POWER PLANT
COMMISSIONING
CONTENTS
S.No.
Description
Page No.
PART 1
A.
Commissioning Activities
17
B.
19
C.
22
D.
26
E.
30
F.
Electronic Precipitator
35
G.
42
H.
44
I.
51
J.
55
K.
64
L..
Valves
68
M.
Steam Boiling
72
N.
81
O.
Soot Blowers.
85
S.No.
Description
PART II
A.
B.
Lubrication
Page No.
&
Governing
88
System
(Oil
94
C.
110
D.
Governing System
115
E.
Regenerative System
128
F.
Barring Gear
146
G.
151
H.
160
I.
Data Logging
172
S.No.
Description
Page No.
PART III
A.
Generator
176
B-
180
C-
199
D-
210
E-
218
PART IV
ELECTRICAL EQUIPMENTS
A-
Switchyard Equipments
231
B-
Switchgear
249
C-
Transformer
251
D-
H.T. Motor
254
INTRODUCTION
The term COMMISSIONING is used to describe the activity involved
during the latter stage of erection upto the completion of the 72 hours trial
run on full load which leads commercial operation.
The commissioning phase is a period of intense activity where many
previously unrelated activities start to merge or interact with one another
forming a complex sequence of events, with the advent of large generating
units, the increased complexity of the plant and the closer limits available on
the operating parameters, it is essential to ensure that the plant has been
thoroughly tested prior to the normal operation so that initial performance
can established and defects and omissions clear.
NTPC has developed an exhaustive commissioning system and philosophy
with the consultancy of BEI. This philosophy and system has been accepted
by NTPC management and is being implemented in NTPC Projects. The
system described in the document is discussed hereunder,
2.
2.1
2.2
2.3
2.4
To check that the plant operates reliably, safety and meets the design
performance.
PMI, NTPC
2.5
3.
RESPONSIBILITES
With any system or organization it is essential that individuals, groups or
departments all know their own responsibilities. The role of each part of the
organization must be clear both within its own boundaries and in relation to
each other.
Commissioning system sets out the duties and responsibilities of the
Corporate Center, the site Erection Department, the site operation &
Maintenance Department and the Contactor. The initiative for the setting up
the detailed system on the site lies clearly with the Erection Department but
in must be emphasized that all activities should be considered jointly by all
the above departments.
It is a fundamental requirements that staff from all the above department
including the contractor must be made available, full time of placing
contracts the contractor is made aware of the significant workload that will
be placed on him by the introduction of an organized commissioning
procedure.
4.
SYSTEM DESCRIPTION
Major committees are formed at least 18 months prior to schedule
commissioning of 1st unit: During this period the following activities will be
taken up:
i
ii
iii
PMI, NTPC
5.
iv.
v.
vi
To associate in commissioning.
Vii
ORGANISATION
The function and responsibilities of the major committees are as follows: -
5.1
Steering Committee
The purpose of this committee is to provide policy and priorities to the
activities of the plant erection and commissioning, ensure that adequate
resource are available both in material and manpower, to demand and
approve programme of work to approve documentation,
The committee would normally be chaired by the site General Manager and
consists of the senior officers from the Corporate Centre, Site and also
senior responsibilities contractors.
5.2
Commissioning Panel
The purpose of this is to control and progress the day-to-day commissioning
activities, to coordinate the activities of the various working parties and test
teams and to report progress and receive priorities from the Steering
Committee
The panel would normally the chaired by the Chief of O&M and the
members would to the take drawn from the test team Leaders, Erection,
Department, O&M Department and Contactors Middle Management as well
as some staff from operation Services.
PMI, NTPC
6.
WORKING PARTIES
Working parties are formed early in the erection phase to carryout a number
of vital tasks. The Working Parties are formed for the major plant areas, The
objectives of the working party are:
6.1
6.2
To Support the Erection Department & Contractors in the efficient and safe
commissioning of the plant.
6.3
6.4
6.5
ii
PMI, NTPC
iii.
iv.
v.
vi
vii.
To define, agree and provide the number the type and content of the
Commissioning documents required to fulfill the objectives laid out in
the paper of the principle.
viii
ix.
xi
xii.
PMI, NTPC
7.
TEST TEAMS
These are made up of the engineers at junior level, who carry out the
agreed Plant Testing and Commissioning Procedures. Members are drawn
from to the various concerned departments and contractors and will operate
under the leadership of the Erection Department Engineers in the case of
the plant in the case of the plant testing, the O&M Engineer in the case of
the plant commissioning, of the commissioning Department Engineer for
both.
The Test Team Leader plays a very important role in commissioning. He
provides a dynamic communication link between the engineers in the field
and the day-to-day commissioning coordinator, He is responsible for the
carrying out the agreed procedures and reporting deviations to the Working
party and finally for the preparation of the Test Report and results.
8.
DOCUMENTATION
There are five main types Documentation that are used in the system.
8.1
Papers of Principle
The papers of the principles are prepared jointly by the erection Department
and Corporate Center. If the O&M Department and contractors are available
at this stage of the constriction their to the main inputs should also be
included. The Paper of Principle is the first and most vital documents to be
produced as it is the base upon which other documents are compiled. Site
staff must be made available full time at Corporate Centre to enable the
documents to be provided.
The objectives of papers of the principles can be briefly summarized as:
i.
ii.
PMI, NTPC
ii.
8.2
8.3
8.4
8.5
Test Reports
PMI, NTPC
SAFETY
The procedure requires that be tore an item of the plant item of the plant is
energized it must come within the scope of the safety Rules and once within
that scope be done on that plant item once the requirements of the safety
Rules have been met.
It a mandatory that a system of the Safety Rules is established . No plant
item may be energized or pressurized until such a Safety Rules systems is
an operation, these are statements deigned not to plant, the first being
irreplaceable and the second representing a massive capital investment.
10
PLANT CERTIFICATION
As the plant is commissioned, critical stage. both operational and
contractual are reached. In the order to the mark events to the ensure that
satisfactory procedures are established, certain technical requirement have
been met and safety measure have been taken, certificates are issued at
different stage e.g.:
i.
ii.
iii
Clearance
PMI, NTPC
for
the
station
operation
certificate
issued
after
8
v.
When the plant is fully commissioned up to the design intent, a final completion
Commissioning report is to be prepared for the plant. It will include plant details,
programmer and schedule and achieved, major deviations, etc.
12.
PMI, NTPC
-------------------------------------------------------------------------------------------------------------MECHANICAL
-------------------------------------------------------------------------------------------------------------STATION
STANDARD CHECK LIST SHEET 1 OF2
-------------------------------------------------------------------------------------------------------------PLANT ITEM
PIPEWORK-CONSTANT LOAD SUPPORT
-------------------------------------------------------------------------------------------------------------PLANT NOMENCLATURE
----------------------------------------------------------------UNIT ------------------------------------------ SYSTEM ---------------------------------------------MANUFACTURER--------------------------- SRL. NO.-------------------------------------------LOCATION----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------NO
ACTIVITY
WITNESSED
Date
------------------------------------NTPC CONTR
------------------------------------------------------------------------------------------------------------1.
General conditions satisfy the
Side standing Instructions as
listed In the Plant Item
Commissioning Essential Pre
requisites(SCL MS1/1)
2.
3.
4.
Access
for
adjustments
maintenance and repairs is a
satisfactory,
5.
Check
that
support-setting
details can be easily read.
-------------------------------------------------------------------------------------------------------------REMARKS
-------------------------------------------------------------------------------------------------------------SCL REF: M/4/6
------------------------------------------------------------------------------------------------------------- PMI, NTPC
10
-------------------------------------------------------------------------------------------------------------MECHANICAL
-------------------------------------------------------------------------------------------------------------STATION
STANDARD CHECK LIST
SHEET 2 OF 2
-------------------------------------------------------------------------------------------------------------PLANT ITEM
PIPE WORK ---- C ONSTANT LOAD SUPPORT
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------NO.
ACTIVITY
Witnessed
----------------------- Date
NTPC CONTR
-------------------------------------------------------------------------------------------------------------6.
Check Marinate rings are
correctly fitted and undamaged
(where appropriate)
7.
8.
9.
Check hanger
system hot.
setting
when
Setting Hot
Pipe Temp
Pipe Press.kg/cm2
Note
for
following
check..Position
when hot .
10.
------------------------------------------------------------------------------------------------------REMARKS
------------------------------------------------------------------------------------------------------SCL REF: M/4/6
-------------------------------------------------------------------------------------------------------
PMI, NTPC
11
1.2
Standard Test gauge if not using a dead weight tester, other standard
pressure vacuum gauge, dependent on the range of the instrument
being tested.
2.
3.
Check the gauge calibration over its entire range 20% steps, increasing and
decreasing, Allow for head correction where necessary, Note the results on
Standard Calibration sheet 1.15.1.
4.
5.
PMI, NTPC
12
7.
Industrial gauges + 1.5% (1%) FSD below 10% & above 90% scale.
8.
PMI, NTPC
13
Part 1
A. Commissioning Activities
1.
INTRODUCTION
1.1
2.
2.1
2.2
Safe running the equipment for 8 hours period with all the interlocks
and protections, indications etc. to the check the behavior of the
equipment and its suitability to put into regular service,
b)
Checking the equipment and associated system with the aid of check
lists /instructions supplied for the same.
c)
In the case of the items like dampers, gates, valves, etc, freeness of
movements, full travel, full closure are checked individually and along
with drives.
2.3
Pre commissioning Tests: Gas tightness and air boiler pressure tests are
carried out identify and rectify leakage points in the systems,
At this stage the repeat hydraulic test on the boiler pressure parts is also carried
PMI, NTPC
17
Alkali boil out: Alkali boil out is carried out into to remove oil grease and
impurities adhering to the interior of the pressure parts of the after erection
of the boiler has been completed, the Alkali boil out operation is performed
at 40 kg/ cm2 gauge with 1000 ppm tri-sodium phosphate for 24 hours, the
boiler is fired for the process.
2.5
Thermal flow tests: In the order to detect possible chocking in the boiler
tubes thermal flow test is carried out. The water wall tubes, economisers
and superheaters tubes are normally checked by means of this test.
2.6
2.7
Steam Boling: Steam purging of super heaters and critical steam pipe lines
is carried out by puffing method to remove mill scales weld beads etc. This
is achieved in a number of the stage planned to suit the layout of the
system, Re heater safety valves are floated at this stage.
2.8
Safety Valve Setting: After steam blowing operations, the safety valves
(drum super heater) are required to be set to operate at the desired
pressure.
2.9
2.10
Reliability run of the boiler: After the Boiler has been commissioned and
various automatic put in the operation the boiler is taken for the reliability
run. The boiler is operated for a predetermined period as agreed upon by
the customer and supplier.
PMI, NTPC
18
INTRODUCTION
1.1
The commissioning team will organise their activities in such a manner that
the following jobs are completed to meet the boiler light up requirements:
a)
b)
Trial run of air heaters and readiness of AH soot blowing and fire
fighting system,
1.2
c)
d)
e)
f)
g)
h)
i)
k)
l)
Many of the above mentioned activities are parallel and with various inputs
given in time it may take nearly two months to complete the above jobs.
2.
Listed below are the various steps (along with tentative time needed to the
achieve them) from first light up to Reliability run of the boiler.
PMI, NTPC
19
2.1
Activity
--------------------a)
Trial light up
b)
c)
Cooling down
10
d)
17
20
22
29
32
15
47
50
e)
f)
g)
h)
2.2
Time of
in days
----------------2
b)
5+
c)
60
d)
63
e)
66
38
69
70
f)
g)
PMI, NTPC
20
h)
10
80
i)
10
90
j)
93
k)
96
l)
100
m)
10
110
n)
12
122
o)
Bearing Inspection
10
132
2.3
a)
b)
c)
Soot blowers
d)
Milling system
e)
f)
g)
PMI, NTPC
2
21
WATER FILLING
1.1
For both drainable and non drainable portions, normally usages of DM water
only is recommended.
1.2
2.
DRAINABLE PARTS
2.1
Economizer, water walls and all drainable portions can be filled with DM
water or condensate containing 10ppm Ammonia as NH3 and 200 ppm of
the hydrazine with a solution pH Value of a approximately 10.0, If DM water
is not available, only the drainable portions can be filled with water free of
chlorine and containing to 10 ppm of ammonia as NH3 and 200 ppm of the
hydrazine with a solution pH approximately 10.0. Prior to usage, filtered
water quality should be ascertained.
2.2
The required quantity of the ammonia and hydrazine should be added into
the water of recommended quality and a homogenous mixture should be
ensured prior to filling.
2.3
All the drainable parts, (economizer, water walls and the drum ) should be
filled through their respective bottom drains with vents open. Filling may be
stopped vent drum is filled half (this can be ensured by keeping level gauge
tapings opened.)
The tank containing clear to the filtered water be drainable and flushed.
PMI, NTPC
22
2.5
All the no drainable parts (includes drainable super heater) should be filled
through their bottom drains with the recommended quality of the water
containing 10 ppm of the ammonia as NH3 and 200 ppm of hydrazine with a
solution pH of approximately 10.00. Prior to filling a homogeneous mixture
of the chemicals and water be ensured. All the respective vents should be
kept opened during filling operation. When water gushes out ensuring free
flow from all the air vents including drum, close the air vents. Now
pressurise the system up to the working capacity of the filling pump.
3.
HYDROSTATIC TESTING
3.1
Water used should be only DM water containing 10 ppm ammonia and 200
ppm hydrazene with a solution pH of 10.0,
3.2
Pressure reading during the tests will be taken from the pressure gauge at
the high point of the boiler.
3.3
As a already indicated boiler shall be partially with the aid of fill pump.
3.4
3.5
4.
GENERAL :
Quantity of the water chemicals required for the one filling.
4.1
Hydraulic
200/210 MW Units
4.1.
200 tonnes.
4.1.2
DM water
175 tonnes
PMI, NTPC
23
4.2
Preservation
4.2.1 DM water
350 tonnes
100 kg
(100%)
4.2.3 Liquor ammonia
30kg
(25 to30%)
Not less than 21oC
4.2.4
4.3
After successful complain of the hydraulic test, the system may be drained
to the as per requirement and kept under wet preservation immediately as
per recommended procedure. In the actual practice, it is found that after first
to the hydraulic test, closing weld joints are to be made.
5.
WET PRESERVATION:
5.1
Ensure to the as a last of to the water kept to the in the boiler used for to the
hydraulic test is having a solution pH of not less than 10.0 with a minimum
hydrazene content of the 200 ppm.
5.2
Keep the under nitrogen blanket at a pressure of 0.5 kg / cm2 (Refer to fig.
No. 1-1.
5.3
Even during cases of the isolated hydraulic test of drainable portion alone,
wet preservation under nitrogen blanket should be practiced for the portion
tested.
5.4
5.5
Periodical tests are for to the pH and hydrazene content should be done for
the samples collected from superheater, As and when the pH goes less
PMI, NTPC
24
PMI, NTPC
25
INTRODUCTION
1.1
The smoke generators are used for the easier direction of the air leak and
ingress points. The smoke-generator is a sealed cylindrical container having
to the chemical in it which produce huge quantity of the smoke when ignited.
The specification of the smoke generator used is of type 24 MKS, 40 IBS wt.
This is being to the produced from the defense stores.
2.1
FURNACE ZONE
3.1
The furnace zone covers up to goose neck and penthouse 4 Nos of gas
generators can be used for this zone. The smoke generators are to be brunt
with a burning swab just above the water -seal of the water wall tubes on
two sides (Left& right). Manholes are inside the Boiler over a temporarily
made platform. All the other Manholes and peepholes are to be a kept
closed tightly.
PMI, NTPC
26
4.
4.1
This portion covers the area from to the Boiler goose neck to air pre heater.
The flue gas inlet dampers to the both air pre-heater are kept closed. In this
zone 2 Nos. of smoke generators can be used. These are to be brunt just
above to the air pre-heater (above the inlet dampers) where manholes are
available.
5.
ELECTROSTATIC PRECIPITATOR
5.1
This portion covers flue path after air pre heater M.P., E.P.S. and up to the
outer the outlet dampers of I.D fans. The portion is again sub divided and
out of four sections of EP is taken for test at a time. The flue gas dampers
after air pre heaters inter connecting damper and damper in the remaining
sections of EP as to be kept closed. The outlet dampers to the of I.D fans
are closed are also to be kept closed. Two smoke generator can be used
for each section. It is to the burnt inside the EP at the lowest possible point.
6.
6.1
HOT AIR DUCT: It will include duct above air heater and extend up to
burner wind box one each side. Totally 2 Nos. can be used for the both
sides on one each side. During to the test interconnecting air dampers are
to the kept closed.
6.2
COLD AIR DUCT: This portion covers the air duct after the F.D. fan outlet
damper and up to air pre heater, the outlet damper of fan F.D. fan the air up
to air connecting dampers heaters are to be kept closed.
6.3
One smoke generator can be closed for to the earth side of the duct. Thus
totally 2 Nos. of the smoke generators will be required.
PMI, NTPC
27
7.
7.1
Cold Air Dusts: This will cover cold air after P.A. fan outlet damper and will
extended up to mills on each side P.A. fan. One smoke generators can be
used in each side. Thus 2 Nos. of gas generators will be required . During
this test, outlet damper of P.A. fan, Inter connecting damper and ho air
dampers of mills are to be kept closed.
7.2
HOT AIR DUCTS: It will include the hot air duct after air heater and will
extended up to the mills. One smoke generator can be used for each side
and it is to be brunt above the air preheater. All the hot air dampers to mills
and dampers before air per heater are closed. It will be better to perform this
test simultaneously for both sides as enormous volume of the smoke will be
available (three is no interlocking damper). Totally 2 Nos. of smoke
Generators can be used.
PMI, NTPC
28
CUSTOMER
PMI, NTPC
CONSULTANT
29
INTRODUCTION
1.1
All equipments are run independently for a period of at least 8 hours before
declaring them available for the regular operation, Firstly the motor is run is
accordance with the manufacture recommend actions. After the motor is
proven O.K. it is coupled with equipment. Now the necessary checks to the
are made as per the checklist for the equipments is run for a period of 8
hours.
1.2
2.
FANS
2.1
Tests
a)
Constructional
b)
Pre commissioning
c)
Commissioning
2.1.1. Constructional tests: The extent of the test necessary and documentation
with checklist to be provided are to be decided and produced by to the
commissioning group. (Refer commissioning checklist attached of the ID
PMI, NTPC
30
fans).
2.1.1 Pre - Commissioning Tests: These tests are will be carried out when
construction is substantially complete and will entail the following :
a)
b)
c)
d)
Checks on the setting on the relief valve (on lub. oil, system)
e)
f)
g)
h)
i)
2.1.3 Commissioning Tests: These tests will involve the initial operation of the
systems to the demonstrate that it is operationally should and conforms to
the specification, the test comprise the following operations:
a)
b)
PMI, NTPC
31
heaters, coolers.
c)
d)
The starting and operation of the fan along with its major
components. (Sections chamber, inlet vane control, flexible coupling
etc.
e)
3.
AIR HEATERS
3.1
Tests
a)
Constructional
b)
Pre commissioning
c)
Commissioning
3.1.1 Constructional Tests : The extent of the test necessary and documentation
with check list to be provided ,are to be decided and produced by to the
Commissioning group.
4.
MILLS
4.1
Test
a)
Constructional
b)
Pre-commissioning.
PMI, NTPC
32
c)
4.1.1.
Commissioning
Constructional Test: The extent of the test necessary and the
documentation with check list to be provided, are to be decided and
produced by the commissioning group.
4.1.2
Pre-Commissioning Tests:
b)
c)
4.1.3
d)
e)
f)
g)
h)
i)
j)
Final inspection.
k)
Commissioning Test: These tests will involve the initial operation of the
system to demonstrate that it is operationally sound and conforms to the
specifications. The tests comprise the following operation.
a) The operational functioning of the dampers.
b) The starting and operation of the system.
PMI, NTPC
33
PART
SHEET
REF. NO.
INDUCED DRAFTFAN
STATION
PLANT
UNIT NO
IDENTIFICATION
I.D. FAN
I.D. FAN
PLANT DETAILS
Manufacture
Type of Lubrication
Type
Capacity
Speed
Fan efficiency
Name of Erector
I.D.FAN MOTOR
Manufacture
Voltage / Current
R.P.M.
Type
Type of Lubrication
Class of Insulation
Rating
Service Factor
Name of the Erector
S. NO
ACTIVITY
COMMENT
1.
2.
3.
4.
5.
6.
PMI, NTPC
34
1.1
Internal checks: Caution - Use only portable lamp operated by dry cells to
avoid electric shocks.
1.2
1.3
a.
b.
c.
d.
e.
f.
b.
c.
d.
e.
b.
1.4
c.
d.
Setting fixing.
e.
Emitting Rapping
a. Condition of shaft insulator.
b. Hammer hitting position on the shock beam.
PMI, NTPC
35
Check for presence of foreign material and cleanliness of the hopper and
walls.
1.6 Check the doors to ensure free swinging easiness to open and close no
seizing of nuts.
1.7 Check the gaskets
tightness.
1.8
Conduct gas tightness test before the gas distribution test and the
insulation work is done.
b.
c.
1.10
PMI, NTPC
36
1.11
2.
b.
c.
Heaters
a.
2.3.1 Precommissioning
a.
b.
Check fuses.
c.
d.
PMI, NTPC
37
b)
c)
d)
e)
g)
h)
i)
j)
k)
l)
m)
2.4
Check if all motors run for 1 minute before stopped by the timer.
Testing of transformer rectifier set: Open circuit test (at partial loading)
should be carried out by authorised engineers.
In this case, the results of the test should be tallied with (he results in the
test certificate. Equipments and instruments required for this purpose are :
a)
b)
c)
d)
3.
PMI, NTPC
38
b)
c)
d)
ii)
Rapping motors are put into trial run and continuously thro'
Auxiliary control panel during oil firing.
4.
4.1
39
such that average air velocity obtained is m/sec. in one of the panes. The
velocity readings are to be taken by an anemometer in the rear end of first
field. Where first field is a dummy, these readings are to be taken in the
second field. Each field is divided into number equal zones and velocity
measured at various heights in each zones. The velocities and flow
pattern are to be studied to determine to fix the deflector plates in the gas
distribution screen. These deflector supplied by Trichy can be easily
hooked . in the zones very high velocities are noted. Velocity
measurements are to be repeated after fixing the plates to calculate the
efficient of variations which is limited to 20%. The GD test as described
above for one path is to be repeated in on the remaining three paths.
4.1.2 Air Load Test of E.P.
Air load test of E.P. is also to be conducted prior to first up of boiler to
indicate the alignment of internal healthiness of insulators and the
transformers/rectifiers. As the test is conducted in the medium of air prior
to first light up, the test is called as air load test. Detail checks to
commission EP rectifier transformer and control panels are separately
given. All the electrical equipments are commissioned and available for air
load test. To conduct air load test, ID/FS fans are kept in service and all
the E.P. zones are charged. Volt-ampere characteristic of each field is
tabulated.
Steam coil Air Preheater should be put into operation to obtain flue gas
temperature at the inlet of EP to 105C during initial operation.
PMI, NTPC
40
PMI, NTPC
41
INTRODUCTION
1.1
As a result of long storage and exposure to atmosphere for a' long period
the oil lines are normally filled with mud. muck and attacked by rust etc.
This calls for a thorough cleaning and removal of rust, millscales etc. to
the extent possible. Failing to do so may result in frequent choking of
filters in the lines resulting in a number of interruptions in the initial stages
of operation of the boiler. Also the choking of oil gun tips resulting in poor
combustion and carryover of oil to the air heater, and hence a cause of air
heater lire.
1.2
Field experience shows that these oil lines, if blown with steam at a
pressure around 10-12 Kg/cm 2 at the rate of 5 to 10 T/hr for a period of 4
to 6 hours continuously, gives a good cleaned surface.
2.
2.1
Inspite of the due care taken for cleaning the oil lines it is observed that
during initial stage of operation the filters provided in the lines particularly
before igniters, and the igniters, atomisers get choked very frequently
causing interruption in the process. It will be a worth exercise to make
some temporary connection for recirculating the H.S.D. back to the
storage tank and keep the oil pumps running for a period of one week or
so before first light up of the boiler.
3.
TESTS
a)
Constructional
b)
Pre-commissioning
c)
Commissioning.
PMI, NTPC
42
3.1
Constructional Tests:
Pre-commissioning Tests:
These tests will- be carried out when construction is substantially complete
and will entail the following;
a) Inspection of the Pump (mechanical, electrical & instrumentation)
b) Ensure tightness of the pipe lines.
c) Checks on settings on relief valve (on oil system)
d) Operational test on valves and fittings.
e) Insulation test on motor.
f) Rotational check on motor.
g) Hydraulic test.
h) Flushing out of the pipe line.
i) Inspection of supports, drains.
3.3
Commissioning Tests : This tests will involve the initial operation of the
system to demonstrate that it is operationally sound and confirms to the
specification.
The tests comprise the following operation:
a) The starting and operating of the pump.
PMI, NTPC
43
SYSTEM
1.1
In order to prepare the boiler for light up the checking can be started
system wise. Broadly the boiler can be divided into six systems. They are;
1.2
1.
Air System
2.
Gas System
3.
Water System
4.
Fuel System
5.
Steam System
6.
FSSS
1.3
1.4
1.5
1.6
1.7
1.8
PMI, NTPC
44
1.9
1.10
2.
2.1
b)
Check for leakage of air in the system especially in all the flange
joints starting from fan outlet to the wind box. Ensure that there is
no gap between ignitor horn supporting plate and its flange.
c)
d) After ensuring that the layout is as per design and there is no leakage
of air in the system and there is no abnormal pressure drop in the
critical sections and the ignition air is passing out through free flow
area inside the horn. still if the farthest ignitor wind box is notgetting the minimum prescribed wind box furnace differental pressure (75 mm in the case of 2 million BTUH and 10'' mm in the case
of 6 million BTUH) the ignitor air fan must 'be checked for its
PMI, NTPC
45
Run the fan with its suction opens to atmosphere and take the
following measurements:
1)
2)
3)
4)
2.2
b)
The flange welded in the ignitor windbox to mount the front plate
must be checked for its verticality.
2.3
PMI, NTPC
46
b)
Keep the front plate on the ground and place the ignitor gun in
position, now check the verticality of the ignitor gun tip slot opening.
A variation of appr. _j_ 1 mm can be allowed. Otherwise modify the
tip seating plate in the eddy plate so that the gun tip slot opening is
vertical.
c)
d)
e)
Check the relative distance between the spark plus centre wire and
the gun tip as given in drgs.
f)
g)
Check the continuity of the ignitor wire, ensure that the insulation is
not damaged. Damaged wire should not be used.
h)
Ensure that the other end of the ignition wire is positively connected
to the transformer in the control cabinet.
i)
j)
Ensure that the high pressure (HP) and low-pressure (LP) tappings
are clean and there is no leakage.
47
Ensure that the pressure gauges provided are calibrated and are in
working condition.
4.2
Check all the equipment in the line are as per the Engineering drawing.
4.3
Check the leakage of all the valves in the line and the strainers.
5.
5.1
Connect the test box to me control cabinet close the oil/air stop valves
before the control cabinet and check the following:
a)
Check the Motor operated valve (MOV) operation and the limit
switch engagements by operating the test box.
b)
The spark plug is kept on platform so that the tri^ is not touching the
platform the intensity of the spark is checked by operating the test
box. If the spark is not strong check the spark plug inner
connections and earthing.
c)
Now open the oil and air stop valves before the control cabinet,
replace the spark plug in its position. Now give command to the
control cabinet by operating the test box. Don't keep the ignite
command more than 10 sees.
d)
If the ignitor is not starting with 6 set atomising air pressure, it could
PMI, NTPC
48
6.1
7.
7.1
Remove all loose construction material around boiler and also cut
off temporary supports, construction platforms etc. not envisaged in
the drawings.
b)
Mark all valves in the Boiler by tag no. and identification plates
usually supplied from Trichy. In the absence of identification plate
this
c)
information
can
be
painted.
Line to Econorniser.
PMI, NTPC
49
d)
e)
f)
g)
7.2
8.
8.1
PMI, NTPC
50
1.1
Chemical cleaning of boiler water & steam system will be carried out to
remove loose foreign materials, oil, grease, rust, mill scale, silica in the
form of silicates in order to obtain steam of high purity.
1.2
1.3
Acid
Stage IV
Cleaning
& Passivation
2.
WATER WASHING
2.1
PMI, NTPC
51
boiler steam &. water circuit. Circulation of water is continued till the
conductivity of inlet &: outlet samples show equal values. Water is then
dumped through w.w. drains. The dumping & refilling is to be repeated till
the conductivity of washing water levels with that of fresh filtered water.
For water washing filtered water may be used.
3.
3.2
Boiler will be filled upto - 180mm level with D.M. water using acid cleaning
pumps or B.F. Pump. A strong solution of about 20% concentration will be
prepared in a tank located at Boiler drum elevation floor. This chemical
suction will then be charged into drum through manhole by suitable means
&: the drum manholes will be closed.
3.3
Boiler will be lighted up within AB elevation warm up oil guns & gradually
pressure in the drum will be raised to 40 Kg/Cm (g). During pressurising
period boiler expansions shall be regularly monitored as indicated by the
expansion markers.
3.4
PMI, NTPC
52
3.5
Samples of each blow down & drum water shall be taken & analysed.
3.6
At the end of blow down operation boiler will be boxed up and hot drained
when pressure has come down to 1.5 Kg/Cm2-
4.
RINSING
4.1
Boiler will be filled to normal level with water by acid cleaning pumps or
B.F.P. and then will be drained. Rinsing will continue till the
Phosphate/NaOH concentration is reduced to nil and conductivity of Boiler
inlet and outlet water becomes equal.
PMI, NTPC
53
PMI, NTPC
54
PROCESS
1.1
1.2
1.3
Acid Washing
Stage II
Stage III
Stage IV -
Stage V
Stage VI -
Stage VII
Inspection
Stage VIII
2.
ACID CLEANING
2.1
PMI, NTPC
55
e. Nitrogen gas.
2.2
2.3
Drum internal will be removed from the drum. Nitrogen capping and
vapour venting temporary arrangements will be made before acid cleaning
process.
2.4
HCL of 30% concentration will be stored in rubber lined acid storage tank.
Suitable arrangements will be provided for charging concentrated acid into
the mixing tank. Mixing tank is provided with steam heating arrangement
and D.M. water/filtered water make up arrangement.
2.5
D.M.Water will be filled in the boiler upto the drum top venting out air
completely. For this purpose acid cleaning pumps will pump the water
from mixing tank to the economiser through temporary piping. Through
economiser water wall enter the drum and flow through down coiner and
water wall tubes into bottom ring header. From bottom ring header water
will flow through temporary drain lines (Welded to hand hole plates
openings) and normal drain lines back to the mixing tank.
2.6
Chemicals other than HCl will be stored on the platform above; mixing
tank for charging through mixing tank manholes. Express Laboratory will
be set up near mixing tanks for quick analysis. Arrangements will be made
for neutralising the acid dump in the neutralising pit using lime powder.
2.7
Having filled the boiler with water, circulation flow of 400t/hr will be
established through the above circuit. Heating steam will be turned on to
PMI, NTPC
56
2.9
2.10
3.
3.1
Having drained the acid, the system will be filled up with water, heating
steam will be turned on simultaneously. Circulation will be established
through the system and temperature of water will be raised to 65C. After
attaining the uniform temperature through out the system. D.M. Water will
PMI, NTPC
57
4.
4.1
4.2
System will be filled with D.M. Water heated between 50-60C and put on
circulation. Citric acid and ammonia will be charged in the mixing tank and
circulation will continued till uniform concentration of citric acid is obtained
at all places. After this, citric acid will be dumped under nitrogen capping.
5.
5.1
6.
NEUTRALISATION
6.1
Chemical to be used.
Na2CO- = 1% OR 10 KG/M3 of Circuit Volume.
6.2
System will be filled with D.M.water, heating and circulation will be done.
When temperature of system has reached 80C NaCO- will be charged in
the mixing tank and recirculation win be continued.
PMI, NTPC
58
6.3
7.
PASSIVATION
It is a process in which a uniform layer of magnetitie will be formed on the
bare metal surface obtained after acid cleaning* Formation of completely
protective layer will begin with 1st stage passivation & develop further in
2nd stage Passivation & continue during normal operation of boiler in the
safe regime of water quality.
7.2
1st Stage Passivation t The system will be filled with D.M.Water put on
circulation and heated to 85C. Hydrazine will be charged in mixing tank to
give concentration of 300 ppm and ammonia will be added to get pH value
of 9.6. Since the reaction of hydrazine at low temperature is a slow
process the solution will be left to circulate for about 24. hours at a
temperature of 85 - 90C. In case the hydrazine concentration drops
below 150 ppm at the end of ten hours concentration of hydrazine will be
increased to 150 ppm by further dosing. After passivation is over solution
will be hot dumped but under normal atmospheric air capping and boiler
air and flue gas path will be set for natural draft cooling.
7.3
PMI, NTPC
59
7.4
of 9.6
200 tonnes of solution of Hydrazine and ammonia will be prepared in
condensate storage tank and will be recirculatcd tor about 20 hrs using
boiler fill pump for 200/210 MW units. Solution will be analysed for
Hydrazine concentration and pH value before starting boiler filling. Boiler
steam & water circuit will be lined up for normal steaming and solution
prepared will be filled up to normal operating level using boiler fill pump.
Boiler will be lighted up with AB elevation oil guns; pressure will be slowly
raised to 40 Kg/Cm and maintained at this value for about 20 hrs. Regular
sampling of boiler water will be done to fine out Hydrazine concentration
and pH value. When Boiler water temperature drops to 90C the water in
the system will be drained. If 2nd stage passivation is followed
immediately by steam blowing boiler water need not be drained
8
8.1
2 Nos.
Specification Capacity
20 T/ Hr.
Head
30 meter
Fluid
Hydrochloric Acid
Temperature Ambient
Construction Hastilloy - C
Material
8.2
2 Nos.
60
Capacity
150 H/br
5 Nos.
Head
95C
Medium to be Water
Handled
Material
Type of
Construction
with horizontal or
Vertical split casing
8.4
Dissolving Tank
Of rectangular shape construction of the mild steel Capacity 20 M3
4 Nos
8.8
PMI, NTPC
61
9. SPECIFICATIONS OF CHEMICALS
Chemical with
Specification
a)
b)
Soda Ash
c)
Hydrochloric Acid
IS 265 1962
d)
Liquor Ammonia
IS 799 1955
e)
f)
Nitrogen Gas
g)
h)
Citric Acid
h)
Hydrazine Hydrate 8
k)
Quantity
IS 252 1972
IS 1747 1972
IS 5464 1970
PMI, NTPC
62
--------------------Kgs
7) Hydrazine hydrate-----------------------------Lts
8) Nitrogen---------------Numbers of f Cylinders
The drum and test is capons were inspected, the following observations are
made:
REMARKS:
Manufacturer
PMI, NTPC
CUSTOMER ENGINEER
63
In the past, tube failures has been a major contribution cause for Boiler
downtime. Our analysis reveals that a Major percentage of the Tube
failure, at least during commissioning and initial operational stages of the
Boiler is due to internal blockage of the tubes. A small tube failure in a
Boiler under operation, if not detected in time can lead to Major Repairs to
the unit.
2.
INSTRUMENT
2.1
3.
PRINCIPLE OF OPERATION
3.1
The Thermal flow meter works on the following principle. The time taken
for a heated tube to cooler depends upon the rate of flow of fluid passing
through the tubes. The tubes are heated and the time taken for the
temperature to drop from 10C to 30 above the ambient at that place
PMI, NTPC
64
This cooling period is compared between all the tubes wherever the
detection is to be made. If there is a blockage inside any particular tube,
then the cooling period for this tube will be much higher compared to the
flow meter period of all other tubes in that section. The accuracy of the
flow meter is good for a fluid velocity inside the tube of 0.15 m/sec. to 3.0
m/sec. There would be about 2 to 3 times greater error if the velocity of
the fluid is less than 0.15 m/sec.
4.
4.1
4.2
7 Econo. would be after the acid cleaning metal debris inside the tubes
could be cleaned by the acid in circulation. For conducting the test after
second stage passivation, the temporary connections may not be
available as the boiler has to be lighted up for second stage passivation. It
is also not advisable to conduct the test after first stage passivation as
circulating water for a continuous period .during the test can dislodge the
thin film of magnetite coating created during first stage passivation.
5.
FOR SUPERHEATERS
5.1
5.2
PMI, NTPC
65
PMI, NTPC
66
Left :
b.
Rear ;
c.
Right :
d.
Front :
CUSTOMER ENGINEER
67
L. Commissioning Of Valves
1. INTRODUCTION
1.1
b)
2.
2.1
2.2
2.3
2.4
Check the opening and closing of all the valves manually. If it is hard to
operate, service the valve.
3. MOTORIZED VALVES
3.1
Check for correct lubricant filled in the gear box to the required level.
PMI, NTPC
68
3.2
3.3
3.4
Set the position and torque switches by manually operating the valve.
3.5
3.6
After checking the correct direction, the valve should be opened and
closed for the full stroke.
3.7
Operate the valve from remote and check for correct indication at the
desks.
3.8
4.2
4.3
4.4
4.5
PMI, NTPC
69
4.6
Switch over to auto operation and check for the correct operation of the
valve.
4.7
If airlock device is provided, initiate simulation of air failure and check the
valve for stay put condition.
4.8
5. CONTROL VALVES
5.1
b)
All the impulse lines connected with the control valve should be
blown by air/steam, before connecting.
5.2
Check the control valve plug for correctness with respect to 0&-M
manual.
5.3
5.4
Do not try to tightly shut the valve, as it is not meant for that duty.
6. SAFETY VALVES
6.1
PMI, NTPC
70
6.2
6.3
6.4
Check the hand-popping lever is properly fixed and does not interfere the
closing of valve after hand popping.
PMI, NTPC
71
M. Steam Blowing
1.
INTRODUCTION
1.1
Steam blowing of Main Steam lines, cold reheat lines, Hot Reheat lines,
Superheaters, Reheaters and transfer pipe lines of turbine will be carried
out in order to remove welding slag loose, foreign material, iron pieces,
rust etc. from the system. These undesirable materials, if not removed
completely from the system during steam blowing, will be loosen and
carried over to the turbine with the steam, in course of operation and will
cause severe damage to the turbine. Also the valves in the steam system
will get damaged resulting into improper functioning or failure of valves.
2.
2.1
The
electrically
operated
temporary
valve
is
closed
immediately. The abrasions on the target plates fixed in the exhaust piping
indicate the effectiveness of blowing The steam blowing process is then
repeated. The standard practice is to limit the no of' blows per day to 6 to
8, at an interval of 11/2 hrs. with overnight cooling (Refer fig.No.I-3).
PMI, NTPC
72
3.
SCHEME
3.1
PMI, NTPC
73
PMI, NTPC
74
PMI, NTPC
75
Stage II
The main steam transfer piping from ESV to HPT control valves are steam
blown in this stage. Temporary piping are suitably routed to atmosphere
from the HPT control valves. At ESV the connections are suitably made
for this purpose.
The upstream of HP bypass line remains blanked.
The HP transfer pipelines remain blanked at the ESV end during the
further stages of steam blowing.
Stage III
The cold reheat lines and the HP bypass lines are covered in this stage.
Stage III (a) :
Temporary connection are made from E.LSV to the flange in CRH line,
provided at the down stream of NRv. The exhaust piping is led to
atmosphere suitably at the boiler end of cold reheat line.
The upstream as well as the downstream of HP Bypass line remains
blanked. Also the isolating valves in the extraction lines from cold reheat
lines are kept closed.
Stage III (b)
The blanks of upstream and downstream lines of H!' 1'iypdss are removed
and a specially fabricated spool piece is introduced in place of HP Bypass
valve. The stop valves in main steam line at the turbine and are kept
closed during this stage of blowing.
PMI, NTPC
76
The steam enters the CRH lines through HP Bypass lines thus ensuring
the cleaning.
After this stage of blowing, the stop valves in main steam lines at the
turbine end are kept opened, thus allowing steam to flow to CRH lines
parallely through these lines and HP bypass lines.
Stage IV
The hot reheat lines are covered in this stage of blowing.
The cold reheat line is connected to the reheater and at turbine end
temporary lines are suitably routed to atmosphere from the Interceptor
valves. Two hand-operated valves are introduced in the exhaust piping
from IV to facilitate reheater safety valve floating at the enc
stage IV
blowing.
At IV suitable blanks are introduced to prevent steam entering the transfer
pipelines. Also the LP bypass upstream is kept blanked.
During Stage IV blowing the hand operating temporary valves are kept fully
open.
4.
4.1
At the end of Stage IV blowing, the boiler firing is continued and pressure
is raised by regulating the hand operated temporary valves in the exhaust
piping. The reheater Safety valves are then floated one by one.
PMI, NTPC
77
Stage V
The reheat transfer piping from Interceptor valves to IPT control valves are
steam blown in this stage.
Temporary piping are suitably rounded to atmosphere from IPT control
valves. The blanks provided during Stage IV at IV are removed. The LP
bypass upstream remains blanked during this stage.
Stage VI
The LP bypass upstream lines are covered in this stage.
The blanking in the line is removed and temporary piping is routed to
atmosphere suitably. During this stage of blowing, the hand operated
temporary valve in the exhaust piping from IPT control valves are kept
closed so that the full quantity of steam is flowing through the LP bypass
upstream lines.
5.
PRECAUTIONS
5.1
In the puffing method of steam blowing, the water level in the drum swings
beyond visible limits at the start of blowing, during blowing and at the end
of blowing. During steam blowing there are chances of water carry over to
saturated steam lines and low temperature superheaters. This can
possible be minimised by keeping the water level in drum at the lowest
visible limit at the start of blow. It is recommended that the water feedings
to drum may be started when the drum level starts falling towards end of
the blow and drum level is to be brought to normal level for subsequent
light up of boiler.
5.2
PMI, NTPC
78
5.4
The boiler pressure during blowing out operation should be kept within the
design pressure of reheater and related piping, temporary piping, fittings
and flanges.
5.5
The boiler pressure during blowing out operation should be kept within the
design pressure of reheater and related piping, temporary piping, fittings
and flanges.
5.6
5.7
5.8
5.9
Internal boiler water treatment to be carried out with NH^ and N-H. only to
maintain a pH of 10 in boiler water and in feed water 5 to 25 ppm of N-t-L
to be maintained.
5.10
PMI, NTPC
79
5.11
5.12
All the drains of connecting piping are to be left open to atmosphere and
not to be connected to drain vessels, to ensure proper draining.
5.13
PMI, NTPC
80
INTRODUCTION
1.1
A safety valve is used principally to save the boiler pressure parts from
being unduly stressed in excrement cases of mal-operation. It is installed
as near to the Boiler or superheater or Reheater outlet headers as
possible to be put into effective use.
1.2
Test
1) Constructional
2) Pre-commissioning
3) Commissioning
2.
CONSTRUCTIONAL TEST
2.1
The extent of the test necessary and the documentation with check list to
be provided, are to be decided and produced by the commissioning group.
3.
PRE-COMMISSIONING TESTS
3.1
2.
3.
4.
5.
6.
Drain from safety valve body and exhaust Tray properly laid.
PMI, NTPC
81
7.
8.
4.
COMMISSIONING
4.1
TO
activities viz.
4.2
i)
ii)
Reheater Safety Valve Floating :-, The floating of Reheater safety valve
will be done after the 4th stage of steam blowing i.e. When cold Reheater
and Hot Reheat steam pine line are steam blown. The drum pressure after
the 3rd stage steam blowing should be maintained at 20 Kg/Cm2 to
facilitate salon valve floating. The floating is to be done from the -highest
pressure safety valve and then proceed to the tower ones.
a) All safety valves should be gaged except the one to be floated.
b) Pressure in the line is to be raised steadily and as pressure reaches
about 80.85% of the set value the valve should be popped by hand
(operating the lever) 4-5 time so that the valve freeness may be
ascertained.
c) Raise steam pressure in line slowly and note the lifting pressure of the
valve and also note the setting pressure.
d)
If lifting pressure is not as per rated value the valve should be gaged
after pressure has dropped considerably and then ring adjustments
made to acquire the wanted value.
PMI, NTPC
82
e)
Once adjustments have been made remove the gag and slowly
start raising pressure and observe the floating and setting of the
valve.
4.3
f)
g)
Safety Valve Floating Of Boiler Drum & Super Heater: - The safety valve
floating of the boiler drum and super heaters will be done after the 5th
stage of steam blowing. Boiler shall be lighted., up and pressure raised
slowly at the rate of 0.6 - 0.8 Kg/Cm /minute. ~At pressure raising above
30 Kg/Cm after every 10 Kg/Cm ' pressure rise the boiler pressure is to
be held at this value for 30 minutes to ensure proper expansions of boiler
at various points. The valves are to be floated in the descending order i.e.
The drum safety valves from the highest pressure are to be floated first
followed by superheater safety valves which are set at a lower pressure.
The safety valves are then to be floated as explained for Reheater safety
valves.
4.4
PMI, NTPC
83
UNIT:-
DATE Location
Lift
RESET
BELOW DOWN
%
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
CONSULATANT
PMI, NTPC
CUSTOMER
84
1.1
Inspect for breakages and other damages that could happened during
transit and erection.
1.2
1.3
1.4
1.5
Check for- proper hanger supports for steam piping as per drawing.
2.
2.1
After completion of Hyd. test, the blanks provided in each blower should
not be removed.
2.2
Open the drain valve .and charge steam slowly. Any leaks in the blank to
be attended.
2.3
Keep the Electrical isolating valve and control valve in full open position
for blowing of lines.
PMI, NTPC
85
3.
Check for healthiness of limit switches and wiring done between the
terminal box and the switches.
c.
Check the I.R. valve of the motors if .it is found to be low then
rectify.
d.
e)
Check
for
shortages
4.1
Switch on the power supply to the panel after by passing the interlocks (like
the inlet valve open, drum valve closed pressure of steam).
4.6
Select the remote manual operation of the blower at the control panel.
PMI, NTPC
86
4.7
Operate the blower one by one from panel and check for the operation of
the relays, proper forward and retract travels of the blower. During this
check, locally one should ensure that the blower is OK and rectify the
defects noticed.
b)
c)
d)
e)
f)
g)
If any blower is bypassed in between then check that the next blower
operates, when in Auto sequence.
h)
Check for the audible and visual alarm when the sequence is
complete.
PMI, NTPC
87
INTRODUCTION
The Turbine oil used in the 200/210/500 Mw Turbo-sets is used for
lubrication of the bearings, for Hydrogen seal system, as well as for
governing system of the turbine. Therefore, the cleanliness of the oil is of
utmost importance. To achieve this, it is necessary that all the oil pipe lines
must be thoroughly cleaned form inside so as to free them form rust
particles, mill scale, grease, protuding welds, etc. as otherwise the oil may
get contaminated while flowing through the system. Following steps are
observed in the cleaning of the oil pipe lines.
1.1
a)
b)
Acid cleaning.
c)
d)
Chipping and grinding of all the protruding welds sticking inside the
pipe lines to be done by using files, chipper or flexible shaft grinder.
Points which are inaccessible otherwise have to be cleaned with the
PMI, NTPC
88
Round wire brushes tied with steel chain/wire are pulled through the
pipes. The process is repeated 8-10 times to remove all the rust,
welding splatters mill scale etc.
c)
d)
All the joining flanges of the pipe lines are to be scrapped and colour
matched with the surface plate.
e)
After all the pipes are mechanically cleaned they are blown by
compressed air to remove the rust and dust and ensure that there is
no blockage in the pipe line. Thorough inspection of the pipe lines
from inside with the help of mirror and light is done, so as to check
the proper cleaning of the pipes.
f)
1.2
Acid Cleaning : Apart from the mechanical cleaning, the acid cleaning of oil
pipes is a must, and should not be left over on the pretext that the
mechanical cleaning has been perfect. During the treatment of the pipes
with orthophosphoric acid, the sulphur which accelerates the corrosion of
metal is removed from the surface of the pipes alongwith the mill scales.
b)
c)
- 10,000 litres
dummies etc.
PMI, NTPC
89
d)
thophosphoric Acid
- 10,000 Kg.
e)
Thermometer
- 1 No
f)
g)
h)
i)
1.2.2 Six to eight number of pipes, depending on their sizes are assembled in
loops at the place where the acid cleaning is to be undertaken. In erecting
the loops, normally pipes of the same dia. should be used.
1.2.3 The delivery end of the acid pump be connected with one end of the loop by
flexible pipe. The other end of the loop is connected to the return pipe of the
tank.
1.2.4 Fill the acid tank with 15% solution of orthophosphoric acid and the temp. of
the solution must be raised to 30 to 40C. In the other tank make 2%
solution of orthophosphoric acid for passivation of the pipe lines.
1.2.5 The loop is flushed with 15% solution of acid for 2-3 hours and then one of
the joint is opened for inspection. For strongly corroded pipes it is
recommended to the first flush the loop for 3 to 4 hours and then stop the
pump and the loop is kept filled with acid solution at 0.5 to 1.0 Kg/sq.cm.
pressure for 6-7 hours and then again the pump is started and circulate the
acid for 2-3 hours. Thus by this process even the strongly corroded oipes
are cleaned.
1.2.6 At the return line of acid to tank, all suspended rust particles should be
collected by providing some stainless steel mesh or by some other
arrangement.
PMI, NTPC
90
1.2.7 The cleaning of the front pedestal inner oil pipe lines of the governing
system is not done by acid. They are only mechanically cleaned.
2.
2.1
After the loop is flushed and cleaned with 15% Acid solution, the passivation
of .the surfaces so cleaned is done by circulation 2% solution of
orthophosphoric acid in the loop. The circulation is done for i to 1&1/2
hours.
2.2
After passivation cycle is over the acid solution from the loop drained and
the loop is dismantled for drying and inspection.
2.3
Dry hot compressed air is blown through each pipe separately. The temp. of
the hot air should be 50 to 60C and should be blown at a pressure of 3 to 4
kg/sq. cm. The duration of blowing should be 30 to 40 minutes. The drying
of each pipe has to be done individually and not in loop. The air is blown
from one end, and is exhausted from the other end.
2.4
Clean dried pipes are subjected to through inspection. The clean dried
surface has a dark steel grey colour, which shows that the acid cleaning is
of required standard.
2.5
After the inspection, the ends of the pipes should be covered with clean new
cloth or with wooden blanks, and must be tied properly to as to ensure that
no foreign matter goes inside the cleaned pipe.
2.6
In case the cleaned oil pipe lines are required to be stored for some time,
and 1-2 months, after cleaning and passivation the oil flushing is
undertaken, it is recommended to cover the cleaned surface of the pipes
with a layer of turbine oil & properly cover the ends with cloth or blanks.
PMI, NTPC
91
2.7
The pipe lines are to be stored in clean dry place on sleepers and not on the
floor. All the precautions should be liken that no dust, moisture or foreign
matter enters these pipes during storage.
3.
3.1
The packing of the correct size, thickness and material should be used. The
details given in the drawing in this regard should be followed. While making
the gasket it must be ensured that the inner bore of the gasket must always
be more than the bore of the pipe.
3.2
IT
The cleaned pipe lines should be erected in position, taking all the
precautions that nothing falls inside them cr they become dirty during
assembly. The ends should be uncovered only just prior to tightening of the
joints.
3.4
All the tappings for the instruments must be temperarily plugged till the
connections to the instruments are done.
4.
SAFETY
4.1
Orthophosphoric acid is not poisonous but may cause skin burning and
hence all the safety 'precautions must be taken during acid cleaning.
a)
b)
The operators must use rubber gloves and eye protecting glasses
while handling the acid.
PMI, NTPC
92
c)
Even for the inspection of inside of dry cleaned pipes for illumination,
candle or match should not be lighted. Electric lamp and mirror may
be used for the purpose.
d)
Due precaution must be taken while tightening the joints of the loop,
so that they do not leak on starting of ac id pump, thereby leading to
acid being sprayed through these joints.
PMI, NTPC
93
INTRODUCTION
1.1
Oil flushing is meant for guaranteed cleanliness of Oil Pipe lines, bearing
housings, elements of governing systems etc.
1.2
All the pipelines must be acid cleaned prior to their final erection in position.
1.3
Before starting the flushing ensures that all the oil pipes, pumps,
centrifuging machine, oil tank with injectors and filters etc. have been
assembled and Installed at their proper places.
1.4
Flushing should be carried out with Turbine Oil IOC-14, which is the working
fluid for the governing and lubrication system. During flushing the
temperature of oil should he maintained at 50 to 55C.
2.
2.1
2.1.1 All the flanges in the system should be checked for proper tightness with
correct gaskets and orifices if any.
2.1.2 All the permanent supports should be checked for proper erection and
tightening. Check that all temporary support are removed. Check the slope
of the pipelines.
2.1.3 Oil tank should be thoroughly cleaned and inspected before oil filling. Check
the paint applied to MOT for proper application.
PMI, NTPC
94
2.1.4 Emergency drain from the oil tank should be properly erected as per
requirement, wherever provided.
2.1.5 All the work on the impulse lines of instruments should be completed and
the instruments erected or local and remote indications is with
compensation for location.
2.1.6 Check the oil level indicator of MOT for correctness.
2.1.7 Check whether injector unit overhaul is completed.
2.1.8 Check that the centrifuge connections are completed it is ready for oil filling.
2.1.9 The oil to be filled, should be tested in the laboratory before filling.
2.1.10 Suction and discharge valves of all the oil pumps should be kept closed.
2.1.11 All the valves in the oil coolers should be kept closed prior to the oil filling.
Afterwards the oil coolers may be charged.
2.1.12 Valves of seal oil injector suction lines should be kept closed.
2.1.13 A gang of workers should be ready with all the necessary tools to attend the
oil leakages, if any. In the event of any leakage, stop the further oil filling at
once.
2.1.14 Ensure proper lighting in the area.
2.1.15 Arrangement of compressed air should be made for cleaning the oil tank
strainers.
2.1.16 Adequate quantity of Turbine Oil should be kept ready.
2.1.17 Inspect the oil tank strainers for any damage to the mesh.
PMI, NTPC
95
3.
CHARGING OF OIL SYSTEM (Refer Fig. No. II-3) Oil Flushing Circuit of
a typical 200/210 MW Turbine Lub. Oil System.
3.1
3.2
While filling up check whether any of the following flanges fitted externally
are leaking.
While filling up, if no external leaks are observed, fill the oil tank upto 520
mm. from the top of the oil tank, which corresponds to zero of the indicator.
3.4
Further fill up the oil tank and check whether the indicator reading
corresponds to that of actual measurement.
3.5
Fill the tank upto 140 m-n from the top of the oil tank which corresponds to
38 cm of the level indicator reading and check that the oil level is below the
strainers.
3.6
Adjust the low level, high-level indicator so as to give alarm at 30cm and 10
cm for high and low respectively.
3.7
Open the suction valve of stand by oil pump for charging the pump and
check for any leakages.
3.8 Open the delivery of the standby pump and check for any leakages.
3.9 Charge one by one the coolers as follows:
3.9.1 Keep open tie oil cooler thermo-well pocket at the outlet before outlet valve.
3.9.2 Open, a little, the inlet valve of the oil cooler.
PMI, NTPC
96
PMI, NTPC
97
3.9.3 Check whether air is being pushed our through the thermo-well pocket. In
case of air lock the AC standby oil pump may be pumped for removal of air
lock.
3.9.4 Keep open the inlet valve fully.
3.9.5 Open the outlet valve gradually to the full open position.
3.10
Check each oil cooler drain by opening a little and observing whether oil
comes out.
3.13
4.
OIL FLUSHING
4.1
After filling oil upto the correct level in the main oil tank start the oil flushing
of a 200/210 MW & MW turbine is done as the following stages :
All the bearing, of TG are by passed in the first stage of oil flushing.
For this, loop the inlet and outlet lines of the lubricating oil lines
suitably at each bearings. Only these lines will-be included in the first
stage of oil flushing and all other lines should be blanked.
b)
Also blank 20kg/c'n~ line at front pedestal MOP suction, CVS.M and
also suction line to MOP at CVSM, to by pass governing system in
the 1st and Und stage flushing. Lub oil line to Barring
PMI, NTPC
98
Check whether the pressure gauges are fixed for all the oil pumps.
d)
Check that the drain valve of the lube oil header is in closed position.
e)
Check whether the oil pumps are coupled with their respective
motors after the completion of the motor trial runs.
f)
g)
Open the suction valve of AC standby oil pump and close the
discharge valve.
h)
Check that cooling water for the bearing of the pump is available and
is sufficient.
i)
Check that the level of oil in the thrust bearing of AC standby oil
pump is normal.
j)
k)
l)
m)
n)
Open the delivery valve a little for charging the system and check for
PMI, NTPC
99
any leakages.
o)
p)
Watch the oil tank level and in any case it should not drop below 15
cms. If necessary fill the tank and maintain a value of 20 cams. at the
indicator.
q)
r)
s)
Open the suction valve of starting oil pump for charging the pump by
opening the air release and close it after completely charging the
pump.
t)
Start the starting oil pump and note down starting current, no load
current and closed delivery pressure.
u)
Open the delivery valve a little for charging the system and check for
any leaks-
v)
If everything is normal, open the delivery valve to the extent such that
the delivery pressure is maintained to the rated value and the
amperage well within the rated value.
w)
Stop the standby oil pump. Watch the oil tank level if necessary fill
the tank upto 15 cms.
x)
Watch the differential level meter. If the differential shows about 200
mm or the level drops to 50 rnm. as per the level indicator clean the
PMI, NTPC
100
z)
Increase the lub. oil temp. and maintain between 0 to 55C with the
centrifuge in circuit. Control the oil temperature by admitting cooling
water to the oil cooler.
za)
Once in an hour tap the welded joints lightly on the lub. oil inlet and
outlet pipes to remove the welding slag.
zb)
zc)
b)
All the journal bearings of the TG are properly tightened after putting
their respective upper halves on them. Then these bearings are
turned by 20 to 25 so that: their oil supply lines to babbit are cut off
and the oil does not go to the babit portion of the bearings. In such
PMI, NTPC
101
position of the bearings the' oil falls in the bearing chamber without
entering the journal babbit area of the bearing.
c)
For Radial Thrust and other spherical seated bearings remove the
top halves of the bearings and then insert tightly a few layers of clean
muslin cloth along the journal of the rotor and in the side oil
clearances, so that during oil flushing the oil does not enter the
journal babbit area of the bearings.
d)
Wrap clean cloth around the rotor at all the places where it extends
immediately out of the bearing chambers so that the oil does not
spread. Normally no oil should leak through these areas.
e)
Close the bearing housings by putting the covers and tighten the
horizontal joint so that the oil does not leak through.
f)
g)
a)
All the TG Bearings are normalised & flushing is done through the
bearings. Ensure that orifices of correct sizes are installed at the
bearings as per the drawing for each bearing.
b)
c)
d)
PMI, NTPC
102
f)
The control oil line and the secondary sensing line near servomotor
to he looped together with an orifice of 25 mm as shown in figure.
g)
h)
i)
j)
Connect the lub. oil distribution pipeline from front bearing which
leads to lubricating the MOP bearing and other gears with the other
ends left free. This piping should be connected to the respective
lubrication point after completion of hydraulic test to ensure thorough
flushing of this lubrication distribution piping.
k)
Control oil line leading to protection system connected from the post
is to be dummied at the base. AK the pipelines connected to the post
except the orifices and the filter are to be placed in position and left
free at the other end.
l)
The inlet and drain pipes at both ESV servomotors are to be looped
together near the valves and the cutlets are to be left in the front
bearing oil drain sight box. Also loop the inlet and drain pipes of both
PMI, NTPC
103
IVs together.
m)
Open the inter connection between lub. oil and governing oil line near
the SOP.
n)
o)
Start SOP and complete the third stage oil flushing as described
earlier.
b)
c)
Start the SOP for fourth stage oil flushing with discharge valve in
throttled condition such that the bearing pedestal does not flood with
oil.
d)
This includes delivery line of MOP upto its base and the governing oil
line inside the pedestal by placing back the MOP. \ As during flushing
there will be a tendency for MOP impeller to rotate in reverse
direction it must be ensured that either the impeller should be free to
rotate or it should be removed and only MOP casing should be
installed in position.
PMI, NTPC
104
b)
After completion of fourth stage flushing put back the dummy on the
suction line of MOP near bearing pedestal.
c)
Remove the delivery dummy &: flap of NRV of MOP delivery line.
d)
Restart the starting oil pump and flush by throttling the delivery valve
to the required flow in the delivery line.
e)
f)
Put back the pump assembly and fix back the NRV of MOP.
g)
h)
Start the starting oil pump after charging of control oil lines.
i)
j)
Put back the dummy at the intermediate pilot valve base on the
control oil line.
k)
Remove the dummy provided on the centre oil post loading to the
protection circuit.
l)
Start the oil pump and do the flushing for the above mentioned line.
m)
105
a)
b)
c)
d)
e)
f)
g)
h)
Assemble all the governing elements and normalise all the pipes
lines in the bearing pedestal. Take governing system characteristics
before doing Hydraulic test.
5.
5.1
Place the control valve servomotor without connecting the rocker arms of
HP & IP cam shafts.
5.2
Change the motor of starting oil pump with a test meter having 1500 rpm for
the pump to develop 40kg/cm pressure.
5.3
5.4
PMI, NTPC
106
5.6
Start the starting oil pump (after establishing the oil circuit by standby oil
pump), with a delivery throttled so as to get a pressure of 20kg/cm2 in the
control oil circuit.
5.7
With the help of control gear, bring the servomotors of control valve of ESV
and IV to the full open position.
5.8
Carryout the Hydraulic test of oil pipelines by further opening of the delivery
valve of the starting oil pump.
5.8.1 Test the Governing system at a pressure of 40 kg/cm2 in the pressure line
for about 5 minutes. (While raising the pressure watch the lub. oil system
pressure). The hydraulic test pressure will be different for KWH Turbine
Governing System.
5.8.2 Test the-lubricating line before the oil coolers at a pressure of 6 kg/cm2 for
about 5 minutes by throttling the outlet valves of oil coolers.
5.8.3 Test the lubricating system after oil coolers at a pressure of 2kg/cm2 for
about 5 minutes by adjusting the spring of the drain valve of the lubrication
line so as to achieve the test pressure.
5.9
After the test reduce the pressure in the oil system to 20kg/cm at control oil
and check' carefully the complete oil system. Any defect leakages noticed
during the test must immediately be attended and oil system should be
tested again hydraulically.
5.10
After, completion of the hydraulic test switch off the oil pump and replace
PMI, NTPC
107
The relief valve which was adjusted during hydraulic test should be
readjusted to the old position.
5.12
Drain entire oil tank, oil coolers, and the entire oil system.
5.13
5.14
5.15
5.16
5.17
Start the centrifuge and circulate the oil in the oil tank by maintaining a
temperature of 55C for about 24 hours.
5.18
5.19
Open the interconnection between lube oil and control oil! system.
5.20
Start the starting oil pump and circulate the oil through bearings and
governing elements for about 24 hours by maintaining oil temperature about
50 to 55C.
5.21
5.22
Adjust the relief valve such that the lube on pressure at the bearings inlet is
about 1.0 kg/cm2 .
5.23
Adjust the pressure switches on lube .oil circuit for auto start of AC standby
PMI, NTPC
108
oil pump at 0.6kg/cm' and the DC emergency oil pump-at 0.5kg/cm and auto
stop of gear motor at 0.3kg/cm .
5.24
Now the oil system is ready for checking and adjusting of the governing
system as well as for barring gear operation.
6.
6.1
Lub. oil flow through bearing number one should be checked by running the
AC lub. oil pump &. keeping the inter-connection valve between lub oil &
governing oil line closed.
This way only lub. oil will be flowing through the bearing number one drain &
not the governing oil. Check the return oil drain sight box for adequate
quantity of oil. Sufficient oil! flow through the other bearings of turbine
should also be checked-
6.2
For checking the sufficient quantity of lub. oil How through the bearings of
Generator, stop the seal oil pump (make sure that the Generator is not
charged with Hydrogen or A if at the time of this checking) and check the
return oil flow.
6.3
The temperature sensing elements should always dip m the oil. For this
check the length of the probe. If it dose not dip in the oil, fill the thermo-well
with oil so that the probe ran sense, the temperature through conduction.
6.4
Work permit system for the T.G. oil system must be followed strictly.
6.5
After this stop all oil pumps and run the A.C. seal oil pump alone and ensure
sufficient drainage through the generator bearings. By this procedure
adequate lube oil to all the bearings and seal oil to the generator seals are
being ensured.
PMI, NTPC
109
OIL FLUSHING
1.1
1.2
The relief valve discharge header is connected back to the bearing oil drain
after removing the dummy. The internals of the NRV's are kept removed.
1.3
By fully opening the globe valve in the suction line oil can be injected into
one of the discharge line to which suction pipe has been connected. The
flushing for each line must be done at least for 45 minutes. Thus all the
discharge lines including the suction line of 30P can be flushed.
1.4
1.5
The flushing of the jacking oil lines is taken up during II stage oil flushing
and can be completed alongwith II stage oil Hushing.
1.6
During flushing special care must be taken to see free flow of oil in the lines.
1.7
After the oil flushing NRV's and the relief valves are normalised.
PMI, NTPC
110
1.8
1.9
The circular blanks welded at 30P discharge pipe lines at 30P and should
be removed by grinding off the welding done and thereafter the permanent
connection to be the discharge pipe lines to 30P must be done.
2.
2.1
All the lines are normalised. Suction and discharge lines are connected to
JOP which is in position.
2.2
During trial run of jacking oil pump, the relief valves must be suitably
adjusted for a working pressure of 140kg/cm2 . This should ensure a lift of
about 0.07 to 0.1 mm in all the bearings.
3.1
The erection of the jacking oil pipe lines is to be completed except for the
jacking oil pump and pipe No.1 connected to the discharge valve.(Fig II-4)
3.2
The jacking oil pipe lines must be kept well cleaned by blowing compressed
air and then steam. The pipe lines must then be kept preserved by applying
oil so as to form a continuous thin layer all along the internal tube surface.
3.3
The connectors should be connected only to pipe No. 2 i.e. 30P end of the
pipe line leading to bearings, which will be hydraulicaily tested.
3.4
PMI, NTPC
111
should be connected to the pr. gauge tapping point in the discharge line.
PMI, NTPC
112
PMI, NTPC
113
3.5
The relief valve in the discharge line header connected to the bearing oil
drain should be disconnected. The top flange is kept open and the bottom
flange is dummied. This arrangement will ensure detection of any water
passing through the relief valve and will also prevent its entry into the main
oil tank.
3.6
The flaps in the NRV's (discharge line) are kept removed and the relief
valve spring is fully tightened so that the relief header is not pressurised.
HYDRAULIC TESTING
4.1
Connect the manual Hydraulic pump at the nipple of the circular blank
welded at 30P end of the pipe lines. Fill each line with water after removing
the blanking nut and then firmly tighten the same.
4.2
By the hand pump build up pressure upto 210kg/cm2 in the lines one by
one. If any leakages are noticed the same must be attended so that the line
can withstand the test pressure for five minutes.
4.3
After the hydraulic testing, the plugs provided should be removed and the
relief valves must be completely released.
4.4
The pipe lines must be completely drained, cleaned and dried by hot
compressed air and then should be preserved by oil spraying.
PMI, NTPC
114
D. Governing System
1
1.1
Preparation
1.1.1 Check whether the front bearing pedestal pipings are completed.
1.1.2 Check that all the governing elements to be mounted in the F.B. Block are
thoroughly cleaned. Slightest dirt or any other foreign matter may hamper
the function of the whole system.
1.1.3 Check that all the pressure gauge impulse lines in the front Bearing Block (5
Nos.) and other pressure gauges in the oil and governing system (6 Nos.)
are properly fitted. Ensure proper calibrations of all pressure gauges are as
follows:
a)
b)
c)
d)
e)
Protection line.
f)
g)
Below differentiator.
h)
PMI, NTPC
115
i)
j)
k)
1.1.4 Check that the pipings in the front bearing pedestal are fitted and tightened
properly to avoid any leakages.
1.1.5 Check during erection that the clearance between the emergency governor
strikers with respect to emergency governor levers is within 1 + 0.2 mm
design limits. This is to be checked byt lifting the main pilot spool of
emergency governor pilot to the max. position and record it in governing
logsheets.
1.1.6 Check during erection that the clearance between the emergency governor
striker with respect to emergency governor rubber rollar for indication are
maintained at 1 + 0.2 mm and record it in governing logsheets.
1.1.7 Check ducing erection the clearance between the speed governor and
'nozzle of follow pilot valve is as punched on the speed governor when the
speed governor block lever pulled out to the extreme and record it in
governing logsheets.
1.1.8 Control valve servomotor should not be connected with camshaft of HP & IP
through the tie rod. The tie rod is to be connected after testing of
servomotor alone. Two eye belts are to be put on the levers and are to be
tied together.
1.1.9 Check during erection the speed governor dimensions as given in the
passport regarding K1, al and a2 and record them in governing log sheets.
PMI, NTPC
116
1.1.10 Check during erection that the clearance between yoke and top cover is 9
mm for both emergency stop valve and interceptor valve as given in the
drawing.
1.1.11 Rotate the load limiter in both direction for checking the freeness and check
up whether the movement of the bush in load limiter unit equals that of
graduation provided on load limiter drum.
1.1.12 Check during erection that the actual full movement of speeder gear pilot
with a dial gauge installed after opening inspection cover provided on top
cover of FBP is 36 + 2.00 - 1.00.
1.1.13 Provide a dial gauge with special attachment to be fixed in the front side of
the bearing pedestal behind follow up pilot valve to measure the movement.
Adjust the dial reading to zero.
1.1.14 Provide a dial gauge with special attachment to be fixed in the top of the
front bearing pedestal just above intermediate pilot valve to measure the
movement. Adjust the dial reading to zero.
1.1.15 Check whether the steam pressure unloading gear unit is in zero position
and the pressure oil inlet valve in closed position.
1.1.16 Check whether the Hydraulic amplifier pilot spool unit of the Electric
Hydraulic Transducer is kept isolated by screwing the pilot spool towards
right stop.
1.2
System Preparation
1.2.1 Check the main oil tank level is about 30 cm. at the oil tank level indicator
when none of the oil pumps are in service and seal oil system damper tank
is full. (Zero level corresponds to 520 mm from the cover of the tank.
PMI, NTPC
117
Highest level permissible in the tank is 140 mm from the cover of the tank).
1.2.2 Check whether the lub. oil cooler inlet and outlet valves are opened
completely on the oil side.
1.2.3 Keep open the suction valves of starting, standby emergency oil pumps.
1.2.4 Keep close the valve interconnecting the lubricating and governing oil line.
1.2.5 Check whether the vapour extraction fans are in operation.
1.2.6 Check the standby oil pump and start it.
1.2.7 Open discharge valve gradually to full open position.
1.2.8 Check whether the bearing inlet oil pressure is 1 kg/cm . If not adjust the
relief valve to maintain a lub. oil pressure to bearing to 1 kg/cm .
1.2.9 Check the main oil tank level is above 10 cm. reading in level indicator.
1.2.10 Open the interconnection line from lub. oil to governing systems for
charging and complete to evacuation of air in the governing systems for
minimum 15 minutes.
1.2.11 Check that turbine trip solenoid is in de-energised condition and turbine in
reset condition.
1.2.12 Rotate the control gear in the anti-clockwise direction upto 8 mm for
charging ESV control oil line.
1.2.13 Check whether any union or flange joints are leaking in the front bearing
pedestal. If so attend to it. Then bring the control gear back to zero position.
PMI, NTPC
118
1.2.14 Turn the overspeed governor testing cock handwheel towards anticlockwise to feed oil to striker No. 1 and check whether oil is coming out
from the nozzle to the chamber of the striker No. 1 by opening the top over
in the front bearing pedestal.
1.2.15
1.2.16
Start the starting oil pump and open slowly the discharge valve.
1.3.1 After the oil temperature is raised to 50 __ 5C, the checking of governing
system is to be started.
1.3.2 Operate the control gear in anticlockwise direction and check whether the
emergency governor pilot gets reset at 2.5 J_ 0.5 mm. This can be ensured
by checking if the pressure gauge ui Emergency Governor Pilot charging
line reads 16 to 17 kg/cm .
PMI, NTPC
119
1.3.3 Check that the ESVs, IVs and CVSM are in closed condition and the scales
read zero. Check that all hand wheels for ESVs and IVs are in fully open
position.
1.3.4 Rotate the control gear in anticlockwise direction and check whether it is
possible to open the ESVs, IVs and CVSM fully.
1.3.5 Bring the control gear back to zero position and see if all the ESVs, IVs and
CVSM, have come back to full closed position.
1.3.6 Check whether at 75 mm travel of interceptor valve corresponds to position
of control gear is 5.3 + 0.8 for both right &. left valves.
1.3.7 The full opening of interceptor valves for right and left corresponding to the
travel of 1.4mm of control gear.
1.3.8 Check whether at 75 mm travel of intercepter valve for both right and left the
oil pressure under piston is 8.0 + 0.2 kg/cm2 and under pilot valve 9.0 + 0.2
kg/cm2 .
1.3.9 Check the full opening of intercepter valves for both right and left and the
total movement is 150 + 2 mm
1.3.10 Press the emergency push button for energising the electro magnet
solenoid provided on turbine tripping circuit and check whether both right
and left intercepter and emergency stop valves close fully and scale reads
to zero. The emergency, governor pilot charging line Pr. gauge should read
below 13 kg/cm .
1.3.11 Bring back the control gear to zero position by rotating clockwise direction.
1.3.12 Operate the control gear further in anti-clockwise position and check the
start off opening of the emergency stop valves.
PMI, NTPC
120
1.3.13 Check whether the emergency stop valve servornotor for both right and left
begins to open when the control gear position is 5.5 mm and fully opens
when the control gear position is 6.7 mm. The full opening of emergency
stop valve servomotor corresponds to the travel of 1.2 mm of control gear.
1.3.14 Check whether at 50 mm travel of emergency stop valve servo-meters for
both right and left corresponds to position of control gear 6.1 + 0.8 mm.
1.3.15 Check whether at 48 mm travel of the emergency stop valve servomotor for
both right and left, the oil pressure under servo-meter piston is 4.2 + 1.4/0.8
kg/cm2 and under 13 + 0.25 kg m2.
1.3.16 check the full opening of emergency stop valve for both right and left and
the total movement is 95 + 3 mm and with movement of damper is 102 + 2
mm2.
1.3.17 Press the knob for tripping turbine manually and check whether both the
emergency stop valves close fully and the scale reads to zero. The
emergency governor pilot charging line Pr. gauge reads below 13 kg/cm2.
1.3.18 Bring back the control gear to zero position by rotating in clock wise
direction.
1.3.19 Rotate the control gear in anticlockwise direction and check whether the
intermediate pilot begins to move from its bottom position when the control
gear position is 6.9 + 0.5 mm by a dial gauge provided on the top of the
pedestal.
1.3.20 Operate further the control gear and check whether the full travel of
intermediate pilot corresponds to displacement of control gear is 7 + 1 mm.
1.3.21 Bring back the control gear to a position of 8 mm.
PMI, NTPC
121
PMI, NTPC
122
1.3.22 Operate the control gear in anticlockwise direction and check whether the
control valve servomotor starts to open 9.6 mm of control gear position.
1.3.23 Open the control valve servomotor upto 60 mm and check whether the
intermediate pilot valve (from dial gauge provided) travel in 6.2 +0.3 mm.
1.3.24 Raise the opening of control valve servomotor to 142 mm and check the
control gear displacement corresponds to 1.54 + 0.3 mm.
1.3.25 Open the control valve servomotor to full and check whether it had travelled
upto 300 mm.
1.3.26 Press the knob for tripping turbine manually and check whether both the
right and left emergency stop valves and intercepter valves and the control
valve and the control valve servomotor close fully.
1.3.27 The emergency ^governor pilot charging line Pr. gauge should read below
13 kg/cm'".
1.3.28 Bring back the control gear to zero position.
1.3.29 Operate the control gear and open all emergency stop valves interceptor
valves and control valves servomotor to the full open position.
1.3.30 Press the emergency push button for energising the Electro magnet
solenoid provided on turbine tripping circuit and check whether both right
and left emergency stop valves and interceptor valves and the control valve
servomotor closes fully.
1.3.31 Bring back to control gear to zero position.
1.3.32 The emergency, governor pilot line pressure gauge should read below 13
kg/cm2.
PMI, NTPC
124
1.3.33 Operate the control gear and open fully the emergency stop valves,
intercepter valves and control valve servomotor.
1.3.34 Operate the load limiter in clockwise direction from zero position gradually
to maximum and check whether control valves servomotor starts closing
gradually to the fully closed position.
1.3.35 Operate the load limiter in anti clockkwise direction towards zero position
and check whether control valve servomotor opens to the full open position.
1.4
4.1
At some of the sites it has been found that the clearance between cam and
roller of the control valve's lever are not kept properly during assembly due
to which either the valves remain open under tripped condition or there is
undue stress on linkages. In order to avoid such type of mistakes, the
following procedure should be adopted, while adjusting the gaps between
cam & rollers at sites.
a)
Initially put 5 mm gap between the cam and rollers of all the 8
number (4 at HPC and 4 at IPC) Control valves in the cold state (at
ambient temperature). Take the governing characteristics and then
plot the curve between the angle of rotation of cam shaft and stem lift
of the valves. (Refer
b)
fig no .11-5).
Adjust the gaps between the cam and roller of each valve, so at to
get approximately the same curve as the design curve given in the
above log sheet. Then measure the gaps for each of the control
valve.
c)
Then for the side control valves of HPC these gaps be increased by
4 mm for IPC by 5 mm, to account for thermal expansion during hot
PMI, NTPC
125
condition of the turbine. Thus in the cold condition the gaps are set
as given at S.No. 3 of Table-1.
d)
The unit is started and load taken on the turbine. The final checking
of these gaps under hot conditions are again done after the unit has
run at full parameter (normal working temperature). Immediately after
turbine trips, in hot condition measure these gaps between cam and
rollers of all the 8
of Table-I.
If these gaps are same as adjusted under cold condition (as~ per
S.No. 2 of
S.No. 2 of Table-1.
f)
modified. Thus the 'Should be' gap under cold condition for that
particular turbine can be
The values of the gaps given at S.No. 5 are the final gaps to be set
under cold condition of turbine. Such that during the working of the
turbine under
further
use
&:
rollers
of
PMI, NTPC
126
TABLE-1
S.
Particulars
2 top
1 top
4 side
1.
Under Cold
Initial
5.0
5.0
5.0
5.0
2.
Under Cold
'Adjusted'
4.5
4.5
4.6
4.7
3.
Under Cold
'Set gaps'
3.5
4.5
4.6
8.7
4.
Under Hot
4.6
4.7
5.2
5.
Cold condition
4.4
4.5
8.2
PMI, NTPC
127
E. Regenerative System
1.
INTRODUCTION
1.1
2.
PREPARATIONS
2.1
Ensure that the hydraulic tests of the entire system as per the pressure
prescribed in the drawings have been completed. After all the regenerative
equipments are installed in position and tested, complete the temporary
pipe line connection as shown in the enclosed Schemes.
2.2
Close tightly all the gate valves of the steam extraction lines to heaters.
Ensure .t all the NRVS in these lines are also closed by keeping open the
drains before these NRVs in atmosphere and observing for any passing. It
should be ensured that the alkali solution does not enter the turbine,
condenser, heaters, GC-1, GC-2 and main ejectors by any chance. Valves
on the delivery of BFPs & Condensate pumps should be closed properly
prior to the flushing to prevent the entry of the flushing fluid into the pumps.
2.3
Make sure that all the chemicals and laboratory reagents and apparatus are
available.
2.4
Ensure that the required quantity of filtered water and D.M. Water is
available for the process. Steam at 8-10 Kg/Cm pressure and 150 to 200C
temperature should be available for heating the alkali solution/water.
PMI, NTPC
128
2.5
All the valves in the steam lines to and from deaerator should be closed.
2.6
2.7
All safety valves are to be removed from H.P. heaters and blanks are to be
provided with a valves for air venting. Temperature stubs in extraction
steam lines for L.P. heaters are to be used for venting of LP heaters. While
carrying out the flushing of shell side of HP and LP heaters, care is to be
taken for properly venting the heaters for proper filling.
2.8
2.9
All the orifices/flow nozzles in the system are to be removed before flushing
and if necessary to be replaced with spool pieces.
2.10
The shell side and the tube side of the regenerative equipments are to be
flushed separately as per the details given below. The flushing has to be
done as per the two schemes attached herewith. For flushing of tube coil
side refer Fig. No. II-1 and for the shell side flushing refer Fig No. 11-2.
2.11
Ensure that all the cutting and welding work, which is done on H.P. heaters
for gauge glass and level switch fittings is completed before commencing
the flushing. However they are to be blanked during flushing.
2.12
2.13
PMI, NTPC
129
alkaline flushing.
2.14
All the instruments in the system which will be subjected to flushing should
be isolated before the flushing starts, except those required during flushing.
2.15
2.16
Requirement of Materials
a)
Sodium hydroxide
1000 kg approx.
b)
Filtered water
c)
d)
Trisodium phosphate
1500 kg approx.
e)
Lissopal-D
150 kg approx.
f)
D.M. Water
g)
Alkali pumps
2 Nos.-200 T/hr.
190 MWC
or 3 Nos.-150 T/hr.
190 MWC
h)
i)
Thermometer (0-200C)
j)
Sampling bottles
PMI, NTPC
2 Nos.
12 Nos.
130
k)
50 tonnes.
3.
PROCEDURE
3.1
a) Mass flushing
b) Alkaline, flushing
c) Rinsing operation
d) Final flushing with DM water.
3.2
Mass Flushing
a)
Firstly mass flushing is done with cold filtered or raw w 'er. The mixing tank
is filled with the filtered water and then the system is also completely filled
with it. After filling the system open the drain do as to drain the water. Again
fill the system with water. Now run the system for 30-45 minutes with D1.
closed and D1, open. After running for this time stop the pumps and drain
the complete system and again refill the system, repeating this procedure till
the effluent is clear.
b)
For hot water flushing close the drain valve D1, and the inlet valve of water
V1, to the mixing tank and me system on recirculation by opening the valve
D1. Start heating the water in the mixing tank, by opening the steam valve
V1, and keep the system on recirculation for about 8 hours with the
temperature of water at about 80C. Then drain the complete system by
closing the valve D, and opening the valve D,,. The process of hot water
mass flushing is deemed complete when the turbidity and conductivity of
water at inlet and outlet are same.
PMI, NTPC
131
3.3
Alkaline Flushing ;
Fill the mixing tank with filtered water and raise its temperature to 50C by
admitting steam through the steam valve V-,. Start the alkaline pump and fill
the system completely. Keep the system on recirculation for 15 to 20
minutes till the temp. of water in the entire system comes to about 50C.
Then chemical reagents may be added in the following quantities in the
mixing tank and properly mixed by starting one of the pumps and opening
the valve V. of the recirculation line and keeping the valve V, in the closed
position.
a) Trisodium phosphate
b) Sodium hydroxide
c) Lissopal - D
Lissopal - D. must be mixed little by little observing the foaming in the tank.
After mixing the chemicals to the required concentration raise the
temperature of the solution to 80C, which is to be maintained throughout
the process. Open valve V5 and close the valve V5. Check the
concentration and if necessary add more chemicals to bring the chemicals
to the desired strength. Keep the loop under circulation, at these conditions
for 10 hours. The samples are taken from inlet and outlet ends of the loop at
intervals of every hour and are to be analysed for mechanical impurities,
iron content and PH value. The process should be deemed as complete
when the above values are same at both inlet and outlet ends. Then drain
the complete loop through valve D0, and stop the circulation.
3.4
PMI, NTPC
132
left over on the surfaces, after alkali flushing. Fill the mixing tank with DM
water by opening the valve V-. Start the alkaline pumps and fill the system,
keep the loop on 'circulation for 15 to 20 minutes. Then open the drain D,,
by a little amount. Make up the level in the mixing tank by DM water. Try to
drain maximum quantity of water from the system continuously throughout
the operation. The samples are taken at outlet and at the interval of 1 hour,
and analysed for phosphate, alkaline contents and conductivity. The
conductivity and PH value of DM water used is also found out. The rinsing
process is deemed to be complete when the conductivity, and PH value are
same at outlet end as at the inlet end. Then drain the complete system.
3.5
Flushing with DM Water: After rinsing operation, final mass flushing should
be done with DM water. Fill the mixing tank and the system with DM water.
Raise the temperature of water to SO'C. Keep the system under circulation
for sometime and drain the system.
3.6
3.6.1 Make the temporary connections as per the scheme shown in the Fig. No.
11-1 The suction and discharge side valves of condensate pumps and
discharge side valves of BFP remain in closed position.
3.6.2 The complete scheme has been divided into three loops and at a particular
time only one of the loop is put into circulation for flushing operation.
a)
b)
PMI, NTPC
133
bypass line and discharge line of feed pumps. This loop can be put
into circuit by opening valves Nos. V-5 and V-6 and closing valves V4, V-7 and V-8.
c)
3.7
Mass flushing of the system is done in two stages. First the loops have to
be flushed with COLD WATER and thereafter with HOT WATER. The
circuitry for mass flushing shall be as follows:
Mixing tank-circulation pump - condensate pump discharge line ejector bypass, GC-1, bypass, LPH-1 bypass, GC-2 bypass, - bypass
lines of LPH 2,3,4 and then to mixing tank from a point before the
deaerator. The flanges at the inlet and outlet of the GC-1 & GC-2 are
to be blanked during the flushing.
b)
Mixing tank - circulation pump-condensate pump discharge line then through ejector and by passing ail other equipments, GC-1 and
by passing all other equipments, then LPH-1 and by passing all other
equipments, then GC-2 and by passing all other equipments then
LPH-2 and bypassing all other equipments, then LPH-3 and by
passing other equipments, and finally through LPH-4, by passing all
other equipments - to mixing tank.
PMI, NTPC
134
PMI, NTPC
135
3.7.2
a)
Loop No. 2
Mixing tank - Circulation pump - feed pump discharge line - bypass
line HP heaters - feed control station to mixing tank from a point
before the NRV of economiser inlet valve.
b)
Mixing tank - Circulation pump - feed pump recirculation line deaerator feed storage tank - suction of BFP - Mixing tank through
strainers at the suction of BFP.
3.7.4 After mass flushing, the loops are to be alkali flushed as per description
given in para 3.3 above. The circuitry for the alkali flushing shall be as
follows:
a)
Loop No. 1
a)
b) Loop No. 2
a) Same as in 3.7.
b) No alkali flushing through the tubes shall be done.
c)
Loop No. 3
a) Same as in 3.7.
3.7.5 Rinsing operation, after alkaline flushing is to be carried out as per circuitry
PMI, NTPC
136
4.
4.1 Make temporary connecting as per the scheme shown in the Fig. 11-2.
4.2
4.3
The mass flushing of the system is done in two stages. First the loop is
flushed with COLD WATER and then with HOT WATER. The circuitry for
the mass flushing shall be as follows:
4.3.1 Fill the individual HP healers and then drain the complete system by fully
opening the bottom shell drains.
4.3.2 Mixing tank - Circulation pump - extraction steam line to HPH-7 downstream
of valve ES-2 shell side of HPH-7 Through heater drain of HPH-7 shell side
of HPH-6. Through heater drain of HPH-6 shell side of HPH-5 Through
heater drain of HPH-5-Shell side of LPH-3 Through heater drain of LPH-3
shell side of LPH-2-to mixing tank through temporary line, by opening valve
no. V-10.
4.4
4.4.1 Remove all the temporary lines 01 the loop and isolate the mixing tank and
alkaline pumps suction, from the permanent operation scheme.
PMI, NTPC
137
4.4.2 Make and check that all the pipe-lines and connections as per the final
scheme of the normal operation.
4.4.3 Fill the condenser hot well with D.M. water and run the condensate pump,
thereby filling the deaerator completely. Open the drainage of the deaerator
and drain it completely.
4.4.4 After draining the deaerator inspect it from inside for it's substance and
clean thoroughly.
5.
5.1
Alkaline solution may cause Skin burning and as its fuels are injurious to
eyes, all the safety precautions must be taken during alkaline flushing.
5.1.1 The operators and workers must use rubber gloves, eyes protecting
glasses, Approns, Gum boots, masks etc. While flushing process is going
on and they are working on the job.
5.1.2 Due precautions must be taken while tightening the flanges of temporary
pipe joints of the loop so that they do not leak when the pumps is started
and thereby a spray of alkali leaks through these joints.
5.1.3 Before a person enters the deaerator for inspection, its manhole may be
kept opened for 8 - 10 hours and air nay be forced in the deaerator during
the period.
5.1.4 No drilling, welding or cutting operation are allowed during the process.
6.
HP/LP HEATERS
6.1
Checks
PMI, NTPC
138
6.1.1 Check whether the heater connections, both on water side as well as steam
side are as per scheme.
6.1.2 Check the extraction drains of each heater and confirm whether they are as
per drawing.
6.1.3 Check whether the heater deaerations are provided on water side as per
scheme.
6.1.4 Check whether the safety valves are mounted after duly testing
hydraulically. Set pressure of the safety valve should also be checked.
6.1.5 Check the relief valve on water side of L.P.H. are mounted after duly testing
hydraulically.
6.1.6 Check all the hand operated valves for their freeness.
6.1.7 Check whether the gate valves and regulations valves are operating
properly and its limit switches are functioning for full opening and full closing
position.
6.1.8 Check whether the float switches are mounted as per drawing and ensure its
proper functioning.
6.1.9 Check whether the shell and extraction line pressure gauges are mounted
as per scheme, after duly calibration.
6.1.10 Check whether the thermometers are mounted properly in water side and
steam side.
6.1.11 Check whether the level instruments are placed in the panel, after duly
calibrating the same.
PMI, NTPC
139
6.1.12 Check that the resistance thermometers are provided as per the scheme
and the same is being properly transmitted to control room.
6.1.13 Check the gauge glass for proper mounting.
6.1.14 Check and ensure the availability of the drip pump after complet-ion of
motor trial.
6.1.15 Check for the insulation of the heaters and its connected pipelines
6.2
Commissioning of LPH
6.2.1 Ensure water side is through and all its by passes are closed.
6.2.2 Check that the cascading drains of all extractions are in open condition.
6.2.3 Check whether the FC NRV water side is kept in charged condition and its
NRV servomotors are in open position.
6.2.4 Check the supply availability for the FCNRV protection solenoids.
6.2.5 Check if the drains between FC NRVs and the heaters are in open
condition.
6.2.6
6.2.7
6.2.8 Check if the deaeration line of each heater (steam side) is opened to
condenser, or to the lower heater as the case may be.
6.2.9 Open slightly the steam extraction electrically operated valve bypass or
PMI, NTPC
140
Commissioning of HPH
6.3.1
Check that the water side is through and its by pass is closed.
6.3.2 Check that the cascading drains of all extractions are in open condition.
6.3.3 Check the drain between the NRVs and the heaters are in open position.
6.3.4 Check that the shell drains are in closed condition.
6.3.5 Check that the cascading drains of heaters are through.
6.3.6 Check that the deaeration of heaters on the shell side are connected to
condenser through LPH.
6.3.7
PMI, NTPC
141
PMI, NTPC
142
6.3.8
6.3.9 Operate the group protection valve and check whether the bypass of HPH,
opens fully and closing command goes for isolation of heaters on water side
by closing inlet and outlet valves.
6.3.10 Recharge the heaters back and check the same operation as 6.3.9 by
actuating the group protection solenoid.
6.3.11 Charge the heaters in water side once again.
6.3.12 Open slightly the steam valve on the extraction line to warm up the line.
6.3.13 Open shell drain and steam air vent for proper warming up.
6.3.14 After proper warming up close the shell drains and air vent and open
gradually the steam valve and observe the level in the heater gauge glass.
6.3.15 Open the steam valve fully and maintain the heater level at normal value, by
keeping the level controller in manual channel.
6.3.16 After satisfactory performance of level controller in manual channel, change
over the auto channel.
6.3.17 Check whether the heater drip is connected to condenser at low loads.
6.3.18 Ensure whether the heater drip is changed over to deaerator at high loads.
6.3.19 Cut in the high level protection circuit in operation for tripping the unit
whenever any of the heater level raises beyond pre set value.
PMI, NTPC
143
7.
7.1
TESTS :-
a)
Constructional Tests
b)
Pre-commissioning Tests
c)
Commissioning Tests
7.1.1 Constructional Test : These will comprise the normal functional trials o?
mechanical & electrical plant through out the system to prove erection and
will be carried out, concurrently with the erection of plant.
7.1.2 Pre-Commissiomn R Tests : These tests will be carried out when
construction is substantially complete and will entail the following :a)
b)
c)
d)
e)
f)
Commissioning of A.O.P.
g)
PMI, NTPC
144
h)
i)
j)
k)
l)
m)
7.1.3 Commissioning Tests ; These tests will involve the initial operation of
system to demonstrate that it is operationally sound and conforms to the
tests comprise the following operations :
a) Starting and operation of Boiler Feed Pumps.
b) Automatic starting of stand by Boiler Feed Pumps.
c)
PMI, NTPC
145
F. Barring Gear
1.
1.1
PREPARATION
Check whether the barring gear assembly is dismantled, serviced and
assembled again in position, ensuring the required clearances in the gear
systems.
1.2
1.3
Check and ensure that the motor is decoupled from the barring gear unit
1.4
1.5
Start the starting oil pump and check whether lubrication oil pressure is
between 1.0 to 1.2kg/cm at 40 to 50C oil temperature,
1.6
1.7
Check the drain oil piping of each bearing for proper flow.
1.7.
Lub. oil flow to bearing No. 1 should be checked by running the A.C.
standby oil pump and closing the charging line of the governing system.
This way only lub. oil will be flowing, through the drain. It should be ensured
before hand that there is no leakage from the line taken as tap off from Brg.
No.l supply line for oil supply to MOP seals techno motor shaft &: gear
coupling lubrication, otherwise considerable quantity of oil will be bypass
from Brg. No.l. Check that adequate quantity of oil is visible in the drain
sight glass.
PMI, NTPC
146
1.7.2 For checking whether adequate quantity of lub. oil is flowing to the
generator bearings, stop the seal oil system and check whether adequate
quantity of oil is flowing through the drain sight glass with BG disengaged
condition.
1.7.3 For checking whether adequate quantity of seal oil is flowing to the
generator scale, stop all lub. oil pumps and run the A.C. seal oil pump
alone. Charge the seal oil system and observe if adequate quantity of oil is
flowing if adequate quantity of oil is flowing through the drain sight glass.
By these procedure adequate quantity of lub. oil to all the bearings and seal
oil to the generator seals is ensured.
1.8
Check in the front bearing pedestal whether all lubrication oil connections
were made properly.
1.9
Check whether the protection for cutting off the barring at lubrication oil
pressure of 0.3 kg/cm is connected.
1.10
Check whether the limit switch installed for cutting off the supply to solenoid
(intended for auto engaging) whenever barring gear engages and trips off
the motor whenever the barring gear disengages is connected properly.
2.
2.1
Arrange for the electrical connection to the barring gear motor and ensure
the electrical soundness of the motor for energising.
2.2
Start the motor and check the directions of rotation of the motor.
2.3
PMI, NTPC
147
2.4
3.
3.1
3.2
3.3
Rotate the barring gear assembly with the rotating disc. in clockwise
direction and check its freeness of the gear train.
3.4
Check whether lubrication oil pressure is normal. In case A.C. standby oil
pump is running the charging line to gov. sys. should be open.
3.5
Check whether the return oil flow from all the bearings are normal.
3.6
Engage the barring gear with the turbine shaft by rotating disc. in clockwise
direction and simultaneously pushing the engaging lever.
3.7
Check whether lubrication for barring gear assembly is proper during oil
flushing.
3.8
3.9
Try the auto engaging of the barring gear (Caution : Without giving supply to
barring gear motor by switching off the CB) by giving supply to engaging
solenoid and simultaneously rotating the rotating disc by hand.
3.10
PMI, NTPC
148
3.11
3.12
Check whether protection for tripping the barring gear when the lubrication
oil pressure drops to 0.3kg/cm is available.
3.13
Check whether A.C. and D.C. emergency oil pump auto scheme is
available.
3.14
Check whether bearing metal temperature, and seal oil system temperature
recording instruments are in working condition.
3.15
Check whether local glass thermometer for measuring the drain oil
temperature are placed in position.
3.16
3.17
Check whether seal oil system is in service with proper oil pressure with
compressed air filled. And also proper interlocks for the seal oil system is
available.
3.18
3.19
3.20
Start the barring gear and note down the starting current and normal
current.
3.21
Check for any abnormal noise at turbine glands and bearings with a hearing
PMI, NTPC
149
Stop the barring gear. Note down the coasting down period. Start the B.G.
again.
3.24
3.25
Watch the return oil temperature from oil bearings and from the generator
seals also.
3.26
Note down the eccentricity value at the control room and at the bearing
No.2 pedestal (dial gauge). It should be same at UCB and Brg. No.2.
3.27
Check once again at turbine glands and generator seals for the healthy
condition. Measure the vibration at Barring Gear Pedestal and at bearing
covers of worm shaft and meter.
PMI, NTPC
150
Vacuum tightness test, is carried out to find out the leakages, if any, in the
vacuum system before first rolling of turbine. This test should be carried out
before the various lines are insulated. This is done in two phases.
1.1
1.2
2.
2.1
This test should be done only when the casing temp. below 50C, if it is
done after synchronisation.
2.1.1
Check whether r" the piping in the vacuum system are completely erected.
The circuit which come under vacuum are HP Cylinder, reheater, IP
cylinder, LP Cylinder, condensate flash tank, HP and LP bypass system,
extraction lines of HP and LP headers, condenser, flange and stud heating
system etc. R.H. should be prepared for raising vacuum.
2.1.2 Check whether all the valves provided are as per the piping -scheme.
2.1.3 Prepare a list of dummies to be provided before filling up of the system.
2.1.4
Check whether gland sealing lines are provided for all the valves which
come under vacuum as detailed at item No. 9.4,1 and ensure that these
lines are flushed and proper flow is established at the open and before
finally connecting these lines.
2.1.5 Check whether all the drain valves in the condenser system and HP heaters
PMI, NTPC
151
Provide a transparent tube at the header or any steam side vent upto 9
meters to know the level in the system during filling up.
2.1.7 Check whether the gauge glasses are provided in Hotwell, GC-1 and all the
LP & HP heaters.
2.1.8 Check whether props/jacks are provided for the condenser spring supports
for jacking purpose during fill test. These props/jacks should be removed
before raising vacuum.
2.1.9. Connect all LP heaters, GC-1, GC-2 and drain expander to the condenser.
All vacuum gauges are to be isolated.
2.1.10
2.1.11
Keep the suction discharge and desecration valves of all the condensate pumps in open position.
2.1.12
Keep closed the valve from condensate pump delivery to the sealing
header for sub-atmospheric valves.
2.1.13
2.1.14
Close the valves in the syphone filling lines (15 M syphon for drain
expander <5c 3 M syphon for ejectors) and isolate them from the
main condensate line.
2.1.15
PMI, NTPC
152
open.
2.1.16
2.1.17
Keep open the air line valve of starting ejector and close the and
exhaust line drain valves.
2.1.18
Keep open the air line valves and the drain valve to condenser of
both main ejectors, (the pressure testing of the ejectors done
separately).
2.1.19
2.1.20
a)
Condenser
b)
c)
LPHs
d)
HPHs
Keep open the deaeration line valves to condenser from LPH 2,3 &
4.
2.1.21
2.1.22
2.1.23
Check whether turbine bottom casing insulation has not been taken
up.
2.1.24
Keep open all heaters extraction valves. Check the level indicating
instruments, pressure & vacuum gauges of LP heaters 2, 3 &: 4 are
made ready.
PMI, NTPC
153
2.1.25
Open the transfer pipe drain valves of HP <5c IP cylinder and curtis
drain valves to condensate flash tank (CFT).
2.1.26
All drains of CFT to be open. Keep the extraction force closing NRV
drains to condensate flash tank in open position (i.e. 7, 6, 5, 4, 3 & 2
steam extraction line NRV).
2.1.27
Provide dummy at the air & steam mixture exhaust flange oi gland
steam cooler.
2.1.28
Keep open CRH and HRH drains to condensate flash tank. Close the
gland steam inlet and its bypass valve.
2.1.29
Keep open the individual valves loading to all turbine glands and the
header drain to condensate flash tank.
2.1.30
Keep open flange and stud heating return line to condenser d its
drain but isolate it from the main steam line.
3.
3.1
Analyse the DM water before filling .up, check PH value corresponds to 7-8
and conductivity below 1 micromhos.
3.2
3.3
While filling up check whether there is any leak and arrest the leak
immediately if noticed.
3.4
If the leak noticed is heavy in nature stop the filling. Attend the leak, then
proceed for further filling up.
PMI, NTPC
154
3.5
Once the water reaches the bottom portion of gauge glasses of LPH's 2, 3
& 4 start watching the float switch operation while further filling up of LPH-2,
3 & 4.
3.6
Stop filling, when the LPH-4 gauge glass level is about 90%.
3.7
3.8
3.9
Check whether all the float switches operation and level instruments are
found satisfactory. Isolate float switches of LPH's, GCII whenever system
filled above normal level.
3.10
3.11
3.12
Check for any leakage in the tubes of condenser, watch the level for about
24 hours and whether the level remains constant or goes down. In general
level drop of about 2 to 3 cms. in 24 hours may be allowed.
3.13
If the level goes down check the system thoroughly again for any leakage
and attend to the defects.
3.14
After ensuring that there is no leak in the system, start draining the
complete system.
3.15
PMI, NTPC
155
3.17
Remove the props/jacks provided for the spring supports of the condenser.
3.18
Check whether the dummies provided for carrying out leak tests are
removed and the connections are made through as per the scheme.
3.19
It is recommended to conduct this test 2-3 tunes before first vacuum raising.
4.
4.1
4.2
4.3
Put the turbine on barring gear when the oil temp. is mm 38C.
4.4
4.5
Check whether a 'U' tube manometer is installed for measuring the vacuum
directly.
4.6
Check whether the atmospheric drains of CRH and HRH lines are closed
4.7
Isolate the HP heaters drip line, which are connected to the condenser and
vacuum circuit.
4.8
PMI, NTPC
156
4.9
4.10
Keep all drain lines to CFT open. Open all inspection lines to check all pipes
are without water and close the inspection valves after checking. Prepare
the main condensate circuit through ejector, gland steam cooler and all
heaters. Close the outlet valve of the LPH-4 on main condensate side.
4.11
Start one main condensate pump and keep it under recirculation through
ejector and gland steam cooler.
4.12
Fill the 15 M siphon line from main condensate and check individually as
per list at Seriatim 9.4-1, that the valves which are coming under vacuum
are sealed with water from the discharge of condensate pump.
4.13
Aux. steam for Gland sealing, GC-1 & Ejectors may be taken through Aux.
PROS.
4.14
Warm up the steam lines of gland steam cooler, ejectors and gland steam
header after opening their respective drains and by opening their respective
steam inlet valves.
4.15
Commission the gland steam cooler and maintain suction pressure from
glands at about 80 mm of mercury column vacuum.
4.16
Open the steam valve of starting ejector by one or two turns for warming up.
After sometime, open the steam valve fully.
4.17
Open the air valve gradually and observe the raise in vacuum.
4.18
Check whether condensate from the delivery of condensate pump for drain
expander is opened.
PMI, NTPC
157
4.19
After changing the ejector^ starting scaling the glands for all three casings
with steam parameters temp. min 150C pr. - 0.1 .to 0.2 atg.
4.20
Take both the main ejectors in service by opening their steam valves.
Ensure that the 1st stage drains at the ejector to the condenser is in open
position.
4.21
4.22
Open the air valve gradually and observe the raise of vacuum in the system.
4.23
4.24
Cut off the starting ejector by first closing the air valve and then the steam
valve when the vacuum becomes constant and note its value. If air valve is
found passing keep open steam valve.
4.25
4.26
Wait till the full vacuum is reached i.e. when it becomes constant. Now cut
off one of the main ejectors. Vacuum is good if it is around 96 to 97%.
4.27
4.28
Check the following with the candle or shock pulse meter if available after
obtaining full vacuum:
a) Parting plane of the LP casing.
b) Explosion diaphragms points.
PMI, NTPC
158
c)
After finishing the vacuum test, the ejector can be cut off by closing the air
valves and steam valves.
4.30
Close the drain valves of both the main ejectors. Note down the rate of drop
of vacuum of mercury column.
4.31
When the vacuum drops to 50 mm of mercury column cut off the sealing
steam of all three casings and cut off gland steam cooler. Also open the
vacuum breaker immediately.
4.32
4.33
PMI, NTPC
159
PREPARATION
1.1
1.2
1.3
1.4
Fill up the feed tank and condenser hotwell upto the normal level.
1.5
Ensure, the control and annunciation circuits for regenerative system are
working satisfactorily.
1.6
Check whether all the differential expansion pick-ups are mounted properly
and their annunciations at the control room are okay.
1.7
Check whether the shaft eccentricity pick-up is mounted properly and its
annunciation at the control room is okay.
1.8
1.9
Check whether the main oil tank high & low level annunciations appear at
control room, while testing the level switches.
1.10
Start the cooling water pump and charge the condenser. Open the air vent
PMI, NTPC
160
1.12
Check that the cooling water is available for oil auxiliaries and the oil
coolers.
1.13
Check the oil level in the bearing and rotate the A.C. standby oil pump rotor
by hand as per direction shown on the pump, before starting the pump and
ensure the deaeration of the pump also check whether cooling water is
available to the bearing.
1.14
1.15
Start the A.C. standby oil pump. Open delivery valve slowly to evacuate the
air and to charge the system with oil. \.
1.16
Run the pump for 10 minutes and check that the return oil flow from each
bearing through the sight window is adequate.
1.17
Open the inter connection line from lub. oil to governing system for
evacuating the air and charging the governing elements with oil. It normally
takes 8 to 10 mins. for proper charging.
1.18
Start the starting oil pump, open the delivery valve slowly and check
whether it develops a pressure of 16 to 17 kg7cm when the delivery valve is
fully opened.
1.19
Stop the standby oil pump and check whether the lub. oil pressure remains
same or above 1.0 kg/cm .
PMI, NTPC
161
1.20
Ensure that the A.C. standby oil pump cuts into service when the lub. oil
pressure drops to 0.6 kg/cm by operation of the oil pressure drc slay.
1.21
Ensure that the D.C. Emergency oil pump cuts into service when the lub. oil
pressure drops to 0.5 kg/cm by operation ot the oil pressure drop relay;
1.22
Switch on all the instruments at control room both recording and indicating
types.
1.23
Check that "Bearing Babbit Temperature High" and "Lub. oil temperature
high after oil coolers", annunciations appear in control room by making the
contacts of the respective relays.
1.24
Maintain the lub. oil temperature after the oil cooler around 40 to 45C.
1.25
Check that the oil channels around the front and middle bearing pedestals
are clean and not clogged. Also check the clearances of the key ways of
HPT and IPT (Sliding surfaces) along the expansion path for any checking.
The spherical washers of the LPT spherical washers of the LPT should be
free.
1.26
Check the interlocks of the barring gear. Ensure that the lub. oil to the
barring gear drive is available. Check the Barring gear operation for auto
engagement.
1.27
Ensure that the seal" oil system is put into operation and the respective
interlocking and protection systems are available.
1.28
1.29
Remove the fuse from motor control circuit and check the protection of or
tripping of barring gear motor by draining the oil near OPDR.
PMI, NTPC
162
1.30
1.31
When the turbine is on barring gear note down the following readings:
1.32.1 Check whether the main steam, cold reheat, hot reheat, expander drains
are in full open position.
1.32.2 Check whether these drain lines are getting hot during warming up.
1.32.3 Close all the valves of LP heaters and HP heaters on the steam side.
1.32.4 All the solenoids for force closing NRV's on extraction side should be in deenergised condition.
PMI, NTPC
163
1.32.5 Gland steam leak off line is to be diverted to LPH4 and rotor heating lines
are to be isolated.
2.
2.1
Ensure that ESVs, IVs and CVs are fully closed. Start the main condensate
pumps and keep it in recirculation. Ensure proper deaeration of the main
condensate line from GCI and from the main condensate line.
2.2
Ensure that all gland seal valves in vacuum system are sealed with
condensate water.
2.3
Ensure that the 15 M syphon, LPH-1 syphon etc. are filled. Check whether
an orifice is there in the 15 M syphon filling line.
2.4
Check whether main steam admission electrically operated valve and its
bypass valves are in closed condition.
2.5
Keep closed the HP & LP bypass system and EV-1 and EV-2 valves.
2.7
Check whether the vacuum breaker is fully closed. Also check whether the
reheater vents are closed.
2.8
PMI, NTPC
164
2.9
When the vacuum reaches about 100 mm seal all the HP, IP <5c LP glands.
2.10
2.11
Take both the main ejectors in service and ensure that the 1st stage drain is
open. Cut off the starting ejector at 500-600 mm of Hg vacuum.
2.12
2.13
After attaining the full vacuum, check the following turbine protections.
2.13.1
2.13.2
2.13.3
2.13.4
2.13.5
2.13.6
2.13.7
2.13.8
PMI, NTPC
165
2.14
2.14.1 Emergency stop valve servomotor limit switch act and following actions
occurs:
a)
b)
The solenoid valves for positive closing of extraction line NRVs get
opening command by closure of one or both ESVs.
c)
2.14.2 Interceptor valve, servomotor limit switches act and following actions occur:
a)
b)
The solenoid valves for positive closing of extraction, line NRVs get
opening command by closure of one or both IVs.
c)
2.14.3
2.14.4
The solenoid valves for positive closing of extraction line NRVs should
reclose after closing of main stop valves and their bypass valves.
2.1.5
Check whether emergency stop valves closed when the oil pressure in
the governing system drops into 10 kg/cm (gauge) and interceptor
valves close when it drops to 6 kg/cm .
PMI, NTPC
166
3.
3.1
Before HP/LP bypass stations are brought into operation, check the
following:
3.1.1 Emergency stop valve & interceptor valves are in closed position.
3.1.2 Oil system of bypass system is put into operation.
3.1.3 Vacuum in condenser is more than 540 mm of Hg column.
3.1.4 Condensate flow to steam throw off devices in the condenser are
established by opening the respective motor operated valves.
3.2
Ensure that all the valves in the bypass system are fully closed and the
respective position indicator reads zero.
3.3
3.4
3.5
Put the LP bypass valve on auto mode and set the temperature set point of
LP bypass station to 200C,
3.6
3.7
Check that the HP turbine evacuating valves EV1 and EV2 and bypass
valves across NRV of cold reheat lines are tightly closed.
3.8
Check whether the superheat flow has been established through the start
up vent.
PMI, NTPC
167
3.9
3.10
If the heating rate of steam lines exceeds me prescribed limits adjust the
position of HP bypass valve to bring down the heating rate within
permissible limits.
3.11
After warming up CRH and HRH lines close the HP & LP bypass and bring
the reheater under vacuum.
3.12
Conduct the test for checking the tight closure of interceptor valves.
3.13
3.14
Make sure that MSV. & its bypass, ESV's, IV's & control valve servometer
are in closed condition.
3.15
Check that steam is not supplied to reheat circuit, through HP bypass valve
from main steam circuit.
3.16
Turn the speeder gear in anti-clockwise direction and open the ESVs, IVs
and control valves of IPT.
3.17
3.18
PMI, NTPC
168
3.19
3.20
While doing the above operation constant watch should be there on the
operation of the barring, gear. If any time, turbine gets speeded up, close
and HPBP, and bring the reheater circuit under vacuum by operating the
LPBP.
3.21
3.22
3.23
Gradually raise the reheater pressure to 4 ata, and check that the
differential pressure in the manometer is less than ^0 mm of mercury
column, it can be construed that the interceptor valves are having tight
closure.
3.24
Close the HPbP system and move the control gear in clockwise direction to
close ESV, IV & IPT control valve.
3.25
3.26
3.27
3.28
PMI, NTPC
169
3.29
Check that the steam pressure in the hot reheat line which should be less
than 1 kg/cm (gauge) before starting the heating of steam admission pipes. If the pressure in the hot reheat line exceeds 1 kg/cm and if the
vacuum is deep, the barring gear may disengage during warming up of
steam admission pipes of 1PT control valves due to side control valves of
IPT have been provided with built in relief holes through which steam may
leak.
3.30
Open ESV upto 10 to 20 mm as per the scale. Care should be taken so that
control valves of HP turbine should remain closed.
3.31
Keep open the transfer pipe drains, cylinder drain & extraction drain, of HP
Turbine.
3.32
Open the MSV bypass valve little by little for warming up transfer pipelines
of HP turbine upto control valves to a temperature of 150C.
3.33
Open the bypass valves across NRV in cold reheat line and heat the HP
turbine upto 150C.
3.34
Open the transfer pipe drains, cylinder drains and extraction drains of IP
turbine;
3.35
3.36
Heat the steam admission line upto control valves of IP Turbine upto a
temperature of 100C.
3.37
During the process of heating the pipelines of HP & IP turbines ensure that
the drain system is working normal and there is no clogging of drain lines.
PMI, NTPC
170
3.38
Close the bypass valve of MSV, ESV's and NRV by pass in the cold reheat
lines when the steam parameters before MSV are 20 kg/cm and 270 280C and HPT steam admission pipes casing are heated upto 150C.
3.39
Close the IVs when the steam admission pipes of IPT are heated upto
100C. The IP casing temp. should be preferably between 75to 80C
minimum to avoid condensations of steam in IP casing.
3.40
Manually close the HP bypass valves and when the pressure in the reheater
reaches condenser pressure, close the LP bypass manually.
PMI, NTPC
171
I.
a)
b)
Time for opening and closing of all motorised valves indicating the condition
of operation.
c)
Vacuum tightness test, i.e. rate of drop of vacuum with the valve, between
condenser and ejector in closed position.
d)
Time to build up the vacuum of 600 mm with the starting elector or plus
normal -ejector indicating the ejectors which were ir-operation while pulling
the vacuum and indicating the steam parameters to the ejector.
e)
Vacuum sustained by the machine when only one x 100% normal ejector is
in operation at full load.
f)
Condenser cooling water inlet, outlet and corresponding vacuum at full load
with valves in circulating lines fully open with normal level of condensate in
the hot well.
g)
h)
PMI, NTPC
172
i)
b)
c)
d)
Discharge pressure of MOP then both MOP and SOP are running.
e)
The setting at which SOP, EOP and seal oil pumps cut in.
j)
Vibrations in all the three directions in all the bearings of turbine generator
and also in the pedestal and foundation indicating exactly the position
where the pick Ups have been placed while taking these readings at 3000
rpm.
k)
l)
The time for machine to come to rest from 3000 rpm, both with and without
breaking the vacuum.
m)
Time taken for operation of ESV, IV & control valve to close on full load
throw off and the maximum speed obtained alongwith a curve of time
against speed till the speed is stabilised.
n)
Time required for operation of forced closing non-return valve (with the help
of XY recorder).
PMI, NTPC
173
o)
p)
q)
Differential expansion at 3000 rpm. 40% load, 60% load, 80% load and
100% load.,
r)
Steam parameters and flow at inlet to emergency stop valve at 3000 rpm.,
40% load, 60% load, 80% load and at 100% load and corresponding
vacuum.
s)
t)
u)
Quantity of make-up oil required every month in the main oil tank.
v)
Rate of hydrogen consumption after ensuring that the bottles used are
100% full.
w)
Results of oil sample from generator transformer for the chemical analysis
and dielectric strength.
x)
PMI, NTPC
174
y)
z)
zb)
zc)
zd)
ze)
*)
PMI, NTPC
175
1.1
1.2
a)
b)
i)
ii)
iii)
Rotor winding
Slip rings shorted together to rotor shaft (rotor shaft grounded).
15 Sec. and 60 Sec. values should be taken with 500 V megger.
c)
d)
e)
PMI, NTPC
176
f)
g)
h)
i)
j)
k)
Generator end shield oil catcher at exciter end to stator with 1 kV megger.
I)
m)
Generator fan shield to end shield (exciter side) with 500 V megger.
1.1.2 For H.P. excitation system the insulation resistance of following should also
be measured and records maintained.
a)
b)
c)
d)
PMI, NTPC
177
1.1.3 For static excitation system the insulation resistance of following should also
be measured and records maintained.
a)
b)
Rectifier power stage field breaker, plus and minus poles to ground
with 500 V megger.
c)
Field breaker, rotor brushes, plus and minus poles with 500 V
megger.
1.2
1.2.1
b)
ii)
c)
Generator R. T. Ds.
1.2.2 Also carry out the following ohmic resistance measurements of H.F.
excitation system.
PMI, NTPC
178
a)
b)
c)
d)
PMI, NTPC
179
EQUIPMENT INSPECTION
1.2
2.
CONTROL PANELS
a)
Ensure that the panels are grouted firmly and anti vibration/shock absorbers
mountings are provided.
2.2
Check and ensure cleanliness of the panels and all panel mounted
equipments. Also ensure that the panels are adequately covered to avoid
ingress of dirt and dust.
2.3
Ensure that the mounted equipments e.g. relays contactor", eu-are free
from mechanical damage.
2.4
Ensure that all the terminals of the various terminals blocks are in good
condition i.e. free from rust, mechanical damage and the fixing is sturdy and
rigid.
3
3.1
PMI, NTPC
180
4.1
5.
OIL INJECTOR
5.1
5.2
6.
6.1
Ensure that ILI is mounted vertically, the plunger with the ball should be free
to move and the coils should be healthy.
7.
7.1
Ensure that the hydraulic test at 12 kg/cm for 15 minutes has been
completed.
7.2
Ensure that the oil and water pipings are connected properly at the inlet and
outlet of the coolers. Also ensure that the coolers are connected in parallel
PMI, NTPC
181
7.4
8.
8.1
8.2
Ensure that the filter elements are free from mechanical damage.
9.
DAMPER TANK
9.1
Open the damper tank end covers and check the cleanliness of the tank.
9.2
Ensure that the elevation of the tank and ILIs mounted on the riser pipe
above the tank are as per the scheme.
10
10.1
Ensure that the inlet/outlet connections, oil and gas impulse connections are
as per scheme and that DPR height -corresponds with the centre line of the
TG.
10.2
Strip open the DPR and ensure the cleanliness of the piston, cylinders,
sleeves and dead weight discs. The ports should be clean and unblocked.
10.3
Measure the clearance between the piston and sleeves at the sealing
zones. The radial clearance should be less than 0.03 mm.
PMI, NTPC
182
10.4
Ensure that the ends of the grooved portion of the piston should be sharp
and surface of the piston and sleeves should be smooth and shining.
11.
11.1
11.2
Strip open the POR and ensure the cleanliness of the piston, cylinders,
sleeves and dead weight discs. The surface finish should be smooth and
shining. The ends of the grooved portion of the piston should be sharp. The
ports of the sleeve and cylinder should be clean and unblocked.
11.3
Measure the clearance between the piston and sleeves at sealing zones.
The radial clearance should be less than 0.03 mm at the top sleeve zone
and it should be within 0.05 mm at the middle and bottom zones.
12.
12.1
Check -the mounting platform of the exhaust fan and motor for rigidity.
12.2
Overhaul the fan and motor, if they were stored for more than one year.
Check for mechanical damage.
12.3
13.
13.1
Check that the piping erection has been completed as per scheme, all the
PMI, NTPC
183
pipes and equipments are properly supported, flange joints are tightened
perfectly and proper gaskets of good quality and correct sizes are provided.
Ensure that the gaskets are not protruding in and obstructing the oil flow.
Ensure that all drain pipes have a downward slope.
13.2
Check that the impulse lines are provided with root valves as well as
equipment isolation valves at the ends and ihey are supported properly.
13.3
Ensure that pipes and impulse lines have been cleaned by blowing
compressed air before final assembly.
13.4
Ensure that non return valves are mounted in Horizontal mode and that the
direction of NRVs and other valves marches with that of the system.
13.5
Ensure that all valves are free to operate and have proper access for
operation. Also check that all valves are provided with proper tags.
13.6
Ensure that valves have been mounted after testing for leakages at rated
pressure and that their glands are properly packed.
14.
14.1
With power cables, both for AC seal oil pump motor and DC seal oil pump
motor isolated from the starting panel the operation of all the logics of the
starting scheme should be checked as described below:
14.2
Check all the relays & contactors for pick up &; dropout voltages & record
these values. While doing this also measure the coil resistance, insulation
resistance and check the proper configuration of the auxiliary contacts.
14.3
PMI, NTPC
184
a)
Ensure that control leads 927 and 940 are not shorted and neither of
the two are earthed.
b)
Measure resistance between 927 & 940 with 8START' push button of
AC motor pressed. It should be about 6 K.Ohm. Also measure
resistance between 927 & 940 with 'STOP' push button pressed. It
should also be about 6 K.Ohm.
c)
Check the supply voltage control fuse and switch 'ON' the isolator.
Check that relay 1 AUXR. is energised.
15.
15.1
15.2
a)
Multimeter
b)
c)
Shorting leads
d)
e)
HRC fuses
f)
500 V. megger.
Check all the relays for pick up and dropout voltage and record these
values. While doing this also measure the coil resistance, insulation
resistance and check the proper configuration of the auxiliary contacts.
15.3
Pre-supply checks
a)
PMI, NTPC
185
b)
15.4
15.4.1 Check the supply voltage and fuse ratings and switch 'ON' the supply to the
panel.
15.4.2 As soon as the supply is switched 'ON' check that the following
annunciations appear:
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
15.4.3 Press the 'Accept' push button and check that the flickering stops and the
hooter sound is cut 'off.
PMI, NTPC
186
15.4.4 Now by opening the initiation contact of each of the above annunciations
check that the annunciation can be reset by pressing the 'Reset' push
button.
15.4.5 Press the 'test' push button and check the appearance of all other remaining
annunciations.
15.4.6 By shorting each of the fault contacts check the appearance of
annunciations with flickering of lamp & sound of hooter. With contacts
shorted in each case press 'Accept' push button & check cancellation of
hooter sound & flickering. Now check in each case that as long as the fault
contacts are shorted indication cannot be reset by pressing the 'Reset' push
button.
16.
16.1
16.2
Switch 'off DC supply and check that DC failure relay drops and DC failure
annunciation appears .with ringing of bell. Accept the annunciation & check
that the ringing of bell stops while indicating lamp keeps glowing even after
pressing the 'reset' push button. Again switch 'ON' the DC supply & reset
the indication.
16.3
16.4
PMI, NTPC
187
and slowly reduce the Rheostat resistance and note the current at which
relay picks up. Slowly increase the resistance and note the value of current
at which the relay drops out. Repeat the same for other relay setting also.
16.5
Check the pick up and drop out of all the current relays by actual movement
of the ILI position. This can be done by filling oil in the ILI.
17.
17.1
17.1.1 Having ensured the healthiness and logics of the control circuits, normalise
the control and power cable connections. Decouple the motor from the
pump and check for the free rotation of the motor rotor.
17.1.2 Ensure that the IR value of the motor and power cables are good. Compare
the present IR value of the motor with that obtained during erection and in
the test certificate. The value should not have deteriorated very much. If so,
examine the cause for deterioration, and eliminate it. Also check the ohmic
resistance of winding and compare it with test protocol. The difference
between the ohmic resistance values of all phases individually should not
be more than 2%.
17.1.3 Put selector switch to local position at the starting panel. Ensure balanced
415 volts supply at the motor control centre (MCC) and give a pump and
stop the motor. Check for the correct direction of rotation and any abnormal
noise, if the direction of rotation is not correct, interchange any two of the
three phases terminations at the motor terminal box.
17.1.4 If the motor has started smoothly, again start it from local and record the
starting current and no load running current in all the phases. Check for the
noise level and temperature rise of the motor particularly at the bearings.
PMI, NTPC
188
Measure and record the axial, vertical and horizontal vibrations of the motor
at free as well as coupling end.
17.1.5 Ensuring that the noise level and the vibrations are within the limits, carryout
the trial run of the motor. Note the phase to phase voltages, no load running
current, vibrations and temperatures at cold state running of the motor, i.e.
soon after starting.
18.
18.1
Carry out the checks similar to checks described in (A) & (B) in 1.27 above.
18.2
18.3
If the motor starting is smooth, again start it and record the starting current,
no load running current, field current, voltage before and after the resistor,
motor, speed, vibrations and surface temperature of the motor near the
bearings. Also observe the noise level. Depending upon the motor speed
and voltage at the armature terminals, the series resistor taps should be
selected. Stop the motor and change the tap if required and again start the
motor. Care should be taken not to exceed the number of permissible start
per hour as recommended by the motor manufacturer.
18.4
Proceed with the trial run of the motor if noise level and vibrations are within
limits. Record the surface temperature at cold state and subsequently at
one hour interval. Observe the thermal stability after 8 hour trial run or later.
PMI, NTPC
189
Stop the motor after achieving the thermal stability. Release the motor for
coupling with the pump.
19.
19.1
The capacity of the exhaust fan motors is very small. Hence, the trial run of
the fan-motor set can be carried out together without dismounting the fan
from the shaft. Follow the same guidelines as described in case of AC seal
oil pump motor, monitor and record the parameters such as voltage,
current, speed, vibration, noise level and temperature rise.
20.
OIL FLUSHING
20.1
The whole of the system should be flushed with oil at about 60-65C
temperature to clean the system of any dirt/dust. Flushing will be carried out
in 5 stages as described below. For valve positions during flushing prefer to
the drawing of seal oil system enclosed with this manual.
Ensure that AC flushing oil pump can be used for initial filling up of
the seal oil system or starting oil pump is commissioned. Alternatively
AC seal oil pump is commissioned as described at para 1.33.
b)
Fill up the system with oil by running the AC flushing oil pump, in the
following sequence. At each step, check for any oil spillage at the
concerned flange joints valve glands and outlet of drain/vent valves.
Utmost care should be taken that at no stage AC flushing oil pump
be over loaded.
PMI, NTPC
190
20.3
20.3.1 With system filled as above (coolers, FOR, DPR and DT bypassed
condition) continue to flush the system by running AC flushing oil pump.
Change-over to filter No. 2 by opening the valves SO-16 & SO-18 after two
hours. Isolate filter ;No. 1 by closing the valves SO-15 & SO-17. Keeping a
tray or bucket underneath the filter No. 1, open the top flange, remove the
internals of the filter. Depending upon the quantum and type of dirt collected
the frequency of the changeover of filters has to be decided from time to
time. Initially, the changeover may be required once in 4 to 8 hours. After
each changeover clean the dirty filter and ensure its availability as standby
filter. One or other filter has to be in service during entire operation of the
system.
20.3.2 Continue the first stage flushing for about two days. Ensure that AC flushing
oil pump is not overloaded because of the overburden caused by the seal
oil system.
21.
21.1
Keep all the valves of the system closed except the balance leak off valve.
Gradually open the suction valves SO-5, of the pump and check for oil
leakage at the flange joints, seals and pressure gauge isolating valve. Vent
end flush the impulse line and valve in the suction gauge. Similarly vent and
flush the impulse line of the discharge gauge too. Keep the discharge gauge
isolated. Deaerate the pump.
21.2
Monitor and record the 3 ph. voltages at the MCC. Ensuring availability of
power supply and control supply, give a starting impulse and stop it
immediately. Check for correct direction of rotation and observe for rubbing
noise, if any. Monitor the starting current.
PMI, NTPC
191
21.3
If the direction of rotation and noise level is okay, restart. Monitor and record
the starting current and running current. Vent & flush the discharge gauge
impulse line once again, and valve in the gauge. Record the shut off
pressure. Record the phase to phase voltages and line currents (shut off
state). By physical inspection check the vibration and temperature rise. If
normal, open the system bypass valve SO-H fully. There should not be any
change in the discharge pressure and line current which ensures perfect
seating of the discharge valve SO-7.
21.4
Monitoring the line current, gradually open the discharge valve by quarter
turn. Record the line currents and discharge pressure. As the system
resistance is very low, the pump would draw the full load cur-^nt for a
fraction of turn opening of the discharge valve. So carefully open the valve
by another quarter turn. Record the discharge pressure and line current. If
the line current is less than the rated current (27.0 Amperes), open the
valve further till that current is drawn. Otherwise close the valve till the
current has come down to rated value. At rated current, record the
discharge pressure, suction pressure, phase to phase voltages, discharge
valve position, vibrations and surface temperature of the seals, bearings,
body and frame of the pump-motor. Monitor the surface temperatures at
every hour and carry out the trial run of the pump for about eight hours
subject to normal vibrations, temperature rise and noise level.
22.
22.1
In this stage cooler No. 1, DPR, POR and DT would be included in the
flushing circuit. This stage of flushing will be started during trial run of AC
seal oil pump & continued.
22.2
Close the bypass valves. Open the inlet and outlet valves of FOR, DPR and
DT. Vent, if required. Flush the impulse lines of pressure gauge before and
after filter. Valve in PG-8 and PG-9. The filters should be changed over
PMI, NTPC
192
when the differential pressure between them is more than 0.5 kg/cm .
22.3
Continue the flushing for a day. Then close the outlet valve, SO-64 of DT to
have effective flow in the pipe lines connecting hydraulic seal tank and
damper tank. Carry out the flushing in this stage for half a day.
23.
23.1
If high pressure starting oil pump has been commissioned further flushing of
seal oil system should be carried out with oil injector in place of AC seal oil
pump or AC flushing oil pump.
Flushing in this stage will be started with coolers, FOR, DPR and DT
bypassed. During flushing these equipments will also be taken in and
flushed.
23.2
Carryout the flushing for about two days. Changeover the filters as guided
by the differential pressure across the-, filters, when the differential pressure
is raised to 0.5 kg/cm , change the filter. With time, the' changeover
frequency should come down indicating the progress of cleaning process of
the system. Ensure that the oil purifier is in continuous service.
24.
24.1
In this stage, the internals of POR and DPR should be assembled and
flushed. Also all the instruments will be taken into service after flushing their
impulse lines. Carry out the flushing preferably with oil injector as the
temperature of oil can then be easily raised to 60 to 65C.
25.
25.1
This is the last stage flushing and hence it should be terminated only when
PMI, NTPC
193
26.1
Seal Oil Tank;- Ensure that the seal tank is drained fully and all valves are
closed but for the locked open valves (suction and balance leak off valves of
AC SOP). Keep both the filters clean and valve in any one of the filters.
Valve in PG-4, PG-5, PG-8, PG-^, PG-10 and PG-11. Start AC flushing oil
pump and open its discharge valve monitoring the discharge pressure.
Charge any one of the coolers. Keep lubricating oil system under shut
down.
26.2
26.3
Charging of Differential Pressure Regulator Open the oil impulse line valve.
Open the air side impulse valve. Open the hydraulic seal tank drain valve
and damper tank bypass valve. Open the inlet valve of DPR. Gradually and
PMI, NTPC
194
cautiously open the outlet valve, observing the DPR outlet pressure at PG10. The outlet pressure would go above 0.9 kg/cm" initially while opening
the valve. Open the valve such that the pressure never goes above 2.0
kg/cm and keep on slowly opening the, valve. The DPR outlet pressure
would settle around 0.9 kg/cm . Keep the outlet valve fully open. Observe
the hydrogen side drain through oil check pipes at either side. It would be
bare minimum. Check the ILI-5 and ensure that no oil is collected at the
liquid collection indicator. As oil drains to- the seal tank, its level would
raise. Maintain normal level in the seal tank by draining through centrifuge.
Flush the impulse lines of ECPG-5 and ECPG-6 and valve in them. The
seal oil pressure at both the seals should be equal and around 0.9 kg/cm .
26.4
Charging of Damper Tank Keep the vent valve crack open with a man
posted near the valve. Instruct him to close the valve after proper venting or
if oil escapes through it. Keep the valve fully open. Open the inlet valve of
DT gradually. Check the oil raise visual window, ILI-1 and 1LI-2. The very
low level and low level in DT annunciations should disappear. Keep a man
posted near seal tank, observing the visual window just above. There
should be no oil through it. Gradually and simultaneously open the outlet
valve and close the bypass valve. Check for no oil collection at the visual
window and open valve. Observe for equal seal oil pressure at PG-10,
ECPG-5 and ECPG-6.
26.4.1 Run the system for couple of hours and ensure normal operation. Thus the
system is commissioned. Open the discharge valve of AC SOP fully and
measure the running current. Record all the pressure gauge readings.
26.5
Trial Run of DC Seal Oil Pump Keep the system under shut down. Open the
balance leak off valve and suction valve of DCSOP, valve in PG-6 and PG7. Check for no oil leak through the glands of the pump. Take all
precautions, as described in para 21. Start the pump and stop it
immediately, Check for any abnormal noise. Start again and monitor the
PMI, NTPC
195
voltages before and after the resistor, starting and running current, field
current and discharge pressure at shut off condition. Keep the system
bypass valve SO-11 fully open. Ensure that the inlet valves and bypass
valve of the cooler and SO-4 are fully closed. Open the discharge valve
gradually monitoring the discharge pressure and running current. Do not
overload the motor. Measure and record the speed of the pump.
26.5.1 If need be adjust the series resistance of shunt field of the motor to achieve
the rated speed. Measure the resistance and the current through the
additional resistance provided.
26.5.2 Close the /pass valve provided and charge the system i.e. cooler, filler,
POR, DPR and DT in sequence. Measure the running current, discharge
pressure and speed. Also record the readings of all pressure gauges.
26.6
26.6.1 Open the root valve gradually and flush the oil impulse line. After thorough
flushing, close the valve and connect back the coupling. After connecting,
open root valve. Gradually open SO-78. The-differential pressure recorder
should read around 0.9 kg/cm and differential pressure low annunciation
should clear. Keep the system and differential pressure recorder in service
for couple of hours and observe the performance.
PMI, NTPC
196
PMI, NTPC
197
PMI, NTPC
198
EQUIPMENT INSPECTION
1.1
2.
HYDROGEN MANIFOLD
2.1
Check that proper stands have been provided for holding the cylinders.
Ensure that suitable pressure regulators are provided for hydrogen
cylinders. Also ensure that the hydrogen manifold has been provided with a
relief valve set to blow off at pressures exceeding 5.5 kg/cm .
3.
3.1
Check that proper stands have been provided for holding the cylinders.
Ensure that the CO- manifold has been provided with a pressure relief valve
set to blow off at pressures exceeding 5.5 kg/cm2.
4.
4.1
Check that proper size of silica gel has been used in the drier and that the
gas can easily pass through it. Ensure that the silica gel in drier is not in the
form of powder. Check that the perforations and the wire mesh are of proper
grade. Also ensure that the silica gel used is in perfect dried up condition.
5.
5.1
PMI, NTPC
199
6.1
7.1
Ensure that the hydrogen gas coolers have been hydraulically tested for
leakages before insertion and that there was no leakage found.
7.2
Ensure that adequate arrangements have been done for venting the
coolers.
8.
8.1
Check that the piping erection has been completed as per scheme, all the
pipes and equipments are properly supported, flange joints are tightened
PMI, NTPC
200
perfectly and proper gaskets of good quality and correct sizes are provided.
8.2
Ensure that pipes and impulse lines have been cleaned by blowing
compressed air before final assembly.
8.3
Ensure that all the valves are free to operate and have proper access for
operation. Also ensure that ail the valves are provided with proper tags.
8.4
Ensure that valves have been mounted after testing for leakages at rated
pressure and that their glands are properly packed.
8.5
Similarly check the piping & valves of hydrogen cooling water system also.
9.
INSTRUMENT
9.1
All the pressure gauges should be checked for proper range, tap size,
calibration, accuracy and repeatability.
9.2
Ensure that pressure indicators on gas control panel have been calibrated
with their respective pressure transducers for accuracy and repeatability.
9.3
Ensure that the gas purity indicator has been calibrated with the gas
analyser and has been checked for accuracy and repeat ability.
10.
10.1
This test is carried out to ensure that there was no damage to weld seams
during transportation and erection, and that the generator assembly along
with the system including flanges & valves are gas tight.
10.2
The test envisages filling the stator of the whole machine along with the
PMI, NTPC
201
pipings of systems with air at a pressure of 3.5 atg/4.0 atg. (for 200/210 MW
machines) and checking the leakage at the possible places by soap
solution.
Generator along with the system piping is said to be gas tight if the leakage
of air in 24 hours referred to atmospheric pressure is not more than 5% of
total internal volume. The quantity of air leakage is determined by finding
out the drop in pressure taking into account the temperature corrections.
10.3
The testing of system for gas tightness will be done in ix stages namely:
REQUIREMENTS
11.1
Dry compressed air which should be free from dust moisture, oil and other
foreign material.
11.2
The seal oil system should be commissioned and established for continuous
operation.
12.
12. 1
PMI, NTPC
202
12.2
Close valve nos. C-il, C-2, C-3, C-4, C-5, C-6, C-7., C-8 and C-10.
12.3
12.4
12.5
Check the various joints for leakages by soap solution. Check for leakage at
blank of valve C-11. Check for the passing of relief valve C-9.
12.6
Check for the passing of valves C-10, C-8, C-7, C-6, C-5, C-4, C-3 and C-2.
Also check valve glands for leakages.
12.7
Check for leakage at weld seams of CO- manifold and piping by applying
soap solution.
13
13.1
13.2
Install a temporary pipe connection between valve nos. H-22 and H-24.
13.3
Close valve nos. H-20, H-19, H-28 and H-ll. Open valves H-12, H-27, H-24
and H-22.
13.4
Fill dry compressed air by opening valve H-ll at a pressure of 5 kg/cm and
then close it.
13.5
13.6
PMI, NTPC
203
13.7
13.8
Check for passing of valve H-23 at the time of gas tightness test of stator
together with system.
14.
14.1
Requirements
14.1.1 Seal oil system in operation with all interlocks and annunciations in service.
14.1.2 Dry compressed air. No water should be present in Hy coolers and stator
winding.
14.1.3 U Tube mercury mano meter to read up to 4 atg/3.5 atg (210/200 MW).
14.1.4 Portable barometric pressure indicator (barometer).
14.1.5 Mercury thermometers in position in Generator and shields and in the
middle of the casing for casing air temperature measurement.
14.1.6 All the pressure gauges/pressure indicating instruments of gas system are
calibrated and mounted in position.
14.1.7 Soap solution and personnel for checking/noting down the leakages and for
attending, if any.
14.1.8 Induction liquid indicator checking completion for proper annunciation on
signalling panel.
14.1.9 Generator should be put on barring gear.
PMI, NTPC
204
14.2
14.2.1 Set the position of the system valves corresponding to 'Filling up of the
system with air' (Except H-15 to be closed to see that air is filled" up through
Gas drier).
14.2.2 Admit dry compressed air through valve A-l upto a pressure of 3..5 atg/4.0
atg. (for 200/210 MW and close the valve A-l and open H-15 valve.
14.2.3 Check by soap solution all the possible places of leakages and if any to be
attended in position or by disassembling the same for which if required the
system may have to be depressurized.
14.3. Method of calculation of gas, leakages from the generator.
14.3.1
P1
(------------273+tt1
P2
-----------)%
273+t2
t 1. & t 2 =
T =
PMI, NTPC
205
Absolute leakage of gas from the generator in M can be calculated from the
formula.
Vo =
SO x V
100
V (air)
= 3.2
V hydrogen)
14.4
= 3.2 (V.air)
Generator and the system is said to be gas tight and ready for hydrogen
filling when the leakage per day is not more than 5% by volume. (Take 60 M
as the volume of the generator system piping).
15.
15.1
15.1.1 Ensure the healthiness and logics of the control circuits. Check the power
supply available at the MCC outgoing terminals after removing the cables.
Normalise the control and power cable connections. Decouple the motor
from the pump and check for the three rotation of the motor rotor.
PMI, NTPC
206
15.1.2 Check the IR valves and ohmic resistance of the motor. Also' check IR of
power cables. The difference between the ohmic resistance values of all
phases individually should not be more than 2% and compare these values
with test protocol. Also compare the present IR values of the motor with that
obtained during erection and that of test certificate. The value should not
have deteriorated very much. If so, examine the cause of deterioration,
eliminate it, and also dryout the windings if required.
15.1.3 Ensure that the motor is adequately protected as recommended /
by the
manufacture.
15.1.4 Bump and stop the motor. Check for the correct direction of rotation and any
abnormal noise. If the direction of rotation is not correct, interchange any
two of the three phase terminations at the motor terminal box.
15.1.5 If the motor has started smoothly again start it and record the starting
current and no load running current in all the phases. Check for the noise
level and temperature rise of the motor particularly at the bearings. Measure
and record the axial, vertical and horizontal vibrations of the motor at free as
well as coupling end.
15.1.6 Ensure that there is no abnormal noise and the vibrations are within the
limits. Carryout the trial run of the motor. Note the phase to phase voltages,
no load running current, vibrations and temperatures at cold state running of
the motor, i.e. soon after starting.
At the end of eight hours run, measure and record the hot state running
current, terminal voltages, vibrations and surface temperature. The surface
temperature should have stabilized by this time. The rate of temperature
rise (degree centigrade per hour) should tend to approach zero. Release
the motor for coupling it with the pump.
PMI, NTPC
207
16.
16.1
Ensure that adequate quantity of water is available for running the pump,
suction and discharge pressure gauges are calibrated and' installed
properly and that the whole piping erection work is completed as per the
s'/stem layout.
16.2
Ensure that the bearings are okay and filled with lubricant upto normal level
and that trial run of the motor has been taken.
16.3
Arrange to measure the starting current and running current of the motor,
voltage at motor terminals, vibrations and temperature rise.
16.4
Keep all the valves of the system closed except balance leak off valve.
Gradually open the suction valve of the pump and check for water leakage
at flange joints, seals and pressure gauge isolating valve. Vent and flush the
impute line and value in the suction gauge. Similarly vent and flush the
impulse line of the discharge gauge too. Keep the discharge gauge isolated.
Deaerate the pump.
16.5
Monitor and record the 3 phase voltages at the MCC. Ensuring availability
of power supply and control supply, give a starting impulse and stop it
immediately. Check for correct and stop it immediately. Check for correct
direction of rotation and observe for rubbing noise if any. Monitor the
starting current.
17.0
17.1
With one of the two hydrogen cooling water pumps in service open the inlet
valve of one cooler.
17.2
Open the vent of the cooler and close it when water starts coming through
PMI, NTPC
208
it. Keep a watch on the induction liquid indicator for detection of presence of
liquid in generator casing and ensure that no water comes in it.
17.3
Now open the discharge valve slowly and close the system bypass valve,
while opening the discharge valve keep a watch on the current drawn by the
motor. It should not be allowed to increase beyond its rated value.
17.4
In a similar way one by one charge the other three coolers also. Each time
keep a watch on the induction liquid indicator and ensure that no water
comes in it. Also while charging the coolers ensure that the motor is not
overloaded.
18.
CONCLUSIONS
18.1
Thus for the gas system including the cooling system has been prepared for
the normal operation except for the actual filling up of the hydrogen gas in
the system. The filling up of the casing with hydrogen will be required after
the dry out of generator in "air has been done. So the operation of filling
hydrogen will be detailed with drying out operation.
PMI, NTPC
209
EQUIPMENT INSPECTION
1.1
2.
2.1
WATER COOLERS
3.1
3.2
Ensure that the primary and secondary DM water pipings are connected
properly at the inlet and outlet of the coolers.
3.3
3.4
PMI, NTPC
210
outlet.
4.
WATER FILTER
4.1
4.2
Open the filters and check that size of meshes used is as per specification.
4.3
Ensure that filter internals are not rusted and filter elements are free from
mechanical damages.
5.
MAGNETIC FILTER
5.1
Check that the magnetic filter is mounted vertically and properly fastened to
corresponding piping flanges by means of bolts.
5.2
Open the magnetic filter and clean the magnetic plates thoroughly.
5.3
Check for proper gap between the plates. Check the magnetic
characteristics of the magnetic plates.
6.
EXPANSION TANK
6.1
Check that the stainless steel body expansion tank is provided with the.
following fittings:
211
Ensure that the tank and the fittings are free from mechanical damage.
6.3
Check that return line from the windings to inlet of the tank is provided with
a perforated plate of specified perforations.
6.4
Ensure that the hydraulic test of expansion tank has been carried out at 1.5
kg/cm pressure for 15 minutes without any leakage.
7.
7.1
Check the internals of the water jet ejector for any physical damage.
7.2
8.
8.1
Check that the piping erection has been completed as per scheme, all the
pipes and equipments are properly supported, flange joints are tightened
perfectly and proper gaskets, of good quality and correct sizes are provided.
Ensure that the gaskets are not protruding in and obstructing the water flow.
8.2
Check that the impulse lines are provided with root valves as well as
equipment isolation valves at the ends and that they are properly supported.
9.
GAS TRAP
9.1
Ensure that the gas trap is firmly fixed on the foundations in the vertical
direction.
PMI, NTPC
212
9.2
10.
INSTRUMENTS
10.1
11.
11.1
Check all the relays and contractors for pick up and drop out voltages and
record these values. Also measure the coil resistance and check the proper
configuration of the auxiliary contacts.
11.2
With power cables for both the motors isolated from the stator water starting
panel the operation of ail the logics of the starting scheme should be
checked.
Since the starting scheme varies from project to project a detailed check list
for logics can not be generalised. It is however necessary that before
switching 'ON' the motor from the starting panel the interlocks and
protections as applicable in case of the project should be checked and
ensured.
12.
12.1
Check the AC supply voltage and fuse ratings. Remove fuses for
instruments and energise the AC circuit while DC is ON'.
12.2
Switch 'OFF' DC supply and check that DC failure relay drops and> DC
PMI, NTPC
213
13.1
Trial run of both the stator cooling water pump motors should be taken as
described in the previous chapter para 15 for the hydrogen cooling water
pump motor. After trial run release the motor for coupling with the pump.
14.
14.1
Purpose The flushing of stator water cooling system is a must to check the
following:
14.1.1 The completion of erection of all mechanical & electrical equipments in the
generator stator water cooling system
14.1.2 To flush the whole system in stages for clearing.
14.1.3 To run the stator water pumps and check their performance.
14.1.4 To find out the defects in the system components if any and to rectify
accordingly.
14.1.5 The different parameters such as pressure and flow are to be monitored.
15.
15.1
PMI, NTPC
214
15.2
Open DM water supply valve gradually. The water flows through the bypass
lines of the pumps and coolers and flushing outside through the temporary
pipings.
15.3
When the flushed out water is clear, <-lose the DM water supply valves.
16.
16.1
16.2
Open DM water supply valve and flush the line and equipment until the
flushed water becomes clear. Open drain of cooler and flush it till clear
water comes out and close drain. Close DM water supply valve.
17.
17.1
Set the valves and proceed as per para 17.2. and proceed as per 16.2.
18.
18.1
Set the valves and flush the system till clear water comes out of the flush
line.
18.2
19.
19.1
Set the valves. Remove the blanks at the expansion tank and blank of
flushing line.
PMI, NTPC
215
19.2
Fill up the expansion tank to full level and check the operation of float valve
by draining the filling.
19.3
Check the free rotation of pump & motor. Apply proper lubricant.
19.4
19.5
20.
20.1
Temporary flushing line is removed after the above flushing and return line
is connected back to the stator water expansion tank. The bypass around
the stator water conductor is removed and normalised. The flow orifice is
introduced.
20.2
While starting the final stage of flushing the air locks if any in the conductors
and headers must be released by opening valves Y-32 & Y-33 and only
then the valve Y-13 opened.
20.3
Start stator water pump A and monitor and record all the parameters such
as pressure, flow etc.
20.4
Check the system parameters with the stator water pumps B running.
20.5
PMI, NTPC
216
20.6
Take water samples and check its properties. If necessary, drain some
water from the system by opening drain valve at the outlet of stator
conductors and fill up fresh DM water in the expansion tank.
20.7
Check the logics and protections of the system by actually creating the
abnormal running condition in the system.
PMI, NTPC
217
1.1
218
2.1
2.1.1 Machine filled with dry air and further supply of dry air for make up
available.
2.1.2
Readiness of drier in gas system along with silica gel and reactivating
arrangements.
2.1.3 Satisfactory completion of gas tightness test at 3.5/4.0 kg/cm for a period of
24 hours.
2.1.4 Generator stator output terminals to be connected to bus bars after IR value
measurement. 3 phase shorting to be prepared on phase side bus duct
beyond the CTs after isolating the rest of bus bar.
2.1.5 Arrangements to be made near neutral grounding transformer for
measurement of insulation resistance during dry out operation. Earthing of
the neutral grounding transformer to be isolated for IR measurements. Also
PMI, NTPC
219
PMI, NTPC
220
b)
c)
d)
e)
f)
2.1.14 Hydrogen system should also be ready together with purity indicator at
UCB.
3.
3.1
Preparation for Rolling Just prior to rolling the protections of the generator
should be ensured by simulating the actual fault conditions. This is
described below;
3.1.1 Oil level in damper tank emergency class B tripping after 20 sec. delay* By
actually reducing the level in damper tank by partially closing the inlet valve,
check this tripping takes place after the specified time delay at the specified
level.
PMI, NTPC
221
3.1.2 Distillate flow to stator winding emergency class B tripping after 2 minutes
time delay.
By closing the inlet valve reduce the flow of distillate through the stator
winding to below 13 M /hr. Check that the tripping occurs after the specified
time delay.
3.1.3 Distillate specific resistance emergency class B tripping.
By switching 'OFF' the resistivity indicator check that the tripping occurs
when the needle passes below 50 K ohm Cm value.
3.1.4 Ensure the tripping of the unit through manual tripping switch.
3.1.5 Ensure that all the bearings and seals have adequate supply of oil for
lubrication.
3.1.6 Check and record all the parameters of all the auxiliary systems prior to
roiling.
3.1.7 Measure and record the IR value of stator and rotor and impedance of rotor
at barring speed.
4.
4.1
Immediately after rolling As soon as the machine is rolled and barring gear
disengages check the bearing vibrations, rubbing if any inside the generator
or any other abnormal sound. Keep a close watch on the bearing oil & sea!
babbit temperature.
4.2
Checks at 500 RPM As the machine speed is stabilised at 500 rpm check
the following:
PMI, NTPC
222
4.2.1 Measure the bearing vibrations and record. Also record the bearing oil &
seal oil drain temperature, seal babbit temperatures and generator RTD
recordings. Also record the important working parameters of all the auxiliary
systems in service.
4.2.2 Measure IR value of the rotor. Also measure the impedance 4.2 of rotor
winding.
4.2.3 Check the bedding of the slip ring brushes at 500 rpm.
4.2.4 Measure the IR values of seal oil inlet and outlet pipes and bearing oil inlet
& outlet pipes of bearing number 7.
4.2.5 In addition the following checks should be carried out on high frequency
excitation system with machine at 500 RPM.
a)
b)
Measure the pilot exciter voltage and record. As the speed is raised
keep on measuring the pilot exciter voltage at a gap of every 200rpm to draw speed Vs. Voltage Characteristics of pilot exciter.
4.3
4.3.1 Measure the bearing vibrations and record. Also record the bearing oil and
seal oil drain temperatures, seal babbit temperatures and generator
temperatures as given by RTDS.
Also record the important working parameters of all the auxiliary systems in
service.
PMI, NTPC
223
5.1
5.1.1 Pressurise the generator casing to 0.2 kg/cm with air. When machine speed
is raised to 3000 rpm charge the hydrogen gas coolers to regulate the
temperature rise to within 5C per hour. Gradually let the stator temperature
get stabilised at 75C.
5.1.2 On completion of mechanical run of turbine i.e. completion of over speed
tests and other governing system checks, continue the dry out at 3000 rpm
with 0.2 kg/cm^ air pressure.
5.1.3 Replace periodically the hot (moist) air by admitting fresh (dry) air. For doing
this first reduce the pressure by purging from 0.2 kg/cm to 0.1 kg/cm and
then admit fresh dry air to increase the pressure back to 0.2 kg/cm . During
the initial stages of dry out period of replacement can be about half an hour
while later on it can be gradually increased to about 2 hours.
5.1.4 Measure IR valves of stator winding periodically and declare completion of
dry out with air operation on reaching acceptable values as given at 1.17.
PMI, NTPC
224
5.1.5 On declaring the dry out with air operation complete, stop the machine and
fill up the casing with hydrogen pressure of 3/3.5 kg/cm & required purity.
5.1.6 Run the machine at 3000 rpm with hydrogen filled in and verify again the IR
value of stator winding. On reaching acceptable IR values as given at 1.17
declare completion of dry out and prepare for circulating distillate through
stator winding for excitation.
5.2
Air pressure
b)
75C
PMI, NTPC
225
c)
75C
temp. of generator,
main exciter &: pilot
exciter.
d)
75C temp.
e)
40C
f)
Cold gas
50C
g)
Hot gas
75C
h)
i)
Pressure oil
j)
9 to 10 kg/cm
k)
2-3 kg/cm .
l)
43C
m)
75'C
n)
100C
o)
65C
p)
Purge out the moist air from the Generator continuously and admit
fresh dry air.
q)
Drain the collected water from the drier and reactivate the silica gel
when required.
5.3.1 Continue the process of dry out until the following results are obtained at
PMI, NTPC
226
6.
6.1
6.2
PMI, NTPC
227
6.2.5 Allow the air inside casing to go out to atmosphere through the pipe at the
top of the casing through the valves H-18, A-2 and H-10.
6.2.6 The pressure of the gas in the manifold as indicated by CPG-1 should not
more than 3 to 3.5 kg/cm .
6.2.7 Purge the following lines till CO- comes out.
a)
b)
c)
Hydrogen driers and compressed air filling line by opening valves H34 and A-l.
d)
e)
6.2.8 Now, ensure that the casing pressure is 0.15 to 0.2 kg/cm and 98% of CO2
in the gas mixture in casing.
6.2.9 CO2 filling can be stopped.
6.3
Hydrogen Filling
6.3.1 Check that the valve are set as shown in the table correspond ing to
"FILLING THE SYSTEM WITH HYDROGEN".
6.3.2 Check that H- cylinders are connected to all the five regulators at the H2
PMI, NTPC
228
During this process discharge/purge the CO2 air mixture through C02 feed
pipe.
b)
Hydrogen gas driers and air filling line by opening valve No. A-l and
H-34.
c)
d)
6.4
Operational Checks
PMI, NTPC
229
PMI, NTPC
230
1.1
b)
c)
d)
e)
Control block
f)
g)
Control insulator
h)
Capacitor
i)
Control cubicle
j)
k)
l)
1.2
The local-remote control switch enables one to operate the breaker either
over remote control or locally from the control cubicle itself over local
control. One for each pole air receiver is provided vertically & supports the
breaker. Interrupting chamber houses the main contracts. Here separation
of contacts &: arc extinction is achieved. The two chambers have a common
fixed contacts on the middle & two moving contacts are at the two ends.
The centre has an aluminum body &: is resting on support insulators.
Interrupting chamber driving mechanism are fixed to the moving contacts &:
PMI, NTPC
231
cause the motion necessary for contacts making & breaking. Control block
houses magnetic valve block, close & trip coils & auxiliary switches etc. It is
mounted on the air receiver. The motion between control valve & magnetic
valve block is transmitted by the control rod. In the line feeders, resistance
is switched across each contact just prior to the closing of main contacts &
cut out once the main contacts close. Condensers are also connected
across each contact.
1.3 Commissioning Checks First the following preliminary checks are made:
1.3.1 Erection work is complete & erection completing certificate is obtained.
1.3.2 Compressed air system is commissioned.
1.3.3 Check leakages on the breaker at all joints, air tank safety valve, at support
insulator mounting & at bifurcation chamber mounting control insulator.
Alignment is also checked.
1.3.4 Check that all auxiliary contacts N/0, N/C prove as per the specifications.
1.3.5 Trip & make coils healthiness & continuity is checked.
1.3.6 Pressure switch contacts &: setting are checked.
1.3.7 All insulator are cleaned and inspect wherever possible functionally check -
Hand valves
NRV
Drain plugs
PMI, NTPC
232
resistance
measurement:
Contact
resistance
is
measured
separately for all the four contacts in each phase. Finally the total resistance
is measured.
1.4.3 Circuit breaker is closed from the local manual control <5c the operation of
the breaker & indicator functioning are checked.
1.4.4 Pressure Tests: Following pressure are observed PMI, NTPC
233
a)
b)
c)
b)
c)
Close & open operation time tests are conducted on each interrupter and
pole. For the breaker close-open &. open-close tests are carried out. The
pressure drops & refilling time taken to reach service pressure are recorded.
Where resistance switching is applicable resistor insertion time and part
resist insertion times are to be recorded during breaker closing.
Resistance Insertion Time = Time measured from the instant of touching of
the last contact of the closing resistor to the instant when the first
interrupting chamber closes.
Part Resistor Insertion time = Time measured from the instant of touching of
contact of the closing resistor to the instant when the last interrupting
chamber closes.
PMI, NTPC
234
2.
2.1
PANTOGRAPH ISOLATOR
Description: It consists of a supporting insulator, drive mechanism, rotating
insulator, operating mechanism and the contact drums. This is a motor
operated unit.
PMI, NTPC
235
2.2 Commissioning Checks: Following general checks are first made 2.2.1 Check the insulators are not damaged and they are properly cleaned.
2.2.2 All moving parts are well lubricated.
2.2.3 Double & separate earthing has been done at -
Channel base
Earthing blade
Commissioning Checks :
2.3.1 Using emergency lever check the manual operation of the isolator.
2.3.2 Ensure that the pantograph blades properly grasp the suspended contacts.
2.3.3 See that the blades operate smoothly around the scissors joint.
2.3.4 There is no abnormal sound due to the malfunctioning of the gears in the
gear box.
PMI, NTPC
236
2.3.5 For earthing switch, the earthing blades engages properly into the earthing
contact.
2.3.6 The vertical operating rods do not buckle during operation.
2.3.7 The indicator shows the correct indication - open/close of isolator.
2.3.8 The limit switches contact make at both end positions.
2.3.9 The electrical interlock between isolator & circuit breaker is proper.
2.3.10 The heaters are working satisfactorily.
2.3.11 Perform five consecutive on-off operations with operating mechanism. The
thermal relay must not switch off.
2.4
CAUTION : Before doing any check, ensure that the marshalling box, main
drive box & earth switch Drive box are dead.
b)
Interlocking Coil
c)
Tripping Coil
d)
Closing Coil.
PMI, NTPC
237
2.5.5 For earthing switch drive box, resistance measurement for the following is
measure bv Wheatstone Bridge.
a) Interlocking Coil
b) Tripping Coil
c) Closing Coil.
2.5.6 Heater resistances are measured for a) Main Drive Box
b) Marshalling Box
c) Earth Switch Drive Box.
2.5.7
3.
3.1
PMI, NTPC
238
3.2.4 Check all three poles operate simultaneously and stop for 'ON' & 'OFF'
operate simultaneously.
3.2.5 Ensure double separate earthing is provided at a) Channel
b) Operating box mechanism
c) Earthing Blade
d) Isolator structure Base.
3.2.6 Check coupling with motor operating mechanism.
3.2.7 Check mechanical interlock provided with earthing switch.
3.2.8 See that remote end indicator shows correct status of isolator.
3.3. Resistance Measurements:
3.3.1 Measure & record insulation resistance between line part & earth. This is
done by a 5 KV Megger for all the three phases.
3.3.2 Measure and record the contact resistances using Kelvin Bridge or suitable
test equipment. Sketch circuit schemes for measurements made showing
points across which measurements are taken.
3.4 Operational Checks :
3.4.1 Operate isolators locally and record times taken for 'ON' &. 'OFF' operations.
3.4.2 Carry out five successive close/open operations on the isolators from local
and check thermal overload relay of the motor drive mechanism does not
operate.
PMI, NTPC
239
CURRENT TRANSFORMERS
Description : Current transformers used at KSTPP switchyard are of BHEL
make. It is of oil filled construction where in oil serves the purpose of cooling
and insulation.
4.2
Commissioning Checks :
Primary
b)
Secondary
c)
by flick test.
4.2.7 Check the ratio of the C.Ts by primary injection for all tapings. The injected
primary current has to be sufficiently high for a reasonable secondary
current.
PMI, NTPC
240
4.3.3 a)
Secondary Core-1 :- here megger test is carried out with the help of a
500V megger between
- Cure 1 to
- Earth Core 1 to Core 2,3,4 & 5.
b)
Secondary Core-2
- Core 2 to Earth
- Core 2 to Core 3,4, & 5.
c)
d)
e)
Polarity test
b)
c)
Winding resistance
d)
Magnetisation characteristic
PMI, NTPC
241
5.
5.1
b)
c)
PMI, NTPC
242
5.1.2 Intermediate Voltage Transformer : This Is of minimum oil type and intended
for out door installation. These are built up on a three legged core with the
windings arranged concentrically on the middle leg. The primary winding
consists of a main winding & trimming windings. The latter are located at
neutral end. Both end of the main windings are connected to copper
screens in order to have an even distribution of voltage stresses. The
insulation is made of oil impregnated paper.
The IVT is furnished with a compensation reactor connected on the high
voltage side in series with the primary winding.
The primary & secondary winding are divided by an earthed screen. A
damping ckt consisting of a reactor and a series resistance is connected in
parallel across one of the secondary windings. There are three secondary
windings each with three terminals.
The IVT is provided with an ample expansion room in the upper par of the
tank which is provided with an oil level indicator of the reflection type. This is
furnished with oil filling plug & oil draining valve.
The amount of free oil is reduced by filling of quartz and in all free spaces.
The windings are dried under vacuum and treatment. The assembled
transformers are evacuated before the filling of well degassed oil. It is
pressurized at this impregnated process.
The transformers are hermetically sealed. All essential metal parts are hotdip galvanised or made of aluminium.
The damping ckt terminals are brought out into the secondary terminal box.
This is to enable control measurement of the damping ckt components.
Terminals
components are housed in a steel tank provided with two terminal boxes,
PMI, NTPC
243
one for the trimming winding terminals and the other for the secondary
terminals. An earth terminal is located adjacent to the trimming winding
terminals.
The high voltage terminal of the capacitor is connected to the line. The low
voltage terminal is connected to the earth terminal at delivery. Both the low
voltage & earth terminals are placed in the trimming winding box.
The carrier equipment shall be connected to the low voltage terminal and
the ling between this terminal and the earth terminal shall be removed. The
secondary terminal box is provided with a separate earth terminal to which
the appropriate winding terminal are to be connected.
The terminal d1 d2 must be short circuited for correct functioning of the
transformer.
5.2
5.2.1 Any connection work in the secondary terminal box should be done only
where the high voltage terminal is earthed.
5.2.3 The tank of CVT should be earthed properly at two independent places.
5.2.4 The upper terminal of the individual capacitor unit should be short circuited
to the box by a bare wire till all connections are completed & unit is ready
for commissioning. This bare wire should be removed without fail prior 10
commissioning.
5.3
PMI, NTPC
244
5.4.1 Megger test is carried out between primary &: earth by a 5KV megger.
5.4.2 Megger test is carried out between primary and secondary core 1,2 & 3,by a
5 KV megger.
5.4.3 Secondary side
a)
PMI, NTPC
245
b)
Secondary core 2 :
- Core 2 to earth
- Core 2 to Core 3.
c)
Secondary core 3 :
- Core 3 to earth.
Polarity test
Other tests.
LIGHTNING RRESTOR
6.1
PMI, NTPC
246
PMI, NTPC
247
6.4
This is carried out by a 5KV megger. Do not forget to disconnect the ground
from the line end before connecting the arrestor back to line.
7.
7.1
EARTHING SWITCH
Description : This essentially consists of an earthing contact mounted on
the isolator's insulator post, connected to the current carrying
pivot,
Commissioning
b)
c)
d)
e)
f)
PMI, NTPC
248
B. Switchgear
1
DESCRIPTION
All high capacity unit auxiliaries and the low voltage distribution
transformers are supplied from the 6.6 KV unit station bus Bar. This is
affected through the 6.6KV circuit breakers, failure of which obviously leads
to the outage of the auxiliaries themselves. Again inter linking of the unit
and station buses are through 6.6 KV switchgear and hence the reliability of
these equipments become still more critical. The contact alignment, contact
smoothness insulation etc. are vital factors contributing to the reliability of
the breaker. Protections and interlocks are to be perfect for the safety of the
breaker and the corresponding auxiliary. In case of OCB's oil quality also is
of prime importance.
TESTS
i) Erection Tests.
ii) Pre-commissioning tests.
iii) Commissioning tests.
2.1
Erection Tests:
These comprises of thorough checking of the breaker for any damage after
erection, proper fixing and the related erection formalities.
2.2
Pre-commissioning tests:
These tests will be carried out when the erection is substantially complete
and will comprise of
i)
Breaker inspection.
ii)
PMI, NTPC
249
2.3
iii)
iv)
Commissioning Tests
These tests will involve the operation of the switchgear, charging and
loading. In" case of breakers connecting two systems (e.g. unit and station
bus coupler) ensure that phasing out test is carried out before charging.
PART
SHEET
REF. No.
MANUFACTURE
SL. NO.
TYPE
MODLE
VOLTS
RUPTURING CAPACITY
MAKING CURRING
AUXILIARY SUPPLY
CLOSING VOLTS
TRIPPING VOLTS
CLOSING DEVICE
AMPS
FREQUENCY
BREAKING CAPACITY
SHORT TIME CURRENT
AMPS
AMPS
SPRING
OPERATION DUTY
PMI, NTPC
250
C. Transformer
1.0
DESCRIPTION
Transformer is the most vital equipment in AC systems. Transformation is
one of the factors, which render AC systems superiority over DC systems.
This
equipment
has
large
range
of
application
in
power
transmission/distribution.
Since this is a vulnerable part of the system extreme care is to be taken
during commissioning, over and above the tests carried out at the
manufacturers works, the commissioning checks and tests play vital role.
The voltage ranges being up to the EHV ranges, insulation is of prime
importance quality of oil is equally important as it serves the dual purpose of
cooling and insulation. Terminal connections body earthing and protections
are to be checked and cross checked cooling scheme has to be foolproof.
2.0
2.1
TESTS
1.
Erection tests
2.
Pre-commissioning tests.
3.
Commissioning tests.
Erection Tests
This comprises of thorough checking of the transformer for any damage of
its parts, proper foundation etc.
2.2
Pre-commissioning Tests
These tests will be carried out when the erection is substantially complete
and will comprise.
PMI, NTPC
251
2.3
1.
2.
3.
4.
5.
6.
7.
Commissioning Tests
These tests include the charging of the transformer no load operation and
full load operation and confirms the operability of all protections.
PMI, NTPC
252
PART
SHEET
REF. NO
-------------------------------------------------------------------------------------------------------------TRANSFORMER
-------------------------------------------------------------------------------------------------------------SATION
----------------------------------------------------------------------------------------------------------PLANT
IDENTIFICATION
NAME PLATE DETALES
MANUFACTURER
SERIAL NO
WINDING
AMPS
KVA
SPECIFICATION
VOLTS
INSULATION
HV
LV
PHASE
FREQUENCY
VECTOR GROUP
% IMPEDANCE
CONNECTION
TYPE OF COOLING
TEMPERATURE RISE 0C OIL
AIR CIRCULATION
M3/MIN
WEIGHT OF COOLERS
C WINDING
WINDING
TOTAL WEIGHT OF
TRANSFORMER
VOL. OF OIL IN
COOLERS
PMI, NTPC
253
D. Ht Motor
1
DESCRIPTION
6.6KV squirrel cage motor is the main driving equipment for the high
capacity rotary machines e.g. I.D. fan, F.D. fan, Bowl Mill, BFL, PA fan,
condensate and C.W. pumps.
Since these motors operate on 6.6KV supply, the insulation provided by the
manufacturer is to be checked thoroughly. Failure of insulation means
damage of the motor and consequently this will increase the down time of
the equipment as well as loss of generation. Before the actual start of
commissioning special care is to be taken for keeping the motor insulation
dry by putting the space heater in service.
The lubricant in the motor bearings plays a vital role. Proper graded
grease/lub oil should be used in order to achieve long life and efficient
performance of the bearings. Proper motor terminal connection is also to be
looked into prior to the first starting of the motor. Loose connections or
damage in the cable core insulation may cause pitting or flash over at the
time of switching on the supply and there by damage to motor. Special care
is also to be taken to check the operation of motor protections and its
interlocks. This will prevent the motor from undesired failure whenever a
fault occurs in its associated system and circuit.
2.0
2.1
TESTS
a)
Constructional/Erection Tests.
b)
Pre-commissioning Tests.
c)
Commissioning Tests.
Constructional/Erection /Tests
PMI, NTPC
254
These will comprise the thorough checking o{ the motor for any damage of
it's parts after erection and the proper placement on the foundation with all
associated erection formalities.
2.2
Pre-Commissioning Tests
These tests will be carried out when the erection is substantially complete
and will comprise of the following ;-
2.3
i.
ii.
iii.
iv.
v.
vi.
vii.
Commissioning Tests;
These tests will involve the initial starting of the motor to demonstrate that it
is operationally sound and confirms to the rated specifications.
The tests will comprise the following operations: i)
ii)
iii)
PMI, NTPC
255
SHEET
REF. NO
------------------------------------------------------------------------------------------------------------PLANT
IDENTIFICATION
-----------------------------------------------------------------------------------------------------------NAME PLANT DETAILS
------------------------------------------------------------------------------------------------------------MANUFACTURE
SERIAL NO
FRAME SIZE
TYPE
KW/HP
VOLTAGE
CURRENT
POWER FACTOR
SPEED
FREQUENCY
PHASE
RATING
INSULATION
BEARING
DE
CONNECTION
NONO
NDE
LUBRICATION
CLASS
TEMP
RISE
------------------------------------------------------------------------------------------------------------SPACE HEATER
-----------------------------------------------------------------------------------------------------------KW/HP
PMI, NTPC
VOLTAGE
PHASE
256
ANNEXURE-I
NATIONAL THERMAL POWER CORPORATION
----------------------------- STPP Unit------------------Ref:-----------------------Dated:--------------------Rectification/ requirements suggested by commissioning group
Area/ Package of Inspection:
List of Participants
Erection
1.
Date Of Inspection
2.
Commissioning
1.
2.
1.
II
PMI, NTPC
257
ANNEXURE I (Contd.)
III.
IV.
2.
3.
4.
Whenever the above works are in the present contractors scope or not:
1.
Yes/NO.
2.
Yes/No.
3.
Yes/No.
4.
Yes/No.
V.
If these works are not in the scope of the contractor indicate the estimates for
the carrying out those works (please enclosed the working sheets/ Drawing
etc.)
1.
PMI, NTPC
258
ANNEXURE-I (Contd.)
2.
3.
4.
VI.
1.
2.
3.
4.
Erection Engineer
Engineer- in Charge
(Commissioning)
VII.
VIII.
PMI, NTPC
259
ANNUXURE-II
FORMAT AND FUIDDANCE FOR COMMISSIONING REPORTS
1.
Tile
2.
Documents
3.
Programme
4.
Testing/ Commissioning
Date commenced
Initial problems- causes- solutions
Staffing.
Omissions
5.
Operational Results
Output/
Rating
achieved
Compare
specifications.
with
Failures
6.
Official lists
Operational defects
Present status.
7. Conclusions
8. Recommendations:
9. Appendices
results, etc.
PMI, NTPC
260
ANNEXURE- III
NATIONALTHERMAL POWER CORPORATION LTD.
SUPER THERMAL POWER STATION
TO..
Certificate No
(Contractor)
SAFTY RULES CLEARANCE CERTIFICATE
I herby give notice that the equipment scheduled below is being MADE ALIVE/put
INTO SERVICE or by reason of its approximately or relation to other must be
regarded as being ALIVE/IN SERVICE, and as from --------------------- hrs, on ---------------will come under the control of NTPC so far as safety rules are concerned NO
further work may be done or near the equipment after this time ands date unless
the person in charge of such work is in possession of a permit to work card on
sanction for the testing issued by a Senior Authorised person in the employ of
NTPC will you please sign the master certificate and retain addressed to you.
1.
For NTPC
Erection Department
Signature-------------------------------------------Designation--------------------------------------Date -----------------------------------------------
PMI, NTPC
261
Acceptance:
I agree the issue of the safety Rules Clearance Certificate for this plant that it
will become subject to the NTPC- Safety Rules from the date and time
specified above.
Acknowledgements:
I/ we acknowledge recipt of the above notice and confirm that all persons in
my/ our charge have been duly warned of the above. My /our men and
material have also been removed from the area / equipment of testing.
Time
Date
Distribution
Note:
a)
Once this certificate is issued no work can be done on the basis equipment
under consideration a proper PTW NTPC.
b)
PMI, NTPC
262
ANNEXURE-III (Contd,)
NATIONAL THERMAL POWER CORPORATION LTD.
. SUPER THERMAL POWER PROJECT
To
Erection Department
Certificate
No
RECORD OF INITIAL OPERATION CERTIFICATE
Contract .
Contract Ref-----------------
Contractor..
1.
2.
Initial Operation
The above plant satisfactory completed its initial operation tests on ----------------19-----------in the pressure of the following witness: The defects and
omissions notice during this trial that are to be liquidated by the contractor is
also
attached.
(Singed-----------------------------------
(Singed)----------------------------------
For Contractor
(Singed)----------------------------------
PMI, NTPC
263
ANNEXURE-III(Contd.)
NATIONAL THERMAL POWER CORPOIRATION LTD.
----------------------------SUPER THERMAL POWER PROJECT
To
O&M Department
Certificate NO.
INTERNAL TAKING OVER CERTIFICATE
Contract.
Contract
Ref..
Contractor.
In accordance with the conditions of the contract, the contractor is initiated to
Taking Over Certificate for the following plants. However., issue of ITOC does not
absolve the contractor his contractual responsibilities to rectify the plant
deficiencies, The defect list/ deviations are enclosed. The defect with a time bound
programmed for the contractor then out will give the discussed. Further deviations if
any also discussed with the contractor Further deviation if any will also be
discussed with the contractor.
1.
2.
Exception:
Subject to any you may wish make overleaf, it is proposed to issue the Taking Over
Certificate.
For NTPC Erection Deptt.
Signature----------------Designation-------------Date------------------------
PMI, NTPC
264
ANNEXURE-III (Contd.)
3.
Acceptance
i)
ii)
For NTPC
Signature-------------------------Designation----------------------Date--------------------------------
* Delete as appropriate
a)
b)
After the issue of this certificate is to the done by NTPC. Breakdown due to
design deficiencies will attended to by Contractor.
PMI, NTPC
265
2.
Acceptance:
a)
b)
Signature--------------------------Designation---------------------Date -----------------------------
* Delete as applicable
PMI, NTPC
266
ANNEXURE-IV
PROCEDURE FOR THE CONTROL& HANDLING OF DEFECTS
Stage I: Requirements for the Issue of safety Clearance Certificate
1.1
Action
Responsibility
The defects
1.2
Commissioning Panel
1.3
D.C.C.
1.5
D.C.C
list
1.6
Daily
D.C.C
D.C.C.
D.C.C/Working Party
Certificate.
PMI, NTPC
267
ANNEXURE IV (Contd.)
Stage II
1.1
- Initial Operation
Action
Responsibility
Working Party.
D.C.C.
1.3
D.C.C./Erection
D.C.C.
Stage III:
1.1
D.C.C
1.2
D.C.C
1.4
Station
Party.
D.C.C.
PMI, NTPC
O&M/
Working.
268
ANNEXURE- IV ( Contd.)
Defects and sends it to the Chief
Erection Manager
1.5
CEM/DCC.
Contractors.
1.6
CONTRACTOR
Defects.
1.7
CEM
1.8
CEM.
1.1
DGM O&M
Guarantee period
1.2
Notification to contractor
G.M.
1.3
Contractor
CEM
PMI, NTPC
269
ANNEXIRE-V
NATIONAL THERMAL POWER CORPORATION LIMITED
(OS COMMISSIONING GROUP)
List of commissioning procedures for thermal units Requiring approval of
Corporate -OS
1.
BOILER
a)
b)
c)
d)
e)
f)
g)
h)
i)
Air in leakage test of ESP (part of PG test but carried out during Precommissioning.)
j)
k)
2.
TURBINE GENERATOR
a)
i.
ii.
iii.
iv.
Heaters
PMI, NTPC
270
ANNEXURE- V ( Contd.)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
PMI, NTPC
271
ANNEXTRE - VI
NATIONAL THERMAL POWER CORPORATION LIMITED
(OS COMMG GROUP)
List of commissioning procedures for combined cycle gas projects !
Requiring approval of corporate -OS
1.
Gas pipelines
ii)
b)
Gas pipelines
ii)
c)
d)
e)
f)
g)
h)
PMI, NTPC
272
ANNEXURE- VI ( Contd.)
2.
COMBINED CYCLE
2.1
BOILER
a) Boiler hydraulic test & pwaervation procedure.
b)
c)
d)
e)
3.
ii)
iii)
iv)
Heaters
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
PMI, NTPC
273
ABHREMATIONS USED
1.
BEI
2.
FQA/QA
3. FICCC
4.
ITOC
5.
RIOC
6.
SRCC
7.
DCC.
GM
General Manager
DGM
10
CEM
11
COS
12
O&M
13
PE/ENGG
14
REB
15
CEA
PMI, NTPC
274