Critical Path Method Problem
Critical Path Method Problem
a) Draw a network diagram and find the critical path and project completion time.
b) Calculate slack time of the activities C, D, G and J.
c) If $1000 can be saved for each delayed day of activity H, then how much dollar can be saved keeping the project completion
time unchanged?
d) Activity G needs a delayed time of two weeks and an extra time of five weeks. Is it possible by keeping the project completion
time unchanged? Explain.
e)The PM wants to shorten the duration of the activity I from 11 weeks to 9 weeks. What is the impact of this change on project
completion time and critical path?
a) Draw a network diagram and find the critical path and project completion time.
b) Calculate float time of the non critical activities.
c) Can activity I be delayed without delaying the project completion time? If so, how many weeks?
d) Activity G needs a delayed time of two weeks and an extra time of one week. Is it possible by keeping the project
completion time unchanged? Explain.
e) The PM wants to shorten the duration of the activity E from 3 weeks to 1 week. What is the impact of this change on the
project completion time and critical path?
3. Schedules and activities of a project are shown below. Answer the questions
(g) Draw the network diagram and find the critical path and project completion time.
(h) Calculate float time of the activities C, D, F, L and K.
(i) Can activity I be delayed without delaying the project completion time? How many weeks?
(j) What is the impact on the project if activity F needs extra 5 weeks?
(k) The PM wants to shorten the duration of the activity H from 16 weeks to 10 weeks. What is the impact of this change on the
project completion time and critical path?
5. Schedules and activities of a project are shown below. Answer the questions.
6. Schedules and activities of a project are shown below. Answer the questions.