Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
0% found this document useful (0 votes)
167 views

Example 7 Critical Path Method

The document is a PERT chart for a software project that shows tasks as ovals with their durations in weeks and dependencies with arrows. The critical path includes the Requirements Engineering, Analysis and Design A, Implementation A, and Test tasks, which have a total duration of 10 weeks from start to finish.

Uploaded by

Waleed Liaqat
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
167 views

Example 7 Critical Path Method

The document is a PERT chart for a software project that shows tasks as ovals with their durations in weeks and dependencies with arrows. The critical path includes the Requirements Engineering, Analysis and Design A, Implementation A, and Test tasks, which have a total duration of 10 weeks from start to finish.

Uploaded by

Waleed Liaqat
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

CSSE3113

Dr. Ali Afzal Malik

Critical Path Method


Q. The diagram below shows the PERT chart for a software project. Each task is represented by an oval. Numbers inside ovals represent task durations in weeks. Arrows indicate task dependencies. Identify the tasks on the critical path. Show your working clearly e.g. indicate start and end times of each task.

Analysis and Design A 3 Implementation A 9

Start 0

Requirements Engineering 2

Analysis and Design B 6

Test 10

Finish 0

Implementation B 7 Analysis and Design C 1