Project Report
Project Report
Boilers are pressure vessels designed to heat water or produce steam, which can then
be used to provide space heating and/or service water heating to a building. In most
commercial building heating applications, the heating source in the boiler is a natural
gas fired burner. Oil fired burners and electric resistance heaters can be used as well.
Steam is preferred over hot water in some applications, including absorption cooling,
kitchens, laundries, sterilizers, and steam driven equipment. Boilers have several
strengths that have made them a common feature of buildings. They have a long life,
can achieve efficiencies up to 95% or greater, provide an effective method of heating a
building, and in the case of steam systems, require little or no pumping energy.
However, fuel costs can be considerable, regular maintenance is required, and if
maintenance is delayed, repair can be costly. Guidance for the construction, operation,
and maintenance of boilers is provided primarily by the ASME (American Society of
Mechanical Engineers). Boilers are often one of the largest energy users in a building.
For every year a boiler system goes unattended, boiler costs can increase approximately
10%. Boiler operation and maintenance is therefore a good place to start when looking
for ways to reduce energy use and save money.
CONTENTS:
CHAPTER-1
INTRODUCTION
INTRODUCTION
COMPANY PROFILE
Product range
1.0
Process plants like Sulphuric acid plants, Sulphur recovery units, Nitric acid
Metallurgical plants like Blast furnaces, Zinc plants, Lead plants, Copper plants
and
Sponge iron plants etc..,
Combined cycle power plants like HRSG behind Gas turbines and Gas engines
Cement plants
DG Gensets
Incinerators
1.2
Engineering equipment
Pressure vessels
Heat exchangers
1.3
Boiler spares
ASME
IBR
BS
DIN
IS
TRD
Manufacturing facilities
Enmax is situated at Balanagar-Narasapur state highway near Jeedimetla industrial area
in Hyderabad (India). Situated in the heavy fabrication and engineering zone where all
kind of facilities like transportation, heavy cranes for material handling, sub vendors
for dish end manufacturing, plate rolling (higher thickness) etc., are available.
Works is spread over 6000 Sq yards (both covered and un-covered) area with
ample natural and supporting lighting system, ventilation, water, Electric power and
ambience.
Shop & manufacturing facilities are approved by Indian Boiler Regulating authorities
(IBR), Lloyds and BVQI. Enmax is holding an ISO accreditation (9001:2008) through
BVQI since 2009.
Chapter-2
Boiler Introduction
1.INTRODUCTION OF BOILER
A boiler is a closed vessel in which water under pressure is transformed into steam by
the application of heat. In the boiler furnace, the chemical energy in the fuel is
converted into heat, and it is the function of the boiler to transfer this heat to the
contained water in the most efficient manner. The boiler should also be designed to
generate high quality steam for plant use.
A boiler must be designed to absorb the maximum amount of heat released in
the process of combustion. This heat is transferred to the boiler water through radiation,
conduction and convection. The relative percentage of each is dependent upon the type
of boiler, the designed heat transfer surface and the fuels. The boiler house or steam
generation facility within any given plant is frequently referred to as the heart.
Boilers have several
strengths that have made them a common feature of buildings. They have a long life,
can achieve efficiencies up to 95% or greater, provide an effective method of heating a
building, and in the case of steam systems, require little or no pumping energy.
However, fuel costs can be considerable, regular maintenance is required, and if
maintenance is delayed, repair can be costly.
energy users in a building. For every year a boiler system goes unattended, boiler costs
can increase approximately 10%. Boiler operation and maintenance is therefore a good
place to start when looking for ways to reduce energy use and save money.
Guidance for the construction, operation, and maintenance of boilers is
provided primarily by the ASME (American Society of Mechanical Engineers).
Figure(1):Refractory
i.
Fire-tube Boilers
Fire tube boilers consist of a series of straight tubes that are housed inside a
water-filled outer shell. The tubes are arranged so that hot combustion gases
flow through the tubes. As hot gases flow through the tubes, they heat the water
that surrounds the tubes. The water is confined by the outer shell of the boiler.
To avoid the need for a thick outer shell, fire tube boilers are used for lowerpressure applications. Generally, the heat input capacities for fire tube boilers
are limited to 50 MBtu/h or less, 5 but in recent years the size of fire tube
boilers has increased. Fire tube boilers are subdivided into three groups.
Horizontal return tubular (HRT) boilers typically have horizontal, selfcontained fire tubes with a separate combustion chamber. Scotch, Scotch
marine, or shell boilers have the fire tubes and combustion chamber housed
within the same shell. Firebox boilers have a water-jacketed firebox and
employ, at most, three passes of combustion gases. Most modern fire tube
boilers have cylindrical outer shells with a small round combustion chamber
located inside the bottom of the shell. Depending on construction details, these
boilers have tubes configured in either one, two, three, or four pass
arrangements. Because the design of fire tube boilers is simple, they are easy to
construct in a shop and can be shipped fully assembled as a package unit.
Table2.1.1 identifies various types of fire tube boilers and the associated fuels
that they typically burn.
Coal
Fuel oil
Natural gas
Biomass
boiler type
HRT boilers
Yes
Yes
Yes
Yes
Scotch boilers
Yes
Yes
Yes
No
Firebox boilers
Yes
Yes
Yes
Yes
Table(1):Fuels used
Relatively inexpensive.
Easy to clean.
Compact in size.
Not suitable for high pressure applications 250 psig and above.
ii.
Water-tube Boilers
In
a water-tube boiler, the water is inside the tubes and combustion gases pass
around the outside of the tubes. The advantages of a water-tube boiler are a
lower unit weight-per-pound of steam generated, less time required to raise
steam pressure, a greater flexibility for responding to load changes, and a
greater ability to operate at high rates of steam generation.
A water-tube design is the exact opposite of a fire-tube. Here, the water
flows through the tubes and is encased in a furnace in which the burner fires.
These tubes are connected to a steam drum and a mud drum. The water is
heated and steam is produced in the upper drum. Large steam users are better
suited for the water-tube design. The industrial water-tube boiler typically
produces steam or hot water primarily for industrial process applications, and is
used less frequently for heating applications. The best gauge of which design to
consider can be found in the duty in which the boiler is to perform. The ability
of water tube boilers to generate superheated steam makes these boilers
particularly attractive in applications that require dry, high-pressure, highenergy steam, including steam turbine power generation. Owing to their
superb working properties, the use of water tube boilers is highly preferred in
following major areas: Variety of process applications in industries Chemical
processing divisions Pulp and Paper manufacturing plants Refining units
Besides, they are frequently employed in power generation plants where large
quantities of steam (ranging up to 500 kg/s) having high pressures i.e.
Are available in sizes far greater than a fire-tube design , up to several million
pounds-per-hour of steam.
2.
Programming modes of operation for different times of the day, that reduce the
amount of money for heating
3.
4.
5.
6.
7.
8.
The system cannot freeze (ion boiler heat carriers do not freeze until a
temperature of -40C),
9.
Figure(4):Package Boiler
Fig 5 6
Whether the boiler is a drum or whether it is an individual unit or a small part of large
complex, it is necessary in design to give proper consideration to performance required
from the total complex of the steam generating unit. Within this frame work, there are
some important items, which must be accomplished in boiler design. The items which
are of importance are as stated below:
1. Determine the heat to be absorbed in the boiler and other heat transfer
equipment, the optimum efficiency to use and the type of fuel or fuels dor
which the unit is to be designed. When a particular fuel is selected, determine
the amount of fuel required the necessary or preferred preheated air temperature
and the quantities of air required and flue gases to be generated.
2. Determine the size and shape required for the furnace, giving considerations to
location, the space requirements of burners or fuel bed, and incorporating
sufficient furnace volume to accomplish complete combustion. Provision must
also be made for proper furnace walls to reduce the gas temperature leaving the
furnace to the desired value.
3. The general disposition of the convection heating surfaces must be so planned
that the super heater and the re-heater when provided, are located at the
optimum temperature zone where the gas temperature is high enough to afford
good heat transfer from the gas to the steam, yet not no high as to result in
excessive tube temperatures or excessive fouling from ash in the fuel.
4. Pressure parts must be designed in accordance with applicable codes using
approves materials with stresses not exceeding those allowable at the
temperatures experienced during operation.
5. A tight boiler setting or enclosure must be constructed around the furnace and
boiler, and gas tight flues or ducts must be provides to convey the gases of
combustion to the stack.
6. Supports for pressure and setting must be designed with adequate consideration
for expansion and local requirements, including wind and earthquake loading.
12. Equipped with the very best gauges, safety valves and other fixtures.
Chapter-3
RAW MATERIALS
ksi [MPa]
55 [380]
5575 [380-515]
60 [415]
6080 [415-550]
65 [450]
6585 [450-585]
70 [485]
7090 [485-
620]
Table(2):Tensile strengths
The maximum thickness of plates is limited only by the capacity of the composition to
meet the specified mechanical property requirements; however, current practice
normally limits the maximum thickness of plates furnished under this specification as
follows:
Maximum
Grade U.S. [SI]
Thickness,
in. [mm]
55 [380]
12 [305]
60 [415]
8 [205]
65 [450]
8 [205]
70 [485]
8 [205]
Table(3):Maximum thickness
Figure(7):Plate
Element
Grade A-1
Grade C
Carbon, max
0.27
0.35
Manganese
0.93 max
0.291.06
Phosphorus, max
0.035
0.035
Sulphur, max
0.035
0.035
Silicon, min
0.10
0.10
Size of Tube
Size of Lot
Diameter
Table(7): Number of tubes in a lot heat treated by the continuous process.
GradeA-1
GradeC
i.
60 [415]
70 [485]
ii.
37 [255]
40 [275]
iii.
30
30
iv.
1.50
1.50
22
20
Figure(9):Tubes
Composition %
Carbon, max
Grade A
0.25
Grade B
0.30
Grade C
0.35
Manganese
0.270.93
0.291.06
0.291.06
Phosphorus, max
0.035
0.035
0.035
Sulphur, max
0.035
0.035
0.035
Silicon, min
0.10
0.10
0.10
Chrome, max
0.40
0.40
0.40
Copper, max
0.40
0.40
0.40
Molybdenum, max
0.15
0.15
0.15
Nickel, max
0.40
0.40
0.40
Vanadium, max
0.08
0.08
0.08
Grade A
Grade B
Grade C
48 000 [330]
60 000 [415]
70 000 [485]
30 000 [205]
35 000 [240]
40 000 [275]
Figure(10):Pipes
Chapter-4
Design Calculations
4.1Different codes
Codes used in Design of boiler are IBR-1950,ASME sec viii Div 1,ASME
sec-1.
4.2 Process design calculations for Boiler
Gas flow : 4000Nm^3/hr
4.2.1Gas composition:
H2O : 2.0% , O2 : 12% , N2 : 74% , CO2 : 12%.
Gas Inlet Temperature
: Tg2 = 9500 c
: Tg2 = 2400 c
: 100mm WG
: g : 1.4456 kg/Nm3
: Pr : 0.68
Thermal conductivity : k
: 0.07 kcal/mhr0c
= ms(h2-h1)
=>1.438 = 2500(h2-100.001)
=>h2 = 675
At Saturated Enthalpy h2 corresponding temperature is 1850c
Tw2 = 1850c
Average Temperature of steam (Tavg)s
(Tavg)s = (185+100)/2
= 142.50c
4.2.5Properties of steam at Tavg is
: w : kg/m3 : 21.3394
i.
Density
ii.
iii.
iv.
Prandtl number
: Pr : 1.3875
v.
Specific heat
: Cp : kcal/kg0c : 0.9820
= 128
= 33
4.2.11Required Area
A= Q/U LMTD
= 1.086316106/(33368.08)
= 89.43 m2
Method of Manufacturing
(1)
(3)
(4)
(5)
Fe330
Fe410
Fe450
ERW
Fe330
Fe410
Fe450
SAW
Fe330
Fe410
Fe450
(2)
Seamless
Electric resistance including
induction welded
Submerged Arc Welding
(including spirally welded)
Figure(11):Arc Welding
TIG WELDING
Gas tungsten arc welding (GTAW), also known as tungsten inert gas (TIG) welding, is
an arc welding process that uses a non-consumable tungsten electrode to produce the weld.
The weld area is protected from atmospheric contamination by an inert shielding
gas (argon or helium), and a filler metal is normally used, though some welds, known as
autogenously welds, do not require it. A constant-current welding power supply produces
energy which is conducted across the arc through a column of highly ionized gas and metal
vapors known as a plasma.
GTAW is most commonly used to weld thin sections of stainless steel and non-ferrous
metals such as aluminum ,magnesium, and copper alloys. The process grants the operator
greater control over the weld than competing processes such as shielded metal arc
welding and gas metal arc welding, allowing for stronger, higher quality welds. However,
GTAW is comparatively more complex and difficult to master, and furthermore, it is
significantly slower than most other welding techniques. A related process, plasma arc welding,
uses a slightly different welding torch to create a more focused welding arc and as a result is
often automated.[
Figure(12):GTAW
Oxy-acetylene gas
The oxyacetylene process produces a high temperature flame, over 3000 degrees C, by
the combustion of pure oxygen and acetylene. It is the only gas mixture hot enough to
melt steel; other gases (propane, LPG or hydrogen) can be used for lower melting point
non-ferrous metals, for brazing and silver soldering and as a preheating/piercing gas for
cutting.
Handling compressed gases
Cylinders are fitted with regulators to reduce the gas pressure in the cylinder to the
working pressure of the torch. The regulator has two gauges, a high pressure gauge for
the gas in the cylinder and a low pressure gauge for the gas being fed to the torch. The
gas flow rate is controlled by a pressure adjusting screw which sets the outlet gas
pressure. The BCGA Code of Practice CP7 recommends the gauges are checked
annually and replaced every 5 years.
Factors to be considered are that the gas system is suitable for the pressure
rating and the hoses are connected without any leaks. Valve threads should be cleaned
before screwing in the regulator. The valve of an acetylene cylinder can be opened
slightly to blow out the threads but the threads in oxygen cylinders are best cleaned
using clean compressed air (the threads on hydrogen cylinders must always be blown
out using compressed air).
As oxygen can react violently with oils and grease, lubricating oils or sealant for the
threads must not be used.
Using compressed gases
Gases are mixed in the hand-held torch or blowpipe in the correct proportions. Hoses
between regulator and torch should be color coded; red for acetylene and blue for
oxygen. Hoses should be kept as short as possible and users should check periodically
that they are not near hot or sharp objects which could damage the hose wall. Acetylene
cylinders must always be used upright.
When connecting the system, and at least at the start of each shift, hoses and torch must
be purged to remove any inflammable gas mixtures. It is essential the oxygen stream
does not come into contact with oil which can ignite spontaneously. Purging should
also not be carried out in confined spaces.
The torch should be lit with a friction lighter or stationary pilot flame to avoid burning
the hands; matches should not be used and the flame should not be reignited from hot
metal, especially when working in a confined space.
Although very little UV is emitted, the welder must wear tinted goggles.
Figure(14):gas cutting
Chanper-5
Manufacturing, Operation and Maintainence Process
Plates are available in 2500 x 10000 x12. Marking of plates as mentioned below.
After cutting of shell sections-I & II, edge preparation of plates is required for Long
seam and circumferential joints as mentioned below.
Fit up of Long seam I and Long seam II, Fit up inspection and clearance for
welding.
After welding, visual inspection of welding and clearance for NDT (Radiography Test)
After welding Visual inspection of Weld joint and clearance for NDT(RT)
Interpretation of RT films and after acceptance main shell is cleared for further
processing.
Figure(17):Shell Rolling
Conclusion: