Contoh Fyp Gmi
Contoh Fyp Gmi
Contoh Fyp Gmi
CHAPTER I
INTRODUCTION
We have overcome to make a Post-Mix Instant Noodle Machine for our Final year
project in our last semester at German Malaysian Institute. This project is being set off
as one of requirement to finish our diploma program and the most important thing is it
gives us a feel of a real working life by making a machine that we create and apply all
things that we have study during these three years of diploma.
First of all, this idea comes from when one of our members wanted to eat instant
noodle. Later we found out that making an instant noodle ready to eat has some step to
follow. So it was good to make our busy live much easier if we have make a ready to
eat instant noodle machine. As it was like a vending machine that are easy for us to
use.
Page |2
1.2 OBJECTIVES
Project Objectives:
The objectives we doing this project are to design and construct Post-Mix
Instant Noodle Machine and acquainting with the process to fully automatic process. As
also to assemble the new machine for SMI (Small Medium Industry) and produce the
cooked instant noodle in 2 minutes.
Page |3
CHAPTER II
Refer to our senior, which is have been done their Final year project to get the
guidance through doing the project.
Give solution through idea, knowledge, skills and experience while studying at
German Malaysian Institute and during Industrial Training.
Page |4
Page |5
Figure 2.1: Primary Source
Material that we are using for placing flavour is plastic. Plastic used in food
packaging should be of greater purity than plastic used for non-food packaging. Food
grade plastic does not contain dyes or recycled plastic deemed harmful to human. It
has to follow HACCP (Hazard Analysis and Critical Control Point) standard
(Source : Plastipedia.co.uk)
Page |6
Resistance to Chemical
Aliphatic Hydrocarbons *
Aromatic Hydrocarbons *
Halogenated Hydrocarbons *
Alcohols ****
good ****
very good
(Source : Plastipedia.co.uk)
It is suitable for oven use. Our silicon ware is manufactured from state-of-the-art
material that is light, flexible & withstands temperatures ranging from -25C to 220C,
making it ideal for use in the freezer, refrigerator, microwave & conventional oven.
The fork and glass symbol guarantees the suitability of using Tupperware products for
foodstuffs. It means that the product has been tested and proven to not transfer
Page |7
components into food in quantities that can endanger human health, change food
composition in an unacceptable way or deteriorate its taste & odour.
Stainless steel is used for the water heating tank. We had chosen to use the
stainless steel grade 304 because it is suitable to be used as water heating tank. The
SS304 also have low carbon properties thus making it safe to use to boil water.
A heating element converts electricity into heat through the process of Joule
heating. Electric current through the element encounters resistance, resulting in
heating of the element. Most heating elements use Nichrome 80/20 (80% nickel, 20%
chromium) wire, ribbon, or strip. Nichrome 80/20 is an ideal material, because it has
Page |8
relatively high resistance and forms an adherent layer of chromium oxide when it is
heated for the first time. Material beneath the wire will not oxidize, preventing the wire
from breaking or burning out.
Experiment 1
Title
Date
: 30/4/2011
Objective
Equipments
: 1) Suction cup
2) Bowl
3) Bowl dispenser
Method
Discussion
: When suction cup try to pull the bowl downwards, the bowl did
not follow it. It seems that the suction cup did not give enough
vacuum air to make bowl removes from bowl dispenser or the
bowl dispenser is too tight for the bowl to removes.
Page |9
Conclusion
Recommendation
: Use a bigger suction cup so it has enough air to pull the bowl.
Experiment 2
Title
Date
: 30/4/2011
Objective
Equipments
: 1) Pump motor
2) Hose
3) Tank
Method
Discussion
: When the motor start running, the water flows too fast inside
the tank. It seems that we had to control the water flow as our
tank is small and only need 300ml water in one time.
Conclusion
P a g e | 10
Recommendation
: Put on water level sensor so that motor pump will stop when
sensor detect.
Experiment 3
Title
Date
: 29/4/2011
Objective
Equipments
: 1) Temperature controller
2) Heater
3) Tank
4) Thermocouple
Method
: 1) Put water inside the tank with heater at side of tank and
connect the thermocouple with temperature controller
2) On supply for heater and temperature controller and start
process
3) Wait until temperature controller cut off which mean it reach
curtain degree of heat.
P a g e | 11
Discussion
Conclusion
Recommendation
P a g e | 12
Experiment 4
Title
Date
: 30/4/2011
Objective
Equipments
: 1) Suction cup
2) Bowl
3) Bowl dispenser
Method
Discussion
: When suction cup try to suck the bowl downward, the bowl did
follow it. It shows that the suction cup have enough vacuum air
to make bowl removes from bowl dispenser.
Conclusion
: Success, suction cup can pull the bowl downward and remove
it from the bowl dispenser.
P a g e | 13
Recommendation
: As other option, if does not have a bigger suction cup, use two
small suction cup as it is also can give enough air to pull the
bowl.
Experiment 5
Title
Date
: 24/5/2011
Objective
Equipments
: 1) Heater
: 2) Relay
: 3) Power Supply
: 4) Test pen
: 5) Water
Method
P a g e | 14
: 5) See if water is boiling or not
Discussion
Conclusion
Recommendation
Auditing methods also has to be considered to avoid over budget. The method
includes:
Make the decision. Consider the cheaper price, good quality and fast delivery.
P a g e | 15
For the recycled components, it has to be checked thoroughly to make sure the
component are usable and in good condition. If there some damage components or
parts cannot be used anymore, change it if it is still available. Otherwise get the new
one from the supplier.
This second method is meant for items, which is low in terms of amount or
value that cannot be purchased in credit item. Due to that, we have to buy it in cash.
This petty cash will only be provided at the end of the month during the implementation
stage through the number of claims, which varies among the different group.
This method is used for the parts that use a large amount of money or standard
part that have a certain specification and to buy at the place itself.
Firstly, we need to give the part specifications to the right company or supplier
and wait for them to give a review about their current product according to the
specification that has been given. Once we are satisfied with the product given, we will
ask for the quotation on product price. Later, after receiving the quotation, we will do a
purchased request for a product to send to GMI finance for their reference and account
statement. One member in a group represent for RM1000 for a project budget. Once
finance receive purchase request, they will process the purchased order for us to send
to the supplier.
P a g e | 16
Recycled part is the part that is being used for the past semester student or part
that are commonly use for all mechatronics course.
Mechanical component
No. Component
Quantity
Price / RM
100
0.50
50.00
330.00
660.00
TOTAL
710.00
Pneumatic component
No
Component
Quantity
Price / RM
250.00
1500.00
250.00
500.00
Standard cylinder
250.00
1500.00
Vacuum module
450.00
900.00
Solenoid valve
250.00
250.00
TOTAL
4650.00
P a g e | 17
Table 2.2: List of Pneumatic Parts (Recycle Part)
Electrical component
No. Component
Quantity
Price
MCCB
8.00
RM 8.00
ELCB
50.00
RM 50.00
Programmable logic
2000.00
2,000.00
controller
4
Expansion module
1250.00
1,250.00
Tower lamp
120.00
120.00
Terminal block
70.00
70.00
Buzzer
32.00
32.00
Emergency button
20.00
20.00
Pushbutton
2.00
6.00
10
Dc geared motor
500.00
2,000.00
11
Dc geared motor
1000.00
1000.00
12
Ac pump motor
159.00
159.00
13
Reed switch
15
75.00
1,125.00
14
Thermocouple
50.80
50.80
15
Temperature Controller
805.00
805.00
16
180.00
900.00
TOTAL
Table 2.3: List of Electrical Parts (Recycle Part)
9595.80
P a g e | 18
No. Component
Price / RM
Pneumatic component
4650.00
Electrical component
9595.80
Mechanical component
710.00
TOTAL
14,955.80
Table 2.4: Total Cost Recycle Parts
Mechanical component
No. Component
Quantity
Price / RM
330.00
660.00
75.00
300.00
TOTAL
960.00
Electrical component
No. Component
Quantity
Price / RM
40.00
40.00
Heater
TOTAL
40.00
Fabrication component
No. Component
Quantity
Price
1000
1000
Boiler Tank
TOTAL
1000
P a g e | 19
Table 2.7: List of Fabrication Parts
Miscellaneous component
No. Component
Quantity
Price / RM
RM
1
Instant noodle
1 packet x 8
13.80
13.80
pieces
2
Curry flavour
1 packet x 500g
6.50
6.50
Chicken flavour
1 packet x 500g
7.00
7.00
Soto flavor
1 packet x 500g
6.00
6.00
Container
1 x 30 container
RM 12.00
12.00
TOTAL
45.30
No. Component
Total Price / RM
Mechanical component
960.00
Electrical component
40.00
Fabrication component
1000
Miscellaneous component
45.30
TOTAL
2045.30
Table 2.9: Total Cost Purchase Parts
Total Costing
P a g e | 20
No. Component
Total Price / RM
Recycled component
14,955.80
Purchased component
2045.30
TOTAL
17,001.10
Table 2.10: Total Overall Costing
We are using 4 types of safety sign. One is Beware of Moving Parts. This sign
is use to make people aware of moving part in our machine. In our machine, there is
conveyor and actuated cylinder that moving without warning as it were following the
sequence.
Second is Hot Surface sign. This sign is use to avoid people from touching our
boiler. The boiler is use a stainless steel as it was hot on the surface and it may cause
a burn on our skin if we touch it.
P a g e | 21
Third is Keep Hands Away sign. This sign is use to make people aware of pick
and place area where our hands may be stuck in between while the process are
running.
Lastly, we are using Electrical Hazard signs. This sign is use to make people
beware of 240v voltage flow in project. And it is dangerous for people to touch it without
a safety as it may hurt our body if we touch it while the current are still flow.
CHAPTER III
PROJECT METHODOLOGY
Machine Description
The design of this product is new in the market. The Automatic instant noodle
machine is constructed based on DIN standard as below:
Machine name
Product
Number of station
Power supply
24 Vdc
Pneumatic source
6 bar
Controller
Sensor
Indicator
Transfer system
Drive system
Cycle time
Dimension
1m x 1m x 1.8m
P a g e | 22
Operation mode
Material specification
Material
Quantity
Noodle
77 gram
Water
300 gram
Flavour
8 gram
Container
1 gram
Cover container
1 gram
No.
Part
1.
Pneumatic
Cylinder
desired place
Dc geared motor
2.
Picture
Description
3.
Dc geared motor
P a g e | 23
4.
Ac pump motor
5.
Proximity
Capacitive Sensor
6.
Heating Element
This Post-Mix Instant Noodle Machine consists of 4 station which is feeding, flavour
filling, water filling and capping station. Operation in station are being controlled by
PLC Siemens S7-200 and actuated by Pneumatic Valve Cylinder.
P a g e | 24
Figure 3.1: Station 1
Firstly, user will choose the instant noodle flavour that they want. We are
including three most wanted flavour which is curry, chicken and asam laksa. After
choosing and press the button, cylinder 1 will pull out bowl and put on the rail. Then,
cylinder 2 will feed instant noodle into the bowl. Later, cylinder 3 which is in extended
position will start to retract until bowl reach on the conveyor.
Station 2: Flavour filling station
After cylinder 3 extend, motor 1 will start running and conveyor start moving.
Bowl that on the conveyor will follow conveyor moving until sensor detect. Conveyor
will stop when sensor are detect for filling a flavour. Conveyor will stop according to the
flavour we are choosing. For sensor 1 is curry flavour, sensor 2 is chicken flavour and
sensor 3 is asam laksa flavour. If we are choosing curry flavour, conveyor will stop
when sensor 1 detects and it will pass for sensor 2 and sensor 3. When sensor 1
has detect and motor 1 stop, motor 2 will start running and fill out the flavour into the
bowl. Motor 2 are run for using a timer and stop when timer stops counting. Then
conveyor will continue move until next station. It happen the same for sensor 2 with
motor 3 and sensor 3 with motor 4.
P a g e | 25
Conveyor will continue to move until sensor 4 detect. Once sensor 4 detect
solenoid valve will start drain water into the bowl. Solenoid valve will stop drain out
when timer off. Then conveyor will continue moving until sensor 5 detects the bowl.
When sensor 5 detect presence of bowl motor 1 will stop the conveyor. Then,
cylinder 4 will extend and push bowl into the rail. Cylinder 4 will only extend half for a
first move, because station 4 is in the middle of the rail.
P a g e | 26
Figure 3.4: Station 4
After cylinder 4 is extend and stop at the middle, cylinder 5 extend and pick up
bowl cover and retract back. Then, cylinder 6 will extend and move the cylinder 5 on
the top of the bowl and cylinder 5 will extend to cap the cover into the bowl. Later, both
cylinders will go back to their initial position. After finish capping station, cylinder 4
continues extend until it reach at the end of the rail and lastly serve to custo
P a g e | 27
P a g e | 28
P a g e | 29
P a g e | 30
P a g e | 31
ELCB
L
N
PE
MCB
3A
MCB
6A
MCB
3A
POWER
SUPPLY 12
VDC , 3A
MCB
10A
MCB
13A
MCB
6A
POWER
SUPPLY 24
VDC , 3A
TEMPERATURE
CONTROLLER
POWER
SUPPLY
24VDC
TOUCH
SCREEN
PLC S7-200
CPU 226 @ 224
K2
K1
K4
K3
K5
K6
EXPANSION
MODULE 1
HEATER
MOTOR 2
MOTOR 3
MOTOR 4
MOTOR
1
DC
MOTOR
DC
MOTOR
DC
MOTOR
DC
MOTOR
MOTOR 5
3 PIN PLUG
AC PUMP
MOTOR
P a g e | 32
Y1
3 Y2
Y3
3Y4
3 Y6
Y7
3Y8
3 Y10
Y11
Y2
Y13
4
3 Y12
45%
3 Y14
Y15
R 19
45%
R 18
R 17
100%
R 16
100%
R 15
70%
70%
Y9
R 14
70%
R 11 R 12 R 13
70%
R 9 R 10
R 8
30%
100%
Y5
R 7
100%
R 6
30%
R 5
100%
R 4
100%
R 3
30%
50%
R 1 R 2
Y16
P a g e | 33
I0.0
I0.1
SN1
I0.2
I0.3
I0.4
I0.5
SN2
I0.6
SN3
I0.7
SN4
I1.0
SN5
SN6
I1.1
RS1
I1.2
RS2
I1.3
RS3
I1.4
RS4
I1.5
RS5
I1.6
I1.7
CPU 226@224
Q0.1
Q0.2
Q0.3
Q0.4
Q0.5
Q0.6
Q0.7
Q1.0
Q1.1
Q1.2
Q1.3
Q1.4
Q1.5
Q1.6
Q1.7
Y1
Y2
Y3
Y4
Y5
Y6
Y7
Y8
Y9
Y10
Y11
Y12
Y13
Y14
Y13
Y14
0V
P a g e | 34
24V
RS6
RS7
I2.0
RS8
I2.1
RS9
I2.2
RS10
I2.3
RS11
I2.4
RS12
I2.5
RS13
I2.6
RS14
I2.7
RS15
I3.0
SN7
I3.1
RS17
I3.2
RS18
I3.3
thermo
I3.4
I3.5
I3.6
I3.7
CPU 226@224
EXPANSION MODULE 1
Q2.0
K1
Q2.1
K2
Q2.2
K3
Q2.3
K4
Q2.4
Q2.5
Q2.6
Q2.7
Q3.0
Q3.1
Q3.2
K5
K6
L1
L2
L3
SL1
BZ
Q3.3
Q3.4
Q3.5
Q3.6
Q3.7
0V
P a g e | 35
Input Table
Symbol
Address
Start
stoper
S1
S2
S3
SN1
SN2
SN3
SN4
SN5
SN6
RS1
RS2
RS3
RS4
RS5
RS6
RS7
RS8
RS9
RS10
RS11
RS12
RS13
RS14
RS15
floating_sensor
RS17
RS18
reset
TERMO
I0.0
I0.1
I0.2
I0.3
I0.4
I0.5
I0.6
I0.7
I1.0
I1.1
I1.2
I1.3
I1.4
I1.5
I1.6
I1.7
I2.0
I2.1
I2.2
I2.3
I2.4
I2.5
I2.6
I2.7
I3.0
I3.1
I3.2
I3.3
I3.4
I3.5
I3.7
Description
Start all program
Stop
curry
chicken
soto
sensor 1 or limit switch
sensor 2 or limit switch
sensor 3 or limit switch
sensor 4 or limit switch
sensor 5 or limit switch
sensor 6 or limit switch
cy1
cy1
cy1
cy2
cy2
cy3
cy3
cy4
cy4
cy4
cy5
cy5
cy5
cy6
cy6
floating sensor
stoper
suction cup (station 1)
reset to initial condition
Termocouple
Table 3.4: Input table PLC
P a g e | 36
Output Table
Symbol
Y1
Y2
Y3
Y4
Y5
Y6
Y7
Y8
Y9
Y10
Y11
Y12
Y13
Y14
Y15
Y16
K1
K2
K3
K4
K5
K6
L1
L2
L3
SL1
BZ
Address
Q0.0
Q0.1
Q0.2
Q0.3
Q0.4
Q0.5
Q0.6
Q0.7
Q1.0
Q1.1
Q1.2
Q1.3
Q1.4
Q1.5
Q1.6
Q1.7
Q2.0
Q2.1
Q2.2
Q2.3
Q2.4
Q2.5
Q2.6
Q2.7
Q3.0
Q3.1
Q3.2
Description
cy1
cy1
cy2
cy2
cy3
cy3
cy4
cy4
cy5
cy5
cy6
cy6
cy7
cy7
suction cup 1
suction cup 2
conveyor motor
dc motor 1
dc motor 2
dc motor 3
pump motor
heater
lamp (red)
lamp (orange)
lamp (green)
solenoid valve (boiler)
buzzer
Table 3.5: Output table PLC
P a g e | 37
START
INITIAL
CONDITION
RS1
STEP 1
Q4.0
STEP 2
Q4.1
M10.1
NS
Q4.0
NS
Q4.1
STEP 4
Q4.1
M10.3
Q4.2
STEP 5
Q4.3
M10.4
NS
Q4.2
Q4.5
M10.0
RS3
RS2
STEP 3
S
T
O
P
E
N
D
M10.2
RS4
RS5
RS7
STEP 6
M10.5
P a g e | 38
SN1
RS6
STEP 7
Q4.4
M10.6
NS Q4.5
SN2
Q6.0
K1,MOTOR 1 (RUN)
STEP 8
NS Q6.0
M10.7
Q5.4
STEP 9
NS Q5.4
M20.0
RS7
S
T
O
P
E
N
D
SN3
SN4
STEP 10
M20.1
Q6.0
SN5
STEP 10
M1, MOTOR 1
NS Q6.0
(STOP)
S Q6.1
M2, MOTOR 2
(RUN)
M20.1
STEP 10
M1, MOTOR 1
NS Q6.0
(STOP)
S Q6.2
M3, MOTOR 3
(RUN)
Y5,
NS Q4.4 CYLINDER 3
(EXT)
3
Figure 3.14: Step Sequence 2
M20.1
NS Q6.0
M1, MOTOR 1
(STOP)
S Q6.3
M4, MOTOR 4
(RUN)
P a g e | 39
3
RS12
RS10
STEP 11
NS
Q4.6
M20.2
Q5.0
NS
Q6.0
STEP 12
NS
Q5.0
M20.3
Q5.2
Q5.0
STEP 14
Q5.1
M20.5
Q5.3
STEP 15
Q4.6
M20.6
NS
Q5.0
NS
Q5.3
STEP 16
Q4.7
M20.7
NS
Q4.6
RS13
RS14
RS12
STEP 13
M20.4
S
T
O
P
E
N
D
RS15
RS13
RS9
RS11
P a g e | 40
1
STEP 11
Q6.0
M20.2
NS
Q6.1
NS
Q6.2
NS
Q6.3
STEP 12
NS
Q6.0
M20.3
Q4.6
STEP 13
NS
Q4.6
M20.4
Q5.0
NS
Q6.0
STEP 14
NS
Q5.0
M20.5
Q5.2
Q5.0
STEP 16
Q5.1
M20.7
Q5.3
STEP 17
Q4.6
M30.0
NS
Q5.0
NS
Q5.3
STEP 18
Q4.7
M30.1
NS
Q4.6
RS8
SN6
RS11
RS9
RS12
RS13
E
N
D
S
T
O
P
RS11
STEP 15
M20.6
RS14
RS12
RS8
RS10
P a g e | 41
Safety factor
P = 6bar
P a g e | 42
Cylinder 3
Mass = 0.71 kg
F = mg
= 0.25(0.71kg) (9.81m/s)
= 17.413 N
Safety factor
= 0.25
P = 6bar
P a g e | 43
Cylinder 4
Safety factor
= 0.25
P = 6bar
P a g e | 44
Cylinder 5 & 6
= 0.25
P = 6bar
F = mg
= 0.25(0.3kg) (9.81m/s)
= 0.735
Safety factor
Conclusion
We are used a recycled cylinder that have the nearer bore size as the calculation.
P a g e | 45
Motor 1
+ fy = 0
N-w = 0
N=w
= 16.65(9.81)
= 163.35 N
If = N
= 0.8(163.35)
= 130.68
+ fx = 0
F-f = 0
F = 130.68
TL = F D/2
= 130.68 (0.03)
= 3.92
4Nm
P a g e | 46
Motor 2
+ fy = 0
N-w = 0
N=w
= 10.00(9.81)
= 98.1 N
If = N
= 0.8(98.1)
= 78.48
+ fx = 0
F-f = 0
F = 78.48
TL = F D/2
= 78.48 (0.03)
= 2.36
3Nm
Conclusion
We are use a recycled motor that are using the same purpose which is motor 1 are
used on conveyor and motor 2 are used on the canister.
P a g e | 47
Circuit Breaker
P a g e | 48
Relays and Contactor
Indicator
Alarm / Buzzer
P a g e | 49
CHAPTER IV
PROJECT IMPLEMENTATION
Station 1:
Station 4:
Feeding station
Capping station
Station 2:
Station 3:
Flavour filling
station
Water filling
station
P a g e | 50
4.1.2 Flowchart
Start
Supply
No
Yes
Initial Position
Filling Flavor
Process
Filling Water
Process
Capping Process
End
P a g e | 51
Station 1
Start
Initial Position
Cylinder 1 Extend
No
RS3 detect
Yes
Vacuum On
Cylinder 1 Retract
RS2 detect
Yes
Vacuum Off
Cylinder 2 Extend
No
RS5 detect
Yes
Cylinder 2 Retract
No
RS4 detect
Yes
Cylinder 3 Retract
End
P a g e | 52
Station 2
Start
Cylinder 3 Extend
No
RS7 detect
Yes
Motor 1 Run
No
Sn1 detect
Yes
No
Motor 1 Stop
Sn2 detect
Yes
No
Motor 2 Run
Motor 1 Stop
Sn3 detect
Yes
Motor 3 Run
Motor 1 Stop
Motor 2 Stop
Motor 4 Run
Motor 3 Stop
Motor 4 Stop
Motor 1 Run
End
P a g e | 53
Station 3
Start
Motor 1 Run
No
Sn4 detect
Yes
Motor 1 Stop
Solenoid valve on
Motor 1 Run
End
P a g e | 54
Station 4
Start
Cylinder 4 Extend
No
RS 9 detect
Yes
Cylinder 4 Retract
Cylinder 5 Extend
No
RS 10 detect
Yes
Cylinder 5 Retract
No
RS 12 detect
Yes
Cylinder 6 Extend
No
RS 15 detect
Yes
Cylinder 5 Extend
No
RS 11 detect
Yes
Cylinder 5 Retract
No
RS 12 detect
Yes
Cylinder 6 Retract
End
P a g e | 55
No
Component
Quality Checking
Power Supply
Capacitive Sensor
Relay
Ac pump Motor
MCB
Contactor
10
Heater
P a g e | 56
bowl of water. If water does boil, it means heater is in
good condition.
Table 4.1: Electrical Component Quality Plan
No.
Component
Quality Checking
Pneumatic cylinder
Canister
Roller
Conveyor
Aluminium profile
PVC plate
Acrylic
P a g e | 57
Every project has its own dateline. To complete this project, we have 4 main
stages that must be follower
Once finish on bring out the idea, we begin to do a feasibility study about the
project and designing the project layout. During feasibility study, we will do a research if
there is other machine that are already made and see how they done the process did.
The research for other machine is only for our reference in making design.
When we start to designing our machine, this is where we are applying what we
had learnt through 2 and half year at German-Malaysian Institute. We will start to
design the mechanical part of the machine by using SolidWork and construct the circuit
wiring by referring to the electrical wiring that we had learn from last semester.
P a g e | 58
After our proposal has been approving, we will start to do a project in a real
time. At this stage, where we will have to really determine the right component that are
going to be use and the mechanical design should be done in a right way as to ensure
the project are in applicable way.
At this stage is where will prove that we are the one that made this machine. All
the progress while do the project are being recorded in data to show it as a copyright
are made by us. It is to ensure that no other people will make a copy of our machine
process through all the features also. All the works that have been done since proposal
until final presentation are represent in this documentation.
At this stage is where we will prove that this machine are finish and can do a
process according to the sequence without having any problem. It is to give a person
know that the machine process and what type of process are being use in visual look.
P a g e | 59
1. Project Design
Designing task is the first stage to start a project. This is where the
project are being design according to standard and propose it to lecturer to see
whether the design that we made are correct or need an improvement or totally
doing in a wrong way. Any mistake that we make at this stage will not make a
project function properly or not function at all.
2. Product Enquiry
First, we make a list of the equipment and then find the vendor or
supplier to get the quotation, before submitting the purchase requisition form.
The specification and delivery date must be confirm from the vendor or supplier.
All of this process is important because some careless mistake will affect the
implementation of project.
P a g e | 60
3. Mechanical construction
This task can be done only after receiving mechanical part, either
fabricated or recycled part. While waiting for purchased fabricated part, we can
start build other station that are using a recycled part and do a self fabricate
part also. It can help to finish a project in a required time.
4. Electrical wiring
This task is being done by person in-charge to finish the wiring part. It is
containing to connect the power supply with plc controller and together with
input and output device. Input device such a s switch, relay and sensor and for
output device like pneumatic cylinder, motor or cylinder. All this input and output
device are connected with plc controller as their link.
Person in-charge will collect all data from the first day starting to do the
project until project finish. The data should contain all information about project
including design, project progress.
P a g e | 61
ELYAS
He has been given responsible as a group leader for this group. Do for designing and
approving on mechanical drawing and layout also for machine wiring including
pneumatic, electrical and PLC. Lastly, he is also responsible to design and
troubleshoot PLC programming.
RAMZUL
Do for designing mechanical drawing and assembly machine layout also purchasing
and costing for fabrication part and recycled part.
HAJAR
Do for designing mechanical drawing and layout and troubleshooting for PLC
programming. Besides, she is also responsible for organizing the schedule, costing of
part, documentation report and presentation.
EMERSON
Do for designing mechanical drawing and assembly machine layout also for
documentation report and presentation.
P a g e | 62
To do this project we must have a proper planning toward the success of Final
Year Project. Therefore, a clear Gantt chart which list down the necessary tasks and
the duration to complete each tasks is drafted. This Gantt chart will list the task to be
performed by our group, the time scale allowed for each individual tasks and task bar
for better visualization of the individual project phases.
During the project stages, it is possible to keep track on the development of the
project according to the chart. It is also possible to measure the projects phase time
allocation and perform any corrective actions needed in order to complete the project
on time.
In order to complete the machine, we must follow the Gantt chart. Scheduling is
also important in the ways that:
To make sure the jobs / tasks follow the sequence and procedures.
To prevent from any consequences that might be interrupt the progress such as
delay time of the part delivery or short of money.
P a g e | 63
Filling station
If using a sensor does not helping in telling how many gram of flavour and water
are filling inside the bowl, we will choose to use a timer.
Transfer system
If transfer by pushing cylinder at station 4 cannot make it stop at the right angle
at pick and place station, we decided to make a stopper at the middle of the conveyor
to make the bowl are state at the right place to put a cover on top of it.
P a g e | 64
CHAPTER VI
No.
Problems Encountered
Countermeasure
For a food and beverage product like For the mechanical parts that do not
our machine, using stainless steel touch the food we replace it by using
surely a must as it was the most a PVC plate only
suitable material to be using for food
product.
Temperature
controller
does
function
3
P a g e | 65
No
Process
Result
Machine Sequence
Product Output
Automatic and Manual All automatic and manual process are running as we
Process
desired
Table 5.2: Result and Discussion
P a g e | 66
CHAPTER 6
CONCLUSION
6.1 CONCLUSION
This machine is can run in manual mode and semi-auto mode as it may not fully
function in auto mode yet. After all the process can be done in 2 minutes and the
water are boil correctly according to standard water heating.
Sequence of process is running according to what we had planned. The
process in each station also according to what we have desired.
Finally, we are able to make the machine function manually and semi-auto and
make an instant noodle are cooked well.
P a g e | 67
6.2 RECOMMENDATIONS
P a g e | 68
REFERENCE
Cals Arizona. (n.d). HACCP Food Safety. Retrieved from
http://cals.arizona.edu/pubs/health/foodsafety/az1082.html
Tupperware Brands (n.d.). Quality Assurance & Warranty, Decoding the codes.
Retrieved from http://tupperware.com.my/safety_assurance_decoding.php