BUILDING CONSTRUCTION I
COURSE CODE: BLD103
TABLE OF CONTENTS WEEK 1: BUILDING COMPONENTS (1.1) Building components (1.2) Major building components (a) Foundation (b) Floor (c) Wall (d) Door (e) Windows (f) Roof PRELIMINARY SITE ACTIVITIES (2.1) Site activities that precede Actual building construction (2.2) Provision of facilities of on site SITE ORGANISATION AND LAYOUT (2.3) Site layout and organization SETTING OUT OF BUILDING (2.4) Setting out of building EXCAVATION (3.1) Method of Excavation (3.2) Tools used in manual Excavation (3.3) Equipment used in mechanical Excavation EARTHWORK SUPPORT (3.4) Method of Earth (3.5) Foundation FOUNDATION (3.6) Importance of foundation to building (3.7) Types of foundation soil (3.8) Simple calculation of the area of concrete foundation TYPES OF FOUNDATION (3.9) Types of foundation and their application TYPES OF FOUNDATION (CONTINUED) METHODS OF REINFORCEMENT IN SUBSTRUCTURES (3.10) Methods of reinforcement in Substructures CONSTRUCTION OF FOUNDATION
WEEK2:
WEEK3:
WEEKK4:
WEEK5:
WEEK6:
WEEK7:
WEEK 8:
WEEK 9: WEEK10:
WEEK11:
3 (3.11) Method of construction of foundation WEEK12: DAMP PROOFING (4.1) Rising damp and seepage of ground water in building (4.2) Damp proof course (DPC) and damp proof membrane (DPM) (4.3) Function of damp proof courses MATERIALS USED FOR DAMP PROOF COURSE (4.6) Materials used for damp proof course BASEMENT TANKING (4.4) Tanking in basement work HARDCORE (4.7) Hardcore layer (4.8) Blinding (4.9) Termite Treatment
WEEK13:
WEEK14:
WEEK15:
Foundation
The function of the foundation is to transmit the load from the building finally to the soil. This, it must do without excessive settlement and compression of the supporting soil layer.
Functions of Foundations
Foundation provides suitable support and stability for building Transmits to the ground all the loads that come on the building over a sufficient area of subsoil Prevents the failure of the building or uneven settlement.
The selection of foundation types is influenced by The type of building The nature of the loading The site condition Foundations are of many types but the more common ones include Strip foundation Pad foundation Pile foundation Raft foundation
Fig.1.1.Strip foundation
Floor
Floor can be defined as the horizontal structure which carries imposed and live loads in a building and divides a building into storeys. It plays an important role in a building.
The most common material used for the construction of floors that will meet the requirement of building regulations and local bye-laws are concrete and wood.
Wall
This is usually the vertical continuous part of a building which encloses or protects the building or divides the building into rooms and compartments. It is made up of blocks, concrete, mortar, stones, metals etc. types of walls include: Internal, External, Buttress, Sleeper, party, parapet partition and cavity walls.
Door
A door is a movable barrier placed across an opening in a building that provides access into the building or between spaces within the building.
Windows
Windows provide natural light and ventilation to the interior of a building while excluding rain and insects. Windows are usually made of timber, steel. But other materials such as plastics (uPVC) and aluminium are also popular. Each material has its own advantages and disadvantages.
Roof
This is the topmost covering in a building. It is done during the finishing of a building. It prevents a lot of sound (minimizing incoming sound), dust, wind and rain and also it helps the occupants cover their privacy.
10 Stability: a roof is constructed to support the dead load of the roof structure and its covering, insulation and internal finishes, snow loads and pressure of suction due to wind without undue deflection or distortion. The dead load can be calculated from the unit weight of materials with which it is covered, varying from the continuous impermeable layer of asphalt covering that can be laid horizontal to exclude rain, to the small units of clay tiles that are laid overlapping down slopes so that rain runs rapidly to the covers.
Weather Resistance: A roof excludes rain through the materials with which it is covered; varying from the continuous impermeable layer of asphalt converging that can be horizontal to exclude rain to the small units of clay titles that are laid overlapping down slop so that rain runs rapidly to the covers.
Durability: The durability of a roof is dependant largely on the ability of the roof covering to exclude rain and snow. Persistent penetration of water into the roof structure may cause or encourage decay of timber, corrosion of steel or disintegration of concrete.
Fire Safety: The requirements for control of spread of fire in schedule of the building regulations for dwelling houses limit roof construction relative to the proximity of boundaries of the site of the building by reference to the materials of roof covering.
Thermal Resistance: The materials of roof structures and roof covering are generally poor insulators against the transfer of heat. It is usually necessary to use some materials which are good insulator. Examples of such materials include light weight boards, mats or loose materials. This is to provide insulation requirements to meet the building regulation for the insulation of roofs of dwellings is a standard value of 0.25 where the SAP ceiling is over 60.
Sound Insulation: The resistance of a roof to the penetration of airborne sound is not generally considered unless the building is close to a busy airport. The mass of the materials of a roof is the main constructions in the reduction of airborne sound.
Test Questions i. List the basic building components. ii. State the functional requirements of four building components.
11
Site Clearance
The preliminary works on a construction project site usually begin after the sit facilities have been set up. Clearing the site is essential. First, the vegetation such as bushes and shrubs should be removed. The roots of trees and bushes must be dug out and cleared away. Site clearance also may involve the demolition of existing buildings . demolition is a skilled occupation and should be tackled by experts in that area. The top soil should also be removed up to a depth of at least 150mm to remove any plant life and decaying vegetable. The presence of vegetation and decaying materials means that the top soil is easily compressible and cannot support building foundation. Top soil is however valuable as a top dressing for gardens and may be disposed of in this manner
The site needs to be cleared of rocks and boulders in the area where the building will be set out. If they are too large, then the boulders or rocks must be broken into smaller pieces and taken away.
Site clearance is done by a combination of manual and mechanical means. The method adopted will be determined by the overall economics which may be influenced by the scale of development ant consideration for any adjacent buildings.
12
Temporary services: These include the provision of such services as water supply and, electricity supply. Water is required on construction site for drinking and for the works. Where the site is close to the public water mains, the water can be connected directly from the public water mains to the site. The stand pipe should be located close to where the mixing of concrete and mortar will take place. Where the site is far from the public water mains, water can be supplied to the site with use of water tankers. The water can be stored in reservoir provided on the site for such a purpose especially for the works.
An electrical supply for power tools, electricity can be supplied from the mains or a petrol generator.
A telephone line should be provided which is secured so that it can only be used for official or authorized calls.
Temporary access road: This should be provided to the site for the purpose of providing access to vehicular traffic that will be bringing men and materials to the site. The access should be constructed so that vehicles can enter the site in all weather. The access road can become part of the permanent site services in the final design.
Site accommodation A site should have an office and sheds for the workers on site to change their clothes and to take rest on site during breaks from work and also have their meals. Site accommodation and similar facilities provided on a site depends on the number of people that are working on the site.
Units of accommodation come usually in two forms Sectional timber huts Mobile caravans or cabins
13 Sectional timber huts are prefabricated for ease of dismantling and assembly to facilitate the reuse on other sites. Huts of this nature should be designed, constructed and maintained with the same care as permanent buildings to ensure their use for many years on a number of different construction site. A well designed sectional hut should permit the addition of more bays to increase the modular size by length and/or width. The anticipated use of each hut will govern the construction and facilities required. Offices need to be weatherproof, provided with artificial lighting, equipped with furniture that might be required on the site. Similar basic construction can be used for other units of accommodation such as meal rooms, and toilets should be provided and equipped with the basic facilities.
Caravan and mobile cabins are available in a wide variety of sizes, styles, and application. The construction is most times of a plywood clad timber frame suitably insulated and decorated. They are usually made of modular system so that by using special connection unit any reasonable plan size and shape is possible. The caravan and cabin are fully equipped with all the necessary furniture light and heating units. The toilets can be connected to site services or be self contained.
Material Storage: The type of storage facilities required on a construction site for any material depends on the following factors Durability ie whether it will need protection from the elements Vulnerability to damage Vulnerability to theft
Cement, plaster and lime supplied in bags form require a dry store free from draughts which can introduce moist air and cause air set of the material. These materials should not be stored on the site for long period of time on site; therefore provision should be made for rotational use so that the material being used comes from older stock.
Aggregates such as sand and gravels require a clean firm base to ensure that foreign matter is not included when extracting materials from the base of the stock pile. Different materials and grades should be kept separated so that the ultimate mix batches are consistent in quality and texture. Care must be taken to ensure that the stock piles are not used as refuse dump. The moisture content of the aggregates should also be taken into consideration if it is exposed to the
14 elements like rain, so as to allow for it in deciding the water cement ratio of the mix.
Bricks and blocks should be stacked in stable piles on a level and well drained surface in a position where double handling is reduced to a minimum. Facing bricks and other coloured bricks should be covered with tarpaulin to protect them from being discoloured by the weather elements. Blocks should be stacked in such a way as to allow for air to flow freely through the stack.
Timber absorbs water easily. To prevent undue moisture movement it should be stored in such a manner that its moisture content remains fairly constant. A rack scaffold tubulars with a sheet roof covering should be used to store timber. The sheet roof protects from rain and the various sizes allow for free flow of air round the timber.
Ironmongery, hand tools and paints are some of the most vulnerable materials on site. Some materials such as locks, power tools and cans of paint should be kept in a locked shed or inside any of the completed rooms in the building under construction.
Test Questions i. List the activities that precede actual building construction on site. ii. What are the temporary services needed on construction site? iii. How is storage provided for the basic materials on construction site?
15
WEEK 3: SITE ORGANISATION AND LAYOUT (2.3) Site Layout and Organisation
The building site can be considered a temporary factory, where the building is produced this activity to take place the builder requires men, materials and plants. All these have to be carefully controlled so that the men have the right machine in the most adequate position, the materials stored so that they are readily available and not interfering with the general site circulation a building and the total size of the site on which the building is to be erected. Therefore is no standard size ratio between the free site spaces required considered as a separation problem in terms of allocating space for men, materials and plant. To obtain maximum efficiency there is an optimum way of laying out the site and also a correct amount of expenditure to support the proposed site layout. Any planned layout should be reviewed periodically and adjusted to suit the changing needs of the site activities. A careful consideration of planning and control of this aspect of the building construction will reflect in the progress and profitability of the building project.
Storage Considerations: the amount and types of material to be stored, security and weather
16
protection requirements, allocation of adequate areas for storing materials and allocating adequate
working space around storage areas required, siting of storage areas to reduce double handling to a minimum without impeding the general site circulation and/or works in progress. Accommodation Consideration: number and type of site staff anticipated, calculate size and select units of accommodation and check to ensure compliance with the minimum requirements of the relevant construction regulations. Select siting for offices to give easy and quick access for visitors and at the same time giving a reasonable view of the site. Select site for resting sheds and toilets to reduce walking time to a minimum without impeding the general site circulation.
Temporary Services Considerations: what, when and where are they required? Possibility of having permanent services installed at an early stage and making temporary connections for site use during the construction period. Coordination with the various service providers is essential.
Plants Considerations: the type and nature of plants and where they will be required on the site are important. Whether the plants will be static or mobile. If static the most appropriate position should be selected and hard standing should be provided. If mobile the circulation routes should be checked for optimum efficiency and stability. Provision of space and hard surface for plant maintenance should also be considered.
Fencing and Hoarding Considerations: distinction should be made between what is mandatory and what is desirable. These will depend on vandalism record in the area, type of fence or hoarding required possibility of using fencing which will form part of the permanent work by erecting it at the early stage of the work.
Safety and Health Considerations: it should be ensured that all the above considerations comply with the relevant construction safety regulations.
On taking over the site one of the first jobs is to layout the site boundaries as they are marked out
17 on the drawings. The security fence should be set up around the site so as to control the movement of people and materials. The boundary fence should have only one access so that someone can check people in and out of the site. The site office should be located close to the entrance into the site together with the site sheds where meals will be taken. The toilet on the site should be located at one corner away from where it will constitute a nuisance and to also enhance privacy.
The aggregates should be stored close to where the mixing will take place which in turn should be located close to where provision has been made for water storage. Generally materials should be stored to close to where they will be put to use.
The site should be laid out in such a way that there will be free movement of vehicles around the site in case it will become necessary to move materials using vehicles around the site.
Administrative area: this will be the location of offices, stores, sub-contractors huts, canteen and similar accommodation.
Construction area: this is the actual site of the building to be constructed, and it will be located close to the consumable stores adjacent to the various buildings and equipment required for the construction purpose. The layout of both these areas form an essential part of the early planning in every construction work, the neglect of which will lead to delay in the initial progress of the job leading to extra wastage of resources on the
18
Fig 3.1 A typical site layout Test Question i. Discuss the factors considered in a construction site layout.
19
After the base line has been established, marked and checked the main lines of the building can be set out, each corner being marked with stout peg. A check should then be made of the setting out lines for right angles and correct lengths. The method of establishing of the right angle is what the setting out sets out to establish in addition to the correct length.
Profiles: When setting out a building, it is an advantage if the line can be secured so that they are well clear of the building line. The trenches can then be dug without interfering with the lines. Timber profiles erected for this purpose consist of pegs driven into the ground and boards nailed across them. The lines can then be stretched above the ground level well clear of any obstruction and may easily be checked for accuracy.
Datum Pegs: Before starting the actual setting out of the building, it is essential to establish a level on the site to which references pertaining to the levels of elements of work may be made in the course of executing the work.
20 In planned cities and town ordinance bench marks are established where a bench mark is far from the proposed site, a levelling instrument such as covering, level can be used to transfer the datum level to the site from where it can be distributed around the proposed site, Datum pegs must be located where it would not be disturbed by the operation on the site.
21
22 4. Tie the string between pegs A and B. Measure the distance between A and B. Check that the distance on the ground is the same measurement as the distance on the drawing. 5. 6. 7. Repeat these steps for corners C and D Measure the diagonals A-D and B-C (the two diagonals should be equal) Use the builders square to check that the corners are at right angles.
Test Questions 1. List the three methods of setting out a building 2. List the equipment used in setting out a building
23
The choice of the method of excavation depends on the size of work. In small construction, it is more economical to use the manual method, while large works will be economical to be executed using the mechanical method of excavation.
Bulldozer: This is used to push the soil layer by layer to one side and pile it up nearby. A bulldozer does not dig out or lift out the soil. Backacter: This equipment digs down with a bucket on a jointed boom and scoops the soil towards itself. Since the bucket is narrow it is useful for forming trenches. It can also deposit soil on trucks or Dumpers.
Mechanical Auger: This digs pile holes. It is a large piece of equipment which has a large drill mounted on a platform. The auger drills a hole in the ground and lifts out a column of soil.
Dump Truck: Used for the movement of soil over short distances. The body of the dump truck tips forward and deposits the soil in the required position.
24 Tipper Truck: This is a road vehicle used to remove large amounts of excavated materials to locations away from the site. The body of the tipper truck tips up and empties the soil at the back of the vehicle.
Test Questions 1. What are the factors that determine selection of excavation method. 2. State the uses of two mechanical excavating plant.
25
If the soil is very wet then the sides of the excavation may become unstable. In both cases it is better to provide temporary supports to the sides of the excavation. Excavation on a confined site may also need support in case heavy loads are placed or driven too close to the edges of the excavation. Earthworks supports retain the size of excavation collapsed during the time the excavation will remain open. The process of providing temporary support to the sides of an excavation is referred to as timbering. It is sometime planking and strutting. Timbering is to: Protect the operatives while working in excavation Keep the excavation open by acting as a retaining wall to the sides of the trend. Prevent drainage to adjacent structures that could be caused by excavation Enable work to proceed within the excavation without interruption.
Components of Timbering
Timbering is made up of the following parts: Polings: These are vertical planks supporting the soil. In sand or gravel, they should be placed close enough to form a continuous timber wall. Depending on the soil type and working conditions, they may be placed about 900 mm apart. The purpose of the wailing is to keep the soil on the sides of the excavation from falling in. Wailings: They are horizontal timber strips supporting the polings Struts: These are the timbers that span across the trench between the wailings. The struts hold the opposite walls of the excavation in place. Wedges: These are the pieces of timber used to maintain the pressure of the polings against the soil. If the soil expands or shrinks while the work is carried out, the wedges may need to be adjusted again.
26
27
(c) Timbering in dry loose soils Fig 1.7 Timbering in various types of soil
Another means of retaining the sides of an excavation without support by sloping the sides of the excavation to the angle of repose of the soil, which is the natural angle at which the soil will remain stable without additional support. When a soil is tipped into a mound it settles to its natural angle of repose. This angle will alter according to the type of soil and its moisture content. Because the angle of repose can rather be shallow, this method of excavation support does, take up a large amount of space on site and is therefore not frequently adopted. However, this technique can be use on talk excavation.
28
(3.5) Foundation
The function of any foundation is to safely sustain and transmit to the ground on which it rests the combined dead, imposed and wind loads in such a manner as not to cause any settlement or other movement which would impair the stability or cause damage to any part of the building.
Test Questions 1. List 4 consideration for providing earthwork support 2. Draw a typical earthwork support to a loose soil.
29
Soils are also classified into two categories which are Cohesive soils in which the particles stick together and examples include silt, clay, clay and silt Non Cohesive soil in which the particles do not stick together but are loose especially when they are dry. Examples include rock, gravel and sand
30 The nature and beaming capacity of the soil The amount of settlement produced by the loading.
31 Soils that are close to the surface are likely to be more compressible than those at greater depth, as deeper soil have been compressed by the weight of the overlaying soil. If the applied load on a clay soil is reduced due to excavation, water tends to move to the unloaded areas and swelling the soil will occur.
Peat and other soils containing a lot of organic matter shrink and swell easily as their water content changes. They are very compressible and settle reality even under light loading. Made up ground behaves in a similar manner unless the materials is well graded, carefully placed and properly compacted in thin layers. Shallow foundation should not be used on sites consisting of made up ground. Slight settlement should not cause problems to the structure of the building. Excessive settlement may cause shear failure of the soil.
Settlement must also be uniform throughout the building; otherwise damage may result from different settlement. The amount of different movement between parts of a building must be kept within acceptable limits.
The bearing capacities of soils are obtained from tables or from soil investigation reports.
Width of foundation required = load per metre run of wall (kN/m) Bearing capacity of soil (kN/m2)
Example 1 Calculate the minimum width of a strip foundation for a house where the total load from the wall
Solution Total load from the wall = 50 kN/m Soil bearing capacity = 150 kN/m2
Minimum width of the strip foundation = load per metre run Soil bearing capacity
= 50 150 = 0.333m
Test Questions 1. What are the factors that determine the size of a foundation? 2. Calculate the minimum width of a strip foundation that supports a wall that transmits a load of 65 kN/m, given that the soil bearing capacity is 120 kN/m2. 3. Calculate the minimum plan area of a pad foundation that carries a column supporting a total load of 250 kN when the load bearing capacity is 200kN/m2.
33
Shallow Foundations
Shallow foundations transfer load of the building to a sub-soil at a level close to the surface. They are nearly always the cheapest to construct and generally used where sufficient depth of a strong soil exists near the surface of the ground. The foundation needs to be designed so that the soil is not overstressed so that the pressure on the subsoil beneath the foundation is equal at all points in order to avoid unequal settlement. The common types of shallow foundations are Strip foundation Pad foundation Raft foundation.
Strip Foundation
Reinforced concrete strip foundations are used to support and transmit the loads from heavy walls. The minimum thickness of a strip foundation is 150 mm. This may be of course, greater where the projection of the edge of the foundation from the base of the wall is greater than 150 mm. A typical strip foundation is as shown in figure 8.1. The width of the strip should be at least equal to three times the thickness of the wall it supports.
34
The thickness of the foundation should be at least equal to the projection of the foundation from the base of the wall so that the load transmitted from the wall will not be dispersed over an area outside the width of the foundation as illustrated in figure 8.2. This is to prevent the shear failure of the foundation.
35 The effect of the wall on the relatively thin foundation is to act as a point load and the resultant ground pressure will induce tension on the underside across the width of the strip. Tensile reinforcement is therefore required in the lower face of strip with distribution bars in the second layer running longitudinally especially in soft soils and in wide strip foundation. The reinforcement arrangement for a wide strip foundation is as shown in figure 8.3
In firm clays the sub-soil is capable of carrying substantial loads and may only require a foundation to be slightly wider than the wall it is supporting. The foundation still needs to be deep enough to overcome the problems of seasonal changes in moisture content of the soil. A deep, narrow foundation, of about 350mm in width and up to 1.50m in depth as shown in figure 8.4 could be constructed.
36
On a sloppy site it is necessary to step the foundation parallel to the slope of the ground. This is called a stepped foundation. To prevent differential settlement in a stepped foundation, the height of the step should not exceed the thickness of the foundation. At each step the higher foundation should overlap the lower foundation for a distance equal to the thickness of the foundation. An illustration of a stepped foundation is given in figure 9.5
37
Test Questions 1. Describe foundation under these headings a. Shallow foundation b. Deep foundation 2. Sketch 4 types of foundation
38
Raft foundation
The principle of any raft foundation is to spread the load over the entire area of the site. This method is particularly useful where the column loads are heavy and thus requiring large bases or where the bearing capacity is low, again resulting in the need for large bases. Raft foundation can be considered under three headings: solid slab rafts, beam and slab rafts, and cellular rafts.
39
Pile Foundation Pile foundation is used to transfer heavy load to a soil layer of adequate strength located far below the ground surface that it will be uneconomical to carry out excavation to reach such a depth. This is used where the soil condition is poor close to the earth surface. Pile foundations could be made using concrete, steel or timber. The concrete could be precast or cast insitu.
Piles are classified by their method of construction into Bored or Replacement Piles which are concrete cores poured into holes in the ground at measured intervals. Driven or Displacement Piles which are driven into the ground at spaced intervals.
By the way they carry their loads pile foundations are classified into two types. These are End bearing pile, and Friction pile
(a) End bearing piles are those piles that are driven down to soil layer of adequate strength in such a way that the end of the piles actually bear on this particular soil layer.
40 (b) Friction piles are used in situations where the soil layer of adequate strength is located far below the ground surface such that it becomes uneconomical to produce piles that will go to such a depth. This type of piles carries their load by the friction that exists between the shaft of the pile and the surrounding soil particles. The surface of the friction piles are made rough so that the desired frictional force could be produced as the pile is driven into the ground.
Test Questions 1. Use drawing to describe a pad foundation 2. State the principle behind raft foundation
41
Pad foundations: The reinforcement in isolated pad foundation is provided as the bottom of the foundation slab. This is because the point load coming from the column or pier subject the bottom part of the foundation to tension. The reinforcement detail is as shown in figure 10.1
Raft foundation: In raft foundation both the top and bottom faces of the slab are subjected to both tension and compression depending on the position of the columns and other structural components that are carried by the raft. The reinforcement is therefore provided both at the top and bottom of the slab as shown in figure 10.2
42
Ground beams: Ground beams are provided to support the foundation wall in place of a strip foundation in poor soil conditions. They are reinforced to enhance their resistance to the loads that might be coming on them from the wall. There are situations where the ground beams form component parts of some types of raft foundation. Typical reinforcement arrangement in ground beams is shown as an integral part of a raft foundation in figure 10.3
Fig 10.3 Reinforcement details for ground beams in a raft foundation Test Questions 1. What is the main function of reinforcement in foundation
43
The construction entails first of carrying out the excavation of the foundation trench up to a depth of at least 1m. This depth is to ensure that the foundation is constructed at a depth where it will not be affected by the seasonal soil movement that will cause its failure. After the excavation is concluded the concrete is then placed and compacted in the trench usually in one single layer.
If the nature of the soil will be such that a wide strip foundation will be used, the reinforcement
44 is placed at the bottom of the exaction and the necessary concrete cover is ensured by the use of spacers placed below the reinforcement before the concrete is poured. This is as shown in figure 11.2
Pad foundation
The construction of the pad foundation entails the excavation of the foundation pit to the desired depth. The bottom of the excavation is overlaid with a weak concrete referred to as blinding. The reinforcement which is placed in both directions is usually tied in a basket form and then placed inside the pit with the spacers to give the necessary concrete cover to the reinforcement. The column starter bars are cast together with the foundation. The concrete of the desired quality is then poured into the pit to form the foundation. A reinforced concrete pad foundation is shown in figure 11.3
45
Raft foundation
Because the raft foundation covers the whole area under the building, the excavation has to be carried out to the desired depth over the whole area the building has to cover. A weak concrete is placed over the whole area which acts as blinding. The reinforcement is placed with the spacers to give the desired concrete cover. The reinforcement is placed in both direction and in both faces. The concrete is then poured and compacted to form the foundation. It might also be necessary to cast the column starter bars, if necessary. The construction is as shown in figure 11.3.
46
Pile Foundation
Pile foundations are constructed either by being driven into the ground by pile drivers or the ground is bored, the reinforcement is placed and concrete pored and vibrated to form the pile foundation. In the first case it is called driven pile. The second type is referred to as replacement pile.
47
WEEK 12: DAMP PROOFING (4.1) Rising Damp and Seepage of Ground Water in Building
The foundation of the building and the foundation walls are usually in direct contact with the sub-soil. The ground water level rises and drops depending on the season. This ground water rises through the fabric of the walling materials and passes through to the superstructure. This rising damp has the adverse effect of damaging fittings and finishes applied to the building. For this reason precaution should be taken to prevent this dampness from rising.
The process of preventing the passage of moisture to the interior of a building through the walls, floors, etc. is referred to as damp proofing. Damp proofing is achieved by the use of damp proof course (DPC) and damp proof membrane (DPM). While the damp proof membrane (DPM) is defined as an impervious material placed horizontally at the floor level to prevent moisture penetration into the interior of the building.
(4.2) Damp Poof Course (DPC) and Damp Proof Membrane (DPM)
Damp proof course (D.P.C) simply means an impervious material used to prevent the vertical rise of moisture through the wall into the interior of the building. The primary function of any damp-proof course (dpc) or damp membrane (dpm) is to provide an impermeable barrier to the passage of moisture. However, D.P.C can be used in: Reveals of doors and widows opening Retaining walls Basement walls enclosing laundry
The three basic purposes for which damp-proof courses are used is to: Resist moisture penetration from below (rising damp) Resist moisture penetration from above Resist moisture penetration from horizontal entry
48 accommodate pipe, insulator and other electrical fitting of the building in terms of concrete (D.P.C) should be capable of adequate resisting any attack by sulphates or any other deleterious matter present in the subsoil.
The movement of water or moisture into the building is most times upward through the foundation of wall from the ground. Paint laid (D.P.C) should be protected on both sides with bitumen to prevent corrosion of the laid, as it is in contact with cement mortar. Care should be taken to ensure a good bonding between slate or brick and the mortar.
The diagram above shows the rise of moisture through material to wall above D. P. C too close to the ground.
Damp proof membrane (DPM) should be impermeable to water either in liquid or vapour from the ground. It should be rough enough to withstand possible damage during the laying of screeds, concrete or floor finishes. It may also be sand witched in or under the concrete slab. Being
impermeable to water, the membrane will delay the drying out of wet concrete to the ground, if it is under the concrete or screed or it is on top of the concrete. Typical details of the procedure used in laying DPC and DPM are shown in figure 12.1
49
Fig. 12.1 Damp proof course (DPC) & damp proof membrane
Test Questions 1. Discuss the importance of damp proofing 2. State 3 basic purposes for which damp proofing is provided in a foundation
50
Lead / Aluminum core A sheet of copper Polythene sheet Fairly firm soil
Damp proof course maybe horizontal or vertical placed either below the ground level or just above the ground level is in order prevent water raising up the wall of the building. These below ground level are provided with the lowest floor in a building. These consist of both horizontal and vertical D. P. C must be placed at least 150mm above the ground level and the vertical D.P.C must connect the two D.P.C form a completion barrier to moisture. Every wall in a building should have a (D. P. C) which is:
51 At least 150mm and above ground level Above the surface of any oversite concrete Below the surface member of the timber floor Moreover the wall should be kept about 25mm away from asphalt and each course flushed up solidly. The asphalt which is laid on the floor slab should also have a protective screed on top to prevent any damage by people walking over it. Therefore, reinforcement is to be placed on it or petrol and oil being spilt from machinery.
Test Question 1. State the materials for damp proofing 2. Briefly describe various materials for damp proofing on different types of soil
52
Asphalt Tanking
Asphalt is a natural or manufactured mixture of bitumen with a substantial proportion of inert mineral matter. When heated, asphalt becomes plastic and can be moulded by hand pressure into any shape. Bitumen has both waterproofing and adhesive properties.
The basic principle of asphalt tanking is to provide a continuous waterproofing membrane to the base and walls of the basement. Continuity between the vertical and horizontal membranes is of utmost importance, and since asphalt sets rapidly once removed from the heat source used to melt the blocks it is applied in layers over small areas. Joints in successive coats should be staggered by at least 150 mm in horizontal work and at least 75 mm in vertical work.
53
(b) Internally applied mastic asphalt tanking Fig 14.1 Basement tanking in mastic asphalt
54 Test Questions 1. List three basic methods of tanking 2. Describe Asphalt taking 3. Draw an basement tanking using mastic asphalt
55
Functions of Hardcore
Provides support to the floor slab Reduces the amount of moisture penetration into the building Used in determining different floor levels in a building wit various floor levels (e.g. dinning area may be higher than sitting area (living room). Used for filling in void before construction. Hardcore is important in the construction of solid ground floor. Used in determining the different levels in a building, in reduced level excavation. Provides an even level before slab is cast. Helps in reducing undergrowth in penetrating into the floor slab and subsequently into the building. Helps to increase the strength level of a building.
(4.8) Blinding
A blinding layer 50 to 75mm thick of weak concrete or coarse sand should be placed under all reinforced concrete foundations. The function of the blinding are to fill in any weak pockets encountered during excavations and to provide a true level surface from which the reinforcement can be positioned. If formwork is required for the foundation some contractors prefer to lay the blinding before assembling the frame work; the alternative is to place the blinding within the
56 frame work and allow this set before positioning the reinforcement and placing the concrete.
Also blinding should be placed on top of the hardcore before the casting of the oversite concrete. This is to safeguard against the mixture of water, fine aggregates and cement from seeping through the large voids present in the hardcore layer. It also prevents the rough surface of the hardcore layer from puncturing the damp proof membrane that may placed on it before the casting of the floor slab.
Test Questions 1. Define hard core and state site functions 2. State 4 type of materials that can be used for tanking 3. Explain the importance of anti termite treatment