A Feasibility Study On The Implementation of A Micro-Hydro Scheme in Sioma, Zambia
A Feasibility Study On The Implementation of A Micro-Hydro Scheme in Sioma, Zambia
A Feasibility Study On The Implementation of A Micro-Hydro Scheme in Sioma, Zambia
Hans Petter Bjrnvold (0602641) 3rd Year Manufacturing & Mechanical Engineering School of Engineering, University of Warwick
Introduction
Visited Zambia and Sioma in 2005 Witnessed the problems the community faces Rural infrastructure development is imperative
Fire fighting problems will not lead to progress
Project Specification
Research and prove viability of hydroelectric scheme in Sioma, Zambia Produce a proposal for such a scheme
Including initial technical analysis
Apply for support from local government Network with charities Put plan into action
Outside academic boundaries
Micro-Hydropower
Small scale harnessing of falling water
Typically generates less than 100 kW
Micro-Hydropower
Sioma
Image Source: maps.google.com, retrieved 24 April 2009
Sioma Village
6 km
Sioma Falls
4 km
Woodworking Workshop
Power Requirements
Village: Woodworking Workshop: 24,830 W 20,000 W
Load Factor = [Average Power] / [Peak Power] Average Power = 20.2083 kW Peak Power = 35 kW Load Factor = 56.92%
Turbine
L-1 Turbine
Manufactured on site through local labour High Efficiency at low head sites Easy operation and low maintenance Scalable to suit different situations using an adjustable distribution
Source: McMULLEN, C., Low Head Micro Hydro in Developing Countries: The L-1 Turbine, April 2004, 3rd Year Project, University of Warwick
Source: LI, S. C., Giving the lowdown on small hydro, International Water Power and Dam Construction, November 2000
Forebay Tank
settling basin Incorporates: Spillway Trashrack Cover Integration of water taps Decreases risks of collecting water Reduces distance to safe water
Primarily used as
Potential Contribution
Local Clinic
Replace diesel generator Increased comfort attract permanent doctor
Woodworking Workshop
Replace diesel generator Allows for economically competitive production
Financial Viability
Total cost approx. 45,000 Return on investment not realistic
Rely on charity sponsorship for start up costs
Conclusions
Power Requirement: 45.83 kW Turbine: L-1 Penstock: estimated 51 metres HDPE, 600 mm diameter Cost: 45,000 + annual maintenance fees (50 per kW)
Source equipment suppliers Complete arrangements with local government Apply for bursaries/fundraise Commence construction July 2010