Ch15 Taylor
Ch15 Taylor
Ch15 Taylor
In SI units:
Power is in (kW), Energy is in (kW-sec), Rotational inertia is in
(kg-m
2
)
k = 9.1189 10
4
(rpm
2
-kg-m
2
/[kW-s])
k
2
= 5.49 10
!6
(kW -sec-min
2
/[kg-m
2
])
k
3
= 1.0 (kW-sec/kJ)
Acceleration (rpm/s):
The instantaneous acceleration is 626.7 rpm/sec.
Trapped energy:
In this example there is only one area of trapped energy to consider:
The total trapped energy is 926.07 hp-sec (691 kW-sec).
Acceleration (rpm/s):
The instantaneous acceleration is 393.6 rpm/sec.
Trapped energy:
In this example there are three principle volumes to consider:
Between stop valve and first stage nozzle,
Between reheat stop valves and reheat turbine, and
Crossover pipes between IP and LP turbines:
Additionally, extractions and turbine shell contribute 29,625 hp-sec
(22,100 kW-sec) (from manufacturer). The total trapped energy is
162,781 hp-sec (121,435 kW-sec).
Acceleration (rpm/s):
The instantaneous acceleration is 1480.9 rpm/sec.
Trapped energy:
In this example trapped energy is negligible. The total trapped
energy is 0 hp-sec (0 kW-sec).
Table of Contents
Maximum rotor speed (rpm):
Converting the total rotor energy into speed, gives the maximum
rotor speed as 4631 rpm.
If a 10 percent rise above the trip speed is allowed, then this response
is not acceptable.
If the control time is varied the following maximum rotor speeds:
With this smaller turbine, it is interesting to note that a control
delay time of only 0.3 seconds would result in the 127 percent
speed being exceeded.
TEST METHODOLOGY
Regular, periodic testing is the only way to ensure a protection
system is working. In some cases, without exercising the system,
mechanical components may become stuck rendering the protection
system inoperable. Regular testing of stop or trip valves is generally
recommended on a weekly or monthly basis where possible.
Additionally it is recommended to shut down with the trip valve(s)
whenever possible.
One of the largest owner/operators of power generation
equipment requires annual testing on large machines. For
mechanical bolts a minimum of two tests are required. If the trip
speed of the second test is higher than the first, then a third
test is required. Electronic systems can be tested at lower
speed. Where there are exceptions to this rule the specific
test requirements would have to be recommended by the
turbine OEM.
Another very large owner/operator allows low speed trips
for testing but requires a full stress (full speed) test after any
front standard work that could affect speed sensors, wiring,
and gap.
Specific test recommendations will come from OEMs and
insurance carriers and each owner/operator will establish test
requirements for a specific unit. There are a number of studies that
discuss testing frequency based on recorded failure probability
either across the industry or for a given site. These procedures
should not be considered static. As more experience is gained with
the unit or as the unit is modified, these procedures, test scope, and
test intervals, should be reexamined. Also, as root causes of
incidents of all units are examined and shared, new best practices
may be recognized.
Low Speed Testing
On generator applications, the full overspeed test point exerts
tremendous forces on the rotating components of the turbine and
generator. This can lead to increased maintenance costs in the long
run so there is some incentive to perform the overspeed system test
at a lower rpm.
On compressor or pump applications, it is often (but not always)
physically impossible to achieve the overspeed setpoint with the
compressors or pumps connected. So users perform overspeed
tests with the units uncoupled. Uncoupling and recoupling is a
labor intensive process. When uncoupled, the rotational inertia of
the system is greatly reduced. This means the control dynamics for
the normal system and the uncoupled system are different. This
may require entering a different set of dynamics or retuning the
governor system for testing (and making sure the original
governing system dynamics are restored when the test is
complete). In some cases special functions have been added to the
governing system to support additional modes for uncoupled
testing. Again, there is a risk that the modes of operation be
specified or selected correctly.
In both of the above cases there are compelling reasons to
perform at least some of the tests of the overspeed protection
system at a lower speed. But, insurance carriers and corporate
testing requirements must also be met. Some sites require
validation of the trip system functionality at full speed but then
allow lower speed tests provided no changes are made in the
system, particularly with the speed pickup, brackets, or sensing
gear that could affect the ability to properly sense speed. There
are some specific case examples that demonstrate the value of
full speed testing.
Trip System Testing While Running
Many units run for long periods of time, multiple years, between
outages. So there may be extended periods of time where actual trip
testing cannot be performed. To ensure reliability and availability
of the overspeed protection system, periodic partial system testing
is performed. This may include confirming mechanical/hydraulic
operation of a part of the trip system or performing some simulated
test on part of the electronic system while the trip circuit is partially
blocked. Ideally the systems should be designed with enough
redundancy that protection is not compromised during the test
process (but this is not always the case).
In some systems it is possible to do some level of valve testing
either at rated or reduced load conditions. While this is valuable,
and in some cases necessary to ensure the operation of the valve, it
does not guarantee a proper seating of the valve. So there is still a
case for a full functional trip test (although this need not be from
full trip speed).
Risks of Testing
An overspeed event requires three components:
Loss of load,
Table of Contents
testing is required prior to performing a full overspeed test.
This may include performing a low speed test prior to full
speed testing.
After a successful test is performed it is equally important that
the system be restored to the normal operating state. A second set
of tests, such as simulated speed testing if the setpoint was changed,
should be performed to confirm the system is correctly restored to
its normal operating conditions.
INCIDENTS AND ROOT CAUSE ANALYSIS
In one case a boiler feedpump turbine (BFPT) was tested at less
than full overspeed trip for years. The setpoint was dialed down for
the test and then reset. A safety audit required a full speed test. At
8000 rpm the unit did not trip and an emergency trip was selected.
Next year the trip failed again. The third year the controls group got
involved. The trip system electronics and program appeared to be
correct. When the turbine was tested, above 6200 rpm the
overspeed device started to miss pulses and the sensed speed
dropped but not enough to trigger loss of speed sensed logic. Work
was done by the OEM on the front standard and on the sensing
wheel and the unit worked. Although the exact cause of the problem
was not identified, one thought is that the rotor shifted slightly at
high speeds and that only in those conditions would the speed
signal be partially lost. Tests with a frequency generator to simulate
speed would not have exposed this problem.
In another case a BFPT was tripped for no apparent reason. Just
prior to this, another BFPT had tripped and the distributed control
systems (DCS) increased the demand to the second BFPT. It picked
up speed and tripped. It was not immediately obvious that an
overspeed had occurred. On analysis of the data it was recognized
that it tripped at the mechanical overspeed trip setpoint. The
electronic governor setpoint was scaled as 0 to 10,000 rpm when
the operating range was only around 8000 rpm. The controllers
protected overspeed were set to 105 percent of this total range
(not 105 percent of the normal maximum operating point). On this
unit additional instrumentation was added to annunciate the
overspeed bolt trip and the controller was rescaled to the proper
operating range.
It is critical that the industry look to and share incidents and root
cause analysis to determine how to prevent the repetition of mistakes.
RESPONSE TIME TESTING
API 612 (2005) 16.3.4.6 states, The response time of the
overspeed shutdown system shall be recorded to confirm compliance
with the requirements of 12.3.1.1. But this is in a list of optional
tests that may be performed as shop tests and not a regular
test requirement.
A great deal of emphasis is placed on overspeed testing but this
is done under controlled conditions. Speed is raised slowly to the
trip point. This confirms the overspeed trip setpoint but does
nothing to confirm the dynamic response of the trip system. This
factor is as critical as the setpoint.
The authors have shown that the response time of the entire
trip system is critical to the protection of the turbine and that
relatively small variations (undetectable to an operator) are very
significant. Since the timing of these electrohydraulic circuits is
so important and the systems so complex, the need to periodically
record the trip time and then trend those response times to
identify any progressive degradation in the system seems
obvious. In the past, achieving a resolution of 1mS to evaluate the
response time of a trip system would require specialized
equipment but today this is readily available from sequence of
event (SOE) cards in DCS systems and programmable logic
controller (PLC) systems.
Periodic trip system response time testing, as with the overspeed
setpoint testing, is needed to ensure the overspeed prevention
system is operating as designed and that the required level of
equipment and personnel protection is provided.
REFERENCES
API Standard 612, 2005, Petroleum, Petrochemical and Natural
Gas IndustriesSteam Turbines Special Purpose Applications,
Sixth Edition, American Petroleum Institute, Washington, D.C.
API Standard 670, 2000, Vibration, Axial-Position, and Bearing-
Temperature Monitoring Systems, Fourth Edition, American
Petroleum Institute, Washington, D.C.
ASME PTC-20.2, 1965, Reaffirmed 1986, Overspeed Trip
Systems for Steam Turbine-Generator Units, American
Society of Mechanical Engineers, New York, New York.
Cote, C., 2008, Small Steam Turbine Trip System Simulation and
Analysis, Unpublished Report ER08112A.
Hesler, S. 2004, Review of Nuclear Industry Experience with
Turbine OPS Reliability Since 1990, Presentation at EPRI
Turbine Overspeed Risk Management and Reliability
Improvement Workshop, February 3-4, Chicago, Illinois.
Jacoby, J., 2008, Designing Overspeed Trip Systems for Large
Power Plant Steam Turbines, Invensys Turbomachinery
Controls Publication.
Younie, D., 2009, Mechanical Overspeed Trip Device Upgrades,
Presentation at Mile High Industrial and Automation
Conference, March 31/April 1.
BIBLIOGRAPHY
Clark, E. E., 1996, Rotating Equipment Loss PreventionAn
Insurers Viewpoint, Proceedings of the Twenty-Fifth
Turbomachinery Symposium, Turbomachinery Laboratory,
Texas A&M University, College Station, Texas, pp. 103-122.
Clark, E. E., August 2004, Steam Turbine Overspeed Incidents.
EPRI, 2003a, Turbine Overspeed Risk Management and Reliability
Improvement Workshop, Palo Alto, California, 1009333.
EPRI, 2003b, Guidelines for Reducing the Time and Cost of
Turbine-Generator Maintenance Overhauls and Inspections,
Volume 1: General Practices, Palo Alto, California, 1009333.
EPRI, 2006, Turbine Overspeed Trip Modernization: Requirements
and Implementation Guide, Palo Alto, California, 1013461.
FM Global, January 2005a, Property Loss Prevention Data Sheets
13-3 Steam Turbines.
FM Global, January 2005b, Property Loss Prevention Data Sheets
13-7 Gas Turbines.
Peterson, J. R. and Schafer, T. K. Jr., June 2005, Insuring Best
Practices, Power Engineering.
Rudd, J., 1999, Electronic Overspeed Detection Systems,
ORBIT, Second/Third Quarters.
Rutan, C. R., 2003, Turbine Overspeed Trip Protection,
Proceedings of the Thirty-Second Turbomachinery Symposium,
Turbomachinery Laboratory, Texas A&M University, College
Station Texas, pp. 109-120.
Schleis, J., 2007, Turbine Speed MeasurementSafety and
Design Considerations, Presentation to Baton Rouge Local
ISA Chapter, March 22.
ACKNOWLEDGEMENTS
Ross Campbell, Southern CompanyThanks for discussions on
test requirements and for sharing some of your experiences.
Edward Clark, Starr Technical Risks Agency, Inc.Thanks for
your discussions regarding incidents and for sharing your experience
and thoughts on protection system testing. Also, thank you for
collecting some more information on current industry practices
with respect to trip time testing.
PROCEEDINGS OF THE THIRTY-EIGHTH TURBOMACHINERY SYMPOSIUM 2009 166
Table of Contents
Charlie Cote, BarnCat Engineering ServicesThank you for
discussing some of the more subtle issues associated with the
mechanical characteristics and responses of turbine systems,
valves and actuator assemblies, and trip systems.
Ding Junying, ConstarThanks for your review and recommen-
dations. They contributed significantly to the readability of this
document. Thanks also for your comments on valve related issues.
Rex Horvath and Matt Cain, Wood GroupThank you for
providing access to your test equipment and supporting some of the
authors investigations.
Jim Jacoby, InvensysThanks for the preview of the new API
annex L.
Rich Kamphaus, WoodwardThanks for your support, review,
and help with the API recommendations.
Charles Rutan, Lyondell EquistarThanks again for your
review, suggestions, and support.
Jeff Schleis, Wood GroupThanks for your insight on speed
sensing issues.
167 TURBINE OVERSPEED SYSTEMS AND REQUIRED RESPONSE TIMES
Table of Contents
PROCEEDINGS OF THE THIRTY-EIGHTH TURBOMACHINERY SYMPOSIUM 2009 168
Table of Contents