix

12 02-Mar-14
12 02-Mar-14
12 02-Mar-14

15-Mar-14
15-Mar-14
15-Mar-14

MEP Risers & First Fix


No DISP
T+27ER26110 Ductworks risers

35 02-Mar-14
35 02-Mar-14
12 02-Mar-14

10-Apr-14
10-Apr-14
15-Mar-14

T+27ER26120

Chilled water & condensate

12 09-Mar-14

22-Mar-14

T+27ER26130

DCW / DHW & CCW riser

12 16-Mar-14

29-Mar-14

T+27ER26140

Sanitary riser

12 16-Mar-14

29-Mar-14

T+27ER26150

Hang FCU

12 16-Mar-14

29-Mar-14

T+27ER26160

Ductwork - supply, make-up air & extract

12 16-Mar-14

29-Mar-14

T+27ER26170

CW supply / return & condensate

12 19-Mar-14

01-Apr-14

T+27ER26180

Plumbing & san distribution

12 20-Mar-14

02-Apr-14

T+27ER26190

FCU connections

12 24-Mar-14

06-Apr-14

T+27ER26200

Cable tray / trunking

12 25-Mar-14

07-Apr-14

T+27ER26220

Test risers ( 3floors vertically )

12 27-Mar-14

09-Apr-14

T+27ER26210

Sprinkler pipes ( Not drops ) from corridor

12 29-Mar-14

10-Apr-14

T+27ER26230

MEP sign off risers (Start)

09-Apr-14

MEP Drops in walls & back boxes

68 01-Apr-14
68 01-Apr-14
12 01-Apr-14

T+27ER26250

Insulate & board walls

12 06-Apr-14

19-Apr-14

T+27ER26260

Ceiling 1st fix

18 10-Apr-14

30-Apr-14

T+27ER26270

Wiring

12 15-Apr-14

28-Apr-14

T+27ER26280

MEP drops in ceiling

12 19-Apr-14

01-May-14

T+27ER26290

Board ceiling

12 20-Apr-14

03-May-14

T+27ER26300

Tape & Joint walls & ceiling

12 24-Apr-14

07-May-14

Bedroom
No DISP
T+27ER26240

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 112 of 180

18-Jun-14
18-Jun-14
14-Apr-14

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+27ER26310

Mist coat all dry lining

12 29-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-May-14

T+27ER26320

Install cornice

12 01-May-14

14-May-14

T+27ER26330

Paint ceiling and cornice

12 06-May-14

19-May-14

T+27ER26340

Wall covering

6 13-May-14

19-May-14

T+27ER26350

Install furniture

12 18-May-14

31-May-14

T+27ER26360

MEP terminations in furniture

12 22-May-14

04-Jun-14

T+27ER26370

MEP 3rd fix- sockets, cover plates etc

12 29-May-14

11-Jun-14

T+27ER26750

Underlay & Carpet

6 12-Jun-14

18-Jun-14
24-Jun-14
24-Jun-14
30-Apr-14

Activity ID

Activity Name

Duration Start

Stud to block walls

59 17-Apr-14
59 17-Apr-14
12 17-Apr-14

T+27ER26390

Waterproof bathroom

12 20-Apr-14

03-May-14

T+27ER26400

Flood test

12 27-Apr-14

10-May-14

T+27ER26410

MEP Drops in walls & back boxes

12 06-May-14

19-May-14

T+27ER26420

Install bath

12 06-May-14

19-May-14

T+27ER26430

Insulate & board walls

12 08-May-14

21-May-14

T+27ER26440

Framing & board for bath

12 08-May-14

21-May-14

T+27ER26450

First fix ceiling

12 11-May-14

24-May-14

T+27ER26460

MEP drops in ceiling

12 13-May-14

26-May-14

T+27ER26470

2nd fix ceiling incl access panel

12 14-May-14

27-May-14

T+27ER26480

Install corniche

12 17-May-14

29-May-14

T+27ER26490

Stone to floors

12 19-May-14

01-Jun-14

T+27ER26500

Stone surround to bath

12 19-May-14

01-Jun-14

T+27ER26510

Stone vanity

12 19-May-14

01-Jun-14

T+27ER26520

Stone to walls incl niche

12 19-May-14

01-Jun-14

T+27ER26530

Casing stone

12 19-May-14

01-Jun-14

T+27ER26540

Grout to all stone

12 19-May-14

01-Jun-14

T+27ER26550

Glass Partition

12 02-Jun-14

15-Jun-14

T+27ER26560

Install and connect " Free issue " mirror

12 03-Jun-14

16-Jun-14

T+27ER26570

Sanitary ware and accessories

12 05-Jun-14

18-Jun-14

T+27ER26580

MEP connections to bath and basin

12 07-Jun-14

19-Jun-14

T+27ER26590

MEP 3rd fix - switch / socket covers

12 09-Jun-14

22-Jun-14

T+27ER26600

Hang glass doors

12 11-Jun-14

24-Jun-14

31 13-May-14
31 13-May-14
12 13-May-14

17-Jun-14
17-Jun-14
26-May-14

Bathroom
No DISP
T+27ER26380

Entrance Vestibule & dressing


No DISP
T+27ER26610 MEP drops in walls
T+27ER26620

Board walls

12 17-May-14

29-May-14

T+27ER26630

Ceiling 1st fix

12 19-May-14

01-Jun-14

T+27ER26640

MEP drops in ceiling

12 21-May-14

03-Jun-14

T+27ER26650

Board ceiling incl access panel

12 25-May-14

07-Jun-14

T+27ER26700

Stone flooring incl grout

12 26-May-14

08-Jun-14

T+27ER26670

Tape & joint walls & ceilings

12 27-May-14

09-Jun-14

T+27ER26680

Mist coat dry lining

12 28-May-14

10-Jun-14

T+27ER26690

Paint ceiling

12 31-May-14

12-Jun-14

T+27ER26710

Pocket door to bathroom

12 01-Jun-14

14-Jun-14

T+27ER26720

Entrance door - Temporary

12 01-Jun-14

14-Jun-14

T+27ER26730

Install wardrobe

12 02-Jun-14

15-Jun-14

T+27ER26740

Wall Coverings

12 04-Jun-14

17-Jun-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 113 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
E+27GR620
Installation of Flexibles / Plenum
E+27GR640

Sprinkler Drops

Duration Start

24 25-Jun-14
24 25-Jun-14
3 25-Jun-14
3 25-Jun-14

28-Jun-14

6 29-Jun-14

08-Jul-14

E+27GR17400 Paint Ceiling

4 10-Jul-14

15-Jul-14

E+27GR17390 Millwork

6 17-Jul-14

26-Jul-14

E+27GR17380 Wall Covering & fabric panels

4 20-Jul-14

26-Jul-14

E+27GR660

Light Fittings Installation

2 27-Jul-14

30-Jul-14

E+27GR670

Sprinkler Installation

2 27-Jul-14

30-Jul-14

3 31-Jul-14

03-Aug-14

E+27GR17410 Underlay & Carpet

T+27PS18140

Close blockwork risers

180
70
70
18

08-Dec-13
08-Dec-13
08-Dec-13
08-Dec-13

10-Jul-14
27-Feb-14
27-Feb-14
28-Dec-13

12 15-Feb-14

27-Feb-14

MEP riser summary


No DISP
T+27PS18480 MEP risers & 1st fix Riser 1

18 04-Jan-14
18 04-Jan-14
18 04-Jan-14

23-Jan-14
23-Jan-14
23-Jan-14

MEP Risers & First Fix


No DISP
T+27PS19940 Ductworks risers

43 04-Jan-14
43 04-Jan-14
12 04-Jan-14

22-Feb-14
22-Feb-14
16-Jan-14

T+27PS20050

Cable tray / trunking

12 11-Jan-14

23-Jan-14

T+27PS19950

Chilled water & condensate

12 11-Jan-14

23-Jan-14

T+27PS19970

DCW / DHW & CCW riser

12 18-Jan-14

30-Jan-14

T+27PS19980

Sanitary riser

12 18-Jan-14

30-Jan-14

T+27PS19990

Hang FCU

12 18-Jan-14

30-Jan-14

T+27PS20000

Ductwork - supply, make-up air & extract

12 18-Jan-14

30-Jan-14

T+27PS20010

CW supply / return & condensate

12 21-Jan-14

03-Feb-14

T+27PS20020

Plumbing & san distribution

12 22-Jan-14

04-Feb-14

T+27PS20040

FCU connections

12 28-Jan-14

10-Feb-14

T+27PS19960

Test risers ( 3floors vertically )

12 01-Feb-14

13-Feb-14

T+27PS20060

Sprinkler pipes ( Not drops ) from corridor

18 02-Feb-14

22-Feb-14

T+27PS20030

MEP sign off risers (Start)

Bedroom
No DISP
T+27PS21610

MEP Drops in walls & back boxes

08-Jun-14
08-Jun-14
30-Jan-14

T+27PS21620

Insulate & board walls

12 04-Feb-14

17-Feb-14

T+27PS21630

Ceiling 1st fix

18 09-Feb-14

01-Mar-14

T+27PS21640

Wiring

12 13-Feb-14

26-Feb-14

T+27PS21650

MEP drops in ceiling

12 17-Feb-14

02-Mar-14

T+27PS21660

Board ceiling

12 18-Feb-14

03-Mar-14

T+27PS21670

Tape & Joint walls & ceiling

12 23-Feb-14

08-Mar-14

T+27PS21680

Mist coat all dry lining

12 27-Feb-14

12-Mar-14

T+27PS21690

Install cornice

12 02-Mar-14

15-Mar-14

T+27PS21700

Paint ceiling and cornice

12 06-Mar-14

19-Mar-14

T+27PS21710

Wall covering

12 14-Apr-14

27-Apr-14

T+27PS21720

Install furniture

12 19-Apr-14

01-May-14

T+27PS21730

MEP terminations in furniture

12 26-Apr-14

08-May-14

Remaining Work
Critical Remaining Work
Milestone

Page 114 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

13-Feb-14

122 18-Jan-14
122 18-Jan-14
12 18-Jan-14

Summary Bar

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
03-Aug-14
03-Aug-14
28-Jun-14

E+27GR17360 Gypsum Ceilings

Guestrooms
Finishes - 1st Fix
No DISP
T+27PS18130 Studwork to walls incl noggins

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+27PS21740

MEP 3rd fix- sockets, cover plates etc

T+27PS26340

Underlay & Carpet

Bathroom
No DISP
T+27PS26310

SS frame to shower & toilet

12 26-May-14

08-Jun-14

132 29-Dec-13
132 29-Dec-13
12 29-Dec-13

01-Jun-14
01-Jun-14
12-Jan-14

12 18-Jan-14

30-Jan-14

T+27PS24280

Stud to block walls

12 01-Mar-14

13-Mar-14

T+27PS24290

Waterproof bathroom

12 04-Mar-14

17-Mar-14

T+27PS24390

Stone to floors

12 08-Mar-14

20-Mar-14

T+27PS24400

Stone surround to bath

12 08-Mar-14

20-Mar-14

T+27PS24410

Stone vanity

12 08-Mar-14

20-Mar-14

T+27PS24420

Stone to walls incl niche

12 08-Mar-14

20-Mar-14

T+27PS24430

Casing stone

12 08-Mar-14

20-Mar-14

T+27PS24300

Flood test

12 11-Mar-14

24-Mar-14

T+27PS24320

Install bath

12 15-Mar-14

27-Mar-14

T+27PS24440

Grout to all stone

12 15-Mar-14

27-Mar-14

T+27PS24330

Insulate & board walls

12 17-Mar-14

30-Mar-14

T+27PS24340

Framing & board for bath

12 17-Mar-14

30-Mar-14

T+27PS24350

First fix ceiling

12 19-Mar-14

01-Apr-14

T+27PS24360

MEP drops in ceiling

12 22-Mar-14

03-Apr-14

T+27PS26320

Vanity S/S & Mirrors

12 22-Mar-14

03-Apr-14

T+27PS26330

Vanity Unit

12 22-Mar-14

03-Apr-14

T+27PS24370

2nd fix ceiling incl access panel

12 23-Mar-14

05-Apr-14

T+27PS24380

Install corniche

12 25-Mar-14

07-Apr-14

T+27PS24450

Glass Partition

12 29-Mar-14

10-Apr-14

T+27PS24500

Hang glass doors

12 29-Mar-14

10-Apr-14

T+27GU18120

Wall covering

12 05-Apr-14

17-Apr-14

T+27PS24460

Install and connect " Free issue " mirror

12 13-May-14

26-May-14

T+27PS24470

Sanitary ware and accessories

12 15-May-14

28-May-14

T+27PS24480

MEP connections to bath and basin

12 17-May-14

29-May-14

T+27PS24490

MEP 3rd fix - switch / socket covers

12 19-May-14

01-Jun-14

131 25-Jan-14
131 25-Jan-14
12 25-Jan-14

25-Jun-14
25-Jun-14
06-Feb-14

T+27PS26250

Stone flooring incl grout

12 08-Mar-14

20-Mar-14

T+27PS26170

Board walls

12 29-Mar-14

10-Apr-14

T+27PS26180

Ceiling 1st fix

12 31-Mar-14

13-Apr-14

T+27PS26190

MEP drops in ceiling

12 02-Apr-14

15-Apr-14

T+27PS26200

Board ceiling incl access panel

12 06-Apr-14

19-Apr-14

T+27PS26210

Door frames

12 08-Apr-14

21-Apr-14

T+27PS26220

Tape & joint walls & ceilings

12 08-Apr-14

21-Apr-14

T+27PS26230

Mist coat dry lining

12 09-Apr-14

22-Apr-14

T+27PS26240

Paint ceiling

12 12-Apr-14

24-Apr-14

T+27PS26280

Install wardrobe

12 22-Apr-14

05-May-14

T+27PS26290

Wall Coverings

12 24-Apr-14

07-May-14

T+27PS26270

Mirrors

12 29-Apr-14

12-May-14

T+27PS26300

3rd fix MEP

12 06-May-14

19-May-14

T+27PS26260

Pocket door to bathroom

12 12-Jun-14

25-Jun-14

Summary Bar
Remaining Work
Milestone

Revised Programme Rev. D

Data date: 16-Nov-13

12 10-May-14

MEP Drops in walls & back boxes

Critical Remaining Work

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
22-May-14

Duration Start

T+27PS24310

Entrance Vestibule & dressing


No DISP
T+27PS26160 MEP drops in walls

Four Seasons Hotel Bahrain

Page 115 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Corridor
No DISP
T+27GR17350

Gypsum Walls

Duration Start

150 13-Jan-14
150 13-Jan-14
6 13-Jan-14

Cable Tray / Trunking

15 27-Jan-14

12-Feb-14

T+27PS600

Duct Installation

12 03-Feb-14

16-Feb-14

T+27PS610

Electrical Containment

12 09-Feb-14

22-Feb-14

T+27PS590

FP Piping

10 17-Feb-14

27-Feb-14

T+27GR630

Cabling and wire pulling

8 23-Feb-14

03-Mar-14

T+27PS640

Sprinkler Dropper piping Installation

6 01-Mar-14

06-Mar-14

T+27PS650

FP Pipe Pressure Testing

3 08-Mar-14

10-Mar-14

T+27GR17360

Gypsum Ceilings

6 25-May-14

31-May-14

T+27GR620

Installation of Flexibles / Plenum

4 27-May-14

31-May-14

T+27GR640

Sprinkler Drops

6 01-Jun-14

07-Jun-14

T+27GR680

Grilles / Diffuser Installation

4 01-Jun-14

04-Jun-14

T+27GR17370

T & J Walls & Ceilings

6 01-Jun-14

07-Jun-14

T+27GR17400

Paint Ceiling

4 08-Jun-14

11-Jun-14

T+27GR17390

Millwork

10 12-Jun-14

23-Jun-14

T+27GR17380

Wall Covering

4 24-Jun-14

28-Jun-14

T+27GR17420

Mirrors

3 24-Jun-14

26-Jun-14

T+27GR660

Light Fittings Installation

4 29-Jun-14

05-Jul-14

T+27GR690

FA / SD installation

4 29-Jun-14

05-Jul-14

T+27GR670

Sprinkler Installation

4 29-Jun-14

05-Jul-14

T+27GR17410

Underlay & Carpet

West Core
Electrical/Telecom Room
Finishes
T+28WR26870 RMX - 01 to floor
T+28WR26880 Permanent door

3 06-Jul-14

10-Jul-14

214 16-Nov-13

05-Aug-14

208
29
3
3

16-Nov-13
30-Nov-13
31-Dec-13
31-Dec-13

27-Jul-14
04-Jan-14
04-Jan-14
04-Jan-14

3 31-Dec-13

04-Jan-14

20 30-Nov-13
3 30-Nov-13

23-Dec-13
03-Dec-13

T+28WR26780 Busbar installation & connection

2 04-Dec-13

05-Dec-13

T+28WR26820 Install IT Panels

2 04-Dec-13

05-Dec-13

T+28WR26830 Install Security Panels

2 04-Dec-13

05-Dec-13

T+28WR26790 Duckwork branch to room

2 07-Dec-13

08-Dec-13

T+28WR26800 Fire alarm cabling

3 09-Dec-13

11-Dec-13

T+28WR26810 Cable terminations

10 12-Dec-13

23-Dec-13

6 24-Dec-13
2 24-Dec-13

30-Dec-13
25-Dec-13

T+28WR26850 Fire alarm devices

2 26-Dec-13

28-Dec-13

T+28WR26860 Light fittings

2 29-Dec-13

30-Dec-13

Finishes - 1st Fix


No DISP
T+28WR26010 Blockwork to risers ( 2 sides )

130 16-Nov-13
130 16-Nov-13
20 16-Nov-13

17-Apr-14
17-Apr-14
09-Dec-13

T+28WR26020 Blockwork to wall full height

20 16-Nov-13

09-Dec-13

T+28WR26030 Screed to bedroom area

10 27-Nov-13

09-Dec-13

T+28WR26040 Screed cure

10 01-Dec-13

12-Dec-13

T+28WR26060 Studwork incl noggins

12 10-Feb-14

23-Feb-14

T+28WR26070 Close blockwork risers

12 05-Apr-14

17-Apr-14

1st & 2nd Fix


T+28WR26890 Electrical Containment

MEP Final Fix


T+28WR26840 Grills & diffusers

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 116 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-Jul-14
10-Jul-14
19-Jan-14

T+27PS580

+28 @ +120.20

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

MEP riser summary


No DISP
T+28WR26080 MEP risers & 1st fix

12 24-Feb-14
12 24-Feb-14
12 24-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
09-Mar-14
09-Mar-14
09-Mar-14

MEP Risers & First Fix


No DISP
T+28WR26110 Ductworks risers

35 24-Feb-14
35 24-Feb-14
12 24-Feb-14

05-Apr-14
05-Apr-14
09-Mar-14

T+28WR26120 Chilled water & condensate

12 03-Mar-14

16-Mar-14

T+28WR26130 DCW / DHW & CCW riser

12 10-Mar-14

23-Mar-14

T+28WR26140 Sanitary riser

12 10-Mar-14

23-Mar-14

T+28WR26150 Hang FCU

12 10-Mar-14

23-Mar-14

T+28WR26160 Ductwork - supply, make-up air & extract

12 10-Mar-14

23-Mar-14

T+28WR26170 CW supply / return & condensate

12 13-Mar-14

26-Mar-14

T+28WR26180 Plumbing & san distribution

12 15-Mar-14

27-Mar-14

T+28WR26190 FCU connections

12 18-Mar-14

31-Mar-14

T+28WR26200 Cable tray / trunking

12 19-Mar-14

01-Apr-14

T+28WR26220 Test risers ( 3floors vertically )

12 22-Mar-14

03-Apr-14

T+28WR26210 Sprinkler pipes ( Not drops ) from corridor

12 23-Mar-14

05-Apr-14

Activity ID

Activity Name

T+28WR26230 MEP sign off risers (Start)

Duration Start

03-Apr-14

66 26-Mar-14
66 26-Mar-14
12 26-Mar-14

10-Jun-14
10-Jun-14
08-Apr-14

T+28WR26250 Insulate & board walls

12 31-Mar-14

13-Apr-14

T+28WR26260 Ceiling 1st fix

18 05-Apr-14

24-Apr-14

T+28WR26270 Wiring

12 09-Apr-14

22-Apr-14

T+28WR26280 MEP drops in ceiling

12 13-Apr-14

26-Apr-14

T+28WR26290 Board ceiling

12 14-Apr-14

27-Apr-14

T+28WR26300 Tape & Joint walls & ceiling

12 19-Apr-14

01-May-14

T+28WR26310 Mist coat all dry lining

12 23-Apr-14

06-May-14

T+28WR26320 Install cornice

12 26-Apr-14

08-May-14

T+28WR26330 Paint ceiling and cornice

12 30-Apr-14

13-May-14

T+28WR26340 Wall covering

12 05-May-14

18-May-14

T+28WR26350 Install furniture

12 10-May-14

22-May-14

T+28WR26360 MEP terminations in furniture

12 14-May-14

27-May-14

T+28WR26370 MEP 3rd fix- sockets, cover plates etc

12 21-May-14

03-Jun-14

T+28WR26760 Underlay & Carpet

6 04-Jun-14

10-Jun-14

Bathroom
No DISP
T+28WR26380 Stud to block walls

64 12-Apr-14
64 12-Apr-14
12 12-Apr-14

24-Jun-14
24-Jun-14
24-Apr-14

T+28WR26390 Waterproof bathroom

12 14-Apr-14

27-Apr-14

T+28WR26400 Flood test

12 21-Apr-14

04-May-14

T+28WR26410 MEP Drops in walls & back boxes

12 30-Apr-14

13-May-14

T+28WR26420 Install bath

12 30-Apr-14

13-May-14

T+28WR26430 Insulate & board walls

12 03-May-14

15-May-14

T+28WR26440 Framing & board for bath

12 03-May-14

15-May-14

T+28WR26450 First fix ceiling

12 05-May-14

18-May-14

T+28WR26460 MEP drops in ceiling

12 07-May-14

20-May-14

T+28WR26470 2nd fix ceiling incl access panel

12 08-May-14

21-May-14

T+28WR26480 Install corniche

12 11-May-14

24-May-14

T+28WR26490 Stone to floors

12 19-May-14

01-Jun-14

Bedroom
No DISP
T+28WR26240 MEP Drops in walls & back boxes

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 117 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+28WR26500 Stone surround to bath

12 19-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
01-Jun-14

T+28WR26510 Stone vanity

12 19-May-14

01-Jun-14

T+28WR26520 Stone to walls incl niche

12 19-May-14

01-Jun-14

T+28WR26530 Casing stone

12 19-May-14

01-Jun-14

T+28WR26540 Grout to all stone

12 19-May-14

01-Jun-14

T+28WR26550 Glass Partition

12 02-Jun-14

15-Jun-14

T+28WR26560 Install and connect " Free issue " mirror

12 03-Jun-14

16-Jun-14

T+28WR26570 Sanitary ware and accessories

12 05-Jun-14

18-Jun-14

T+28WR26580 MEP connections to bath and basin

12 07-Jun-14

19-Jun-14

T+28WR26590 MEP 3rd fix - switch / socket covers

12 09-Jun-14

22-Jun-14

T+28WR26600 Hang glass doors

12 11-Jun-14

24-Jun-14

Entrance Vestibule & dressing


No DISP
T+28WR26610 MEP drops in walls

39 07-May-14
39 07-May-14
12 07-May-14

21-Jun-14
21-Jun-14
20-May-14

T+28WR26620 Board walls

12 11-May-14

24-May-14

T+28WR26630 Ceiling 1st fix

12 13-May-14

26-May-14

T+28WR26640 MEP drops in ceiling

12 15-May-14

28-May-14

T+28WR26650 Board ceiling incl access panel

12 19-May-14

01-Jun-14

T+28WR26670 Tape & joint walls & ceilings

12 21-May-14

03-Jun-14

T+28WR26680 Mist coat dry lining

12 22-May-14

04-Jun-14

T+28WR26690 Paint ceiling

12 25-May-14

07-Jun-14

T+28WR26700 Stone flooring incl grout

12 26-May-14

08-Jun-14

T+28WR26710 Pocket door to bathroom

12 01-Jun-14

14-Jun-14

T+28WR26720 Entrance door - Temporary

12 01-Jun-14

14-Jun-14

T+28WR26730 Install wardrobe

12 02-Jun-14

15-Jun-14

T+28WR26740 Wall Coverings

12 04-Jun-14

17-Jun-14

T+28WR26750 3rd fix MEP

12 08-Jun-14

21-Jun-14

20 25-Jun-14
20 25-Jun-14
3 25-Jun-14

27-Jul-14
27-Jul-14
28-Jun-14

Activity ID

Activity Name

Pier Corridors & Lift Lobby


No DISP
W+28GR620
Installation of Flexibles / Plenum
W+28GR640

Sprinkler Drops

Duration Start

3 25-Jun-14

28-Jun-14

W+28GR17360 Gypsum Ceilings

4 29-Jun-14

05-Jul-14

W+28GR17400 Paint Ceiling

2 06-Jul-14

08-Jul-14

W+28GR17390 Millwork

6 10-Jul-14

19-Jul-14

W+28GR17380 Wall Covering & fabric panels

4 13-Jul-14

19-Jul-14

W+28GR660

Light Fittings Installation

2 20-Jul-14

22-Jul-14

W+28GR670

Sprinkler Installation

2 20-Jul-14

22-Jul-14

3 24-Jul-14

27-Jul-14

W+28GR17410 Underlay & Carpet


East Core
Finishes - 1st Fix
No DISP
T+28ER26010 Blockwork to risers ( 2 sides )

214
141
141
20

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

05-Aug-14
30-Apr-14
30-Apr-14
09-Dec-13

T+28ER26020

Blockwork to wall full height

20 16-Nov-13

09-Dec-13

T+28ER26030

Screed to bedroom area

10 27-Nov-13

09-Dec-13

T+28ER26040

Screed cure

10 01-Dec-13

12-Dec-13

T+28ER26060

Studwork incl noggins

12 17-Feb-14

02-Mar-14

T+28ER26070

Close blockwork risers

12 17-Apr-14

30-Apr-14

12 09-Mar-14
12 09-Mar-14

22-Mar-14
22-Mar-14

MEP riser summary


No DISP
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 118 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+28ER26080

MEP risers & 1st fix

MEP Risers & First Fix


No DISP
T+28ER26110 Ductworks risers

17-Apr-14
17-Apr-14
22-Mar-14

12 16-Mar-14

29-Mar-14

DCW / DHW & CCW riser

12 23-Mar-14

05-Apr-14

T+28ER26140

Sanitary riser

12 23-Mar-14

05-Apr-14

T+28ER26150

Hang FCU

12 23-Mar-14

05-Apr-14

T+28ER26160

Ductwork - supply, make-up air & extract

12 23-Mar-14

05-Apr-14

T+28ER26170

CW supply / return & condensate

12 26-Mar-14

08-Apr-14

T+28ER26180

Plumbing & san distribution

12 27-Mar-14

09-Apr-14

T+28ER26190

FCU connections

12 31-Mar-14

13-Apr-14

T+28ER26200

Cable tray / trunking

12 01-Apr-14

14-Apr-14

T+28ER26220

Test risers ( 3floors vertically )

12 03-Apr-14

16-Apr-14

T+28ER26210

Sprinkler pipes ( Not drops ) from corridor

12 05-Apr-14

17-Apr-14

T+28ER26230

MEP sign off risers (Start)

16-Apr-14

MEP Drops in walls & back boxes

68 08-Apr-14
68 08-Apr-14
12 08-Apr-14

T+28ER26250

Insulate & board walls

12 13-Apr-14

26-Apr-14

T+28ER26260

Ceiling 1st fix

18 17-Apr-14

07-May-14

T+28ER26270

Wiring

12 22-Apr-14

05-May-14

T+28ER26280

MEP drops in ceiling

12 26-Apr-14

08-May-14

T+28ER26290

Board ceiling

12 27-Apr-14

10-May-14

T+28ER26300

Tape & Joint walls & ceiling

12 01-May-14

14-May-14

T+28ER26310

Mist coat all dry lining

12 06-May-14

19-May-14

T+28ER26320

Install cornice

12 08-May-14

21-May-14

T+28ER26330

Paint ceiling and cornice

12 13-May-14

26-May-14

T+28ER26340
T+28ER26350

Wall covering
Install furniture

6 20-May-14
12 25-May-14

26-May-14
07-Jun-14

T+28ER26360

MEP terminations in furniture

12 29-May-14

11-Jun-14

T+28ER26370

MEP 3rd fix- sockets, cover plates etc

12 05-Jun-14

18-Jun-14

T+28ER26760

Underlay & Carpet

25-Jun-14
25-Jun-14
21-Apr-14

6 19-Jun-14

25-Jun-14
03-Jul-14
03-Jul-14
07-May-14

Stud to block walls

59 24-Apr-14
59 24-Apr-14
12 24-Apr-14

T+28ER26390

Waterproof bathroom

12 27-Apr-14

10-May-14

T+28ER26400

Flood test

12 04-May-14

17-May-14

T+28ER26410

MEP Drops in walls & back boxes

12 13-May-14

26-May-14

T+28ER26420

Install bath

12 13-May-14

26-May-14

T+28ER26430

Insulate & board walls

12 15-May-14

28-May-14

T+28ER26440

Framing & board for bath

12 15-May-14

28-May-14

T+28ER26450

First fix ceiling

12 18-May-14

31-May-14

T+28ER26460

MEP drops in ceiling

12 20-May-14

02-Jun-14

T+28ER26470

2nd fix ceiling incl access panel

12 21-May-14

03-Jun-14

T+28ER26480

Install corniche

12 24-May-14

05-Jun-14

T+28ER26490

Stone to floors

12 26-May-14

08-Jun-14

T+28ER26500

Stone surround to bath

12 26-May-14

08-Jun-14

T+28ER26510

Stone vanity

12 26-May-14

08-Jun-14

Summary Bar
Remaining Work
Milestone

Data date: 16-Nov-13

35 09-Mar-14
35 09-Mar-14
12 09-Mar-14

Chilled water & condensate

Critical Remaining Work

Revised Programme Rev. D

12 09-Mar-14

T+28ER26130

Bathroom
No DISP
T+28ER26380

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
22-Mar-14

Duration Start

T+28ER26120

Bedroom
No DISP
T+28ER26240

Four Seasons Hotel Bahrain

Page 119 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+28ER26520

Stone to walls incl niche

12 26-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
08-Jun-14

T+28ER26530

Casing stone

12 26-May-14

08-Jun-14

T+28ER26540

Grout to all stone

12 26-May-14

08-Jun-14

T+28ER26550

Glass Partition

12 09-Jun-14

22-Jun-14

T+28ER26560

Install and connect " Free issue " mirror

12 10-Jun-14

23-Jun-14

T+28ER26570

Sanitary ware and accessories

12 12-Jun-14

25-Jun-14

T+28ER26580

MEP connections to bath and basin

12 14-Jun-14

26-Jun-14

T+28ER26590

MEP 3rd fix - switch / socket covers

12 16-Jun-14

29-Jun-14

T+28ER26600

Hang glass doors

12 18-Jun-14

03-Jul-14

34 20-May-14
34 20-May-14
12 20-May-14

28-Jun-14
28-Jun-14
02-Jun-14

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+28ER26610 MEP drops in walls

Duration Start

T+28ER26620

Board walls

12 24-May-14

05-Jun-14

T+28ER26630

Ceiling 1st fix

12 26-May-14

08-Jun-14

T+28ER26640

MEP drops in ceiling

12 28-May-14

10-Jun-14

T+28ER26650

Board ceiling incl access panel

12 01-Jun-14

14-Jun-14

T+28ER26700

Stone flooring incl grout

12 02-Jun-14

15-Jun-14

T+28ER26670

Tape & joint walls & ceilings

12 03-Jun-14

16-Jun-14

T+28ER26680

Mist coat dry lining

12 04-Jun-14

17-Jun-14

T+28ER26690

Paint ceiling

12 07-Jun-14

19-Jun-14

T+28ER26710

Pocket door to bathroom

12 08-Jun-14

21-Jun-14

T+28ER26720

Entrance door - Temporary

12 08-Jun-14

21-Jun-14

T+28ER26730

Install wardrobe

12 09-Jun-14

22-Jun-14

T+28ER26740

Wall Coverings

12 11-Jun-14

24-Jun-14

T+28ER26750

3rd fix MEP

12 15-Jun-14

28-Jun-14

214 16-Nov-13
214 16-Nov-13
3 16-Nov-13

05-Aug-14
05-Aug-14
18-Nov-13

Pier Corridors & Lift Lobby


No DISP
E+28GR640
Sprinkler Drops
E+28GR620

Installation of Flexibles / Plenum

3 28-Jun-14

01-Jul-14

E+28GR17360 Gypsum Ceilings

6 03-Jul-14

12-Jul-14

E+28GR17400 Paint Ceiling

4 13-Jul-14

19-Jul-14

E+28GR17390 Millwork

6 20-Jul-14

30-Jul-14

E+28GR17380 Wall Covering & fabric panels

4 24-Jul-14

30-Jul-14

E+28GR660

Light Fittings Installation

2 31-Jul-14

02-Aug-14

E+28GR670

Sprinkler Installation

2 31-Jul-14

02-Aug-14

3 03-Aug-14

05-Aug-14

E+28GR17410 Underlay & Carpet


Guestrooms
Finishes - 1st Fix
No DISP
T+28PS18130 Studwork to walls incl noggins
T+28PS18140

Close blockwork risers

168
69
69
18

29-Dec-13
29-Dec-13
29-Dec-13
29-Dec-13

20-Jul-14
19-Mar-14
19-Mar-14
19-Jan-14

20 25-Feb-14

19-Mar-14

MEP riser summary


No DISP
T+28PS18480 MEP risers & 1st fix Riser 1

18 14-Jan-14
18 14-Jan-14
18 14-Jan-14

03-Feb-14
03-Feb-14
03-Feb-14

MEP Risers & First Fix


No DISP
T+28PS19940 Ductworks risers

43 14-Jan-14
43 14-Jan-14
12 14-Jan-14

04-Mar-14
04-Mar-14
27-Jan-14

T+28PS20050

Cable tray / trunking

12 21-Jan-14

03-Feb-14

T+28PS19950

Chilled water & condensate

12 21-Jan-14

03-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 120 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+28PS19970

DCW / DHW & CCW riser

12 28-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-Feb-14

T+28PS19980

Sanitary riser

12 28-Jan-14

10-Feb-14

T+28PS19990

Hang FCU

12 28-Jan-14

10-Feb-14

T+28PS20000

Ductwork - supply, make-up air & extract

12 28-Jan-14

10-Feb-14

T+28PS20010

CW supply / return & condensate

12 01-Feb-14

13-Feb-14

T+28PS20020

Plumbing & san distribution

12 02-Feb-14

15-Feb-14

T+28PS20040

FCU connections

12 08-Feb-14

20-Feb-14

T+28PS19960

Test risers ( 3floors vertically )

12 11-Feb-14

24-Feb-14

T+28PS20060

Sprinkler pipes ( Not drops ) from corridor

18 12-Feb-14

04-Mar-14

T+28PS20030

MEP sign off risers (Start)

Activity ID

Activity Name

Bedroom
No DISP
T+28PS21610

MEP Drops in walls & back boxes

Duration Start

24-Feb-14

113 28-Jan-14
113 28-Jan-14
12 28-Jan-14

08-Jun-14
08-Jun-14
10-Feb-14

T+28PS21620

Insulate & board walls

12 18-Feb-14

03-Mar-14

T+28PS21630

Ceiling 1st fix

18 23-Feb-14

15-Mar-14

T+28PS21640

Wiring

12 27-Feb-14

12-Mar-14

T+28PS21650

MEP drops in ceiling

12 03-Mar-14

16-Mar-14

T+28PS21660

Board ceiling

12 04-Mar-14

17-Mar-14

T+28PS21670

Tape & Joint walls & ceiling

12 09-Mar-14

22-Mar-14

T+28PS21680

Mist coat all dry lining

12 13-Mar-14

26-Mar-14

T+28PS21690

Install cornice

12 16-Mar-14

29-Mar-14

T+28PS21700

Paint ceiling and cornice

12 20-Mar-14

02-Apr-14

T+28PS21710

Wall covering

12 28-Apr-14

11-May-14

T+28PS21720

Install furniture

12 03-May-14

15-May-14

T+28PS21730

MEP terminations in furniture

12 10-May-14

22-May-14

T+28PS21740

MEP 3rd fix- sockets, cover plates etc

12 14-May-14

27-May-14

T+28PS26340

Underlay & Carpet

6 02-Jun-14

08-Jun-14

120 20-Jan-14
120 20-Jan-14
12 20-Jan-14

08-Jun-14
08-Jun-14
02-Feb-14

Bathroom
No DISP
T+28PS26310

SS frame to shower & toilet

T+28PS24310

MEP Drops in walls & back boxes

12 28-Jan-14

10-Feb-14

T+28PS24280

Stud to block walls

12 04-Mar-14

17-Mar-14

T+28PS24330

Insulate & board walls

12 04-Mar-14

17-Mar-14

T+28PS24350

First fix ceiling

12 06-Mar-14

19-Mar-14

T+28PS24360

MEP drops in ceiling

12 09-Mar-14

22-Mar-14

T+28PS24370

2nd fix ceiling incl access panel

12 10-Mar-14

23-Mar-14

T+28PS24290

Waterproof bathroom

12 11-Mar-14

24-Mar-14

T+28PS24380

Install corniche

12 12-Mar-14

25-Mar-14

T+28PS24300

Flood test

12 18-Mar-14

31-Mar-14

T+28PS24390

Stone to floors

12 19-Mar-14

01-Apr-14

T+28PS24400

Stone surround to bath

12 19-Mar-14

01-Apr-14

T+28PS24410

Stone vanity

12 19-Mar-14

01-Apr-14

T+28PS24420

Stone to walls incl niche

12 19-Mar-14

01-Apr-14

T+28PS24430

Casing stone

12 19-Mar-14

01-Apr-14

T+28PS24320

Install bath

12 25-Mar-14

07-Apr-14

T+28PS24440

Grout to all stone

12 26-Mar-14

08-Apr-14

T+28PS24340

Framing & board for bath

12 27-Mar-14

09-Apr-14

T+28PS26320

Vanity S/S & mirrors

12 02-Apr-14

15-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 121 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+28PS26330

Vanity Unit

12 02-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
15-Apr-14

T+28PS24450

Glass Partition

12 09-Apr-14

22-Apr-14

T+28PS24500

Hang glass doors

12 09-Apr-14

22-Apr-14

T+28GU18120

Wall covering

12 16-Apr-14

29-Apr-14

T+28PS24460

Install and connect " Free issue " mirror

12 20-May-14

02-Jun-14

T+28PS24470

Sanitary ware and accessories

12 22-May-14

04-Jun-14

T+28PS24480

MEP connections to bath and basin

12 24-May-14

05-Jun-14

T+28PS24490

MEP 3rd fix - switch / socket covers

Activity ID

Activity Name

Entrance Vestibule & dressing


No DISP
T+28PS26160 MEP drops in walls

Duration Start

12 26-May-14

08-Jun-14

128 04-Feb-14
128 04-Feb-14
12 04-Feb-14

05-Jul-14
05-Jul-14
17-Feb-14

T+28PS26170

Board walls

12 04-Mar-14

17-Mar-14

T+28PS26180

Ceiling 1st fix

12 06-Mar-14

19-Mar-14

T+28PS26190

MEP drops in ceiling

12 09-Mar-14

22-Mar-14

T+28PS26200

Board ceiling incl access panel

12 12-Mar-14

25-Mar-14

T+28PS26210

Door frames

12 15-Mar-14

27-Mar-14

T+28PS26220

Tape & joint walls & ceilings

12 15-Mar-14

27-Mar-14

T+28PS26230

Mist coat dry lining

18 16-Mar-14

05-Apr-14

T+28PS26240

Paint ceiling

12 18-Mar-14

31-Mar-14

T+28PS26250

Stone flooring incl grout

12 20-Mar-14

02-Apr-14

T+28PS26280

Install wardrobe

12 03-Apr-14

16-Apr-14

T+28PS26290

Wall Coverings

12 06-Apr-14

19-Apr-14

T+28PS26270

Mirrors

12 10-Apr-14

23-Apr-14

T+28PS26300

3rd fix MEP

12 17-Apr-14

30-Apr-14

T+28PS26260

Pocket door to bathroom

12 19-Jun-14

05-Jul-14

156 13-Jan-14
156 13-Jan-14
6 13-Jan-14

20-Jul-14
20-Jul-14
19-Jan-14

Corridor
No DISP
T+28GR17350

Gypsum Walls

T+28PS580

Cable Tray / Trunking

15 13-Feb-14

02-Mar-14

T+28PS600

Duct Installation

12 20-Feb-14

05-Mar-14

T+28PS610

Electrical Containment

12 26-Feb-14

11-Mar-14

T+28PS590

FP Piping

10 06-Mar-14

17-Mar-14

T+28PS640

Sprinkler Dropper piping Installation

6 18-Mar-14

24-Mar-14

T+28PS650

FP Pipe Pressure Testing

3 25-Mar-14

27-Mar-14

T+28GR620

Installation of Flexibles / Plenum

8 29-May-14

07-Jun-14

T+28GR640

Sprinkler Drops

6 01-Jun-14

07-Jun-14

T+28GR17360

Gypsum Ceilings

6 01-Jun-14

07-Jun-14

T+28GR680

Grilles / Diffuser Installation

4 08-Jun-14

11-Jun-14

T+28GR17370

T & J Walls & Ceilings

6 08-Jun-14

14-Jun-14

T+28GR17400

Paint Ceiling

4 15-Jun-14

18-Jun-14

T+28GR17390

Millwork

10 19-Jun-14

01-Jul-14

T+28GR17380

Wall Covering

4 03-Jul-14

08-Jul-14

T+28GR17420

Mirrors

3 03-Jul-14

06-Jul-14

T+28GR660

Light Fittings Installation

4 10-Jul-14

15-Jul-14

T+28GR690

FA / SD installation

4 10-Jul-14

15-Jul-14

T+28GR670

Sprinkler Installation

4 10-Jul-14

15-Jul-14

T+28GR17410

Underlay & Carpet

3 17-Jul-14

20-Jul-14

138 11-Oct-13 A

26-Mar-14

+29 @ +124.40
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 122 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Facades
Facades
No DISP
T+29FA230

Curtain Wall to guestrooms + 29

Mechanical Plantroom
Finishes
No DISP
T+29MP220
Painting on walls & floor

138
12
12
12

26-Mar-14
19-Nov-13
19-Nov-13
19-Nov-13

Access from Structure

T+29MP260

Drainage Riser

10 21-Nov-13

03-Dec-13

T+29MP270

Rain Water Riser

8 25-Nov-13

04-Dec-13

T+29MP280

CD Pipe Riser

8 25-Nov-13

04-Dec-13

T+29MP290

Water Supply Risers

12 27-Nov-13

11-Dec-13

T+29MP300

Electrical Risers

12 30-Nov-13

14-Dec-13

T+29MP310

LPG Riser

6 30-Nov-13

07-Dec-13

T+29MP320

Ducting Risers

14 01-Dec-13

17-Dec-13

T+29MP330

FP Pipe Riser

10 01-Dec-13

12-Dec-13

T+29MP340

CHW Pipe Supply/Return riser

14 07-Dec-13

22-Dec-13

84 16-Nov-13
84 16-Nov-13
10 16-Nov-13

23-Feb-14
23-Feb-14
26-Nov-13

T+29MP410

FCU Installation

8 16-Nov-13

24-Nov-13

T+29MP470

MCC Panels and Switches

21 25-Nov-13

19-Dec-13

T+29MP400

Piping and Valve connection to Pumps

16 27-Nov-13

16-Dec-13

T+29MP360

Drainage Piping

10 04-Dec-13

15-Dec-13

T+29MP580

Condensate Drain Pipe connection

8 05-Dec-13

14-Dec-13

T+29MP620

Electrical Containment

18 08-Dec-13

28-Dec-13

T+29MP380

FF Piping

14 14-Dec-13

29-Dec-13

T+29MP460

Cable Tray & Trunking

21 15-Dec-13

08-Jan-14

T+29MP370

Drainage Pipe Testing

6 16-Dec-13

22-Dec-13

T+29MP350

Ducting connection to AHU

21 18-Dec-13

12-Jan-14

T+29MP420

Duct connection to FCU

18 18-Dec-13

08-Jan-14

T+29MP430

CHW Pipe and valve connections to AHU

21 23-Dec-13

16-Jan-14

T+29MP440

CHW Pipe and valve connections to FCU

18 23-Dec-13

13-Jan-14

T+29MP570

FF Pipe pressure Testing

6 30-Dec-13

06-Jan-14

T+29MP480

Cable & Wire Pulling

21 09-Jan-14

02-Feb-14

T+29MP450

Installation of Dampers and Plenums

12 13-Jan-14

26-Jan-14

T+29MP560

Fans Installation & connection

16 13-Jan-14

30-Jan-14

T+29MP610

CHW Pipe insulation

18 15-Jan-14

04-Feb-14

T+29MP510

CHW Pipe Pressure Testing

6 18-Jan-14

23-Jan-14

T+29MP490

Cable Termination

18 03-Feb-14

23-Feb-14

Installation of floor Drains

80 23-Dec-13
80 23-Dec-13
4 23-Dec-13

26-Mar-14
26-Mar-14
26-Dec-13

MEP Final Fix


No DISP
T+29MP520
T+29MP500

Sprinkler Installation

8 28-Jan-14

05-Feb-14

T+29MP530

Grilles & Louvres

14 05-Feb-14

20-Feb-14

T+29MP550

Light fittings

10 24-Feb-14

06-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

11-Oct-13 A
11-Oct-13 A
11-Oct-13 A
11-Oct-13 A

22-Dec-13
22-Dec-13

MEP 1st & 2nd Fix


No DISP
T+29MP390
Installation of Fire Pumps

Revised Programme Rev. D

01-Mar-14
01-Mar-14
01-Mar-14
01-Mar-14

27 20-Nov-13
27 20-Nov-13
0 20-Nov-13

MEP Risers
No DISP
T+29MP250

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
06-Mar-14
06-Mar-14
06-Mar-14
06-Mar-14

Duration Start

6
6
6
6

Four Seasons Hotel Bahrain

Page 123 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+29MP540

FA & SD Devices

T+29MP590

Clean & Snag

+30 @ +129.40
Guestrooms
Facades
No DISP
T+30FA120
Roof
General
No DISP
T+30SW100

Curtain Wall to Guestrooms + 30

BMU concrete upstands & electricity distribution

Duration Start

8 02-Mar-14
14 11-Mar-14

26-Mar-14

140 20-Oct-13 A

06-Apr-14

6
6
6
6

01-Mar-14
01-Mar-14
01-Mar-14
01-Mar-14

06-Mar-14
06-Mar-14
06-Mar-14
06-Mar-14

36
36
36
4

24-Feb-14
24-Feb-14
24-Feb-14
24-Feb-14

06-Apr-14
06-Apr-14
06-Apr-14
27-Feb-14

Screed with slope

6 08-Mar-14

13-Mar-14

T+30SW150

BMU rails on concrete upstands

6 08-Mar-14

13-Mar-14

T+30SW160

BMU installation/testing & commissioning

4 10-Mar-14

13-Mar-14

T+30SW120

Waterproofing

6 15-Mar-14

20-Mar-14

T+30SW170

Waterproof Water test

4 22-Mar-14

25-Mar-14

T+30SW130

Insulation

4 26-Mar-14

30-Mar-14

T+30SW140

Pavers & gravel protection

6 31-Mar-14

06-Apr-14

132
123
123
4

20-Oct-13 A
20-Oct-13 A
20-Oct-13 A
16-Nov-13

27-Mar-14
17-Mar-14
17-Mar-14
19-Nov-13

T+30MP100

Masonry

12 20-Oct-13 A

26-Nov-13

T+30MP200

Painting on walls & floor

18 20-Nov-13

11-Dec-13

T+30MP140

Painting on walls first coat

9 20-Nov-13

30-Nov-13

T+30MP120

Metal door with frames

9 08-Mar-14*

17-Mar-14

Access from Structure

27 27-Nov-13
27 27-Nov-13
0 27-Nov-13

T+30MP230

Drainage Riser

10 28-Nov-13

10-Dec-13

T+30MP240

Rain Water Riser

8 03-Dec-13

11-Dec-13

T+30MP250

CD Pipe Riser

8 03-Dec-13

11-Dec-13

T+30MP260

Water Supply Risers

12 05-Dec-13

18-Dec-13

T+30MP270

Electrical Risers

12 08-Dec-13

21-Dec-13

T+30MP280

LPG Riser

6 08-Dec-13

14-Dec-13

T+30MP290

Ducting Risers

14 09-Dec-13

24-Dec-13

T+30MP300

FP Pipe Riser

10 09-Dec-13

19-Dec-13

T+30MP310

CHW Pipe Supply/Return riser

14 14-Dec-13

29-Dec-13

85 20-Nov-13
85 20-Nov-13
12 20-Nov-13

01-Mar-14
01-Mar-14
04-Dec-13

MEP Risers
No DISP
T+30MP220

MEP 1st & 2nd Fix


No DISP
T+30GE010
Transformer Installation

29-Dec-13
29-Dec-13

T+30GE050

Installation of HEX

16 26-Nov-13

15-Dec-13

T+30GE080

MCC Panels and Switches

21 01-Dec-13

25-Dec-13

T+30GE020

Installation of HV Switchgears

18 05-Dec-13

25-Dec-13

T+30GE060

FCU Installation

14 05-Dec-13

21-Dec-13

T+30GE110

Cable Tray & Trunking

21 08-Dec-13

31-Dec-13

T+30GE040

Drainage Piping

10 12-Dec-13

23-Dec-13

T+30GE150

Electrical Containment

18 14-Dec-13

04-Jan-14

T+30GE030

Installation & connection to Tertiary CHW Pumps

18 16-Dec-13

06-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 124 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-Mar-14

T+30SW110

Mechanical Plantroom
Finishes
No DISP
T+30MP110
Concrete Plinths

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

FP Piping

T+30GE120

Condensate Drain Pipe connection

8 22-Dec-13

30-Dec-13

T+30GE100

Drainage Pipe Testing

6 24-Dec-13

30-Dec-13

T+30GE140

Duct connection to FCU

18 25-Dec-13

15-Jan-14

T+30GE130

HV cable pulling & connections

21 26-Dec-13

20-Jan-14

T+30GE160

CHW Pipe and valve connections to HEX

21 30-Dec-13

23-Jan-14

T+30GE170

CHW Pipe and valve connections to FCU

18 30-Dec-13

20-Jan-14

T+30GE200

Cable & Wire Pulling

21 05-Jan-14

28-Jan-14

T+30GE070

Installationn & connection to Expansion Tanks

8 07-Jan-14

15-Jan-14

T+30GE180

FP Pipe pressure Testing

6 07-Jan-14

13-Jan-14

T+30GE190

Installation of Dampers and Plenums

12 16-Jan-14

29-Jan-14

T+30GE210

Fans Installation & connection

16 21-Jan-14

08-Feb-14

T+30GE230

CHW Pipe Pressure Testing

8 25-Jan-14

02-Feb-14

T+30GE220

CHW Pipe insulation

18 25-Jan-14

13-Feb-14

T+30GE240

Cable Termination

18 09-Feb-14

01-Mar-14

Installation of floor Drains

74 31-Dec-13
74 31-Dec-13
4 31-Dec-13

27-Mar-14
27-Mar-14
05-Jan-14

T+30GE270

Sprinkler Installation

8 14-Jan-14

22-Jan-14

T+30GE280

Grilles & Louvres

14 15-Feb-14

02-Mar-14

T+30GE300

Light fittings

10 02-Mar-14

12-Mar-14

T+30GE290

FA & SD Devices

8 08-Mar-14

16-Mar-14

T+30GE310

Clean & Snag

+31 @ +133.20
General
Finishes
No DISP
T+31GE110

Masonry

10 17-Mar-14

27-Mar-14

144 16-Nov-13

04-May-14

115
115
115
6

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

31-Mar-14
31-Mar-14
31-Mar-14
21-Nov-13

T+31GE210

Install metal frames & doors

6 18-Mar-14

24-Mar-14

T+31GE220

Final Painting

9 22-Mar-14

31-Mar-14
24-Dec-13
24-Dec-13

Access from Structure

27 23-Nov-13
27 23-Nov-13
0 23-Nov-13

T+31GE310

Drainage Riser

10 24-Nov-13

05-Dec-13

T+31GE320

Rain Water Riser

8 27-Nov-13

07-Dec-13

T+31GE330

CD Pipe Riser

8 27-Nov-13

07-Dec-13

T+31GE340

Water Supply Risers

12 30-Nov-13

14-Dec-13

T+31GE350

Electrical Risers

12 03-Dec-13

16-Dec-13

T+31GE370

Ducting Risers

14 04-Dec-13

19-Dec-13

T+31GE380

FP Pipe Riser

10 04-Dec-13

15-Dec-13

T+31GE390

CHW Pipe Supply/Return riser

14 09-Dec-13

24-Dec-13

T+31GE360

LPG Riser

6 15-Dec-13

21-Dec-13

12 17-Mar-14
12 17-Mar-14
6 17-Mar-14

30-Mar-14
30-Mar-14
23-Mar-14

6 24-Mar-14

30-Mar-14

144 16-Nov-13
121 16-Nov-13
121 16-Nov-13

04-May-14
07-Apr-14
07-Apr-14

MEP Risers
No DISP
T+31GE300

General
No DISP
T+31GE260
T+31GE270

Testing & commissioning


Inspection & snag list

Electrical Plantroom
Finishes
No DISP
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 125 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
06-Jan-14

T+30GE090

MEP Final Fix


No DISP
T+30GE260

14 21-Dec-13

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

Masonry

T+31EP120

Concrete support for equipments

12 17-Nov-13

30-Nov-13

T+31EP130

Painting on walls first coat

12 01-Dec-13

15-Dec-13

T+31EP110

Metal door with frames

6 25-Mar-14

31-Mar-14

T+31EP190

Final Painting

6 01-Apr-14

07-Apr-14

89 01-Dec-13
89 01-Dec-13
12 01-Dec-13

16-Mar-14
16-Mar-14
15-Dec-13

T+31EP330

Electrical Containment

18 03-Dec-13

23-Dec-13

T+31EP230

Drainage Piping

10 07-Dec-13

17-Dec-13

T+31EP300

FP Piping

14 16-Dec-13

31-Dec-13

T+31EP270

Installation of HV Switchgears

18 16-Dec-13

06-Jan-14

T+31EP280

FCU Installation

14 16-Dec-13

31-Dec-13

T+31EP310

Cable Ladders, Tray & Trunking

21 17-Dec-13

11-Jan-14

T+31EP250

Drainage Pipe Testing

6 18-Dec-13

24-Dec-13

T+31EP340

Duct connection to FCU

18 02-Jan-14

22-Jan-14

T+31EP360

CHW Pipe and valve connections to FCU

18 02-Jan-14

22-Jan-14

T+31EP370

Condensate Drain Pipe connection

8 02-Jan-14

11-Jan-14

T+31EP390

FP Pipe pressure Testing

6 02-Jan-14

08-Jan-14

T+31EP260

Installation of LV Panels

16 07-Jan-14

25-Jan-14

T+31EP380

HV cable pulling & connections

21 12-Jan-14

04-Feb-14

T+31EP410

Cable & Wire Pulling

21 12-Jan-14

04-Feb-14

T+31EP420

Installation of Dampers and Plenums

12 23-Jan-14

05-Feb-14

T+31EP430

CHW Pipe Pressure Testing

8 23-Jan-14

01-Feb-14

T+31EP440

CHW Pipe insulation

18 23-Jan-14

12-Feb-14

T+31EP520

LV Cable pulling and connections

14 26-Jan-14

10-Feb-14

T+31EP450

Fans Installation & connection

16 05-Feb-14

23-Feb-14

T+31EP460

Cable Termination

18 24-Feb-14

16-Mar-14

Sprinkler Installation

35 25-Mar-14
35 25-Mar-14
8 25-Mar-14

04-May-14
04-May-14
02-Apr-14

MEP Final Fix


No DISP
T+31EP480
T+31EP470

Installation of floor Drains

4 25-Mar-14

29-Mar-14

T+31EP490

Grilles & Louvres

14 25-Mar-14

09-Apr-14

T+31EP500

Light fittings

10 08-Apr-14

19-Apr-14

T+31EP510

FA & SD Devices

8 14-Apr-14

22-Apr-14

T+31EP530

Clean & Snag

10 23-Apr-14

04-May-14

Testing & commissioning

24 17-Mar-14
24 17-Mar-14
24 17-Mar-14

13-Apr-14
13-Apr-14
13-Apr-14

6 23-Nov-13

28-Nov-13

6
6
6
6

23-Nov-13
23-Nov-13
23-Nov-13
23-Nov-13

28-Nov-13
28-Nov-13
28-Nov-13
28-Nov-13

142 30-Nov-13

15-May-14

142
112
112
6

15-May-14
10-Apr-14
10-Apr-14
07-Dec-13

General
No DISP
T+31EP200

+32 @ +137.00
General
Finishes
No DISP
T+32GE410

Masonry

+35 @ +148.40
General
Finishes
No DISP
T+35GE100

Masonry

30-Nov-13
30-Nov-13
30-Nov-13
30-Nov-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 126 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
21-Nov-13

T+31EP100

MEP 1st & 2nd Fix


No DISP
T+31EP240
Transformer Installation

6 16-Nov-13

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+35GE200

Install metal frames & doors

T+35GE210

Final Painting

6 05-Apr-14

10-Apr-14
08-Jan-14
08-Jan-14

Access from Structure


Drainage Riser

10 09-Dec-13

19-Dec-13

T+35GE310

Rain Water Riser

8 12-Dec-13

21-Dec-13

T+35GE320

CD Pipe Riser

8 12-Dec-13

21-Dec-13

T+35GE330

Water Supply Risers

12 15-Dec-13

28-Dec-13

T+35GE340

Electrical Risers

12 17-Dec-13

30-Dec-13

T+35GE360

Ducting Risers

14 18-Dec-13

04-Jan-14

T+35GE370

FP Pipe Riser

10 18-Dec-13

29-Dec-13

T+35GE350

LPG Riser

6 19-Dec-13

25-Dec-13

T+35GE380

CHW Pipe Supply/Return riser

14 23-Dec-13

08-Jan-14

69 21-Dec-13
69 21-Dec-13
10 21-Dec-13

11-Mar-14
11-Mar-14
31-Dec-13

T+35GE430

FCU Installation

14 22-Dec-13

07-Jan-14

T+35GE410

FP Piping

14 30-Dec-13

15-Jan-14

T+35GE570

Cable Tray & Trunking

21 31-Dec-13

25-Jan-14

T+35GE450

Electrical Containment

18 31-Dec-13

21-Jan-14

T+35GE440

Drainage Pipe Testing

T+35GE460

Duct connection to FCU

T+35GE480

6 02-Jan-14

08-Jan-14

18 08-Jan-14

28-Jan-14

Condensate Drain Pipe connection

8 09-Jan-14

18-Jan-14

T+35GE490

FP Pipe pressure Testing

6 16-Jan-14

22-Jan-14

T+35GE470

CHW Pipe and valve connections to FCU

18 20-Jan-14

09-Feb-14

T+35GE580

Cable & Wire Pulling

21 26-Jan-14

18-Feb-14

T+35GE520

Installation of Dampers and Plenums

12 29-Jan-14

11-Feb-14

T+35GE530

CHW Pipe Pressure Testing

8 10-Feb-14

18-Feb-14

T+35GE540

CHW Pipe insulation

18 10-Feb-14

02-Mar-14

T+35GE590

Cable Termination

18 19-Feb-14

11-Mar-14
15-May-14
15-May-14
16-Apr-14

Sprinkler Installation

33 08-Apr-14
33 08-Apr-14
8 08-Apr-14

T+35GE620

Grilles & Louvres

14 08-Apr-14

23-Apr-14

T+35GE630

Light fittings

10 12-Apr-14

22-Apr-14

T+35GE640

FA & SD Devices

8 17-Apr-14

26-Apr-14

T+35GE650

Clean & Snag

MEP Final Fix


No DISP
T+35GE600

+39 @ +163.60
General
Finishes
No DISP
T+39GE100

Masonry

10 05-May-14

15-May-14

148 08-Dec-13

29-May-14

112
112
112
6

08-Dec-13
08-Dec-13
08-Dec-13
08-Dec-13

17-Apr-14
17-Apr-14
17-Apr-14
14-Dec-13

T+39GE200

Install metal frames & doors

6 08-Apr-14

14-Apr-14

T+39GE210

Final Painting

6 12-Apr-14

17-Apr-14

12 19-Mar-14
12 19-Mar-14
6 19-Mar-14

01-Apr-14
01-Apr-14
25-Mar-14

6 26-Mar-14

01-Apr-14

General
No DISP
T+39GE250
T+39GE260

Testing & commissioning


Inspection & snag list

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Revised Programme Rev. D

Data date: 16-Nov-13

6 01-Apr-14

T+35GE300

MEP 1st & 2nd Fix


No DISP
T+35GE400
Drainage Piping

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
07-Apr-14

Duration Start

27 08-Dec-13
27 08-Dec-13
0 08-Dec-13

MEP Risers
No DISP
T+35GE290

Four Seasons Hotel Bahrain

Page 127 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Mechanical Plantroom
Finishes
No DISP
T+39MP100
Masonry

Duration Start

148
127
127
6

08-Dec-13
08-Dec-13
08-Dec-13
08-Dec-13

Concrete Plinths

9 09-Dec-13

18-Dec-13

T+39MP140

Painting on walls first coat

9 19-Dec-13

29-Dec-13

T+39MP120

Install metal frames & doors

6 08-Apr-14

14-Apr-14

T+39MP200

Painting on walls & floor

18 15-Apr-14

05-May-14
15-Jan-14
15-Jan-14

Access from Structure

27 15-Dec-13
27 15-Dec-13
0 15-Dec-13

T+39MP230

Drainage Riser

10 16-Dec-13

26-Dec-13

T+39MP240

Rain Water Riser

8 19-Dec-13

28-Dec-13

T+39MP250

CD Pipe Riser

8 19-Dec-13

28-Dec-13

T+39MP260

Water Supply Risers

12 22-Dec-13

05-Jan-14

T+39MP270

Electrical Risers

12 24-Dec-13

07-Jan-14

T+39MP290

Ducting Risers

14 25-Dec-13

11-Jan-14

T+39MP300

FP Pipe Riser

10 25-Dec-13

06-Jan-14

T+39MP280

LPG Riser

6 25-Dec-13

31-Dec-13

T+39MP310

CHW Pipe Supply/Return riser

14 30-Dec-13

15-Jan-14

76 19-Dec-13
76 19-Dec-13
16 19-Dec-13

18-Mar-14
18-Mar-14
07-Jan-14

MEP 1st & 2nd Fix


No DISP
T+39MP350
Installation of HEX
T+39MP320

Drainage Piping

10 28-Dec-13

08-Jan-14

T+39MP370

FCU Installation

14 29-Dec-13

14-Jan-14

T+39MP380

MCC Panels and Switches

21 30-Dec-13

23-Jan-14

T+39MP390

FP Piping

14 07-Jan-14

22-Jan-14

T+39MP440

HW Pipe and valve connections to HEX

21 08-Jan-14

01-Feb-14

T+39MP400

Cable Tray & Trunking

21 08-Jan-14

01-Feb-14

T+39MP410

Installation & connection to DHW Pumps

18 08-Jan-14

28-Jan-14

T+39MP340

Drainage Pipe Testing

6 09-Jan-14

15-Jan-14

T+39MP420

Electrical Containment

18 12-Jan-14

01-Feb-14

T+39MP430

Duct connection to FCU

18 15-Jan-14

04-Feb-14

T+39MP460

Condensate Drain Pipe connection

8 15-Jan-14

23-Jan-14

T+39MP450

CHW Pipe and valve connections to FCU

18 16-Jan-14

05-Feb-14

T+39MP540

Fans Installation & connection

16 23-Jan-14

10-Feb-14

T+39MP480

FP Pipe pressure Testing

6 23-Jan-14

29-Jan-14

T+39MP500

Cable & Wire Pulling

21 02-Feb-14

25-Feb-14

T+39MP510

Installation of Dampers and Plenums

12 05-Feb-14

18-Feb-14

T+39MP520

CHW Pipe Pressure Testing

8 06-Feb-14

15-Feb-14

T+39MP530

CHW Pipe insulation

18 06-Feb-14

26-Feb-14

T+39MP550

Cable Termination

18 26-Feb-14

18-Mar-14

Sprinkler Installation

36 19-Apr-14
36 19-Apr-14
8 19-Apr-14

29-May-14
29-May-14
27-Apr-14

MEP Final Fix


No DISP
T+39MP560
T+39MP570

Installation of floor Drains

4 21-Apr-14

24-Apr-14

T+39MP580

Grilles & Louvres

14 23-Apr-14

08-May-14

T+39MP590

Light fittings

10 06-May-14

17-May-14

T+39MP600

FA & SD Devices

8 10-May-14

18-May-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 128 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
29-May-14
05-May-14
05-May-14
14-Dec-13

T+39MP110

MEP Risers
No DISP
T+39MP220

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+39MP610

Clean & Snag

+41 @ +171.20
General
Finishes
No DISP
T+41GE100

Masonry

T+41GE200

Install metal frames & doors

T+41GE210

Final Painting

Duration Start

10 19-May-14
112 15-Dec-13

24-Apr-14

112
112
112
6

15-Dec-13
15-Dec-13
15-Dec-13
15-Dec-13

24-Apr-14
24-Apr-14
24-Apr-14
21-Dec-13

6 15-Apr-14

21-Apr-14

6 19-Apr-14

24-Apr-14
09-Feb-14
09-Feb-14
19-Jan-14

Plumbing & FP distr, tests

T+41GE130

HVAC Duct, pipes distr, FCU & tests

24 22-Dec-13

19-Jan-14

T+41GE140

Electrical distribution LV&LC

24 22-Dec-13

19-Jan-14

T+41GE170

Pb&FF equip (sprinkler heads...)

12 20-Jan-14

02-Feb-14

T+41GE180

HVAC Grilles & diffusers...

12 20-Jan-14

02-Feb-14

T+41GE190

Electr equip, lighting fixt....

12 20-Jan-14

02-Feb-14

T+41GE220

Pb&FF tests

6 03-Feb-14

09-Feb-14

T+41GE230

HVAC tests

6 03-Feb-14

09-Feb-14

T+41GE240

Electr tests

6 03-Feb-14

09-Feb-14

50 12-Oct-13 A

28-Dec-13

12-Oct-13 A
12-Oct-13 A
12-Oct-13 A
12-Oct-13 A

28-Dec-13
28-Dec-13
28-Dec-13
07-Dec-13

+42 @ +175.00

Secondary steel & metal soffit

50
50
50
30

T+42CCT160

Secondary steel & BMU installation

24 19-Oct-13 A

05-Dec-13

TGETO100

Remove RMD framing & platform to +30

18 08-Dec-13

28-Dec-13

210 30-Oct-13 A

19-Jul-14

Guestrooms
Civil Works
No DISP
T+42CCT150

+43 @ +178.80
Facades
Facades
No DISP
T+44CCT110
Corridor
Finishes
No DISP
P+43RE370
Kitchen
Finishes
No DISP
T+43KI100

Skypod Curtain Wall

12
12
12
12

07-Dec-13
07-Dec-13
07-Dec-13
07-Dec-13*

19-Dec-13
19-Dec-13
19-Dec-13
19-Dec-13

Marble to Corridor Floor

10
10
10
10

11-May-14
11-May-14
11-May-14
11-May-14

21-May-14
21-May-14
21-May-14
21-May-14

190
190
190
4

26-Nov-13
26-Nov-13
26-Nov-13
26-Nov-13

12-Jul-14
12-Jul-14
12-Jul-14
30-Nov-13

12 15-Feb-14

27-Feb-14

6 01-Mar-14

06-Mar-14

Masonry kitchen

T+43KI200

Waterproofing & tests on floor

T+43KI210

Screed

T+43KI220

Floor ceramic tiles

12 08-Mar-14

20-Mar-14

T+43KI330

Wall finish - FRP01

12 22-Mar-14

03-Apr-14

T+43KI120

Coldroom installation

18 05-Apr-14

24-Apr-14

T+43KI170

Hood installation

12 19-Apr-14

01-May-14

T+43KI240

Acoustic false ceiling

9 03-May-14

12-May-14

T+43KI290

Install metal frames & doors

6 13-May-14

19-May-14

T+43KI300
T+43KI310

Kitchen equipment
Millwork

24 20-May-14
12 17-Jun-14

16-Jun-14
01-Jul-14

T+43KI320

Painting

6 03-Jul-14

12-Jul-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 129 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
29-May-14

42 22-Dec-13
42 22-Dec-13
24 22-Dec-13

General
No DISP
T+41GE120

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

Access from Structure

T+43Kl20

Drainage Riser

10 03-Dec-13

14-Dec-13

T+43Kl30

Rain Water Riser

12 07-Dec-13

19-Dec-13

T+43Kl40

CD Pipe Riser

12 07-Dec-13

19-Dec-13

T+43Kl50

Water Supply Risers

12 09-Dec-13

22-Dec-13

T+43Kl60

Electrical Risers

12 11-Dec-13

24-Dec-13

T+43Kl80

Ducting Risers

18 12-Dec-13

02-Jan-14

T+43Kl90

FP Pipe Riser

10 12-Dec-13

23-Dec-13

T+43Kl100

CHW Pipe Supply/Return riser

14 17-Dec-13

02-Jan-14

T+43Kl70

LPG Riser

12 25-Dec-13

08-Jan-14

116 24-Dec-13
116 24-Dec-13
36 24-Dec-13

08-May-14
08-May-14
04-Feb-14

General
No DISP
T+43KI130

Plumbing & FP distr, tests

T+43KI140

HVAC Duct, pipes distr, FCU & tests

36 04-Jan-14

13-Feb-14

T+43KI150

Electrical distribution LV

36 04-Jan-14

13-Feb-14

T+43KI250

Pb & FP equip (sprinkler heads...)

6 03-May-14

08-May-14

T+43KI260

Plumbing & FP access

6 03-May-14

08-May-14

T+43KI270

HVAC Grilles & diffusers...

6 03-May-14

08-May-14

T+43KI280

Electr equip, lighting fixt....

6 03-May-14

08-May-14

Meeting Rooms & Board Room


Finishes
No DISP
P+43RE260
Masonry

189
189
189
12

30-Oct-13 A
30-Oct-13 A
30-Oct-13 A
30-Oct-13 A

Gypsum Partitions

12 02-Feb-14

15-Feb-14

P+43RE300

Gypsum Ceilings

18 16-Feb-14

08-Mar-14

P+43RE350

Operable Partitions

18 09-Mar-14

29-Mar-14

P+43RE310

Stairs to Level 44

24 30-Mar-14*

26-Apr-14

P+43RE330

Marble to floor

12 27-Apr-14

10-May-14

P+43RE320

Millwork

24 22-May-14

18-Jun-14

P+43RE380

Wallcovering

15 09-Jun-14

25-Jun-14

P+43RE360

Final Paint

6 26-Jun-14

05-Jul-14

P+43RE340

Carpet

6 06-Jul-14

15-Jul-14

160 21-Dec-13
160 21-Dec-13
12 21-Dec-13

25-Jun-14
25-Jun-14
04-Jan-14

Plumbing & FP distr, tests

T+43MR130

HVAC Duct, pipes distr, FCU & tests

12 28-Dec-13

11-Jan-14

T+43MR140

Electrical distribution LV&LC

12 05-Jan-14

18-Jan-14

T+43MR190

Pb & FP equip (sprinkler heads...)

6 19-Jun-14

25-Jun-14

T+43MR200

HVAC Grilles & diffusers...

6 19-Jun-14

25-Jun-14

T+43MR210

Electr equip, lighting fixt....

6 19-Jun-14

25-Jun-14

Restaurant
Finishes
No DISP
P+43RE100

Masonry

210
206
206
12

14-Nov-13 A
14-Nov-13 A
14-Nov-13 A
14-Nov-13 A

Gypsum partitions

12 02-Feb-14

16-Feb-14

P+43RE280

Gypsum ceiling

24 16-Feb-14

15-Mar-14

P+43RE160

Fitout Asian restaurant

96 16-Mar-14

08-Jul-14

Remaining Work
Critical Remaining Work
Milestone

Page 130 of 180

Data date: 16-Nov-13

19-Jul-14
12-Jul-14
12-Jul-14
25-Nov-13

P+43RE270

Summary Bar

Revised Programme Rev. D

15-Jul-14
15-Jul-14
15-Jul-14
23-Nov-13

P+43RE290

General
No DISP
T+43MR120

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
08-Jan-14
08-Jan-14

32 01-Dec-13
32 01-Dec-13
0 01-Dec-13

MEP Risers
No DISP
T+43Kl10

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

P+43RE170
General
No DISP
P+43RE120

Fitout Moroccan bar

Plumbing & FP distr, tests

Duration Start

86 30-Mar-14
174 21-Dec-13
174 21-Dec-13
24 21-Dec-13

19-Jul-14
19-Jul-14
18-Jan-14

Electrical distribution LV&LC

24 05-Jan-14

01-Feb-14

P+43RE130

HVAC Duct, pipes distr, FCU & tests

24 19-Jan-14

15-Feb-14

P+43RE190

Pb & FP equip (sprinkler heads...)

4 13-Jul-14

19-Jul-14

P+43RE200

HVAC Grilles & diffusers...

4 13-Jul-14

19-Jul-14

P+43RE210

Electr equip, lighting fixt....

4 13-Jul-14

19-Jul-14

201 26-Nov-13

31-Jul-14

201
201
201
6

26-Nov-13
26-Nov-13
26-Nov-13
26-Nov-13

31-Jul-14
31-Jul-14
31-Jul-14
03-Dec-13

General
Finishes
No DISP
T+44GE100

Masonry

T+44GE270

Screed

6 04-Dec-13

10-Dec-13

T+44GE280

Gypsum walls

12 06-Feb-14

20-Feb-14

T+44GE290

Gypsum ceiling

18 20-Feb-14

12-Mar-14

T+44GE310

Prayer room

42 13-Mar-14

30-Apr-14

T+44GE300

Floor finishes

24 27-Apr-14

24-May-14

T+44GE320

Wall finishes

30 14-May-14

17-Jun-14

T+44GE200

Millwork incl doors

24 11-Jun-14

13-Jul-14

T+44GE210

Painting

6 22-Jul-14

31-Jul-14

183 11-Dec-13
183 11-Dec-13
24 11-Dec-13

20-Jul-14
20-Jul-14
08-Jan-14

General
No DISP
T+44GE120

Plumbing & FP distr, tests

T+44GE130

HVAC Duct, pipes distr, FCU & tests

24 02-Jan-14

29-Jan-14

T+44GE140

Electrical distribution LV&LC

24 23-Jan-14

19-Feb-14

T+44GE170

Pb&FF equip (sprinkler heads...)

4 15-Jul-14

20-Jul-14

T+44GE180

HVAC Grilles & diffusers...

4 15-Jul-14

20-Jul-14

T+44GE190

Electr plates, lighting fixt

4 15-Jul-14

20-Jul-14

Roof
General
No DISP
T+44SW100

BMU concrete upstands & electricity distribution

72
72
72
6

22-Dec-13
22-Dec-13
22-Dec-13
22-Dec-13

17-Mar-14
17-Mar-14
17-Mar-14
29-Dec-13

T+44SW110

Screed with slope

6 29-Dec-13

06-Jan-14

T+44SW150

BMU rails on concrete upstands

9 06-Jan-14

16-Jan-14

T+44SW160

BMU installation

9 16-Jan-14

27-Jan-14

T+44SW120

Waterproofing

6 27-Jan-14

03-Feb-14

T+44SW130

Insulation

6 03-Feb-14

10-Feb-14

T+44SW140

Pavers & gravel protection

6 10-Feb-14

17-Feb-14

T+44SW190

Fall arrest system

6 17-Feb-14

24-Feb-14

T+44SW170

Glass panel windscreen

12 24-Feb-14

10-Mar-14

T+44SW180

Stairs & platform

6 10-Mar-14

17-Mar-14

Mechanical Plantroom
Finishes
No DISP
T+44MP100
Masonry

109
109
109
9

26-Nov-13
26-Nov-13
26-Nov-13
26-Nov-13

03-Apr-14
03-Apr-14
03-Apr-14
07-Dec-13

T+44MP110

Concrete Plinths

4 12-Dec-13

16-Dec-13

T+44MP140

Painting on walls first coat

6 17-Dec-13

23-Dec-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 131 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-Jul-14

P+43RE140

+44 @ +184.30

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

T+44MP200

Final Painting

T+44MP120

Metal frames & doors

03-Apr-14

AHU, pumps, Chillers installation

15 24-Dec-13

11-Jan-14

T+44MP170

Pipes & duct insulation

30 08-Jan-14

11-Feb-14

T+44MP180

Electrical distribution & tests

18 22-Jan-14

11-Feb-14

T+44MP190

Electrical boards

12 12-Feb-14

25-Feb-14

161
161
161
12

25-Feb-14
25-Feb-14
21-Jan-14

08-Dec-13
08-Dec-13
08-Dec-13
08-Dec-13

14-Jun-14
14-Jun-14
14-Jun-14
21-Dec-13

T+44MR120

Plumbing & FP distr, tests

12 22-Dec-13

05-Jan-14

T+44RE290

Gypsum Partitions

18 22-Dec-13

12-Jan-14

T+44MR130

HVAC Duct, pipes distr, FCU & tests

12 06-Jan-14

19-Jan-14

T+44MR140

Electrical distribution LV&LC

12 20-Jan-14

02-Feb-14

T+44RE300

Gypsum Ceilings

24 03-Feb-14

02-Mar-14

T+44RE330

Marble to floor and Corridor

12 13-Apr-14*

26-Apr-14

T+44RE320

Millwork

24 27-Apr-14

24-May-14

T+44MR190

Pb & FP equip (sprinkler heads...)

6 25-May-14

31-May-14

T+44MR200

HVAC Grilles & diffusers...

6 25-May-14

31-May-14

T+44MR210

Electr equip, lighting fixt....

6 25-May-14

31-May-14

T+44RE360

Final Paint

T+44RE340

Carpet

General
Finishes
No DISP
T+45GE100

Masonry

T+45GE200

Install metal frames & doors

T+45GE210

Final Painting

6 25-May-14

31-May-14

12 01-Jun-14

14-Jun-14

138 16-Nov-13

27-Apr-14

138
97
97
9

16-Nov-13
22-Dec-13
22-Dec-13
22-Dec-13

27-Apr-14
14-Apr-14
14-Apr-14
31-Dec-13

6 05-Apr-14

10-Apr-14

6 08-Apr-14

14-Apr-14
02-Feb-14
02-Feb-14

Access from Structure

27 02-Jan-14
27 02-Jan-14
0 02-Jan-14

T+45GE300

Drainage Riser

10 04-Jan-14

14-Jan-14

T+45GE310

Rain Water Riser

8 07-Jan-14

15-Jan-14

T+45GE320

CD Pipe Riser

8 07-Jan-14

15-Jan-14

T+45GE330

Water Supply Risers

12 09-Jan-14

22-Jan-14

T+45GE340

Electrical Risers

12 12-Jan-14

25-Jan-14

T+45GE360

Ducting Risers

14 13-Jan-14

28-Jan-14

T+45GE370

FP Pipe Riser

10 13-Jan-14

23-Jan-14

T+45GE380

CHW Pipe Supply/Return riser

14 18-Jan-14

02-Feb-14

119 16-Nov-13
119 16-Nov-13
21 16-Nov-13

05-Apr-14
05-Apr-14
10-Dec-13

MEP Risers
No DISP
T+45GE290

MEP 1st & 2nd Fix


No DISP
T+45GE680
Cable Tray & Trunking
T+45GE450

MCC Panels and Switches

21 02-Jan-14

26-Jan-14

T+45GE420

Drainage Piping

10 15-Jan-14

26-Jan-14

T+45GE460

FP Piping

14 25-Jan-14

09-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

6 29-Mar-14*

HVAC distribution, quip & tests

+45 @ +188.10

Revised Programme Rev. D

6 26-Feb-14

T+44MP160

Meeting Rooms & Board Room


General
No DISP
T+44RE260
Masonry

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
04-Mar-14

Duration Start

54 24-Dec-13
54 24-Dec-13
24 24-Dec-13

General
No DISP
T+44MP150

Four Seasons Hotel Bahrain

Page 132 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

T+45GE480

Cable Tray & Trunking

21 26-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
18-Feb-14

T+45GE520

Electrical Containment

18 26-Jan-14

15-Feb-14

T+45GE400

AHU Installation

12 27-Jan-14

09-Feb-14

T+45GE470

Drainage Pipe Testing

6 27-Jan-14

02-Feb-14

T+45GE550

FP Pipe pressure Testing

6 10-Feb-14

16-Feb-14

T+45GE500

Ducting connection to AHU

21 10-Feb-14

05-Mar-14

T+45GE440

FCU Installation

8 10-Feb-14

18-Feb-14

T+45GE530

CHW Pipe and valve connections to AHU

21 10-Feb-14

05-Mar-14

T+45GE570

Cable & Wire Pulling

21 19-Feb-14

15-Mar-14

T+45GE490

Condensate Drain Pipe connection

8 19-Feb-14

27-Feb-14

T+45GE510

Duct connection to FCU

18 19-Feb-14

11-Mar-14

T+45GE540

CHW Pipe and valve connections to FCU

18 19-Feb-14

11-Mar-14

T+45GE590

CHW Pipe insulation

18 10-Mar-14

30-Mar-14

T+45GE600

CHW Pipe Pressure Testing

6 12-Mar-14

18-Mar-14

T+45GE560

Installation of Dampers and Plenums

12 12-Mar-14

25-Mar-14

T+45GE610

Cable Termination

18 16-Mar-14

05-Apr-14

Sprinkler Installation

14 12-Apr-14
14 12-Apr-14
8 12-Apr-14

27-Apr-14
27-Apr-14
20-Apr-14

Activity ID

Activity Name

MEP Final Fix


No DISP
T+45GE620

Duration Start

T+45GE630

Installation of Floor Drains

4 12-Apr-14

15-Apr-14

T+45GE640

Grilles & Louvres

14 12-Apr-14

27-Apr-14

T+45GE650

Light fittings

10 15-Apr-14

26-Apr-14

T+45GE660

FA & SD Devices

+46 @ +191.90
General
Finishes
No DISP
T+46GE100

Masonry

8 19-Apr-14

27-Apr-14

97 02-Jan-14

24-Apr-14

94
94
94
9

02-Jan-14
02-Jan-14
02-Jan-14
02-Jan-14

21-Apr-14
21-Apr-14
21-Apr-14
12-Jan-14

T+46GE200

Install metal frames & doors

6 12-Apr-14

17-Apr-14

T+46GE210

Painting

6 15-Apr-14

21-Apr-14
12-Feb-14
12-Feb-14

Access from Structure

27 13-Jan-14
27 13-Jan-14
0 13-Jan-14

T+46GE300

Drainage Riser

10 14-Jan-14

25-Jan-14

T+46GE310

Rain Water Riser

8 18-Jan-14

26-Jan-14

T+46GE320

CD Pipe Riser

8 18-Jan-14

26-Jan-14

T+46GE330

Water Supply Risers

12 20-Jan-14

02-Feb-14

T+46GE340

Electrical Risers

12 22-Jan-14

04-Feb-14

T+46GE360

Ducting Risers

14 23-Jan-14

08-Feb-14

T+46GE370

FP Pipe Riser

10 23-Jan-14

03-Feb-14

T+46GE380

CHW Pipe Supply/Return riser

14 28-Jan-14

12-Feb-14

88
88
88
9

13-Jan-14
13-Jan-14
13-Jan-14
13-Jan-14

24-Apr-14
24-Apr-14
24-Apr-14
22-Jan-14

MEP Risers
No DISP
T+46GE290

Electrical Plantroom
Finishes
No DISP
T+46EP100
Masonry
T+46EP120

Concrete support for equipments

T+46EP190

Painting on walls & floor

T+46EP110

Metal door with frames

MEP 1st & 2nd Fix

6 14-Jan-14

20-Jan-14

12 21-Jan-14

03-Feb-14

6 19-Apr-14

24-Apr-14

69 21-Jan-14

10-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 133 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

Transformer Installation

69 21-Jan-14
12 21-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-Apr-14
03-Feb-14

T+46GE680

Drainage Piping

10 26-Jan-14

05-Feb-14

T+46GE690

FP Piping

14 04-Feb-14

19-Feb-14

T+46GE700

Installation of HV Switchgears

18 04-Feb-14

24-Feb-14

T+46GE710

FCU Installation

14 04-Feb-14

19-Feb-14

T+46GE720

Cable Ladders, Tray & Trunking

21 05-Feb-14

01-Mar-14

T+46GE670

Electrical Containment

18 05-Feb-14

25-Feb-14

T+46GE730

Drainage Pipe Testing

6 06-Feb-14

12-Feb-14

T+46GE740

Duct connection to FCU

18 20-Feb-14

12-Mar-14

T+46GE750

CHW Pipe and valve connections to FCU

18 20-Feb-14

12-Mar-14

T+46GE760

Condensate Drain Pipe connection

8 20-Feb-14

01-Mar-14

T+46GE770

FP Pipe pressure Testing

6 20-Feb-14

26-Feb-14

T+46GE780

Installation of LV Panels

10 25-Feb-14

08-Mar-14

T+46GE790

HV cable pulling & connections

21 02-Mar-14

25-Mar-14

T+46GE800

Cable & Wire Pulling

18 02-Mar-14

22-Mar-14

T+46GE850

Fans Installation & connection

16 03-Mar-14

20-Mar-14

T+46GE840

LV Cable pulling and connections

14 09-Mar-14

24-Mar-14

T+46GE810

Installation of Dampers and Plenums

12 13-Mar-14

26-Mar-14

T+46GE820

CHW Pipe Pressure Testing

8 13-Mar-14

22-Mar-14

T+46GE830

CHW Pipe insulation

12 20-Mar-14

02-Apr-14

T+46GE860

Cable Termination

18 22-Mar-14

10-Apr-14

Sprinkler Installation

47 27-Feb-14
47 27-Feb-14
8 27-Feb-14

22-Apr-14
22-Apr-14
08-Mar-14

Activity ID

Activity Name

No DISP
T+46GE660

MEP Final Fix


No DISP
T+46GE610
T+46GE620

Installation of floor Drains

T+46GE630

Grilles & Louvres

T+46GE640

Duration Start

4 02-Mar-14

05-Mar-14

14 13-Mar-14

29-Mar-14

Light fittings

6 29-Mar-14

03-Apr-14

T+46GE650

FA & SD Devices

4 12-Apr-14

15-Apr-14

T+46GE870

Clean & Snag

6 16-Apr-14

22-Apr-14

+47 @ +195.70
General
Finishes
No DISP
T+47GE100

Masonry

108 13-Jan-14

18-May-14

108
97
97
9

13-Jan-14
13-Jan-14
13-Jan-14
13-Jan-14

18-May-14
05-May-14
05-May-14
22-Jan-14

T+47GE220

Install metal frames & doors

6 26-Apr-14

01-May-14

T+47GE230

Final Painting

6 29-Apr-14

05-May-14
23-Feb-14
23-Feb-14

Access from Structure

27 23-Jan-14
27 23-Jan-14
0 23-Jan-14

T+47GE320

Drainage Riser

10 25-Jan-14

04-Feb-14

T+47GE330

Rain Water Riser

8 28-Jan-14

05-Feb-14

T+47GE340

CD Pipe Riser

8 28-Jan-14

05-Feb-14

T+47GE350

Water Supply Risers

12 30-Jan-14

12-Feb-14

T+47GE360

Electrical Risers

12 02-Feb-14

15-Feb-14

T+47GE370

Ducting Risers

14 03-Feb-14

18-Feb-14

T+47GE380

FP Pipe Riser

10 03-Feb-14

13-Feb-14

T+47GE390

CHW Pipe Supply/Return riser

14 08-Feb-14

23-Feb-14

62 23-Jan-14

05-Apr-14

MEP Risers
No DISP
T+47GE310

MEP 1st & 2nd Fix


Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 134 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

FCU Installation

62 23-Jan-14
4 23-Jan-14

T+47GE420

Drainage Piping

5 05-Feb-14

10-Feb-14

T+47GE490

Condensate Drain Pipe connection

3 06-Feb-14

09-Feb-14

T+47GE470

Drainage Pipe Testing

6 11-Feb-14

17-Feb-14

T+47GE460

FP Piping

6 15-Feb-14

20-Feb-14

T+47GE480

Cable Tray & Trunking

12 16-Feb-14

01-Mar-14

T+47GE520

Electrical Containment

12 16-Feb-14

01-Mar-14

T+47GE510

Duct connection to FCU

6 19-Feb-14

25-Feb-14

T+47GE550

FP Pipe pressure Testing

6 22-Feb-14

27-Feb-14

T+47GE540

CHW Pipe and valve connections to FCU

12 24-Feb-14

09-Mar-14

T+47GE560

Installation of Dampers and Plenums

12 26-Feb-14

11-Mar-14

T+47GE570

Cable & Wire Pulling

12 02-Mar-14

15-Mar-14

T+47GE600

CHW Pipe Pressure Testing

6 10-Mar-14

16-Mar-14

T+47GE590

CHW Pipe insulation

12 15-Mar-14

27-Mar-14

T+47GE610

Cable Termination

18 16-Mar-14

05-Apr-14

Sprinkler Installation

14 03-May-14
14 03-May-14
8 03-May-14

18-May-14
18-May-14
11-May-14

4 03-May-14

06-May-14

T+47GE630

Installation of floor Drains

T+47GE640

Grilles & Louvres

14 03-May-14

18-May-14

T+47GE650

Light fittings

10 06-May-14

17-May-14

T+47GE660

FA & SD Devices

8 10-May-14

18-May-14

61 16-Nov-13

27-Jan-14

27
27
27
4

27-Jan-14
27-Jan-14
27-Jan-14
30-Dec-13

+48 @ +199.50 - Roof


General
MEP 1st & 2nd Fix
No DISP
T+47GE700
Install Chiller
T+47GE710

26-Dec-13
26-Dec-13
26-Dec-13
26-Dec-13*

MEP 1st & 2nd fix

23 31-Dec-13

27-Jan-14

BMU concrete upstands & electricity distribution

34
34
34
6

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

25-Dec-13
25-Dec-13
25-Dec-13
21-Nov-13

T+48SW110

Screed with slope

12 20-Nov-13

04-Dec-13

T+48SW150

BMU rails on concrete upstands

9 23-Nov-13

03-Dec-13

T+48SW160

BMU installation

6 26-Nov-13

03-Dec-13

T+48SW120

Waterproofing

12 05-Dec-13

18-Dec-13

T+48SW130

Insulation

6 12-Dec-13

18-Dec-13

T+48SW140

Pavers & gravel protection

6 19-Dec-13

25-Dec-13

325 09-Jun-13 A

05-Aug-14

293 09-Jun-13 A

17-Jun-14

Roof
General
No DISP
T+48SW100

EAST PODIUM
Lower level

Facade brackets & framing - East El.

60
60
60
18

PL1FA200

PCC Brackets - East El.

18 31-Dec-13

21-Jan-14

PL1FA110

Precast Concrete Cladding - East El.

30 22-Jan-14

25-Feb-14

PL1FA140

Stone Cladding - East

24 12-Feb-14

11-Mar-14

PL1FA190

Install windows - South elevation ( 2 No. )

2 17-Feb-14

18-Feb-14

Facades
Facades
No DISP
PL1FA100

31-Dec-13
31-Dec-13
31-Dec-13
31-Dec-13*

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 135 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
05-Apr-14
27-Jan-14

No DISP
T+47GE440

MEP Final Fix


No DISP
T+47GE620

Four Seasons Hotel Bahrain

11-Mar-14
11-Mar-14
11-Mar-14
21-Jan-14

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

General
Finishes
No DISP
PL1GE940

Masonry - G

Duration Start

293
293
293
10

09-Jun-13 A
09-Jun-13 A
09-Jun-13 A
20-Jun-13 A

Elect embeds in masonry

30 09-Jun-13 A

21-Dec-13

PL1GE180

Wall finishes

40 20-Nov-13

07-Jan-14

PL1GE160

Gypsum & cement plaster

40 30-Oct-13 A

19-Jan-14

PL1GE1340

Ceramic wall tiles

40 03-Oct-13 A

23-Feb-14

PL1GE170

Internal & external windows

36 12-Feb-14

25-Mar-14

PL1GE200

Gypsum False ceiling

36 26-Mar-14

06-May-14

PL1GE190

Ceramic tiles on floor

36 16-Apr-14

27-May-14

PL1GE110

Install Metal doorsets

36 23-Apr-14

03-Jun-14

PL1GE260

Painting

36 07-May-14

17-Jun-14

212 20-Jun-13 A
212 20-Jun-13 A
21 20-Jun-13 A

15-Jun-14
15-Jun-14
23-Nov-13

Cable Ladder, Tray and Trunking

PL1GE580

Electrical Conduiting

18 03-Oct-13 A

07-Dec-13

PL1GE590

Duct Installation

21 03-Oct-13 A

08-Dec-13

PL1GE610

Cabling and Wiring

21 05-Oct-13 A

18-Dec-13

PL1GE600

FP Piping

14 09-Dec-13

24-Dec-13

PL1GE650

Cable Termination

14 19-Dec-13

05-Jan-14

PL1GE620

FP Dropper Piping

10 08-Apr-14

19-Apr-14

PL1GE630

Flexible ducts and Plenums

16 13-Apr-14

30-Apr-14

PL1GE640

FP Pipe Pressure Testing

5 20-Apr-14

24-Apr-14

PL1GE660

Sprinkler installation

10 07-May-14

18-May-14

PL1GE670

Grilles and Diffusers

12 19-May-14

01-Jun-14

PL1GE680

Light Fittings

10 02-Jun-14

12-Jun-14

PL1GE690

ELV Devices

MEP 1st & 2nd Fix


No DISP
PL1GE710
Drainage Piping

7 08-Jun-14

15-Jun-14

169 24-Nov-13
169 24-Nov-13
18 24-Nov-13

10-Jun-14
10-Jun-14
15-Dec-13

12 16-Dec-13

29-Dec-13

5 16-Dec-13

21-Dec-13

PL1GE720

Cable Tray and Trunking

PL1GE730

Drainage Pipe Testing

PL1GE740

Electrical Conduiting

14 25-Dec-13

11-Jan-14

PL1GE750

Duct Installation

21 30-Dec-13

23-Jan-14

PL1GE810

Cabling and Wiring

18 30-Dec-13

20-Jan-14

PL1GE760

FCU Installation

8 20-Jan-14

28-Jan-14

PL1GE850

Cable Termination

14 21-Jan-14

05-Feb-14

PL1GE780

FP Piping

14 25-Jan-14

09-Feb-14

PL1GE770

CHW Piping & valve connection to FCU

10 29-Jan-14

09-Feb-14

PL1GE790

CHW Pipe pressure Testing

4 10-Feb-14

13-Feb-14

PL1GE800

CHW Pipe Insulation

6 13-Feb-14

19-Feb-14

PL1GE820

FP Dropper Piping

12 08-Apr-14

21-Apr-14

PL1GE830

Flexible ducts and Plenums

16 13-Apr-14

30-Apr-14

PL1GE840

FP Pipe Pressure Testing

7 22-Apr-14

29-Apr-14

PL1GE860

Sanitary Fittings and Accs.

12 28-May-14

10-Jun-14

PL1GE870

Floor Drains

5 28-May-14

02-Jun-14

18 25-May-14
18 25-May-14

14-Jun-14
14-Jun-14

MEP Finishes
No DISP
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 136 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
17-Jun-14
17-Jun-14
17-Jun-14
21-Nov-13

PL1GE950

Corridor
No DISP
PL1GE570

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PL1GE880

Sprinkler installation

10 25-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
04-Jun-14

PL1GE900

Grilles and Diffusers

12 25-May-14

07-Jun-14

PL1GE890

Wiring Accessories

14 26-May-14

10-Jun-14

PL1GE910

Light Fittings

10 31-May-14

10-Jun-14

PL1GE920

ELV Devices

8 05-Jun-14

14-Jun-14

220 05-Oct-13 A

24-Jun-14

128
89
89
21

05-Oct-13 A
05-Oct-13 A
05-Oct-13 A
05-Oct-13 A

20-Mar-14
03-Feb-14
03-Feb-14
07-Dec-13

Activity ID

Activity Name

Lower Level - Area G


General
Corridor
No DISP
PL1GE980

Cable Ladder, Tray and Trunking

Duration Start

PL1GE990

Electrical Conduiting

18 10-Oct-13 A

28-Nov-13

PL1GE1020

FP Dropper Piping

10 16-Nov-13

26-Nov-13

PL1GE1010

FP Pipe Pressure Testing

5 27-Nov-13

03-Dec-13

PL1GE1030

Sprinkler installation

10 04-Dec-13

15-Dec-13

PL1GE970

Duct Installation

21 13-Oct-13 A

31-Dec-13

PL1GE1050

Cabling and Wiring

21 08-Dec-13

31-Dec-13

PL1GE1040

Flexible ducts and Plenums

16 02-Jan-14

20-Jan-14

PL1GE1090

Cable Termination

14 02-Jan-14

18-Jan-14

PL1GE1060

Light Fittings

10 19-Jan-14

29-Jan-14

PL1GE1070

Grilles and Diffusers

12 21-Jan-14

03-Feb-14

PL1GE1080

ELV Devices

MEP 1st & 2nd Fix


No DISP
PL1GE1130
Drainage Piping

7 25-Jan-14

01-Feb-14

84 16-Nov-13
84 16-Nov-13
18 16-Nov-13

23-Feb-14
23-Feb-14
07-Dec-13

PL1GE1140

Drainage Pipe Testing

5 08-Dec-13

12-Dec-13

PL1GE1230

Cable Tray and Trunking

12 08-Dec-13

21-Dec-13

PL1GE1120

Sanitary Fittings and Accs.

12 14-Dec-13

26-Dec-13

PL1GE1160

Floor Drains

5 14-Dec-13

18-Dec-13

PL1GE1240

Electrical Conduiting

14 17-Dec-13

02-Jan-14

PL1GE1110

Cabling and Wiring

18 22-Dec-13

12-Jan-14

PL1GE1220

Duct Installation

21 22-Dec-13

15-Jan-14

PL1GE1200

FCU Installation

8 31-Dec-13

11-Jan-14

PL1GE1170

CHW Piping & valve connection to FCU

10 11-Jan-14

21-Jan-14

PL1GE1150

Cable Termination

14 13-Jan-14

28-Jan-14

PL1GE1100

Flexible ducts and Plenums

16 16-Jan-14

03-Feb-14

PL1GE1250

FP Piping

14 16-Jan-14

01-Feb-14

PL1GE1180

CHW Pipe pressure Testing

4 22-Jan-14

26-Jan-14

PL1GE1190

CHW Pipe Insulation

6 26-Jan-14

01-Feb-14

PL1GE1270

FP Dropper Piping

12 02-Feb-14

15-Feb-14

PL1GE1260

FP Pipe Pressure Testing

7 16-Feb-14

23-Feb-14

Light Fittings

44 29-Jan-14
44 29-Jan-14
10 29-Jan-14

20-Mar-14
20-Mar-14
09-Feb-14

PL1GE1320

Wiring Accessories

14 29-Jan-14

13-Feb-14

PL1GE1300

Grilles and Diffusers

12 04-Feb-14

17-Feb-14

PL1GE1310

ELV Devices

8 04-Feb-14

12-Feb-14

PL1GE1280

Sprinkler installation

10 24-Feb-14

06-Mar-14

PL1GE1330

Clean & Snag

12 08-Mar-14

20-Mar-14

170 09-Oct-13 A

08-May-14

MEP Final Fix


No DISP
PL1GE1290

Staff Dining / Kitchen


Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 137 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Finishes
No DISP
PL1LA330

Gypsum & cement plaster

PL1LA360

Wall ceramic tiles

PL1LA420
PL1LA400
PL1LA390

Duration Start

148 16-Nov-13
148 16-Nov-13
4 16-Nov-13*

30-Nov-13

Acoustic ceiling first fix & service tiles

12 28-Jan-14

10-Feb-14

Ceramic tiles to Floor

15 11-Feb-14

27-Feb-14

Install doors

6 01-Mar-14

06-Mar-14

PL1LA370

Internal windows

6 08-Mar-14

13-Mar-14

PL1LA380

Kitchen equipment

15 15-Mar-14

31-Mar-14

PL1LA410

Final Painting

12 01-Apr-14

14-Apr-14

PL1LA430

Acoustic ceiling tiles

6 15-Apr-14

21-Apr-14

PL1LA600

Wall covering

9 22-Apr-14

01-May-14

PL1LA610

Vinyl Floor

6 03-May-14

08-May-14

PL1GE1390

Complete

08-May-14

114 09-Oct-13 A
114 09-Oct-13 A
18 09-Oct-13 A

04-Mar-14
04-Mar-14
28-Nov-13

12 30-Nov-13

14-Dec-13

5 30-Nov-13

05-Dec-13

PLEPSK130

Cable Tray and Trunking

PLEPSK140

Drainage Pipe Testing

PLEPSK150

Electrical Conduiting

14 10-Dec-13

25-Dec-13

PLEPSK160

Duct Installation

21 15-Dec-13

08-Jan-14

PLEPSK220

Cabling and Wiring

18 15-Dec-13

05-Jan-14

PLEPSK280

Installation of Kitchen Ecology Unit

8 18-Dec-13

26-Dec-13

PLEPSK170

FCU Installation

8 24-Dec-13

04-Jan-14

PLEPSK180

CHW Piping & valve connection to FCU

10 04-Jan-14

14-Jan-14

PLEPSK260

Cable Termination

14 06-Jan-14

21-Jan-14

PLEPSK240

Flexible ducts

16 09-Jan-14

27-Jan-14

PLEPSK200

CHW Pipe pressure Testing

4 15-Jan-14

19-Jan-14

PLEPSK210

CHW Pipe Insulation

PLEPSK230

FP Dropper Piping

PLEPSK250

FP Pipe Pressure Testing

MEP Finishes
No DISP
PLEPSK320

Light Fittings

6 19-Jan-14

25-Jan-14

12 11-Feb-14

24-Feb-14

7 25-Feb-14

04-Mar-14

42 22-Jan-14
42 22-Jan-14
6 22-Jan-14

11-Mar-14
11-Mar-14
28-Jan-14

PLEPSK300

Wiring Accessories

6 22-Jan-14

28-Jan-14

PLEPSK310

Grilles and Diffusers

6 28-Jan-14

03-Feb-14

PLEPSK330

ELV Devices

8 28-Jan-14

05-Feb-14

PLEPSK290

Floor Drains

5 11-Feb-14

16-Feb-14

PLEPSK270

Sprinkler installation

6 05-Mar-14

11-Mar-14

Staff Restrooms & Locker rooms


Finishes
No DISP
PL1LA440
Gypsum & cement plaster

202
163
163
18

14-Oct-13 A
01-Dec-13
01-Dec-13
01-Dec-13*

Wall - ceramic tiles

18 23-Dec-13

13-Jan-14

PL1LA550

Cement board walls

12 14-Jan-14

27-Jan-14

PL1LA570

Gypsum ceiling 1st fix

9 28-Jan-14

06-Feb-14

PL1LA580

Board Gypsum ceiling

9 02-Mar-14

11-Mar-14

PL1LA460

Waterproofing to floor

9 12-Mar-14

22-Mar-14

PL1LA480

Ceramic floor tiles & skirting

18 23-Mar-14

12-Apr-14

Remaining Work
Critical Remaining Work
Milestone

Page 138 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

10-Jun-14
10-Jun-14
10-Jun-14
22-Dec-13

PL1LA450

Summary Bar

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
08-May-14
08-May-14
19-Nov-13

9 20-Nov-13

MEP 1st & 2nd Fix


No DISP
PLEPSK120
Drainage Piping

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PL1LA520

Vanity units

9 13-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
22-Apr-14

PL1LA530

Shower/Toilet cubicles & doors

9 23-Apr-14

03-May-14

PL1LA500

Install doors

6 04-May-14

10-May-14

PL1LA590

Vinyl floor ing & skirting to locker rooms

6 11-May-14

17-May-14

PL1LA540

Final Painting

12 18-May-14

31-May-14

PL1LA560

Install lockers

9 01-Jun-14

10-Jun-14

PL1GE1420

Complete

10-Jun-14

Activity ID

Activity Name

MEP 1st & 2nd Fix


No DISP
PLEPST120
Drainage Piping

Duration Start

115 14-Oct-13 A
115 14-Oct-13 A
12 14-Oct-13 A

01-Mar-14
01-Mar-14
26-Nov-13

12 27-Nov-13

11-Dec-13

5 27-Nov-13

03-Dec-13

14 08-Dec-13

23-Dec-13

PLEPST130

Cable Tray and Trunking

PLEPST140

Drainage Pipe Testing

PLEPST150

Electrical Conduiting

PLEPST170

FCU Installation

8 11-Dec-13

21-Dec-13

PLEPST160

Duct Installation

12 12-Dec-13

25-Dec-13

PLEPST220

Cabling and Wiring

12 12-Dec-13

25-Dec-13

PLEPST180

CHW Piping & valve connection to FCU

10 21-Dec-13

31-Dec-13

PLEPST240

Flexible ducts and Plenums

12 26-Dec-13

09-Jan-14

PLEPST260

Cable Termination

14 26-Dec-13

12-Jan-14

PLEPST200

CHW Pipe pressure Testing

4 02-Jan-14

06-Jan-14

PLEPST210

CHW Pipe Insulation

6 06-Jan-14

12-Jan-14

PLEPST230

FP Dropper Piping

12 08-Feb-14

20-Feb-14

PLEPST250

FP Pipe Pressure Testing

7 22-Feb-14

01-Mar-14
01-Jun-14
01-Jun-14
27-Mar-14

Floor Drains

61 23-Mar-14
61 23-Mar-14
5 23-Mar-14

PLEPST280

Sanitary Fittings and Accs.

12 23-Apr-14

06-May-14

PLEPST300

Wiring Accessories

14 26-Apr-14

12-May-14

PLEPST270

Sprinkler installation

10 04-May-14

14-May-14

PLEPST310

Grilles and Diffusers

12 04-May-14

17-May-14

PLEPST320

Light Fittings

10 18-May-14

28-May-14

PLEPST330

ELV Devices

8 24-May-14

01-Jun-14

MEP Finishes
No DISP
PLEPST290

Truck Dock
Finishes
No DISP
PL1GE1370

Plaster to walls - Driver restroom

80
80
80
5

28-Dec-13
28-Dec-13
28-Dec-13
28-Dec-13*

31-Mar-14
31-Mar-14
31-Mar-14
02-Jan-14

PL1GE1500

Ceramic tiles to walls and floor - Driver restroom

6 04-Jan-14

09-Jan-14

PL1GE1510

Sanitaryware - Driver restroom

6 11-Jan-14

16-Jan-14

PL1GE1520

Install loading dock

4 28-Jan-14*

01-Feb-14

PL1GE1550

Handrail to stairs

6 02-Feb-14

08-Feb-14

PL1GE1560

Install doors

6 09-Feb-14

15-Feb-14

PL1GE1540

Install roller shutter door

6 15-Mar-14*

20-Mar-14

PL1GE1570

Final paint

5 22-Mar-14

26-Mar-14

PL1GE1590

MEP final fix

5 22-Mar-14

26-Mar-14

PL1GE1580

RMX01 to floor

4 27-Mar-14

31-Mar-14

PL1GE1530

Complete

31-Mar-14

Kitchen
Finishes
No DISP

205 06-Oct-13 A
173 16-Nov-13
173 16-Nov-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 139 of 180

07-Jun-14
07-Jun-14
07-Jun-14
Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PL1KI120

Gypsum & cement plaster

12 16-Nov-13*

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
28-Nov-13

PL1KI220

Wall ceramic tiles

36 30-Nov-13

12-Jan-14

PL1KI180

Acoustic false ceiling first fix

18 29-Dec-13

19-Jan-14

PL1KI160

Internal windows

PL1KI190

Waterproofing to floor

PL1KI370

Water test

PL1KI210

Floor ceramic tiles

PL1KI290
PL1KI360
PL1KI300

Activity ID

Activity Name

Duration Start

6 13-Jan-14

19-Jan-14

12 20-Jan-14

02-Feb-14

9 03-Feb-14

12-Feb-14

26 13-Feb-14

15-Mar-14

Install doors

9 16-Mar-14

25-Mar-14

Acoustic false ceiling tiles

9 16-Mar-14

25-Mar-14

Kitchen equipment

36 30-Mar-14

10-May-14

PL1KI310

Millwork

12 11-May-14

24-May-14

PL1KI320

Painting

MEP 1st & 2nd Fix


No DISP
PL1KI130
Plumbing & FP distr, tests

12 25-May-14

07-Jun-14

122 06-Oct-13 A
122 06-Oct-13 A
48 06-Oct-13 A

02-Mar-14
02-Mar-14
09-Dec-13

PL1KI140

HVAC Duct, pipes distr, FCU & tests

48 08-Oct-13 A

29-Dec-13

PL1KI150

Electrical distribution LV

36 13-Oct-13 A

19-Dec-13

PL1KI170

Hood installation

9 29-Dec-13

08-Jan-14

PL1KI230

Coldroom installation

15 13-Feb-14

02-Mar-14
29-Mar-14
29-Mar-14
29-Mar-14

Pb&FF equip (sprinkler heads...)

12 16-Mar-14
12 16-Mar-14
12 16-Mar-14

PL1KI260

Plumbing & FP access

12 16-Mar-14

29-Mar-14

PL1KI270

HVAC Grilles & diffusers...

12 16-Mar-14

29-Mar-14

PL1KI280

Electr equip, lighting fixt....

12 16-Mar-14

29-Mar-14

MEP Finishes
No DISP
PL1KI250

Laundry
Finishes
No DISP
PL1LA220

Paint to walls

PL1LA210

Vinyl Floor & skirting

PL1LA290

Install doors

PL1LA310

Laundry equipment

PL1LA160

Internal windows

PL1LA320

Painting

MEP 1st & 2nd Fix


No DISP
PL1LA120
Plumbing & FP distr, tests

143
87
87
12

07-Oct-13 A
15-Dec-13
15-Dec-13
15-Dec-13

26-Mar-14
26-Mar-14
26-Mar-14
28-Dec-13

9 29-Dec-13

08-Jan-14

6 09-Jan-14

15-Jan-14

48 16-Jan-14

12-Mar-14

6 13-Mar-14

19-Mar-14

12 13-Mar-14

26-Mar-14

48 07-Oct-13 A
48 07-Oct-13 A
48 07-Oct-13 A

14-Dec-13
14-Dec-13
14-Dec-13

PL1LA130

HVAC Duct, pipes distr, FCU & tests

48 31-Oct-13 A

14-Dec-13

PL1LA140

Electrical distribution LV

48 31-Oct-13 A

14-Dec-13

Wall 6 mastclimber removed

47 30-Apr-14
47 30-Apr-14
47 30-Apr-14
0

24-Jun-14
24-Jun-14
24-Jun-14
30-Apr-14

Housekeeping
Finishes
No DISP
PL1LA680
PL1LA690

Complete Ground floor suspended slab

6 01-May-14

07-May-14

PL1LA700

Complete Low level slab

6 08-May-14

14-May-14

PL1LA620

Gypsum Partitions

6 15-May-14

21-May-14

PL1LA710

Gypsum Ceiling

9 22-May-14

01-Jun-14

PL1LA640

Install doors & windows

4 02-Jun-14

05-Jun-14

PL1LA720

MEP final fix

4 07-Jun-14

10-Jun-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 140 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

PL1LA630

Vinyl Floor & skirting

PL1LA670

Painting

Security room & Systems


Finishes
No DISP
PL1GE1610
MEP 1st & 2nd fix

24-Jun-14

30-Nov-13
30-Nov-13
30-Nov-13
30-Nov-13*

25-Feb-14
25-Feb-14
25-Feb-14
10-Dec-13
17-Dec-13

PL1GE1600

Paint walls

5 18-Dec-13

23-Dec-13

PL1GE1630

Acoustic ceiling 1st fix

6 24-Dec-13

30-Dec-13

PL1GE1640

Install windows & doors

5 18-Jan-14*

22-Jan-14

PL1GE1650

Wall covering

6 23-Jan-14

29-Jan-14

PL1GE1700

MEP Final fix

6 30-Jan-14

05-Feb-14

PL1GE1710

Acoustic ceiling tiles

6 06-Feb-14

12-Feb-14

PL1GE1660

Vinyl flooring & skirting

3 13-Feb-14

16-Feb-14

PL1GE1670

Millwork

6 17-Feb-14

23-Feb-14

PL1GE1680

Carpet

2 24-Feb-14

25-Feb-14

PL1GE1400

Complete

25-Feb-14

71
71
71
71

30-Jan-14
30-Jan-14
30-Jan-14
30-Jan-14*

22-Apr-14
22-Apr-14
22-Apr-14
22-Apr-14

66
66
66
9

11-Dec-13
11-Dec-13
11-Dec-13
11-Dec-13*

26-Feb-14
26-Feb-14
26-Feb-14
21-Dec-13

PL1GE1730

Gypsum board to walls

6 22-Dec-13

28-Dec-13

PL1GE1740

Paint walls

5 29-Dec-13

04-Jan-14

PL1GE1750

Acoustic ceiling 1st fix

6 05-Jan-14

11-Jan-14

PL1GE1770

MEP Final fix

6 12-Jan-14

18-Jan-14

PL1GE1760

Install windows & doors

5 18-Feb-14*

23-Feb-14

PL1GE1780

Vinyl flooring & skirting

3 24-Feb-14

26-Feb-14

PL1GE1380

Complete

26-Feb-14

Lower Level - Area H


Heat Exchange & Pump Room
MEP Finishes
No DISP
PL1MP470
Installation of Expansion Tanks

162 06-Oct-13 A

05-May-14

127
127
127
7

14-Apr-14
14-Apr-14
14-Apr-14
23-Nov-13

06-Oct-13 A
06-Oct-13 A
06-Oct-13 A
16-Nov-13

PL1MP650

Installation of Chemical Dosing unit

PL1MP660

Chilled Water Piping (Main runs)

PL1MP740

FCU installation

PL1MP820

Equipment connections

PL1MP750

CHW pipe & valve connection to FCU

PL1MP670

Chilled Water Pipe Pressure Testing

PL1MP680

Chilled Water Pipe insulation

18 06-Feb-14

26-Feb-14

PL1MP690

Cable Trays

10 06-Feb-14

17-Feb-14

PL1MP810

MCC panels and switches

8 09-Feb-14

17-Feb-14

PL1MP700

GI Conduiting

10 18-Feb-14

01-Mar-14

PL1MP710

Cable and Wire pulling

10 02-Mar-14

12-Mar-14

PL1MP730

DDC Panel and wiring

6 08-Mar-14

13-Mar-14

7 24-Nov-13

01-Dec-13

28 06-Oct-13 A

28-Dec-13

2 29-Dec-13

30-Dec-13

24 29-Dec-13

26-Jan-14

5 31-Dec-13

06-Jan-14

12 27-Jan-14

09-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Data date: 16-Nov-13

6 18-Jun-14
74
74
74
9

6 11-Dec-13

Lifts & mach inst + tests SE 7-8

Revised Programme Rev. D

6 11-Jun-14

Gypsum board to walls

Receiving/Storage
Finishes
No DISP
PL1GE1720
MEP 1st & 2nd fix

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
17-Jun-14

Duration Start

PL1GE1620

Lifts
Lifts
No DISP
PL1GE210

Four Seasons Hotel Bahrain

Page 141 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PL1MP790

FP Pipe Pressure testing

12 13-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
26-Mar-14

PL1MP720

Cable Termination

14 15-Mar-14

30-Mar-14

PL1MP800

Sprinkler installation

6 27-Mar-14

02-Apr-14

PL1MP770

Light Fittings

7 31-Mar-14

07-Apr-14

PL1MP830

Clean & Snag

6 08-Apr-14

14-Apr-14

Activity ID

Activity Name

Water Tank Room


MEP Finishes
No DISP
PL1EP960
Electrical Conduiting

Duration Start

45
45
45
12

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

08-Jan-14
08-Jan-14
08-Jan-14
28-Nov-13

PL1EP1000

Installation for RO System

45 16-Nov-13

08-Jan-14

PL1EP1030

Installation of Booster Pumps

14 16-Nov-13

01-Dec-13

PL1EP970

Cable Tray & Trunking

14 30-Nov-13

16-Dec-13

PL1EP1050

Installation of Water Supply Valves

10 30-Nov-13

12-Dec-13

PL1EP1040

Installation of Water Supply Piping

12 03-Dec-13

16-Dec-13

PL1EP1010

Installation & connection to Fire Pumps

12 04-Dec-13

17-Dec-13

PL1EP980

Wirng / cabling

8 17-Dec-13

25-Dec-13

PL1EP990

Starter Panel for Mech Equipment

14 17-Dec-13

02-Jan-14

PL1EP1060

Installation of FF valves

14 18-Dec-13

04-Jan-14

PL1EP1070

Installation of Fire Protection Piping

15 18-Dec-13

05-Jan-14

Install door

69
8
8
2

05-Feb-14
05-Feb-14
05-Feb-14
29-Jan-14

Boiler Room
Finishes
No DISP
PL1GE1470

16-Nov-13
28-Jan-14
28-Jan-14
28-Jan-14*

PL1GE1460

RMX01 to floor

6 30-Jan-14

05-Feb-14

PL1GE1480

Final paint

4 30-Jan-14

03-Feb-14

PL1GE1490

Complete

03-Feb-14

MEP 1st & 2nd Fix


No DISP
PL1MP860
Installation heating water pipes

63 16-Nov-13
63 16-Nov-13
28 16-Nov-13

29-Jan-14
29-Jan-14
18-Dec-13

PL1MP940

Installation of Chemical Dosing unit

4 16-Nov-13

19-Nov-13

PL1MP950

Chilled Water Piping (Main runs)

22 16-Nov-13

11-Dec-13

PL1MP990

Cable Trays

10 16-Nov-13

26-Nov-13

PL1MP1000

MCC panels and switches

8 18-Nov-13

26-Nov-13

PL1MP850

FP Piping

8 21-Nov-13

30-Nov-13

PL1MP1010

GI Conduiting

10 27-Nov-13

09-Dec-13

PL1MP870

FCU installation

2 01-Dec-13

03-Dec-13

PL1MP890

FP Pipe Pressure testing

3 01-Dec-13

04-Dec-13

PL1MP880

CHW pipe & valve connection to FCU

5 04-Dec-13

09-Dec-13

PL1MP920

Install chimneys

14 05-Dec-13

21-Dec-13

PL1MP900

Sprinkler installation

4 05-Dec-13

09-Dec-13

PL1MP1020

Cable and Wire pulling

10 10-Dec-13

21-Dec-13

PL1MP1030

DDC Panel and wiring

6 16-Dec-13

22-Dec-13

PL1MP910

Installation of steam boilers

5 19-Dec-13*

24-Dec-13

PL1MP1070

Installation of hot water boilers

7 22-Dec-13*

29-Dec-13

PL1MP1040

Cable Termination

PL1MP1090

Flushing of steam boilers

5 25-Dec-13*

30-Dec-13

PL1MP960

Completion of LPG connection to boilers

7 30-Dec-13

07-Jan-14

PL1MP1080

Flushing of water boilers

5 30-Dec-13*

05-Jan-14

PL1MP970

Chilled Water Pipe Pressure Testing

14 23-Dec-13

12 08-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 142 of 180

08-Jan-14

21-Jan-14
Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

PL1MP980

pressure testing & flushing of pipwork

Telephone Switch/PABX
Finishes
No DISP
PL1GE1360
RMX01 to floor

Duration Start

7 22-Jan-14
12
12
12
6

21-Jan-14
21-Jan-14
21-Jan-14
21-Jan-14

Install door

2 28-Jan-14*

29-Jan-14

Final paint

4 30-Jan-14

03-Feb-14

PL1GE1440

Complete

03-Feb-14

MEP Finishes
No DISP
PL1MP400

Chilled Water Pumps Installation

14-Oct-13 A
16-Oct-13 A
16-Oct-13 A
16-Oct-13 A

26-Apr-14
07-Dec-13
07-Dec-13
07-Dec-13

148 14-Oct-13 A
148 14-Oct-13 A
12 14-Oct-13 A

26-Apr-14
26-Apr-14
21-Nov-13

PL1MP550

FCU installation

2 16-Nov-13

17-Nov-13

PL1MP600

FP Pipe Pressure testing

3 16-Nov-13

18-Nov-13

PL1MP560

CHW pipe & valve connection to FCU

5 18-Nov-13

23-Nov-13

PL1MP610

Sprinkler installation

4 19-Nov-13

23-Nov-13

PL1MP420
PL1MP430

Installation of Expansion Tanks


Installation of Chemical Dosing unit

7 23-Nov-13
4 01-Dec-13

30-Nov-13
05-Dec-13

PL1MP440

Chilled Water Piping (Main runs)

40 07-Dec-13

22-Jan-14

PL1MP570

Floor Drains

6 08-Dec-13

14-Dec-13

PL1MP630

Equipment connections

24 23-Jan-14

19-Feb-14

PL1MP480

Chilled Water Pipe Pressure Testing

12 20-Feb-14

05-Mar-14

PL1MP490

Chilled Water Pipe insulation

18 03-Mar-14

23-Mar-14

PL1MP500

Cable Trays

10 03-Mar-14

13-Mar-14

PL1MP620

MCC panels and switches

8 05-Mar-14

13-Mar-14

PL1MP510

GI Conduiting

10 15-Mar-14

25-Mar-14

PL1MP520

Cable and Wire pulling

10 26-Mar-14

06-Apr-14

PL1MP540

DDC Panel and wiring

6 01-Apr-14

07-Apr-14

PL1MP530

Cable Termination

14 08-Apr-14

23-Apr-14

PL1MP580

Light Fittings

7 16-Apr-14

23-Apr-14

PL1MP640

Clean & Snag

2 24-Apr-14

26-Apr-14

0 31-Mar-14
0 31-Mar-14
0 31-Mar-14
0

31-Mar-14
31-Mar-14
31-Mar-14
31-Mar-14

Maintenance Engineerng
Finishes
No DISP
PL1GE1350
Complete
Electrical Plantroom
Finishes
No DISP
PL1EP1080
Install louvres
MEP 1st & 2nd Fix
No DISP
PL1EP140
Fuel tank installation

145
12
12
12

16-Nov-13
22-Feb-14
22-Feb-14
22-Feb-14*

05-May-14
06-Mar-14
06-Mar-14
06-Mar-14

145 16-Nov-13
145 16-Nov-13
18 16-Nov-13*

05-May-14
05-May-14
07-Dec-13

PL1EP230

Testing & commissioning

24 16-Nov-13

14-Dec-13

PL1EP150

Electrical distribution & tests

60 23-Nov-13

02-Feb-14

PL1EP160

Transformers installation

36 08-Dec-13

19-Jan-14

PL1EP170

Diesel generator installation

18 08-Dec-13

28-Dec-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 143 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

03-Feb-14
03-Feb-14
03-Feb-14
28-Jan-14

PL1GE1430

154
18
18
18

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
29-Jan-14

PL1GE1450

Mechanical Plantroom
Finishes
No DISP
PL1MP200
Painting on walls & floor

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PL1EP180

High Voltage cables & bus bars installation

60 22-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
02-Mar-14

PL1EP200

TGBT & Motor control system installation

60 29-Dec-13

09-Mar-14

PL1EP210

Electrical boards installation

24 03-Feb-14

02-Mar-14

PL1EP240

Clean & Snag

10 24-Apr-14

05-May-14

Activity ID

Activity Name

Plumbing Plantroom
Finishes
No DISP
PL1PP100
Concrete support for equipments
PL1PP120

Metal door with frames

MEP 1st & 2nd Fix


No DISP
PL1PP210
Painting on walls first coat

Duration Start

145
52
52
6

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

05-May-14
16-Jan-14
16-Jan-14
21-Nov-13

6 11-Jan-14*

16-Jan-14

139 23-Nov-13
139 23-Nov-13
18 23-Nov-13

05-May-14
05-May-14
14-Dec-13

PL1PP150

Fire Protectrion pumps installation

12 23-Nov-13

07-Dec-13

PL1PP140

Booster pumps installation

12 08-Dec-13

21-Dec-13

PL1PP160

Plumbing pumps installation

12 22-Dec-13

05-Jan-14

PL1PP180

Water tank equipment installation

30 06-Jan-14

09-Feb-14

PL1PP190

Pipes distribution & tests

48 06-Jan-14

02-Mar-14

PL1PP170

Water treatments installation

30 10-Feb-14

16-Mar-14

PL1PP200

Water tank waterproofing

36 17-Mar-14

27-Apr-14

PL1PP220

Electrical distribution & tests

25 17-Mar-14

14-Apr-14

PL1PP230

Electrical boards

20 25-Mar-14

16-Apr-14

PL1PP240

Painting on walls & floor

12 03-Apr-14

16-Apr-14

PL1PP280

Clean & Snag

10 24-Apr-14

05-May-14

Electrical Plantroom Low Voltage


Finishes
No DISP
PL1EL110
Metal door with frames
PL1EL240
Area H
No DISP
PL1EL140

Final Painting

LV cables distribution

110
24
24
12

16-Nov-13
27-Jan-14
27-Jan-14
27-Jan-14*

26-Mar-14
23-Feb-14
23-Feb-14
09-Feb-14

12 10-Feb-14

23-Feb-14

110 16-Nov-13
110 16-Nov-13
60 16-Nov-13*

26-Mar-14
26-Mar-14
26-Jan-14

PL1EL150

Fire Fighting System installation

36 29-Dec-13

09-Feb-14

PL1EL160

Building Management System

36 29-Dec-13

09-Feb-14

PL1EL170

Security/Access & Alarm System installation

36 29-Dec-13

09-Feb-14

PL1EL180

Security System installation

36 29-Dec-13

09-Feb-14

PL1EL190

Uninterruptable power supply UPS

24 29-Dec-13

26-Jan-14

PL1EL200

CCTV System installation

36 29-Dec-13

09-Feb-14

PL1EL210

PBX & Telephone Equipmnt installation

36 29-Dec-13

09-Feb-14

PL1EL220

External PBX & Telephone connection

36 29-Dec-13

09-Feb-14

PL1EL230

Music Audio System installation

36 29-Dec-13

09-Feb-14

PL1EL250

Testing & commissioning

50 27-Jan-14

25-Mar-14

PL1EL260

Telecommunication & Low Voltage connection

Ground level
Facades
Facades
No DISP
PGLFA230

Stone Cladding - North El.

0 26-Mar-14
246 16-Jun-13 A

05-Aug-14

148
148
148
36

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
05-Oct-13 A

01-Apr-14
01-Apr-14
01-Apr-14
19-Dec-13

PGLFA240

Facade brackets & framing - North El.

18 03-Oct-13 A

17-Nov-13

PGLFA210

Facade brackets & framing - West El.

18 18-Nov-13

09-Dec-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 144 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

P+2FA160

Curtain Wall Frames - South El. ( 1 )

10 23-Nov-13*

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
04-Dec-13

PGLFA220

Stone Cladding - West El.

30 03-Dec-13

07-Jan-14

P+2FA120

Curtain Wall Frames - East El. ( 2 )

13 04-Dec-13

18-Dec-13

P+2FA150

Curtain Wall Frames - North El. (3 )

9 18-Dec-13

28-Dec-13

P+2FA140

Curtain Wall Frames - West El. ( 4 )

6 29-Dec-13

05-Jan-14

P+2FA200

East Podium Vestibule CW Frames ( 10 )

14 14-Jan-14

30-Jan-14

PGLFA100

Facade brackets & framing - East El.

24 22-Jan-14

18-Feb-14

PGLFA190

Facade brackets & framing - South El.

24 29-Jan-14

25-Feb-14

PGLFA140

Stone Cladding - East El.

36 12-Feb-14

25-Mar-14

P+2FA130

Curtain Wall Glass - South El. ( 1)

4 15-Feb-14*

18-Feb-14

P+2FA170

Curtain Wall Glass - East El. ( 2 )

5 15-Feb-14

19-Feb-14

P+2FA220

Curtain Wall Frames - North El. Strip adj Tower (12)

PGLFA200

Stone Cladding - South El.

P+2FA180

Activity ID

Activity Name

Duration Start

5 16-Feb-14

22-Feb-14

36 19-Feb-14

01-Apr-14

Curtain Wall Glass - North El. ( 3 )

3 20-Feb-14

23-Feb-14

P+2FA190

Curtain Wall Glass - West El. ( 4 )

2 22-Feb-14

23-Feb-14

P+2FA240

Curtain Wall Frames -South El. Strip adj Tower (13)

5 22-Feb-14

27-Feb-14

P+2FA210

East Podium Vestibule Glass ( 10 )

5 13-Mar-14

18-Mar-14

P+2FA230

Curtain Wall Glass - North El. Strip adj Tower (12)

2 24-Mar-14

25-Mar-14

P+2FA250

Curtain Wall Glass -South El. Strip adj Tower (13)

2 26-Mar-14

27-Mar-14

General
Finishes
No DISP
PGLGE100

Masonry

228
225
225
26

16-Jun-13 A
16-Jun-13 A
16-Jun-13 A
16-Jun-13 A

06-Jul-14
01-Jul-14
01-Jul-14
28-Nov-13

PGLGE160

Gypsum & cement plaster

30 12-Oct-13 A

05-Jan-14

PGLGE170

Internal windows, doorsets

45 24-Dec-13*

15-Feb-14

PGLGE190

Gypsum False ceiling

42 06-Jan-14

23-Feb-14

PGLGE200

Stone wainscot

35 24-Mar-14*

03-May-14

PGLGE210

Stone flooring

36 10-Apr-14

21-May-14

PGLGE250

Doors & millwork

45 28-Apr-14

18-Jun-14

PGLGE1600

Wall covering

45 29-Apr-14

19-Jun-14

PGLGE260

Painting

45 10-May-14

01-Jul-14

216 10-Oct-13 A
216 10-Oct-13 A
24 10-Oct-13 A

26-Jun-14
26-Jun-14
07-Dec-13

Corridor
No DISP
PGLGE810

Cable Tray and Trunking

PGLGE820

Electrical Conduiting

24 16-Oct-13 A

08-Dec-13

PGLGE800

Duct Installation

24 12-Oct-13 A

30-Dec-13

PGLGE830

FP Piping

24 31-Dec-13

28-Jan-14

PGLGE880

Cabling and Wiring

36 20-Jan-14

02-Mar-14

PGLGE850

FP Dropper Piping

10 29-Jan-14

09-Feb-14

PGLGE870

Flexible ducts and Plenums

16 30-Jan-14

17-Feb-14

PGLGE840

FP Pipe Pressure Testing

5 10-Feb-14

15-Feb-14

PGLGE1090

Cable Termination

8 22-Feb-14

02-Mar-14

PGLGE900

Grilles and Diffusers

12 31-May-14

12-Jun-14

PGLGE890

Light Fittings

10 14-Jun-14

24-Jun-14

PGLGE910

ELV Devices

7 19-Jun-14

26-Jun-14

MEP Finishes
No DISP
PGLGE920

Access from Structure

184 30-Nov-13
184 30-Nov-13
0 30-Nov-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 145 of 180

06-Jul-14
06-Jul-14

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PGLGE1060

Drainage Piping

18 08-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
28-Dec-13

PGLGE930

Cable Tray and Trunking

12 29-Dec-13

12-Jan-14

PGLGE1070

Drainage Pipe Testing

5 29-Dec-13

04-Jan-14

PGLGE940

Electrical Conduiting

14 08-Jan-14

23-Jan-14

PGLGE950

Duct Installation

21 13-Jan-14

05-Feb-14

PGLGE970

Cabling and Wiring

18 20-Jan-14

09-Feb-14

PGLGE1150

FCU Installation

8 22-Jan-14

01-Feb-14

PGLGE1260

Cabling and Wiring

18 25-Jan-14

13-Feb-14

PGLGE1120

CHW Piping & valve connection to FCU

10 01-Feb-14

11-Feb-14

PGLGE960

FP Piping

14 06-Feb-14

22-Feb-14

PGLGE990

Flexible ducts and Plenums

16 06-Feb-14

24-Feb-14

PGLGE1080

Cable Termination

14 10-Feb-14

25-Feb-14

PGLGE1130

CHW Pipe pressure Testing

4 12-Feb-14

16-Feb-14

PGLGE1330

Cable Termination

14 15-Feb-14

02-Mar-14

PGLGE1140

CHW Pipe Insulation

6 17-Feb-14

23-Feb-14

PGLGE980

FP Dropper Piping

12 23-Feb-14

08-Mar-14

PGLGE1270

Light Fittings

10 03-Mar-14

13-Mar-14

PGLGE1000

FP Pipe Pressure Testing

7 09-Mar-14

16-Mar-14

PGLGE1240

Sprinkler installation

10 17-Mar-14

27-Mar-14

PGLGE1400

Clean & Snag

10 29-Mar-14

08-Apr-14

PGLGE1050

Sanitary Fittings and Accs.

12 22-May-14

04-Jun-14

PGLGE1100

Wiring Accessories

14 22-May-14

08-Jun-14

PGLGE1110

Floor Drains

5 22-May-14

27-May-14

PGLGE1010

Sprinkler installation

10 27-May-14

07-Jun-14

PGLGE1030

Light Fittings

10 14-Jun-14

24-Jun-14

PGLGE1020

Grilles and Diffusers

12 14-Jun-14

26-Jun-14

PGLGE1040

ELV Devices

8 25-Jun-14

06-Jul-14

Activity ID

Activity Name

Wedding facility
Finishes
No DISP
PGLGE1490

Gypsun stud and board one side

Duration Start

241
239
239
36

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

30-Jul-14
26-Jul-14
26-Jul-14
10-Dec-13

PGLGE1500

High level MEP installation

36 16-Nov-13

28-Dec-13

PGLGE1570

MEP drops in wall

12 29-Dec-13

12-Jan-14

PGLGE1520

Close walls tape & joint

24 13-Jan-14

09-Feb-14

PGLGE1510

Screed floor

12 10-Feb-14

23-Feb-14

PGLGE1540

Gypsum ceiling & Corniche

30 24-Feb-14

30-Mar-14

PGLGE1530

Wallcoverings/Upholstered panels

18 31-Mar-14

20-Apr-14

PGLGE1580

MEP final fix

12 07-Apr-14

20-Apr-14

PGLGE1610

Marble to WC,Pantry & bathroom

18 17-Apr-14*

07-May-14

PGLGE1620

Wood floor to Photoghraphy room

18 08-May-14

28-May-14

PGLGE1560

Install Millwork

18 29-May-14

18-Jun-14

PGLGE1590

Install doors & frames

12 05-Jun-14

18-Jun-14

PGLGE1630

Special finish SF-05 to millwork

18 19-Jun-14

15-Jul-14

PGLGE1550

Carpet

6 17-Jul-14

26-Jul-14

Light Fittings

8 17-Jul-14
8 17-Jul-14
4 17-Jul-14

30-Jul-14
30-Jul-14
22-Jul-14

Grilles and Diffusers

4 17-Jul-14

22-Jul-14

MEP Finishes
No DISP
PGLGE2340
PGLGE2350
Summary Bar

Remaining Work
Critical Remaining Work
Milestone

Page 146 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

PGLGE2360
Banquet Kitchen
Finishes
No DISP
PGLGE1420

ELV Devices

High level MEP installation

Duration Start

4 24-Jul-14
108
108
108
24

14-Oct-13 A
14-Oct-13 A
14-Oct-13 A
14-Oct-13 A

Ceramic tiles to walls

24 23-Nov-13

21-Dec-13

Acoustic ceiling

24 22-Dec-13

19-Jan-14

PGLGE1470

Ceramic tiles to floor

24 20-Jan-14

16-Feb-14

PGLGE1480

Install kitchen equipment

24 17-Feb-14

16-Mar-14

Gypsun board & T&J

16-Nov-13
17-Dec-13
17-Dec-13
17-Dec-13*

Waterproofing

4 28-Dec-13

31-Dec-13

PGLGE1670

Screed floor

4 02-Jan-14

06-Jan-14

PGLGE1690

Gypsum ceiling

9 07-Jan-14

16-Jan-14

PGLGE1700

Marble to Walls & Floor

18 31-Mar-14*

20-Apr-14

PGLGE1780

Accent tiling to walls

9 10-Apr-14

20-Apr-14

PGLGE1730

Install Millwork incl feature wall

15 21-Apr-14

07-May-14

PGLGE1740

Install doors & frames

6 01-May-14

07-May-14

PGLGE1710

Wallcoverings

6 08-May-14

14-May-14

PGLGE1760

Mirrors

4 15-May-14

19-May-14

PGLGE1790

Carpet

4 10-Jul-14

15-Jul-14

MEP 1st & 2nd Fix


No DISP
PGLBQ1060
Cable Tray and Trunking

26 16-Nov-13
26 16-Nov-13
6 16-Nov-13*

16-Dec-13
16-Dec-13
21-Nov-13

PGLBQ1080

Electrical Conduiting

4 18-Nov-13

21-Nov-13

PGLBQ1100

Duct Installation

8 23-Nov-13

01-Dec-13

PGLBQ1110

FP Piping

4 23-Nov-13

26-Nov-13

PGLBQ1070

Cabling and Wiring

8 23-Nov-13

01-Dec-13

PGLBQ1130

FP Pipe drops

5 27-Nov-13

03-Dec-13

PGLBQ1230

CHW Piping

4 27-Nov-13

01-Dec-13

PGLBQ1120

Flexible ducts and Plenums

4 03-Dec-13

07-Dec-13

PGLBQ1170

Cable Termination

8 03-Dec-13

11-Dec-13

PGLBQ1240

FCU installation

2 03-Dec-13

04-Dec-13

PGLBQ1250

CHW Pipe pressure testing

3 03-Dec-13

05-Dec-13

PGLBQ1140

FP Pipe Pressure Testing

5 04-Dec-13

09-Dec-13

PGLBQ1260

CHW Pipe insulation

9 07-Dec-13

16-Dec-13

244
244
244
12

10-Oct-13 A
10-Oct-13 A
10-Oct-13 A
10-Oct-13 A

03-Aug-14
03-Aug-14
03-Aug-14
21-Nov-13

PGLBL590

MEP hangers - from deck

12 10-Oct-13 A

21-Nov-13

PGLBL600

Stub brackets and track for operable partitions

12 23-Nov-13

07-Dec-13

PGLBL720

MEP high level installation

30 13-Oct-13 A

19-Dec-13

PGLBL610

Gypsum False ceiling

30 21-Dec-13

25-Jan-14

PGLBL620

Paint ceiling

24 05-Jan-14

01-Feb-14

PGLBL630

Remove scaffold

12 02-Feb-14

15-Feb-14

PGLBL640

Screed

9 09-Feb-14

18-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 147 of 180

Data date: 16-Nov-13

15-Jul-14
15-Jul-14
15-Jul-14
26-Dec-13

PGLGE1770

Ballroom Prefunction & corridor


Finishes
No DISP
PGLBL570
Ceiling hanger supports

Revised Programme Rev. D

16-Mar-14
16-Mar-14
16-Mar-14
07-Dec-13

PGLGE1460

201
175
175
9

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
30-Jul-14

PGLGE1450

Prayer Rooms
Finishes
No DISP
PGLGE1640

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PGLBL780

Drylined walls

24 16-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
15-Mar-14

PGLBL650

Install openable partitions

18 19-Feb-14

11-Mar-14

PGLBL730

Screed cure

12 19-Feb-14

04-Mar-14

PGLBL740

Stone wainscot

18 30-Apr-14*

20-May-14

PGLBL750

Stone flooring

12 21-May-14

03-Jun-14

PGLBL670

Install doors and frames

15 04-Jun-14

21-Jun-14

PGLBL660

Wall paneling

30 04-Jun-14

13-Jul-14

PGLBL680

Acoustic Paneling to openable partitions

18 18-Jun-14

13-Jul-14

PGLBL690

Final Painting

6 15-Jul-14

24-Jul-14

PGLBL700

Carpet

6 26-Jul-14

03-Aug-14

Activity ID

Activity Name

Ballroom
Finishes
No DISP
PGLBL770

Drylined walls

Duration Start

233
201
201
42

03-Oct-13 A
16-Nov-13
16-Nov-13
16-Nov-13

15-Jul-14
15-Jul-14
15-Jul-14
05-Jan-14

PGLBL880

Hangpoint & BusPort support steel

9 17-Nov-13*

26-Nov-13

PGLBL840

BusPort Manufactured

23-Nov-13

PGLBL850

BusPort shipping from USA

36 24-Nov-13

06-Jan-14

PGLBL160

Gypsum False ceiling ( 85% )

42 14-Dec-13

01-Feb-14

PGLBL790

Structure for glass columns

12 28-Dec-13

11-Jan-14

PGLBL860

BusPort Installation

12 07-Jan-14

20-Jan-14

PGLBL560

Paint ceiling

24 14-Jan-14

10-Feb-14

PGLBL870

BusPort Wiring

12 14-Jan-14

27-Jan-14

PGLBL820

Chandelier winch support steel

PGLBL890

Complete Gypsum ceiling

PGLBL180

Remove scaffold

PGLBL210

6 18-Jan-14*

23-Jan-14

12 21-Jan-14

03-Feb-14

9 04-Feb-14

13-Feb-14

Screed

12 15-Feb-14

27-Feb-14

PGLBL170

Install openable partitions

18 01-Mar-14

20-Mar-14

PGLBL760

Screed Cure

12 01-Mar-14

13-Mar-14

PGLBL230

Wall paneling

40 15-Mar-14

29-Apr-14

PGLBL550

Acoustic Paneling to openable partitions

24 22-Mar-14

17-Apr-14

PGLBL800

Glass columns

18 30-Apr-14

20-May-14

PGLBL240

Install doors and frames

18 21-May-14

10-Jun-14

PGLBL810

Install free issue chandelier

3 08-Jun-14

10-Jun-14

PGLBL250

Final Painting

18 11-Jun-14

03-Jul-14

PGLBL260

Carpet

7 05-Jul-14

15-Jul-14

220 03-Oct-13 A
220 03-Oct-13 A
24 10-Oct-13 A

24-Jun-14
24-Jun-14
28-Nov-13

MEP Finishes
No DISP
PGLBL300

Duct Installation

PGLBL280

Cable Tray and Trunking

24 03-Oct-13 A

28-Nov-13

PGLBL290

Electrical Conduiting

24 06-Oct-13 A

03-Dec-13

PGLBL310

FP Piping

24 13-Oct-13 A

21-Nov-13

PGLBL330

FP ceiling drops

12 23-Nov-13

07-Dec-13

PGLBL320

Cabling and Wiring

24 12-Oct-13 A

14-Dec-13

PGLBL350

FP Pipe Pressure Testing

5 08-Dec-13

12-Dec-13

PGLBL360

Cable Termination

12 15-Dec-13

28-Dec-13

PGLBL340

Flexible ducts and Plenums

18 12-Jan-14

01-Feb-14

PGLBL410

Wiring Accessories

10 05-Jun-14

17-Jun-14

PGLBL380

Grilles and Diffusers

12 11-Jun-14

24-Jun-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 148 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PGLBL370

Sprinkler installation

7 17-Jun-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
24-Jun-14

PGLBL390

Light Fittings

6 18-Jun-14

24-Jun-14

PGLBL400

ELV Devices

6 18-Jun-14

24-Jun-14

Activity ID

Activity Name

Banquet Prefunction & Corridor


Finishes
No DISP
PGLBQ850
MEP hangers - from deck

Duration Start

244
244
244
12

21-Oct-13 A
21-Oct-13 A
21-Oct-13 A
21-Oct-13 A

03-Aug-14
03-Aug-14
03-Aug-14
25-Nov-13

12 21-Oct-13 A

25-Nov-13

6 26-Nov-13

03-Dec-13

PGLBQ860

Ceiling hanger supports (40x40)

PGLBQ870

Stub brackets and track for operable partition

PGLBQ890

MEP high level installation

36 26-Nov-13

08-Jan-14

PGLBQ900

Gypsum False ceiling

36 18-Dec-13

29-Jan-14

PGLBQ910

Paint ceiling

18 16-Jan-14

05-Feb-14

PGLBQ920

Remove Scaffold for soffite works

12 30-Jan-14

12-Feb-14

PGLBQ930

Screed

6 13-Feb-14

19-Feb-14

PGLBQ940

Install openable partition

6 20-Feb-14

26-Feb-14

PGLBQ950

Screed Cure

12 20-Feb-14

05-Mar-14

PGLBQ1040

Drylined walls

24 20-Feb-14

19-Mar-14

PGLBQ1010

Carpet

6 05-Apr-14*

10-Apr-14

PGLBQ1020

Stone wainscot & base

18 07-May-14

27-May-14

PGLBQ1030

Stone flooring

18 28-May-14

17-Jun-14

PGLBQ990

Install doors and frames

18 18-Jun-14

13-Jul-14

PGLBQ960

Wall panelling

24 18-Jun-14

24-Jul-14

PGLBQ1000

Final Painting

12 15-Jul-14

03-Aug-14

PGLBQ970

Acoustic wall panels to openable partitions

12 15-Jul-14

03-Aug-14

Banquet Hall
Finishes
No DISP
PGLBQ780

MEP high level installation

PGLBL830

Hangpoint & BusPort support steel

PGLBQ200
PGLBQ450

216
216
216
36

10-Oct-13 A
10-Oct-13 A
10-Oct-13 A
10-Oct-13 A

05-Aug-14
05-Aug-14
05-Aug-14
07-Dec-13

9 17-Nov-13

26-Nov-13

Gypsum False ceiling ( 85 % )

36 08-Dec-13

19-Jan-14

Paint ceiling

24 29-Dec-13

26-Jan-14

PGLBL900

BusPort Installation

12 07-Jan-14

20-Jan-14

PGLBL910

BusPort Wiring

12 14-Jan-14

27-Jan-14

PGLBL920

Complete Gypsum ceiling

12 28-Jan-14

10-Feb-14

PGLBQ790

Remove Scaffold for soffite works

6 11-Feb-14

17-Feb-14

PGLBQ190

Screed

9 18-Feb-14

27-Feb-14

PGLBQ810

Install openable partitions

6 01-Mar-14

06-Mar-14

PGLBQ830

Screed Cure

6 01-Mar-14

06-Mar-14

PGLBQ1050

Drylined walls

36 01-Mar-14

10-Apr-14

PGLBQ820

Acoustic wall panels to openable partitions

12 08-Mar-14

20-Mar-14

PGLBQ180

Wall Fabric panels

42 12-Apr-14

29-May-14

PGLBQ170

Wood columns

24 31-May-14

26-Jun-14

PGLBQ250

Install doors and frames

18 28-Jun-14

27-Jul-14

PGLBQ240

Carpet

9 28-Jul-14

05-Aug-14

121 16-Nov-13
121 16-Nov-13
18 16-Nov-13

07-Apr-14
07-Apr-14
07-Dec-13

MEP Finishes
No DISP
PGLBQ290

Cable Tray and Trunking

PGLBQ590

Cabling and Wiring

16 16-Nov-13

04-Dec-13

PGLBQ300

Electrical Conduiting

14 25-Nov-13

11-Dec-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 149 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PGLBQ630

Cable Termination

18 05-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
25-Dec-13

PGLBQ310

Duct Installation

24 08-Dec-13

05-Jan-14

PGLBQ340

FP Piping

24 08-Dec-13

05-Jan-14

PGLBQ380

FP Pipe drops

10 24-Dec-13

05-Jan-14

PGLBQ400

FP Pipe Pressure Testing

5 06-Jan-14

11-Jan-14

PGLBQ350

Flexible ducts and Plenums

12 06-Jan-14

19-Jan-14

PGLBQ410

Sprinkler installation

6 12-Jan-14

18-Jan-14

PGLBQ390

Grilles and Diffusers

12 20-Jan-14

02-Feb-14

PGLBQ420

Floor Conduiting and Boxes

6 18-Feb-14

24-Feb-14

PGLBQ320

Cabling and Wiring

16 25-Feb-14

15-Mar-14

PGLBQ330

Cable Termination

8 16-Mar-14

24-Mar-14

PGLBQ360

Light Fittings

10 25-Mar-14

05-Apr-14

PGLBQ430

Wiring Accs.

6 25-Mar-14

31-Mar-14

PGLBQ370

ELV Devices

7 31-Mar-14

07-Apr-14

Activity ID

Activity Name

Restrooms
Finishes
No DISP
PGLGE1800

Blockwork to close MEP risers

Duration Start

197
146
146
12

16-Nov-13
14-Jan-14
14-Jan-14
14-Jan-14

08-Jul-14
05-Jul-14
05-Jul-14
27-Jan-14

PGLGE1940

Steel frame for vanity units

6 21-Jan-14

27-Jan-14

PGLGE1900

Stud to block walls

6 25-Jan-14*

30-Jan-14

PGLGE1910

MEP drops in walls

5 01-Feb-14*

05-Feb-14

PGLGE1920

Cement board to walls

9 06-Feb-14*

16-Feb-14

PGLGE1960

Stud & board to cubicle partitions

18 17-Feb-14

09-Mar-14

PGLGE1830

Gypsum ceiling

18 10-Mar-14

30-Mar-14

PGLGE1950

Install corniche

9 24-Mar-14

02-Apr-14

PGLGE1810

Waterproofing

6 03-Apr-14

09-Apr-14

PGLGE1930

Waterproofing Test complete

4 10-Apr-14

14-Apr-14

PGLGE1820

Screed floor

4 15-Apr-14

19-Apr-14

PGLGE1840

Marble to Walls,Floor, cubicles & vanity tops

30 20-Apr-14

24-May-14

PGLGE1860

Install Millwork & wall panelling

18 28-May-14

17-Jun-14

PGLGE1870

Install doors & frames

6 11-Jun-14

17-Jun-14

PGLGE1880

Wallcoverings

9 18-Jun-14

28-Jun-14

PGLGE1890

Mirrors

MEP 1st & 2nd Fix


No DISP
PGLBQ1270
Cable Tray and Trunking

4 29-Jun-14

05-Jul-14

49 16-Nov-13
49 16-Nov-13
6 16-Nov-13*

13-Jan-14
13-Jan-14
21-Nov-13

PGLBQ1400

Drainage piping

6 16-Nov-13*

21-Nov-13

PGLBQ1280

Electrical Conduiting

4 23-Nov-13

26-Nov-13

PGLBQ1310

Lighting & power wiring

8 23-Nov-13

01-Dec-13

PGLBQ1410

Drainage pipe testing

3 23-Nov-13*

25-Nov-13

PGLBQ1450

ELV cabling

8 23-Nov-13

01-Dec-13

PGLBQ1290

Duct Installation

15 26-Nov-13

14-Dec-13

PGLBQ1300

FP Piping

9 27-Nov-13

08-Dec-13

PGLBQ1350

Cable Termination

8 03-Dec-13

11-Dec-13

PGLBQ1320

FP Pipe drops

5 09-Dec-13

14-Dec-13

PGLBQ1330

CHW Piping

4 09-Dec-13

12-Dec-13

PGLBQ1420

Domestic water Piping

18 09-Dec-13

29-Dec-13

PGLBQ1360

FCU installation

2 14-Dec-13

15-Dec-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 150 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PGLBQ1370

CHW Pipe pressure testing

3 14-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
16-Dec-13

PGLBQ1380

FP Pipe Pressure Testing

5 15-Dec-13

19-Dec-13

PGLBQ1340

Flexible ducts and Plenums

5 15-Dec-13

19-Dec-13

PGLBQ1390

CHW Pipe insulation

9 17-Dec-13

26-Dec-13

PGLBQ1430

Pressure test for Domestic water

6 30-Dec-13

06-Jan-14

PGLBQ1440

Insulation to Domestic water

6 07-Jan-14

13-Jan-14
08-Jul-14
08-Jul-14
03-Apr-14

Activity ID

Activity Name

Duration Start

Sprinkler installation

83 31-Mar-14
83 31-Mar-14
4 31-Mar-14

PGLBQ1460

Sanitaryware & connections

15 11-May-14

27-May-14

PGLBQ1200

Light Fittings

6 29-Jun-14

08-Jul-14

PGLBQ1220

ELV Devices

6 29-Jun-14

08-Jul-14

PGLBQ1180

Wiring Accs.

4 03-Jul-14

08-Jul-14

188 05-Oct-13 A

18-May-14

136
136
136
60

05-Oct-13 A
05-Oct-13 A
05-Oct-13 A
05-Oct-13 A

18-Mar-14
18-Mar-14
18-Mar-14
09-Jan-14

MEP Finishes
No DISP
PGLBQ1190

+01 @ +16.00
Facades
Facades
No DISP
P+1FA100

PCC brackets - Ballroom

P+1FA110

PCC - Ballroom North

40 10-Oct-13 A

22-Dec-13

P+1FA180

PCC - Ballroom East

30 01-Dec-13

06-Jan-14

P+1FA160

PCC brackets - Banquet Hall

40 05-Dec-13

21-Jan-14

P+1FA190

PCC - Ballroom West

36 23-Dec-13

03-Feb-14

P+1FA170

PCC - Banquet Hall North

18 24-Dec-13

14-Jan-14

P+1FA200

PCC - Ballroom South

40 07-Jan-14

22-Feb-14

P+1FA210

PCC - Banquet Hall East

18 15-Jan-14

04-Feb-14

P+1FA220

PCC - Banquet Hall South

18 05-Feb-14

25-Feb-14

P+1FA230

PCC - Banquet Hall West

18 26-Feb-14

18-Mar-14

Roof, Terrace
Area H
No DISP
P+1SW220

Screed - H

125
60
60
12

23-Dec-13
15-Jan-14
15-Jan-14
15-Jan-14

18-May-14
25-Mar-14
25-Mar-14
28-Jan-14

P+1SW230

Waterproofing - H

24 29-Jan-14

25-Feb-14

P+1SW240

Insulation - H

12 26-Feb-14

11-Mar-14

P+1SW250

Pavers & gravel protection - H

12 12-Mar-14

25-Mar-14

125 23-Dec-13
125 23-Dec-13
12 23-Dec-13

18-May-14
18-May-14
06-Jan-14

Area G
No DISP
P+1SW100

Screed - G

P+1SW110

Waterproofing - G

24 07-Jan-14

03-Feb-14

P+1SW120

Insulation - G

12 04-Feb-14

17-Feb-14

P+1SW130

Pavers & gravel protection - G

12 18-Feb-14

03-Mar-14

P+1SW260

Complete roofing after removal of Wall 1 mastclimber

9 08-May-14

18-May-14

Mechanical Plantroom
Finishes
No DISP
P+1MP100
Masonry Ballroom MP
P+1MP130

Metal door with frames

Mech Plantroom (Area G)


No DISP
P+1MP850
Access from Structure

124
101
101
24

05-Oct-13 A
05-Oct-13 A
05-Oct-13 A
05-Oct-13 A

18 16-Feb-14*

08-Mar-14

94 15-Dec-13
94 15-Dec-13
0 15-Dec-13

03-Apr-14
03-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

03-Apr-14
08-Mar-14
08-Mar-14
14-Dec-13

Page 151 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

P+1MP860

AHU Installation

14 15-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
30-Dec-13

P+1MP460

Electrical Tray & Trunking

12 22-Dec-13

05-Jan-14

P+1MP430

FCU installation

P+1MP870

CHW pipe installation

14 31-Dec-13

16-Jan-14

P+1MP960

Condensate drain piping

14 31-Dec-13

16-Jan-14

P+1MP520

FP Piping

10 06-Jan-14

16-Jan-14

P+1MP490

MCC Panel installation

12 18-Jan-14

30-Jan-14

P+1MP530

FP Pipe Pressure Testing

P+1MP890

Duct Installation

P+1MP950

Activity ID

Activity Name

Duration Start

4 31-Dec-13*

05-Jan-14

4 18-Jan-14

21-Jan-14

16 18-Jan-14

04-Feb-14

CHW pipe and valve connection to FCUs

5 18-Jan-14

22-Jan-14

P+1MP1080

Floor Drains

5 18-Jan-14

22-Jan-14

P+1MP540

Sprinkler installation

5 22-Jan-14

27-Jan-14

P+1MP910

CHW Pipe pressure Testing

10 23-Jan-14

03-Feb-14

P+1MP470

Electrical conduiting

10 01-Feb-14

11-Feb-14

P+1MP410

CHW pipe insulation

18 04-Feb-14

24-Feb-14

P+1MP880

CHW pipe & Valve Package connection to AHUs

21 04-Feb-14

27-Feb-14

P+1MP900

Duct connection to AHUs

24 05-Feb-14

04-Mar-14

P+1MP480

Cabling and wire pulling

14 12-Feb-14

27-Feb-14

P+1MP560

Cable termination

14 01-Mar-14

16-Mar-14

P+1MP920

CHW pipe insulation

18 01-Mar-14

20-Mar-14

P+1MP930

Dampers and Plenum installation

16 05-Mar-14

23-Mar-14

P+1MP500

Light Fittings

7 17-Mar-14

24-Mar-14

P+1MP1090

Clean & Snag

10 24-Mar-14

03-Apr-14

P+1MP510

FA & SD installation

4 25-Mar-14

29-Mar-14

77 16-Nov-13
77 16-Nov-13
10 16-Nov-13

15-Feb-14
15-Feb-14
26-Nov-13

12 27-Nov-13

11-Dec-13

8 27-Nov-13

07-Dec-13

10 27-Nov-13

09-Dec-13

5 08-Dec-13

12-Dec-13

10 10-Dec-13

21-Dec-13

7 12-Dec-13

19-Dec-13

Mech Plantroom (Area H)


No DISP
P+1MP1140
AHU Installation
P+1MP1150

CHW pipe installation

P+1MP1240

Condensate drain piping

P+1MP1280

MCC Panel installation

P+1MP1120

Floor Drains

P+1MP1260

Electrical conduiting

P+1MP660

CHW Pipe pressure Testing

P+1MP1160

CHW pipe & Valve Package connection to AHUs

18 12-Dec-13

02-Jan-14

P+1MP1170

Duct Installation

14 12-Dec-13

28-Dec-13

P+1MP670

CHW pipe insulation

14 14-Dec-13

29-Dec-13

P+1MP720

CHW pipe & Valve Package connection to AHUs

18 21-Dec-13

11-Jan-14

P+1MP1270

Cabling and wire pulling

12 22-Dec-13

05-Jan-14

P+1MP1180

Duct connection to AHUs

18 29-Dec-13

19-Jan-14

P+1MP790

Condensate drain piping

P+1MP1110

Cable termination

P+1MP810

Floor Drains

P+1MP1210

Dampers and Plenum installation

P+1MP1290
P+1MP1300
P+1MP830

Clean & Snag

8 30-Dec-13

08-Jan-14

14 06-Jan-14

21-Jan-14

5 09-Jan-14

14-Jan-14

16 20-Jan-14

06-Feb-14

Light Fittings

7 22-Jan-14

29-Jan-14

FA & SD installation

4 30-Jan-14

03-Feb-14

10 04-Feb-14

15-Feb-14

12 25-Feb-14

10-Mar-14

12 25-Feb-14

10-Mar-14

+02 @ +24.85
General
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 152 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

MEP Finishes
No DISP
P+2GE10220

Lightning Protection Works

WEST PODIUM
Foundation
Civil Works West Podium
Area K
No DISP
WPECE380
Blinding & waterproofing

Lower level
Civil Works West Podium
Area K
No DISP
WP1CEP150
Slab on grade @ +5.05

Duration Start

12 25-Feb-14
12 25-Feb-14
12 25-Feb-14*

14-Aug-14

12 07-Sep-13 A

16-Nov-13

12
12
12
12

07-Sep-13 A
07-Sep-13 A
07-Sep-13 A
07-Sep-13 A

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

253 09-Sep-13 A

14-Aug-14

09-Sep-13 A
09-Sep-13 A
09-Sep-13 A
09-Sep-13 A

18-Dec-13
18-Dec-13
18-Dec-13
16-Nov-13

WP1CEP300

Cast Lap Pool

24 24-Oct-13 A

19-Nov-13

WP1CEP310

Cast Whirlpool

24 20-Nov-13

18-Dec-13

Slab on grade @ +5.05

18 14-Sep-13 A
18 14-Sep-13 A
18 14-Sep-13 A

19-Nov-13
19-Nov-13
19-Nov-13

Area L
No DISP
WP1CEP230
Facades
Area K
WP Glass
WP1FA210

Split face Stone to Mens Hammam ( 6 )

153
118
83
12

27-Oct-13 A
10-Dec-13
15-Jan-14
15-Jan-14

Split face Stone to Mens Spa ( 8 )

12 01-Feb-14

15-Feb-14

AWP1FA130

Split face Stone to Lap Pool ( 9 )

12 15-Feb-14

01-Mar-14

WP1FA220

Glass to Mens Hammam ( 6 )

12 24-Feb-14

09-Mar-14

WP1FA250

Glass to Mens Spa ( 8 )

12 24-Mar-14

06-Apr-14

WP1FA140

Glass to Lap Pool ( 9 )

13 07-Apr-14

21-Apr-14

118 10-Dec-13
30 10-Dec-13

27-Apr-14
14-Jan-14

Waterproof & insulation for Split face Stone

WP1FA290

CW Frames to Mens Hammam ( 6 )

15 17-Dec-13

05-Jan-14

WP1FA310

CW Frames to Lap Pool ( 9 )

15 31-Dec-13

19-Jan-14

WP1FA300

CW Frames to Mens Spa ( 8 )

15 14-Jan-14

01-Feb-14

WP1FA230

Screen Panels to Mens Hammam ( 6 )

12 03-Mar-14

16-Mar-14

WP1FA260

Screen Panels to Mens Spa ( 8 )

12 31-Mar-14

13-Apr-14

WP1FA150

Screen Panels to Lap Pool ( 9 )

12 14-Apr-14

27-Apr-14

129 27-Oct-13 A
78 21-Dec-13
12 21-Dec-13

30-Mar-14
23-Mar-14
05-Jan-14

Area L
WP Glass
WP1FA190

Split face Stone to Pool dining & KFS ( 5 )

WP1FA160

Split face Stone to Unisex fitness ( 7 )

12 19-Jan-14

02-Feb-14

WP1FA200

Glass to Pool dining & KFS ( 5 )

15 24-Feb-14

12-Mar-14

WP1FA170

Glass to Unisex fitness ( 7 )

12 10-Mar-14

23-Mar-14

129 27-Oct-13 A
36 27-Oct-13 A

30-Mar-14
23-Dec-13

No DISP
WP1FA280

Waterproof & insulation for Split face Stone

WP1FA330

CW Frames to Pool dining & KFS ( 5 )

23 23-Nov-13*

21-Dec-13

WP1FA320

CW Frames to Unisex fitness ( 7 )

15 31-Dec-13

19-Jan-14

WP1FA180

Screen Panels to Unisex fitness ( 7 )

12 17-Mar-14

30-Mar-14

137 22-Dec-13
76 04-Mar-14
76 04-Mar-14

31-May-14
31-May-14
31-May-14

General
Thermal cabins
No DISP
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 153 of 180

Revised Programme Rev. D

Data date: 16-Nov-13

27-Apr-14
27-Apr-14
21-Apr-14
28-Jan-14

WP1FA240

No DISP
WP1FA270

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
10-Mar-14
10-Mar-14
10-Mar-14

253 07-Sep-13 A

60
60
60
18

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

WP1GE870

Install thermal cabins

36 04-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
14-Apr-14

WP1GE890

Finishes to thermal cabins

40 15-Apr-14

31-May-14

North Equipment room


No DISP
WP1GE850
Install pool equipment

60 22-Dec-13
60 22-Dec-13
60 22-Dec-13

02-Mar-14
02-Mar-14
02-Mar-14

South Equipment room


No DISP
WP1GE860
Install pool equipment

60 10-Feb-14
60 10-Feb-14
60 10-Feb-14

20-Apr-14
20-Apr-14
20-Apr-14

Activity ID

Activity Name

Substations 2 & 3
Area L
Finishes
WP1EP250
Masonry

Duration Start

128
128
37
12

07-Oct-13 A
07-Oct-13 A
07-Oct-13 A
21-Oct-13 A

23-Mar-14
23-Mar-14
07-Dec-13
27-Nov-13

WP1EP270

Concrete plinths

6 07-Oct-13 A

27-Nov-13

WP1EP280

Paint plinths

6 28-Nov-13

05-Dec-13

WP1EP290

Access from structure

0 07-Dec-13

MEP
WP1EP310

Electrical containment

80 07-Dec-13
18 07-Dec-13

10-Mar-14
26-Dec-13

WP1EP320

Cable tray & truncking

30 07-Dec-13

11-Jan-14

WP1EP300

Duct installation

12 18-Dec-13

31-Dec-13

WP1EP360

Installation of HV Dicsonnect switch

12 24-Dec-13

06-Jan-14

WP1EP410

HV cable pulling & connections

24 24-Dec-13

20-Jan-14

WP1EP420

Installation of LV & PFC panels

12 26-Dec-13

08-Jan-14

WP1EP390

Lighting & power wiring

21 28-Dec-13

20-Jan-14

WP1EP400

ELV cabling

10 02-Jan-14

13-Jan-14

WP1EP430

LV cable pulling & connections

18 09-Jan-14

29-Jan-14

WP1EP440

FM 200 system

12 18-Jan-14

30-Jan-14

WP1EP350

Transformer installation

20 26-Jan-14

17-Feb-14

WP1EP450

Cable terminations

18 18-Feb-14

10-Mar-14

Light fittings

11 11-Mar-14
4 11-Mar-14

23-Mar-14
15-Mar-14

MEP Final Fix


WP1GE5630
WP1GE5640

Inverter panel installation

4 12-Mar-14

16-Mar-14

WP1GE5650

ELV devices

9 13-Mar-14

23-Mar-14

WP1GE5660

Grills & diffusers

4 13-Mar-14

17-Mar-14

Mens Spa & Hammam


Area K
Finishes
WP1GE3150
Masonry

236
236
209
9

10-Oct-13 A
10-Oct-13 A
20-Nov-13
20-Nov-13*

04-Aug-14
04-Aug-14
04-Aug-14
30-Nov-13

WP1GE3160

Drywall partitions - Stud & 1 board

12 21-Jan-14

03-Feb-14

WP1GE3170

Drywall partitions - 2nd board, Tape & joint

18 23-Jan-14

12-Feb-14

WP1GE3210

MEP Complete above ceiling

WP1GE3200

Gypsum ceiling

18 06-Feb-14

26-Feb-14

WP1GE3190

Venetion plaster to walls

24 27-Mar-14

23-Apr-14

WP1GE3240

Curtain wall installed

0 07-Apr-14

WP1GE3180

Accent tiles to walls

18 24-Apr-14

14-May-14

WP1GE3230

Accent Tile Flooring

18 15-May-14

04-Jun-14

WP1GE3250

Wood ceilings

18 29-May-14

18-Jun-14

WP1GE3270

Wood flooring

18 12-Jun-14

05-Jul-14

WP1GE3220

Moterised mechoshades and blinds

12 19-Jun-14

05-Jul-14

WP1GE3260

Millwork incl doors

18 06-Jul-14

04-Aug-14

0 23-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 154 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

Drainage piping

80 10-Oct-13 A
12 10-Oct-13 A

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
22-Jan-14
26-Nov-13

WP1GE1090

Plumbing piping

14 20-Oct-13 A

07-Dec-13

WP1GE960

Fire fighting piping

14 12-Oct-13 A

12-Dec-13

WP1GE970

Gravity test for Drainage

6 27-Nov-13

04-Dec-13

WP1GE980

CHW piping

12 05-Dec-13

18-Dec-13

WP1GE990

Cable tray & trunking

12 17-Dec-13

30-Dec-13

WP1GE1000

Duct installation

14 19-Dec-13

05-Jan-14

WP1GE1010

Pressure test CHW piping

6 19-Dec-13

25-Dec-13

WP1GE1020

CHW pipe insulation

9 26-Dec-13

06-Jan-14

WP1GE1030

ELV cabling

10 31-Dec-13

12-Jan-14

WP1GE1060

Earthing/Lightning protection

12 31-Dec-13

14-Jan-14

WP1GE1070

FCU installation

9 06-Jan-14

15-Jan-14

WP1GE1080

Installation of fans

9 06-Jan-14

15-Jan-14

WP1GE1040

Small power wiring

10 12-Jan-14

22-Jan-14

WP1GE1050

Cabling

10 12-Jan-14

22-Jan-14

Light fittings

11 19-Jun-14
9 19-Jun-14

03-Jul-14
29-Jun-14

Activity ID

Activity Name

MEP
WP1GE950

MEP Final Fix


WP1GE3280

Duration Start

WP1GE3290

Sprinkler heads

9 21-Jun-14

01-Jul-14

WP1GE3300

FA devices

9 22-Jun-14

03-Jul-14

WP1GE3310

Grills & diffusers

9 22-Jun-14

03-Jul-14

Lap Pool
Area K
Finishes
WP1GE3320

Masonry

221
221
208
15

16-Nov-13
16-Nov-13
01-Dec-13
01-Dec-13

14-Aug-14
14-Aug-14
14-Aug-14
18-Dec-13

30 11-Feb-14

17-Mar-14

WP1GE3350

Gypsum ceiling

WP1GE3360

MEP Complete above ceiling

WP1GE3330

Drywall partitions - Stud & 1 board

18 18-Feb-14

10-Mar-14

WP1GE3340

Drywall partitions - 2nd board, Tape & joint

24 04-Mar-14

31-Mar-14

WP1GE3380

Venetion plaster to walls

30 23-Mar-14*

26-Apr-14

WP1GE3370

Stone to walls

36 13-Apr-14*

24-May-14

WP1GE3390

Curtain wall installed

WP1GE3410

AccentTile Flooring

36 11-May-14

21-Jun-14

WP1GE3430

Stone flooring

36 01-Jun-14

19-Jul-14

WP1GE3440

Millwork incl shutters to windows

18 20-Jul-14

14-Aug-14

WP1GE4740

Glass doors & Screens

12 20-Jul-14

07-Aug-14

WP1GE6460

Wall Murals

18 20-Jul-14

14-Aug-14

MEP
WP1GE3450

Drainage piping

60 01-Dec-13
12 01-Dec-13

10-Feb-14
15-Dec-13

WP1GE3460

Plumbing piping

14 09-Dec-13

24-Dec-13

WP1GE3470

Fire fighting piping

14 16-Dec-13

31-Dec-13

WP1GE3480

Gravity test for Drainage

6 16-Dec-13

22-Dec-13

WP1GE3490

CHW piping

10 23-Dec-13

04-Jan-14

WP1GE3500

Cable tray & trunking

10 02-Jan-14

13-Jan-14

WP1GE3510

Duct installation

14 05-Jan-14

20-Jan-14

WP1GE3520

Pressure test CHW piping

6 05-Jan-14

11-Jan-14

WP1GE3530

CHW pipe insulation

12 12-Jan-14

25-Jan-14

WP1GE3540

ELV cabling

10 14-Jan-14

25-Jan-14

0 11-Feb-14

0 22-Apr-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 155 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

Earthing/Lightning protection

WP1GE3560

FCU installation

9 21-Jan-14

30-Jan-14

WP1GE3570

Installation of fans

9 21-Jan-14

30-Jan-14

WP1GE3580

Small power wiring

15 25-Jan-14

10-Feb-14

WP1GE3590

Cabling

15 25-Jan-14

10-Feb-14

Light fittings

8 16-Nov-13
6 16-Nov-13

24-Nov-13
21-Nov-13

WP1GE3610

Sprinkler heads

6 17-Nov-13

23-Nov-13

WP1GE3620

FA devices

6 18-Nov-13

24-Nov-13

WP1GE3630

Grills & diffusers

6 18-Nov-13

24-Nov-13

Unisex Fitness
Area L
Finishes
WP1GE3640

Masonry

208
208
200
18

20-Nov-13
20-Nov-13
20-Nov-13
20-Nov-13

03-Aug-14
03-Aug-14
20-Jul-14
11-Dec-13

12 04-Feb-14

17-Feb-14

WP1GE3650

Drywall partitions - Stud & 1 board

WP1GE3670

MEP Complete above ceiling

WP1GE3660

Drywall partitions - 2nd board, Tape & joint

18 11-Feb-14

03-Mar-14

WP1GE3690

Venetion plaster to walls

20 04-Mar-14

26-Mar-14

WP1GE3700

Curtain wall installed

WP1GE3710

Gypsum ceiling

24 27-Mar-14

23-Apr-14

WP1GE3970

Wood ceiling

24 17-Apr-14

14-May-14

WP1GE3740

Wood flooring & borders

24 08-May-14

04-Jun-14

WP1GE3720

Moterised mechoshades and blinds

12 05-Jun-14

18-Jun-14

WP1GE3750

Millwork

18 05-Jun-14

25-Jun-14

WP1GE4730

Glass doors & Screens

6 19-Jun-14

25-Jun-14

WP1GE3980

Mirrors

9 26-Jun-14

10-Jul-14

WP1GE3730

Vinyl Flooring

6 12-Jul-14

20-Jul-14
03-Feb-14
04-Dec-13

Drainage piping

WP1GE3770

Plumbing piping

14 28-Nov-13

15-Dec-13

WP1GE3780

Fire fighting piping

14 05-Dec-13

21-Dec-13

WP1GE3790

Gravity test for Drainage

6 05-Dec-13

11-Dec-13

WP1GE3800

CHW piping

12 12-Dec-13

25-Dec-13

WP1GE3810

Cable tray & trunking

12 24-Dec-13

07-Jan-14

WP1GE3820

Duct installation

18 26-Dec-13

16-Jan-14

WP1GE3830

Pressure test CHW piping

6 26-Dec-13

02-Jan-14

WP1GE3840

CHW pipe insulation

6 04-Jan-14

09-Jan-14

WP1GE3850

ELV cabling

12 08-Jan-14

21-Jan-14

WP1GE3860

Earthing/Lightning protection

12 08-Jan-14

21-Jan-14

WP1GE3870

FCU installation

9 18-Jan-14

27-Jan-14

WP1GE3880

Installation of fans

9 18-Jan-14

27-Jan-14

WP1GE3890

Small power wiring

12 21-Jan-14

03-Feb-14

WP1GE3900

Cabling

12 21-Jan-14

03-Feb-14

Light fittings

8 22-Jul-14
6 22-Jul-14

03-Aug-14
31-Jul-14

WP1GE3920

Sprinkler heads

6 24-Jul-14

02-Aug-14

WP1GE3930

FA devices

6 26-Jul-14

03-Aug-14

WP1GE3940

Grills & diffusers

6 26-Jul-14

03-Aug-14

Summary Bar
Remaining Work
Milestone

Data date: 16-Nov-13

0 24-Mar-14

63 20-Nov-13
12 20-Nov-13

Critical Remaining Work

Revised Programme Rev. D

0 04-Feb-14

MEP
WP1GE3760

MEP Final Fix


WP1GE3910

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
27-Jan-14

WP1GE3550

MEP Final Fix


WP1GE3600

12 14-Jan-14

Four Seasons Hotel Bahrain

Page 156 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Poolside Dining
Area L
Finishes
WP1GE3990

Masonry

Duration Start

197
197
197
12

12-Dec-13
12-Dec-13
12-Dec-13
12-Dec-13

Kitchen hood

9 22-Feb-14

03-Mar-14

WP1GE4180

Walk in coldroom

6 22-Feb-14

27-Feb-14

WP1GE4000

Drywall partitions - Stud & 1 board

12 11-Mar-14

24-Mar-14

WP1GE4060

Curtain wall installed

WP1GE4010

Drywall partitions - 2nd board, Tape & joint

18 15-Mar-14

03-Apr-14

WP1GE4040

Ceramic tiles to walls

18 24-Apr-14*

14-May-14

WP1GE4050

Gypsum ceiling

24 01-May-14

28-May-14

WP1GE4750

Glass doors & Screens

12 15-May-14

28-May-14

WP1GE4190

Wall covering

9 19-May-14

28-May-14

WP1GE4020

Moterised mechoshades and blinds

12 26-May-14

08-Jun-14

WP1GE4080

Stone flooring

24 29-May-14

25-Jun-14

WP1GE4110

Kitchen equipement

18 26-Jun-14

26-Jul-14

WP1GE4090

Millwork

12 27-Jul-14

12-Aug-14

WP1GE4070

Starfish feature to ceiling

12 27-Jul-14

12-Aug-14

H/L Drainage piping

48 26-Dec-13
12 26-Dec-13

22-Feb-14
09-Jan-14

WP1GE1120

Plumbing piping

12 31-Dec-13

14-Jan-14

WP1GE1130

Fire fighting piping

12 11-Jan-14

23-Jan-14

WP1GE1140

Gravity test for Drainage

3 11-Jan-14

13-Jan-14

WP1GE1150

CHW piping

10 14-Jan-14

25-Jan-14

WP1GE1160

Cable tray & trunking

10 23-Jan-14

03-Feb-14

WP1GE1170

Duct installation

12 26-Jan-14

08-Feb-14

WP1GE1180

Pressure test CHW piping

4 26-Jan-14

29-Jan-14

WP1GE4160

Conduit drops in walls

12 28-Jan-14

10-Feb-14

WP1GE1190

CHW pipe insulation

6 30-Jan-14

05-Feb-14

WP1GE1200

ELV cabling

6 04-Feb-14

10-Feb-14

WP1GE1210

Earthing/Lightning protection

6 04-Feb-14

10-Feb-14

WP1GE1220

FCU installation

4 09-Feb-14

12-Feb-14

WP1GE1230

Installation of fans

4 09-Feb-14

12-Feb-14

WP1GE1240

Small power wiring

10 10-Feb-14

20-Feb-14

WP1GE1250

Cabling

10 10-Feb-14

20-Feb-14

WP1GE4030

MEP Complete above ceiling

0 22-Feb-14

Light fittings

8 02-Aug-14
6 02-Aug-14

11-Aug-14
09-Aug-14

WP1GE4130

Sprinkler heads

6 03-Aug-14

10-Aug-14

WP1GE4140

FA devices

6 04-Aug-14

11-Aug-14

WP1GE4150

Grills & diffusers

6 04-Aug-14

11-Aug-14

MEP Final Fix


WP1GE4120

Kids 4 All Seasons


Area L
Finishes
WP1GE4200
Masonry

180
180
180
12

26-Dec-13
26-Dec-13
26-Dec-13
26-Dec-13

Data date: 16-Nov-13

05-Aug-14
05-Aug-14
05-Aug-14
09-Jan-14

Curtain wall installed

WP1GE4210

Drywall partitions - Stud & 1 board

12 18-Mar-14

31-Mar-14

WP1GE4220

Drywall partitions - 2nd board, Tape & joint

12 01-Apr-14

14-Apr-14

WP1GE4290

Gypsum ceiling

12 15-Apr-14

28-Apr-14

0 13-Mar-14

Summary Bar
Remaining Work
Milestone

Revised Programme Rev. D

0 13-Mar-14

WP1GE4240

Critical Remaining Work

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-Aug-14
12-Aug-14
12-Aug-14
25-Dec-13

WP1GE4170

MEP
WP1GE1110

Four Seasons Hotel Bahrain

Page 157 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

WP1GE4260

Accent tiles to walls

12 29-Apr-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-May-14

WP1GE4250

Stone to walls ( all WC )

12 13-May-14

26-May-14

WP1GE4310

Accent tile flooring

18 27-May-14

16-Jun-14

WP1GE4270

Moterised mechoshades and blinds

12 17-Jun-14

01-Jul-14

WP1GE4320

Millwork

12 17-Jun-14

01-Jul-14

WP1GE4550

Wall coverings

12 17-Jun-14

01-Jul-14

WP1GE4710

Starfish feature to ceiling

9 03-Jul-14

17-Jul-14

WP1GE4720

Painting & Special finishes

9 03-Jul-14

17-Jul-14

WP1GE4340

Vinyl flooring

6 19-Jul-14

27-Jul-14

WP1GE4560

Carpet

6 30-Jul-14

05-Aug-14

H/L Drainage piping

58 26-Dec-13
12 26-Dec-13

05-Mar-14
09-Jan-14

WP1GE4400

Plumbing piping

12 31-Dec-13

14-Jan-14

WP1GE4410

Fire fighting piping

12 11-Jan-14

23-Jan-14

WP1GE4420

Gravity test for Drainage

3 11-Jan-14

13-Jan-14

WP1GE4430

CHW piping

10 14-Jan-14

25-Jan-14

WP1GE4440

Cable tray & trunking

10 23-Jan-14

03-Feb-14

WP1GE4450

Duct installation

12 26-Jan-14

08-Feb-14

WP1GE4460

Pressure test CHW piping

4 26-Jan-14

29-Jan-14

WP1GE4470

Conduit drops in walls

12 28-Jan-14

10-Feb-14

WP1GE4480

CHW pipe insulation

6 30-Jan-14

05-Feb-14

WP1GE4490

ELV cabling

6 04-Feb-14

10-Feb-14

WP1GE4500

Earthing/Lightning protection

6 04-Feb-14

10-Feb-14

WP1GE4510

FCU installation

4 09-Feb-14

12-Feb-14

WP1GE4520

Installation of fans

4 09-Feb-14

12-Feb-14

WP1GE4530

Small power wiring

10 10-Feb-14

20-Feb-14

WP1GE4540

Cabling

10 22-Feb-14

04-Mar-14

WP1GE4230

MEP Complete above ceiling

0 05-Mar-14

Light fittings

9 03-Jul-14
6 03-Jul-14

17-Jul-14
12-Jul-14

WP1GE6390

Sanitaryware & accessories

9 03-Jul-14

17-Jul-14

WP1GE4360

Sprinkler heads

6 05-Jul-14

13-Jul-14

WP1GE4370

FA devices

6 06-Jul-14

15-Jul-14

WP1GE4380

Grills & diffusers

6 06-Jul-14

15-Jul-14

Activity ID

Activity Name

MEP
WP1GE4390

MEP Final Fix


WP1GE4350

Support Kitchen
Area L
Finishes
WP1GE4570

Masonry

Duration Start

184
184
176
12

30-Nov-13
30-Nov-13
30-Nov-13
30-Nov-13

06-Jul-14
06-Jul-14
24-Jun-14
14-Dec-13

WP1GE4580

Drywall partitions - Stud & 1 board

12 15-Dec-13

28-Dec-13

WP1GE4590

Drywall partitions - 2nd board, Tape & joint

12 29-Dec-13

12-Jan-14

WP1GE4600

MEP Complete above ceiling

WP1GE4630

Ceramic tiles to walls

12 16-Mar-14*

29-Mar-14

WP1GE4660

Gypsum ceiling

18 30-Mar-14

19-Apr-14

WP1GE4620

Kitchen hood

9 20-Apr-14

29-Apr-14

WP1GE4650

Walk in coldroom

9 20-Apr-14

29-Apr-14

WP1GE4680
WP1GE4670

Ceramic flooring
Wall covering - FRP01

12 30-Apr-14
9 14-May-14

13-May-14
24-May-14

WP1GE4700

Kitchen equipement

18 25-May-14

14-Jun-14

0 16-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 158 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

Millwork

18 04-Jun-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
24-Jun-14

Cable tray & trunking

53 15-Dec-13
18 15-Dec-13

15-Feb-14
05-Jan-14

WP1GE1370

Electrical distribution LV

18 16-Dec-13

06-Jan-14

WP1GE1280

Domestic hot & cold piping

18 16-Dec-13

06-Jan-14

WP1GE1270

High level Drainage

12 17-Dec-13

30-Dec-13

WP1GE1290

Fire fighting piping

14 17-Dec-13

02-Jan-14

WP1GE1330

Duct installation

24 17-Dec-13

14-Jan-14

WP1GE1300

Gravity test for Drainage

3 31-Dec-13

04-Jan-14

WP1GE1400

Small power wiring

10 06-Jan-14

16-Jan-14

WP1GE1310

CHW piping

18 07-Jan-14

27-Jan-14

WP1GE1380

FCU installation

14 07-Jan-14

22-Jan-14

WP1GE1420

Pressure test water supply piping

6 07-Jan-14

13-Jan-14

WP1GE1430

LPG piping

18 12-Jan-14

01-Feb-14

WP1GE1390

Installation of Ecology units

20 23-Jan-14

15-Feb-14

WP1GE1340

Pressure test CHW piping

4 28-Jan-14

01-Feb-14

WP1GE1350

CHW pipe insulation

6 02-Feb-14

08-Feb-14

WP1GE1440

Leak test on LPG piping

4 02-Feb-14

05-Feb-14

Light fittings

8 25-Jun-14
6 25-Jun-14

06-Jul-14
03-Jul-14

WP1GE6420

Sprinkler heads

6 26-Jun-14

05-Jul-14

WP1GE6430

FA devices

6 28-Jun-14

06-Jul-14

WP1GE6440

Grills & diffusers

6 28-Jun-14

06-Jul-14

Activity ID

Activity Name

WP1GE4690
MEP
WP1GE1320

MEP Final Fix


WP1GE6400

Mechanical Plantroom
Area L
Finishes
WP1MP240
Masonry

Duration Start

116
116
116
12

16-Nov-13
16-Nov-13
16-Nov-13
16-Nov-13

01-Apr-14
01-Apr-14
01-Apr-14
28-Nov-13

WP1MP280

Painting on walls first coat

9 23-Nov-13

03-Dec-13

WP1MP550

Metal doors & frame

4 18-Mar-14

22-Mar-14

WP1MP340

Painting on walls & floor

9 23-Mar-14

01-Apr-14

HVAC distribution ( Ducting )

92 04-Dec-13
40 04-Dec-13

22-Mar-14
20-Jan-14

WP1MP300

AHU installation

30 04-Dec-13

08-Jan-14

WP1MP370

CHW piping

24 14-Dec-13

11-Jan-14

WP1MP450

Drainage piping

24 14-Dec-13

11-Jan-14

WP1MP490

Fire fighting piping

10 18-Dec-13

29-Dec-13

WP1MP420

Pressure testing CHW piping

4 12-Jan-14

15-Jan-14

WP1MP460

Testing & inspection of drainage piping

4 12-Jan-14

15-Jan-14

WP1MP330

Electrical boards

30 14-Jan-14

17-Feb-14

WP1MP430

Insulate CHW piping

30 16-Jan-14

19-Feb-14

WP1MP470

Connection to equipment

18 16-Jan-14

05-Feb-14

WP1MP320

Installation of fans

12 21-Jan-14

03-Feb-14

WP1MP380

Cable tray & trunking

24 21-Jan-14

17-Feb-14

WP1MP440

Damper installation

10 21-Jan-14

01-Feb-14

WP1MP390

Installation of panels

14 18-Feb-14

05-Mar-14

WP1MP400

Small power cabling & wiring

10 18-Feb-14

01-Mar-14

WP1MP410

LV cabling

14 18-Feb-14

05-Mar-14

WP1MP480

ELV cabling

14 18-Feb-14

05-Mar-14

MEP
WP1MP290

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 159 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

Cable termination

14 06-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
22-Mar-14

MEP Final Fix


WP1MP510

Light fittings

14 02-Mar-14
10 02-Mar-14

17-Mar-14
12-Mar-14

WP1MP540

FA devices

8 06-Mar-14

15-Mar-14

WP1MP520

Sprinkler heads

4 13-Mar-14

17-Mar-14

Activity ID

Activity Name

WP1MP500

Back of House
Area K
Finishes
WP1GE330

Masonry

Duration Start

210
201
185
30

12-Oct-13 A
12-Oct-13 A
16-Nov-13
16-Nov-13

17-Jul-14
01-Jul-14
21-Jun-14
21-Dec-13

WP1GE440

Lifts & mach inst + tests PE 9,10 & 12

58 22-Dec-13*

27-Feb-14

WP1GE5670

Lifts & mach inst + tests PE 11

71 22-Dec-13

15-Mar-14

WP1GE390

Gypsum Partitions

24 29-Dec-13

26-Jan-14

WP1GE5680

Lifts & mach inst + tests SE-09

58 25-Jan-14

01-Apr-14

WP1GE430

Gypsum suspended ceiling

30 26-Jan-14

01-Mar-14

WP1GE480

Install doors & joinery

24 20-Apr-14*

17-May-14

WP1GE5700

ID Fitout PE 9,10 & 12

30 07-May-14

10-Jun-14

WP1GE5620

Vinyl flooring

18 18-May-14

07-Jun-14

WP1GE490

Final Painting

18 01-Jun-14

21-Jun-14

Plumbing piping

68 12-Oct-13 A
20 16-Nov-13

26-Jan-14
09-Dec-13

WP1GE5010

H/L Drainage piping

12 12-Oct-13 A

12-Dec-13

WP1GE5030

Fire fighting piping

12 14-Dec-13

26-Dec-13

WP1GE5040

Gravity test for Drainage

3 14-Dec-13

16-Dec-13

WP1GE5050

CHW piping

10 17-Dec-13

28-Dec-13

WP1GE5060

Cable tray & trunking

10 26-Dec-13

07-Jan-14

WP1GE5070

Duct installation

20 29-Dec-13

21-Jan-14

WP1GE5080

Pressure test CHW piping

4 29-Dec-13

02-Jan-14

WP1GE5090

Conduit drops in walls

12 31-Dec-13

14-Jan-14

WP1GE5100

CHW pipe insulation

10 04-Jan-14

14-Jan-14

WP1GE5110

ELV cabling

6 08-Jan-14

14-Jan-14

WP1GE5120

Earthing/Lightning protection

6 08-Jan-14

14-Jan-14

WP1GE5150

Small power wiring

10 14-Jan-14

25-Jan-14

WP1GE5160

Cabling

10 14-Jan-14

25-Jan-14

WP1GE5130

FCU installation

4 22-Jan-14

26-Jan-14

WP1GE5140

Installation of fans

4 22-Jan-14

26-Jan-14

Light fittings

8 22-Jun-14
6 22-Jun-14

01-Jul-14
28-Jun-14

WP1GE5180

Sprinkler heads

6 23-Jun-14

29-Jun-14

WP1GE5190

FA devices

6 24-Jun-14

01-Jul-14

WP1GE5200

Grills & diffusers

6 24-Jun-14

01-Jul-14

MEP
WP1GE5020

MEP Final Fix


WP1GE5170

Area L
Finishes
WP1GE560

Masonry

198 20-Nov-13
190 20-Nov-13
30 20-Nov-13

17-Jul-14
03-Jul-14
25-Dec-13

WP1GE5690

Lifts & mach inst + tests PE 13

86 22-Dec-13

01-Apr-14

WP1GE620

Gypsum Partitions

24 27-Jan-14

23-Feb-14

WP1GE790

Lifts & mach inst + tests SE 10

70 09-Feb-14

30-Apr-14

WP1GE660

Gypsum suspended ceilings

30 13-Feb-14

19-Mar-14

WP1GE5710

ID Fitout PE 13

30 02-Apr-14

06-May-14

WP1GE710

Install doors & joinery

24 04-May-14

31-May-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 160 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

WP1GE5610

Vinyl flooring

18 01-Jun-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
21-Jun-14

WP1GE720

Final Painting

18 11-Jun-14

03-Jul-14

H/L Drainage piping

49 05-Dec-13
12 05-Dec-13

01-Feb-14
18-Dec-13

WP1GE4820

Plumbing piping

12 10-Dec-13

23-Dec-13

WP1GE4830

Fire fighting piping

12 19-Dec-13

02-Jan-14

WP1GE4840

Gravity test for Drainage

3 19-Dec-13

22-Dec-13

WP1GE4850

CHW piping

10 23-Dec-13

04-Jan-14

WP1GE4860

Cable tray & trunking

10 02-Jan-14

13-Jan-14

WP1GE4870

Duct installation

20 05-Jan-14

27-Jan-14

WP1GE4880

Pressure test CHW piping

4 05-Jan-14

08-Jan-14

WP1GE4890

Conduit drops in walls

12 07-Jan-14

20-Jan-14

WP1GE4900

CHW pipe insulation

10 09-Jan-14

20-Jan-14

WP1GE4910

ELV cabling

6 14-Jan-14

20-Jan-14

WP1GE4920

Earthing/Lightning protection

6 14-Jan-14

20-Jan-14

WP1GE4950

Small power wiring

10 20-Jan-14

30-Jan-14

WP1GE4960

Cabling

10 20-Jan-14

30-Jan-14

WP1GE4930

FCU installation

4 28-Jan-14

01-Feb-14

WP1GE4940

Installation of fans

4 28-Jan-14

01-Feb-14

Light fittings

8 05-Jul-14
6 05-Jul-14

17-Jul-14
13-Jul-14

WP1GE4980

Sprinkler heads

6 06-Jul-14

15-Jul-14

WP1GE4990

FA devices

6 08-Jul-14

17-Jul-14

WP1GE5000

Grills & diffusers

6 08-Jul-14

17-Jul-14

Activity ID

Activity Name

MEP
WP1GE4810

MEP Final Fix


WP1GE4970

Toilets & Showers


Finishes
No DISP
PGLGE2170
Drywall partitions - Stud & 1 board

Duration Start

196
129
129
9

30-Nov-13
04-Feb-14
04-Feb-14
04-Feb-14

27-Jul-14
06-Jul-14
06-Jul-14
13-Feb-14

PGLGE2190

Blockwork to close MEP risers

6 08-Feb-14

13-Feb-14

PGLGE2200

Steel frame for vanity units

6 08-Feb-14

13-Feb-14

PGLGE2210

Stud to block walls

6 15-Feb-14

20-Feb-14

PGLGE2180

Drywall partitions - 2nd board, Tape & joint

9 15-Feb-14

24-Feb-14

PGLGE2220

MEP drops in walls

5 22-Feb-14

26-Feb-14

PGLGE2230

Cement board to walls

12 27-Feb-14

12-Mar-14

PGLGE2240

Gypsum ceiling

18 13-Mar-14

02-Apr-14

PGLGE2250

Waterproofing

9 03-Apr-14

13-Apr-14

PGLGE2260

Waterproofing Test complete

6 14-Apr-14

20-Apr-14

PGLGE2270

Screed floor

4 21-Apr-14

24-Apr-14

PGLGE2280

Acent tiling to walls & floor

24 26-Apr-14

22-May-14

PGLGE2300

Marble vanity tops

PGLGE2290

Install Millwork

PGLGE2310

9 24-May-14

02-Jun-14

15 03-Jun-14

19-Jun-14

Install doors & frames

6 21-Jun-14

26-Jun-14

PGLGE2320

Mirrors

4 28-Jun-14

03-Jul-14

PGLGE2330

Shower Glass doors & partitions

MEP 1st & 2nd Fix


No DISP
PGLBQ1710
Cable Tray and Trunking
PGLBQ1720

Drainage piping

6 28-Jun-14

06-Jul-14

58 30-Nov-13
58 30-Nov-13
6 30-Nov-13*

06-Feb-14
06-Feb-14
07-Dec-13

6 30-Nov-13

07-Dec-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 161 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PGLBQ1730

Electrical Conduiting

4 08-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
11-Dec-13

PGLBQ1740

Lighting & power wiring

8 08-Dec-13

16-Dec-13

PGLBQ1750

Drainage pipe testing

3 08-Dec-13*

10-Dec-13

PGLBQ1760

ELV cabling

PGLBQ1770

Duct Installation

PGLBQ1800

Activity ID

Activity Name

Duration Start

8 08-Dec-13

16-Dec-13

10 11-Dec-13

22-Dec-13

Cable Termination

8 17-Dec-13

25-Dec-13

PGLBQ1780

FP Piping

9 23-Dec-13

02-Jan-14

PGLBQ1860

Flexible ducts and Plenums

5 23-Dec-13

28-Dec-13

PGLBQ1790

FP Pipe drops

5 04-Jan-14

08-Jan-14

PGLBQ1810

CHW Piping

4 04-Jan-14

07-Jan-14

PGLBQ1820

Domestic water Piping

18 04-Jan-14

23-Jan-14

PGLBQ1830

FCU installation

2 08-Jan-14

09-Jan-14

PGLBQ1840

CHW Pipe pressure testing

3 08-Jan-14

11-Jan-14

PGLBQ1850

FP Pipe Pressure Testing

5 09-Jan-14

14-Jan-14

PGLBQ1870

CHW Pipe insulation

9 12-Jan-14

21-Jan-14

PGLBQ1880

Pressure test for Domestic water

6 25-Jan-14

30-Jan-14

PGLBQ1890

Insulation to Domestic water

6 01-Feb-14

06-Feb-14

MEP Finishes
No DISP
PGLBQ1900

Sprinkler installation

18 28-Jun-14
18 28-Jun-14
4 28-Jun-14

27-Jul-14
27-Jul-14
03-Jul-14

PGLBQ1910

Light Fittings

6 05-Jul-14

13-Jul-14

PGLBQ1920

ELV Devices

6 05-Jul-14

13-Jul-14

PGLBQ1930

Wiring Accs.

4 08-Jul-14

13-Jul-14

PGLBQ1940

Sanitaryware & connections

12 08-Jul-14

27-Jul-14

Mens Locker room & Lounge


Area K
Finishes
WP1GE6070
Drywall partitions - Stud & 1 board

241
241
184
18

05-Nov-13 A
05-Nov-13 A
30-Dec-13
30-Dec-13*

14-Aug-14
14-Aug-14
14-Aug-14
20-Jan-14

WP1GE6080

Drywall partitions - 2nd board, Tape & joint

18 14-Jan-14

03-Feb-14

WP1GE6090

Gypsum ceiling

24 18-Jan-14

13-Feb-14

WP1GE6100

MEP Complete above ceiling

WP1GE6140

Curtain wall installed

0 07-Apr-14

WP1GE6110

Accent tiles to walls

24 12-Apr-14*

08-May-14

WP1GE6120

Venetion plaster to walls

18 15-May-14

04-Jun-14

WP1GE6130

Accent Flooring

24 29-May-14

25-Jun-14

WP1GE6170

Glass doors & Screens

12 26-Jun-14

15-Jul-14

WP1GE6150

Millwork

20 26-Jun-14

30-Jul-14

WP1GE6160

Millwork Lockers

18 10-Jul-14

07-Aug-14

WP1GE6180

Install doors

12 31-Jul-14

14-Aug-14

MEP
WP1GE6190

Drainage piping

72 05-Nov-13 A
12 05-Nov-13 A

16-Jan-14
27-Nov-13

WP1GE6200

Plumbing piping

14 21-Nov-13

08-Dec-13

WP1GE6210

Fire fighting piping

14 28-Nov-13

15-Dec-13

WP1GE6220

Gravity test for Drainage

3 28-Nov-13

01-Dec-13

WP1GE6230

CHW piping

10 03-Dec-13

14-Dec-13

WP1GE6240

Cable tray & trunking

10 08-Dec-13

18-Dec-13

WP1GE6250

Duct installation

14 15-Dec-13

30-Dec-13

WP1GE6260

Pressure test CHW piping

4 15-Dec-13

18-Dec-13

0 18-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 162 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

CHW pipe insulation

WP1GE6280

ELV cabling

10 19-Dec-13

30-Dec-13

WP1GE6290

Earthing/Lightning protection

12 19-Dec-13

02-Jan-14

WP1GE6330

Conduit drops in walls

18 19-Dec-13

09-Jan-14

WP1GE6300

Small power wiring

15 30-Dec-13

16-Jan-14

WP1GE6310

Cabling

15 30-Dec-13

16-Jan-14

WP1GE6320

FCU installation

4 31-Dec-13*

05-Jan-14

WP1GE6340

Installation of fans

4 06-Jan-14

09-Jan-14

Light fittings

8 31-Jul-14
6 31-Jul-14

10-Aug-14
07-Aug-14

WP1GE6360

Sprinkler heads

6 02-Aug-14

09-Aug-14

WP1GE6370

FA devices

6 03-Aug-14

10-Aug-14

WP1GE6380

Grills & diffusers

6 03-Aug-14

10-Aug-14

253 03-Oct-13 A

14-Aug-14

131
111
84
12

23-Nov-13
17-Dec-13
05-Jan-14
05-Jan-14

27-Apr-14
27-Apr-14
13-Apr-14
19-Jan-14

Ground level
Facades
Area K
WP Glass
WPLFA230

Split face Stone to womans Hammam ( 6 )

WPLFA260

Split face Stone to Womans Spa ( 8 )

12 01-Feb-14

15-Feb-14

WPLFA150

Split face Stone to Spa reception & womans lounge ( 9 )

12 15-Feb-14

01-Mar-14

WPLFA240

Glass to Womans Hammam ( 6 )

6 24-Feb-14

02-Mar-14

WPLFA270

Glass to Womans Spa ( 8 )

6 24-Mar-14

30-Mar-14

WPLFA160

Glass to Spa reception and womans lounge(9)

6 07-Apr-14

13-Apr-14

111 17-Dec-13
15 17-Dec-13

27-Apr-14
05-Jan-14

No DISP
WPLFA290

CW Frames to Womans Hammam ( 6 )

WPLFA310

CW Frames to Spa reception and womans lounge (9)

15 31-Dec-13

19-Jan-14

WPLFA300

CW Frames to Womans Spa ( 8 )

15 14-Jan-14

01-Feb-14

WPLFA250

Screen Panels to Womans Hammam ( 6 )

12 03-Mar-14

16-Mar-14

WPLFA280

Screen Panels to Womans Spa ( 8 )

12 31-Mar-14

13-Apr-14

WPLFA170

Screen Panels to Spa reception & womans lounge ( 9 )

12 14-Apr-14

27-Apr-14

107 23-Nov-13
72 21-Dec-13
12 21-Dec-13

30-Mar-14
16-Mar-14
05-Jan-14

Area L
WP Glass
WPLFA210

Split face & ST01 Stone to Bar ( 5 )

WPLFA180

Split face Stone to exercise area ( 7 )

12 19-Jan-14

02-Feb-14

WPLFA220

Glass to Bar ( 5 )

15 24-Feb-14

12-Mar-14

WPLFA190

Glass to exercise area ( 7 )

6 10-Mar-14

16-Mar-14

107 23-Nov-13
23 23-Nov-13

30-Mar-14
21-Dec-13

No DISP
WPLFA330

CW Frames to Bar ( 5 )

WPLFA320

CW Frames to exercise area ( 7 )

15 31-Dec-13

19-Jan-14

WPLFA200

Screen Panels to exercise area ( 7 )

12 17-Mar-14

30-Mar-14

Womens Spa & Hammam


Area K
Finishes
WP1GE1450
Masonry

253
253
253
24

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

Drywall partitions - Stud & 1 board

12 16-Dec-13*

29-Dec-13

WP1GE2270

Drywall partitions - 2nd board, Tape & joint

18 30-Dec-13

20-Jan-14

WP1GE2300

Gypsum ceiling

24 09-Jan-14

05-Feb-14

WP1GE2310

MEP Complete above ceiling

WP1GE2290

Venetion plaster to walls

Data date: 16-Nov-13

0 09-Jan-14
24 03-Mar-14

Summary Bar
Remaining Work
Milestone

Revised Programme Rev. D

14-Aug-14
14-Aug-14
14-Aug-14
25-Nov-13

WP1GE2260

Critical Remaining Work

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
25-Dec-13

WP1GE6270

MEP Final Fix


WP1GE6350

6 19-Dec-13

Four Seasons Hotel Bahrain

Page 163 of 180

31-Mar-14
Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

Curtain wall installed

0 03-Mar-14

WP1GE2280

Accent tiles to walls

24 31-Mar-14*

27-Apr-14

WP1GE2340

Wood ceilings

20 28-Apr-14

20-May-14

WP1GE2350

Wood flooring

18 21-May-14

10-Jun-14

WP1GE2320

Accent Flooring

18 11-Jun-14

03-Jul-14

WP1GE2360

Moterised mechoshades and blinds

12 11-Jun-14

24-Jun-14

WP1GE2390

Millwork

24 29-Jun-14

07-Aug-14

WP1GE4760

Glass doors & Screens

6 09-Aug-14

14-Aug-14

Drainage piping

65 06-Oct-13 A
12 10-Oct-13 A

08-Jan-14
25-Nov-13

WP1GE1470

Plumbing piping

14 16-Nov-13

01-Dec-13

WP1GE1480

Fire fighting piping

14 06-Oct-13 A

10-Dec-13

WP1GE1490

Gravity test for Drainage

3 26-Nov-13

28-Nov-13

WP1GE1500

CHW piping

10 30-Nov-13

11-Dec-13

WP1GE1510

Cable tray & trunking

10 05-Dec-13

16-Dec-13

WP1GE1520

Duct installation

14 11-Oct-13 A

24-Dec-13

WP1GE1530

Pressure test CHW piping

4 12-Dec-13

16-Dec-13

WP1GE1540

CHW pipe insulation

6 17-Dec-13

23-Dec-13

WP1GE1550

ELV cabling

10 17-Dec-13

28-Dec-13

WP1GE1560

Earthing/Lightning protection

12 17-Dec-13

30-Dec-13

WP1GE2380

Conduit drops in walls

18 17-Dec-13

07-Jan-14

WP1GE1570

FCU installation

WP1GE1590

Small power wiring

10 28-Dec-13

08-Jan-14

WP1GE1600

Cabling

10 28-Dec-13

08-Jan-14

WP1GE1580

Installation of fans

4 30-Dec-13

04-Jan-14

Light fittings

8 21-May-14
6 21-May-14

29-May-14
27-May-14

WP1GE2410

Sprinkler heads

6 22-May-14

28-May-14

WP1GE2420

FA devices

6 24-May-14

29-May-14

WP1GE2430

Grills & diffusers

6 24-May-14

29-May-14

Install thermal cabins

84 21-Jan-14
84 21-Jan-14
36 21-Jan-14

28-Apr-14
28-Apr-14
03-Mar-14

Finishes to thermal cabins

48 04-Mar-14

28-Apr-14

MEP Final Fix


WP1GE2400

Thermal cabins
Finishes
WP1GE880
WP1GE2880

Reception and Womens terrace


Area K
Finishes
WP1GE1610
Masonry

4 25-Dec-13*

204
204
204
18

26-Nov-13
26-Nov-13
26-Nov-13
26-Nov-13

04-Aug-14
04-Aug-14
04-Aug-14
17-Dec-13

Drywall partitions - Stud & 1 board

12 30-Dec-13

13-Jan-14

WP1GE2450

Drywall partitions - 2nd board, Tape & joint

12 14-Jan-14

27-Jan-14

WP1GE2480

Gypsum ceiling

24 04-Feb-14

03-Mar-14

WP1GE2490

MEP Complete above ceiling

WP1GE2470

Venetion plaster to walls

24 04-Mar-14

31-Mar-14

WP1GE2460

Stone to walls

18 01-Apr-14

21-Apr-14

WP1GE2520

Curtain wall installed

WP1GE2530

Wood ceilings

18 14-Apr-14

04-May-14

WP1GE2510

Accent Flooring

24 05-May-14

01-Jun-14

WP1GE2500

Moterised mechoshades and blinds

12 05-May-14

18-May-14

Data date: 16-Nov-13

0 04-Feb-14

0 14-Apr-14

Summary Bar
Remaining Work
Milestone

Revised Programme Rev. D

29-Dec-13

WP1GE2440

Critical Remaining Work

Print date: 20-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714

WP1GE2330

MEP
WP1GE1460

Four Seasons Hotel Bahrain

Page 164 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

WP1GE2550

Wood flooring

18 02-Jun-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
22-Jun-14

WP1GE2540

Millwork

18 23-Jun-14

20-Jul-14

WP1GE4770

Glass doors & Screens

9 22-Jul-14

04-Aug-14

Activity ID

Activity Name

Duration Start

MEP
WP1GE1620

Drainage piping

52 04-Dec-13
12 04-Dec-13

03-Feb-14
17-Dec-13

WP1GE1630

Plumbing piping

14 09-Dec-13

24-Dec-13

WP1GE1640

Fire fighting piping

14 18-Dec-13

04-Jan-14

WP1GE1650

Gravity test for Drainage

3 18-Dec-13

21-Dec-13

WP1GE1660

CHW piping

10 22-Dec-13

02-Jan-14

WP1GE1670

Cable tray & trunking

10 31-Dec-13

12-Jan-14

WP1GE1680

Duct installation

14 04-Jan-14

19-Jan-14

WP1GE1690

Pressure test CHW piping

4 04-Jan-14

07-Jan-14

WP1GE1700

CHW pipe insulation

6 08-Jan-14

14-Jan-14

WP1GE1710

ELV cabling

10 13-Jan-14

23-Jan-14

WP1GE1720

Earthing/Lightning protection

12 13-Jan-14

26-Jan-14

WP1GE1730

FCU installation

4 20-Jan-14

23-Jan-14

WP1GE1740

Installation of fans

4 20-Jan-14

23-Jan-14

WP1GE1750

Small power wiring

10 23-Jan-14

03-Feb-14

WP1GE1760

Cabling

10 23-Jan-14

03-Feb-14

Light fittings

8 23-Jun-14
6 23-Jun-14

03-Jul-14
29-Jun-14

WP1GE2570

Sprinkler heads

6 24-Jun-14

01-Jul-14

WP1GE2580

FA devices

6 25-Jun-14

03-Jul-14

WP1GE2590

Grills & diffusers

6 25-Jun-14

03-Jul-14

MEP Final Fix


WP1GE2560

Exercise Area
Area L
Finishes
WP1GE2600

Masonry

176
176
176
18

18-Dec-13
18-Dec-13
18-Dec-13
18-Dec-13

19-Jul-14
19-Jul-14
19-Jul-14
08-Jan-14

WP1GE2610

Drywall partitions - Stud & 1 board

12 14-Jan-14

27-Jan-14

WP1GE2620

Drywall partitions - 2nd board, Tape & joint

18 28-Jan-14

17-Feb-14

WP1GE2660

Gypsum ceiling

24 01-Mar-14

27-Mar-14

WP1GE2670

MEP Complete above ceiling

WP1GE2690

Curtain wall installed

WP1GE2640

Venetion plaster to walls

20 31-Mar-14

22-Apr-14

WP1GE2700

Wood ceilings

18 23-Apr-14

13-May-14

WP1GE2650

Moterised mechoshades and blinds

12 07-May-14

20-May-14

WP1GE2710

Wood flooring

18 21-May-14

10-Jun-14

WP1GE2720

Millwork

12 11-Jun-14

24-Jun-14

WP1GE3960

Openable partitions

6 11-Jun-14

17-Jun-14

WP1GE6470

Fabric Acoustic panels to Openable partitions

12 18-Jun-14

03-Jul-14

WP1GE4780

Glass doors & Screens

9 25-Jun-14

08-Jul-14

WP1GE3950

Mirrors

6 10-Jul-14

19-Jul-14
27-Feb-14
12-Jan-14

0 01-Mar-14
0 17-Mar-14

MEP
WP1GE1780

Drainage piping

52 29-Dec-13
12 29-Dec-13

WP1GE1790

Plumbing piping

14 04-Jan-14

19-Jan-14

WP1GE1800

Fire fighting piping

14 13-Jan-14

28-Jan-14

WP1GE1810

Gravity test for Drainage

3 13-Jan-14

15-Jan-14

WP1GE1820

CHW piping

10 16-Jan-14

27-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 165 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

WP1GE1830

Cable tray & trunking

10 26-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
05-Feb-14

WP1GE1840

Duct installation

14 28-Jan-14

12-Feb-14

WP1GE1850

Pressure test CHW piping

4 28-Jan-14

01-Feb-14

WP1GE1860

CHW pipe insulation

6 02-Feb-14

08-Feb-14

WP1GE1870

ELV cabling

10 06-Feb-14

17-Feb-14

WP1GE1880

Earthing/Lightning protection

12 06-Feb-14

19-Feb-14

WP1GE1890

FCU installation

4 13-Feb-14

17-Feb-14

WP1GE1900

Installation of fans

4 13-Feb-14

17-Feb-14

WP1GE1910

Small power wiring

10 17-Feb-14

27-Feb-14

WP1GE1920

Cabling

10 17-Feb-14

27-Feb-14

Light fittings

8 14-May-14
6 14-May-14

22-May-14
20-May-14

WP1GE2740

Sprinkler heads

6 15-May-14

21-May-14

WP1GE2750

FA devices

6 17-May-14

22-May-14

WP1GE2760

Grills & diffusers

6 17-May-14

22-May-14

Activity ID

Activity Name

MEP Final Fix


WP1GE2730

Bar/Arrivals Lounge & Restrooms


Area L
Finishes
WP1GE2770
Masonry

Duration Start

182
182
182
12

02-Jan-14
02-Jan-14
02-Jan-14
02-Jan-14

14-Aug-14
14-Aug-14
14-Aug-14
15-Jan-14

WP1GE2780

Drywall partitions - Stud & 1 board

18 16-Jan-14

05-Feb-14

WP1GE2790

Drywall partitions - 2nd board, Tape & joint

18 10-Feb-14

02-Mar-14

WP1GE2820

MEP Complete above ceiling

WP1GE2830

Curtain wall installed

WP1GE2800

Venetion plaster to walls

18 23-Apr-14

13-May-14

WP1GE2810

Gypsum ceiling

18 04-May-14

24-May-14

WP1GE2840

Wood ceilings

15 18-May-14

03-Jun-14

WP1GE2890

Venetian plaster to ceiling

18 25-May-14

14-Jun-14

WP1GE2850

Moterised mechoshades and blinds

9 04-Jun-14

14-Jun-14

WP1GE2970

Stone flooring

12 15-Jun-14

28-Jun-14

WP1GE2960

Install feature stair structure

9 18-Jun-14

29-Jun-14

WP1GE2860

Wood flooring

12 29-Jun-14

19-Jul-14

WP1GE4800

Finishes to feature stair

24 29-Jun-14

07-Aug-14

WP1GE2870

Millwork

18 20-Jul-14

14-Aug-14

WP1GE2940

Glass walls & door to Whisky room

9 20-Jul-14

03-Aug-14

WP1GE4790

Glass doors & Screens

9 20-Jul-14

03-Aug-14

WP1GE2950

Inlay carpets

6 09-Aug-14

14-Aug-14
03-Mar-14
15-Jan-14

0 04-Mar-14
0

12-Mar-14

MEP
WP1GE1940

Drainage piping

52 02-Jan-14
12 02-Jan-14

WP1GE1950

Plumbing piping

14 07-Jan-14

22-Jan-14

WP1GE1960

Fire fighting piping

14 16-Jan-14

01-Feb-14

WP1GE1970

Gravity test for Drainage

3 16-Jan-14

19-Jan-14

WP1GE1980

CHW piping

10 20-Jan-14

30-Jan-14

WP1GE1990

Cable tray & trunking

10 29-Jan-14

09-Feb-14

WP1GE2000

Duct installation

14 01-Feb-14

16-Feb-14

WP1GE2010

Pressure test CHW piping

4 01-Feb-14

04-Feb-14

WP1GE2020

CHW pipe insulation

6 05-Feb-14

11-Feb-14

WP1GE2030

ELV cabling

10 10-Feb-14

20-Feb-14

WP1GE2040

Earthing/Lightning protection

12 10-Feb-14

23-Feb-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 166 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

WP1GE2050

FCU installation

4 17-Feb-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
20-Feb-14

WP1GE2060

Installation of fans

4 17-Feb-14

20-Feb-14

WP1GE2070

Small power wiring

10 20-Feb-14

03-Mar-14

WP1GE2080

Cabling

10 20-Feb-14

03-Mar-14

Light fittings

8 04-Jun-14
6 04-Jun-14

12-Jun-14
10-Jun-14

WP1GE2910

Sprinkler heads

6 05-Jun-14

11-Jun-14

WP1GE2920

FA devices

6 07-Jun-14

12-Jun-14

WP1GE2930

Grills & diffusers

6 07-Jun-14

12-Jun-14

Activity ID

Activity Name

MEP Final Fix


WP1GE2900

Back of House
Area K
Finishes
WPLGE330

Masonry

Duration Start

249
237
237
24

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

10-Aug-14
22-Jul-14
22-Jul-14
07-Dec-13

WPLGE390

Gypsum Partitions

24 14-Jan-14

10-Feb-14

WPLGE420

Gypsum suspended ceiling

30 11-Feb-14

17-Mar-14

WPLGE480

Install doors & joinery

12 07-Jun-14*

19-Jun-14

WPLGE1100

Vinyl floor

9 21-Jun-14

01-Jul-14

WPLGE490

Final Painting

12 03-Jul-14

22-Jul-14

H/L Drainage piping

48 08-Dec-13
12 08-Dec-13

02-Feb-14
21-Dec-13

WP1GE5220

Plumbing piping

12 12-Dec-13

25-Dec-13

WP1GE5230

Fire fighting piping

12 22-Dec-13

05-Jan-14

WP1GE5240

Gravity test for Drainage

3 22-Dec-13

24-Dec-13

WP1GE5250

CHW piping

10 25-Dec-13

06-Jan-14

WP1GE5260

Cable tray & trunking

10 05-Jan-14

15-Jan-14

WP1GE5270

Duct installation

12 07-Jan-14

20-Jan-14

WP1GE5280

Pressure test CHW piping

4 07-Jan-14

11-Jan-14

WP1GE5290

Conduit drops in walls

12 09-Jan-14

22-Jan-14

WP1GE5300

CHW pipe insulation

6 12-Jan-14

18-Jan-14

WP1GE5310

ELV cabling

6 16-Jan-14

22-Jan-14

WP1GE5320

Earthing/Lightning protection

6 16-Jan-14

22-Jan-14

WP1GE5330

FCU installation

4 21-Jan-14

25-Jan-14

WP1GE5340

Installation of fans

4 21-Jan-14

25-Jan-14

WP1GE5350

Small power wiring

10 22-Jan-14

02-Feb-14

WP1GE5360

Cabling

10 22-Jan-14

02-Feb-14

Light fittings

8 18-Mar-14
6 18-Mar-14

26-Mar-14
24-Mar-14

WP1GE5380

Sprinkler heads

6 19-Mar-14

25-Mar-14

WP1GE5390

FA devices

6 20-Mar-14

26-Mar-14

WP1GE5400

Grills & diffusers

6 20-Mar-14

26-Mar-14

199 08-Dec-13
199 08-Dec-13
18 08-Dec-13

10-Aug-14
10-Aug-14
28-Dec-13

MEP
WP1GE5210

MEP Final Fix


WP1GE5370

Area L
Finishes
WPLGE1090

Masonry

WPLGE840

Gypsum Partitions

24 11-Feb-14

10-Mar-14

WPLGE860

Gypsum suspended ceiling

24 11-Mar-14

07-Apr-14

WPLGE900

Install doors & joinery

12 21-Jun-14

06-Jul-14

WPLGE1050

Vinyl Flooring

9 08-Jul-14

22-Jul-14

WPLGE910

Final Painting

12 24-Jul-14

10-Aug-14

48 29-Dec-13

23-Feb-14

MEP
Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 167 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

WP1GE5410

H/L Drainage piping

12 29-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
12-Jan-14

WP1GE5420

Plumbing piping

12 04-Jan-14

16-Jan-14

WP1GE5430

Fire fighting piping

12 13-Jan-14

26-Jan-14

WP1GE5440

Gravity test for Drainage

3 13-Jan-14

15-Jan-14

WP1GE5450

CHW piping

10 16-Jan-14

27-Jan-14

WP1GE5460

Cable tray & trunking

10 26-Jan-14

05-Feb-14

WP1GE5470

Duct installation

12 28-Jan-14

10-Feb-14

WP1GE5480

Pressure test CHW piping

WP1GE5490

Conduit drops in walls

WP1GE5500

Activity ID

Activity Name

Duration Start

4 28-Jan-14

01-Feb-14

12 30-Jan-14

12-Feb-14

CHW pipe insulation

6 02-Feb-14

08-Feb-14

WP1GE5510

ELV cabling

6 06-Feb-14

12-Feb-14

WP1GE5520

Earthing/Lightning protection

6 06-Feb-14

12-Feb-14

WP1GE5530

FCU installation

4 11-Feb-14

15-Feb-14

WP1GE5540

Installation of fans

4 11-Feb-14

15-Feb-14

WP1GE5550

Small power wiring

10 12-Feb-14

23-Feb-14

WP1GE5560

Cabling

10 12-Feb-14

23-Feb-14

Light fittings

8 24-Jul-14
6 24-Jul-14

04-Aug-14
02-Aug-14

WP1GE5580

Sprinkler heads

6 26-Jul-14

03-Aug-14

WP1GE5590

FA devices

6 27-Jul-14

04-Aug-14

WP1GE5600

Grills & diffusers

6 27-Jul-14

04-Aug-14

MEP Final Fix


WP1GE5570

Womens Locker rooms & Lounge


Area K
Finishes
WP1GE5930
Drywall partitions - Stud & 1 board

241
241
207
12

05-Nov-13 A
05-Nov-13 A
01-Dec-13
01-Dec-13*

18 26-Dec-13

14-Aug-14
14-Aug-14
13-Aug-14
15-Dec-13

WP1GE5940

Drywall partitions - 2nd board, Tape & joint

WP1GE5960

MEP Complete above ceiling

16-Jan-14

WP1GE5950

Gypsum ceiling

WP1GE6020

Curtain wall installed

WP1GE5990

Venetion plaster to walls

18 14-May-14

03-Jun-14

WP1GE5980

Accent tiles to walls

20 04-Jun-14

26-Jun-14

WP1GE6000

Accent Flooring

20 21-Jun-14

20-Jul-14

WP1GE6050

Millwork

18 06-Jul-14

04-Aug-14

WP1GE6040

Millwork Lockers

12 17-Jul-14

04-Aug-14

WP1GE6010

Glass doors & Screens

12 27-Jul-14

12-Aug-14

WP1GE6060

Install doors

9 27-Jul-14

09-Aug-14

WP1GE6450

Mirrors

4 10-Aug-14

13-Aug-14
11-Jan-14
27-Nov-13

0 11-Jan-14
24 18-Jan-14

13-Feb-14

0 31-Mar-14

MEP
WP1GE5720

Drainage piping

67 05-Nov-13 A
12 05-Nov-13 A

WP1GE5730

Plumbing piping

14 21-Nov-13

08-Dec-13

WP1GE5750

Gravity test for Drainage

3 28-Nov-13

01-Dec-13

WP1GE5760

CHW piping

10 03-Dec-13

14-Dec-13

WP1GE5770

Cable tray & trunking

10 08-Dec-13

18-Dec-13

WP1GE5740

Fire fighting piping

14 11-Dec-13

26-Dec-13

WP1GE5780

Duct installation

14 15-Dec-13

30-Dec-13

WP1GE5790

Pressure test CHW piping

4 15-Dec-13

18-Dec-13

WP1GE5800

CHW pipe insulation

6 19-Dec-13

25-Dec-13

WP1GE5810

ELV cabling

10 19-Dec-13

30-Dec-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 168 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

WP1GE5820

Earthing/Lightning protection

12 19-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
02-Jan-14

WP1GE5830

Conduit drops in walls

18 19-Dec-13

09-Jan-14

WP1GE5840

Small power wiring

10 30-Dec-13

11-Jan-14

WP1GE5850

Cabling

10 30-Dec-13

11-Jan-14

WP1GE5860

FCU installation

4 31-Dec-13*

05-Jan-14

WP1GE5870

Installation of fans

4 06-Jan-14

09-Jan-14

Light fittings

8 05-Aug-14
6 05-Aug-14

14-Aug-14
12-Aug-14

WP1GE5890

Sprinkler heads

6 07-Aug-14

13-Aug-14

WP1GE5900

FA devices

6 09-Aug-14

14-Aug-14

WP1GE5910

Grills & diffusers

6 09-Aug-14

14-Aug-14

Activity ID

Activity Name

MEP Final Fix


WP1GE5880

Toilets & Showers


Finishes
No DISP
PGLGE2130
Drywall partitions - Stud & 1 board

Duration Start

217
192
192
9

16-Nov-13
16-Dec-13
16-Dec-13
16-Dec-13

10-Aug-14
10-Aug-14
10-Aug-14
25-Dec-13

PGLGE2140

Drywall partitions - 2nd board, Tape & joint

9 26-Dec-13

06-Jan-14

PGLGE1970

Blockwork to close MEP risers

6 12-Jan-14

18-Jan-14

PGLGE1980

Steel frame for vanity units

6 12-Jan-14

18-Jan-14

PGLGE1990

Stud to block walls

6 15-Jan-14

21-Jan-14

PGLGE2000

MEP drops in walls

5 22-Jan-14

27-Jan-14

PGLGE2010

Cement board to walls

9 28-Jan-14

06-Feb-14

PGLGE2030

Gypsum ceiling

18 08-Feb-14

27-Feb-14

PGLGE2050

Waterproofing

6 01-Mar-14

06-Mar-14

PGLGE2060

Waterproofing Test complete

4 08-Mar-14

11-Mar-14

PGLGE2070

Screed floor

4 12-Mar-14

16-Mar-14

PGLGE2080

Acent tiling to walls & floor

12 14-Jun-14

26-Jun-14

PGLGE2090

Install Millwork

15 28-Jun-14

22-Jul-14

PGLGE2150

Marble vanity tops

6 28-Jun-14

06-Jul-14

PGLGE2100

Install doors & frames

6 24-Jul-14

02-Aug-14

PGLGE2120

Mirrors

4 03-Aug-14

07-Aug-14

PGLGE2160

Shower Glass doors & partitions

6 03-Aug-14

10-Aug-14

35 30-Nov-13
35 30-Nov-13
6 30-Nov-13*

11-Jan-14
11-Jan-14
07-Dec-13

MEP 1st & 2nd Fix


No DISP
PGLBQ1470
Cable Tray and Trunking
PGLBQ1480

Drainage piping

6 30-Nov-13

07-Dec-13

PGLBQ1490

Electrical Conduiting

4 08-Dec-13

11-Dec-13

PGLBQ1500

Lighting & power wiring

8 08-Dec-13

16-Dec-13

PGLBQ1510

Drainage pipe testing

3 08-Dec-13*

10-Dec-13

PGLBQ1520

ELV cabling

8 08-Dec-13

16-Dec-13

PGLBQ1530

Duct Installation

10 11-Dec-13

22-Dec-13

PGLBQ1540

FP Piping

4 12-Dec-13

16-Dec-13

PGLBQ1550

FP Pipe drops

5 17-Dec-13

22-Dec-13

PGLBQ1560

Cable Termination

8 17-Dec-13

25-Dec-13

PGLBQ1570

CHW Piping

4 17-Dec-13

21-Dec-13

PGLBQ1580

Domestic water Piping

12 17-Dec-13

30-Dec-13

PGLBQ1590

FCU installation

2 22-Dec-13

23-Dec-13

PGLBQ1600

CHW Pipe pressure testing

3 22-Dec-13

24-Dec-13

PGLBQ1610

FP Pipe Pressure Testing

5 23-Dec-13

28-Dec-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 169 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

PGLBQ1620

Flexible ducts and Plenums

5 23-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
28-Dec-13

PGLBQ1630

CHW Pipe insulation

9 25-Dec-13

05-Jan-14

PGLBQ1640

Pressure test for Domestic water

3 31-Dec-13

04-Jan-14

PGLBQ1650

Insulation to Domestic water

Activity ID

Activity Name

MEP Finishes
No DISP
PGLBQ1660

Sprinkler installation

Duration Start

6 05-Jan-14

11-Jan-14

217 16-Nov-13
217 16-Nov-13
4 16-Nov-13

10-Aug-14
10-Aug-14
19-Nov-13

PGLBQ1680

Light Fittings

6 20-Nov-13

26-Nov-13

PGLBQ1690

ELV Devices

6 20-Nov-13

26-Nov-13

PGLBQ1700

Wiring Accs.

4 23-Nov-13

26-Nov-13

PGLBQ1670

Sanitaryware & connections

Facades
Area L
WP Glass
WP1FA130
No DISP
WP1FA340
Cut Reastaurant
Area L
Finishes
WP1GE2980

12 24-Jul-14
227 13-Oct-13 A

+01 @ +16.00

10-Aug-14
02-Aug-14

Glass to Restaurant ( 5 )

92
92
15
15

23-Nov-13
23-Nov-13
24-Feb-14
24-Feb-14

12-Mar-14
12-Mar-14
12-Mar-14
12-Mar-14

CW Frames to Restaurant ( 5 )

23 23-Nov-13
23 23-Nov-13

21-Dec-13
21-Dec-13

Masonry

199
199
199
12

30-Nov-13
30-Nov-13
30-Nov-13
30-Nov-13*

02-Aug-14
02-Aug-14
02-Aug-14
14-Dec-13

WP1GE2990

Drywall partitions - Stud & 1 board

12 25-Dec-13

09-Jan-14

WP1GE3000

Drywall partitions - 2nd board, Tape & joint

18 09-Jan-14

29-Jan-14

WP1GE3030

Gypsum ceiling

24 01-Feb-14

27-Feb-14

WP1GE3040

MEP Complete above ceiling

WP1GE3010

Venetion plaster to walls

WP1GE3070

Curtain wall installed

WP1GE3050

Venetian plaster to ceiling

18 22-Mar-14

10-Apr-14

WP1GE6480

Openable partitions

12 29-Mar-14

10-Apr-14

WP1GE3080

Wood Panels to openable partitions

12 12-Apr-14

24-Apr-14

WP1GE3090

Moterised mechoshades and blinds

12 12-Apr-14

24-Apr-14

WP1GE3020

Glass walls & door to Wine room

9 12-Apr-14

21-Apr-14

WP1GE3100

Stone flooring to wine room

12 22-Apr-14

05-May-14

WP1GE6490

Stone flooring - Arrivals lounge & Restrooms

18 06-May-14

26-May-14

WP1GE3110

Wood flooring

12 20-May-14

02-Jun-14

WP1GE6500

Stone walls - Restrooms

12 27-May-14

09-Jun-14

WP1GE3120

Millwork

18 03-Jun-14

23-Jun-14

WP1GE6510

Vanity units - Restrooms

6 10-Jun-14

16-Jun-14

WP1GE6540

Wood panelling - Arrivals Lounge

18 24-Jun-14

22-Jul-14

WP1GE6530

Mirrors - Restrooms

6 03-Jul-14

12-Jul-14

WP1GE3130

Inlay carpets

0 01-Feb-14
18 01-Mar-14
0

20-Mar-14
12-Mar-14

6 24-Jul-14

02-Aug-14

Drainage piping

181 30-Nov-13
12 30-Nov-13

01-Jul-14
14-Dec-13

WP1GE2110

Plumbing piping

14 05-Dec-13

21-Dec-13

WP1GE2130

Gravity test for Drainage

3 15-Dec-13

17-Dec-13

WP1GE2250

Fire fighting piping

14 15-Dec-13

30-Dec-13

WP1GE2140

CHW piping

10 18-Dec-13

29-Dec-13

WP1GE2150

Cable tray & trunking

10 28-Dec-13

08-Jan-14

MEP
WP1GE2100

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 170 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Duration Start

Duct installation

WP1GE2170

Pressure test CHW piping

4 30-Dec-13

04-Jan-14

WP1GE2180

CHW pipe insulation

6 05-Jan-14

11-Jan-14

WP1GE2190

ELV cabling

10 09-Jan-14

20-Jan-14

WP1GE2200

Earthing/Lightning protection

12 09-Jan-14

22-Jan-14

WP1GE2210

FCU installation

4 16-Jan-14

20-Jan-14

WP1GE2220

Installation of fans

4 16-Jan-14

20-Jan-14

WP1GE2230

Small power wiring

10 20-Jan-14

30-Jan-14

WP1GE2240

Cabling

10 20-Jan-14

30-Jan-14

WP1GE6520

Sanitaryware & commections

12 17-Jun-14

01-Jul-14

100
70
70
18

13-Oct-13 A
16-Oct-13 A
16-Oct-13 A
16-Nov-13

23-Feb-14
19-Jan-14
19-Jan-14
07-Dec-13

WP1SW140

Screed with slope

18 16-Oct-13 A

03-Dec-13

WP1SW160

Insulation

18 08-Dec-13

28-Dec-13

WP1SW170

Pavers & gravel protection

18 29-Dec-13

19-Jan-14
23-Feb-14
23-Feb-14
04-Dec-13

Curbs/Parapets for Mech. louvers & Skylight

94 13-Oct-13 A
94 13-Oct-13 A
12 13-Oct-13 A

WP1SW260

Screed with slope

18 04-Dec-13

24-Dec-13

WP1SW270

Waterproofing

18 22-Dec-13

12-Jan-14

WP1SW280

Insulation

18 13-Jan-14

02-Feb-14

WP1SW290

Pavers & gravel protection

Area L
No DISP
WP1SW320

+2 @ + 21.3
Roof
Area L
No DISP
WP1SW300
WP1SW180

Pads & Conduit for Feature Lighting

18 03-Feb-14

23-Feb-14

145 04-Dec-13

22-May-14

145
145
145
12

04-Dec-13
04-Dec-13
04-Dec-13
04-Dec-13

22-May-14
22-May-14
22-May-14
17-Dec-13

18 03-May-14

22-May-14

CARPARK

269 03-Oct-13 A

02-Sep-14

Lower level

244 03-Oct-13 A

03-Aug-14

Screed

244
75
75
75

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

03-Aug-14
31-Dec-13
31-Dec-13
31-Dec-13

Painting to walls & Ceilings

203 03-Oct-13 A
203 03-Oct-13 A
55 26-Nov-13

03-Aug-14
03-Aug-14
30-Jan-14

Carpark
Civil Works
No DISP
RL1PK760
Finishes
No DISP
RL1PK770

Standing seam roof

RL1PK780

Masonry

30 03-Oct-13 A

01-Feb-14

RL1PK790

Finishes

60 08-Jan-14

18-Mar-14

RL1PK800

Doors installation

18 26-Feb-14

18-Mar-14

P+2SW300

Traffic Coating

42 19-Mar-14

06-May-14

RL1PK810

Parkings curbs

18 07-May-14

27-May-14

RL1PK820

Parkings space lines

18 21-May-14

10-Jun-14

RL1PK1030

Signage

36 11-Jun-14

03-Aug-14

188 03-Oct-13 A
188 03-Oct-13 A
48 03-Oct-13 A

18-May-14
18-May-14
28-Dec-13

MEP Finishes
No DISP
RL1PK830

Drainage Piping

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 171 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
15-Jan-14

WP1GE2160

Roof/Terrace @ +16
Area K
No DISP
WP1SW150
Waterproofing

14 30-Dec-13

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

RL1PK840

Floor Drains

45 05-Oct-13 A

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
31-Dec-13

RL1PK850

Drainage Pipe Testing

24 29-Dec-13

26-Jan-14

RL1PK860

FP piping

42 29-Dec-13

16-Feb-14

RL1PK870

Cable Tray / Trunking

24 27-Jan-14

23-Feb-14

RL1PK900

FCU installation

12 01-Feb-14

13-Feb-14

RL1PK920

CHW Pipe & Valve package connection to FCU

24 15-Feb-14

13-Mar-14

RL1PK930

Parking Exhaust Fan / Jet Fan Installation

30 15-Feb-14

20-Mar-14

RL1PK880

FP Pipe pressure testing

18 17-Feb-14

09-Mar-14

RL1PK890

Electrical Conduiting

24 24-Feb-14

23-Mar-14

RL1PK910

Cabling / Wire Pulling

24 10-Mar-14

06-Apr-14

RL1PK980

CHW Pipe insulation

18 13-Mar-14

02-Apr-14

RL1PK990

CHW Pipe Pressure Testing

12 15-Mar-14

27-Mar-14

RL1PK940

FHC / FE installation

24 19-Mar-14

15-Apr-14

RL1PK950

Sprinkler installation

24 19-Mar-14

15-Apr-14

RL1PK1000

MFSD installation

12 22-Mar-14

03-Apr-14

RL1PK960

Lighting Panels

12 07-Apr-14

20-Apr-14

RL1PK970

Light Fittings

12 07-Apr-14

20-Apr-14

RL1PK1040

CO2 Monitoring Panels & terminations

36 07-Apr-14

18-May-14

RL1PK1010

ELV Devices

12 21-Apr-14

04-May-14

269 03-Oct-13 A

02-Sep-14

Screed

269
75
75
75

02-Sep-14
16-Feb-14
16-Feb-14
16-Feb-14

Painting to walls & Ceilings

189 13-Jan-14
189 13-Jan-14
75 13-Jan-14

02-Sep-14
02-Sep-14
09-Apr-14

Activity ID

Activity Name

Mezzanine level
Carpark
Civil Works
No DISP
RL1PK730
Finishes
No DISP
RL1PK150

Duration Start

03-Oct-13 A
19-Nov-13
19-Nov-13
19-Nov-13

RL1PK220

Masonry

30 17-Feb-14

23-Mar-14

RL1PK180

Finishes

60 10-Apr-14

18-Jun-14

RL1PK170

Doors installation

18 29-May-14

18-Jun-14

P+2SW240

Traffic Coating

42 29-May-14

26-Jul-14

RL1PK100

Parkings curbs

18 27-Jul-14

19-Aug-14

RL1PK1020

Signage

30 27-Jul-14

02-Sep-14

RL1PK750

Parkings space lines

18 13-Aug-14

02-Sep-14

239 03-Oct-13 A
239 03-Oct-13 A
48 03-Oct-13 A

26-Jul-14
26-Jul-14
24-Dec-13

MEP Finishes
No DISP
RL1PK470

Drainage Piping

RL1PK480

Drainage Pipe Testing

24 25-Dec-13

22-Jan-14

RL1PK580

Floor Drains

45 25-Dec-13

16-Feb-14

RL1PK630

FP piping

42 25-Dec-13

12-Feb-14

RL1PK570

Cable Tray / Trunking

24 23-Jan-14

19-Feb-14

RL1PK640

FP Pipe pressure testing

18 13-Feb-14

05-Mar-14

RL1PK590

Electrical Conduiting

24 20-Feb-14

19-Mar-14

RL1PK600

Cabling / Wire Pulling

24 06-Mar-14

02-Apr-14

RL1PK490

FCU installation

12 10-Apr-14

23-Apr-14

RL1PK500

CHW Pipe & Valve package connection to FCU

24 24-Apr-14

21-May-14

RL1PK520

Parking Exhaust Fan / Jet Fan Installation

30 24-Apr-14

28-May-14

RL1PK510

CHW Pipe insulation

18 21-May-14

10-Jun-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 172 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

RL1PK550

CHW Pipe Pressure Testing

12 22-May-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
04-Jun-14

RL1PK530

MFSD installation

12 29-May-14

11-Jun-14

RL1PK540

Lighting Panels

12 19-Jun-14

05-Jul-14

RL1PK560

FHC / FE installation

24 19-Jun-14

26-Jul-14

RL1PK610

Light Fittings

12 19-Jun-14

05-Jul-14

RL1PK650

Sprinkler installation

24 19-Jun-14

26-Jul-14

RL1PK620

ELV Devices

12 06-Jul-14

26-Jul-14

Activity ID

Activity Name

Ground level
Civil Works
Civil Works
No DISP
RL1PK680
RL1PK710
Carpark
Finishes
No DISP
RL1PK690

Knee walls & parapets


Roads

Waterproofing

Duration Start

241 03-Oct-13 A

30-Jul-14

175
175
175
36

03-May-14
03-May-14
03-May-14
10-Dec-13

03-Oct-13 A
03-Oct-13 A
03-Oct-13 A
03-Oct-13 A

24 06-Apr-14
158
158
158
45

03-May-14

16-Jan-14
16-Jan-14
16-Jan-14
16-Jan-14

30-Jul-14
30-Jul-14
30-Jul-14
09-Mar-14

RL1PK700

Backfill

48 09-Feb-14

05-Apr-14

RL1PK410

Finishes incl traffic coating

48 04-May-14

28-Jun-14

RL1PK720

Shade structures

30 04-May-14

07-Jun-14

RL1PK420

White line painting

EXTERNAL WORKS
General
External Works
Zone 2
No DISP
EEWGE320

Stone to retaining walls

20 26-Jun-14

30-Jul-14

180 12-Oct-13 A

15-Jun-14

183 12-Oct-13 A

15-Jun-14

183
32
32
32

15-Jun-14
23-Dec-13
23-Dec-13
22-Dec-13

12-Oct-13 A
16-Nov-13
16-Nov-13
16-Nov-13

EEWGE1110

Armour coat cable for external lighting

EEWGE1480

Slab-on-grade at East Podium

6 16-Nov-13

21-Nov-13

15 23-Nov-13

EEWGE1850

Handover to TLT

0 23-Dec-13

09-Dec-13

Zone 3
SAN & Storm M/H or pipe
EEWGE1690
Pipe connection to CB-5 from CB-4B

45 12-Oct-13 A
25 16-Nov-13
2 16-Nov-13

06-Jan-14
14-Dec-13
17-Nov-13

EEWGE1710

Excavate & Install SAN.MH-10

3 19-Nov-13*

21-Nov-13

EEWGE1670

Excavate & install CB-16, CB-17 & Pipe run CB-15 => C...

6 26-Nov-13

02-Dec-13

EEWGE1680

Test & B/F CB-16, CB-17 & Pipe run CB-15 => CB-16

5 03-Dec-13

08-Dec-13

EEWGE1720

Excavate & install CB-6B, CB-6A & Pipe run to CB6

6 03-Dec-13

09-Dec-13

EEWGE1730

Test & B/F CB-6B, CB-6A & Pipe run to CB6

No DISP
EEWGE1270

RC Wall 23 - Phase 2

4 10-Dec-13

14-Dec-13

45 12-Oct-13 A
6 16-Nov-13

06-Jan-14
21-Nov-13

EEWGE1890

Place & grout Capstones

9 12-Oct-13 A

19-Nov-13

EEWGE1740

Waterproof & Backfill W23 & W24 - Phase 2 to formation

5 23-Nov-13

27-Nov-13

EEWGE1900

RC Wall 25

6 23-Nov-13

28-Nov-13

EEWGE1830

Stone cladding to retaining walls

33 28-Nov-13

05-Jan-14

EEWGE1770

Install Precast road kerbs

24 30-Nov-13*

26-Dec-13

EEWGE1910

Waterproof & B/F Wall 25

6 30-Nov-13

05-Dec-13

EEWGE1750

Place Quay wall to Jetty area

6 03-Nov-13 A

09-Dec-13

EEWGE1790

Excavate & install Fire Hydrant main @ 4.365

6 09-Dec-13

15-Dec-13

EEWGE1800

Install Armour coat cable for B1 lignting ( FFL - 60 cm )

6 16-Dec-13

22-Dec-13

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 173 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

EEWGE1810

Install Armour coat cable for SP lignting ( FFL - 60 cm )

6 16-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
22-Dec-13

EEWGE1820

Excavate & install Fire Hydrant branch to Hotel @ 4.365

6 16-Dec-13*

22-Dec-13

EEWGE1780

Final Backfill to Capstones

9 23-Dec-13

01-Jan-14

EEWGE1840

TLT Handover

Activity ID

Activity Name

Zone 4
SAN & Storm M/H or pipe
EEWGE2000
Install STMH-1B & CB-19 & line between

Duration Start

0 06-Jan-14
74 16-Nov-13
33 21-Nov-13
6 21-Nov-13

09-Feb-14
29-Dec-13
27-Nov-13

EEWGE2020

Test & B/F STMH-1B & CB-19 & line between

6 28-Nov-13

04-Dec-13

EEWGE2030

Install CB-20 & line to CB-19

6 28-Nov-13

04-Dec-13

EEWGE2040

Test & B/Fl CB-20 & line to CB-19

6 05-Dec-13

11-Dec-13

EEWGE2060

Install Sanitary Lift Station

9 05-Dec-13

15-Dec-13

EEWGE2090

Install Sanitary Grease Trap

6 14-Dec-13

19-Dec-13

EEWGE2160

Install SAN.MH-6 & PVC pipe => SAN.MH-7

6 14-Dec-13

19-Dec-13

EEWGE2170

Install SAN.MH-7 & Line to Lift station

6 16-Dec-13

22-Dec-13

EEWGE2200

250 PVC pipe San Bldg Connection => SAN.MH-7 (@ 2.0)

5 19-Dec-13

24-Dec-13

EEWGE2150

Test Sanitary Grease Trap & SAN.MH-6 & B/F

6 21-Dec-13

26-Dec-13

EEWGE2190

Test & B/F SAN.MH-7 & Line to Lift station

4 25-Dec-13

29-Dec-13

29 16-Nov-13
5 16-Nov-13

18-Dec-13
20-Nov-13

MEP
EEWGE1970

Dewater for STMH-1B & CB-19 & line between

EEWGE2010

Dewater for CB-20

5 21-Nov-13

26-Nov-13

EEWGE2050

Dewater for Sanitary Lift Station & SAN.MH-7

5 27-Nov-13

02-Dec-13

EEWGE2080

Dewater for Sanitary Grease Trap & SAN.MH-6 & Line =...

9 03-Dec-13

12-Dec-13

EEWGE2180

Dewater for San Line Bldg => SAN.MH-7

5 14-Dec-13

18-Dec-13

74 16-Nov-13
0

09-Feb-14
16-Nov-13

No DISP
EEWGE2070

Sanitary Grease Trap on site

EEWGE1990

Start delivery of Manholes

0 17-Nov-13

EEWGE1960

Place & grout Capstones

15 20-Nov-13*

07-Dec-13

EEWGE2100

Install Fire Hydrant Line & branches

12 05-Dec-13

18-Dec-13

EEWGE2110

Backfill & haunching for road kerbs

6 19-Dec-13

25-Dec-13

EEWGE2120

Install road kerbs

9 26-Dec-13

05-Jan-14

EEWGE2130

Backfill to formation- road kerbs => capston

6 02-Jan-14

08-Jan-14

EEWGE2140

Install Amourflex cable for external lighting

6 06-Jan-14

12-Jan-14

EEWGE930

TLT Works ( Durn to be confirmed )

24 13-Jan-14

09-Feb-14

Zone 5
SAN & Storm M/H or pipe
EEWGE2590
Install CB-25 & 25m of line to CB-51

50 16-Nov-13
37 16-Nov-13
4 16-Nov-13

13-Jan-14
28-Dec-13
19-Nov-13

EEWGE2600

Install CB-26 & Line => CB-25

4 20-Nov-13

24-Nov-13

EEWGE2660

Install 10m of line CB-26 => CB-29

4 25-Nov-13

28-Nov-13

EEWGE2670

Install 6m of line CB-26 => CB-28

4 30-Nov-13

03-Dec-13

EEWGE2680

Install CB-27A & Line => CB-26

7 04-Dec-13

11-Dec-13

EEWGE2690

Install CB-27 & Line => CB-27A

5 12-Dec-13

17-Dec-13

EEWGE2700

Install CB-30 & Line => CB-27A

5 18-Dec-13

23-Dec-13

EEWGE2720

25mm LPG pipe to fire feature & test

4 24-Dec-13

28-Dec-13
13-Jan-14

U/G Storm & San revisions frozen

50 16-Nov-13
0 16-Nov-13*

EEWGE2610

Walls W20 & W19

36 25-Nov-13

05-Jan-14

EEWGE2630

Place & grout Capstones

15 08-Dec-13*

24-Dec-13

EEWGE2620

Manholes for power supply

9 09-Dec-13

18-Dec-13

No DISP
EEWGE2540

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 174 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

EEWGE2640

Place & grout Key wall blocks

6 15-Dec-13*

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
21-Dec-13

EEWGE2710

Backfill to formation against capstones

9 19-Dec-13

29-Dec-13

EEWGE2730

Conduit for external lighting

9 23-Dec-13

01-Jan-14

EEWGE2650

Waterproof W20 & W19 & B/f to formation

12 30-Dec-13

12-Jan-14

EEWGE770

TLT Handover

0 13-Jan-14

Reduce level

105 16-Nov-13
55 08-Dec-13
6 08-Dec-13*

Activity ID

Activity Name

Zone 6
Family Pool
EEWGE2750

Duration Start

17-Mar-14
09-Feb-14
14-Dec-13

EEWGE2740

Remove Quay wall blocks

3 15-Dec-13

17-Dec-13

EEWGE2760

Geotextile and backfill to formation

9 18-Dec-13

28-Dec-13

EEWGE3220

AHM piping - gutter intake

9 22-Dec-13

31-Dec-13

EEWGE2770
EEWGE2780

Blockwork for first waffle adj Quay wall


Pre-cast capping stone

6 25-Dec-13
4 25-Dec-13

31-Dec-13
29-Dec-13

EEWGE3230

AHM piping for all pool sections

12 29-Dec-13

11-Jan-14

EEWGE2790

Form, rebar & cast 1st section of Infinity egde base

6 01-Jan-14

07-Jan-14

EEWGE2810

Form, rebar & cast 3 rd section of Infinity egde base

6 01-Jan-14

07-Jan-14

EEWGE2960

Form, rebar & cast 5th section of Infinity egde base

6 01-Jan-14

07-Jan-14

EEWGE3240

Test & Backfill AHM piping for all pool sections

6 05-Jan-14

11-Jan-14

EEWGE2800

Form, rebar & cast 2nd section of Infinity egde base

6 08-Jan-14

14-Jan-14

EEWGE2820

Form, rebar & cast 4 th section of Infinity egde base

6 08-Jan-14

14-Jan-14

EEWGE2830

Blockwork for Waffle slabs for Section 1

4 08-Jan-14

12-Jan-14

EEWGE2850

Blockwork for Waffle slabs for Section 3

4 08-Jan-14

12-Jan-14

EEWGE2970

Blockwork for Waffle slabs for Section 5

4 08-Jan-14

12-Jan-14

EEWGE3250

AHM electrical conduits for all pool sections

9 08-Jan-14

18-Jan-14

EEWGE3320

LPG Pipe in Pool

6 12-Jan-14

18-Jan-14

EEWGE2920

Backfill between blockwork for Section 1

4 13-Jan-14

16-Jan-14

EEWGE2930
EEWGE2980

Backfill between blockwork for Section 3


Backfill between blockwork for Section 5

4 13-Jan-14
4 13-Jan-14

16-Jan-14
16-Jan-14

EEWGE2840

Blockwork for Waffle slabs for Section 2

4 15-Jan-14

19-Jan-14

EEWGE2860

Blockwork for Waffle slabs for Section 4

4 15-Jan-14

19-Jan-14

EEWGE2900

Rebar & Cast pool slab - Section 3

6 18-Jan-14

23-Jan-14

EEWGE2990

Rebar & Cast pool slab - Section 5

12 18-Jan-14

30-Jan-14

EEWGE2880

Rebar & Cast pool slab - Section 1

12 19-Jan-14

01-Feb-14

EEWGE2940

Backfill between blockwork for Section 2

6 20-Jan-14

26-Jan-14

EEWGE2950

Backfill between blockwork for Section 4

6 20-Jan-14

26-Jan-14

EEWGE2890

Rebar & Cast pool slab - Section 2

12 27-Jan-14

09-Feb-14

EEWGE2910

Rebar & Cast pool slab - Section 4

6 27-Jan-14

02-Feb-14

105 16-Nov-13
4 16-Nov-13

17-Mar-14
19-Nov-13

12 20-Nov-13

03-Dec-13

MEP
EEWGE3180

Excavate Al Mahroos Pipe Trench ( 1.96 ) Phase 1 to K4...

EEWGE3190

Al Mahroos Pipes to K4AS corner - Phase 1

EEWGE4720

Excavate Al Mahroos Pipe Trench ( 1.96 ) Phase 2 to Fa...

EEWGE4730

Al Mahroos Pipes to Family Pool - Phase 2

EEWGE3030

6 23-Nov-13

28-Nov-13

18 26-Nov-13

16-Dec-13

SAN.MH-3 & line to SAN.MH-2

9 17-Dec-13

26-Dec-13

EEWGE3040

SAN PVC line to service cabana

4 23-Dec-13

26-Dec-13

EEWGE3050

SAN PVC line to Surge Tank

4 23-Dec-13

26-Dec-13

EEWGE3020

SAN.MH-3 & 20 M of PVC line

6 28-Dec-13

02-Jan-14

EEWGE3090

Line to CB-37 => CB-36

6 28-Dec-13

02-Jan-14

EEWGE4740

SAN.MH-3 & 30 m of PVC line => SAN.MH-4

6 28-Dec-13

02-Jan-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 175 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

EEWGE3080

CB-37 & Line to CB-38

6 04-Jan-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
09-Jan-14

EEWGE3210

San PVC line to Outdoor Shower

6 04-Jan-14

09-Jan-14

EEWGE3060

CB-38 & line to CB-39

6 11-Jan-14

16-Jan-14

EEWGE3010

CB-39 & line to trench drain

6 14-Jan-14

20-Jan-14

EEWGE3310

LPG Pipe @ 4.00

6 18-Jan-14

23-Jan-14

EEWGE3100

CB-40 & line to CB-41

9 19-Jan-14

28-Jan-14

EEWGE3110

SAN.MH-2 & line to SAN.MH-1

6 22-Jan-14*

28-Jan-14

EEWGE3120

SAN.MH-1 & line to SAN.MH-13B

9 29-Jan-14

08-Feb-14

EEWGE3140

CB-41 & line to CB-42A

6 29-Jan-14

04-Feb-14

EEWGE3350

Install & Test FH,Water & DCW DHW & DHWR

12 15-Feb-14

27-Feb-14

EEWGE3380

Electric conduits - Manhole to Manhole

9 08-Mar-14

17-Mar-14

45 21-Jan-14
12 21-Jan-14

13-Mar-14
03-Feb-14

Activity ID

Activity Name

Civils
EEWGE610

Walls & Steps by Family pool

Duration Start

EEWGE3330

Walls & Steps by Family pool _ WP & B/F

9 04-Feb-14

13-Feb-14

EEWGE3340

MEP Trench for FH,Water & DCW DHW & DHWR

6 08-Feb-14

13-Feb-14

EEWGE3360

B/F MEP Trench for FH,Water & DCW DHW & DHWR

6 01-Mar-14

06-Mar-14

EEWGE3370

Electric Manholes ( 8 No. )

12 01-Mar-14

13-Mar-14

36 15-Dec-13
6 15-Dec-13

25-Jan-14
21-Dec-13

Poolside changing rooms


EEWGE3300
Underground MEP Services
EEWGE3260

RC slabs

6 22-Dec-13

28-Dec-13

EEWGE3270

RC Walls

6 29-Dec-13

04-Jan-14

EEWGE3280

RC Roof

6 05-Jan-14

11-Jan-14

EEWGE3290

Cure & Strip scaffold

12 12-Jan-14

25-Jan-14

Family Pool surge Tank


EEWGE3150
Dewater for Surge Tank ( base at 0.82 )

24 16-Nov-13
6 16-Nov-13

12-Dec-13
21-Nov-13

12 23-Nov-13

05-Dec-13

6 07-Dec-13

12-Dec-13

106 16-Nov-13
82 14-Dec-13
12 14-Dec-13

18-Mar-14
18-Mar-14
26-Dec-13

9 28-Dec-13

06-Jan-14

EEWGE3160

Construct Surge Tank

EEWGE3170

External waterproofing & backfill Surge tank

Zone 7
MEP
EEWGE4830

Run from STMH - 14 to CB -37 complete

EEWGE4840

Install Capstones

EEWGE3130

SAN.MH-13B & line to SAN.MH-13

12 09-Feb-14

22-Feb-14

EEWGE4850

Run from STMH - 13 to SAN.MH -14 complete

12 23-Feb-14

08-Mar-14

EEWGE4860

Run from CB - 47 to CB - 48A complete

9 23-Feb-14

04-Mar-14

EEWGE4870

Run from STMH-12 to CB-46A complete

12 05-Mar-14

18-Mar-14

EEWGE4880

Run from SAN.MH-15 to SAN.MH-17 complete

9 09-Mar-14

18-Mar-14

Walls W29 & W29E

60 16-Nov-13
24 16-Nov-13

23-Jan-14
12-Dec-13

EEWGE4900

Walls W26 & W27

24 30-Nov-13

26-Dec-13

EEWGE4910

Wall W30

24 14-Dec-13

09-Jan-14

EEWGE4920

Waterproof & B/F Wall W30

12 11-Jan-14

23-Jan-14

21 16-Nov-13
6 16-Nov-13

09-Dec-13
21-Nov-13

Civils
EEWGE4890

Kids deck Surge Tank


EEWGE4930
Dewater for Surge Tank ( base at 1.5 )
EEWGE4940

Construct Surge Tank

9 23-Nov-13

02-Dec-13

EEWGE4950

External waterproofing & backfill Surge Tank

6 03-Dec-13

09-Dec-13

Access requirement
EEWGE4960
West Podium Facade complete

0 16-Nov-13
0

16-Nov-13
16-Nov-13

No DISP
EEWGE4970

0 16-Nov-13
0

16-Nov-13
16-Nov-13

TLT Handover

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 176 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain


Activity ID

Activity Name

Zone9
SAN & Storm M/H or pipe
EEWGE4750
Install STMH- 4 & SAN.MH - 5 & line between
EEWGE4770

Install CB - 28 and line => STMH- 4

EEWGE4780

Install Conduit manholes

EEWGE4790
EEWGE4800

Duration Start

165 20-Nov-13
30 15-Feb-14
12 15-Feb-14
6 01-Mar-14

06-Mar-14
13-Mar-14

Install fire hydrant

6 08-Mar-14

13-Mar-14

Install LPG line

6 15-Mar-14

20-Mar-14

MEP
EEWGE4760

Dewater for SAN.MH-5A & line => SAN.MH - 4

5 09-Feb-14
5 09-Feb-14

13-Feb-14
13-Feb-14

Civils
EEWGE2370

Founation slab for W14,7,10,15,11,21 &22 ( GCO Phas...

69 20-Nov-13
9 20-Nov-13*

08-Feb-14
30-Nov-13

Walls to CJ W14,7,10,15,11,21 &22 ( GCO Phase 3)

EEWGE2390

Waterproof & B/F to W14,7,10,15,11,21 &22 ( GCO Ph...

EEWGE2400
EEWGE2410

9 01-Dec-13

10-Dec-13

12 11-Dec-13

24-Dec-13

Foundation slabs for W6,12,13 & 8 ( GCO Phase 5 )

9 25-Dec-13

04-Jan-14

Walls to W6,7,10,12,13,8,11, ( GCO Phase 6 )

6 05-Jan-14

11-Jan-14

EEWGE2420

Ground floor slab ( GCO Phase 7 )

9 12-Jan-14

21-Jan-14

EEWGE2430

Walls & pararet W6,14,12,13,15,8 ( GCO Phase 8 )

6 22-Jan-14

28-Jan-14

EEWGE2440

Walls W18 & W16 ( GCO Phase 9 )

9 29-Jan-14

08-Feb-14

Access requirement
EEWGE4810
Access required to South side of Tower

0 31-May-14
0

31-May-14
31-May-14

No DISP
EEWGE4820

0 31-May-14
0

31-May-14
31-May-14

182 16-Nov-13
99 16-Nov-13
4 16-Nov-13

15-Jun-14
10-Mar-14
19-Nov-13

TLT Handover

Zone 13
Super Cabana - 6
EEWGE3390
Backfill to formation
EEWGE3400

MEP below slab sevices into Cabana

9 20-Nov-13

30-Nov-13

EEWGE3410

Blinding

2 01-Dec-13

02-Dec-13

EEWGE3420

Waterproofing

2 05-Dec-13

07-Dec-13

EEWGE3430

Form, rebar & pour slab + MEP conduit & clearence

4 08-Dec-13

11-Dec-13

EEWGE3440

Privicy wall (W31) foundation

4 08-Dec-13

11-Dec-13

EEWGE3450

Rebar, shutter & pour walls W02, W03, W04 & columns

5 12-Dec-13

17-Dec-13

EEWGE3460

Privicy Wall (W31)

4 12-Dec-13

16-Dec-13

EEWGE3470

Strip wall & column shutters

2 18-Dec-13

19-Dec-13

EEWGE3480

Scaffold & formwork for roof slab & edge beams

4 21-Dec-13

24-Dec-13

EEWGE3490

Rebar & pour roof slab & edge beams

4 25-Dec-13

29-Dec-13

EEWGE3500

Strip scaff & formwork - roof slab & edge beams

4 06-Jan-14

09-Jan-14

EEWGE3510

Blockwork

6 11-Jan-14

16-Jan-14

EEWGE3520

MEP 1st fix

12 18-Jan-14

30-Jan-14

EEWGE3530

Plaster to walls & ceiling

9 29-Jan-14

08-Feb-14

EEWGE3540

Roofing

9 03-Feb-14

12-Feb-14

EEWGE3550

Ceilings

6 11-Feb-14

17-Feb-14

EEWGE3560

External Jura stone

9 13-Feb-14

23-Feb-14

EEWGE3570

Floor finishes

6 18-Feb-14

24-Feb-14

EEWGE3580

Glazed screens & window

6 25-Feb-14

03-Mar-14

EEWGE3590

Wall finishes

6 04-Mar-14

10-Mar-14

EEWGE3600

Millwork

4 04-Mar-14

08-Mar-14

99 28-Nov-13
4 28-Nov-13

23-Mar-14
02-Dec-13

9 03-Dec-13

12-Dec-13

Super Cabana - 1
EEWGE3610
Backfill to formation
EEWGE3620

MEP below slab sevices into Cabana

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 177 of 180

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
31-May-14
20-Mar-14
27-Feb-14

12 01-Mar-14

EEWGE2380

Four Seasons Hotel Bahrain

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

EEWGE3630

Blinding

2 14-Dec-13

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
15-Dec-13

EEWGE3640

Waterproofing

2 18-Dec-13

19-Dec-13

EEWGE3650

Form, rebar & pour slab + MEP conduit & clearence

4 21-Dec-13

24-Dec-13

EEWGE3660

Privicy wall (W31) foundation

4 21-Dec-13

24-Dec-13

EEWGE3670

Rebar, shutter & pour walls W02, W03, W04 & columns

5 25-Dec-13

30-Dec-13

EEWGE3680

Privicy Wall (W31)

4 25-Dec-13

29-Dec-13

EEWGE3690

Strip wall & column shutters

2 31-Dec-13

01-Jan-14

EEWGE3700

Scaffold & formwork for roof slab & edge beams

4 02-Jan-14

06-Jan-14

EEWGE3710

Rebar & pour roof slab & edge beams

4 07-Jan-14

11-Jan-14

EEWGE3720

Strip scaff & formwork - roof slab & edge beams

4 19-Jan-14

22-Jan-14

EEWGE3730

Blockwork

6 23-Jan-14

29-Jan-14

EEWGE3740

MEP 1st fix

12 30-Jan-14

12-Feb-14

EEWGE3750

Plaster to walls & ceiling

9 11-Feb-14

20-Feb-14

EEWGE3760

Roofing

9 16-Feb-14

25-Feb-14

EEWGE3770

Ceilings

6 24-Feb-14

02-Mar-14

EEWGE3780

External Jura stone

9 26-Feb-14

08-Mar-14

EEWGE3790

Floor finishes

6 03-Mar-14

09-Mar-14

EEWGE3800

Glazed screens & window

6 10-Mar-14

16-Mar-14

EEWGE3810

Wall finishes

6 17-Mar-14

23-Mar-14

EEWGE3820

Millwork

Activity ID

Activity Name

Super Cabana - 2
EEWGE3830
Backfill to formation

Duration Start

4 17-Mar-14

20-Mar-14

99 16-Feb-14
4 16-Feb-14*

10-Jun-14
19-Feb-14

EEWGE3840

MEP below slab sevices into Cabana

9 20-Feb-14

02-Mar-14

EEWGE3850

Blinding

2 03-Mar-14

04-Mar-14

EEWGE3860

Waterproofing

2 08-Mar-14

09-Mar-14

EEWGE3870

Form, rebar & pour slab + MEP conduit & clearence

4 10-Mar-14

13-Mar-14

EEWGE3880

Privicy wall (W31) foundation

4 10-Mar-14

13-Mar-14

EEWGE3890

Rebar, shutter & pour walls W02, W03, W04 & columns

5 15-Mar-14

19-Mar-14

EEWGE3900

Privicy Wall (W31)

4 15-Mar-14

18-Mar-14

EEWGE3910

Strip wall & column shutters

2 20-Mar-14

22-Mar-14

EEWGE3920

Scaffold & formwork for roof slab & edge beams

4 23-Mar-14

26-Mar-14

EEWGE3930

Rebar & pour roof slab & edge beams

4 27-Mar-14

31-Mar-14

EEWGE3940

Strip scaff & formwork - roof slab & edge beams

4 08-Apr-14

12-Apr-14

EEWGE3950

Blockwork

6 13-Apr-14

19-Apr-14

EEWGE3960

MEP 1st fix

12 20-Apr-14

03-May-14

EEWGE3970

Plaster to walls & ceiling

9 01-May-14

11-May-14

EEWGE3980

Roofing

9 06-May-14

15-May-14

EEWGE3990

Ceilings

6 14-May-14

20-May-14

EEWGE4000

External Jura stone

9 17-May-14

26-May-14

EEWGE4010

Floor finishes

6 21-May-14

27-May-14

EEWGE4020

Glazed screens & window

6 28-May-14

03-Jun-14

EEWGE4030

Wall finishes

6 04-Jun-14

10-Jun-14

EEWGE4040

Millwork

Super Cabana - 3
EEWGE4050
Backfill to formation

4 04-Jun-14

08-Jun-14

99 16-Feb-14
4 16-Feb-14*

10-Jun-14
19-Feb-14

EEWGE4060

MEP below slab sevices into Cabana

9 20-Feb-14

02-Mar-14

EEWGE4070

Blinding

2 03-Mar-14

04-Mar-14

EEWGE4080

Waterproofing

2 08-Mar-14

09-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 178 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

EEWGE4090

Form, rebar & pour slab + MEP conduit & clearence

4 10-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
13-Mar-14

EEWGE4100

Privicy wall (W31) foundation

4 10-Mar-14

13-Mar-14

EEWGE4110

Rebar, shutter & pour walls W02, W03, W04 & columns

5 15-Mar-14

19-Mar-14

EEWGE4120

Privicy Wall (W31)

4 15-Mar-14

18-Mar-14

EEWGE4130

Strip wall & column shutters

2 20-Mar-14

22-Mar-14

EEWGE4140

Scaffold & formwork for roof slab & edge beams

4 23-Mar-14

26-Mar-14

EEWGE4150

Rebar & pour roof slab & edge beams

4 27-Mar-14

31-Mar-14

EEWGE4160

Strip scaff & formwork - roof slab & edge beams

4 08-Apr-14

12-Apr-14

EEWGE4170

Blockwork

6 13-Apr-14

19-Apr-14

EEWGE4180

MEP 1st fix

12 20-Apr-14

03-May-14

EEWGE4190

Plaster to walls & ceiling

9 01-May-14

11-May-14

EEWGE4200

Roofing

9 06-May-14

15-May-14

EEWGE4210

Ceilings

6 14-May-14

20-May-14

EEWGE4220

External Jura stone

9 17-May-14

26-May-14

EEWGE4230

Floor finishes

6 21-May-14

27-May-14

EEWGE4240

Glazed screens & window

6 28-May-14

03-Jun-14

EEWGE4250

Wall finishes

6 04-Jun-14

10-Jun-14

EEWGE4260

Millwork

4 04-Jun-14

08-Jun-14

99 20-Feb-14
4 20-Feb-14

15-Jun-14
24-Feb-14

Activity ID

Activity Name

Super Cabana - 4
EEWGE4270
Backfill to formation

Duration Start

EEWGE4280

MEP below slab sevices into Cabana

9 25-Feb-14

06-Mar-14

EEWGE4290

Blinding

2 08-Mar-14

09-Mar-14

EEWGE4300

Waterproofing

2 12-Mar-14

13-Mar-14

EEWGE4310

Form, rebar & pour slab + MEP conduit & clearence

4 15-Mar-14

18-Mar-14

EEWGE4320

Privicy wall (W31) foundation

4 15-Mar-14

18-Mar-14

EEWGE4330

Rebar, shutter & pour walls W02, W03, W04 & columns

5 19-Mar-14

24-Mar-14

EEWGE4340

Privicy Wall (W31)

4 19-Mar-14

23-Mar-14

EEWGE4350

Strip wall & column shutters

2 25-Mar-14

26-Mar-14

EEWGE4360

Scaffold & formwork for roof slab & edge beams

4 27-Mar-14

31-Mar-14

EEWGE4370

Rebar & pour roof slab & edge beams

4 01-Apr-14

05-Apr-14

EEWGE4380

Strip scaff & formwork - roof slab & edge beams

4 13-Apr-14

16-Apr-14

EEWGE4390

Blockwork

6 17-Apr-14

23-Apr-14

EEWGE4400

MEP 1st fix

12 24-Apr-14

07-May-14

EEWGE4410

Plaster to walls & ceiling

9 06-May-14

15-May-14

EEWGE4420

Roofing

9 11-May-14

20-May-14

EEWGE4430

Ceilings

6 19-May-14

25-May-14

EEWGE4440

External Jura stone

9 21-May-14

31-May-14

EEWGE4450

Floor finishes

6 26-May-14

01-Jun-14

EEWGE4460

Glazed screens & window

6 02-Jun-14

08-Jun-14

EEWGE4470

Wall finishes

6 09-Jun-14

15-Jun-14

EEWGE4480

Millwork

4 09-Jun-14

12-Jun-14

94 20-Feb-14
4 20-Feb-14

09-Jun-14
24-Feb-14

Super Canaba - 5
EEWGE4490
Backfill to formation
EEWGE4500

MEP below slab sevices into Cabana

9 25-Feb-14

06-Mar-14

EEWGE4510

Blinding

2 08-Mar-14

09-Mar-14

EEWGE4520

Waterproofing

2 12-Mar-14

13-Mar-14

EEWGE4530

Form, rebar & pour slab + MEP conduit & clearence

4 15-Mar-14

18-Mar-14

EEWGE4540

Privicy wall (W31) foundation

4 15-Mar-14

18-Mar-14

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 179 of 180

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved

Four Seasons Hotel Bahrain

Four Seasons Hotel Bahrain

Print date: 20-Nov-13

Revised Programme Rev. D

Data date: 16-Nov-13

EEWGE4550

Rebar, shutter & pour walls W02, W03, W04 & columns

5 19-Mar-14

2013
2014
Early Finish
September
October
November
December
January
February
March
April
May
June
July
August September
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 0714
24-Mar-14

EEWGE4560

Privicy Wall (W31)

4 19-Mar-14

23-Mar-14

EEWGE4570

Strip wall & column shutters

2 25-Mar-14

26-Mar-14

EEWGE4580

Scaffold & formwork for roof slab & edge beams

4 27-Mar-14

31-Mar-14

EEWGE4590

Rebar & pour roof slab & edge beams

4 01-Apr-14

05-Apr-14

EEWGE4600

Strip scaff & formwork - roof slab & edge beams

4 13-Apr-14

16-Apr-14

EEWGE4610

Blockwork

6 17-Apr-14

23-Apr-14

EEWGE4620

MEP 1st fix

10 24-Apr-14

05-May-14

EEWGE4630

Plaster to walls & ceiling

9 04-May-14

13-May-14

EEWGE4640

Roofing

8 08-May-14

17-May-14

EEWGE4650

Ceilings

6 15-May-14

21-May-14

EEWGE4660

External Jura stone

8 18-May-14

26-May-14

EEWGE4670

Floor finishes

6 22-May-14

28-May-14

EEWGE4680

Glazed screens & window

4 29-May-14

02-Jun-14

EEWGE4690

Wall finishes

6 03-Jun-14

09-Jun-14

EEWGE4700

Millwork

4 03-Jun-14

07-Jun-14

TLT Handover

0 09-Jun-14
0

09-Jun-14
09-Jun-14

External Works

46 01-Feb-14

26-Mar-14

Connection
General
No DISP
GEWCO110

46 01-Feb-14
46 01-Feb-14
46 01-Feb-14
0

26-Mar-14
26-Mar-14
26-Mar-14
01-Feb-14

Activity ID

Activity Name

No DISP
EEWGE4710

GEWCO170

Rain water pipe connection


Telecommunication & Low Voltage connection

Duration Start

Summary Bar
Remaining Work
Critical Remaining Work
Milestone

Page 180 of 180

26-Mar-14

Date
19-May-13
02-Jul-13
05-Oct-13
19-Nov-13

Revision
A - Issued for Review
B - General Revisions
C - General Revisions
D - General Revisions

Checked
AO'F
AO'F
AO'F
AO'F

Approved