Module 4 Lecture 8 Final
Module 4 Lecture 8 Final
IIT BOMBAY
Instructional objectives
The objective of this lecture is to exhibit how real components are designed in industry following some of the principles that are outlines in the previous lectures.
Figure 4.8.1 Schematic diagram of a typical shell and tube heat exchanger
IIT BOMBAY
Tube Sheet
Tube
Figure 4.8.2 Photograph showing tube sheet, tube & tube to tube sheet joint
The tube to tube sheet joint is the most critical joint in a heat exchanger. The applicable code of construction specifies some of the standard tube to tube sheet weld joint configurations and various tests to be performed primarily from the mechanical design considerations. For example, as per ASME Sec VIII Div-2, following are the design considerations for a typical tube to tubesheet joint in case of a heat exchanger.
[a] Tubes used in the construction of heat exchangers may be considered to act as stays which support or contribute to the strength of the tube sheet [b] Tube to tube sheet joint shall be capable of transferring the applied tube loads. [c] The design of tube to tube sheet joint depends on type of joint, degree of examination, and shear load tests, if performed
In a tube to tube sheet joint, mechanical design is usually based on the shear strength of the joint and the tube thickness is based on the thermal design. Hence, tube to tube sheet is a perfect example of trade-off between thermal and mechanical design principles. Some of the conventional types of tube to tube sheet joints used in manufacturing of heat exchangers are shown in Figure 4.8.3.
IIT BOMBAY
However, over and above the requirements of standard codes, a number of additions factors needs to be considered while designing tube-to-tube sheet joint for a specific application including service conditions, manufacturability, access for inspection, equipment life and ease of repair.
Service environment
Waste heat boiler is a type of heat exchanger used in fertilizer, methanol and hydrogen Plants. In reformed gas / converter gas boiler, the combinations of high pressure, high temperature and process gas composition results in higher heat fluxes in the tube inlet. This requires efficient cooling of the tubes and tube sheet, which is accomplished by keeping the tube sheet wall thickness as thin as possible. These flexible tube sheet, typically (25 to 30 mm) thick, allows good cooling by the water on the rear face and lowers the operating temperature. Boilers used in fertilizer and petrochemical process plants, which have to work at very high operating pressures require a thicker tube sheet with the thickness ranging from 300 to 500 mm e.g. synthesis loop boiler in Ammonia plant. With conventional design for the tube to tube sheet joint, high heat flux at the tube inlet causes evaporation & decomposition of water in the gap between tube & tube hole resulting in severe crevice corrosion.
IIT BOMBAY
Crevice Corrosion
It can be characterized as a localized attack on a metal surface at or immediately adjacent to the gap or crevice between two joining surfaces. Outside the gap or without the gap, both metals are resistant to corrosion. The damage is normally confined to one metal at localized area within or close to the joining surfaces. Crevice corrosion is initiated by a difference in concentration of some chemical constituents, usually oxygen, which set up an electrochemical concentration cell. Figure 4.8.4 shows a typical tube to tube sheet joint attacked by crevice corrosion.
Crevice Corrosion
On the contrary, providing a full penetration tube to tube sheet weld for this application will ascertain tube sheet integrity, eliminate the crevice on water side and ensure the stress in the weld to be same as that of on the tube sheet.
Selection of Material
Generally metals are chosen in the fabrication of Boilers. Tube and tube sheet material used for manufacturing of boilers should meet the following basic criteria.
IIT BOMBAY
Resist high temperature H 2 attack and nitriding, Withstand design pressure and temperature, Provide sufficient ductility for forming operations, Provide easily weldability,
IIT BOMBAY
Figure 4.8.5 Nelson curve for use of material that would undergo H2 service conditions
IIT BOMBAY
This joint design calls for large-scale development of welding technology. Factors such as limited access, difficulty of gas shielding, high degree of preheat (1500C minimum) associated with creep resistant 1 Cr Mo steel and protection of weld penetration from oxidation etc.needs to be considered while selecting a suitable manufacturing (welding) procedure for producing this joint. Salient features of this type of tube to tube sheet weld is as follows Welding performed by manual gas tungsten arc welding process Full penetration joint welded in 12 to 15 layers Due to high thickness built up in layers, joint safety margin is very high Special GTAW torches are required for welding in narrow and deep groove using long projection of tungsten electrode. Large diameter ceramic nozzle with suitably designed gas lens is necessary for effective argon shielding inside the groove. Welding filler wire shall match the composition of tube and tube sheet material In order to account for the distortion, welding is carried out with 2 to 3 passes at a time at various portions of the tube sheet in a staggered way
IIT BOMBAY
Procedures have been qualified to ASME Code and various customer specifications with dye penetrant test, radiography examination, macro & micro examination and hardness survey across the joint. Highly skilled welders are required for producing this joint.
Here, unlike the Type-I design; the welding is completed in 2 to 4 passes depending upon the tube thickness. In the current design, the minimum leak path is very critical because of less safety margin. With lesser margin of safety, the production of a sound joint with consistent quality and repeatability is of prime concern for satisfactory operation under severe working conditions thus necessitating the requirement for automation of these weld joints. Generally these welds are performed by automatic GTAW process with tube sheet in vertical position.
IIT BOMBAY
Here welding is carried out by Internal Bore Welding technique from ID of the tube. The task becomes further critical due its non-accessibility since the welding has to be done at a depth of 300 500 mm from the Tube sheet face. The designer should have the full know-how of these requirements which would help him in selecting a suitable joint configuration for the given application.
IIT BOMBAY
Figure 4.8.9 Flow of manufacturing and assembly processes for tube to tube sheet joining
IIT BOMBAY
Table 4.8.1
Possible defects, associated causes and likely remedial measures during tube to tube sheet assembly
Possible Defects
Cause
Remedial Measures Sufficient flow of shielding and purging gas, proper cleaning of base metal and filler wire, etc. like low Use of proper welding parameters, clean surface
Porosity
In sufficient shielding & purging gas, unclean base material, unclean filler, etc. Improper welding parameters
current, high speed, unclean surface, etc. Improper welding parameters, improper arc
length, insufficient / excess flow of shielding Use of proper welding parameters, and purging gas, etc. Reduce heat input by reducing Excessive heat input current, increasing speed, use of heat sink, etc Improper welding parameters like high Use of proper welding technique and current, long arc length, high travel speed, etc welding parameters Low amperage, tight root opening, high Use of proper welding technique and travel speed, short arc length, etc. welding parameters Use of proper welding technique and High amperage, poor quality of tungsten welding parameters, use of good quality tungsten electrode, etc. Improper preheat temperature, high restraint, Follow recommended preheat, ensure unclean surface, base material impurity, etc. Incorrect welding technique. proper cleaning, etc. Use of proper welding technique
IIT BOMBAY
Mockup welding
Figure 4.8.10 depicts the details of the initial mock-up weld joints that must be produced before the final assembly is made.
Figure 4.8.10 Suggested mock-up welding practices for tube to tube sheet joining
Visual Examination
The mockup weld joints shall be subjected to visual examination as below [Figure 4.8.11].
IIT BOMBAY
Figure 4.8.11 Guidelines for visual inspection of for tube to tube sheet mockup welds
Figure 4.8.12 Acceptance criteria in liquid penetrant examination of tube to tube sheet mockup welds
IIT BOMBAY
Macro Examination
Mockup welds shall be subjected to macro-examination as per details in Figure 4.8.13.
However, over and above the code requirements, the mockups are also subjected to various testing based on the job specification requirements like X-ray radiography and ultrasonic testing, pull out and tearing testing, crack and flaw examination, etc.
Type-I joints are subjected to visual examination, dye penetrant examination, air test and global hydro-test. The Type-II joints are subjected to visual examination on front and root side of weld, dye penetrant examination, air test, and global hydro test. The Type-III joints are also subjected to visual examination on front and root side of weld, dye penetrant examination, radiographic examination, air test, individual joint helium test, individual joint hydro test and global hydrotest.
Acknowledgements
The help and complete support of Mr. M K Mukherjee and Mr. S. Krishnan from M/s Larsen and Tubro (Powai, Mumbai, India) are sincerely acknowledged for the preparation of the above casestudy.
IIT BOMBAY