Health and Safety
Health and Safety
Health and Safety
2014
Table of Contents
1.0 INTRODUCTION ................................................................................................................ 1 2.0 NATURE OF THE CONSTRUCTION WORK ......................................................................... 2 2.1 Scope of Work .............................................................................................................. 2 2.2 Schedule of work ......................................................................................................... 2 2.3 Working Hours ............................................................................................................. 2 3.0 ORGANISATIONAL ARRANGEMENTS ................................................................................... 3 Contracting Arrangements: ................................................................................................... 3 Construction Supervision: ...................................................................................................... 3 4.0 APPOINTMENT OF PROJECT SUPERVISORS ......................................................................... 4 5.0 COMMUNICATION ............................................................................................................... 5 5.1 Communication between Designers and PSCS ................................................................ 5 5.2 Pre-Construction Meeting ............................................................................................... 5 6.0 THE EXISTING ENVIRONMENT ............................................................................................. 6 6.1 Existing services: .............................................................................................................. 6 7.0 INFORMATION ON THE PRESENCE OF PARTICULAR RISKS TO SAFETY & HEALTH .............. 6 7.1 Construction Work Involving Particular Risks .................................................................. 7 7.1.1 Aggravated risk of falls or burial ............................................................................... 7 7.1.2 Risks from chemical or biological substances ........................................................... 7 7.1.3 Risks from high voltage ............................................................................................. 7 7.1.4 Risk of drowning ....................................................................................................... 7 7.1.5 Risks from underground work .................................................................................. 8 8.0 PLANS FOR CHECKING THE IMPLEMENTATION OF SAFE WORKING PROCEDURES ............ 8 8.1 Site Meetings ................................................................................................................... 8 8.2 Safety Inspection.............................................................................................................. 8 8.3 Safety Audits .................................................................................................................... 8
8.4 Safety Inductions ............................................................................................................. 9 8.5 Accident / Incident Record Book ..................................................................................... 9 8.6 Record Keeping ................................................................................................................ 9 9.0 SITE RULES .......................................................................................................................... 10 9.0 FIRST AID ............................................................................................................................ 12 9.1 Emergency Contact Details ............................................................................................ 12
1.0 INTRODUCTION
This document is prepared in accordance with the requirements of the Safety, Health and Welfare at Work (Construction) Regulations 2006 otherwise known as the Construction Regulations. This Preliminary Safety and Health Plan covers the design process for the project. Its main purpose is to provide information to the Project Supervisor for the Construction Stage to allow the preparation of the site induction meeting, Site Specific Safety Statement and help the PSDP compile or update the Safety File. The Preliminary Safety and Health Plan will be made available to all those tendering for the role of Project Supervisor for the Construction Stage (PSCS). It will be the duty of the appointed PSCS to further develop the Preliminary Safety and Health Plan during the construction stage. The PSCS shall develop, implement and monitor the controls deployed to mitigate the risks associated with the hazards identified in this plan. Having regard to the progression of works, additional hazards maybe identified during construction.
Contracting Arrangements:
A main Contractor shall be appointed to carryout the works. Contracts will be entered into for the main Contract.
Construction Supervision:
Construction will be supervised by the appointed main contractor. The designers will make periodic inspection visits.
I wish to confirm acceptance as PSCS for the project: ______________________________. Health and Safety Officer for Construction Stage: To be Confirmed Any changes of personal must be formally made by writing and acknowledged by the new appointed personal.
5.0 COMMUNICATION
5.1 Communication between Designers and PSCS
Arrangements shall be put in place to facilitate the provisions of any design assumptions or matters relating to safety as identified by the design process.
The provision of information regarding the indicative control measures as identified in the Design Process Risk Assessment
Agree Traffic Management Plan Exchange contact details of PSDP and PSCS
Minutes from the pre-start meeting must be recorded and filed on the Safety and Health File. If the indicative or proposed Traffic Management Plan (TMP) conflicts with the PSCS/Contractors schedule of works a revised TMP must be agreed with between the PSDP and PSCS before commencement of the works. The PSCS is to include the revised TMP in the Developed Safety and Health Plan.
Particular risk identified There will be the normal risk of working in the Vicinity of high voltage power lines where carrying out excavation work along roads etc. 7.1.4 Risk of drowning Work exposing persons at work to the risk of drowning. Particular risk identified
This risk does not arise within the proposed construction area.
7.1.5 Risks from underground work Work on wells, underground earthworks and tunnels Particular risk identified The will be normal risk of working in the vicinity of foundation trenches, construction of dairy washings pit, etc.
8.7 Arrangements for Reporting and Recording of Accidents and Dangerous Occurrences
Notification of Accidents to H.S.A. (where applicable) will be done by the injured persons Employer, using the approved Form IR1. All accidents on Site will be notified to the main contractor, and investigated by them if appropriate to prevent recurrence. Any dangerous occurrence must be investigated and steps taken to avoid a recurrence. Accidents involving injury to any member of the Public are immediately reported to the H.S.A. using the approved form IR1.
1. All site visitors, personnel and contractors are required to comply with the Site Safety and Health Policy and the specific Construction Stage Safety and Health Plan. 2. The PSCS shall ensure that all subcontractors are assessed with regard to their level of competence and availability of resources. 3. All risks identified in the Design Process Safety and Health Plan and in the Health, Safety and Welfare (Construction) Regulations 2006 are to be individually identified and addressed by the PSCS. 4. Method Statements and Safety Statements should be reviewed and revised on an ongoing basis to take into account any new issues which arise during the course of the works. Revisions, which could affect safety, health and welfare, should be raised at site meetings. 5. All site personnel and safety and health personnel should be advised on an ongoing basis of any revisions to the Safety and Health Plan by the PSCS/Health and Safety Coordinator for Construction Stage. 6. Standard and proof of adequate training of personnel on site should be included in the Safety and Health Plan prepared by the PSCS/Health and Safety Coordinator for Construction Stage. 7. Smoking is not permitted within designated working areas. 8. Eating and drinking should not be allowed in designated working areas. 9. The PSCS/Health and Safety Coordinator for Construction Stage should ensure that all excavations are supported in accordance with the requirements of the 2006 Regulations. 10. The PSCS/Health and Safety Coordinator for Construction Stage must ensure that all relevant Safety and Health Regulations are adhered to at all times. The information contained in this Safety and Health Plan has been prepared prior to the commencement of the work on site. Signed: ______________________________ (Project Supervisor for Design Phase) Signed: ______________________________ (Health and Safety Coordinator) Date: ______________ Date: ______________
The Health and Safety Plan must be kept and for 5 Years.
Emergency Details
First Aider (s): To be confirmed
044-123456
Local A&E/Hospital:
Cavan Regional Hospital 049-123456
057-123456
Local Doctors:
043-123456
Local Gardai: