The daily work report summarizes construction activities on January 4, 2009 for the expansion of the KINDASA Tanker-Filling Station #1. Key tasks completed included the installation of power cables, roof columns for Tank 3, and excavation for an 800 mm grp line. Daily equipment usage and staffing levels are provided. No safety incidents were reported.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online from Scribd
The daily work report summarizes construction activities on January 4, 2009 for the expansion of the KINDASA Tanker-Filling Station #1. Key tasks completed included the installation of power cables, roof columns for Tank 3, and excavation for an 800 mm grp line. Daily equipment usage and staffing levels are provided. No safety incidents were reported.
The daily work report summarizes construction activities on January 4, 2009 for the expansion of the KINDASA Tanker-Filling Station #1. Key tasks completed included the installation of power cables, roof columns for Tank 3, and excavation for an 800 mm grp line. Daily equipment usage and staffing levels are provided. No safety incidents were reported.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online from Scribd
The daily work report summarizes construction activities on January 4, 2009 for the expansion of the KINDASA Tanker-Filling Station #1. Key tasks completed included the installation of power cables, roof columns for Tank 3, and excavation for an 800 mm grp line. Daily equipment usage and staffing levels are provided. No safety incidents were reported.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online from Scribd
Download as xls, pdf, or txt
You are on page 1of 1
DAILY WORK SCHEDULE REPORT
Project : Expansion of KINDASA Tanker-Filling Station #1 Weather : Sunny Date 01/04/2009
Work Done Today WEDNESDAY 01/04/2009
installation of power cables for MCC panels for pumps
Installation of roof coloums for tank-3 Excavation in progress for 800 mm grp line inside the seaport area completed Installation of power fedder panals for CPS system for external /internal Installation of roof coloums for tank-3 Daily Equipment / Tools Status Description Prv. Ttl Today Total Description of Equipment Total Project Manager 277 1 278 bobcat 1 M. Engineer 197 1 198 forklift 0 Site.Engineer 210 1 211 dyna 1 Surveyor 78 1 79 mini roller 0 Site Supervisor 51 1 52 air compressor 1 Labourers 3768 19 3787 plate Compactor medium 2 Operators 779 1 780 Welding machines 11 crane Operator 166 1 167 butt welder 2 generator 2 Total Station 0 Levelling Instrument 1 Fire Extinguisher 1 Crane 1
Total No. of days 4776 19 4795 Total 23
Material Received Today S.No Description Prv. Ttl Today Total
1 Average No. of workers 7833 19 7852 2 No. of Lost time Accidents 0 0 0 3 No.of Restricted work Cases 0 0 0 4 No. of Medical Treatement Cases 0 0 0 5 No. of First Aid Cases 0 0 0 6 No. of occupational illness Cases 0 0 0 7 Any Accident on site Cases 0 0 0 8 Any Incident on site Cases 0 0 0
Site Manager Salco Received ACEC/ACE
Eng'r Nasser Omar Eng'r Saeed Omar/ Eng'r Abdul Aziz