FE Old Questions and Answers (Time Management)

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

FE – OQ 2018 October (Morning)

Q53. Which of the following is an appropriate description of the activities on the critical path of a project?
a) Any activity on the critical path is called a critical path activity.
b) The critical path is the sequence of activities that represents the shortest path through a project.
c) The critical path must contain the activity that has the longest duration compared to the other all activities.
d) The sum of activities on the critical path determines the longest possible project duration.

Answer : a

FE – OQ 2019 April (Morning)


Q54. Which of the following is the critical path of the project activities shown in the figure below?
(FE – 2020S April Q53)

a) A → B → E → I → L
b) A → C → D → E → H → K
c) A → C → F → I → L
d) A → C → G → J → L
Answer : d

FE – OQ 2019 October (Morning)

Q51. Which of the following is an appropriate explanation of the PERT diagram as shown in
the figure below?

a) The critical path is A – C – G.


b) This project needs at least 11 days.
c) When the activity F becomes unnecessary, the project will end 1 day earlier.
d) When the activity H has a delay of 2 days, it will cause the project to be delayed by 2
days.

Answer : c
Q54. When the triangular distribution formula in the three-point estimation technique is used,
which of the following is the expected duration in days required for an activity? The
estimates are as shown below. FE – OQ 2022 April (Morning)

Conditions – Estimates for the duration of the activity


Case 1: Two (2) days – if an experienced employee is assigned to this activity
Case 2: Four (4) days – if an average employee is assigned to this activity
Case 3: Twelve (12) days – if an inexperienced employee is assigned to this activity

a) 4 b) 5 c) 6 d) 7

FE – OQ 2022 April (Morning)


Q55. The arrow diagram below shows a project’s activities and milestones. Which of the
following is the minimum project completion time in days?

a) 20 b) 24 c) 25 d) 26

Answer : d

FE – OQ 2020 October (Morning)

Q52. The activities and milestones of a project are shown in the arrow diagram below. Which
of the following is an impact of reducing the duration of activity, D, by 3 days?(2021A October Q54.)
a) Project duration is not changed.
b) Project duration is reduced by 1 day.
c) Project duration is reduced by 2 days.
d) Project duration is reduced by 3 days.

Answer : b

Q53. The functional size of a new system was estimated to be 500 function points (FP). Apart
from development, the project requires 10 person-months in total for installation of the system and education
of developers. Additionally, for project management, 10% of the total personmonths of development,
installation, and education is required. How many person-months are required in total for this project? Here,
the productivity in development is 10 FPs per personmonth.

a) 51 b) 60 c) 65 d) 66

FE – OQ 2020 April (Morning)


Q52. A project with a development period of 10 months and the person-hours required for
development as 200 person-months is planned. Which of the following is the number of staff
members required during the peak time based on the distribution sheet shown below? Here,
the number of staff members does not change from the start till the end of every process.
a) 18 b) 20 c) 21 d) 22

FE – OQ 2021 April (Morning)

Q52. In project time management, which of the following descriptions is appropriate for “slack
time”?
a) It is the amount of time between the earliest start time and earliest finish time of an
activity or between the latest start time and latest finish time of an activity.
b) It is the amount of time for which a non-critical path activity can be deferred without
delaying the project.
c) It is the amount of time that an activity can be deferred without delaying the earliest start
time of any succeeding activity or violating a schedule constraint.
d) It is the amount of time that an activity can be delayed past its latest start time or latest
finish time.

Q54. In system development, when the relationship between person-months and the duration
(months) is represented in the approximate expression shown below, and the total person-month is 4096,
how many months does it take?
Duration = 2.5 x person-months 1/3

a) 16 b) 40 c) 64 d) 160

FE – OQ 2021A October (Morning)

Q53. In project time management, which of the following is the amount of time that the start
of a successor activity requires to be delayed after the finish of a predecessor activity?
a) Free float b) Lag c) Lead d) Total float

Answer : b