Wasit - Detailed Design Report - Updated PDF
Wasit - Detailed Design Report - Updated PDF
ANNEX 5
Detailed Design Report
January 2008
- Amman
SEWSSP
WASIT WATER TREATMENT PLANT
1,000 m3/h CAPACITY
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
CONTENTS
Page
1. INTRODUCTION
1.1
Background
1.2
Summary and Scope of Work
2. Design of Process Units
2.1
Scope of Work
2.2
Approach and Methodology
2.2.1
WTP Capacity
2.2.2
Raw Water Quality
2.2.3
Design Criteria
2.2.4
Process Unit Sizing
2.2.5
Process Flow / Mass Balance Diagrams
2.2.6
Process and Instrumentation Diagrams
2.3
Basis of Design
2.3.1
Process Design Overview
2.3.2
Process Functions
2.3.3
Process Flow
2.3.4
Water Quality
2.3.4.1
Raw Water Quality
2.3.4.2
Treated Water Quality
2.3.4.3
Determination of the Chemical Dose with Jar Tests
2.3.4.4
In-Line Chemical Dispenser
2.3.5
Design Parameters
2.3.5.1
Sludge Mass Balance
2.3.5.2
Filters
2.3.5.2.1 Filter backwash
2.3.5.2.2 Filter dump volume
2.3.5.3
Clean wash water tank
2.3.5.4
Wastewater holding tank
2.3.5.5
Elevated Storage Tank
2.3.5.6
Chlorination System
2.3.5.6
Chemical dose rates and storage
2.3.5.6.1 Alum
2.3.5.6.2 Chlorine
2.3.5.7
Service water
2.4
Process Calculations
2.4.1
Basis of Design for all Plant Flows
2.4.2
Conceptual Design
2.4.3
Flocculation
2.4.4
Clarifier Plate Pack Design
2.4.5
Clarifier Hydraulics
2.4.6
RGF Trough Location
2.4.7
Filter
2.4.8
Clean Wash Water Tank
2.4.9
Chlorine Contact Tank
2.4.10
Sludge System
2.4.11
Waste Water Holding Tank
2.4.12
Chemical Storage and Dosing
7
7
8
8
9
9
9
10
10
10
10
10
11
11
12
12
12
12
12
13
13
13
13
14
14
14
14
14
14
15
15
15
15
16
16
18
19
20
22
24
26
27
28
29
31
2
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
2.4.13
Service Water Requirment
2.4.14
Mass Balance
3. Hydraulics and Hydrology
3.1
Hydraulics Study
3.2
Hydrological Study in Al-Dujaila- River
4. Mechanical Design
4.1
Mechanical Equipment- General
4.1.1
Introduction
4.1.2
Scope of the Work
4.1.3
Design Criteria
4.1.4
Calculations
4.1.5
References
4.1.6
Sample of Calculations
4.1.6.1
Head losses calculation for raw water pumps
4.1.6.2
Head losses calculation for treated water pumps
4.1.6.3
Head losses calculation for waste water pumps
4.1.6.4
Head losses calculation for over flow pumps
4.1.6.5
Head losses calculation for backwash water pumps
4.1.6.6
Head losses calculation for service water pumps
4.2
Pump Station and Pipeline Hydraulic Transient Analysis
4.2.1
Purpose
4.2.2
Transient Mathematical Model
4.2.3
Criteria and Analysis
4.2.3.1
Raw Water Pump Station
4.2.3.2
Treated Water Pump Station
4.2.4
Analysis Summary and Recommendation
4.2.5
References
4.3
Mechanical Equipment-HVAC
Introduction
4.3.1
4.3.2
Design Criteria
Cooling
4.3.2.1
Heating
4.3.2.2
4.3.2.3
Ventilation
4.3.3
Systems
4.3.3.1
Cooling system
Heating system
4.3.3.2
Ventilation systems
4.3.3.3
4.3.4
Sample of calculations
4.3.4.1
Non-processing building
4.3.4.2
Process buildings
4.3.5
The Changed Drawings
4.3.6
Bill of Quantities
4.3.7
Specifications
4.4
Mechanical Equipment-Safety
4.4.1
Chlorine Scrubber System
4.4.1.1
Design Criteria
4.4.1.2
Operation
4.4.2
Fire Hydrant
4.4.3
Fire Extinguishers
32
33
34
34
35
35
35
36
36
37
37
38
39
40
41
42
43
45
45
45
46
46
47
48
48
53
53
53
53
53
53
54
54
54
54
55
55
56
56
56
56
66
66
66
66
67
67
3
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
4.4.4
Emergency Showers
5. Electrical Equipment
5.1
Introduction
5.2
Scope of Work
5.3
Design Criteria and Parameters
5.3.1
Compliance with Regulations and Standards
5.3.2
The Incoming Supply
5.3.3
Transformers
5.4
Methodology
5.5
Sample of Calculations
5.5.1
Load Estimation
5.5.2
Voltage Drop Calculations
5.5.3
Indoor Lighting Calculations
5.6
Drawings
5.7
Bills of Quantity
5.8
Specifications
6. Instrumentation Control and Automation
6.1
Instrumentation and Controls System
6.1.1
Introduction
6.1.2
6.1.3
6.1.4
6.1.5
6.2
6.3
6.3.1
6.4
6.4.1
6.4.2
6.4.3
6.4.4
6.4.5
6.5
Control Descriptions
6.5.1
6.5.1.1
6.5.1.2
6.5.2
6.5.3
6.5.4
6.5.5
6.5.6
6.5.7
6.5.8
6.5.9
6.5.10
6.5.11
6.5.12
6.5.13
6.5.13.1
68
69
69
69
69
69
69
69
70
70
71
73
74
74
74
75
75
75
75
76
76
77
77
78
81
81
81
81
81
81
82
82
84
85
85
86
87
88
89
91
92
93
94
96
98
100
100
4
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
6.5.13.2
6.5.13.3
6.5.13.4
6.5.13.5
6.5.13.6
6.5.14
6.5.14.1
6.5.15
6.5.16
6.5.17
General criteria
Support Buildings
Process Buildings
7.4
Basis of Design
7.4.1
Codes And Standards
7.4.2
Primary Elements
External walls
7.4.2.1
7.4.2.2
Internal walls
7.4.2.3
In-situ R.C. floor and roof slabs
7.4.3
Finishing
7.4.3.1
Wall finishing
Floor Finishings
7.4.3.2
7.4.3.3
Base
7.4.3.4
Ceilings
7.4.3.5
Metal works
7.4.3.6
Carpentry
7.4.3.7
Roofing system
Flashing
7.4.3.8
7.4.3.9
Water proofing
7.4.3.10 Sealants
7.4.3.11 Doors and Hardware
7.4.3.12 Windows
7.4.3.13 Glass and glazing
7.4.3.14 Fencing
7.4.4
Project Particulars
7.4.4.1
Adminstration buildings
Maintenance shop and spare part storage building
7.4.4.2
7.4.4.3
Residential buildings
7.4.4.4
Guard house
7.5
Architectural Design and Working Drawings
7.5.1
New Drawings
7.5.2
Modified Drawings
8. Structural Design
8.1
Introduction
8.2
Design Criteria
101
102
103
104
106
108
109
110
112
114
116
116
116
116
116
117
117
117
117
117
117
117
118
118
118
118
118
118
118
118
118
118
119
119
119
119
119
119
119
120
120
120
120
121
121
122
122
5
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
8.2.1
Design Codes
8.2.2
Design Software
8.2.3
Structural Materials
8.2.4
Foundations
8.2.5
Reinforced Concrete Structures : Design Basis General
8.2.5.1
General
8.2.5.2
Design Loads
8.2.5.3
Material Requirements
8.2.6
Structural Steel: Design Basis
8.2.6.1
General
8.2.6.2
Design loads
8.2.7
Concrete Block Work
8.2.8
Site Investigation
8.3
Sample of Calculations
8.4
Structural and Civil Drawings
8.5
General description of civil works
8.5.1
Non-Process Buildings
8.5.2
Process Buildings
9. Ancillary Works
9.1
Geotechnical Report
9.1.1
9.1.2
9.1.3
9.1.4
9.1.5
9.1.6
122
124
124
124
125
125
125
126
126
126
126
127
127
127
143
144
144
144
Introduction
Laboratory Works
Stratigraphy
Groundwater
Soil Classification and Identification
Shear Strength Parameters
9.1.7
Soil Compressibility
9.1.8
Chemical Tests for Soil and Groundwater
9.1.9
Geotechnical Design
9.1.9.1
Allowable bearing pressure
9.1.9.2
Shallow Foundations
9.1.9.3
Pile Foundations
9.1.9.4
De-watering
9.1.10
Suitability of Materials for Re-use
9.1.11
Smmary of Design Parameters
9.1.12
Conclusions
9.2
Road Report
9.2.1
Introduction
9.2.2
Aim of Report
9.2.3
Scope of Report
9.2.4
Structural Components of a Flexable Pavement
9.2.5
Design Procedure Input Parameters
9.2.6
Asphalt Concrete Design Requirements
9.2.7
Flexible Pavement Design (1993 AASHTO Pavement Design)
10. Environmental Management Plan
148
148
148
150
151
152
155
156
157
158
158
159
159
160
160
160
161
163
163
163
163
163
164
165
166
168
6
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
1. INTRODUCTION
1.1 Background
Wasit subdistrict center is located in the south eastern part of the Wasit Governorate. It is
about 28 km to the south east of Al Kut city. The topography of Wasit subdistrict is flat. The
total population of Wasit subdistrict is about 38,293 inhabitants, about 10,500 of them are
urban and the rest are rural.
The climate in Wasit is dry and cold in the winter season and very hot in the summer. The
average annual precipitation ranges from 120 to 130mm, most of this occurs in the winter
months. The average daily temperatures range between 9-13C in winter and 40-50C in
summer. The main occupation in the subdistrict is agriculture and animal husbandry. In
general, Wasit is considered a poor subdistrict. The rural areas in Wasit subdistrict appear to
be very populated; more than 72 percent of the population is living in the rural areas.
The main source of water in Wasit city is the Al-Dujaila irrigation canal which is a branch of
the Tigris River. Al-Dujaila canal passes through the urban area of Wasit city with continuous
water flow throughout the year. The canal is under the jurisdiction of the Ministry of Water
Resources.
Only about 40% of the total population of Wasit city is served by a piped system, the
remaining population is served by tankers or take water directly from the canal. Wasit
subdistrict center is served through an old water distribution network.
The distribution system in the city is very old and is mostly of asbestos, cast iron, plastic and
cement pipes. It has been reported that about 10% the maximum water head in the network is
about 3.0 m and may go down to 0.5 m. Only 25% of the total area is covered by existing
water facilities. The main transmission pipe is 250 mm in diameter, while the distribution
pipes diameters range from 110 mm to 200 mm.
The present project includes construction of a new 1,000 m3 per hour WTP, river intake with
raw water pumping station and transmission line, treated water ground storage tank, and
elevated water storage tank. The site of the new water treatment plant is on the main street but
drainage of the site might make access difficult during the rainy seasons.
It is anticipated that no negative impacts on the environments will take place due to the
sewage produced since most of water produced by the plant is utilized to improve the quality
of water consumed by the inhabitants which are presently using poor quality water.
1. 2 Summary and Scope of Work
This report has been prepared to show the detailed design of Water Treatment Plant utilizing
standard process units, structures and buildings developed by 3MWH for MMPW. The designs
are based on plant capacity (works throughput) of 1000 m /h. It is intended that standard
designs are incorporated into the site specific design with the necessary alterations. Several
site specific alterations are described in this report and as a result, many new drawings and
calculations are presented. The report also describes the procedures used to undertake the full
site design of Wasit plant including preliminary site selection, topographical, geotechnical
and hydrological surveys and raw water quality testing. This is followed by descriptions for
developing the process design utilizing calculation spreadsheets and typical Process and
Instrumentation, Process Flow, Mass Balance, Hydraulic Profile Diagrams, Mechanical,
Electrical, Instrumentation and Control, Architectural and Structural Design. The design
process determines the amendments which were required to the standard process units.
Site selection, site layout development and site work designs are also covered, with reference
to the physical features covered by the above surveys.
7
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The report consists of ten chapters. The chapters describe the procedure for the design of Wasit
Water Treatment Plant utilizing both Standard Designs and design specific to a particular
capacity of works and location.
Creation of a simple, reliable, effective, and proven system by applying the best
knowledge and skill to the design.
4. Designing a plant that is easy and safe to construct as well as simple and safe to
operate.
5. Allowing for maximam and minimum operational flexibility.
The Standard Designs are based on river sources. However, the raw water quality varies
depending on location. The following parameters are those for which treatment is provided.
-Turbidity
-Bacteriological
-Algal content
It is not considered that the treatment process will change from the standard flocculation,
clarification, filtration and disinfection using the standard process units. However, the water
quality will affect the coagulant dosing rate, the clarifier sludge draw off quantity, filter
backwash frequency and the wastewater production.
2.2.1 WTP Capacity
8
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The stated capacity of Wasit WTP is 1000 m3 of treated water output. In order to achieve the
necessary treated water output, the quantity of raw water will have to account for the amount
of water lost through the process.
The main factor that affects the water losses and hence the raw water flow is the raw water
quality. Raw water with high suspended solids content will produce a large amount of sludge
and hence the amount of water lost throughout the treatment will increase.
Allowance has also be required for filter backwash water and filter rinse to waste during start
up following a backwash. These quantities was calculated and shown in the material balance
sheet. The Process Flow Diagram (PFD) and Mass Balance Diagram (MBD) were developed
to assist in the design of hydraulics, process pipe work and wastewater disposal.
2.2.2 Raw Water Quality
The turbidity of the raw water influences the amount of sludge produced and the coagulant
dose. The amount of coagulant required will also influence the amount of wastewater. Typical
analysis of raw water quality includes
pH
Turbidity (Tur)
Alkalinity (Alk)
Magnesium (Mg)
Calcium (Ca)
Chloride (Cl)
Analysis of a set of raw water samples taken over a suitable period from Al-Dujaila- River
was carried out to evaluate the coagulant dose and waste streams. The full raw water quality
data is shown in Table 1. The analysis is done by the Local Municipal laboratory located at
Wasit City. The sample dates and temperatures were included.
Table 1 Wasit Raw Water Quality Data (Source : Al-Dujaila- River)
Date
25-01-2006
19-02-2006
29-01-2007
22-03-2007
11-05-2007
Mean
Minimum
Maximum
Count
Temp
17
25
20
22
26
Turb.
25
115
30
60
53
pH
7.70
8.10
7.50
7.84
7.95
E.C.
1393
1404
1395
1211
1283
Chlor.
81.7
163.4
85.0
132
90
Alk.
160.0
160
165
114
120
T.H.
500.0
473.5
495
620
480
Ca
97.2
117.5
100.0
144
112
Mg
61.8
43.1
65.0
63.7
49
TDS
928
936
930
774
593
TSS
52
125
65
52
55
22
17
26
5
56.6
25
115
5
7.818
7.5
8.1
5
1337.2
1211
1404
5
110.42
81.7
163.4
5
143.8
114
165
5
513.7
473.5
620
5
114.1
97.2
144
5
56.52
43.1
65
5
832.2
593
936
5
69.8
52
125
5
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The water treatment system is designed to provide 1,000 m /h of treated water at full capacity
and can handle at least a 3:1 plant turndown ratio. The overall process requirement is to
extract raw water from Al-Dujaila- River, physically and chemically treat that water to the
agreed standards, and supply the treated water to distribution network of Wasit City. Waste
10
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
streams generated from the treatment process will be disposed to Nagara River located near
the WTP site without any treatment. The process is designed to be operated continuously
without frequent start-up and shut down.
2.3.2 Process Functions
The main process functions include:
Extraction and transmission of raw water from the intake area to the treatment plant
area.
Storage and injection of disinfection chemical (Chlorine Gas) into the filtered water
stream.
Transmission of treated water from the treatment plant site to the Distribution
Network
Extraction and storage of dirty backwash water from the filters and sludge from the
flocculator/clarifiers.
Transmission of wastewater and sludge and miscellaneous process wastes from the
treatment plant site to the near river outfall.
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Filtered water is treated with chlorine and flows through the chlorine contact tank to the
treated water storage tank. The treated water pumps transfer treated water to the Distribution
Network via treated water pipeline.
From the splitter box onwards, the flow gravitates through the treatment works, ending up in
the treated water storage tank. A portion of the treated water flow is extracted for use as
service water and also domestic water on the treatment plant site. Emergency overflow water
is directed to a dedicated overflow tank containing a pump to transmit the water to the river.
2.3.4 Water Quality
2.3.4.1 Raw Water Quality
Raw water quality is dependent upon the river source, local conditions and in some cases time
of year. Samples taken over a one year period were analyzed to understand the variability of
the water quality, particularly with regard to pH and turbidity.
The basic parameters analyzed are: pH, temperature, turbidity, conductivity, alkalinity, total
hardness, calcium, magnesium, chloride, TDS, TSS, TOC, and aluminum. Table 1 shows a
typical water quality data for Al-Dujaila- River.
2.3.4.2 Treated Water Quality
The plant was designed to treat the above raw water, and to produce the following quality of
water, to the following standards:
Target Turbidity 0.5 NTU average, 1 NTU maximum
E coli or thermo tolerant coliform bacteria 0 in 100 ml sample
It is anticipated that the target residual metals will be as follows, subject to confirmation
of concentrations in the inlet raw water,
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Most of the design parameters are standard for the plant designs. However some factors affect
the process calculations, which are detailed in this section.
2.3.5.1 Sludge Mass Balance
To achieve the desired plant flow at the outlet, the inlet flow has to be greater to account for
the losses through the process. The losses through the processes are as follows:
Clarifiers Intermittent desludging.
Wash Water Tank filling: the wash water tank is filled from the filter outlet flow.
Filter dump volume: the mass balance assumes there is 2 dump volumes lost per day
from the filters, during the backwash cycle.
Treated Water Tank: the service water is taken from the treated water storage tanks
The volume of clarifier sludge depends on the raw water quality and the coagulant dose. The
instantaneous maximum flow can be calculated assuming that all the clarifiers desludge at the
same time. Using the raw water turbidity, the amount of clarifier sludge produced can be
predicted, using the following equation:
1000Sc 2To
S = C
1
1000S c 4Ti 0.234A
Where:
S: Sludge flow (MLD)
Sc: Sludge solids concentration
- Min 1 NTU
-Max 2 NTU
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
2.3.5.7.1 Alum
Chemical makeup
2.3.5.7.2 Chlorine
Prechlorination
-Predicted dose 3mg/l
-1 duty drums
-No standby is required
Disinfection
-Predicted dose 2mg/l
-Number of drums - 1 duty/1 standby
-Calculated using maximum draw off rates from a chlorine drum as follows:
30 oC = 15kg/hr
20 oC = 10kg/hr
15 oC = 5kg/hr
Storage
- Maximum 30 days
- A 9 (1 tonne) chlorine drum store was adopted for the Standard Designs
2.3.5.8 Service water
The service water is taken off from the treated water tank
Assumed Service water consumption 8 m3/day
Assumed wash down water 23 m3/day
2.4 Process Calculations
Process design was done utilizing calculation spreadsheets, by EXEL software considering
the main factors affecting the water treatment plant of Wasit. Mass balance was done to
calculate the amount of sludge, amount of water lost throughout the treatment process, filter
backwash water and filter rinse, alum and chlorine doses required. Unit sizing and
dimensions, as well as unit hydrulics and levels were also recalculated and checked.
15
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
10/11/2007
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
4.45
4.45
4.45
m
m
m
500 m3/h nett Clarification stage designed on a maximum velocity of 0.65m/h on the projected plate area.
Nom. length
9 m
Nom. width
9 m
Nom. depth
4.4 m
Flowrate
1000
m3/h
No of Streams
2
500
m3/h
Filtration
The filters will be of the single cell type with width 4.75m (nominally internal wall to wall)
Flowrate
1000
m3/h
No of filters n
Length
Width
Area
n Velocity
n-1 Velocity
5
5.2
4.75
24.7
8.1
10.1
m
m
m2
m/h
m/h
ES mm
Depth m
0.65
1.3
55
34
45
0.5
0.75
m/hr
m/hr
Nm3/hr
Max at 30C
Min at 5 C
1000
333
Clarification
The Flocculation/Clarification plant will consist of two streams
Each stream will comprise the following:
Dimensions (nominally internal wall to wall)
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
16
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Flocculation stage comprising 3 No chambers to give an overall nominal residence time of 30 mins.
Nom. length
Nom. width
Nom. depth
Clarification stage
Nom. length
Nom. width
Nom. depth
4.45
4.45
4.45
m
m
m
9.0
9.0
4.4
m
m
m
Filtration
There will be 5 no filters of the single cell type
No of filters n
Length
Width
Area
n Velocity
n-1 Velocity
5
5.2
4.75
24.7
8.1
10.1
m
m
m2
m/h
m/h
1030
0.3
0.95
2
0.69
1.38
1.00
m3/h
m/s
m2
1001
0.3
0.93
2
0.68
1.36
1.50
m3/h
m/s
m2
m
m
m
m2
m
m3
m3
m3
Sized to hold one filter wash plus 1 hour of average clarifier flow plus 30 mins rinse washwater channel
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
17
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
2.4.3 Flocculation
PROJECT TITLE
PROJECT NO
PROCESS UNIT
DESCRIPTION
PREPARED BY
CHECKED BY
VERIFIED BY
VERSION NO
Wasit
FLOCCULATION TANKS
2 STREAM
DATE
DATE
DATE
DATE
INFLUENT CONDITIONS
NOTES
AVG
INFLUENT FLOW
INFLUENT TEMEPRATURE
DESIGN CONDITIONS
RESIDENCE TIME REQUIRED
TOTAL VOLUME REQUIRED
TOTAL VOLUME INSTALLED
NO OF STREAMS
NO OF UNITS PER STREAM
DYNAMIC VISCOSITY
VOLUME PER STREAM
VOLUME PER UNIT
LENGTH PER STREAM
WIDTH PER STREAM
DEPTH PER STREAM
LENGTH PER UNIT
ASSUMED EFFICIENCY
OPERATING CONDIITONS
RESIDENCE TIME
28/10/2007
Ml/d
C
s
m3
m3
kg/m s
m3
m3
m
m
m
m
%
10
0.001308
MIN
8.37
5
0.001519
13.37
4.46
4.46
MAX
25.48
30
1800
531
531
2
3
0.000801
265.4
88.5
4.45
4.45
4.47
4.45
100%
AVG
#DIV/0!
MIN
1800
MAX
5481
AVG
MIN
W
%
kW
567
347
0.81
0.50
MAX
70
658
0.7
0.94
SELECTED POWER
ACTUAL G
kW
s-1
82
104
1.1
74
CALCULATED
18
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
LENGTH
WIDTH
DEPTH
m
m
m
13.35
4.45
4.5
OPERATING CONDIITONS
RESIDENCE TIME
0
s
s
#DIV/0!
0
kW
s-1
1.1
74
MIXING
SELECTED POWER
ACTUAL G
1800
0
5481
0
Any plate
Area
No. requd
Rows
Horl.
Offset
Area requd
Width
Q=
Rate
Proj.Area
1.5
2.41
329
4
82.2
63.5
5220
1555
6775
pack
22
792.4
15.7
4
3.91
7147
1.5
531
0.67
792.4
m wide
m
m/h
m/h
m
Avail. F. C
Width
Flow per trough
-6
-1.5
0.036868
m
m
m/s
No
mm
mm
m long
Allowing for shaft
m
pack
38.56
18
m
50.61
m
packs
Rows
packs
pack
17
mm long
8035
packs
Rows
packs
mm
long
2
2
not o.k.
6
4
20
20.5
4
5.14
19
2
2
o.k.
m
40.97
19.3
4
4.84
packs
Rows
packs
8416
mm long
6
4
20
No.plates
17
18
19
20
21
Area m
38.56
40.97
43.38
45.79
48.2
b1
1080
1144
1207
1271
1334
Length
2635
2699
2762
2826
2889
22
50.61
1398
23
53.02
1462
63.5 mm horzl. distance
2953
3017
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
no
m3/h units
541
4.810
Overflow
4.962
4.510
4.712
4.512
5.50
4.74 4.84
4.964
0.272
4.505
10
m TBC
0.3
0.98
1.40
1.40
0.70
m/s
m2
m
m
m
0.005
0.5
0.002
0.2
m
4.510
4.512
4.512
m
4.712
4.44
m
0.272
No
2
3
1.00
0.147
0.15
0.003
0.000
Area m2
0.125
0.250
m2
m3/s
m/s
m
4.715
20
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
4.45
0.2
0.17
0.004
0.000
m
m
m/s
m
m
20
0.120
0.226
0.022
m
m2
m
4.741
0.100
m
4.841
2.000
0.120
m
m
4.961
0.3
2.8
1061.8
0.152
m
4.810
m
m3/h
m
4.962
0.539
5.501
21
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Comprising
No
24.7
Filters
TWL
20.013
16.420
16.655
16.120
16.00
14.870
m2 area
Syphon level
Expanded media level
Normal media level
Natural ground level
Bottom of the media level
13.720
TWL in FW channel
Rise to inlet weir
Soffit of weir
Weir length
Water depth
Invert of channel
1.2
0.68
16.200
15.319
260
0.105
m3/h
m
0.08
0.8
0.34
0.35
0.75
0.60
m/s
m
m
m/s
m/s
16.120
Temp C
Kinematic visc
g
DH
Fittings
0.2
Actual Level m
16.000
16.200
5
1.52E-06
9.81
DH = (0.25LV^2)/((2Dg((log((k/3.7D)) + 5.74 /(Re^0.9)))^2))
Size
mm
No
Flow
m3/s
22
Velocity
m/s
Vel. Head
m
Headloss
m
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Exit loss
Butterfly valve
Tee (with rinse pipe)
Entry loss into pipe
1
1
1
1
Pipe length
TBC but to allow for future
installation of flow meter
1
1.54
0
0.5
0.07
0.07
0.07
0.07
0.75
0.75
0.75
0.75
0.029
0.029
0.029
0.029
Length m
0.4
0.029
0.044
0.000
0.014
Re
0.00015
0.072
0.751
197768
Total
0.008
0.008
16.313
3.700
20.013
16.120
0.750
0.500
0.05
0.200
0.900
m
m
m
m
m
Underside of slab
14.620
13.720
48%
35%
0.535
0.178
0.56
3.893
0.047
0.05
17.440
16.655
16.833
1.2
260
0.105
0.105
3
0.15
0.3
assumed
m
m
m
17.393
m
m
m sized to suit
m
m
m
m
m3/h
m
m
m
m
23
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
2.4.7 Filter
24972
Filter inflow
1041
Comprising
4.505
4.455
24.7
Filters
m2 area
4.350
4.197
TWL
4.100
FW Overflow
0.350
0.494
0.305
1.393
0.000
0.120
-0.681
Filtered Water Channel
-2.280
Head losses through filter
No of filters
TWL in FW channel
Rise to inlet weir
Soffit of weir
Weir length
Water depth
Invert of channel
260
0.105
m3/h
m
-1.13
0.08
0.8
0.34
0.35
0.75
0.60
m/s
m
m
m/s
m/s
0.120
5
1.52E06
9.81
DH = (0.25LV^2)/((2Dg((log((k/3.7D)) + 5.74 /(Re^0.9)))^2))
24
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
16.12
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Fittings
Size
No
mm
Exit loss
Butterfly valve
Tee (with rinse pipe)
Entry loss into pipe
1
1
1
1
Velocity
Vel.
Head
Headloss
m3/s
m/s
0.07
0.07
0.07
0.07
0.75
0.75
0.75
0.75
Length
m
Pipe length
TBC but to allow for future
installation of flow meter
1
1.54
0
0.5
Flow
0.4
0.029
0.029
0.029
0.029
0.029
0.044
0.000
0.014
Re
0.00015
0.072
0.751
197768
Total
0.008
0.095
0.400
3.700
4.100
0.750
0.500
0.05
0.200
0.900
48%
35%
0.535
0.178
0.56
3.980
0.047
0.05
0.12
0.34
0.2
1.2
260
0.105
0.120
m
m
m
m
m
-2.280
assumed
m
m
m
1.393
m
m
Underside of slab
-1.380
0.655
0.833
m
m
1.440
m sized to suit
m2
m
square
m
4.350
m
m3/h
m
4.455
0.05
m sized to suit
25
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
4.505
3.000
0.144
0.350
Overflow pipework
Flowrate
Dia
Velocity
24726
0.6
1.01
m3/d
m
m/s
Siphon
3
0.15
0.3
1.393
Weir level
0.420
m
m
104.05
69.4
278
1
0.064
5
2.5
695
347
once every 48 h
m3/d
m3/d
34
55
1360
2.5
0.44
26
m3/m2.h
m3/m2.h
m3/h
m/s
m
at 10C
at 30 C
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Adopted dia
0.45
0.36
1.05
0.15
m2
m/s
m
45
1111.5
20
0.140
0.15
Nm3/2.h
Nm3/h
m/s
m/s
m
Temp C
Kinematic visc
g
DH
Fittings
Exit loss into
CCT
Butterfly
valve
Tee
Entry loss into
pipe
Pipe length
Assumed
5
1.52E-06
9.81
DH = (0.25LV^2)/((2Dg((log((k/3.7D)) + 5.74 /(Re^0.9)))^2))
Size
mm
No
Flow
m3/s
Velocity
m/s
Vel.
Head
m
Headloss
m
0.7
0.28
0.72
0.027
0.027
0.7
0.7
1
1
1.54
1.2
0.28
0.28
0.72
0.72
0.027
0.027
0.041
0.032
0.7
0.7
1
Length m
0.5
0.28
0.72
0.027
Re
0.013
10
0.00015
0.278
0.723
333052
Total
0.006
0.119
0.7
27
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Turbidity
Raw water
Clarified water
Clarified water
57
25
115
2
1
NTU mean
NTU min
NTU max
NTU max
NTU min
C
Cw
F
W
Cw
Chemical addition
Alum dose
Assumed ratio SS/NTU
Solids concentration
Solids production
50
4
8.00
10.00
236
104
468
24.73
240
2
8000
25.48
0.76
Mld
mg/l
mg/l
mg/l
Mld
Mld
24.73
472
2
10000
25.94
1.22
Mld
mg/l
mg/l
mg/l
Mld
Mld
8.37
111.7
2
8000
8.49
0.12
Mld
mg/l
mg/l
mg/l
Mld
Mld
6059
931
kg/d
kg/day
Solids removed
Max flow average turbidity
Min flow min turbidity
28
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
12189
kg/day
11514.75
Inlet turbidity
Outlet turbidity
Flowrate max
Flowrate ave
Flowrate min
2
0.1
24726
24726
8369
NTU max
NTU for design basis
m3/d
m3/d (for solids calc basis)
m3/d
30.875
4.5
139
5
30.6
2.71
0.97
m3
Dump volume
Max wash volume per day
Min wash volume per day
110
695
347
m3
per day
m2 approx. assumes weir wall thickness 0.25m
m
0.3 above media for siphon
m3 per filter comprising vol above weir + vol of 2 no washwater troughs+ vol
below troughs
m3 excluding dump
m3
914
94
0.1
347
32
0.1
m3
kg/d assumes SS/NTU ratio = 2
kg/m3
FILTERS
44.506238
1360.5
1.0
0.7
m3/h
m/s
m
m3
m3
m
m2
W/m3
29
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Absorbed power
4.29
kW
Individual Pump
Flow
Pipe dia
Velocity
Temp C
Kinematic visc
g
DH
Fittings
Exit loss
Butterfly valve
NRV
Tee
Bends
107
0.15
1.69
m3/h
m
m/s
5
1.52E06
9.81
DH = (0.25LV^2)/((2Dg((log((k/3.7D)) + 5.74 /(Re^0.9)))^2))
Size
m
0.25
Pipe length
No
1
1
1
1
12
Flow
m3/s
1
1.54
1.7
0
0.75
0.06
0.06
0.06
0.06
0.06
Velocity
m/s
1.21
1.21
1.21
1.21
1.21
Length m
0.25
Vel.
Head
m
0.075
0.075
0.075
0.075
0.075
Headloss
m
0.075
0.116
0.128
0.000
0.677
Re
3500
0.00015
30
0.060
1.21
199942
Total
Adopt
20.474
21.470
25
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
25.48
50
10%
1258.00
12580
1.06
0.49
11.3
0.50
Mld
mg/l Al2(SO4)3.14 H2O
kg/d
kg/d
approx.
m3/h
m3/d
m3/h
19.0
2.5
7.60
2.76
2.5
3.04
0.5
m3
m
2.50
m
m
m
20128
2012.8
18115.2
18.079042
1.6
kg
kg
kg
m3
25.48
5
127.4
3.8
9
Mld
mg/l
Kg/d
Tonne
1 Tonne drum store for commonality
0.2
5.1
0.20%
2.55
1.4
1.66
2.0
152.9
4
20
mg/l
kg/d
m3/d
m
m
say 6 No 25 kg bags
kg/T d.s
Tonnes/d
31
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Consumption max
Concentration
Volume
Tank dia
depth
Adopt
Weight required
in 30 days
79.5
0.20%
39.73
2.5
8.09
3.0
Kg/d
m3/d
m
2384.1
say 32 No 25 kg bags
18.1
0
22.8
m3/d
m3/d ( Future requirement and not taken into consideration)
m3/d assuming no prechlorination ( intermittent)
20
400
8
23
assumed
l/p.e
m3/d
m3/d assumed
Potable to houses
Population equiv
Consumption p.e
Consumption per day
Washdown
Treated water losses max.
Treated water losses min.
31
22
m3 max /day
m3 min /day assuming min flow
6
2.05
2
0.653
2
hours
m3
m
m
m dia
32
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Distribution
EST
Alum
F1
Inlet Pumping
Station
F2
Lamella
Clarifiers
F3
Rapid Gravity
Filters
F4
F6
Chlorine
Contact Tank
Treated water
Storage Tank
F5
F11
F9
F7
F8
Waste Water
Holding Tank
To River
Stream Description
Fluid
Flow Regime
Flow
Instantaneous max m3/h
Maximum/max solids m3/d
Maximum /av solids
Minimum m3/d
F1
Raw Water
Continuous
F2
Conditioned RW
Continuous
F3
Clarified
Continuous
F4
Filtered
Continuous
F5
Treated
Continuous
25945
25483
8369
25945
25483
8369
24726
24726
8369
24031
24000
8022
8000
Mass flow
Instantaneous kg/h
Maximum kg/d
Average kg/d
Minimum kg/d
F6
Sludge
Intermittent
F7
Sludge
Intermittent
371
1219
757
0
1360
914
695
347
3706
12189
6059
0
33
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
94
32
F8
Sludge
Continuous
F9
Filtered
Intermittent
F10
Filtered
Intermittent
F11
Treated
1914
104
695
1360
695
31
347
347
347
22
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The design flow in Dujaila River is 45 m3/s. The water diverted for the water treatment plant is 1000
m3/h, or 0.28 m3/s, which amount to 0.62% of the design flow in the river, and will not have any effect
on downstream users.
34
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
4. MECHANICAL DESIGN
4.1 Mechanical Equipment General
4.1.1 Introduction
The raw water system transfers water from the Al-Dujaila- River to the flocculators/clarifier via the raw
water pipeline of 500 mm in diameter. The raw water pumping station is located on the Al-DujailaRiver bank and consists of an above-ground pump room and a below-ground wet well. The pump room
is located above wet well and consists of four vertical turbine pump (one standby) each with flow rate
of 350 m3/hr and 11.8 m head.
The treated water pumping station consists of a pump room and electrical room located above the
pumping station. The treated water storage tank chambers act as wet wells for the treated water pumps
and service water pumps. The treated water pumping station consists of four electric driven, two speed
vertical turbine pumps (one standby) each with capacity of 333.3 m3/hr and with head of 40.8 m. The
treated water is pumped from treated water storage tank to the elevated storage tank with 30 m head via
the treated water pipeline of 500 mm in diameter. The treated water pipeline also supplies the site
potable water system.
In backwash system, the two 100% capacity backwash pumps are provided. They are designed for 1350
m3/hr which is equivalent to a wash rate of 55 m3/hr.This is sufficient to provide the necessary bed
expansion at a water temperature of 30 oC. The backwash pumps will operate in alternating duty with
one serving as a standby.
Filter backwash water, clarifier sludge, and miscellaneous process wastes are routed from structures
and process units to the wastewater holding tank. All flow is by gravity with process unit sources
operating under the static heads in each chamber. Wastewater will be discharged by three pumps (one
standby) each with capacity of 410 m3/hr and a head of 12.2 m back to the Dujaila River downstream
of the plant intake via the wastewater pipeline of 250 mm diameter (see drawing no. 13-231-2212).
An emergency overflows from the process units are piped to an overflow tank sized to hold 30 minutes
full works flow. A single vertical spindle pump with capacity of 126 m3/hr and a head of 6.5 m is
located in the tank which pumps the overflow at a controlled rate through a pipe of 200 mm diameter to
outside treatment plant area.
The service water system provides treated water to miscellaneous plant service such as chemical makeup, wash down and fire fighting. The system is primarily located in the treated water pumping station
and consists of duty assist and standby pumps.
4.1.2 Scope of the Work
For Wasit subproject the length of transmission pipelines, service pipelines and static heads for all
pumping stations (Raw, Treated, Wastewater, Overflow and Service water) are different than the
standard design .Also; the produced water through a transmission treated water pipeline will be directly
connected to the elevated storage tank with a minimum height of 30 m.
Based on the above circumstance, many drawings from standard design are selected and major changes
have been performed for calculating the slopes for interconnecting pipes and head losses for
transmission and service pipelines for each pumping station. All the levels in pumping stations general
arrangement drawings have been changed to fit the new natural ground level of Wasit site. Cross
reference numbers in all drawings are reviewed to fit the new set of the drawings .Also; several new
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
35
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
drawings are constructed to cope with new subproject in Wasit. Finally the bill of quantities and
technical specifications for each item is revised and changed accordingly.
4.1.3 Design Criteria
The mechanical system is designed to meet the criteria specified below:- Colebrook-White formula is used for head loss calculations for all piping systems.
- 1.25 mm roughness coefficient is used for Ductile Iron pipe (cement lined) up to 20 years old.
- Pump discharge velocity (2-3) m/s.
- Pump discharge header velocity (1.5-2) m/s.
- DI pipe will adopt for all process yard pipe work to carry water and wastewater.
- Treated water pipeline is designed for ultimate capacity.
- The slopes for interconnecting pipes in site are adopted to fit the required invert for each unit.
- A wastewater pumps are sized to evacuate the tank in 2 hours.
- NPSH definition is used to calculate and check the cavitations for pump suction side.
- Natural ground level of Wasit site is 16.00 m.
4.1.4 Calculations
A computer program is developed for calculations of head losses in transmission and service pipelines,
Net Positive Suction Heads (NPSH) and power required for the pumps in order to check the previously
selected pumps in standard design technical specifications. The results of the calculations are shown in
computer outputs.
Based on the scope of the work, design criteria and the results of the calculations, the major changes in
standard design can be summarized as follows:1- The slopes for interconnecting pipes in the yard piping are calculated and adopted to fit the required
invert for each unit within the new layout and new drawings (13-231-2200/13-231-2201/ 13-231-2202/
13-231-2203 and 13-231-2204) have been constructed.
2-New dimensions for longitudinal sections of yard piping layout for process, wastewater and overflow
are calculated and new drawings (13-231-2205/13-231-2206 and 13-231-2207) have been constructed.
3- Based on new layout, new tables for manholes specifications (13-231-2208) and piping length,
diameters and fittings (13-231-2210) are formed.
4- Based on Wasit site layout a new drawing for yard service and potable water piping systems (13231-2211) is produced. Also, another new drawing (13-231-2212) is formed for drainage system of
wastewater and overflow water.
5- For off-yard transmission pipelines, pump head losses for raw water, treated water, wastewater and
overflow pumping stations are calculated. Generally, the head losses calculation results showed lower
values for pumps heads than that selected pumps in the standard design. Therefore, the pump capacities
for raw water, treated water, and wastewater pumping stations in standard design are charged for Wasit
subproject. The results of the calculations for pump heads are shown in attached computer outputs.
6- For on-yard piping, the pump head losses for service and backwash pumping stations are
calculated. The results showed that, the values for pump head losses are almost the same as that for
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
36
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
pumps heads selected in standard design. Therefore, the selected pumps for standard design will be
recommended and used for service and backwash pumping stations. The results of the calculation are
shown in attached computer outputs.
7- The net positive suction heads for all pumping stations are calculated as shown in computer output,
checked and compared with the values of NPSH in technical specification of standard design. All the
values are within the selected range.
4.1.5 References
- All general arrangements
- Hydraulic design guide
- Drawing No. 13-231-2200 Wasit landscape pipelines
- Drawing No. 13-231-2201 Piping layout 1 0f 4
- Drawing No. 13-231-2202 Piping layout 2 0f 4
- Drawing No. 13-231-2203 Piping layout 3 0f 4
- Drawing No. 13-231-2204 Piping layout 4 0f 4
- Drawing No. 13-231-2205 Yard piping process pipelines
- Drawing No. 13-231-2206 Yard piping wastewater pipelines
- Drawing No. 13-231-2207 Yard piping overflow piplines
- Drawing No. 13-231-2208 Manhole schedule
- Drawing No. 13-231-2209 Thrust block schedule
- Drawing No. 13-231-2210 Pipe schedule
- Drawing No. 13-231-2211 Service and potable water piping system
- Drawing No. 13-231-2212 Draniage system for wastewater and overflow water
- Treatment plant process output
- Fluid Mechanics, F. White, Second Edition
4.1.6 Sample of the Calculations
The results of all the calculations for yard piping, transmission pipelines head losses, net positive
suction heads for pumps and pumps power are represented and attached as a computer outputs for:- Head losses calculation for raw water pumps
- Head losses calculation for treated water pumps
- Head losses calculation for wastewater pumps
- Head losses calculation for overflow pumps
- Head losses calculation for backwash pumps
- Head losses calculation for service water pumps
37
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
38
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
39
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
40
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
41
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
42
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
43
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
44
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
45
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
46
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
pressures are developed at the pumping station. Vacuum condition is developed that violates the
downsurge pressure criteria; the minimum pressure level was 11.16m at the pumping station. The
developed maximum pressure level of 32.86m occurs at the station, and is within the acceptable limit
that the system can withstand. It is recommended that this system be equipped with a surge system to
control the negative pressure and to control undesired mass oscillation.
Trials were made with different surge tank sizes. It was found that a surge take with a circular cross
section 1.4m in diameter is suitable to control the pressures within the system during the transient state.
Figure (2) shows the system response when protected by the surge tank that is connected to the main
pipeline at the station by a pipe of a diameter of 300mm. With the surge tank the downsurge pressure
head is limited to a positive head. The maximum water level inside the tank was 24.2m, which was
developed during pump start, and the minimum water level during the pump failure was 18.47m. The
bottom level of the surge tank is set equal to the ground level of 16m. The height of the surge tank is set
equal to the maximum water level developed during the pumps start plus 10% of the surge tank height, as
a factor of safety and to account for the pipeline aging, plus 1m as a free board. Thus, the top level of the
surge tank is set equal to 26m.
4.2.3.2 Treated Water Pump Station
The finished water pump station and pipeline system was modeled with the following assumptions:
Surge Events: The causes of the surge events are simultaneous power failure to pumps and simultaneous
pump start up.
Pipelines: All pipelines are assumed to be ductile iron pipeline with a rated water working pressure of
105m and an allowable downsurge and upsurge pressure allowances as follows:
Downsurge: To eliminate problems resulting from air admission to the system, no negative or subatmospheric pressure is allowed along the pipeline.
Upsurge: Ductile iron pipeline has a surge pressure allowance of 70m for a total working plus surge
pressure allowance of 175m.
Roughness Coefficient: The pipeline was assumed to have a relative roughness, , of 1.5 mm for a
Darcy-Weisbach friction factor, f, of 0.026.
Source/Delivery Points: The source of supply of the treated water pump station is the water treatment
plant clear well. The clear well is modeled with maximum and minimum levels of 15m and 10m,
respectively. The treated water pump station feeds an elevated storage tank with a maximum water level
of 49.1m and a minimum of 44.1m.
Pump Station: Similar to the raw water pump station, each pump is modeled with a rotational moment
of inertia equal to the pump/motor combination. For the finished water pump station three pumps are
assumed to be operating. Each pump produces 350m3/h and for a total flow rate of 1000 m3/h. The higher
capacity pump/motor units have a combined moment of inertia of 4.7 kg-m2.
Pump Characteristics: Similar to the raw water pump station power failure at the pump station and
pumps start are modeled to assess the worst-case surge condition. The curves for a pump of the same
type with approximately the same specific speed was used.
Valve Characteristics: Similar to the raw water pump station, check valves on the pump discharge
piping are used to prevent reverse flow through the pumps. The check valve was treated in similar way as
in the raw water pump station.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
47
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Pressure Wave Speed: A wave speed of approximately 1,160 m/s was utilized in the model. The
program performs minor adjustments to the wave speed to accommodate pipeline segments of different
lengths.
The head variation at the pump station due to pumps start and failure are shown in Figure (3). The
maximum pressure developed within the system reached a level of 66. No vacuum pressure occurred. A
minimum pressure level of 31.12m occurred at the station.
It is recommended that the system be equipped with a surge control system. Several mathematical model
runs were made with different air vessels sizes, the recommended surge control system is a 10 m3 hydro
pneumatic tank with 70% of the total volume initially charged with water and 30% charged with
compressed air. The results for the protected system are shown in Figure (4). The pressures are kept
within acceptable limits at the station and along the pipeline.
It should be noted that both raw water and treated water analyses and control strategies that are
recommended should be verified once refinements to system control logic and equipment selection has
been made. Field tests are required to verify the variation of the pressures due to pump failure and pump
start just when the raw and treated water stations are completed
4.2.4 Analysis Summary and Recomendations
Surge control facilities are required for both of the raw water and finished water systems. A surge tank of
a cross sectional area of 1.4m with a maximum top level of 25.5m is recommended to control the
transient pressures within the raw water system. .
A 10 cubic meter hydro-pneumatic tank is recommended to control the transient pressures within the
finished water system. Generally, hydro-pneumatic tanks of this size have a free water surface to
compressed air interface. The water surface level in the tank will fluctuate with system pressure and
therefore is continuously adjusted by a compressor and receiving tank. This type of system allows
significant flexibility and will protect the system over a wide range of operating conditions. However,
general maintenance on the compressor is required to ensure operation. If the compressor is not
operational, the hydro-pneumatic tank will not protect the system during a transient event. An alternative
to the compressor system is an air bladder. The bladder is positioned within the tank during the
manufacturing process and after installation the bladder is inflated to a set pressure. This set pressure is
generally the higher end of the systems normal operating bandwidth. A bladder system does not provide
as much flexibility as a compressor designed system, but the inflated bladder system will maintain the set
pressure for an extended period of time without the need for constant adjustments. For a hydropneumatic tank this size periodic adjustments may be required depending on temperature and bladder
elasticity. Also, there are limited manufacturers of bladder hydro-pneumatic tank systems. If available
and cost feasible, a bladder tank is recommended.
4.2.5 References
1- Chaudhry, M. H., Applied Hydraulic Transients, 2d ed., Van Nostrand Reinhold, New Yorle 1987.
2- Larock, B. E., Jeppson R. W., and Watters G. Z., Hydraulics of Pipeline Systems, CRC Press LLC,
2000.
3- Parmakian, J., Water Hammer Analysis, Prentice-Hall, New York, 1955.
4- Wylie, E. B., and Streeter, V. L., Fluid Transients in Systems, Prentice-Hall, 1993.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
48
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
35
Head (m)
25
20
15
10
0
25
50
Time (Sec.)
Figure (1). Head variation at the raw water pump station without pressure control device.
49
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
75
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
26
Head (m)
24
22
20
18
0
25
50
Time (Sec.)
Figure (2). Head variation at the raw water pump station with pressure control device.
50
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
75
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
70
60
Head (m)
55
50
45
40
35
30
0
25
50
Time (Sec.)
Figure (3). Head variation at the finished water pump station without pressure control device.
51
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
75
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
60
Head (m)
55
50
45
40
0
25
50
75
100
125
150
175
200
Time (Sec.)
Figure (4). Head variation at the finished water pump station with pressure control device.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
52
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Non-process building
53
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
54
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
In addition to the air ventilation specified for chlorinating station, a complete air cleaning
system (scrubber unit) will be provided for removable of chlorine from contaminated exhaust
air following a chlorine leak in the drum store.
4.3.4 Sample of Calculations
4.3.4.1 Non-processing building
A computer program is developed for the calculations of cooling and heating loads for all
spaces in the non-processing building . All the coefficients used in the calculations are based
on ASHRE standards with correction to our ambient conditions (latitude, month,
temperature,..etc.) and with the following conditions.
- Outside Summer: 46 C Dry bulb and 23C Wet bulb.
- Outside Winter:
0C
55
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
= 847 x 20
= 16940 m3/hr
= 9960 CFM
- (2) Nos. Evaporator Air Coolers with 5000 CFM each are selected.
- Load calculation for conditioned zones
A computer program is developed for calculation of cooling load for various zones in nonprocessing building. The calculations are based on the design criteria and the correction
procedure to fit the ambient temperature of 50 oC. The computer output shows the details of
the calculations and cooling loads for other zones are shown in the attached table.
4.3.4.2 Process buildings
The process buildings comprise pumps halls, rapid gravity filter, chemical, chlorine buildings
and other associated buildings. These buildings are provided with ventilation system thought
fan extraction units and sand trap filters. A computer program is developed for calculation of
ventilation loads for various spaces. The result of sample calculation is shown in computer
output. Loads for others zones are calculated and checked.
4.3.5 The Changed Drawings:
The drawing No. (13-299-5600) shows the technical information about the HAVC
equipment used in the WTP. The following units are not found in above drawing.
1-
2-
3-
4-
5-
EXF-80-1001
6-
EXF-80-1002
Chemical Building
So, these units are added in the table with their technical information ( split unit type,
capacity, power, voltage, phase .etc)
4.3.6
Bill of Quantities:
The bill of quantities is revised, checked and changed accordingly to fit the supplied
drawings.
4.3.7
Specifications:
The specifications of all HVAC system equipment are checked based on the load calculations
and requirements.
56
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Building
Admini.
Mainten.
3-BR
2-BR
2-BR
Guard
RWPS
RGF
Chemical
Electrical
TWPS
Zone
02
08
11
12,13
14
17
07
09
10
03
06
07
08
10
11
B07
B03
B06
B08
B11
A03
A06
A07
A08
A10
02
05
Main Switch
Operator
Panels
Control
MCC
Main Switch
Panels
Admin.
Elect.
Total Heat
(Watt)
Total Heat
(Btu/hr)
GTH
(Btu/hr)
19628
12568
12009
12673
11170
22155
8592
7016
3169
6533
4822
5512
4499
5422
4485
3918
5429
3255
5248
5797
5762
5101
3918
3255
5429
3028
2562
16800
4700
9900
12400
12600
2300
16600
10900
1800
8600
66931
42731
40050
43088
38092
75548
29298
23924
10815
22277
16464
18812
15355
18505
15307
13372
18529
11101
17911
19709
19648
17409
13372
11101
18529
10334
8744
57120
15980
33660
42160
42840
7820
56440
37060
6120
29240
83664
53413
51186
53860
47615
94436
36623
29905
13518
27846
20580
23515
19193
23131
19133
16715
23161
13876
22388
24636
24560
21761
16715
13876
23161
12917
10930
59976
19176
35679
46376
46695
9384
59800
40700
8000
35088
57
Selected
Capacity
(Btu/hr)
3x30000
2x30000
2x30000
2x30000
1x48000
2x48000
2x22300
2x22300
1x22300
1x30000
1x22300
1x30000
1x22300
1x30000
1x22300
1x22300
1x30000
1x22300
1x30000
1x30000
1x30000
1x30000
1x22300
1x22300
1x30000
1x18000
1x22300
2x30000
1x23200
1x36000
2x23800
2x23800
1x12000
2x30000
1x42000
1x12000
2x18000
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Admin. Building
SUBJECT
HVAC
Sample of Calculations
DATE
30/6/2007
CHECKED
DATE
06/01/2007
REFERENCES
(1). ASHRAE FUNDAMENTALS 2001.
(2). ASHRAE FUNDAMENTALS 1997.
DESIGN DATA
Maximum DB
C
50
(Ref. 1, Ref. 4)
Outside Design Air Temperatures
Maximum WB
C
F
122
23
73.4
Minimum DB
C
F
Daily DB Range
C
F
24
19
75.2
66.2
Ventilated Spaces
Relative
Humidity
%
73.4
30
86
50
Max. Temperature
BUILDING DATA
Surface Conductances and Resistances
Inside Surface
Min. Temperature
C
F
8
46.4
Max. Temperature
C
F
40
Surface Type
Surface
Position
Inside Surface
Horizontal
Vertical
58
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
hi (W/m2.oC)
9.26
8.29
Ri (oC.m2/W)
0.108
0.121
104
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Outside Surface
Surface Type
Outside Surface
Surface
Position
hi (W/m2.oC)
Ri (oC.m2/W)
Any
22.70
0.04
summer
Thermal Properties
Item
Roof
Exposed Walls
Gypsum Plaster
Concrete
Cement Morter
Asphalet
Insulation Styrafoam
Sand
Concrete Tile
Gypsum Plaster
Brick
Cement Morter
Thickness
Conductivity
Resistance
ka
Rb
mm
m.
W.m/m2.oC
20
200
20
0.020
0.200
0.020
1.000
0.500
0.100
0.040
0.020
0.025
0.020
0.81
1.37
0.72
97.5
0.517
1.83
0.76
0.81
0.72
0.72
100
40
20
25
20
Ud
Total Resistance
R c (oC.m2/W)
C.m2/W
W/m2.oC
Rsummer
0.025
0.146
0.028
0.010
0.967
0.055
0.053
1.000
0.035
0.450
Usummer
1.44
0.697
1.65
0.606
ZONE DIMENSIONS
Length
Width
Height
Volume
Room
ft
ft
ft
m3
ft3
Zone
8.50
27.9
4.50
14.8
3.50
###
134
4727
59
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Cooling Load from Heat Gain through Exposed Roof, Walls, Doors and Conduction through Galss
Equation: q = UA(CLTDCORR.)
Section
m2
Net A
Roof
NE wall
NW wall
SE wall
SW wall
1
0
0
1
0
Where:
U-Factor (W/m2.oC)
CLTD
o
C
LM
0.697
0.606
0.606
0.606
0.606
16
10
8
12
8
0.50
-0.50
0.00
0
0
28
21
40
29.75
0
K = darkness correction
Corr.
CLTD
o
C
1.00
40
Table 30, Roof 1
0.85
35
Table 32, Wall 5
0.85
24
Table 32, Wall 5
0.85
39.4
0.85
33
Table 32, Wall 1
F=ventilation correction through
falsh ciling
tm = mean outdoor
temperature
Net A
Windows
Solar Cooling Load Through Glass
Equation: q = A(SC)(SCL)(SHGmax)
where
W/m2.oC
6.42
Corr.
CLTD
o
C
27
Windows
NE window
m2
Net A
0
SC
SCL
SHGmax
0.64
0.81
445
60
Cooling Load
W
Cooling
Load
Btu/h
1040
3547
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
NW window
SE window
SW window
0
0
6
0.64
0.64
0.64
0.81
0.81
0.81
445
571
571
0
0
1776
1776
Where
Sensible Heat
12
latent Heat W
90
CLF
95
qsensible
1.0
1080
Ful
Factor
Fsa
CLF
q
(W)
q
(Btu/h)
720
3.41
1
1.2
1
864
2946
Cooling Load from Infiltration Air
Infiltration through wall surface is neglected as insignificant.
To calculate the infiltration through doors, estimate 100 ft3 per person per door passage (Ref. 2 on pg. 28.34).
Further estimate each door use is at 2 persons hour.
74.40 L/s
Qinfiltration = 2 x 100 /( 60 *
qsensible = 1.22Q(to - ti)
2.118 =
qlatent = 2940Q(Wo-Wi)
Q
L/s
74.40
74.40
Factor
1.22
2940
Oc
kg(water)/kg(dry
air)
27
0.0010
61
q
W
2451
219
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
q
Btu/h
8357
746
qlatent
W
1140
Cooling
Load W
2220
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
item
Roof
Exposed surfaces
Glass
Equipment
People
Lights
Infiltration
Subtotal
Grand Total Load
Summary of Cooling Load Calculations
Sensible Cooling
Load W
780
1161
3996
1000
1080
864
2451
2451
11332
219
1359
1359
3887
746
4633
9267
Total Cooling
Load
Btu/h
47602
3.97
EQUPIMENT SELECTION
The load calculation is based on 46C temperaure outside condtion.
Equipment design is based on 35 C ambinent temperature
Total Load will
be=
Meter/Ton=
4.96
Tons
0.130
59503
62
2661
3958
13626
3410
3683
2946
8357
8357
38641
1140
Total Cooling
Load
W
12690
Room
Zone
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
Btu/h
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Nos. of Units=
0.89
Q=
0.1
(Ref. 4)
RSH
1.228(1BPF)(tr ADP)1000
Where
Qsupply =
0.897
m3/s
Qsupply =
CFM/Ton=
Fresh Air=
1900
383
190
Cfm
701
CFM Each
Unit
CFM
63
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Sample of Calculations
SUBJECT
PROJECT NAME:
COMPUTED
DATE
24/5/2007
Chlorinating B.
CHECKED
DATE
28/5/2007
Drum Store
Ventilation System
Wasit WTP
REFERENCES
(1). ASHRAE FUNDAMENTALS 2001.
DESIGN
DATA
Maximum DB
C
F
46
115
24
75
46.4
Max. Temperature
C
F
23
Minimum DB
C
F
8
46
Ventilated Spaces
Relative
Min.
Humidity
Temperature
%
C
F
73
50
Daily DB Range
C
F
19.2
66.56
Max. Temperature
C
F
46.4
40
104
ROOM DIMENSIONS
Ventilated Spaces
Length
Room
Chlorinating Building
Width
Height
Volume
3
ft
ft
ft
ft3
18.00
59.8
10.90
35.8
6.00
19.7
1177
41567
ft3
# of air changes
per hour
Air
Required
cfm
Air Required
+ 10%
cfm
41567
5542
6374
6374
Volume
Room
Chlorinating Building
Total
EQUIPMENT
SELECTION
The Chlorinating building will be provided with one Exhuast Ventilator
Select Centrifugal Exhaust Ventilator, Roof Mounted, Belt Drive
Required Unit Numbers
Unit with Capacity of
Intake Louvers:
Select Sand Trap Louver.
1
6374
CFM
3009
l/s
2700
l/s
64
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Heat Required
Q
Q= 1.22xVol. Flow
Rate ( m3/s)x Chang in Temp.(C)
kW
47.7
0.2
F.S
Tatal Heat Required
The selected capacity is recommended
Buildings
Chlorinaing
WWHT
TWPS
Raw Water P.S
Chemical
Rapid Filter
57.27
kW
65
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
4.4.1.2 Operation
The Scrubber system shall be integrated into the Chlorine Building gas detection and
ventilation system. The anticipated system operation [subject to the particular suppliers
operation and HSE guidelines] shall be briefly as follows:
1. Should chlorine gas be detected by the sensors at concentrations greater than the
recommended sustained exposure threshold [0.5ppm] but less than 3ppm, the low level air
extraction system would be initiated, the building evacuated, and the vapours discharged to
atmosphere via the high level ducting system. When gas concentration levels have reduced to
below the exposure threshold, operations can re-commence.
2. Should chlorine gas be detected by the sensors at high concentrations [>3mg/l], an
Emergency Alarm would be sounded. On alarm conditions all persons would be evacuated
from the building and the low-level air extraction and associated louvers would be
automatically closed, thus containing the chlorine vapours. Site emergency procedures would
be initiated.
The high-level air inlet louver should be opened and the Gas Scrubber started. Once
concentration levels have significantly reduced to less than 3mg/l for a sustained period, the
gas scrubber would be shut down. The chlorine detector or manual remote start switch will
activate the system in two steps. The caustic pump is activated first to permit proper wetting
of packing in the scrubber stages before starting the exhaust fan, with a 0-5 second adjustable
time delay. The time delay would be typically set for 3-5 seconds. This feature will allow the
scrubber to be ready prior to passing any chlorine-laden gases through it. The exhaust fan will
be placed downstream of the scrubber. This feature will allow the complete system to be
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
66
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
under negative pressure until the gases are completely scrubbed. The absorber would be
placed on top of the caustic storage tank, which is an integral part of the system. Secondary
containment of the caustic will be by means of a concrete bund covered within the Civil
works. The technical specifications of Chlorine Gas Scrubber are given below.
Storage Gas
Chlorine
Capacity
1 Ton
Leak Rate
45 kg/min
Flash Rate
45 kg/min
Ventilation Rate
5000 cfm
180.787 ppm
3 ppm
99.9972
Caustic Requirements
7.949 liters
The fire protective measures for the building shall comprise of (1) providing portable
fire extinguishers (2) hydraulic hose reels with packaged pump sets.
The lay-out as specified, workmanship and materials of pipes and fittings shall
conform to the National fire protection standards and/or the relevant BS: codes of
practice CP: 402 and its parts.
Portable fire extinguishers of the specified type and weight shall be sited as directed
by the Engineer in prominent positions on exit routes in such a way that no person
need travel more than 30 m.
The extinguishers shall be supporting, the handles are 1.00 m above floor level, and
shall be fixed in similar positions on each floor.
67
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The hose shall be of red rubber 19 mm/25mm smooth hose or of the specified size
with a working pressure of ( 50 Ibs /sq. in ) and of the specified length from 18.30 36.60 m terminating in 6.4 mm nozzles as specified.
The hose reel and cabinets should be fixed so that the centre is between 765 mm and
1370 mm above floor levels.
An adjustable type pressure reducer shall be provided between the hose and standpipe
to protect the hose against excessive pressure beyond 50 psi.
The installation of the system shall closely follow the construction of the building to
provide protection during the construction period.
Positions for inlets should under all circumstances be electrically earthed and be
contained in a glass fronted box, complying with BS: 3980.
The system shall be of carbon dioxide and ABC powder according to the standard
codes and regulations.
They shall all be complete with header tank, heater and eye bath in accordance with ANSI
2358.0-1998 and the specification detailed herein.
The showers shall be provided with:
Volt free contact remote alarm facility indicating safety shower in use
Water break tank with twin ball float valves and 220 Volt thermostatically
Controlled heater
Volt free contact remote alarm facility indicating tank low level
Eye bath, Located on the left hand side of the shower units and accessed from the front
Mounting brackets
68
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
5. ELECTRICAL EQUIPMENT
5.1 Introduction
The electrical works, referred to, in this report include the electrical installation for the whole
project, the site lighting, the electrical substation for the raw water intake and the electrical substation
for the water treatment plant.
Rated voltage
Rated frequency
Rated short time current (1 Sec)
Impulse withstand voltage
Rated power frequency withstand
Nominal interrupting capacity
12kV
50Hz
25kA
75kV peak
28kV/1 min
500 MVA
5. 3.3 Transformer
Phase frequency
3/50 Hz
Connection
Delta/star with the neutral point solidly earthed
Vector group
Dyn 11
Nominal voltage ratio
11kV-416/240V
Tapping : HV off Load
at2X2.5 %
Cooling
ONAN
5.4 Methodology
For each individual building, the lighting system was designed according to the code for lighting,
CIBSE. For all installations the voltage drop in wires and cables have been calculated according to the
IEE wiring regulation, and found to be within the accepted limits.
69
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
PANELBOARD: ELE.MDP2-12.1001
LOCATION: MAINTENANCE
BLDG (RM NO 8)
11.92
---
10.27
---
9.8
ELE.DP2-12.1002
12.55
---
13.73
---
13.65
TPN OULET
1.33
---
1.33
---
1.33
TPN OULET
1.33
---
1.33
---
1.33
27.13
26.66
26.11
PHASE LOAD
33.8
33.33
32.78
CKT
BKR
BKR
ELE.DP1-12.1001
kVA
A
PHASE: 3PH
MOUNTING: SURFACE
CKT
LOAD
DESCRIPTION
VOLTS: 230/400V
50
15
13
3P
3P
14
WIRE: 4W
kVA
A
1.33
TPN OULET
1.33
15
60
20
16
3P
3P
17
6
15
20
19
3P
3P
20
2.67
15
20
22
11
3P
3P
23
12
2.67
--2.67
2.67
--TPN OULET
2.67
--2.67
0.0
--SPARE
0.0
24
TOTAL
--TPN OULET
21
10
--1.33
18
LOAD
DESCRIPTION
--0.0
6.67
6.67
6.67
TOTAL LOAD
99.91 kVA
70
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
---
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
PANELBOARD: ELE:DP1-10.1001
BUS AMPS: 60 A
LOCATION: SITE
VOLTS: 230/400V
PHASE: 3PH
MOUNTING: FLOOR
0.16
---
0.16
---
0.16
SITE LIGHTING
0.32
---
0.32
---
0.32
SITE LIGHTING
---
---
1
1.48
1.48
1.48
PHASE LOAD
2.98
2.98
2.98
CKT
BKR
BKR
SITE LIGHTING
kVA
CKT
LOAD
DESCRIPTION
10
20
10
3P
3P
11
WIRE: 4W
kVA
A
SITE LIGHTING
1.5
1.5
12
10
20
13
3P
3P
14
LOAD
DESCRIPTION
--1.5
0.0
--SPARE
0.0
15
--0.0
---
10
16
BLANK
3P
17
---
18
---
9
TOTAL
1.5
1.5
1.5
TOTAL LOAD
8.94 kVA
The other boards schedules are included in drawings (13-232-6011, 13-232-6012, 13-232-6013, 13232-6014, 13-232-6015, 13-232-6016 & 13-232-6017).
The size of wires and cables required have been chosen according to the IEE regulation. It should be
appreciated that the important factor in this choice, namely, the voltage drop is calculated and checked
to be within the accepted limits. Sample of calculation for voltage drop is shown in section 5.5.2. The
cable and wire sizes for the individual building are shown on the relevant drawings. The sizes of the
main cables are shown on the cable schedules (drawings No. 13-232-6032, 13-232-6033, 13-2326034, 13-232-6035, 13-232-6036, 13-232-6037, 13-232-6038, 13-232-6039, 13-232-6040, 13-2326041, 13-232-6042 & 13-232-6043 ).
2 (Sxl)
xAxVs2
x 100% ..(1)
3Sxl
xAxVs
x 100% ..(2)
71
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
This voltage drop should not exceed 1.5% for the farthest load unit to the distribution board, as shown
through the entire examples.
Where:
V%: Voltage drop percentage.
S: Apparent power [VA] per phase
l :Length of cable [m].
A: Cross sectional area of cable [mm 2 ].
: Cupper Conductivity [m / . mm 2 ].
Vs: Voltage [V].
Throughout this project, A and values are as the following:
A: - 4.0 mm2 (For power circuits)
- 2.5 mm2 (For lighting circuits)
: 56 m / . mm 2 (cupper conductors)
2. Alternatively, the voltage drop may be calculated through the use of the tabulated voltage drop
values, taken from the reference below.
Reference:
Requirement for Electrical Installations-IEE wiring regulation-sixteenth edition BS 7671:2001.
3. Calculation Results
Example 1: Consider the lighting circuit number (4) RWI Raw Water Intake building, which is
presented as shown below. (Units are presented as load and cable length).
22.1
Single phase line
ELE.DP1-20.1002
130 VA
V% =
2 ( Sxl )
xAxVs2
x 100%
2 x130 x 22.1
x 100%
56 x 2.5 x 230 2
This may be corrected for a conductor temperature of 70 C , and the result would be V%=
0.093< 1.5 %
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
72
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
8.5
4.7
3.3 KVA
V% =
3Sxl
xAxVs2
x 100%
3 x1100 x13.2
x 100%
56 x 4 x 230 2
This may be corrected for a conductor temperature of 70 C , and the result would be V%=
0.25
The alternative method would give V%= 0.24
So it is safe to use the previous design
n..u.m
A
73
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Bld No.
Room No.
Lumen per
Fittings
No. of
Fittings
Area m2
Illumination
Lux
12+13
4*1350
45
346
17
1350
42
35.4
769
14
1350
23
24.38
611
4*1350
32.77
475
4*1350
12
61.41
506
08
2*3350
18
81
714
07
2*3350
12
52.68
732
11
12
Reference:
5.6 Drawings
The BOQ has been checked and all necessary changes have been made to comply with the
changes in the drawings.
5.8 Specifications
74
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
A Supervisory Control and Data Acquisition (SCADA) system will be employed for the new
Wasit Water Treatment Plant (WTP). The SCADA will be designed around Programmable
Logic Controllers (PLCs) connected to the facility communications network. PC based
Operator Workstations, also connected to the network will provide the operator access to the
process via the Human-Machine Interface (HMI) graphical software package.
The SCADA shall be installed in a distributed manner in that the PLCs will be located
throughout the facility in close proximity to the process equipment they serve.
In addition to the SCADA system, the process control will be supplemented by a range of
Local Control Panels (LCP) and Vendor Control Panels (VCP) that provide local manual back
up control capabilities for the associated process equipment.
6.1.2 Main Process Control Center
The main Process Control Center (PCC) will be located in the Filter Building and allow the
operators access to monitor and control the WTP facility. The PCC shall be equipped with a
main operator console to house Operator Workstations (OWS), and an Operator/Engineering
Workstation (EWS). Two networked printers will support the PCC Workstations with one
serving as a screen printer (color laser) and one serving as an alarm printer (B&W laser). A
modem is supplied for remote access to the SCADA system as well as for an Internet
connection to the facility.
The Operator Workstations shall be Windows-based PCs with the most recent Pentium
processor and furnished with the necessary application software to provide the graphical
interface. The Operator Workstation graphical interface screens allow for monitoring and
control of the various process systems as well as alarm monitoring, trending and report
generation.
The Plant Historian, also located in the main operator console shall collect process data and
archive it at an adjustable time interval. Archive data can be retrieved at the Operator
Workstations to provide trending and log displays. Optical disks shall be provided for longterm data storage. The Plant Historian is a dedicated computer for the role of information
handling and should serve no other function.
The Engineering Workstation will be used for modifications to the PLC ladder logic,
additions/deletions of system database, modifying and building graphic screens, and
monitoring the network status. When this station is not being used in an engineering role it
can be used as a secondary Operator Workstation.
A communication closet will serve as the central location for termination and routing of the
on-premises network and communications wiring systems. The communication closet will
house the network communications cabinet as well as the Uninterruptible Power Supply
(UPS), the telephone point of demarcation and equipment, a load panel for lighting and
receptacle power and miscellaneous ancillary facility support equipment.
6.1.3 Control Network
The Process Control System shall use a state-of-the-art open, distributed control configuration
for maximum reliability, fault-tolerant reliability, expandability, and ease of operation and
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
75
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
maintainability. Local control panels serve as the local input/output (I/O) cabinets as well as
local manual control.
The Control Network shall be a manufacturer standard network that interconnects the
distributed PLCs, operator workstation, engineering workstation at the Process Control
Center.
The control network shall be the PLC manufacturers standard communication configuration.
The network shall consist of CAT5 (copper) for node to node connections.
A bus topology will serve as the backbone for the control network. The bus topology
increases the fail-safety of a network, as communications can be maintained even if a node on
the network fails.
A wireless Ethernet connection shall serve as the link between the main treatment facility and
the remotely located Raw Water Pump Station.
6.1.4 Local Control Panels
Local input/output (I/O) is handled using rack mounted I/O modules connected to the
respective PLC processor. Analog and discrete process signals from the field are connected to
the I/O modules for inclusion to the SCADA monitoring and control system.
Each Local Panel equipped with a PLC shall be fed power from an UPS located in the
respective LCP. Equipment shall be properly grounded for minimal interference from
electrical noise.
The LCPs shall be connected to the facility communications network by means of copper
cable in a bus (drop) configuration.
The facility is serviced by six (6) local control panels that are each fitted with a PLC. Each
cabinet shall contain the respective PLC chassis and components as required. The hardware
includes a PLC processor module, a communication module, a power supply, UPS and
assorted input/output (I/O) modules. All wiring from the field devices to the I/O cabinet shall
be terminated on terminal blocks in the lower portion of the enclosure.
The six local control panels and their associated process areas are as outlined below.
Reference drawing 13/200/7106 for details relating to the SCADA system arrangement.
6.1.5
Distributed PLCs
PLC-WW and its associated hardware is located in local panel WW.P-70.1000 LCP,
Wastewater local control panel, reference drawing 13/200/7250. This PLC serves all
I/O points associated with the Wastewater tanks and pumps. This cabinet is
connected directly to the main facility communication network via copper cable.
76
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
PLC-TW and its associated hardware is located in local panel TW.P-60.1001 LCP,
Treated Water Pump local control panel, reference drawing 13/200/7265. This PLC
serves all I/O points associated with the Treated Water Pumps, Treated Water Pump
Storage Tank, Elevated Storage Tank, Electrical Generator and Service Water
Pumps. This cabinet is connected directly to the main facility communication
network via copper cable.
Equipment furnished with an L-O-R mode selector will provide local control from the LCP
start and stop pushbuttons or remote control from the PLC. When remote control is selected,
this can be either automatic PLC based control from PLC software algorithms (Hand-OffAuto) or, if selected at a workstation, operator manual control from the SCADA workstations.
When a piece of equipment requires a mode changed i.e. from Local to Remote or Hand to
Auto then that piece of equipment first should be stopped. Changing modes on the fly may
result in a highly undesirable scenario of operation and should be avoided.
Equipment with PLC control and monitoring will be equipped with an L-O-R mode selector
switch and those with PLC monitoring only have an H-O-A mode selector switch where
applicable.
For PLC controlled equipment, place the LOR in the Local (L) mode and the control will be
via the LCP start/stop pushbuttons, Off (O) the equipment will be stopped and in Remote (R)
mode the control will be via the associated PLC/HMI.
For equipment without PLC control, place the H-O-A in the Hand (H) mode and the control
will be via the LCP start/stop pushbuttons, Off (O) the equipment will be stopped and in Auto
(A) mode the control will be via the field interlocks, i.e. level switches, pressure switches, etc.
6.3 General Guidelines for Control Logic
NOTE: Common functions that are generally applicable to all controls or to many similar
controls are described below as "General Control Functions." These functions are not repeated
in the descriptions for each individual control strategy. The following general control
functions shall be provided as outline below.
The I/O listing document shall be referenced and used in conjunction with the control
descriptions.
The project instrument list shall be referenced and used in conjunction with the control
descriptions.
77
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Local manual mode shall be defined as controls local to the specific equipment for
maintenance purposes that will directly operate the equipment.
Remote shall be defined as controls remote from the specific equipment for
operational purposes that will directly operate the equipment.
Remote Automatic shall be defined as controls remote from the specific equipment for
operational purposes that will automatically operate equipment after operator prompting, i.e.
setpoint entry, mode selection, initiation, etc.
A.
All motors shall be monitored for their associated run, stopped and fault status. When
the SCADA initiates a run command, the PLC logic shall monitor the running status
feedback from the motor starter and produce a FAULT alarm if the field feedback
doesnt correspond with the status of the command issued from the PLC. A nominal
delay of 15 seconds shall be built into each logic statement allowing the field device
time to comply with the PLC command.
B.
All automatic control valves with limit switch position feedback shall be monitored for
their associated open, closed and fault status. When the SCADA initiates an
open/close command, the PLC logic shall monitor the position feedback from the
control valves and produce a failure alarm if the field feedback doesnt correspond
with the status of the command issued from the PLC. A nominal delay of 60 seconds
shall be built into each logic statement allowing the field device time to comply with
the PLC command.
C.
All analog control loops shall have a standard PID controller incorporated into the
graphic screen. The PID controllers shall include as a minimum, bar graphs for
setpoint, process variable and percent output, poke points for auto/manual mode
selection and a field to enter the setpoint value and percent output value. The PID
controller operator interfaces graphic shall include but not limited to, the following
functions:
LOCAL/REMOTE set point selection. In LOCAL, the set point shall be operator
adjustable. In REMOTE, the set point shall be adjustable from a REMOTE set
point input.
78
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
A. All PID control algorithms shall monitor the discrepancy between the process
setpoint and the actual process variable. A deviation of +/- 10% between setpoint
and process variable shall generate a deviation alarm alerting the operator to the
problem.
B. All analog inputs shall have an instrument Out Of Range alarm when the input is
below 3.8 mADC or above 20.5 mADC (tunable) for an adjustable amount of time,
initially set at 20 seconds.
C. All discrete FAULT inputs shall be alarmed. Other discrete inputs shall be alarmed
as noted in the control strategy descriptions.
D. Where alarms are specified in the control strategy descriptions, alarms shall be
initiated from the applicable inputs. If discrete inputs are not available for a fault
condition, the specified alarms shall be derived from the logic, by internal coils and
contacts.
E. Pressure and flow alarms (PALL, PAL, PAH, PAHH, FAL) that are digital inputs
to the SCADA System shall be programmed as follows. Upon activation of a
pressure switch, the PLC shall confirm the input by use of an internal on-delay
timer with a 15-second pre-set value. When the timers accumulated value equals
the pre-set value (i.e. timed out), then the local logic shall generate the associated
alarm. Typically, pressure and/or flow alarms do not shut the equipment down
unless otherwise noted in the specific control description. When the alarm is
activated, the operator will need to make a decision to remove the alarming
equipment with a back-up unit.
F. All analog inputs shall be trended and recorded on the plant historian.
G. All flow inputs shall be totalized (integrated) and recorded on the plant historian.
All totalized values shall be displayed in the appropriate engineering units.
H. Controls shall be grouped together functionally for ease of operation. Both analog
and discrete functions associated with a piece of equipment or a grouping of
equipment shall be provided on the same graphic display where possible.
I.
Unless otherwise stated, all discrete outputs shall be maintained outputs. For
START/STOP control functions, the control shall issue a RUN command for the
duration of the run time required, then remove the signal when the STOP
command is issued. Reference the Electrical Schematic Diagrams for the specific
requirements.
J.
For equipment that is controlled from the SCADA, a control mode permissive
signal will be inputted to the PLC to indicate that the PLC is allowed to control
the equipment. The SCADA shall monitor the LCP mounted LOR mode selector
switch (LOCAL/OFF/REMOTE) and attempt to control only equipment that is in
the REMOTE mode.
K. For equipment that the SCADA is permitted to control, a FAIL or FAULT alarm
will be initiated if the equipment fails to comply with a PLC command signal
(START, STOP, OPEN, CLOSE) that has been present for more than a tunable
time period. In this event, the output command shall be removed subsequent to the
expiration of the tunable time period.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
79
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
80
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
T. All I/O points shown in the PLC portion of the PIDs shall be incorporated into
the graphic screens as indicated by their function. Appendix A of this document
contains the project I/O listing and shall be referenced and used in conjunction
with the control descriptions.
6.4 SCADA Failure Modes
6.4.1 Workstations:
(a)
(b)
(c)
Should all workstations fail, the PLCs shall continue control functions independent of
the workstation status.
6.4.2 PLC
PLC (or processor) failures shall be indicated on SCADA and locally at the PLC.
(b)
Independent watchdog routines shall include, but not be limited to the following:
(i)
(ii)
PLC failure
(iii)
In the event of a PLC subsection failure, the associated PLC outputs shall be disconnected to
ensure that they all fail to a de-energised state.
Hard-wired local control will be required for a any equipment affected by the loss of its
associated PLC as described in following sections of this control philosophy.
6.4.3 Process I/O Modules:
The PLC shall have internal diagnostics that detect and report I/O module failures.
6.4.4 SCADA System Monitoring
A graphic screen will be required for monitoring the SCADA Network, PLC cabinets and I/O
Modules. Any system faults shall be indicated on this graphic screen.
6.4.5 Equipment Re-start
Equipment furnished with a Local-Off-Remote selector switch will have to be re-started after
a utility power outage. This equipment shall be programmed not to automatically re-start after
a loss of power. Equipment furnished with a Hand-Off-Auto selector switch will re-start after
a power outage based on the status of the associated field interlocks, i.e. a level switch is
calling for a pump to rune.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
81
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Control Descriptions are typically written around a single piece of equipment, i.e. if there are
four Raw Water Pumps the description addresses how Pump No.1 operates and is typical for
Pumps No.2, 3, and 4 unless otherwise noted. In some cases the equipment operates
collectively such as a Lead/Lag configuration in which case the control descriptions will
address this provision.
Fixed and Portable Sump Pump operation is not described in this document. These units are a
vendor-supplied package with an integral float control assembly and local control for
operation of the pump. There are no monitoring requirements for these units and their
function is mainly an operational maintenance procedure.
6.5.1 Raw Water Pump Station
The raw water intake structure is a pier structure with a reinforced concrete deck, steel
support columns and a frame designed to support the steel intake screen assemblies. The pier
is fitted with area lighting and a warning beacon. The screens, which are installed below the
minimum expected river level, are protected from contact by watercraft and large debris by
submerged piles on their upstream sides.
The Raw Water Pumping Station (RWPS) is located on the riverbank. It consists of an aboveground pump room, a below-ground wet well, and electrical room. The pump room is located
above the wet well. The pier structure supporting the intake screens extends out from the bank
into the river. The inlet pipes from the screens terminate in the wet well.
Major equipment housed in the building are the raw water pumps, the screen cleaning air
compressors and air receiver, the substation transformers and the electrical switchgear, the
motor control center (MCC), power panels and local control panels. A standby diesel
generator and fuel storage tank are provided.
The RWPS at Wasit is constructed with four 33%, two-speed pumps to provided raw water to
the Wasit Water Treatment Plant (WTP). The RWPS discharge header is also provided with a
modulating control valve to provide sufficient back pressure to the pumps as outlined below.
Reference Raw Water Process and Instrumentation Diagrams 13/203/7501 and 7502.
The RWPS has the following equipment:
RW.P-20.1010
Raw Water Pump (No1)
RW.P-20.1020
Raw Water Pump (No2)
RW.P-20.1030
Raw Water Pump (No3)
RW.P-20.1040
Raw Water Pump (No4)
RW.MOV-20.1000
RW Motor Operated Pressure Control Valve
The raw water pumping station operation can be remotely monitored and controlled via PLCRWPS and the operator station graphic display located at the Process Control Center (PCC) in
the Chemical Building. The raw water pumping station has full local, manual control.
Local control of the Raw Water Pumping Station is from Panel RW.P-20.1000 LCP located at
the process equipment.
Each raw water pump has a LCP mounted Local-Off-Remote selector switch (20.HS-1010), a
Lead-Lag-Backup selector switch (20.HS-1011), a Fast/Slow selector switch (20.HS-1012), a
Start Pushbutton (20.HMS-1010), a Stop Pushbutton (20.HMS-1011), a Fault status indicator
(20.YA-1010) and a Run status indicator (20.YL-1010), a High Pressure discharge alarm
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
82
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
status indicator (20.PAH-1010), a Low Pressure discharge alarm status indicator (20.PAL1010) and Alarm Reset Pushbutton (20-HMS-1012) for local control and monitoring. Each
raw water pump has local control capabilities from the LCP mounted operator devices as
outlined below:
Local mode (L), pump can be started/stopped via the start/stop pushbuttons located on the
LCP.
Off mode (O), pump cannot be started locally at the LCP or from the operator station.
Remote mode (R), pump can be started/stopped via the graphical start/stop poke points and
placed in Hand-Off-Auto mode via the graphical H-O-A poke point located on the operator
station graphic display. Additionally, the pump can be controlled by the PLC in the Auto
mode for start/stop, fast/slow and lead/lag/backup operations as outlined below.
LOR switch mode position (20.HS-1030) is displayed on the operator station graphic display.
Lead-Lag-Backup selector switch (20.HS-1011):
Each Raw Water Pump is fitted with a Lead-Lag-Backup selector switch. The position of this
switch is a digital input to the PLC for the control of pumps that are to be placed on line. A
pump placed in the Lead mode will be placed in service first. Should the demand of the water
treatment plant exceed the rating of the lead pump, the PLC will place the Lag pump in
service. Should either the Lead or the Lag pump fail the PLC will replace the failed unit with
the Backup pump.
The Lead-Lag-Backup selector switch function is only effective while in the Remote mode of
operation. The operator must select the appropriate mode for each pump (Lead, Lag or
Backup) with the forth pump placed in the Off position via the LOR Selector Switch.
Fast/Slow selector switch (20.HS-1012):
Fast mode (F), pump can be manually started in the Local mode using the high-speed motor
windings via the start/stop pushbuttons located on the LCP.
Slow mode (S), pump can be manually started in the Local mode using the slow-speed motor
windings via the start/stop pushbuttons located on the LCP.
The operator selectable Fast/Slow selector switch shall be utilized based on river level
conditions as outlined below. In the Remote mode the PLC shall establish the proper speed
for each pump based on river level and externally from this selector switch position.
Start/Stop Pushbuttons (20.HMS-1030 / 1031):
The Local LCP Start pushbutton initiates the hard-wired run command via the pump motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the pump
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
83
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the
Pump motor starter run circuit. The PLC discrete output signal (20.HS-1010 fast or 20.HS1011 slow) is energized while the pump is called to run and de-energized when called to stop.
Reference the Electrical elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
In addition to the pump controls (typical for four units) the Raw Water Pump Station is
equipped with a modulating control valve RW.MOV-20.1000. This control valve is used to
help keep the pumps functioning on their operating curve as required.
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Run status indication (YL) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
Pressure alarm (PAH/PAL) indicated at the operator station graphic display shall be
programmed in the PLC logic as described in section II. GENERAL GUIDELINES FOR
CONTROL LOGIC. Local panel Pressure alarm indication is generated from the hard-wire
logic in the motor starter circuit must be reset with the Alarm Reset Pushbutton (20.HMS1012) to unlatch the hardwire logic. Reference the Electrical elementary schematics for
requirements of the Fault conditions.
6.5.1.1 RWPS Operation:
The RWPS speed shall be controlled based on the Treated Water Storage Tank (TWST) level
(60-LIT-1011). One pump (operator selectable) will be in operation at all times, unless the
facility is down for maintenance. The operator shall enter a TWST level setpoint from the
graphic display located at the Process Control Center for which the RWPS operation will be
based on. When the level falls below this setpoint for a specific period of time a second pump
(Lag) shall be called to start. When the level in the TWST rises above the operator adjustable
setpoint, the pumps will be taken off line by the same technique as they were placed on line.
The RWPS has two speed pumps (fast and slow) that discharge through a modulating control
valve (20-RW.MOV-20.1000). This control valve is provided to keep the pump operating on
its Q/H curve at high and low river levels (20-LIT-1001). Pump operation at both speeds will
be as follows:
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
84
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
At low river level as detected by the level transmitter in the wet well, pump will operate at
high speed
At high river level as detected by the level transmitter in the wet well, pump will operate at
low speed
The modulating control valve (20-RW.MOV-20.1000) shall operate to maintain two
minimum pump total dynamic heads (TDHs) one for low speed and one for high speed. The
PLC shall be programmed to achieve these functions during RWPS automatic operation. In
manual mode the Operator shall select the speed based on river level (20-LIT-1001) and shall
start and stop the pumps manually. The operator shall also have the ability to manually adjust
the control valve position as required for proper pump operation as stated above.
The control valve (20-RW.MOV-20.1000) on the discharge header of the RWPS shall
modulate to control the flow into the WTP to maintain the level range in the TWST at the
WTP. The flow is measured by the flow meter (26-RW.FIT-1010) at the WTP and transmitted
to the RWPS. As the river level (20-LIT-1001) drops below the level range and the control
valve is open to the extent possible maintaining a minimum pump TDH depending on the
pump speed, the Lag pump is called to start. Simultaneously the control valve closes to the
extent possible and the 2nd pump starts. The control valve then begins to regulate the flow
into the WTP to maintain TWST level range. The pump TDH control will override the flow
required to maintain the pump(s) within its operating range. On rising level the reverse
operation is applied.
6.5.1.2 Station Power Loss
The pump station power will automatically switch from line (Utility) power to generator
(backup) power upon the loss of the line (Utility) power. After power failure and return, the
Raw Water Pumps shall be re-started with staggered time delays to avoid unacceptable load
changes on the supply power and/or generator.
Mechanical break before make interlocking of incoming circuit breakers is provided to avoid
parallel operation of line (Utility) power mains and generator backup power.
6.5.2
The RWPS wetwell is fed river water through four identical intake screens that are cylindrical
wire screen devices and are cleaned by an air-burst system (Air Scour) utilizing compressed
air. The screen cylinders may be lifted from their normal position to a maintenance position
via vertical guide rails on the pier. A manually operated jib crane with a motorized hoist is
used to lift the screens. The jib crane can rotate in order to transfer a screen onto or off of a
small truck, which can access the end of the pier.
The four intake screens feed two wetwell compartments, screens No.1 and No.2 for wetwell
compartment No.1 and screens No.3 and No.4 for wetwell compartment No.2. A vendorsupplied package provides the compressed air and controls required to air scour the intake
screens. A Vendor Control Panel (VCP) is furnished to provide local control of this system
and remote monitoring is available at Process Control Center (PCC) in the Chemical
Building.
The Air Scour System has the following equipment:
RW.SOL-20.1001
Air Scour to Intake Screen (No1)
RW.SOL-20.1002
Air Scour to Intake Screen (No2)
RW.SOL-20.1003
Air Scour to Intake Screen (No3)
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
85
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
RW.SOL-20.1004
RW.CMP-20.1000
The air scour system shall be controlled from a local control panel RW.CMP- 20.1000 VCP,
located in the pump room of the Raw Water Pump Station. The compressor control panel
shall be supplied with the compressor package.
The local control panel shall provide manual and automatic control features. A cleaning cycle
shall be defined as the period from when the air burst is initiated at the first screen to when the
air burst is completed at the fourth screen.
The air scour system has no automatic PLC control capabilities. The systems operation can
be remotely monitored via PLC-RGF and the operator station graphic display located at the
Process Control Center (PCC) in the Chemical Building.
For local automatic/manual control, reference the manufacturer documentation for specific
operational procedures. For remote alarm and status monitoring requirements, reference the
PID drawings and the project I/O listing.
6.5.3 Sampler Control
The water treatment facility is serviced by a number of sample pumps to furnish process water
to a variety of process analyzers and connections to the facilitys laboratory. The control of
these samplers is identical and the control description is for a typical unit. Reference the
PIDs for the detailed requirements of the samplers.
Reference Process and Instrumentation Diagrams 13/206/7501, 13/207/7501 and 7502,
13/212/7505, 13/229/7501, and 13/243/7502.
The WTP sample pumps are as follows:
RW.SP-26.1000
RW.SP-26.1001
SW.SP-30.1410
SW.SP-30.1420
FTR.SP-40.1002
CCT.SP-50.1020
TW.SP-60.1001
Local control of the Post Chlorination Sample Pump No.1 is from RW.SP-26.1000 LCP
located in the field near the sampler unit.
The sampler has a LCP mounted Run/Off selector switch (26.HS-1000), a Fault status
indicator (26.YA-1000), a Low Flow Alarm (26.FAL-1000), a Rest pushbutton (26.HMS1000) and a Run status indicator (26.YL-1000) for local control and monitoring. The sampler
has local control capabilities from the LCP mounted operator devices as outlined below:
Run/Off Selector Switch (26.HS-1000):
86
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The Run/Off selector switch initiates the hard-wired run command via the sampler motor
starter run circuit. There is no PLC control of the samplers. Reference the Electrical
elementary schematics for requirements of the hardwired control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
The Low Flow alarm is generated from the filed mounted flow switch (26.FSL-1000). When
the flow switch detects the lack of flow through the sample pump and the timer (TR1) will
begin timing down. Should the low flow condition remain present throughout the TR1 preset
time then the timers output contact will change states and generate the Low Flow Alarm.
Reference the Electrical elementary schematics for requirements of the Low Flow Alarm
conditions.
6.5.4 Inline Chemical Disperser
The 500-mm raw water line is fitted with a single motorized Inline Chemical Disperser (ICD)
to blend the alum chemical feed with the Raw Water Supply. The Inline Chemical Disperser
operation can be remotely monitored and controlled via PLC-RGF and the operator station
graphic display located at the Process Control Center (PCC) in the Chemical Building.
Typically, the ICD will run continuously unless alum is not being fed or the Plant is down for
maintenance. Inline Chemical Disperser unit has full local control.
Reference Inline Chemical Disperser Process and Instrumentation Diagram 13/206/7501.
RW.FE-26.1010
Mag Meter
RW.MX-26.1010
Inline Chemical Disperser
Local control of the Inline Chemical Disperser is from RW.ICD-26.1010 located at the
process equipment.
The ICD has a LCP mounted Local-Off-Remote selector switch (26.HS-1010), a Start
Pushbutton (26.HMS-1010), a Stop Pushbutton (26.HMS-1011), a Fault status indicator
(26.YA-1010) and a Run status indicator (26.YL-1011) for local control and monitoring. The
ICD has local control capabilities from the LCP mounted operator devices as outlined below:
LOR Selector Switch (30.HS-1010):
Local mode (L), ICD can be started/stopped via the start/stop pushbuttons located on the LCP.
Off mode (O), ICD cannot be started locally at the LCP or from the operator station.
Remote mode (R), ICD can be started/stopped via the graphical start/stop poke points located
on the operator station graphic display.
LOR switch mode position (26.YL-1010) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (30.HMS-1010 / 1011):
The Local LCP Start pushbutton initiates the hard-wired run command via the ICD motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the ICD
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
87
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the ICD
motor starter run circuit. The PLC discrete output signal (26.HMS-1010) is energized while
the mixer is called to run and de-energized when called to stop. Reference the Electrical
elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Sludge Collection
The Flocculation basins have limited automatic PLC control capabilities. The sedimentation
basins, the sludge collection operation and the sampling operation can be remotely monitored
and controlled via PLC-RGF and the operator station graphic display located at the Process
Control Center (PCC) in the Chemical Building. Both the sludge collection equipment and
the water sampling pumps have full local control.
Local control of the sludge collectors is from SW.COL-30.1001 LCP (train 1) and SW.COL30.1002 LCP (train 2) located at the process equipment.
The water sampling pumps are controlled locally at SW.SP-30.1410 LCP (train 1) and
SW.SP-30.1420 LCP (train 2) also located in the field at the process equipment. Reference the
Sampler Controls Description Section for specific requirements.
The Splitter Chamber high and high-high level alarms are indicated on the SW.COL-30.1001
LCP. The level switches are an input to PLC-RGF and displayed and alarmed at the operator
station graphic display. Should a splitter chamber high or high-high level condition occur, the
operator will need to take the appropriate action to reduce the level in the chamber.
6.5.5 Flocculation
Each of the six Flocculation tank (SW.TK-30.1001 and 1002) compartments are fitted with a
single mixer. The mixer has an LCP mounted Local-Off-Remote selector switch (30.HS1010), a Start Pushbutton (30.HMS-1010), a Stop Pushbutton (30.HMS-1011), a Fault status
indicator (30.YA-1010) and a Run status indicator (30.YL-1011) for local control and
monitoring.
Reference Clarifiers Process and Instrumentation Diagrams 13/207/7501 and 7502.
The Flocculation Mixers are as follows:
SW.MX-30.1010
SW.MX-30.1020
SW.MX-30.1030
SW.MX-30.1040
SW.MX-30.1050
SW.MX-30.1060
Flocculator (No. 1)
Flocculator (No. 2)
Flocculator (No. 3)
Flocculator (No. 4)
Flocculator (No. 5)
Flocculator (No. 6)
88
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Each mixer has local control capabilities from the LCP mounted operator devices as outlined
below. There is no PLC automatic control required for the mixers.
LOR Selector Switch (30.HS-1010):
Local mode (L), mixer can be started/stopped via the start/stop pushbuttons located on the
LCP.
Off mode (O), mixers cannot be started locally at the LCP or from the operator station.
Remote mode (R), mixer can be started/stopped via the graphical start/stop poke points
located on the operator station graphic display.
LOR switch mode position (30.YL-1010) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (30.HMS-1010 / 1011):
The Local LCP Start pushbutton initiates the hard-wired run command via the mixer motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the mixer
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the
mixer motor starter run circuit. The PLC discrete output signal (30.HMS-1010) is energized
while the mixer is called to run and de-energized when called to stop. Reference the Electrical
elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC. .
Local panel Run status indication (YL) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
6.5.6
Sludge Collection
The sludge scrapers have limited automatic PLC control capabilities. The scrapers and the
sludge collection operation can be remotely monitored and controlled via PLC-RGF and the
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
89
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
operator station graphic display located at the Process Control Center (PCC) in the Chemical
Building. The sludge collection equipment has full local control.
Reference Clarifiers Process and Instrumentation Diagrams 13/207/7501 and 7502.
The Sludge Scrapers are listed below:
SW.COL-30.1510
SW.COL-30.1520
Scraper (No. 1)
Scraper (No. 2)
Local control of the sludge scrapers is from SW.COL-30.1001 LCP (train 1) and SW.COL30.1002 LCP (train 2) located at the process equipment.
Each Clarifier (SW.CLAR-30.1001 and 1002) is fitted with a sludge scraper. The scraper has
an LCP mounted Local-Off-Remote selector switch (30.HS-1510), a Start Pushbutton
(30.HMS-1510), a Stop Pushbutton (30.HMS-1511), a Fault status indicator (30.YA-1510), a
Run status indicator (30.YL-1511), a Scraper High Torque status alarm (30.NA-1510), and an
Alarm Reset Pushbutton (30.HMS-1512) for local control and monitoring. Each sludge
scraper has local control capabilities from the LCP mounted operator devices as outlined
below:
LOR Selector Switch (30.HS-1510):
Local mode (L), scraper can be started/stopped via the start/stop pushbuttons located on the
LCP.
Off mode (O), scraper cannot be started locally at the LCP or from the operator station.
Remote mode (R), scraper can be started/stopped via the graphical start/stop poke points
located on the operator station graphic display.
LOR switch mode position (30.YL-1510) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (30.HMS-1510 / 1511):
The Local LCP Start pushbutton initiates the hard-wired run command via the scraper motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the scraper
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the
scraper motor starter run circuit. The PLC discrete output signal (30.HMS-1510) is energized
while the scraper is called to run and de-energized when called to stop. Reference the
Electrical elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
90
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
High Torque alarm (NA) indicated at the operator station graphic display shall be
programmed in the PLC logic as described in section II. GENERAL GUIDELINES FOR
CONTROL LOGIC. Local panel Torque alarm indication and shutdown are generated from
the hard-wire logic in the motor starter circuit and will shut down the scraper drive if the High
Torque signal is present long enough for timer TR1 to trip. Should the high torque condition
occur, the operator will need to take action and remove this tank from service. Reference the
Electrical elementary schematics for requirements of the Fault conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC. .
Local panel Run status indication (YL) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
6.5.7 Sludge Removal
Each Clarifier is fitted with a Desludging Valve Chamber to house a motorized control valve
(SL.MOV-30.1310). As the sludge is collected at the bottom of the Clarifier it is removed by
opening the desludging valve based on a cycle timer located on the LCP. The removal
operation can be remotely monitored at the operator station graphic display located at the
Process Control Center (PCC) in the Chemical Building. The desludging equipment has full
local control and there is no PLC control available for this function.
Reference Clarifiers Process and Instrumentation Diagrams 13/207/7501 and 7502.
The Desludging Valves are as follows:
SL.MOV-30.1310
SL.MOV-30.1320
Local control of the Desludging Valve is from SW.COL-30.1001 LCP (train 1) and SW.COL30.1002 LCP (train 2) located at the process equipment.
The Desludging Valve has an LCP mounted Hand-Off-Auto selector switch (30.HS-1310), an
Open/Stop/Close spring return to center selector switch (30.HMS-1310), an Open and Closed
status indicator (30.ZLO-1310 and 30.ZLC-1310), and a Cycle Timer (30.KY-1510) for local
control and monitoring. Each valve has local control capabilities from the LCP mounted
operator devices as outlined below:
HOA Selector Switch (30.HS-1310):
Hand mode (H), Valve can be manually opened/closed via the Open/Stop/Close selector
switch located on the LCP.
Off mode (O), Valve cannot be opened/closed locally at the LCP.
Auto mode (A), Valve will be opened/closed via the cycle timer (30.KY-1510) settings. The
operator will adjust the cycle timers settings as follows:
On Time: the desired time period the valve is required to be open (sludge removal).
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
91
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Off Time: the desired time period the valve is required to be closed between removal
operations (sludge removal stopped).
The Desludging Valve open/close position is displayed on the operator station graphic
display.
The Desludging Valve open/close position indication and fault alarms at the operator station
graphic display shall be programmed in the PLC logic as described in section II. GENERAL
GUIDELINES FOR CONTROL LOGIC.
6.5.8
Filter Control
The below control description is for Filter No.1 and is the identical for all filters at the water
treatment facility.
Reference Filter Backwash Process and Instrumentation Diagrams 13/212/7501 - 7506.
The filter is operated via numerous motorized vales, solenoid valves and weirs as listed
below:
FTR.MOV-40.1110
Actuated Slide Gate (Filter Inlet)
FTR.MOV-40.1120
Actuated Slide Gate (Backwash Discharge)
FTR.MOV-40.1130
Actuator Valve (Vent)
FTR.MOV-40.1140
Actuator Valve (Wastewater)
FTR.MOV-40.1150
Actuator Valve (Air Scour)
FTR.MOV-40.1160
Actuator Valve (Effluent)
FTR.MOW-40.1170
Actuated Slide Gate (Backwash Inlet)
FTR.MOV-40.1180
Actuator Valve (Backwash Water)
Local control of the Filter is from FTR.CC-40.1100 control console (CC) located at the filter.
The Filter has a CC mounted In/Out of Service selector switch (40.HS-1113) for placing the
filter in and out of service. Additionally, each motorized valve has a Hand-Off-Auto selector
switch, an Open/Stop/Close spring return to center selector switch and valve Open and valve
Closed status indication. The Filter has local control capabilities from the CC mounted
operator devices as outlined below:
The incoming clarified water enters the common filter inlet channel where it flows through
the Motor Actuated Slide Gate FTR.MOV-40.1110 and over the weir into the filter. At
commissioning, the weir plates will be set at the same height thereby distributing the clarified
water equally from the common inlet channel to all filters in service.
The weir plate on each filtered water outlet box will also be set at the same height (all weir
plates being manually adjustable via slots). This weir is fixed at approximately 81mm above
the filter media thereby preventing dry bedding of the media.
The flow into and from each filter is consequently the same. As the filter bed becomes
progressively more blocked, the headloss through the media increases resulting in the head
above the media rising (NB under clean bed conditions, the head is estimated to be about
0.68m at maximum flow with one filter out of service for backwash. The head will rise to
about 3.68m before theoretically needing to backwash.
The filter Effluent exists via Motor Actuator Valve FTR.MOV-40.1160 and into the common
filtered water channel and onto the Chlorine Contact Tank (CCT). The Clean Water Holding
Tank is also connected to the common filtered water channel and is discussed under the
Backwash description.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
92
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The Common Filtered Water Channels level is monitored by FTR.LIT-1001. Should the
channel level rise to within 150 mm of the filtered water weir plate an alarm shall be
generated indicating a process problem is taking place. The operator should intervene to
reduce this level either by dropping the Raw Water flow or by increasing the Treated Water
pump rate.
When the operator selects Filter In Service via selector switch (40.HS-1113), the Filter Inlet
gate FTR.MOV-40.1110 and Filter Effluent valve FTR.MOV-40.1160 are instructed to open
allowing water to flow through the filter. The Backwash Discharge gate FTR.MOV-40.1120,
the Wastewater gate FTR.MOV-40.1140, the Air Scour valve FTR.MOV-40.1150 and the
Backwash Inlet valve FTR.MOW-40.1170 are instructed to close.
When the operator selects Filter Out Service via selector switch (40.HS-1113), the Filter Inlet
gate FTR.MOV-40.1110 will close and after a pre-set period of time as set in PLC-RGF the
Filter Effluent valve FTR.MOV-40.1160 will be instructed to open allowing water to flow out
of the filter. The Backwash Discharge gate FTR.MOV-40.1120, the Wastewater gate
FTR.MOV-40.1140, the Air Scour valve FTR.MOV-40.1150 and the Backwash Inlet valve
FTR.MOW-40.1170 are instructed to remain closed. The remaining Filter water that did not
drain will be drawn down by the outlet siphons (typically three required) which are located
about 200 mm above the filter media. Care should be taken not to allow the water level to
drop to less than 81mm above the filter media to prevent a dry bed condition.
After a period of time in operation, the filter will require a backwash and will be initiated on
the following criteria:
High Turbidity (signal from the filtered water discharge Turbidity meter 40.AIT1010)
Excessive Headloss (signal from the loss of head pressure transmitter 40.PIT1010)
Turbidity is monitored at each filter effluent. The Turbidity indications are used as the
primary parameter in monitoring performance and controlling filter operations.
6.5.9 Backwash Sequence
93
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The filter will drain to the top of the Backwash Discharge gate FTR.MOV-40.1120. This can
be determined by time or by the static pressure signal from the loss of head pressure
transmitter 40.PIT-1010. Normally, the Backwash Discharge gate would be opened on a time
basis and the filter siphons would then draw the water above the media into the outlet channel.
The outlet of the siphons (typically three required) would be located about 200 mm above the
media. There is no automatic control on the siphons.
After a pre-set time as set in PLC-RGF, the filter effluent Motor Actuator Valve FTR.MOV40.1160 will close. The Air Scour Blower AS.BLW-40-1710 or AS.BLW-40-1720 will start
up and the Air Scour Motor Actuator Valve FTR.MOV-40.1150 will be opened. The blower
would run for a pre-set period of time as set in PLC-RGF, typically 5 minutes (operator
adjustable). At the end of this period, the Air Scour valve would close, the blower will stop,
and the Air Vent solenoid valve FTR.SOL-40.1130 will be opened.
After a short delay, the Backwash Pump FBW.P-40.1810 or FBW.P-40.1820 will start,
Backwash Motor Actuator Valve FTR.MOV-40.1180 will open with a wash time of
approximately 5 minutes (operator adjustable) as set in PLC-RGF. At the end of this pre-set
period, the Backwash valve will close, and the Backwash Pump will be stopped.
The Filter Inlet gate FTR.MOV-40.1110 will open, and the Wastewater Motor Actuator Valve
FTR.MOV-40.1140 will open to allow the water discharged to the Wastewater Holding Tank
WW.TK-70-1000 for a period of thirty minutes (operator adjustable) as set in PLC-RGF. At
the end of this pre-set time, the Wastewater valve would close, and the Filter Effluent valve
FTR.MOV-40.1160 will open. An alarm will be generated by PLC-RGF if the filtered water
Turbidity exceeded a pre-set value.
6.5.10 Filter Backwash Control
Backwash water for the filter backwashing operation is supplied from the Common Filtered
Water Channel through the Clean Water Holding Tank Inlet Motorized Weir FTR.MOW40.1170. Alternatively, in an emergency, the Service Water System can be manually valved to
draw off the Service Water distribution ring to fill the Clean Water Holding Tank. This
operation must be manually supervised, as normal level controls will be inoperative.
A duty and an assist fixed speed pumps will deliver clean wash water from the Clean Water
Holding Tank to the Filter that is to be back washed. The pumps will be arranged with
individual suction pipe connections from the tank.
An ultrasonic level transmitter and high, low and low-low level switches will be provided in
the tank for control of re-filling, pump protection and indication of tank level. Magnetic
flowmeter measures the discharge flow of clean wash water into the filters. A high/low
pressure switch on the discharge pipe monitors failure of the inlet/outlet valves or possible
issues with the Backwash Pump.
When the Clean Water Holding Tank level reaches a low level condition (40-LSL-1800), the
PLC will open the Clean Water Holding Tank inlet weir (FTR.MOW-40.1170) to a predetermined percent open position to allow filtered water flow to fill the holding tank. When
the tank level reaches a high level condition (40-LSH-1800), the PLC will command the inlet
weir to close and stop the filtered water flow into the holding tank.
Low and high rate flows are required for different stages of the backwash sequence. These are
achieved by running one pump by itself through a throttling pipe for low rate and two pumps
together by-passing the throttling pipe for high rate.
94
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Local control of the Backwash Pump is from FBW.P-40.1810 LCP located at the process
equipment.
The Backwash Pumps have an LCP mounted Local-Off-Remote selector switch (40.HS1810), a Start Pushbutton (40.HMS-1810), a Stop Pushbutton (40.HMS-1811), a Fault status
indicator (40.YA-1810), a Run status indicator (40.YL-1810), a discharge press High Pressure
status alarm (40.PAH-1810), a discharge press Low Pressure status alarm (40.PAL-1810) and
an Alarm Reset Pushbutton (40.HMS-1812) for local control and monitoring.
Reference Filter Backwash Process and Instrumentation Diagrams 13/212/7501 - 7506.
Each Backwash Pump has local control capabilities from the LCP mounted operator devices
as outlined below:
LOR Selector Switch (40.HS-1810):
Local mode (L), Backwash Pump can be started/stopped via the start/stop pushbuttons located
on the LCP.
Off mode (O), Backwash Pump cannot be started locally at the LCP or from the operator
station.
Remote mode (R), Backwash Pump can be started/stopped via the graphical start/stop poke
points located on the operator station graphic display. Pumps that are in the auto mode via the
graphical H-O-A poke points will start/stop automatically as described in the Filter Backwash
Control Descriptions.
LOR switch mode position (40.YL-1810) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (40.HMS-1810/ 1811):
The Local LCP Start pushbutton initiates the hard-wired run command via the Backwash
Pump motor starter run circuit. The Stop pushbutton unlatches the hard-wired run command
via the Backwash Pump motor starter run circuit. Reference the Electrical elementary
schematics for requirements of the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the
Backwash Pump motor starter run circuit. The PLC discrete output signal (40.HMS-1810) is
energized while the Backwash Pump is called to run and de-energized when called to stop.
Reference the Electrical elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
95
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Pressure alarm (PAH/PAL) indicated at the operator station graphic display shall be
programmed in the PLC logic as described in section II. GENERAL GUIDELINES FOR
CONTROL LOGIC. Local panel Pressure alarm indication is generated from the hard-wire
logic in the motor starter circuit must be reset with the Alarm Reset Pushbutton (30.HMS1812) to unlatch the hardwire logic. Reference the Electrical elementary schematics for
requirements of the Fault conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC. .
Local panel Run status indication (YL) is generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
The common filtered water channel is fitted with a continuous level transmitter
(40.LIT.1001), which will generate a high (LAH) and a low (LAL) channel level alarm. The
low level alarm should be closely monitored in the event that the Clean Water Holding Tank
inlet weir (FTR-MOW 40.1170) fails to close when called to. There is a remote possibility
that the filters could drain through the holding tank overflow. Additionally, the valve fault
alarm and the holding tank high level alarm are closely monitored to avoid this situation.
Should weir motor operator fail, the operator should manually operate the unit in the field.
6.5.11
Compressed air for the filter air scour function is supplied from a duty and a standby fixed
speed blower (AS.BLW-40-1710 and AS.BLW-40-1720) to the common discharge header
through a motorized control valve FTR.MOW-40.1450 and into the filter underdrain.
A high/low pressure switch on the discharge pipe monitors failure of the inlet/outlet valves or
possible issues with the blowers.
Reference Filter Backwash Process and Instrumentation Diagrams 13/212/7501 - 7506.
The Air Scour equipment includes the following:
AS.BLW-40.1710
AS.BLW-40.1720
Local control of the Air Scour Blowers is from AS.BLW-40.1700 VCP located at the process
equipment.
The Air Scour Blowers have a VCP mounted Local-Off-Remote selector switch (40.HS1710), a Start Pushbutton (40.HMS-1710), a Stop Pushbutton (40.HMS-1711), a Fault status
indicator (40.YA-1710), a Run status indicator (40.YL-1710), a discharge press High Pressure
status alarm (40.PAH-1710), a discharge press Low Pressure status alarm (40.PAL-1710) and
an Alarm Reset Pushbutton (40.HMS-1712) for local control and monitoring. Each Air Scour
Blower has local control capabilities from the VCP mounted operator devices as outlined
below:
The Air Scour Discharge line is fitted with a condensation drain valve to discharge any
accumulated water in the system. The solenoid cycle timer (40.KY-1700) mounted on the
Vendor Control Panel. The operator will set the valve open time and the valve closed time
pre-sets. The valve shall sequence per the timer pre-set times.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
96
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Local mode (L), Air Scour Blower can be started/stopped via the start/stop pushbuttons
located on the LCP.
Off mode (O), Air Scour Blower cannot be started locally at the LCP or from the operator
station.
Remote mode (R), Air Scour Blower can be started/stopped via the graphical start/stop poke
points located on the operator station graphic display. Blowers that are in the auto mode via
the graphical H-O-A pore points will start/stop automatically as described in the Filter
Backwash Control Descriptions.
LOR switch mode position (40.YL-1710) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (40.HMS-1710/ 1711):
The Local VCP Start pushbutton initiates the hard-wired run command via the Air Scour
Blower motor starter run circuit. The Stop pushbutton unlatches the hard-wired run command
via the Air Scour Blower motor starter run circuit. Reference the Electrical elementary
schematics for requirements of the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the VCP
when the Hand-Off-Auto graphical pore point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the Air
Scour Blower motor starter run circuit. The PLC discrete output signal (40.HMS-1710) is
energized while the Air Scour Blower is called to run and de-energized when called to stop.
Reference the Electrical elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
High/Low Pressure alarm (PAH/PAL) indicated at the operator station graphic display shall
be programmed in the PLC logic as described in section II. GENERAL GUIDELINES FOR
CONTROL LOGIC. Local panel Pressure alarm indication is generated from the hard-wire
logic in the motor starter circuit must be reset with the Alarm Reset Pushbutton (40.HMS1712) to unlatch the hardwire logic. Reference the Electrical elementary schematics for
requirements of the Fault conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
97
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Local panel Run status indication (YL) is generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
6.5.12 Wastewater Pumping System
Wastewater flows from the Flocculator/Clarifiers and filters to the wastewater holding tank
(WWHT) via yard piping. Minor process drains also flow from other buildings to the WWHT.
Tank contents are prevented from settling by the use of separate Wastewater Mixing Pumps.
The WWHT is a single-chamber, reinforced concrete tank located partially below grade. The
structure is partially covered and constructed entirely of reinforced concrete.
The wastewater pumping station (WWPS) consists of a dry-well pump room located adjacent
to the WWHT. Wastewater pumps transfer wastewater from the WWHT to the river outfall
via the wastewater pipeline.
Reference Wastewater Process and Instrumentation Diagram 13/220/7501.
The WWPS equipment includes the following:
WW.P-70.1010
Wastewater Pump (No. 1)
WW.P-70.1020
Wastewater Pump (No. 2)
WW.P-70.1030
Wastewater Pump (No. 3)
WW.P-70.1040
Wastewater Mixer Pump (No. 1)
WW.P-70.1050
Wastewater Mixer Pump (No. 2)
WW.P-70.1060
Fixed Sump Pump
Local control of the WWPS is from WW.P-70.1000 LCP located at the process equipment.
The Wastewater Pumps have an LCP mounted Mode selector switch (70.HS-1000), for
Lead/Lag selections. Hand-Off-Automatic selector switch (70.HS-1010), a Start Pushbutton
(70.HMS-1010), a Stop Pushbutton (70.HMS-1011), a Fault status indicator (70.YA-1010), a
Run status indicator (70.YL-1110), a discharge press High Pressure status alarm (70.PAH1010), a discharge press Low Pressure status alarm (70.PAL-1010) and an Alarm Reset
Pushbutton (70.HMS-1012) for local control and monitoring. Each Wastewater Pump has
local control capabilities from the LCP mounted operator devices as outlined below:
Mode Selector Switch (70.HS-1000):
When position 1-2 is selected, Pump No.1 will be Lead with Pump No.2 as Lag. When
position 2-3 is selected, Pump No.2 will be Lead with Pump No.3 as Lag. When position 3-1
is selected, Pump No.3 will be Lead with Pump No.1 as Lag. This is an operator selectable
function. To change the lead/Lag selection all pumps must be stop prior to making any
changes.
HOA Selector Switch (70.HS-1010):
Hand mode (H), pump can be started/stopped via the start/stop pushbuttons located on the
LCP.
Off mode (O), pump cannot be started locally at the LCP or from the operator station.
Auto mode (A), pump will be started/stopped via the multi-point level switch (tipping ball)
mounted in the Wastewater tank. The level switches are configured as Pump(s) stop (70.LSL1000), Lead Pump Start (70.LSM-1000) and Lag Pump start (70.LSH-1000)
HOA switch mode position (70.HS-1010) is displayed on the operator station graphic display.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
98
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The Local LCP Start pushbutton initiates the hard-wired run command via the Wastewater
Pump motor starter run circuit. The Stop pushbutton unlatches the hard-wired run command
via the Wastewater Pump motor starter run circuit. Reference the Electrical elementary
schematics for requirements of the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the HOA selector switch is in the
Local mode (H).
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Pressure alarm (PAH/PAL) indicated at the operator station graphic display shall be
programmed in the PLC logic as described in section II. GENERAL GUIDELINES FOR
CONTROL LOGIC. Local panel Pressure alarm indication is generated from the hard-wire
logic in the motor starter circuit must be reset with the Alarm Reset Pushbutton (70.HMS1012) to unlatch the hardwire logic. Reference the Electrical elementary schematics for
requirements of the Fault conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Run status indication (YL) is generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
Local control of the Wastewater Mixer Pumps are from WW.P-70.1000 LCP located at the
process equipment.
The Wastewater Mixer have an LCP mounted Local-Off-Remote selector switch (70.HS1040), a Start Pushbutton (70.HMS-1040), a Stop Pushbutton (70.HMS-1041), a Fault status
indicator (70.YA-1040), a Run status indicator (70.YL-1040), a discharge press High Pressure
status alarm (70.PAH-1040), a discharge press Low Pressure status alarm (70.PAL-1040) and
an Alarm Reset Pushbutton (70.HMS-1012) for local control and monitoring. Each
Wastewater Mixer has local control capabilities from the LCP mounted operator devices as
outlined below:
LOR Selector Switch (70.HS-1040):
Local mode (L), Mixer can be started/stopped via the start/stop pushbuttons located on the
LCP.
Off mode (O), Mixer cannot be started locally at the LCP or from the operator station.
Remote mode (R), Mixer can be started/stopped via the graphical start/stop poke points and
placed in Hand-Off-Auto mode via the graphical H-O-A poke point located on the operator
station graphic display. Additionally, the pump can be controlled by the PLC in the Auto
mode as outlined below. In the Remote mode of operation, the mixer pumps will be shut
down when a low alarm (70.LSLL-1000) condition occurs.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
99
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
LOR switch mode position (70.HS-1040) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (70.HMS-1040, / 70.HMS-1041):
The Local LCP Start pushbutton initiates the hard-wired run command via the Mixer motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the Mixer
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the
Mixer motor starter run circuit. The PLC discrete output signal (70.HS-1040) is energized
while the Mixer is called to run and de-energized when called to stop. Reference the Electrical
elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Run status indication (YL) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
Pressure alarm (PAH/PAL) indicated at the operator station graphic display shall be
programmed in the PLC logic as described in section II. GENERAL GUIDELINES FOR
CONTROL LOGIC. Local panel Pressure alarm indication is generated from the hard-wire
logic in the motor starter circuit must be reset with the Alarm Reset Pushbutton (70.HMS1012) to unlatch the hardwire logic. Reference the Electrical elementary schematics for
requirements of the Fault conditions.
6.5.13 Chlorine Systems:
6.5.13.1 Overview:
The Chlorine Feed system is comprised of two separate systems. The system includes two
chlorine chlorinators for the TWST Disinfection and one chlorinator for the pre treated Raw
Water feed.
Reference Chlorine System Process and Instrumentation Diagrams 13/217/7501 - 7503.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
100
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The flow of chlorine gas through the chlorinators can be flow-paced based on the raw water
flow (26.FIT.1010) for the pretreatment chlorinators and can be trimmed using the free
chlorine residual analyzer (26.AIT-1013) at the discharge header of the RWPS. Additionally,
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
101
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
a manual timer (81-KY-1010) is provided so that the chlorine feed to the Raw water line can
not be accidentally left on for long periods of time. The operate must set the period of time
that he wishes to chlorinate and upon the timer accumulated valve reaching the preset value
the timer will de-energize and shut off the chlorine feed.
The finished water flow (60.FIT.1000) for the post-treatment chlorinators flow pacing and can
also be trimmed using the free chlorine residual analyzer (60.AIT-1001) at the discharge
header of the distribution pumps. The chlorine gas is transported to the point of application by
ejectors and the motive water pumping system.
Each of the chlorinators is supplied with a feed rate controller mounted locally at the process
equipment. The controller allows the operator to control the feed rate locally in either a
manual, automatic or flow paced mode.
Each feed rate controller has a Local-Off-Remote selector switch (81.HS-1200), a Start
Pushbutton (81.HMS-1200), a Stop Pushbutton (81.HMS-1201), a Fault status indicator
(81.YA-1200) and a Run status indicator (81.YL-1200), a manual speed control potentiometer
(81.SC-1200), and a speed indicator (81.SI-1200), for local control and monitoring.
The gas feeders have an automatic control system (CL.MOD-81.1501 VCP) to control feed
rates. The control system compares the operator-selected setpoint to the residual chlorine
signal from the analyzer (26.AIT-1013 or 60.AIT-1001). Proportional and integral gain
adjustments, in conjunction with a fixed and variable lag time to correct for the deviation
from setpoint and reposition the feed rate actuator accordingly.
In the compound loop control mode, the controller adjusts the feed rate in response to plant
flow and residual (concentration of free chlorine). The controller accepts signals from both
the flowmeter and the residual analyzer. The gas feed rate is instantaneously corrected for
changes in flow. The controller also compares the residual signal to an operator-selected
setpoint and corrects for any deviation for each lag time interval. The compound loop mode is
used for closed loop mode feedback control in applications where flow changes and chlorine
demand vary over a wide range.
In the direct residual mode, the feed rate is adjusted by the controller, based on the residual as
measured by a residual analyzer similar to the compound loop mode described above. The
direct residual control mode is used to maintain a desired residual in applications where the
flow is constant or changes only gradually.
6.5.13.3 Remote Manual Mode of Operation:
In the remote mode of operation, PLC-CLB shall assume control of the chlorine feeds
systems based on the operators settings. The operator shall have the capability of adjusting
feed rates and dosing rates from main Process Control Center (PCC) as well as monitor all
process parameters and alarms.
Individual chlorinators are put in remote mode at the chlorinator controller (CL.CFC-81.1002
VCP or CL.CFC-81.1003 VCP). The selection between remote manual and remote automatic
is made at the main Process Control Center (PCC).
Once the selection for remote automatic mode is made the operator must then select either
Flow Paced remote automatic operation or Compound Loop remote operation. PLC-CLB
shall then take complete control of the chlorinator selected for this mode of operation that is
either flow paced or compound loop operated.
102
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
In either flow paced or compound loop operation, it is then necessary for the operator to enter
a desired dosage in mg/L. The specific chemical equation would then be as follows for a flow
paced mode of operation:
[Gas dosage (mg/L)-operator selectable x 8.34 x flow rate (MGD)- from respective flow
meter] = pounds per day (lbs./day)
The specific flow rate to use in the equations is dependent on the point of application, and
shall be, raw water flow meter 26.FIT.1010 for post-treatment chlorinators CL.CFC81.1002 or CL.CFC-81.1003 and treated water flow meter 60.FIT.1000 for pre-treatment
chlorinator CL.CFC-81.1001.
When the gas Chlorinator is in compound loop mode, the calculated dosages above would be
adjusted (trimmed) as necessary based on the feedback from the treated water chlorine
analyzer 60.AIT-1001. An operator adjustable field shall be provided on the display to allow
for a feedback set point for this specific analyzer. This shall be displayed next to the actual
reading from this analyzer.
6.5.13.4 Monitoring Requirements:
The chlorine system (pre and post) has a local vendor control panel to monitor process
parameters as outlined below:
The weight of each liquid chlorine cylinder in service shall be monitored locally and at the
main Process Control Center (PCC).
Low pressure alarm for the liquid lines to the chlorinators shall be monitored locally and at
the main Process Control Center (PCC).
Chlorine lines high and low temperature alarms and power failure alarm shall be monitored
locally and at the main Process Control Center (PCC).
The low and high vacuum alarms as well as the low flow alarm for each chlorine feeder shall
be monitored locally and at the main Process Control Center (PCC)
Chlorine leak detected alarms shall be monitored locally and at the main Process Control
Center (PCC)
A flow switch is provided to verify the flow of each ejector water. This shall also be
incorporated into the control logic to determine failure of the system. On no flow of ejector
motive water the individual ejector shall be isolated and an alarm initiated. The operator shall
then manually switch the flow of the corresponding chlorinator as required. Reference the
Chlorine Motive Water Pumps for specific requirement of a low flow alarm condition.
It is necessary that the PCC system calculate a daily chlorine inventory and average dosage
based on the weight reduction in the cylinder(s) over a 24-hour period. Weigh Scales are
provided for this purpose. Weight is indicated locally and remotely at the PCC. The total
usage would be reported in pounds and the average dosage for the day would be calculated as
follows:
[Total weight reduction (lbs.)] / [total daily plant production (MG)] / 8.34 = Total average
dosage (mg/L)
Approximate % post chlorine dosage = Total Average Dosage* [(Total Chlorine feed through
Chlorinator CL.CFC-81.1002 or CL.CFC-81.1003/Total chlorine feed through all
Chlorinators]
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
103
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Approximate % pre chlorine dosage = Total Average Dosage* [(Total Chlorine feed through
Chlorinator CL.CFC-81.1001/Total chlorine feed through all Chlorinators]
The system must recognize when a change in point of application is made, and entered by the
operator, to take into account the change in chlorinators for calculating the dosage of pre or
post chlorine feed.
The system must also recognize that cylinders can be replaced during the day, possibly more
than once, and on each side of the automatic switchover. This can be accomplished by
monitoring the changes in weight (increasing or decreasing) and incorporating it into the
logic.
6.5.13.5 Chlorine Motive Water Pumps
Liquid chlorine is vaporized and metered to the Raw and Treated water ejectors where it is
dissolved in motive water. The motive water pumps draw their supply from the common
filtered water channel.
Chlorine Motive Water Pump No.1 feeds the Raw Water Ejector and the Treated Water outlet
Ejector. Chlorine Motive Water Pump No. 2 and No. 3 operate in a Lead/Backup mode to
supply the Pre-treated Water Ejector.
Reference Chemicals - Chlorine Process and Instrumentation Diagrams 13/217/7501.
The Chlorine Motive Water Pump system has the following equipment:
CL.BP-81.1710
Chlorine Motive Water Pump (No. 1)
CL.BP-81.1720
Chlorine Motive Water Pump (No. 2)
CL.BP-81.1730
Chlorine Motive Water Pump (No. 3)
The Chlorine Motive System operation can be remotely monitored and controlled via PLCRFG and the operator station graphic display located at the Process Control Center (PCC) in
the Chemical Building. The system has full local, manual control.
Local control of the Chlorine Motive Water Pump system is from Panel CL.BP-81.1700 LCP
located at the process equipment.
Each Motive Water pump has an LCP mounted Local-Off-Remote selector switch (81.HS1710), a Start Pushbutton (81.HMS-1710), a Stop Pushbutton (81.HMS-1711), a Fault status
indicator (81.YA-1710) for local control and monitoring.
Additional controls for Motive Water pumps No2 and No3 include a Lead/Backup selector
switch (81.HS-1722).
Motive Water pumps has local control capabilities from the LCP mounted operator devices as
outlined below.
LOR Selector Switch (81.HS-1710):
Local mode (L), pump can be started/stopped via the start/stop pushbuttons located on the
LCP.
Off mode (O), pump cannot be started locally at the LCP or from the operator station.
Remote mode (R), pump can be started/stopped via the graphical start/stop poke points and
placed in Hand-Off-Auto mode via the graphical H-O-A poke point located on the operator
station graphic display.
Lead/Backup Selector Switch (81.HS-1722):
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
104
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
In the Auto mode, pumps No2 and No3 will be controlled by the PLC. During normal
operation, the pump selected for Lead mode will operate to supply motive water to the
Treated Water Ejector. In the event that The Lead pump fails, the pump selected as Backup
will start and take over the task to supply motive water to the Treated Water Ejector.
Each of the three Motive Water pump discharge lines is fitted with an inline, low flow switch
located at the associated ejector to monitor the pumps operation. In addition to the low flow
switch, each pump is monitored by a motor overload and single phase relay to generate a
motor fault condition. When the motor fault condition is activated as an alarm input to the
PLC for the Lead pump, the logic will remove the Lead from service and place the Backup
pump online.
The Lead Backup selector switch function is only effective while in the Remote mode of
operation. The operator must select the appropriate mode for each pump (Lead or Backup).
LOR switch 81.HS-1710 and Lead/Backup Selector Switch 81.HS-1722 mode position are
displayed on the operator station graphic display.
Start/Stop Pushbuttons (81.HMS-1710/ 1711):
The Local LCP Start pushbutton initiates the hard-wired run command via the pump motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the pump
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the
Pump motor starter run circuit. The PLC discrete output signal (81.HS-1710) is energized
while the pump is called to run and de-energized when called to stop. Reference the Electrical
elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Low Flow alarm (FAL) indicated at the operator station graphic display shall be programmed
in the PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL
LOGIC. Local panel Flow alarm indication is generated from hard-wire logic circuit must be
reset with the Alarm Reset Pushbutton (81.HMS-1732) to unlatch the hardwire logic.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
105
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC. .
Local panel Run status indication (YL) is generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
6.5.13.6 Chlorine Scrubber System
Local mode (L), Circulation Pump can be started/stopped via the start/stop pushbuttons
located on the VCP.
Off mode (O), Circulation Pump cannot be started locally at the LCP or from the operator
station.
Remote mode (R), Circulation Pump can be started/stopped via the graphical start/stop poke
points located on the operator station graphic display.
LOR switch mode position (81.HS-1010) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (81.HMS-1010 / 1011):
The Local LCP Start pushbutton initiates the hard-wired run command via the Pump motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the Pump
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
106
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L) and the graphical Hand Off-Auto poke point is in the Hand mode.
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the
Pump motor starter run circuit. The PLC discrete output signal (81.HS-1013) is energized
while the Pump is called to run and de-energized when called to stop. Reference the Electrical
elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Fault (YA) alarms indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel alarms indication are generated from the hard-wire logic in the motor starter
circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Pressure alarm (PAH/PAL) indicated at the operator station graphic display shall be
programmed in the PLC logic as described in section II. GENERAL GUIDELINES FOR
CONTROL LOGIC. Local panel Pressure alarm indication is generated from the hard-wire
logic in the motor starter circuit must be reset with the Alarm Reset Pushbutton (81.HMS1012) to unlatch the hardwire logic. Reference the Electrical elementary schematics for
requirements of the Fault conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC. .
Local panel Run status indication (YL) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
Local control of the Extraction Fan is from Panel CCS-SYS-81.1010 VCP located at the
process equipment.
HOA Selector Switch (81.HS-1610):
Hand mode (H), Fan can be started/stopped via the start/stop pushbuttons located on the LCP.
Off mode (O), Fan cannot be started locally at the LCP or from the operator station.
Auto mode (A), Fan will be started/stopped via the chlorine leak detection analyzers as
outline above.
HOA switch mode position (81.HS-1610) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (81.HMS-1610/ 81.HMS-1611):
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
107
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The Local LCP Start pushbutton initiates the hard-wired run command via the Fan motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the Fan
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
The Local Start/Stop Pushbuttons are operational only when the HOAselector switch is in the
Local mode (H).
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Run status indication (YL) is generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
6.5.14
Alum System
The chemical building consists of the alum storage area alum mixing chambers and a room
for installation of a future polyelectrolyte system.
Bagged alum is loaded into a crane-mounted hopper and dumped via an inlet basket into one
of two mixing chambers. The alum is dissolved in water supplied by the service water system.
Each chamber has a single motor-driven mixer with a manually adjusted-speed gearbox. The
alum solution is fed via two variable speed diaphragm pumps into the raw water pipeline
upstream of the in-line chemical Disperser by dosing pumps. Dosing pumps can draw from
either mixing chamber. Additional equipment housed in the building include a manuallyoperated crane, power panels, and local control panels.
The Alum Feed System operation can be remotely monitored and controlled via PLC-CB and
the operator station graphic display located at the Process Control Center (PCC) in the
Chemical Building.
Local control of the Alum Feed System is via a feed rate controller (ALS.CFC-80.1100 VCP
and ALS.CFC-80.1200 VCP) located at the process equipment. The diaphragm pumps are
configured in a Duty/Standby arrangement with the speed control managed by a SCR Drive
(DC).
Each of the diaphragm pumps is supplied with a feed rate controller mounted locally at the
process equipment. The controller allows the operator to control the feed rate locally in either
a manual, automatic or flow paced mode.
Each feed rate controller has a Local-Off-Remote selector switch (80.HS-1100), a Start
Pushbutton (80.HMS-1100), a Stop Pushbutton (20.HMS-1101), a Fault status indicator
(80.YA-1100) and a Run status indicator (80.YL-1100), a manual speed control potentiometer
(80.SC-1100), and a speed indicator (80.SI-1100), for local control and monitoring.
Reference Alum System Process and Instrumentation Diagram 13/228/7501.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
108
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Local mode (L), controller can be started/stopped via the start/stop pushbuttons located on the
VCP.
Off mode (O), controller cannot be started locally at the LCP or from the operator station.
Remote mode (R), controller can have its speed controlled via the graphical operator entered
setpoints poke points and placed in Hand-Off-Auto mode via the graphical H-O-A poke point
located on the operator station graphic display. Additionally, the controller can be controlled
by the PLC in the Auto mode for operations as outlined below.
Once the selection for remote automatic mode is made the operator must then select Flow
Paced remote automatic operation. PLC-CB shall then take complete control of the feed
system selected for this mode of operation.
In the flow paced mode, it is then necessary for the operator to enter a desired dosage in
mg/L. The specific chemical equation would then be as follows for a flow paced mode of
operation:
[Alum feed rate (mg/L)-operator selectable x 8.34 x flow rate (MGD)- from respective flow
meter] = pounds per day (lbs./day)
The specific flow rate to use in the above equations is the raw water flow meter
26.FIT.1010 for Alum feed to the raw water Inline Chemical Disperser (IDC).
LOR switch mode position (80.HS-1100) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (20.HMS-1100 / 1101):
The Local VCP Start pushbutton initiates the internal run command via the run circuit. The
Stop pushbutton unlatches the internal run command. Reference the Reference the
manufacturer documentation for requirements of the start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the internal logic in the
controllers circuit. Reference the manufacturers documentation for requirements for
requirements of the Fault conditions.
6.5.14.1 Alum Mixing System
The Alum Mixing System operation can be remotely monitored and controlled via PLC-CB
and the operator station graphic display located at the Process Control Center (PCC) in the
Chemical Building. The feed system has full local, manual control.
Local control of Alum Mixing System is from Panel ALS.MX-80.1000 LCP located at the
process equipment.
The Alum Mixing System has a LCP mounted Local-Off-Remote selector switch (80.HS1010), a Start Pushbutton (80.HMS-1010), a Stop Pushbutton (80.HMS-1011), a Fault status
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
109
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
indicator (80.YA-1010) and a Run status indicator (80.YL-1011) for local control and
monitoring.
Reference Alum System Process and Instrumentation Diagram 13/228/7501.
The Alum Mixing System has local control capabilities from the LCP mounted operator
devices as outlined below:
LOR Selector Switch (80.HS-1010):
Local mode (L), Mixer can be started/stopped via the start/stop pushbuttons located on the
LCP.
Off mode (O), Mixer cannot be started locally at the LCP or from the operator station.
Remote mode (R), Mixer can be started/stopped via the graphical start/stop poke points
located on the operator station graphic display.
LOR switch mode position (80.YL-1010) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (80.HMS-1010 / 1011):
The Local LCP Start pushbutton initiates the hard-wired run command via the Mixer motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the Mixer
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the
Mixer motor starter run circuit. The PLC discrete output signal (80.HS-1010) is energized
while the mixer is called to run and de-energized when called to stop. Reference the Electrical
elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC. .
Local panel Run status indication (YL) are generated from the hard-wire logic in the motor
starter circuit. Reference the manufacturers documentation for requirements of the Run status
indication.
6.5.15
Filtered water is treated with chlorine and flows through the chlorine contact tank to the
Treated Water Storage Tank (TWST) via yard piping. The TWST is a two-chamber tank
treated water storage tank. The Treated Water Pumping Station (TWPS) transfer treated water
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
110
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
back to the Elevated Storage Tank (EST) located at the Raw Water Pump Station via the
treated water pipeline.
The Treated Water Pumping Station consists of a pump room and an electrical room located
above the TWST. The TWST chambers act as wet wells for the treated water pumps.
Additional equipment housed in the pump room include the treated water and service water
discharge piping and valves, the service water hydro-pneumatic sub-system. Equipment
housed in the electrical room includes the treated water MCC, distribution panels and the
treated water pumps local control panel.
Reference Treated Water Process and Instrumentation Diagrams 13/243/7501 and 7502.
The TWPS has the following equipment:
TW.P-60.1050
Portable Sump Pump
TW.FE-60.1000
Mag Meter (TW Flowmeter)
TW.P-60.1010
Treated Water Pump (No. 1)
TW.P-60.1020
Treated Water Pump (No. 2)
TW.P-60.1030
Treated Water Pump (No. 3)
TW.P-60.1040
Treated Water Pump (No. 4)
TW.CRN-60.1000
Bridge Crane Hoist
TW.CRN-60.1000
Bridge Crane Cross Travel
TW.CRN-60.1000
Bridge Crane Long Travel
TW.MOV-60.1000
Actuator Valve (TW discharge pressure)
TW.SP-60.1001
Sample Pump
The Treated Water Pumping Station operation can be remotely monitored and controlled via
PLC-TW and the operator station graphic display located at the Process Control Center (PCC)
in the Chemical Building. The TWPS has full local, manual control.
Local control of the TWPS is from Panel TW.P-60.1001 LCP located at the process
equipment.
Each treated water pump has a LCP mounted Local-Off-Remote selector switch (60.HS1010), a Start Pushbutton (60.HMS-1010), a Stop Pushbutton (60.HMS-1011), a Fault status
indicator (60.YA-1010) and a Run status indicator (60.YL-1010), a High Pressure discharge
alarm status indicator (60.PAH-1010), a Low Pressure discharge alarm status indicator
(60.PAL-1010) and an Alarm Reset Pushbutton (60.HMS-1012) for local control and
monitoring. Each treated water pump has local control capabilities from the LCP mounted
operator devices as outlined below:
LOR Selector Switch (60.HS-1010):
Local mode (L), pump can be started/stopped via the start/stop pushbuttons located on the
LCP.
Off mode (O), pump cannot be started locally at the LCP or from the operator station.
Remote mode (R), pump can be started/stopped via the graphical start/stop poke points and
placed in Hand-Off-Auto mode via the graphical H-O-A poke point located on the operator
station graphic display. Additionally, the pump can be controlled by the PLC in the Auto
mode for start/stop, fast/slow and lead/lag/backup operations as outlined below.
LOR switch mode position (60.HS-1010) is displayed on the operator station graphic display.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
111
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The Local LCP Start pushbutton initiates the hard-wired run command via the pump motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the pump
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the
Pump motor starter run circuit. The PLC discrete output signal (60.HS-1010) is energized
while the pump is called to run and de-energized when called to stop. Reference the Electrical
elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
The Treated Water Pumps are manually placed on and off line by the operator as required to
maintain sufficient level in the EST and adequate pressure on the distribution discharge line.
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Pressure alarm (PAH/PAL) indicated at the operator station graphic display shall be
programmed in the PLC logic as described in section II. GENERAL GUIDELINES FOR
CONTROL LOGIC. Local panel Pressure alarm indication is generated from the hard-wire
logic in the motor starter circuit must be reset with the Alarm Reset Pushbutton (60.HMS1012) to unlatch the hardwire logic. Reference the Electrical elementary schematics for
requirements of the Fault conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC. .
Local panel Run status indication (YL) is generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
6.5.16
The Service Water System (SRW) pumps and Service Water tanks are all located on the
operating floor of the filter building, which is located above the pipe gallery. Service water
draws its supply from the TWST chambers, which act as wet wells for the treated water
pumps and service water pumps.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
112
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The Service Water System feeds numerous entities, reference the PID 13/243/7503 for
specific service water distribution points and applications. The system provides 100% standby
capacity for the facility.
The Service Water System has the following equipment:
SRW.P-60.1100
Service Water Pump (No1)
SRW.P-60.1200
Service Water Pump (No2)
SRW.P-60.1300
Service Water Pump (No3)
SRW.P-60.1400
Service Water Pump (No4)
SRW.TK-60.1000
Accumulator Vessel
The Service Water System operation can be remotely monitored and controlled via PLC-TW
and the operator station graphic display located at the Process Control Center (PCC) in the
Chemical Building. The SRW has full local, manual control.
Local control of the SRW is from Panel SRW.SYS-60.1000 VCP located at the process
equipment.
Each Service Water pump has a VCP mounted Local-Off-Remote selector switch (60.HS1100), a Start Pushbutton (60.HMS-1100), a Stop Pushbutton (60.HMS-1101), a Fault (prime)
status indicator (60.YA-1100) for local control and monitoring. Each Service Water pump has
local control capabilities from the VCP mounted operator devices as outlined below.
LOR Selector Switch (60.HS-1100):
Local mode (L), pump can be started/stopped via the start/stop pushbuttons located on the
LCP.
Off mode (O), pump cannot be started locally at the LCP or from the operator station.
Remote mode (R), pump can be started/stopped via the graphical start/stop poke points and
placed in Hand-Off-Auto mode via the graphical H-O-A poke point located on the operator
station graphic display.
Additionally, in the Auto mode, the pump will be controlled by the PLC. During normal
operation, a single pump should be able to supply the demand and keep the Accumulator
Vessel charged under sufficient pressure. In time of peak load, multiple pumps will operate in
a Lead/Lag/Backup configuration based on the operator selected mode. Operation of the
pumps is individually controlled by separate pressure switch settings in 5 PSIG increments
with cut-in and cut-out.
LOR switch mode position (60.HS-1010) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (60.HMS-1100 / 1101):
The Local LCP Start pushbutton initiates the hard-wired run command via the pump motor
starter run circuit. The Stop pushbutton unlatches the hard-wired run command via the pump
motor starter run circuit. Reference the Electrical elementary schematics for requirements of
the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the LOR selector switch is in the
Local mode (L).
The Remote Start/Stop Pushbuttons located on the operator station graphic display perform
the equivalent function as the Local hard-wired Start/Stop Pushbuttons mounted on the LCP
when the Hand-Off-Auto graphical poke point is in the Hand mode.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
113
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The operator station Start/Stop Pushbuttons are operational only when the LOR selector
switch is in the Remote mode (R) and the graphical Hand Off-Auto poke point is in the Hand
mode.
The operator station Start/Stop Pushbuttons initiates the hard-wired run command via the
Pump motor starter run circuit. The PLC discrete output signal (60.HS-1100) is energized
while the pump is called to run and de-energized when called to stop. Reference the Electrical
elementary schematics for requirements of the PLC start/stop control.
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Pressure alarm (PAL) indicated at the operator station graphic display shall be programmed in
the PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL
LOGIC. Local panel Pressure alarm indication is generated from the hard-wire logic in the
motor starter circuit must be reset with the Alarm Reset Pushbutton (60.HMS-1012) to
unlatch the hardwire logic. Reference the Electrical elementary schematics for requirements
of the Fault conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
6.5.17
The Overflow Holding tank receives flow from three main sources, the CCT overflow, the
Clean Wash water Tank and from the Clarifier overflow. The overflow water is pump to the
existing Irrigation Ditch for use by the locals. The overflow system is required to
hydraulically overcome the variance in elevation between the Treatment Facility and the
Irrigation Ditch.
Reference Process Overflow Process and Instrumentation Diagram 13/223/7501.
The Overflow system has the following equipment:
OF.P-67.1010
Overflow Pump
Local control of the Overflow Pump is from OF.P-67.1010 LCP located at the process
equipment.
The Overflow Pump has a LCP mounted Hand-Off-Automatic selector switch (67.HS-1010),
a Start Pushbutton (67.HMS-1010), a Stop Pushbutton (67.HMS-1011), a Fault status
indicator (67.YA-1010), a Run status indicator (67.YL-1010), a overflow tank High Level
status alarm (67.LAHH-1000), a discharge press Low Level status alarm (67.LALL-1000)
and an Alarm Reset Pushbutton (67.HMS-1012) for local control and monitoring. Each
Overflow Pump has local control capabilities from the LCP mounted operator devices as
outlined below:
HOA Selector Switch (67.HS-1010):
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
114
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Hand mode (H), pump can be started/stopped via the start/stop pushbuttons located on the
LCP.
Off mode (O), pump cannot be started locally at the LCP or from the operator station.
Auto mode (A), pump will be started/stopped via the multi-point level switch (tipping ball)
mounted in the Overflow tank. The level switches are configured as Pump stop (67.LSL1000) and Pump Start (67.LSH-1000).
HOA switch mode position (67.HS-1010) is displayed on the operator station graphic display.
Start/Stop Pushbuttons (67.HMS-1010/67.HMS-1011):
The Local LCP Start pushbutton initiates the hard-wired run command via the Overflow
Pump motor starter run circuit. The Stop pushbutton unlatches the hard-wired run command
via the Overflow Pump motor starter run circuit. Reference the Electrical elementary
schematics for requirements of the start/stop control.
The Local Start/Stop Pushbuttons are operational only when the HOA selector switch is in the
Hand mode (H).
The Run status and elapsed run time are monitored and displayed at the operator station
graphic display.
Status/Alarm Indication:
Fault alarms (YA) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Fault alarms indication (YA) are generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Fault
conditions.
Run status (YL) indicated at the operator station graphic display shall be programmed in the
PLC logic as described in section II. GENERAL GUIDELINES FOR CONTROL LOGIC.
Local panel Run status indication (YL) is generated from the hard-wire logic in the motor
starter circuit. Reference the Electrical elementary schematics for requirements of the Run
status indication.
Level alarms (LAHH and LALL) indicated at the operator station graphic display shall be
programmed in the PLC logic as described in section II. GENERAL GUIDELINES FOR
CONTROL LOGIC. Local panel Level alarm indication is generated from the hard-wire logic
in the motor starter circuit and must be reset with the Alarm Reset Pushbutton (67.HMS1012) to unlatch the hardwire logic. Reference the Electrical elementary schematics for
requirements of the Fault conditions.
115
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The project design concept is based on local natural and cultural environment. The plants are
proposed to be located in hot-arid zone with special architectural characteristics related to
local materials such as clay brick and local cultural heritage that will be present in the
architectural project and architectural language. The design concept is manifested in two
different levels, the whole (site layout level) and the part (individual building level). Site
layout concept started from using a symbol reflecting the common elements for all water
treatment plants.
Architectural concept for individual building uses simple functional layouts, that can be
constructed by using local experiences and materials which reflect the continuity between the
past local cultural heritage and present technologies. This will be reflected by using two layers
in treating the elevations. The outer will be simple smooth frame and the inner will be brick
infill with local patterns and arrangements.
7.2 Scope of Work
Scope of architectural work to be undertaken comprises the design of general layout of the
specific site and grouping of buildings according to their functions, process and non-process
buildings, and prepairing designs and working drawings for each individual building for
execution.
Architectural work includes also arrangement of walkways, roads and landscaping of the site.
7.3 Methodology
7.3.1 General criteria
Architectural design shall recognize the separate functions of various building areas, but shall
also integrate these functions into a compatible whole design.
Site layout, building layouts, room arrangements, buildings general massing and elevations
will be based on actual site survey for Wasit irregular shape and dimensions and design a
seperated site for Raw Water Intake and Pump Station .
Minimum ceiling height in all buildings shall be 3.0 meters. Buildings where hoists or crane
are permanently installed, or where temporary hoists are required, shall have heights dictated
by appropriate distances and clearances for the hoisting equipment, hoisting motors, chairs
and hooks equipment being moved and level of receiving vehicle.
The structure shall be functional and practical with emphasis on long life and minimum
maintenance under all conditions, so the architectural language shall convey this sense of
functionality, durability and sustainability.
7.3.2 Support Buildings
116
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
between the past local cultural heritage and present technologies. This will be reflected by
using two layers in treating the elevations, the outer will be simple smooth frame and the
inner will be brick infill with local patterns and arrangement.
7.3.3 Process Buildings
This part of the architectural design criteria is applicable to the process buildings which include Raw
Water Pumping Station (RWPS), Treated Water Pumping Station (TWPS), Wastewater Pumping
Station (WWPS), Chlorine Building (CLB), Chemical building (CB) with outside W.Cs., Filter
Building (FB), and Electrical MCC Building (EB). They will be located in a manner that will
facilitate process operations with a special emphasis on permitting gravity flow through the entire
process. The hydraulic profile will, to a great degree, control the elevations of the process structures.
Process building layouts and arrangement will be provided based on applicable codes, process and
equipment requirements.
Architectural design of the process buildings shall continue the consistent architectural themes
developed for the support buildings while accommodating the unique structural requirements
dictated by the processes. Brick shall be used as an infill between columns. Brick work shall
be plastered with 20mm thick cement/sand plastering. All walls shall be rendered in colours
matching support buildings.Exterior details shall be designed for extended service under
conditions of severe exposure. Expansion joints shall be provided for anticipated building
movements and thermal movement.
7.4.Basis of Design
7.4.1 Codes And Standards
Architectural design shall conform to the following applicable standards and codes:
BS 5359
Stair, Ladder and walkway
BS 4211
Ladder for permanent access to chimney, other high structures, silos
and bins.
BS 12373
Aluminium and aluminium alloys-anodizing
BS 3416
Specifications for bitumen-based coating for cold application suitable
for use in contact with potable water.
BS 6180
Barriers in and about buildings- Code of Practice.
BS 6100
Glossary of building and civil engineering term.
BS 12944
Paint and Varnishes- Corrosion protection of steel structures by
protective paint system.
7.4.2 Primery Elements
7.4.2.1 External walls
All non process building will be constructed using load bearing brickwalls (24 cm thickness)
7.4.2.2 Internal walls
Internal walls will be constructed using 24 cm thickness brickwalls for loadbearing walls and
12 cm thickness for non-load bearing brickwalls.
7.4.2.3 In-situ R.C. floor and roof slabs
117
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
7.4.3 Finishing
7.4.3.1 Wall finishing
External walls
Finishings are either with white smooth cement plastering, which shall be used as module
framing, or brick cladding with traditional style for filling the panels between the frames.
Internal wall
Finished with painted gypsum plastering or cermatic tiles for the lab and sanitary areas and
changing rooms, epoxy-painted on cement plastering for workshope area, and plastic paint for
adminstration building corridors.
Finishes shall conform to flame spread and smoke developed requirments as per the
applicable building codes.
7.4.3.2 Floor Finishings
Floor will have mosaic tiles in general, non-slip floor ceramic tiles bathrooms & wet areas,
epoxy paint for workshop.
7.4.3.3 Base
Rooms scheduled for sealed concrete floors shall be provided with 100 mm high cement
skirting. Rooms scheduled for tile floors shall be provided with tile base matching floor
finish.
7.4.3.4 Ceilings
Acoustic suspended ceiling will be used in adminstration building. Painted cement plastering
for bathrooms and wet areas. Painted gypsum plastering for the remaining space.
7.4.3.5 Metal works
Mild steel will be used for the construction of main entrance gates, workshop sliding door,
windows screens, staircases and ladders. Steel surfaces will be primed & paint finished
coated. Aluminum sections will be used for all windows and kitchen benches.
7.4.3.6 Carpentry
Timber will be used for internal doors in administration and residential building.
7.4.3.7 Roofing system
Roof system consists of the following:
- Pre-cast concrete roof tiles.
- Sand layer for slopping surfaces
- Insulation layer
- Clear sand layer
- Membrane sheet roofing over reinforced concrete slab
7.4.3.8 Flashing
Pre-cast concrete parapet cap and external window sills will be used. Anodized aluminum at
all locations except stainless steel at corrosive environment.
7.4.3.9 Water proofing
Structural wall beneath ground level shall be cement plastered & coated with water proofing
layers. Damp proof R.C. course shall be used at external and internal ground level, along
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
118
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
external & internal walls. Cementation waterproofing provided at internal side of concrete
tanks. Water prooofing shall be suitable for potable water. Torch applied membrane provided
at exterior side of tanks to prevent groundwater infiltration.
7.4.3.10 Sealants
Silicones shall be used for sealing vertical joints of concrete structures cast in-situ or of
prefabricated concrete elements, as well as for parametrical seals.
Polyurethane made from two components shall be used for joints in vertical elements and
ceilings, for sealing between dissimilar matrials as well as for the filling of expansion
joints, horizontal joints, for surface subjected to traffic and for concrete joints.
Indoor sealing compounds shall be used as follows:
Single component polyurethane shall be used where movement of joints are anticipated
due to dynamic loading.
Elastic silicone sealing compounds shall be used to seal the perimeters of sheers, skins,
toilets, and urinals.
Heavy-duty hollow metal doors and frames shall be provided at all interior and exterior
location except entrance doors and corrosive enviroments (i.e, chemical rooms and wet
areas).Aluminum doors and frames will be provided at locations in corrosive
enviroments.Door and frame material in chemical enviroments will be selected based upon
the specific chemical present. Aluminum doors and frames shall have anodized finish. Hollow
metal doors and frames shall be factory primed with finished coats applied in field. Hardware
shall be heavy-duty and keying shall be finalized by owner.
7.4.3.12 Windows
All exterior glazing shall be double-pane, tinted, tempered insulated glass. Interior glazing
shall be 6 mm clear tempered glass. Reinforced glass shall be provided at pass-thru window.
7.4.3.14 Fencing
Fencing shall be provided around the perimeter of the water treatment plant. R.C. columns
and brickwork infill with brick cladding shall be used for constructing the fence.
7.4.4 Project Particulars
The project is to design Wasit water treatment plant of 1000m3/hr capacity. The essential
building components of the project are as follows:
7.4.4.1Adminstration building
Entrance and reception hall with reseptionist desk & small office facilities such as copy
machine, fax machine, computer terminal, file cabinet, and stock shelves.
119
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Offices for DG and five other office persons. Note that types and areas of space had been
taken according to the total number of staff are 24 person (for 1000 m3/h WTP).
Service facilities (Males/Females WCs with female doubled as disabled), and cleaning
supplies room.
The project will have two houses (one with two floors) for operators or other staff members
that will be constructed with load bearing walls and fine finishes. Each contains the following
spaces:
-
2 bedrooms
Dining area
Laundry room
Storage room
The project needs a place for guards dwelling, which must contain the following spaces:
- Entrance and waiting room
- Bed room
- Bathroom
- Kitchen
7.5 Architectural Design and Working Drawings
Architectural drawings shall be submmited in two types, new drawings for site layout,
landscaping and raw water intake pump station and modified drawings for other individual
buildings after checking, modifying their levels and orientation.
The list of drawings to be submmited are as follows:
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
120
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
121
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The objectives of the structural design are to achieve the required safety with the maximum
economy within the architectural, mechanical and electrical requirements.
Safety has been defined according to the requirements of the Local Building Regulations and
the High Standards International Codes. Economical structures could be achieved through the
implementation of the most practical structural systems permitted within the constraints of the
architectural requirements, proper co-ordination with the architectural design to choose a
modular grid that will yield an economical structure, with full attention to avoid costly
construction procedures.
8.2 Design Criteria
The main items of the civil GA and the structural design SOW are indicated as follow:
8.2.1 Design Codes
The building structures will be designed according to sound engineering principles based on
the British Standard Codes listed below. Relevant parts of the following Codes of Practice
will be used as needed for the structural design purposes:
BS 6399-Part 1: 1997
BS 6399-Part 3: 1988
BS 648: 1964
BS 8666: 2000
BS 4483: 1998
122
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
BS 6031: 1981
BS 8007: 1987
BS 8002: 1994
BS 8004: 1986
BS 5950 Part 2:
123
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
8.2.2
Design Software
STAAD-PRO is the computer software which is used for the design of the structures; it is
applied for the structural analysis of the building structures and the design of the reinforced
concrete or steel elements, design of reinforced concrete flat slabs and mat foundations.
8.2.3
Structural Materials
Concrete:
- All main reinforcing steel shall be of uncoated deformed high tensile steel bars with a
minimum yield stress of 414 N/mm2.
- All beams stirrups and column ties and hoops shall be mild steel bars with a minimum
yield stress of 275 N/mm2.
- The available reinforcement bar diameters in Iraq are confirmed to be 8, 10, 12, 16, 20
and 25 mm.
Structural steel:
Standard shapes and plates-BS 5950 with high yield strength of 275 N/mm2.
8.2.4
Foundations
The type of foundation, depth and size of footings that can support the building structure will
depend on several factors among these:
-
The combination of dead loads consisting of self-weight of structural elements, floor and
roof finishing materials and partition loads, and the live loads imposed on the floors.
124
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The information regarding the foundation soil and the recommendations of the site
investigation report, to be prepared for the structures locations, will serve as the bases for
the footing design.
8.2.5
8.2.5.1 General
Design and detailing of reinforced concrete structures will be in accordance with BS 8110.
Underground structures will be statically checked for flotation. In the case of pits, basins,
manholes and other water retaining structures the factor of safety against flotation may be
increased up to 1.25 by engineering judgment, according to specific site conditions.
8.2.5.2 Design Loads
Dead Loads
The structures are designed for the vertical loads due to the weight of all permanent building
components, such as floors, reinforced concrete walls, plastered concrete block works,
imposed finishing materials, fixed equipments, suspended ceilings, suspended electrical
lighting, piping and duct works, if any.
The unit weight of the materials and components are as defined in BS 648 "Schedule of
weight for building materials" or information from the product supplier giving installed
weights of materials or components.
Live Load
The floors of the buildings are designed for the proper live loads needed to serve the use of
each floor.
Live loads are as defined in BS 6399- Part 1 and Part 3: Design Loading for Buildings.
Wind Load
The wind pressure is to be calculated in accordance with CP3, Chapter V, Part 2, 1972 "Basic
data for Design of Buildings-Wind Loads".
The design wind speed factors will be determined according to each site location and
geographical data.
Structures, such as elevated water tanks, will be designed for a basic wind speed of 45 m/sec.
For design purposes wind will be assumed to come from any direction.
Snow Load
The snow load will be computed according to BS 6399-Part 3, according to the basic snow
loads record in Iraq.
Load Combinations
125
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Cement for structural reinforced concrete and paving shall be Ordinary Portland Cement
(OPC) complying with BS 12 or equivalent and sulphate resisting Cement (SRC) complying
with BS 4027:1980, according to each project site conditions.
Concrete Cover
Concrete cover thickness to all steel reinforcement including links shall be as follows:
-
for all reinforced concrete members the minimum nominal cover to the reinforcement is
40 mm.
For mechanical and electrical rooms the recommendation of section 4 of BS 8110, Part 2:
1985 regarding the fire protection of structural concrete elements, for a min. 2 hours fire
resistance will be also taken into consideration.
The nominal covers thickness may be increased according to the recommendations of the
soil Investigation Report of each site.
Concrete Protection
Unless a particular finish is specified, all exposed concrete surfaces shall be protected with a
minimum of two coats of UV resistance aliphatic acrylic coating applied as per
manufacturers instructions.
8.2.6
8.2.6.1 General
Structural steel used in the construction of steel walkways, stairs and canopies and sunshades
for buildings, will follow the provisions of this item.
The design, details, fabrication and erection of structural steel will be in accordance with the
recommendations of BS 5950.
8.2.6.2 Design loads
Dead Loads
The structures will be designed for the vertical loads due to the weight of all permanent
building components, in addition to any collateral loads suspended from the roof as
suspended electrical lighting and piping.
Live Loads
126
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Block work will be designed to BS 5628. External walls will be cavity type comprising 150
mm solid concrete externally, a 50mm insulated cavity and 100mm hollow concrete block
internal skin.
Internal partition walls will be minimum 150mm hollow concrete block.
Block work walls will be tied to structural columns and beams using a propriate stainless steel
system that complies with the requirements of BS 5628. Cavity wall ties will also be stainless
steel.
8.2.8
Site Investigation
The purpose of the subsoil investigation is to determine the surface and subsurface conditions
of the project site, the physical, mechanical and chemical properties of the substrata and
groundwater conditions in order to provide the structural engineer with sufficient information
for the design of the most suitable and safe foundations.
Field tests and laboratory testing shall be carried out in accordance with the requirements of
British Standards BS 5930 and 1377.
A comprehensive interpretative report shall be prepared including full engineering
recommendations and conclusions for design of foundations, concrete mix &protection,
earthing (electrical resistivity), roads and pavements, surface water drainage, walkways etc.
8.3 Sample of Calculations
Administration Building: Structural Analysis and Design
Loads Calculations:
1. Dead Load
The total dead load on the slab consists from the following:
Reinforced concrete slab (18 cm thick.) = 0.18m 24 kN/m3
= 4.32 kN/m2
Clean earth (15 cm thick.) = 0.15m 18 kN/m3
= 2.7 kN/m2
3
Concrete tiles (80804cm) = 0.04m 24 kN/m
= 0.96 kN/m2
Total Dead Load
= 7.98 kN/m2
2. Live Load
Live Load (including false ceiling load) = 2 kN/m2
3. Earthquake Load
According to Iraqi Seismic Code /97, it was decided to consider zone II for calculations of earthquake
loading.
V = Z I S KW
where:
V
= Total horizontal shear
Z
= Seismic zone factor (Z = 0.07 for zone II).
I
= Importance factor (I=1.25).
S
= Soil coefficient (S=1.0)
W
= Total weight of the structure.
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
127
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
K
= Structural coefficient (K=1.0)
Hence:
V = 0.071.251.01.0W = 0.0875 W
V= 0.0875x4200 = 368 kN
Load per floor joint (refer to input file) = 368/31 = 11.85 kN say 12.0 kN
Analysis and Design
-
Output data including analysis and design are give in Appendix (B)
Footing Design
Footing of grid line (A-3) Node 3:
x
Lz = 2.8m
P = 440.8 kN
Mz =33.9 kN.m
N.G.L. = -0.1
1m
0.5 m
2.8 m
128
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
P3 = soil load = 23 kN
Total load (P) = 285.8 + 132 + 23 = 440.8 kN
Mx = 25.5 kN.m
Mz = 33.9 kN.m
q max,
min
= soil pressure =
P 6ez 6ex
A
Lz
Lx
A = 2.8m2.8m = 7.84 m2
ez =
Mz
33.8
=
= 0.077 m
P
440.8
ex =
Mx
25.5
=
= 0.0579 m
P
440.8
q max =
q min =
1
= 40.0 kN/m < 75 kN/m (no tension zone) O.K.
7.84
2.8
2.8
129
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
x
Lz = 2.8m
P = 308 kN
Mz =28 kN.m
N.G.L. = -0.1
1m
0.5 m
2.8 m
min
= soil pressure =
P 6ez 6ex
A
Lz
Lx
A = 2.8m2.8m = 7.84 m2
ez =
Mz
28
=
= 0.09 m
P
308
130
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
ex =
Mx
26
=
= 0.084 m
P
308
q max =
q min =
1
= 24.75 kN/m2 < 75 kN/m2 (no tension zone) O.K.
7.84
2.8
2.8
131
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
x
Lz = 4.25m
z
P = 570 kN
Mz =2.3 kN.m
N.G.L.
1m
0.5 m
1.6m
Footing dimensions (4.25m1.6m)
q allowable = allowable bearing capacity = 75 kN/m2
P1 = Total unfactored dead and live loads without partitions ( P cols.)= 195+217=417 kN
P2 = Partitions load = 103kN
P3 = soil load = 50 kN
Total load (P) = 417+ 103 + 50 = 570 kN
Mx = 20.1 kN.m
Mz = 2.3 kN.m
q max,
min
= soil pressure =
P 6ez 6ex
1
A
Lz
Lx
A = 4.251.6m = 6.8 m2
Mz
2 .3
=
= 0.004 m
P
570
M
20.1
= 0.035 m
ex = x =
P
570
ez =
132
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
q max =
q min =
1
= 62.2 kN/m < 75 kN/m (no tension zone) O.K.
18
5
5
d/2
d/2
133
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
x
Lz = 5m
z
P = 1268 kN
Mz =31 kN.m
N.G.L.
1m
0.5 m
3.6m
min
= soil pressure =
P 6ez 6ex
1
A
Lz
Lx
A = 5.03.6m = 18 m2
ez =
Mz
31
=
= 0.025 m
1268
P
134
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
ex =
M x 31.5
=
= 0.025 m
1268
P
q max =
q min =
1
= 62.2 kN/m < 75 kN/m (no tension zone) O.K.
18
5
5
d/2
d/2
135
4/11/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
12
11
49
10
30
8
19
29
17
27
40
14
55
39
1
38
48
26
37
15
25
36
52
24
51
13
47
16
56
442
41
54
4
53
3
28
45
42
20
18
32
31
43
50
21
22
35
23
46
34
Y
X
33
Load 1
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
43
5
11
60 49
61
42
16
10
48
3
40
14
46
13
39
27
45
56
57
12
44 21
58
18
22
7
38
52
37
29
47
32
54
20
24
9
2
63
15
41
55
25 62
53
23 19
64
67 28
66
31
36
70
65
69
35
51
17
68
26
59
50
30
34
X
Z
33
Load 1
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
105.279 kN
-31.540 kN
133.507 kN
-14.407 kN
-113.677 kN
86.010 kN
30.230 kN
-132.563 kN
132.312 kN
-30.763 kN
-85.833 kN
124.664 kN
7.164 kN
-133.758 kN
38.849 kN
-116.609 kN
-31.540 kN
-14.407 kN
30.230 kN
-30.763 kN
7.164 kN
38.849 kN
Y
Z
Load 5 : Shear Y
Force - kNm
Fig.(3) Shear Force Diagram for the frame along grid A and between (1 and 7)
138
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
42.038 kNm
8
-93.539 kNm
9
-127.642 kNm
10
-56.757 kNm
11
12
-109.482 kNm
-127.114 kNm
21.013 kNm
-29.941 kNm
28.978 kNm
-15.355 kNm
Y
Z
Load 5 : Bending Z
Moment - kNm
Fig.(4) Bending Moment Diagram for the frame along grid A and between (1 and 7)
139
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
-52.098 kNm
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
357.146 kN
108.901 kN
8.782 kN
-77.446 kN
-147.764 kN
-14.445 kN
-127.693 kN
262.052 kN
11.317 kN
-11.919 kN
-371.595 kN
8.782 kN
-14.445 kN
369.663 kN
11.317 kN
-264.599 kN
-11.919 kN
154.330 kN
13.787 kN
143.320
kN kN
88.976
-6.638 kN
-126.053 kN
-359.077 kN
13.787 kN
-6.638 kN
Y
Z
Load 5 : Shear Y
Force - kNm
Fig.(5) Bending Moment Diagram for the frame along grid B and between (1 and 7)
140
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
17
19
20
-38.679 kNm
-379.854 kNm
21
75.426 kNm
30.537 kNm
49
22
-379.649 kNm
7.791 kNm
12.482 kNm
-10.003 kNm
10.273 kNm
-12.166 kNm
-5.661 kNm
45
13
14
15
16
47
Y
Z
Load 5 : Bending Z
Moment - kNm
Fig.(6) Bending Moment Diagram for the frame along grid B and between (1 and 7)
141
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Piles Calcualtions
Overflow Holding Tank and Pumping Station:
Design Data:
Vc = 4297
kN > Vu
142
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Illustrated all the civil general arrangement drawings to be matching with the mechanical
drawings.
Illustrated all the structural design drawings for all process and non-process buildings and
modify drawings accordingly as indicated in the list of the modified drawings table shown
below.
13-207-2001
13-207-2002
13-207-2003
13-212-2006
13-212-2007
13-212-2008
13-203-3103
13-203-3104
13-206-3001
13-206-3002
13-206-3003
13-206-3004
13-217-3001
13-217-3004
13-217-3005
13-236-3802
13-236-3803
13-236-3804
13-236-3805
13-236-3806
13-236-3807
13-236-3808
13-241-3822
13-241-3823
13-241-3824
13-241-3825
13-241-3826
13-241-3827
13-241-3828
13-241-3829
13-245-3842
13-245-3843
13-245-3844
13-246-3882
13-246-3883
13-299-3004
13-222-2001
13-222-2002
13-222-2003
13-222-2004
13-223-2001
13-223-2002
13-228-2003
13-244-2001
13-244-2002
13-244-2003
13-244-2004
13-203-3001
Non-Revised Drawings
13-203-2002
13-212-3007
13-203-3005
13-212-3008
13-203-3008
13-212-3009
13-203-3013
13-212-3010
13-203-3014
13-212-3013
13-207-3001
13-212-3014
13-207-3002
13-212-3015
13-207-3003
13-212-3016
13-207-3004
13-212-3017
13-207-3005
13-212-3018
13-207-3006
13-212-3019
13-207-3007
13-212-3020
13-207-3008
13-212-3021
13-207-3009
13-212-3022
13-207-3010
13-212-3023
13-207-3011
13-212-3024
13-207-3012
13-212-3025
13-207-3013
13-222-3001
13-207-3014
13-222-3002
13-212-3001
13-222-3003
13-212-3002
13-222-3004
13-212-3003
13-222-3006
13-212-3005
13-222-3007
13-212-3006
13-222-3008
13-222-3009
13-222-3010
13-222-3011
13-222-3012
13-222-3013
13-228-3002
13-228-3004
13-228-3005
13-228-3007
13-228-3010
13-228-3011
13-228-3012
13-229-3001
13-229-3002
13-229-3003
13-229-3004
13-229-3005
13-229-3006
13-229-3007
13-229-3008
13-229-3009
13-229-3010
13-229-3011
13-229-3012
13-243-3003
13-243-3004
13-243-3005
13-243-3006
13-243-3007
13-243-3008
13-243-3009
13-243-3010
13-244-3001
13-244-3002
13-244-3003
13-244-3004
13-244-3005
13-244-3006
13-244-3007
13-244-3008
13-299-3001
13-299-3002
13-299-3003
143
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
13-207-2004
13-212-2001
13-212-2002
13-212-2003
13-212-2004
13-212-2005
13-217-2001
13-217-2002
13-229-2001
13-229-2002
13-243-2201
13-243-2202
13-243-2203
13-243-2204
13-217-3002
13-217-3003
Revised Drawings
13-223-3001
13-203-3102
13-223-3002
13-203-3105
13-223-3003
13-228-2001
13-236-3801
13-228-2002
13-241-3821
13-203-3003
13-245-3841
13-203-3004
13-246-3881
13-212-3004
13-203-3101
13-212-3011
13-212-3012
13-222-3005
13-228-3001
13-228-3003
13-228-3006
13-228-3008
13-228-3009
13-239-3003
13-203-3006
13-203-3007
13-203-3009
13-203-3010
13-203-3011
13-203-3012
13-231-3003
Maintenance Building:
This building consists of one-story reinforced concrete frames infill with brick walls. The
building has been modeled as a three-dimensional frames using ready-made package program
STAAD Pro. The design was carried out according to BS8110. The building was analyzed
under several load combinations of dead, live, and earthquake loads. The foundation consists
of separate footing connected together using under ground beams.
Administration Building
This building consists of one-story reinforced concrete frames infill with brick walls. The
building has been modeled as a three-dimensional frames using ready-made package program
STAAD Pro. The design was carried out according to BS8110. The building was analyzed
under several load combinations of dead, live, and earthquake loads. The foundation consists
of separate footing connected together using under ground tie beams.
This building consists of one-story bearing brick walls. The design was carried out according
to BS8110. The building was analyzed under load combinations of dead and live loads. The
foundation consists of continuous strip footing.
8.5.2
Process Buildings
Raw Water Intake
The raw water intake structure is a pier structure with a reinforced concrete deck, steel
support columns and a frame designed to support the steel intake screen assemblies. The
identical screens are cylindrical wire-wound devices which are cleaned by an air burst
cleaning system. The screen cylinders may be lifted from their normal position to a
maintenance position via vertical guide rails on the pier. A manually operated jib crane with a
motorized hoist is used to lift the screens. The jib crane can traverse in order to transfer a
screen onto or off of a small truck which can access the end of the pier. The screens, which
are installed below the minimum expected river level, are protected from contact by water
craft and large debris by submerged piles on their upstream sides.
The raw water pumping station (RWPS) is located on the river bank. It consists of an above
ground pump room, two electrical rooms and an operators room. The pump room is located
144
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
above the wet well. The pier structure supporting the intake screens extends out from the bank
into the river and runs along the north side of the RWPS. The inlet pipes from the screens
terminate in the wet well.
The RWPS structure is reinforced concrete below grade. Above grade the structure is
composed of reinforced concrete beams and columns with non-load-bearing masonry walls.
The roof is a reinforced concrete slab.
Major equipment housed in the building are the raw water pumps, the screen cleaning air
compressor, the electrical switchgear, the motor control centre (MCC) power panels and local
control panels. The substation transformers, standby diesel generator and fuel storage tank
are located outside adjacent to the RWPS.
Chemical Disperser
Alum is mixed with the raw water via an in-line chemical disperser equipped with a direct
driven agitator with electrical motor, coagulant distribution manifold with isolating and nonreturn valves, and vanes to aid dispersion all located in the raw water pipe upstream of the
flocculators. The disperser is contained in a below ground chamber which also contains a bypass and isolating valves.
Clarifiers
Raw water is pumped from the RWPS to the clarifiers, entering the splitter box located at the
head end of the structure. There are two identical flocculation/clarification trains. Each train
contains three flocculation chambers and a clarifier chamber. Raw water flows through the
three baffled flocculation chambers where it is slowly mixed to encourage flocculation. The
water then enters the lamella clarifier chamber in which the flocculated solids settle out, and
are discharged under head to the wastewater tank. The clarifier effluent streams join in a
common outlet channel which becomes the common inlet channel for the filters.
The entire structure is reinforced concrete and open at the top. The trains share a common
centre dividing wall and cannot be cross-connected downstream of the splitter.
Major equipment located in the structure are the flocculator mixers, lamella separation units,
clarifier scrapers, power panels and local control panels.
Filter Building
The filter building is located downstream of the clarifiers. It consists of the common inlet
channel, five filter chambers, the common backwash channel, the common filtered water
channel, the clean wash water tank, the pipe gallery, and the operating floor. Each filter
chamber consists of filter media, backwash launders, under drains and backwash channels.
The control room, air scour blowers, service water pumps, service water tanks, and sample
pumps area are all located on the operating floor which is located above the pipe gallery. The
main control console is located in the control room. The backwash pumps are located in the
pipe gallery.
Settled water enters the common inlet channel and is routed to each of the five filter units via
a motor-operated penstock, the filter inlet weir and a scour-avoiding baffle wall. The water
passes through the dual-media filter to the under drain area below the nozzle floor. From the
under drain area the filtered water enters the filtered water pipe which passes through the pipe
145
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
gallery and discharges into the filtered water channel via a weir box. The filtered water
channel is connected to the chlorine contact tank via yard piping.
The clean wash water tank is filled via a motorized weir from the common filtered water
channel. The backwash pumps take suction on the clean wash water tank and discharge into
the individual filtered water pipes. When the filter is backwashed, dirty wash water enters the
launders above the filter media and flows into the backwash channel which is separated from
the filter media by the backwash weir. From the backwash channel, dirty wash water flows
into the common backwash channel via a motor-operated penstock where it gravitates to the
wastewater holding tank via yard piping. Following backwashing, the filters may be ripened
and the rinse water produced during this process is diverted from the individual filtered water
pipes to the wastewater holding tank.
The filter building structure is reinforced concrete below grade and above grade up to the top
of the filters and the operating floor. Above the filters and operating floor, the structure is
composed of reinforced concrete beams and columns with non-load-bearing masonry walls.
The roof is a reinforced concrete slab. Under drain access is via a manway from the pipe
gallery.
Additional equipment housed in the building include power panels, local control panels, and
the traveling crane.
The chlorine contact tank (CCT) is located downstream of the filters. It tank consists of two
mirrored chambers and a pipe gallery. Filtered water, injected with chlorine enters pipe
gallery from the yard where the flow is split to each contact tank. Treated water makes its way
down the U-shaped tank and overflows a weir to the outlet sump. From the outlet sump, the
flows are combined into a single outlet pipe in the pipe gallery. There is a valve chamber at
the opposite end of the tank from the pipe gallery which also serves as an overflow chamber.
The structure is located below grade, is covered and constructed entirely of reinforced
concrete.
Treated water flows from the CCT to the treated water storage tank (TWST) via yard piping.
The TWST is a two-chamber, reinforced concrete tank located partially below grade. The
structure is covered and constructed entirely of reinforced concrete.
The treated water pumping station (TWPS) consists of a pump room located above a twochamber wet well. Treated water flows from each chamber of the TWST to the TWPS wet
wells via two short yard pipes. Each wet well chamber serves two treated water pumps.
The TWPS structure is reinforced concrete below grade. Above grade the structure is
composed of reinforced concrete beams and columns with non-load-bearing masonry walls.
The roof is a reinforced concrete slab.
Additional equipment housed in the building include power panels and local control panels.
Chemical Building
The chemical building consists of the alum storage area, two alum mixing chambers and a
room for installation of a future polyelectrolyte system.
146
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The structure is composed of reinforced concrete slab-on-grade, beams and columns with
non-load-bearing masonry walls. The roof is a reinforced concrete slab. The mixing
chambers are constructed of reinforced concrete.
Bagged alum is loaded into crane-mounted hopper and dumped via an inlet basket into the
mixing chambers. The alum is dissolved in water supplied by the service water system. Each
chamber has a single motor-driven mixer with an adjustable-speed gearbox. The alum
solution is pumped into the raw water pipeline upstream of the flash mixer by two dosing
pumps. Either dosing pump can draw from either mixing chamber. Additional equipment
housed in the building includes a manually-operated crane, power panels and local control
panels.
Chlorine Building
The chlorine building consists of the chlorine drum storage area, the equipment room, and the
chlorinator room. The chlorine scrubber system is located outside adjacent to the chlorine
building. Chlorine drums are loaded and unloaded with a traveling crane equipped with a
motorized hoist. Liquid chlorine is vaporized and metered to the raw water ejector where it
dissolved in motive water, supplied by motive water pumps which draw from the common
filtered water channel. The building is ventilated to a chlorine scrubber system which
neutralizes atmospheric chlorine with a recirculation caustic soda solution.
The structure is composed of reinforced concrete slab-on-grade, beams and columns with
non-load-bearing masonry walls. The roof is a reinforced concrete slab. Additional
equipment housed in the building include power panels and local control panels.
The electrical MCC building consists of two electrical rooms, one containing the main 11KV
switchgear and the other containing the MCC, associated electrical components, and power
panels.
The structure is composed of reinforced concrete slab-on-grade, beams and columns with
non-load-bearing masonry walls. The roof is a reinforced concrete slab. Additional
equipment located outside adjacent to the building include the two main substation
transformers, the standby diesel generator and fuel storage tank.
Wastewater flows from the flocculator/clarifiers and filters to the wastewater holding tank
(WWHT) via yard piping. Minor process drains also flow from other process buildings to the
WWHT. Tank contents are prevented from settling by a motor-driven mixer equipped with a
variable speed gearbox.
The WWHT is a single-chamber, reinforced concrete tank located partially below grade. The
structure is partially covered and constructed entirely of reinforced concrete.
The wastewater pumping station (WWPS) consists of a pump room located adjacent to the
WWHT Three wastewater pumps transfer wastewater from the WWHT to the river outfall via
the wastewater pipeline.
The WWPS structure is reinforced concrete below grade. Above grade the structure is
composed of reinforced concrete beams and columns with non-load-bearing masonry walls.
The roof is a reinforced concrete slab.
147
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
9. ANCILLARY WORKS
The main ground investigation undertaken at Dujailah site was carried out between 27th to
30th of October 2007. The investigations include sinking exploratory holes, performing insitu
testing and laboratory testing on selected samples.
The purpose of the investigation was to obtain information on the ground and ground water
condition at the proposed site and the physical, mechanical and chemical properties of the
foundation materials to enable the design and construction of the proposed structures.
The scope of the site works comprised drilling a total of six boreholes in the proposed
treatment plant and intake. Location and depth of each borehole are presented in the following
table:
Borehole No.
Location
BH1
Treatment Plant
20
BH2
Treatment Plant
20
BH3
Treatment Plant
15
BH4
Intake
15
BH5
Treatment Plant
10
BH6
Treatment Plant
10
148
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
149
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Test
No. of tests
Atterberg Limits
LL and PL
Classification
Grain Size
Sieve
Analysis
Hydrometer
13
Testing
Standard
ASTM D 4318
18
ASTM D 422
12
BS 1377: 1990
Specific Gravity
25
36
ASTM D 2216
Unit Weight
19
BS1377:1990
Unconfined
ASTM D 2850
ASTM D2166
ASTM D3080
ASTM D2435
Part 2
Physical properties
Strength
Compressibility
Chemical
25
25
BS 1377: 1990
25
Gypsum Content
25
Manual
Chloride Content
25
9.1.3
BS 1377:1990
Part 3
Stratigraphy
The test borings showed that the site is covered with agricultural soil consists of clayey silt
with organics and roots. This layer extended to a depth of about 0.4m from the natural ground
level. From the soil profile it can be seen that the silty CLAY to clayey SILT and sandy silty
CLAY material is the most abundant constituent of the soil sequence with pockets and thin
layers of silty SAND to silty or clayey SAND occur at different places of most boreholes. In
general speaking it can be seen that the cohesive soil can be found at the upper layer of up to
5.0 meter from the natural ground level. On the other hand a thick layer of cohesionless soil
was noticed at a depth of 5.0 to 10.5m at some places (see Fig. 9.1.2).
150
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
9.1.4
Groundwater
Groundwater was encountered in all of the boreholes during drilling at level varies from 2.60
to 2.95 m.b.g.l at the treatment plant site. The ground water level at intake site (B.H.4) is 2.90
m.b.g.l.
Figure 9.1.2 (a): Soil Profile for BH1, BH2 and BH3.
Figure 9.1.2 (b): Soil Profile for BH5, BH6 and BH1.
151
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
9.1.5
Atterberg Limits: The results of Atterberg limits and indices as well as some
physical properties are given in Table 9.1.2. According to the Unified Soil
Classification System, most of the cohesive soil are clayey soil with low plasticity
(CL).
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Values of Activity in Table 5.1 less than 0.75 are termed inactive clays. Normally
active clays have activities between 0.75-1.25. The samples with activity more
than 1.25 are active clays.
Depth (m)
B.H.
No. From
0.3
1.5
2.5
4.5
6.0
7.5
8.0
10.5
11.0
15.0
15.5
18.0
19.5
1.5
2.0
6.0
6.5
10.5
14.5
15.0
19.5
1.5
2.0
2.5
4.5
5.0
5.5
To
1.5
2.0
3.0
5.0
7.5
8.0
9.0
11.0
11.5
15.5
16.0
19.5
20.0
2.0
2.5
6.5
7.0
11.0
15.0
16.5
20.0
2.0
2.5
4.5
5.0
5.5
7.5
Gs
Atterberg
Limits
LL PL PI
Consistency
LI
2.74
29.71
29
31
2.64
2.73
21.22 2.74
18.7
25.26 2.76
26.76
2.61
29.77 2.77
24.44
26.68
21.37
27.35 2.77
24.17 2.79
20.28 2.80
2.67
21.37
25.05
32.65 2.71
20
20
9
11
SP-SC
87
11
SP
93
CL
49
44
CL
CL
0
0
7
25
76
72
17
3
SP-SC
89
CL
1
1
13
93
25.2
33
22
11 0.647
0.222
28
20
0.171
45
20
25
0.202
24.32
24.02
SP-SM
60
26
6
2.64
153
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Depth (m)
B.H.
No. From
9.0
9.5
12.0
14.5
1.5
2.0
4.5
5.0
9.0
9.5
10.0
12.0
14.5
0.3
1.5
2.0
2.5
4.5
5.0
9.0
9.5
1.5
2.0
2.5
4.5
5.0
7.5
9.5
To
9.5
10.0
14.5
15.0
2.0
2.5
5.0
5.5
9.5
10.0
12.0
14.5
15.0
1.5
2.0
2.5
4.5
5.0
5.5
9.5
10.0
2.0
2.5
4.5
5.0
5.5
9.0
10.0
Gs
Atterberg
Limits
LL PL PI
18.38
31.11 2.79
2.68
27.51
18.86 2.75
25.00
22.96
25.65 2.68
Consistency
A
LI
32
31
21
19
11
12
0.919
41
20
21
-0.054
36
30
19
22
17
8
0.233
0.456
SP-SC
88
CL
SP-SC
0
1
2
90
57
7
41
2
SP
92
CL
69
27
CL
16
70
14
SP-SM
CL
1
0
91
14
6
69
2
17
CL
90
89
SP
96
26.43 2.78
2.68
2.79
30.78
31.34
23.68 2.77
19.72
23.08 2.65
2.71
22.31 2.77
31.44
32.3
2.72
21.6
28.86 2.80
2.64
22.66 2.71
40
22
18
29
21
28
20
0.519
n P .L.
P.I .
P .I .
clay fraction
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
10
15
20
25
30
35
40
45
50
55
1
2
3
4
5
6
7
Depth, m
8
9
10
11
12
13
14
15
16
17
18
19
20
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Consolidation test were carried out to assess the compressibility of the soil. The
overconsolidation ratio OCR is slightly greater than 1.0. So the soil is slightly
overconsolidated to normally consolidated.
Values of compression index and swelling index are shown in Table 9.1.4. The ranges of
compression index varies from 0.147 to 0.217 and swelling index (0.017 to 0.023).
Table 9.1.3 Results of Shear Strength Tests
Shear Test
BH
No.
1
2
3
Depth
(m)
t
kN/m3
n
%
1.5-2.0
19.28
19.53
19.87
19.00
20.00
19.60
19.05
19.95
18.96
19.77
19.92
19.00
20.50
21.06
19.73
20.18
19.98
29.71
21.22
25.26
24.44
21.37
25.05
24.32
18.38
18.86
22.96
26.43
31.34
19.72
24.65
31.44
21.60
26.85
10.5-11.0
15.0-15.5
1.5-2.0
6.0-6.5
1.5-2.0
4.5-5.0
9.0-9.5
1.5-2.0
4.5-5.0
9.0-9.5
1.5-2.0
4.5-5.0
9.0-9.5
1.5-2.0
4.5-5.0
9.0-9.5
Direct Shear
C
kPa
0.0
13.3
0.0
36.8
10.6
0.0
0.0
0.0
0.0
38.7
34.8
33.2
19.8
35.8
36.0
44.7
39.7
42.3
UCS
kPa
166.3
225.0
100.1
93.7
96.3
-
Triaxial (UU)
C
kPa
60.7
36.8
33.3
-
4.7
3.7
2.3
-
9.1.8
Depth
(m)
10.5-11.0
15.0-15.5
Pc
Po
n
mv
cv
eo
cc
cs
OCR
t
2
2
%
m /MN m /year kPa kPa
3
kN/m
19.96 21.22 0.664 0.147 0.017 0.137
6.03
145 130.1 1.11
20.08 25.26 0.707 0.217 0.023 0.140
4.23
175 148.8 1.17
Both soil and groundwater samples were analyzed for sulphate and chloride content. Samples
were taken from the majority of boreholes at varying depths. pH and TDS were also analyzed
for water. The results are summarized in Table 9.1.5.
156
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
It can be seen that the range of sulphate (SO3) in most of soil samples tested is between 0.55
and 1.48% and the range of sulphate (SO4) in water between 247 and 314 mg/l. The range of
chloride content is 200 to 2200 mg/l for soil samples and 300 to 400 mg/l for water samples.
The range of pH values for water samples were 7.1 to 7.7. Organic matters of the soil samples
were vary from 0.2 to 4.5. According to the requirement for concrete exposed to sulphate
containing solutions, it is recommended to use sulphate-resisting cement (maximum watercement ratio by weight is 0.45 and minimum fcu is 35 MPa). Also, due to high chloride
content in some places, protection of the foundation by bitumen martial is recommended.
Table 9.1.5 Results of Chemical Analysis
Depth (m)
BH
No. From To
0.3
7.5
8.0
18.0
19.5
6.5
10.5
14.5
17.0
2.0
5.5
9.5
12.0
5.0
9.5
10.0
12.0
2.0
5.0
9.0
9.5
2.5
5.0
7.5
9.5
Soil
O.C.
Cl
TSS
% (mg/l) %
1.5
1.7
2100 1.9
8.0
0.6
1800 2.5
9.0
2.0
1600 3.0
19.5 4.5
650
4.0
20.0 3.7
1100 2.8
7.0
0.6
300
2.5
11.0 0.7
200
4.5
15.0 0.2
300
4.5
19.5 1.8
400
3.0
2.5
2.3
200
5.1
7.5
2.4
300
3.3
10.0 2.1
300
4.5
14.5 3.3
300
2.5
5.5
0.2
200
4.2
10.0 1.0
400
3.6
12.0 1.1
500
3.0
14.5 2.5
300
2.5
2.5
1.0
400
3.5
5.5
0.5
600
2.9
9.5
1.5
2200 3.2
10.0 0.2
1700 5.5
4.5
1.8
1300 4.5
5.5
1.3
1300 2.5
9.0
0.6
800
2.5
10.0 2.7
2100 2.6
-
SO3
%
0.63
0.91
0.68
0.91
0.80
0.81
1.02
1.25
0.57
1.14
0.55
1.25
0.68
0.91
0.68
0.59
0.57
0.92
0.81
0.80
1.14
1.48
0.82
0.91
0.92
Water
Gypsum
Cl
SO3
SO4
TDS
pH
%
(mg/l) (mg/l) (mg/l) (mg/l)
1.35
1.96
7.4 300
262
299
858
1.46
1.96
1.72
1.74
2.19
7.2 300
275
314
1160
2.69
1.23
2.45
1.18
7.7 400
264
302
920
2.69
1.46
1.96
1.46
7.2 300
258
295
844
1.27
1.23
1.98
1.72
7.1 400
248
283
1100
1.72
2.45
3.18
1.76
7.5 300
216
247
1166
1.96
1.98
-
The foundation types for the proposed buildings are dependent upon the size of the structures,
the anticipated loads and the allowable bearing pressure.
157
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
qnf = 5 1 + 0.2
1 + 0.4 cu ..1
B
L
Where:
Df = depth of footing
B = width of footing
L = length of footing
cu = undrained cohesion
For cohesionless soil, the net allowable bearing capacity, qa can be calculated from the
following eq.:
N B + 0.3
D
qa =
1 + 0.33 ..2
0.08 B
B
2
Where:
N: number of blows from SPT
D: depth of footing, m
B: width of footing, m
The safe bearing pressure may be determined using a factor of safety of 3 against shear. The
safe bearing pressure would be 80 kPa at a depth of 1.5 m.
The soil is slightly overconsolidated to Normally consolidated soil. Accordingly, the
consolidation settlement could be calculated using the following equations:
sc =
p + p
cc H
...3
log o
1 + eo
po
Where
Sc = consolidation settlement
cc: compression Index
H: thichness of compressible layer
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
p = stress increment
eo= initial void ratio
The recommended value of cc and eo for design purposes is 0.217 and 0.707 respectively.
To avoid excessive settlement, the allowable pressure at a depth 1.5m is 80 kPa for the water
treatment plant and intake site.
9.1.9.2 Shallow Foundations
It is anticipated that shallow foundations (spread footings and/or wall footings) placed within
a depth 1.5 m are generally considered appropriate for the non-process buildings such as
residual houses. Raft foundation is recommended for relatively lightly loaded process
building structures.
Preparation for shallow footings would require removal of undesirable material underneath
footing. However, at least 50 cm of soil underneath footings should be replaced with well
compacted subbase material.
9.1.9.3 Pile Foundations
The use of precast or bored cast in place pile foundation is considered appropriate for
supporting the relatively heavier structural loadings.
For the site of the treatment plant the piles will require to be designed to support the axial
compression, tension and resist lateral loading. Using precast piles, the group action should be
considered in the design of pile group. The estimated uplift resistance of the Precast, Franki
and Bored pile is 150, 250 and 300 kN respectively. The estimated working loads for the piles
12 m long are as follows:
Type of pile
Precast pile 28.5*28.5 cm
Franki pile 50 cm dia.
Bored pile 60 cm dia.
Working load, kN
300-350
500-550
600-650
The estimated lateral resistance of the above Precast, Franki and Bored pile is 30, 50 and 60
kN, respectively. The working load should be confirmed by carrying out pile load tests.
For the intake site the use of H-steel piles is considered appropriate for supporting the intake
structure. Other types of piles such as steel tube piles may also be used. The piles are required
to to support axial compression, tension and resist lateral loading.
The recommended working loads for the piles 10 m embedded length in the soil, are as
follows:
Type of pile
Working load, kN
Tension Capacity, kN
HEA 300
(200-250) 25
100
HEA 400
(300-350) 25
150
159
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
The lateral resistance of piles may be taken equal to 20 kN for HEA 300 and 30 kN for HEA
400 piles respectively.
9.1.9.4 De-watering
The site investigation data shows that groundwater level varies between 2.60 to 2.95 m.b.g.1.
at the treatment plant site and 2.90 m.b.g.1. at the intake site. It may also be affected by
seasonal variations.
For the safe excavation of shallow foundations below this level, de-watering will probably be
required. Groundwater control measures could take the form of local de-watering by the
construction of perimeter drains and sump pumping.
For deep excavation, such as the underground storage tank, de-watering will certainly be
required.
Due to the anticipated depth of excavation for constructing the underground storage tank, it is
recommended that well points be installed in the proposed excavation area.
Potential uplift pressures to the underside of proposed structure should be taken into account
in the final long-term design of the structure.
9.1.10 Suitability of Materials for Re-use
The proposed site has different type and function of structures. Removal or addition of other
materials may be required, and an estimation of the compaction characteristics can be made.
From the basic soil properties the maximum dry unit weight is in the range of 18.0 to 19.8
kN/m3 and the range of optimum water content varies between 9.0 to 15.0 %.
Examination the results of chemical and physical properties, these results suggest that the
excavated material will be suitable for re-use in the earth works if needed. Compaction should
be in accordance with Highway Specification.
9.1.11 Summary of Design Parameters
The soil parameters summarized in Table 9.1.6 are recommended for the design of
foundations and earth retaining structures.
Table 9.1.6: Recommended Values of the Design Parameters
Unconfined Compressive Strength at a depth (1.0-2.0) m
80 kPa
33 degree
Compression Index
0.217
Swelling Index
0.023
0.707
19.6 kN/m3
9.8 kN/m3
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
1.0
Ka = Kp = Ko
1/3
1
Kp
0.5
Ko
9000 kN/m3
50 kPa
30
Bored Piles
0.45
Precast Piles
0.60
9.1.12 Conclusions
Geotechnical investigations were carried out for the Dujailah site. A total of six
boreholes were drilled, five boreholes were drilled at the treatment plant site
and one borehole was drilled at the intake location.
In-situ standard penetration tests were carried out. Laboratory tests were
undertaken to determine Atterberg limits, grading, shear strength parameters,
void ratio-effective stress relationship (consolidation tests), chemical tests for
soils (sulphate, organic content, total soluble salts, gypsum and chloride) and
chemical analysis for water (pH, Cl, SO4 and TDS).
Ground conditions encountered in the exploratory holes showed that the silty
CLAY to clayey SILT material is the most abundant constituent of the soil at
the upper layer with thin layers and pockets of sand. Also a layer of sandy soil
was found at different locations in the investigated area.
Groundwater levels have been recorded. The groundwater table is 2.60 and
2.95 m.b.g.l below natural ground level at the treatment plant and 2.90 m.b.g.l
at the intake site.
Chemical tests carried out during the site investigation indicate sulphate
concentration SO4 in the groundwater of between 247 and 314 mg/l and the
range of chloride content was 300 to 400 mg/l. It is recommended to use
sulphate-resisting cement, maximum water-cement ratio by weight is 0.45 and
minimum fcu is 35MPa. Due to high salt content in some places, protection of
the foundation by bitumen martial is recommended.
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
162
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
All pavement designs for Iraqi roads must use the most cost-effective design that meets the
objectives of the project and all applicable design standards. All pavement designs for these
roads must be developed using a recognized design procedure.
Examples of acceptable procedures include, but are not exclusive to:
1993 AASHTO Guide for Design of Pavement Structures and Supplements
The Asphalt Institute
Portland Cement Association
American Concrete Pavement Association
The design criteria and procedures presented in this report follow American Association of
State Highway and Transportation Officials (AASHTO) 1993 Guide for the Design of
Pavement Structures. The type of pavement which has been adopted in the Wasit Water
Treatment Plant is flexible pavement.
9.2.2 Aim of Report
The purpose of this report is to present the Roads Structural Design Criteria required for use
on all roads in the Wasit Water Treatment Plant.
9.2.3 Scope of Report
This report contained articles that describe some terms which will be mentioned later. The
parameters for AASHOTO design procedure will be presented in this report. Beside, a design
example will be provided in this report.
9.2.4 Structural Components Of a Flexible Pavement
Flexible pavement usually consists of asphalt surface underlaid with a layer of either an
asphalt material or granular material and followed by a layer of suitable mixture of coarse and
fine materials.
Traffic loads are transferred by the wearing surface to the underlying supporting materials
through the interlocking of aggregate, the frictional effect of the granular materials, and the
cohesion of the fine materials.
Subgrade
For all subgrade soil types, the subgrade under the subbase course must be compacted to a
minimum depth of 15 cm. If the densities of the natural subgrade materials are equal to or
greater than 95 percent of the maximum density from ASTM D 1557, no rolling is necessary
other than that required to provide a smooth surface. Compaction requirements for cohesive
soils (LL > 25; PI > 5) will be 95 percent of maximum density for the top 15 cm of cuts and
the full depth of fills. Compaction requirements for cohesionless soils (LL < 25: PI <5) will
be 95 percent for the top 15 cm of cuts and the full depth of fills. Compaction of the top 6
inches of cuts may require the subgrade to be scarified and dried or moistened as necessary
and recompacted to the desired density.
Subbase Course
The subbase course may consist of natural, processed, or stabilized materials. The material
selected should be the one that best accomplishes the intended purpose of the subbase course.
163
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Gradation requirements:
50
25
9.5
4.75
2.0
0.425
0.075
% finer
100
75-95
40-75
30-60
20-45
15-30
5-15
Asphalt Cement
(ASTM D 1883)
Asphalt cement shall be of uniform consistency, free from water to the extent that it will not
foam when heated to three hundred fifty degrees (350) F., and it shall meet the following
requirements for physical and chemical properties:
Agg.Max. Size : 20 mm
The material presented in this article relates to the AASHTO Pavement Design Procedure.
Traffic Analysis
164
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
For pavement designs, a traffic analysis must be performed in order to obtain an expected
value for 18 kip (80 kN) equivalent single axle loads (ESALs) over the structural design life
of the section. In order to estimate design ESALs the Designer must know the average daily
traffic (ADT), percent trucks, vehicle class distribution, and an annual growth rate or
expansion factor.
To calculate the design ESALs, the daily truck counts from each axle group are multiplied by
a conversion factor to arrive at an annual ESAL value. The annual ESALs from each axle
group are summed to arrive at a total annual ESAL value. Using the annual growth rate, the
ESALs must first be expanded to the year of construction and then forecasted to the end of
the design life. The design ESALs are simply the sum of the annual ESALs through the
design life, starting with the year following construction.
An important factor in many pavement design methods is the resilient modulus (MR) of the
subgrade soil. A discussion on roadbed soil can be found in Part 1, Section 1.5 of the 1993
AASHTO Guide for Design of Pavement Structures. Selection of a value for subgrade MR is
a critical step in the AASHTO Pavement Design Procedure.
Reliability
The level of reliability for the pavement design must be selected in accordance with the
pavement design procedure used.
Serviceability
Part 2, Section 2.2.1 of the 1993 AASHTO Guide for Design of Pavement Structures provides
a discussion on serviceability. Typical values for initial serviceability are 4.5 for rigid
pavement and 4.2 for flexible pavement. For terminal serviceability, AASHTO recommends
2.0 2.5 for low volume roads (<3,000 ADT), 2.5 3.0 for medium volumes (3,000 10,000
ADT) and 3.0 3.5 for high volumes (>10,000 ADT).
Overall standard deviation is a design input for the AASHTO procedure that takes into
account uncertainty in traffic estimation and varying construction materials and conditions.
AASHTO recommended values are included in Part 1, Section 4.3 of the 1993 AASHTO
Guide for Design of Pavement Structures.
9.2.6 Asphalt Concrete Design Requirements
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
SN value is structural number which will be used in determining the thickness of each layer
and according to the equation:
SN=a1*D1 +a2 *D2 +a3*D3
Where a1,a2 and a3 are the layers coefficients for surface(two layers), base and subbase
respectively. D1,D2 and D3 are the thickness for the same layers in inches.
9.2.7 Flexible Pavement Design (1993 AASHTO Pavement Design)
Initial Serviceability, po
Terminal Serviceability, pt
Reliability Level, R
Overall Standard Deviation, So
Performance Period
4.2
2.5
90%
0.45
20 years
AADT
% Heavy Trucks
Heavy Trucks Factor
Year
Days
Directional Distribution, %
Design Lane, %
100
40
4
20
365
100
100
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Layer
1
2
3
4
Material
HMA Type 3,
Wearing Course
HMA Type 2,
Binder Course
HMA Type 1,
Base Course
Granular Material,
Subbase
Layer
Coefficient
Drainage Thickness,
Coefficient
cm
Layer
Structural
Number, SN
0.44
0.86
0.4
1.10
0.35
10
1.37
0.11
40
1.73
167
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
168
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Report/fd
Detailed Design Report
F249A
20/07/07
Wasit Detailed Design
c.a.:
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Impact
Air quality
Construction
Magnitude
-
Noise
-/0
Traffic
-/- - -
Surface
water
-/- -
Soil and
groundwater
Biological
environment
Socioeconomics
- -/+
Cultural
heritage
0/- -
Health and
safety
Landscape
and visual
intrusions
-/- -
Solid waste
generation
-/- -
Comment
Release of high levels of particulate matter (PM) generated from land clearing, excavation, & cut & fill operations
Construction equipment on-site are expected to release vehicular induced pollutants (carbon monoxide (CO),
nitrogen oxides (NOx), sulfur oxides (SOx), particulate matter (PM) and hydrocarbons (HCs))
Noise is expected to be generated as a result of ground clearing, excavation, foundations, erection, and finishing
Installing the water network is expected to sever routes and cause traffic jams in the areas that will be serviced
Transportation of construction equipment and materials is expected to impact the traffic flow to and from the site
Movement of heavy construction machinery may impact traffic movement particularly in small rural areas that
have traffic networks not suitable for such machinery
Increase in turbidity of nearby surface water bodies as a result of soil erosion from excavation works
Accidental chemical leakage or spillage resulting from lining, cleaning work, and other similar activities
Accidental leakage or spillage of construction chemicals, and fuels
Local soil erosion can result from excavation works
Excavation and earth removal activities may render slopes and topsoil more vulnerable to landslides and erosion
Noise impacts, increased physical activities on the land, and vegetation modification may impact the existing
biodiversity by affecting animal behavior and inhibiting mating, breeding, nesting, and feeding-foraging activities
Disturbance to streams, aquatic plant and animal habitats, and spawning and nursery areas
The execution of the project is expected to provide local job opportunities
The project may temporarily damage the infrastructure in serviced areas thus causing economic & social hardships
The project should not cause land acquisition, resettlement, and property take
Damage to known archeological/cultural sites
Destruction of unknown archeological/cultural sites
Health and safety issues related to construction activities are mainly related to accidents resulting from the
improper handling and storage of construction material
Accidents occurring with the operation of heavy equipment
Presence of equipment or material, soil heaps, and borrow pits present an unsightly view
Excavation and earth removal activities render slopes and topsoil more vulnerable to landslides and erosion
Unplanned development induced or facilitated by infrastructure
Disturbing activities and infrastructure in urban and rural areas as a result of network layout
Construction activities are inherently associated with the generation of wastes such as rocks, dredged/excavated
sediment, construction waste, chemical waste, and general refuse
169
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Phase
Impact
Air quality
Noise
Surface
water
Magnitude
-/0
-/- --
Soil and
groundwater
- -/+ +
Biological
environment
Operation
Socioeconomics
Solid waste
generation
Traffic
+ +/- -
Health and
safety
- - -/+ + +
Landscape
and visual
intrusions
Comment
Pollutant emissions from the operation of power generators to power pumping and treatment works
Noise may be generated from the operation of the pumping stations, motors, and generator(s)
Alteration in watershed hydrologic balance when water is pumped to feed water network
Pollution risk to surface water bodies in case the wastewater infrastructure is not developed concurrently with the
water supply network due to the expected increase in water use (in case wastewater discharge is destined to open
surface water bodies)
Pollution risk to groundwater and soil in case the wastewater infrastructure is not developed concurrently with the
water supply network due to the expected increase in water use (in case open wastewater discharge or cesspools
are still in use)
Increased salt water intrusion and depletion of aquifers in the areas that are tapped unsustainably for groundwater
(not applicable in this case)
Reduction in groundwater tapping by the general public as a result of providing a steady and safe water supply
Possibility of increasing the level of the water table in areas that experience leakage
Biodiversity may be impacted if water is diverted from sensitive areas or in case groundwater is exploited
unsustainably (salt water intrusion and/or a drop in the water table not applicable in this case))
Perceived or actual nuisances and adverse aesthetic impacts from pumping and water distribution works
Availability of a steady water supply will help industrial, tourist, commercial, and agricultural sector to prosper
Availability of a steady & safe water supply will reduce expenditure of the serviced population on water purchase
Decrease in the business of water vendors in the serviced areas
Uncontrolled migration of people into area, made possible by access roads and enhanced infrastructure
Creation of local job opportunities
Generation of empty chemical containers (chlorination containers, oils, lubricants, etc.) and damaged parts
Disruption of traffic in case of maintenance
Proper operation of the water network is expected to reduce health risks associated with the consumption and/or
use of low quality water sources. Decreased water borne diseases as a result of providing treated water supply.
Worker accidents caused by chlorination (or other disinfection techniques) in confined spaces
Serious public health hazard in case of improper treatment and disinfection or in case network is not properly
monitored or maintained
Complimentary structures such as inlet/outlet pipes and extension network may interfere with the natural setting of
the overall scenery
170
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Air quality
Noise
Traffic
Design/ Construction
Water surfaces
Use chemicals to treat exposed surfaces
Install windbreaks or source enclosures to reduce surface
wind speed
Pave heavily-used roads
Cover road surfaces with a new material of lower silt content
Maintain roads regularly
Maintain good housekeeping practices
Properly maintain trucks and on-site equipment
Adopt a traffic management plan to avoid congested routes
Ensure quality of diesel fuel used with on-site equipment
Turn off all equipment when not in use
Erect noise barriers along active work sites
Install vegetative screens
Operate on-site well-maintained mechanical equipment only
Shut down equipment that may be intermittent in use between
work periods or throttle them down to a minimum
Utilize silencers or mufflers on construction equipment
Properly maintain construction equipment
Use material stockpiles and other structures to screen noise
from on-site construction activities
Schedule noisy activities during daytime periods
Study possibility of construction during night hours
Disseminate information regarding construction schedule
Guide motorists through construction zones in a clear and
safe manner (adequate warning, signing, delineation and
channeling at least 500 m down and up-gradient from site)
Develop and communicate preliminary routing schemes
Limit the movement of heavy machinery to off-peak hours
Provide a traffic management plan for the impacted area
Operation
Use low sulfur content fuel to operate power generators
Use high efficiency water pumps and motors
Install mufflers and noise barriers around the air blowers and
pumps
Enclose noisy equipment
Underground or indoor housing of noise generating point
sources
171
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Impact
Surface water
Soil and
groundwater
Design/ Construction
Adopt a rolling construction program to minimize disruption
to infrastructure
Proper surface and ground drainage
Minimize water usage
Proper storage of chemicals on site
Minimize usage of chemical (lubricants, oil, solvents)
Storage of used oils in proper containers for further disposal
or recycling
Continuous removal of construction spoils to minimize
sediment transport
Avoid commencing construction activities during rainy
season
Direct surface run-off into storm drains via adequately
designed sand/silt removal facilities
Provide channels, earth bunds or sand bag barriers on-site to
properly direct stormwater to silt removal facilities
Regularly maintain silt removal facilities
Cover open stockpiles of construction materials with
tarpaulin or similar fabric during rainstorms events
Prepare guidelines and procedures for immediate clean-up
actions following any spillages of oil, fuel or chemicals
Properly store chemicals on-site
Provide proper surface drainage
Minimize on-site water and chemical usage (oil, lubricants
and fuel)
Limit exposure of the soil to accidental releases of pollutants
Use non-toxic and readily biodegradable chemicals
Operation
172
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Impact
Biodiversity
Socio-economic
Archeology and
cultural heritage
Design/ Construction
Siting of the water network should take into account avoiding
and/or minimizing the impact on biodiversity
Postponing construction activities till after the mating season
of key species in impacted areas
Re-allocation of endangered species to areas outside the
construction zone
Relocation of people to suitable area
Provision of compensation in kind for any resource lost
Encourage local recruitment of workforce
Restrict movement of construction machinery outside the site
during peak traffic hours
Provide a traffic management plan for the impacted area
Adopt a rolling construction program to minimize disruption
to infrastructure
Change siting of water network to avoid losses to important
sites
Salvage or protection of cultural properties
Chance Find procedures to be implemented
Known sites adjacent to the project area should be out-ofbounds to crews
Important sites should be fenced by Contractor
Safety instructions to workers
Provision of personal protective equipment (helmets, boots,
gloves, earplugs)
Plan to construct water supply network pipes on top of
existing or planned wastewater network in order to avoid
cross-contamination
Provision of construction barriers and proper warning signs
Development of emergency response plans
Provide on-site medical facility/first aid
Implement speed limits for trucks entering and exiting site
Follow CDR guidelines for health and safety
Provide fire-fighting equipment such as dry powder
173
Operation
Ensure that tapping water supply sources will not result in a
decrease in the biodiversity of the area (or downstream) by
providing minimal required flow in water bodies or by
ensuring sustainable tapping of groundwater
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Impact
Design/ Construction
extinguishers within the premises of the plant
Landscape and
visual intrusion
Waste generation
Operation
Clear walkways of any debris
Promote use of Supervisory Control & Data Acquisition
System (SCADA) system to monitor the water treatment and
distribution system for leaks and losses
Fit walkways & tanks where the top wall level is less than 1
m above finished ground level with handrails & toe boards
Maintain on-site facilities
Rehabilitate areas that are disturbed by maintenance works
174
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Impact
Design/ Construction
Establish a recording system for the amount of waste
generated, recycled and disposed
175
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
Operation
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Project scale
Location
Small-scale
Construction site
Large-scale
Small-scale
Construction site
PM generation
Noise levels
Large-scale
Traffic
Large-scale
Small-scale
Monitoring means
Inspection and measurement of PM
level upon complaints
Inspection and measurement of PM
level at selected receptors
Inspection and measurement of
noise level upon complaints
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
Frequency
Phase
NA
Construction
Monthly
Upon complaints
Construction
NA
Construction
Monthly
Construction
Operation
upon complaints
Weekly and upon
complaints
Daily
Bimonthly
Construction
Operation
Daily
Daily to weekly
depending on
parameter and
previous results
Operation
Daily to weekly
depending on
parameter and
previous results
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Parameter
Terrestrial biological
environment
Project scale
Location
Small-scale
Large-scale
Small-scale
Large-scale
Socio-economic
Small-scale
Project site
Monitoring means
Undesirable parameters: Nitrates,
Nitrites, Ammonium, Kjeldahl
Nitrogen, Oxidation Potential,
Hydrogen Sulphide, Phenols,
Dissolved/ Emulsified
Hydrocarbons, Reactive surface
reagents, Iron, Manganese,
Copper, Zinc, Phosphorus, Silver,
Floride, Barium, Organo-chloric
compounds (other than pesticides),
Polycyclic aromatic hydrocarbons,
pesticides, Arsenic, cadmium,
Cyanide, Total Chromium,
Mercury, Nickel, Lead, Selenium,
Antimony
Presence of key species
Visual inspection and photographic
documentation of the general
condition of the floral cover
Jobs created for local people
Damaged or severed infrastructure
Field questionnaires Interviews
(Population perception and
employment records)
Damaged or severed infrastructure
Visual inspection and photographic
documentation
Water quality: Total and Fecal
Coliforms, ammonia, free chlorine
(other parameters can be added
depending on the area and previous
results)
177
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
Frequency
Monthly to yearly
depending on
parameter and
previous results
Before project
execution
Before project
execution and
annual follow-up
Biannually
Bimonthly
Annually
Phase
Construction
Construction
Operation
Construction
Construction
& Operation
Bimonthly
Monthly
Construction
Bimonthly
Operation
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Parameter
Project scale
Large-scale
Location
Project site
Monitoring means
Health and safety surveys (Proper
use of PPE, presence of signs, first
aid kit, and fire fighting devices)
Bacteriological parameters: Total
coliforms, Faecal streptococcus,
Faecal coliforms, Sulphidereducing bacteria, Thermophilic
coliforms, Salmonella,
Staphylococcus, Faecal
bacteriophages, Enterovirus
Physio-chemical parameters:
Temperature, pH, Color, Turbidity,
Electrical conductivity, Chlorides,
Sulphates, Sodium, Potassium,
Magnesium, Calcium, Total
Aluminum, Dry residues
Undesirable parameters: Nitrates,
Nitrites, Ammonium, Kjeldahl
Nitrogen, Oxidation Potential,
Hydrogen Sulphide, Phenols,
Dissolved/ Emulsified
Hydrocarbons, Reactive surface
reagents, Iron, Manganese,
Copper, Zinc, Phosphorus, Silver,
Floride, Barium, Organo-chloric
compounds (other than pesticides),
Polycyclic aromatic hydrocarbons,
pesticides, Arsenic, cadmium,
Cyanide, Total Chromium,
Mercury, Nickel, Lead, Selenium,
Antimony
Water borne diseases (typhoid,
diarrhea, hepatitis, etc)
178
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
Frequency
Continuous
Phase
Construction
Daily to weekly
depending on
parameter and
previous results
Operation
Daily to weekly
depending on
parameter and
previous results
Monthly to yearly
depending on
parameter and
previous results
Annual health
survey
Operation
C. LOTTI & ASSOCIATI S.p.A. in collaboration with CEB Baghdad University and Engicon
Parameter
Project scale
Location
Small-scale
At site boundaries
Large-scale
Small-scale
Cultural heritage
Large-scale
Small-scale
Solid waste
Large-scale
Monitoring means
Visual inspection and photographic
documentation
Visual inspection and photographic
documentation
The sustainability of landscape
planting
At site boundaries
Frequency
Biannually
Phase
Construction
Operation
Construction
& Operation
Operation
Monthly
Monthly
Annually
Construction
Biannually
Construction
Construction site
Disposal site
Monthly
Construction
Construction
& operation
179
Ministry of Municipalities and Public Works Republic of Iraq
Second Emergency Water Supply and Sanitation Project
Detailed Design Report
20/07/07
Wasit Detailed Design Report/fd
c.a.: F249A
Continuous