Babcock and Wilcox Boiler.
Babcock and Wilcox Boiler.
Babcock and Wilcox Boiler.
F. Belin M. Maryamchik D.J. Walker D.L. Wietzke The Babcock & Wilcox Company Barberton, Ohio, U.S.A. Presented to: 16th International Conference on FBC May 13-16, 2001 Reno, Nevada, U.S.A.
BR-1711
Abstract
The distinctive feature of Babcock & Wilcox (B&W) CFB boilers is a two-stage solids separation system consisting of the impact-type primary solids separator (U-beams) and the secondary multi-cyclone dust collector. Lessons learned from 15 years of B&Ws CFB technology application have been used to develop a reliable, low cost boiler design. Advantages of boilers with a two-stage solids separation system are described. Operation of B&W coal-fired CFB boilers over the last 10 years has demonstrated high reliability of the two-stage solids separator. Superior solids collection efficiency of the two-stage separator provides higher furnace heat-transfer rate, ability to better control furnace temperature, and increased residence time of fine carbon and sorbent particles. As a result, the required boiler performance is achieved with lower furnace height and smaller boiler footprint. The current B&W IR-CFB boiler design is described. Compactness of the IR-CFB makes it especially attractive for PC boiler retrofit applications. Considerations for IRCFB scale-up are provided.
Background
The major distinction between circulating fluidized-bed (CFB) boilers competing in todays market is in the type of the solids separator. CFB boilers with large cyclone separators connected to the furnace outlet (hot-cyclone type) were introduced in mid-1970s and are being offered by several boiler manufacturers. CFB boilers with impact separators, offered by Babcock&Wilcox (B&W) and its licencees, entered the market more than ten years later and since then have been gaining wide acceptance.
B&W CFB boilers feature a two-stage solids separator. The primary stage is an impact solids separator located at the furnace exit collecting the bulk of the solids (95-97%) that are then returned to the furnace by gravity. The primary separator is arranged as an array (Figure 1) of U-shaped vertical elements (Ubeams). The secondary separation stage, typically a multi-cyclone dust collector (MDC), is located in the lower gas temperature region of the boiler convection pass, i.e., 480 F to 950 F (250 C to 510 C). In some cases the first fields of an electrostatic precipitator are used as the secondary separator. The fine particles collected by the secondary separator are returned to the furnace via a pneumatic (in earlier designs) or gravity transport system. The U-beam separator has evolved through three B&W CFB boiler design generations: First generation (first started-up in1986) - All U-beams (11 rows) installed external to the furnace with solids recycle through non-mechanical controllable L-valves.(1) Second generation (first started-up in 1989) - Two rows of in-furnace U-beams discharging collected particles (about 70 % of incoming solids) directly to the furnace and seven rows of external U-beams with solids recycle through L-valves. (2) Third generation (first started-up in 1996) - Two rows of in-furnace U-beams and three or four rows of external U-beams with all solids internally recycled within the furnace (currently offered IR-CFBseparator shown in Figure 2). (3) As a result, dramatic simplification and cost reduction of the U-beam separator have been achieved.
Over the same period, the design of the MDC separator has been improved for better efficiency, reliability and maintainability. The current design (Figure 3) has a top gas inlet and a side gas outlet. The cyclone elements have 9 in. (229 mm) diameter regardless of boiler capacity. The cyclone sleeves and spin vanes are made of high hardness (550 BHN) material. The MDC solids recycle system has evolved from dense-phase pneumatic transport (first generation) to dilute-phase pneumatic transport (second generation) to gravity conveying (third generation). The second-generation CFB boiler at Ebensburg, Pennsylvania, in a cogeneration plant commissioned in early 1991, exemplifies the long-term boiler performance. This boiler (Figure 4) burns high-ash (average 45% ash) Western Pennylvania waste bituminous coal. The unit was designed for 55 MWe capacity (211 tph steam flow), but was uprated in 1995 and again in 1997 and since has been operated at 10% overload. Boiler performance and availability are shown in Table 1 and Figure 5 respectively. The Ebensburg plant received the Association of Independent Power Producers of Pennsylvania (ARIPPA) award for the highest availability among plants firing coal mine waste fuels. The CFB boiler at Southern Illinois University (SIU) in Carbondale, Illinois, represents the third generation design. The boiler (Figure 6) was designed for 35 MWt output for cogeneration application, utilizing high-sulfur Illinois bituminous coal. Boiler performance and availability are shown in Table 2 and Figure 7, respectively. The third generation design was also used for the Kanoria Chemical project in India and is the design ba-
sis for all new offerings including the most recent contract for a 90 MWe IR-CFB in Tychy, Poland. Operating experience of B&W coal-fired CFB boilers has clearly confirmed their efficient performance and high reliability.
Design Features
The design of a solids separator is the core of a CFB combustion technology since it has major impact on the boiler layout, cost, fuel and sorbent utilization, operational flexibility and reliability. In all these aspects B&Ws CFB boilers with the twostage solids separation provide the following design features:
Furnace Roof Gas Flow In -Furnace U-Beams External U-Beams Solids Transfer Hopper
Table 1 Ebensburg Operating Data Operating Steam Flow, t/hr (klb/hr) Steam Flow @ MCR, t/hr (klb/hr) Steam Temperature, C (F) Steam Pressure, MPa (psig) SH Steam Temperature Control Range, % Load Turndown Ratio Without Auxiliary Fuel Emissions NOx, ppm (lb/106 Btu) SO2, ppm (lb/106 Btu) CO, ppm (lb/106 Btu) Ca/S Molar Ratio 234 (516) 211 (465) 512 (953) 10.6 (1540) 30-110 5:1 <100 (<0.14) <300 (<0.60) <230 (<0.20) 2.1-2.4
Forced Outage
Planned Outage
Boiler Availability
100
Boiler Availability, Percent
1.9
1.2
3.9 5.3
2.6
2.2 2.8
1.4 5.6
1.8 4.2
0.7 1.3
95 90
8.4
9.4
4.5 5.6
85
89.7
89.4
91.6 89.1
90.8
80 0 1991 (May-Dec.) 1992 1993 1994 1995 1996 1997 1998 2000 1999 (Jan.-July) (Jan.-June)
Table 2 SIU Operating Data Steam Flow @ MCR, t/hr (klb/hr) Steam Temperature, C (F) Steam Pressure, MPa (psig) SH Steam Temperature Control Range, % Load Turndown Ratio Without Auxiliary Fuel Emissions NOx, ppm (lb/106 Btu) SO2, % removal CO, ppm (lb/10 6 Btu) Ca/S Molar Ratio 46 (101.5) 399 (750)
Boiler Availability, %
100 95 90
4.9
95.1 85 80 85 1997 (Jul 15-Dec 31) 1998 1999 2000 (Jan-Jun) 89.0 89.7 87.9
vided to accommodate possible U-beam temperature deviations from the expected value based on average gas temperature leaving the furnace. These margins eliminate the possibility of the U-beams being damaged during operational upsets. Mechanical conditions of U-beams along with related boiler thermal performance data have been monitored over the 10 years of operation at the Ebensburg CFB boiler. B&W confirmed that erosion losses were negligible due to a tough, erosion-resistant film formed on the surface of the U-beams. B&W also determined that the material was resistant to corrosion and deformation when operated within the design margins. The Ebensburg CFB boiler capacity was increased by 10% over original design. For evaluated economic reasons no other changes to the boiler were made to maintain the design temperature and excess air at the furnace exit. This resulted in more than three years of operation with local U-beam temperatures approaching or exceeding the design margins. After this three year period of operation with excessively high temperatures, signs of U-beam mechanical degradation began appearing where the maximum temperatures or maximum solids loading occur. Some U-beam channels began to flare, and the mid-sections of several U-beams rotated up to 10 degrees from the original position. Also, several corrosion spots were found near the bottom of the rear-most rows of U-beams where U-beams were covered with ash deposits. The current design has been changed to avoid these degradations even during prolonged high-temperature operation. Regardless of some U-beam deformation observed as a result of the off-design operating conditions, no deterioration of boiler performance was detected and no U-beams have had to be replaced. Maintenance work on U-beams has been minimal, consisting primarily of cleaning solids accumulated on the top side of the alignment pans located near the bottom of U-beams, and an occasional repair of the pan and strap attachment welds. The resilience of U-beams to operating conditions associated with excessive temperatures and increased gas velocities contrasts to that of vortex finders (a part of hot-cyclones) which are made of similar materials and exposed to a similar gas/solids environment. Vortex finder failures have been reported with a substantial detrimental effect on boiler performance and considerable maintenance costs.
MDC experience
At Ebensburg, due to the waste coals high ash content and ash abrasiveness, about 20% of the MDC internal elements are being replaced during each yearly outage to avoid a loss of MDC efficiency. At other B&W CFB boilers burning high-sulfur bituminous coal, circulating solids are typically less abrasive as compared to the Ebensburg unit, and the MDC internal elements have either not required replacement or have been replaced as needed during planned outages. At Southern Illinois University (SIU) firing medium-ash high-sulfur coal, practically no erosion of the internal elements has been detected since the startup four years ago. Maintenance work was needed on the Ebensburg pneumatic MDC solids recycle system which normally is done on line, or during planned boiler outages. At SIU, where air-slide ash conveyors were used, virtually no maintenance work was needed on the return system during four years of boiler operation. This system has been further simplified for new offerings. The simplicity and low maintenance features of the current MDC solids return system design are discussed below (see Design improvements).
from the forced draft fan. Material velocity in the sloping return lines is low, resulting in low erosion potential. This design simplifies the recycle system, improves its reliability, and reduces power consumption. - Variable speed, inclined screw(s) are used at the MDC hopper discharge(s), in place of previously used rotary valves, to control the flow rate of recycled solids. The solids in the inclined screw provide the required pressure seal without the maintenance associated with the close-tolerance, machined surfaces found in rotary valves.
Maintenance cost
The maintenance cost of the solids separators in the B&W CFB boilers is intrinsically low. At Ebensburg, the total maintenance cost for U-beams and L-valves over 10 years of operation was about US$20,000. The average maintenance cost for the MDC was about $25,000 per year. There was no loss of power generation due to U-beam or L-valve related problems and only a negligible loss of generation due to the load reduction during MDC recycle system problems and its on-line repairs.
Design improvements
A number of design improvements to the two-stage solids separation system have been implemented based on experience and design developments: - Laboratory testing and boiler operating experience have shown that with proper design parameters, fewer rows of Ubeams provide equal collection efficiency. The number of rows of U-beams has been reduced to eliminate inactive rows thereby reducing the space occupied by the separator as well as reducing pressure differential across the separator and the corresponding auxiliary power requirement. - The alignment pan at the bottom of each U-beam has been reconfigured to form an open funnel which reduces solids accumulation. Together with the reduced number of U-beam rows, this reduces solids accumulation at the bottom of the U-beams and the possibility of corrosion in this zone. - Variations such as fuel properties and limestone sizing and/ or type, as well as other operational upsets, may cause prolonged gas temperature increase over the design temperature in the Ubeam zone. Also, U-beams lack protection from metal temperature excursions similar to those available for the superheater metal (such as attemperators). Thus, wide design margins are provided for the U-beams by specifying high quality materials for these off-normal conditions. U-beam materials and constructions with an oxidation temperature limit as high as 2100 F (1150 C) are used. - Locating the MDC upstream of the economizer, and thereby at higher elevation in the convection downpass, allows recycling of the MDC solids to the lower furnace using a sloping gravity return line(s) with a small quantity of assist air taken
100
Collection Efficiency, %
90 80 70 60
20
40
60
80
100
Fuel is fed to the lower furnace through the front wall using four air-assisted chutes. Limestone is injected pneumatically through multiple points uniformly across the width of the furnace near the bottom. Start-up fuel (light oil) is fired using five burners mounted at the rear wall. Separate fans supply primary and secondary air. Primary air is introduced through the bubble cap grid at the furnace floor with secondary air introduced uniformly across the furnace width using nozzles at the front and rear walls sized to provide air distribution across the furnace. The lower furnace is protected from erosion and corrosive conditions by a layer of low-cement, high-strength refractory. This material has proven to require little maintenance in the lower CFB furnace environment. The membrane tubes at the upper edge of the refractory in the lower furnace are protected from erosion by the patented Reduced Diameter Zone (RDZ) (Figure 11). The RDZ consists of a reduced diameter tube section mating to a specially shaped ceramic tile. The reduced diameter tube section on each tube slopes away from the solids
100
80
Percent Passing
falling down the wall along the surface profile of the tube panel, thereby eliminating the discontinuity adjacent to the tube. The RDZ feature is applicable for enclosure walls and internal walls, and has been proven effective in B&W CFB boiler commercial operation. The U-beam separator consists of two rows of in-furnace and three rows of external U-beams. Pendant superheater banks are located downstream of the U-beams in the horizontal convection pass. Steam from the drum flows through the side walls of the pendant superheater enclosure, then through the primary superheater bank followed by the wing walls and the secondary superheater bank to the main steam outlet. The MDC is located immediately downstream of the horizontal convection pass. Further in the gas path it is followed by
60
40
20
100
200
300
Hot Cyclone (Ref. 4) Hot Cyclone (Ref. 5) Hot Cyclone (Ref. 6) Hot Cyclone (Ref. 7) Two-Stage Solids Separation (B&W-SIU)
Division Wall
Fig. 9 Particle size distribution of fly ash for hot cyclones and two-stage separation system.
the economizer and tubular air heater (air inside tubes). The air heater is side-split for the primary and secondary air. After the air heater, gas flows through an electrostatic precipitator and two parallel ID fans to a stack. Solids collected by the MDC are recycled back to the furnace through six recycle lines utilizing inclined screw conveyors and gravity feed.
tile matter content). Based on test results for a similar fuel in the 2.5 MWt CFB pilot unit at B&Ws Alliance Research Center, the furnace height was increased about 30 ft (9 m) as compared to the PC boiler to attain the guaranteed combustion efficiency of 97%. High combustion efficiency is achieved by utilizing effective collection and recycle of fine solids from the MDC. Figure 12 shows how the new unit fits within the existing bay when the only required modification to the building is a height increase. The fore-to-aft footprint of this unit as compared to the Tychy unit is reduced by two means: a) placing part of the superheater in the vertical downpass, thus reducing the depth of the horizontal pass, and b) utilizing available space for the air heater at the side of the downpass.
CFB Boiler
7600
3600
6400
8590
3360
3700
Fig. 12 Size comparison of PC boiler firing anthracite culm and its repowering CFB boiler.
fuels to be fired are local high-ash, high-sulfur lignite and lowreactive, medium-ash bituminous coal. CFB boilers of Belenergomash design will fit into the existing PC-boiler steel (Figure 13). IR-CFB scale-up. Since scaling-up the two-stage solids separator does not present a problem, the only issue of designing larger capacity IR-CFB boilers is providing an acceptable furnace aspect ratio and acceptable gas velocity in the U-beams. With the current design approach, IR-CFB boilers with the design similar to that described above are offered for capacities up to 180 MWe (540 MWt).
Conclusion
Lessons learned from 15 years of B&Ws CFB technology application have led to development of the reliable, low-cost IR-CFB boiler design. Long-term operating experience of the distinct two-stage solids separator has proven its high reliability and superior collection efficiency. The main advantages of this boiler design are higher furnace heat transfer rate, ability to better control furnace temperature, and increased residence time of fine carbon and sorbent particles. The IR-CFB boiler achieves the required performance with lower furnace height and smaller boiler footprint. This design is especially attractive for replacing existing obsolete PC boilers in the same space.
CFB Boiler
Fig. 13 Size comparison of PC boiler firing lignite and bituminous coal and its repowering CFB boiler.
References
1. F. Belin, et al., Waste Wood Combustion in Circulating Fluidized Bed Boilers, Proceedings of the Second International Conference on Circulating Fluidized Beds, 1988. 2. C. E. Price and D. J. Walker, Coal and Waste Coal-Fired Boilers Accumulate Operating Experience, Proceedings of 12th International Conference on Fluidized-Bed Combustion, 1993. 3. F. Belin, et al. , Update of Operating Experience of B&W IR-CFB Coal-Fired Boilers, Proceedings of 15th International Conference on Fluidized-Bed Combustion, 1999. 4. D. R. Hajicek et al. , The Impact of Coal Quality on Circulating Fluidized Bed Combustor Performance, EPRI Coal Quality Conference, 1992. 5. W. vom Berg and K.-H. Puch, Verwertung von Ruckstanden aus Wirbelschichtfeuerungsanlagen, Vortrage VGB Konferenz, Wirbelschihtsysteme 1992. 6. M. Gierse, Aspects of the Performance of Three Different Types of Industrial Fluidized Bed Boilers, Proceedings of the 3rd International Conference on Circulating Fluidized Beds, 1990. 7. U. Muschelknautz and E. Muschelknautz, Improvements of Cyclones In CFB Power Plants and Quantitative Estimation on Their Effects on the Boiler Solids Inventory, Proceedings of the 6 th International Conference on Circulating Fluidized Beds, 1999. 8. D.A. Shaposhnik and S.V. Berdin, Issues of CFB Boilers Design for Power Plant Retrofits, VTI Science and Technology Seminar, 2001.
Copyright 2001 by The Babcock & Wilcox Company, All rights reserved. No part of this work may be published, translated or reproduced in any form or by any means, or incorporated into any information retrieval system, without the written permission of the copyright holder. Permission requests should be addressed to: Market Communications, The Babcock & Wilcox Company, P.O. Box 351, Barberton, Ohio, U.S.A. 44203-0351. Disclaimer Although the information presented in this work is believed to be reliable, this work is published with the understanding that The Babcock & Wilcox Company and the authors are supplying general information and are not attempting to render or provide engineering or professional services. Neither The Babcock & Wilcox Company nor any of its employees make any warranty, guarantee, or representation, whether expressed or implied, with respect to the accuracy, completeness or usefulness of any information, product, process or apparatus discussed in this work; and neither The Babcock & Wilcox Company nor any of its employees shall be liable for any losses or damages with respect to or resulting from the use of, or the inability to use, any information, product, process or apparatus discussed in this work.