Sod-08556 - LSP-005 - Fat-005..
Sod-08556 - LSP-005 - Fat-005..
Sod-08556 - LSP-005 - Fat-005..
DOCUMENT INFORMATION
Doc No:
LSP-005-FAT-2015
Srl No:
Revision
Mag file
Issued
02-02-2015.
Author
Unique
FAT
LSP-005
VK
CLIENT
16 June 2013
Page 1 of 24
Contents
1. Introduction ........................................................................................................................................................ 4
1.1 Scope ............................................................................................................................................................ 4
1.2 Objective ....................................................................................................................................................... 4
1.3 Definitions..................................................................................................................................................... 4
1.4 Responsibilities ............................................................................................................................................. 4
1.5 Reference Documents .................................................................................................................................. 4
2. GENERAL ............................................................................................................................................................. 5
2. 1 Operations manual ...................................................................................................................................... 5
2.2 Cleanliness of System ................................................................................................................................... 5
2.3 Permanent marking of equipment ............................................................................................................... 6
2.4 Calibration of essential gauges and clocks ................................................................................................... 6
2.5 Structural integrity and corrosion status of system ..................................................................................... 6
2.6 Gas distribution system ................................................................................................................................ 7
2.7
2.10
2.11
FAT
Communication systems...................................................................................................................... 19
16 June 2013
Page 2 of 24
Fire Protection.................................................................................................................................. 20
2.14.
2.15.
FAT
16 June 2013
Page 3 of 24
1. Introduction
This FAT has been compiled to define testing requirements for maintaining the certification of the portable chamber
control (Life Support Package). It may also form the basis of the certificate that is to be issued upon successful completion
of the testing and inspection listed herein.
Only a nominated competent person may sign for the completion of a task detailed in this manual. Before doing so,
section 1.1 must be completed by the person signing.
IMPORTANT
This manual is used for each periodic survey. During each year, the equipment comprising the portable chamber control
may change. Always check that the copy being used has been revised for the year and type of survey being performed.
1.1 Scope
The scope of this Factory Acceptance Test (FAT) covers the testing of all equipment that is contained in the Life Support
System ( LSP 005) as defined by the client approved manufacturing design data provided with the FAT.
1.2 Objective
To Ensure that the LSP design & Operation meets the contractual requirements.
1.3 Definitions
The following terms and abbreviations are used throughout this manual and their meaning will be as defined below.
Classification Society
Det Norske Veritas (DNV)
ECU
Environmental Control Unit
HRV
Hyperbaric Rescue Vessel
SPP
Sound Powered Phone
SWL
Safe Working Load.
1.4 Responsibilities
Unique System shall prepare the FAT and carry out all the testing.
The Client Representative shall approve the FAT and witness all the testing.
Unique
name
& Sign
FAT
16 June 2013
Page 4 of 24
2. GENERAL
2. 1 Operations manual
Inspection
1.
2.
3.
4.
Accept/Reject
Reason
Accept/Reject
Reason
2.
3.
4.
5.
Unique
name
& Sign
FAT
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 5 of 24
Accept/Reject
Reason
Accept/Reject
Reason
Accept/Reject
Reason
2.
3.
Ensure the serial number and certificate numbers and test date
labels are available on the gauges
The container should be made as per DNV rules DNV 2.7-1 and
review the DNV certificate of the container.
2.
3.
4.
Unique
name
& Sign
FAT
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 6 of 24
Accept/Reject
Reason
3.
Ensure the pressure testing of the panels are satisfactory and review
the certificate.
Unique
name
& Sign
FAT
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 7 of 24
Accept/Reject
1.
2.
Complete a visual inspection of the ECU and ensure all areas are free
of dirt, bad workmanship or scratches.
Ensure all bolts where used on vibration applications are nylock or
have spring washers.
Ensure all lifting arrangements are full safety bolts with split pin and
castle nut.
Ensure all supplied nuts are replaced with stainless steel, including
nuts, etc.
Inspect filter after use and ensure it is clean before packing.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Ensure all exhaust pipe-work such as relief valve vents, etc vent in to
an enclosed space or safe place. (Never into a person face or body)
Ensure pipe clamps are secure.
16.
17.
Inspect insulation and ensure all areas are covered. Ensure insulation
is neat and tidy.
Unique
name
& Sign
FAT
Client
name &
Sign
Reason
N/A
Client
name &
Sign
16 June 2013
Page 8 of 24
Reason
Inspection
Accept/Reject
19.
20.
21.
22.
23.
24.
25.
With the power OFF at the main circuit breaker and disconnected,
conduct a panel wire pull test; ensure all wires are installed tightly.
26.
1.
HOT Supply
3 Bar
2.
HOT Return
3 Bar
3.
COLD Supply
3 Bar
4.
COLD Return
3 Bar
5.
HOT Tank
Surface
6.
COLD Tank
Surface
7.
Leak test at WP
8.
Leak test at WP
Unique
name
& Sign
FAT
Client
name &
Sign
Pass/Fail
Client
name &
Sign
16 June 2013
Page 9 of 24
Required result
Result obtained
Accept/
Reject
1.
2.
3.
+/-1C Difference
4.
Functioning
5.
6.
7.
9.
11.
No Leaks
12.
13.
Unique
name
& Sign
FAT
Ambient
Temp:
HOT WATER
PUMP:
COLD WATER
PUMP:
3 successful indications
required
Cold water- 20C to 6C
Hot Water- 49.5C to 60 C
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 10 of 24
U1 V1
2.
V1 W1
3.
W1 U1
Megger result
Continuity result
U1 V1
2.
V1 W1
3.
W1 U1
2.
3.
Unique
name
& Sign
FAT
Megger result
Client
name &
Sign
Continuity result
Client
name &
Sign
16 June 2013
Page 11 of 24
Test Method
Required result
1.
Control Parameters
setting
2.
Control Parameters
setting
9. Amp
O/L-2
9 Amp
O/L-3
2.3 Amp
O/L-4
2.3 Amp
3.
4.
5.
Result
obtained
Accept/Reject
1C
6.
7.
8.
9.
Unique
name
& Sign
FAT
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 12 of 24
Accept/Reject
1.
2.
Complete a visual inspection of the ECU and ensure all areas are free
of dirt, bad workmanship or scratches.
Ensure all bolts where used on vibration applications are nylock or
have spring washers.
Ensure all lifting arrangements are full safety bolts with split pin and
castle nut.
Ensure all supplied nuts are replaced with stainless steel, including
nuts, etc.
Inspect filter after use and ensure it is clean before packing.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Ensure all exhaust pipe-work such as relief valve vents, etc vent in to
an enclosed space or safe place. (Never into a person face or body)
Ensure pipe clamps are secure.
16.
17.
Inspect insulation and ensure all areas are covered. Ensure insulation
is neat and tidy.
Unique
name
& Sign
FAT
Client
name &
Sign
Reason
N/A
Client
name &
Sign
16 June 2013
Page 13 of 24
Reason
Inspection
Accept/Reject
19.
20.
21.
22.
23.
24.
25.
With the power OFF at the main circuit breaker and disconnected,
conduct a panel wire pull test; ensure all wires are installed tightly.
26.
1.
HOT Supply
3 Bar
2.
HOT Return
3 Bar
3.
COLD Supply
3 Bar
4.
COLD Return
3 Bar
5.
HOT Tank
Surface
6.
COLD Tank
Surface
7.
Leak test at WP
8.
Leak test at WP
Unique
name
& Sign
FAT
Client
name &
Sign
Pass/Fail
Client
name &
Sign
16 June 2013
Page 14 of 24
Required result
Result obtained
Accept/
Reject
1.
2.
3.
+/-1C Difference
4.
Functioning
5.
6.
7.
9.
Off @ 6C; On @ 8 C
11.
No Leaks
12.
Off @ 60C; On @ 59 C
13.
Unique
name
& Sign
FAT
Ambient
Temp:
HOT WATER
PUMP:
COLD WATER
PUMP:
3 successful indications
required
Cold water- 18C to 6C
Hot Water- 53.5C to 64 C
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 15 of 24
U1 V1
2.
V1 W1
3.
W1 U1
Megger result
Continuity result
U1 V1
2.
V1 W1
3.
W1 U1
2.
3.
Unique
name
& Sign
FAT
Megger result
Client
name &
Sign
Continuity result
Client
name &
Sign
16 June 2013
Page 16 of 24
Test Method
Required result
1.
Control Parameters
setting
2.
Control Parameters
setting
9. Amp
O/L-2
9 Amp
O/L-3
2.3 Amp
O/L-4
2.3 Amp
3.
4.
1C
5.
7.5 AMPS(0.5)
6.
Result
obtained
Accept/Reject
7.
8.
10.
11.
Unique
name
& Sign
FAT
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 17 of 24
IMCA SECTION
PARAGRAPH
6.8
Electrical Protection
UDp-14-64184,64185,64186
6.9
Electrical testing
UDp-14-64184,64185,64186
6.10
UDp-14-64184,64185,64186
8.5
UDP-14-64473
8.6
UDP-14-64474
8.7
12-36753-1
8.10
Communication testing
UDP-14-64187,64188
8.22
Communication testing
UDP-14-64187,64188
8.31
UDP-14-64216,64217,64218
8.32
UDP-14-64467,64468,64469
8.33
UDP-14-64467,64468,64469
8.35
8.36
UDP-14-64191,64192,64193,64194, 64195
UDP-14-64191,64192,64193,64194, 64195
8.38
UDp-14-64184,64185,64186
8.48
8.49
UDP-14-64182, 64183
9.3
UDP-14-64210, 64214
11.5
UDP-14-64170,171,173,175
11.5
UDP-14-64170,171,173,175
11.5
12.6
12.7
12.8
12.8
12.2
Unique
name
& Sign
FAT
Client
name &
Sign
Report Number(s)
UDP-14-64182, 64183
UDP-14-64170,171,173,175
UDP-14-64169,172,174,176,
177,178,179, 180,181,182,183
UDP-14-64169,172,174,176,
177,178,179, 180,181,182,183
UDP-14-64169,172,174,176,
177,178,179, 180,181,182,183
158561/1 , 158561/2
Client
name &
Sign
16 June 2013
Page 18 of 24
2.10
2.
3.
Monitoring devices
4.
Control Panel
5.
6.
7.
8.
1.
9.
Accept/Reject
Reason
Accept/Reject
Reason
2.11
Communication systems
Inspection
1.
Accept
2.
The test should include the use of the sound powered phone and
headsets.
Accept
3.
Accept
Unique
name
& Sign
FAT
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 19 of 24
Accept/Reject
1.
2.
3.
Reason
Accept/Reject
1.
2.
3.
Ensure the testing of the fire extinguisher is in date and review the
certificate.
Reason
SYSTEM
POWER
Internal Lighting
OPERATIONAL
Comments
Unique
name
& Sign
FAT
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 20 of 24
Equipment/System
Requirement
Walkways
Clear
Non Slip
Sea fastenings
Electrical supply
Gas supply
Unique
name
& Sign
FAT
Findings
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 21 of 24
3. PRESSURE TESTING
3.1 Piping pressure testing
Pressure testing is to be carried out on all relevant components the following Table gives indicative test pressures for
typical components of the control panel & system.
ITEM
Hydro Testing
(Review)
Pass/ Fail
Mix-1 In
Mix-1 Out
Mix-2 in
Mix-2 out
O2 Injection in
O2 Injection Out
Bibs in
Bibs out
Depth in
Sample in
Panel Exhaust
Flow test need to carried out with full working pressure of the system along with the whips and hoses
Visual Examination: E External; I Internal.
All above to be witnessed by DNV surveyor.
Hydro-test covers thorough visual inspection, internally.
Leak test with minimum 100% Nitrogen. Note fire risk with air at high pressure.
When testing gauges ensure the gauge is not pressurized above maximum pressure.
Unique
name
& Sign
FAT
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 22 of 24
Hydro
Testing
Length
Working
Pressure
Gas Leak
Testing
(Witnessed)
1 hour
Hydro test
(Witnessed)
Pass/ Fail
Depth
Sample
O2 Make-up
In
Out
BIBS Supply
In
Out
Mix-1
In
Out
Mix-2
In
Out
Exhaust
Hot Water Supply
In
Out
In
Out
Flow test from the panel through the interconnecting hoses with 200 bar on line.
Hot and cold water flow test through hoses
Pressure and leak test of the hoses
Unique
name
& Sign
FAT
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 23 of 24
4. Control Measures
The following are typical controls which may be required from the task risk assessment
Inspection
1.
Accept/Reject
Reason
2.
Hearing protection for gas testing
3.
4.
5.
6.
7.
8.
9.
Eye protection
Hose and whip securing
Permit to work to be raised for the test
Provision of suitable ventilation in the area of the pressure test
Provision of suitable escape routes for test personnel
Provision of oil contamination cleanup materials if the test medium
is oil
Ensuring that a failure during the pressure test will not cause
damage to the surrounding area (water leakage causing damage to
surrounding area due to poor drainage or gas escape causing
localized
overpressure)
Unique
name
& Sign
FAT
Client
name &
Sign
Client
name &
Sign
16 June 2013
Page 24 of 24