E & M of E.O.T.
E & M of E.O.T.
E & M of E.O.T.
CRANES:-
1.1GENERAL:
An E.O.T. crane stands for Electric Overhead Travelling crane. this is used for handling &
moving a maximum specified weight of the components called capacity of the crane within
a specified area. the crane can be operated manually or by electric power. electrically
operated crane can be divided into different sections as follows:-
1.2ERECTION OF CRANE:-
Besides testing the rope & trusses for strength, they should be tested for stability
under horizontal forces acting at right angle to the truss plane.
The winches employed for lifting the crane should be equipped with ratched stops.
The wire rope employed for erection must have tags indicating wire breaking forces
& should be free of defects, fractures, kinks etc.
When hoisting the crane or its parts the following conditions should be kept in mind.
(a) The angle of inclination of the slings should not be less than 45º.
(b) To prevent rupture of the rope due to sharp edges of lifted materials, wooden or metal
lining should be used.
(c) The number of clamps to be used for fastening the rope should be sufficient.
We should also ensure that the axes of the winch drum should be exactly at right
angle to rope direction.
Depending on the weight of the crane, the strength of the rope, trusses, the crane
can be lifted by one winch or two or four winches. if the weight of the crane is not
very high the crane structure can be assembled at the floor & the complete crane can
be lifted. in case the crane is very heavy we may lift different portions of the crane in
sequence as follows:-
For the safety of the people engaged in erection work, the following safety rules
should be observed:-
1. When lifting the crane structure the dangerous zone of assembly must be protected
with flags barriers etc. & no un-authorised person should be admitted in the area.
2. Do not lift the crane if the erection area is badly illuminated.
3. Although the lifted structures should not be allowed to suspend for a long time but in
case of exception we must see that:-
(a) The safety factors of the ropes & cross girders should be twice than the normal
working.
(b) The last line of rope running off the blocked should be clamped near the block.
(c) In case the load is lifted by means of hand winch, remove the handles, apply &
secure the brakes.
(d) Post workers to ensure security.
4. It is strictly forbidden to stand or walk under the crane when the crane is being
lifted.
5. The scaffolds must comply with the safety rules. the fitter working on top, must
handle the parts & tools carefully so as to prevent them to fall down.
The erection supervisor must ensure that all the components are assembled in
accordance to the sub assembly drawings. after the crane has been fully erected,
we must do the electrical connection exactly as per its wiring diagram. before
we actually do the load test we must run all the motions in idle condition. during
idle running of different motions we should particularly observe the following:-
(a) Eccentric running of moving parts.
(b) Alignment of shafts.
(c) Fauling of moving components.
(d) Any un-usual noise.
(e) Presence of lubricant at desired surfaces.
After the idle running of different motions & satisfactory performance of motors,
limit switches, brakes & controllers we may go ahead with load testing of the
crane in accordance to relevant Indian standards.
If the contract for erection & commissioning of the crane is not given to the
manufacturer of the crane, it will be desirable to seek their supervision during
Erection & commissioning. This will ascertain the alignments of components &
thus longer life of the crane.
Fig.:- Aerial View of E.O.T. Cranes.
2. OPERATION:-
2.1 MECHANICAL:-
Before operation, check all parts are lubricated properly as per lubricating chart.
electrical wiring is to be completed as per wiring diagram. during initial test it
should be checked that bridge, crab & other components mounted on crab are
clear of roof beam & walls. all motors are connected properly & that the limit
switches cut off the supply to motors in proper direction. In case the limit
switches don’t cutoff the supply in the proper direction make the necessary
changes in wiring. the crane should be run light for a little while before loading
the same & it should be checked that all the limit switches work satisfactorily.
Commence lifting the load in stages, starting with not more than 5% of the safe
working load & then increasing this gradually in succeeding trails, till you have
reached the full load. during this we must ensure that any part of the crane
does not show any sign of giving way while going through all motions of
hoisting, traverse & travel. finally, test the crane with 25% overload before
the same is put into operation.
2.2 ELECTRICAL:-
Before pressing ‘ON’ Push button of main contactor, see that all drum controllers
or master controllers are in off position. there are 4, 6, 8 steps in drum controller
depending on HP. of motor. on the 1st step full resistance of resistance box is
inserted & smoothly all resistance is cut off by the controller. whenever motor
gets supply, brake is released, thus allowing motor to accelerate smoothly.
whenever motor supply is cut off, thrustor brake applies brake & brings the motor
to stand-still. whenever load reaches extreme position, limit switch cuts off the
supply to that motor in that particular direction & load can’t be moved further
in that direction. the operator can move the load in backward direction by moving the
drum controller in reverse direction, or pressing the related push button.
Hand operated & electric hoist & trolleys of different types are deigned with the
safety of the operating personnel first in mind. your own safety & that of your
fellow workers will be assured when overhead materials handling equipment
is used as recommended by the manufacturer. disregarding such recommendations
endangers life & property. Following are the basic rules worthy of your careful
consideration & attention.
1. Do not load beyond the rated capacity- the immediate danger is the possible
failure of some load carrying parts. Overloading might also start a defect
which could lead to some future failure even at less than rated capacity.
2. Do not use any overhead materials handling equipment for handling personnel.
4. CALCULATIONS:-
4.1 ELECTRICAL :-
To determine the relationship between rotor weight, MVA rating & speed.the rotor weight
was proportional to the output & inversely proportional to the square root of the
speed.however, a wide variation in rotor weight was found, which could only be explained
by variations in unit design & method of rating.
Rw = 50(MVA/n0.5) 0.74
Where, Rw= Rotor weight in tones for rotors with standard inertia.
MVA= Rotor rating at 60ºC temperature rise.
n = Rotor speed, 90 rev/min minimum.
This equation is used to determine the weight of a generator rotor for units with standard
inertia & speeds in excess of 90 rev/min. Data obtained for units with slower speeds
indicated a wide variation in rotor weight .when plotted in the same manner, & therefore it
was not possible to derive a formula for large slow speed units.the study had to be confined
to relatively small rotors with ratings below about 100MVA.since large rotors are
connected to major power networks where added inertia is not a requirement.it is only on
small & isolated systems where extra inertia is required for stability. Standard inertia for
generator rotors can be determined from the following equation.
Rw = 50(MVA/n0.5)0.74{ 1+ C(K-1)}
Where,
C= Coefficient of added inertia.
K = Inertia ratio defined as rotor inertia divided by standard inertia.
In the case of an overhauling load when using an adjustable frequency control & a squirrel
cage motor, the speed of the motor & load is directly a function of the applied frequency to
the motor. By changing the applied frequency to the motor, the synchronous speed of the
motor changes in accordance with the following equation:
Where, f is the applied frequency & P is the number of poles in the machine.
4.2 MECHANICAL:-
4.2.1 TORQUE:
The horsepower equation may be used to determine the maximum continuous full-load
torque a motor can produce. The equation is:
T= HP×5250
-----------
N