REHAU Catalog
REHAU Catalog
REHAU Catalog
RAUTITAN pink
Under Floor Heating System
System
Page
13
19
24
25
Version: Mar-2012
Page: 1
GENERAL
This section relates to REHAU Under Floor
Heating / Cooling (UFH/C) system.
SYSTEM DESCRIPTION
The REHAU RAUTITAN system for under floor heating and cooling applications consists of:
RAUTITAN pink pipe, fittings and accessories
REHAU manifolds
REHAU flow temperature control
REHAU zone control
Main supply and return pipes including valves and fittings, main circulation pump, heat source
and all other components required to render the system fully operational are not included in
this section.
REFERENCE DOCUMENTATION
The documents referred to in this section are:
NCC / BCA
Building Code of Australia
BS EN 1264
Floor heating - Systems and components
BS 7291
Thermoplastic pipes and associated fittings for hot and cold water for
domestic purposes and heating installations in buildings
3.1
Manufacturers documentation
Manufacturers and suppliers documents relating to work in this section are:
REHAU Piping, Connection and System Guidelines Technical information
REHAU Under Floor Heating/Cooling Technical Information
The above information is available from REHAU:
Web:
www.rehau.com.au
Phone: 1300 768 033 (Australia only) or +61 2 8741 4500
Pipe dimensions
16 x 2.2mm or 20 x 2.8mm
System
In-Slab
Reverse Spiral
Version: Mar-2012
Page: 2
Double Meander
Single Meander
Pipe spacing
Number of zones
Number of manifolds
Number of circuits
29 C
m3/h
Zone control
RAUMATIC M
Standard
Control
Comfort (optional with floor sensor)
MATERIALS
6.1
6.2
RAUTITAN pink
Colour
Pink
Material
Pressure rating
Design pressure
Continuous operation
70 C at 1,000 kPa
90 C
100 C
50 years
Available sizes in mm
16 x 2.2mm
32 x 4.4mm
50 x 6.9 mm*
20 x 2.8mm
40 x 5.5mm
63 x 8.6 mm*
25 x 3.5mm
* Non-standard item in Australia. Check for availability.
AS/NZS 2492:2007
BRANZ appraisal no. 434
Version: Mar-2012
Page: 3
6.3
6.4
REHAU manifold
Manifolds shall be installed at a location approved by the Architect. The number of manifold
outlets shall correspond to the number of circuits served by that manifold.
Option 1: Brass
REHAU manifold manufactured from standard (CW508L) brass as a distributor and collector
for the individual heating and cooling circuits. Pre-assembled and mounted on sound-insulated
galvanised steel brackets. Combined flow meter 0-4 l / min and quick stop in the supply
header, thermostat insert with flow rate control in return header. 2 to 12 outlets male thread
euro-cone. Maximum operational pressure 600kPa (6 bar) at 80C. N.B. 7-port, 9-port and 11port manifolds are non-standard items in Australia and New Zealand, please check with your
local REHAU Sales Office for availability.
Option 2: Polymer
Modular REHAU manifold manufactured from corrosion resistant and thermal resistant
reinforced fibreglass as a distributor and collector for the individual heating and cooling
circuits. Supply modules in red colour with integrated shut-off valve, attachment of actuator
possible. Return modules in blue colour with integrated, adjustable flow meter, lead-sealable
cap. 2 to 17 outlets male thread euro-cone. Operating temperatures from -20 to +90C.
Maximum test pressure 1,000kPa (10 bar), maximum operational pressure 600kPa (6 bar).
6.5
Page: 4
7
7.1
Version: Mar-2012
Page: 5
7.3
Initial Warm-Up
Allow the concrete to dry for 3 weeks. Balance the system via the valves on the manifold to
achieve an even flow and heat up. Start the warm-up procedure according with BS EN 1264
and REHAU requirements. Provide signed and witnessed warm-up protocol.
7.4
Commissioning
Ensure the complete central heating system, including main supply circulation pump and
radiators if present, is working. Based on the real pipe length noted during laying of the
pipework, adjust each circuit slowly via the valves on the manifold to ensure an even flow and
heat up is achieved (hydraulic balancing). Provide commissioning certificate.
Run the system for at least two weeks before the floor covering is finally laid. For floor
coverings use adhesive suitable for temperatures up to 40C.
DOCUMENTATION
8.1
Design Data
Installer to provide pipe layout drawing to main contractor prior to installation.
8.2
8.3
MANUFACTURER WARRANTY
25 years Pipe warranty period from date of completion of system test, based on the Terms and
Conditions of the REHAU RAUTITAN Warranty Certificate in the manufacturers standard form.
Version: Mar-2012
Page: 6
GENERAL
This section relates to REHAU Under Floor Heating /
Cooling (UFH/C) system.
SYSTEM DESCRIPTION
The REHAU tacker system for under floor heating and cooling applications consists of:
RAUTITAN pink pipe, fittings and accessories
REHAU tacker sheet
REHAU tacker staples
REHAU edge insulation strip
REHAU expansion joints
REHAU manifolds
REHAU flow temperature control
REHAU zone control
Main supply and return pipes including valves and fittings, main circulation pump, heat source
and all other components required to render the system fully operational are not included in
this section.
REFERENCE DOCUMENTATION
The documents referred to in this section are:
NCC / BCA
Building Code of Australia
BS EN 1264
Floor heating - Systems and components
BS EN 13163
Thermal insulation products for buildings. Factory made products of
expanded polystyrene. Specification
BS 7291
Thermoplastic pipes and associated fittings for hot and cold water for
domestic purposes and heating installations in buildings
3.1
Manufacturers documentation
Manufacturers and suppliers documents relating to work in this section are:
REHAU Piping, Connection and System Guidelines Technical information
REHAU Under Floor Heating/Cooling Technical Information
The above information is available from REHAU:
Web:
www.rehau.com.au
Phone: 1300 768 033 (Australia only) or +61 2 8741 4500
Version: Mar-2012
Page: 7
Pipe
Pipe dimensions
16 x 2.2mm or 20 x 2.8mm
System
Tacker
Reverse Spiral
Double Meander
Single Meander
Pipe spacing
Number of zones
Number of manifolds
Number of circuits
29 C
m3/h
Zone control
RAUMATIC M
Standard
Control
Comfort (optional with floor sensor)
MATERIALS
6.1
6.2
RAUTITAN pink
Colour
Pink
Material
Pressure rating
Design pressure
Continuous operation
70 C at 1,000 kPa
90 C
100 C
50 years
Available sizes in mm
16 x 2.2mm
20 x 2.8mm
Version: Mar-2012
32 x 4.4mm
40 x 5.5mm
50 x 6.9 mm*
63 x 8.6 mm*
Page: 8
25 x 3.5mm
* Non-standard item in Australia. Check for availability.
Australia and New Zealand approvals and
certifications
6.3
AS/NZS 2492:2007
BRANZ appraisal no. 434
6.4
Version: Mar-2012
Page: 9
6.5
REHAU manifold
Manifolds shall be installed at a location approved by the Architect. The number of manifold
outlets shall correspond to the number of circuits served by that manifold.
Option 1: Brass
REHAU manifold manufactured from standard (CW508L) brass as a distributor and collector
for the individual heating and cooling circuits. Pre-assembled and mounted on sound-insulated
galvanised steel brackets. Combined flow meter 0-4 l / min and quick stop in the supply
header, thermostat insert with flow rate control in return header. 2 to 12 outlets male thread
euro-cone. Maximum operational pressure 600kPa (6 bar) at 80C. N.B. 7-port, 9-port and 11port manifolds are non-standard items in Australia and New Zealand, please check with your
local REHAU Sales Office for availability.
Option 2: Polymer
Modular REHAU manifold manufactured from corrosion resistant and thermal resistant
reinforced fibreglass as a distributor and collector for the individual heating and cooling
circuits. Supply modules in red colour with integrated shut-off valve, attachment of actuator
possible. Return modules in blue colour with integrated, adjustable flow meter, lead-sealable
cap. 2 to 17 outlets male thread euro-cone. Operating temperatures from -20 to +90C.
Maximum test pressure 1,000kPa (10 bar), maximum operational pressure 600kPa (6 bar).
6.6
6.7
Page: 10
Thermal actuators to allow the individual control of circuits by opening and closing the
corresponding isolating valve on the manifold. The RAUMATIC actuator is controlled by room
thermostat Standard, Comfort or Control. Operating voltage 24 VAC
7
7.1
7.2
Page: 11
under pressure until concrete is cured. Provide signed and witnessed pressure testing
protocol.
7.3
Initial Warm-Up
Allow the concrete to dry for 3 weeks. Balance the system via the valves on the manifold to
achieve an even flow and heat up. Start the warm-up procedure according with BS EN 1264
and REHAU requirements. Provide signed and witnessed warm-up protocol.
7.4
Commissioning
Ensure the complete central heating system, including main supply circulation pump and
radiators if present, is working. Based on the real pipe length noted during laying of the
pipework, adjust each circuit slowly via the valves on the manifold to ensure an even flow and
heat up is achieved (hydraulic balancing). Provide commissioning certificate.
Run the system for at least two weeks before the floor covering is finally laid. For floor
coverings use adhesive suitable for temperatures up to 40C.
DOCUMENTATION
8.1
Design Data
Installer to provide pipe layout drawing to main contractor prior to installation.
8.2
8.3
MANUFACTURER WARRANTY
25 years Pipe warranty period from date of completion of system test, based on the Terms and
Conditions of the REHAU RAUTITAN Warranty Certificate in the manufacturers standard form.
Version: Mar-2012
Page: 12
GENERAL
This section relates to REHAU Under Floor Heating /
Cooling (UFH/C) system.
SYSTEM DESCRIPTION
The REHAU RAUFIX system for under floor heating and cooling applications consists of:
RAUTITAN pink pipe, fittings and accessories
REHAU RAUFIX rails
REHAU RAUFIX retaining pins
REHAU manifolds
REHAU flow temperature control
REHAU zone control
Main supply and return pipes including valves and fittings, main circulation pump, heat source
and all other components required to render the system fully operational are not included in
this section.
REFERENCE DOCUMENTATION
The documents referred to in this section are:
NCC / BCA
Building Code of Australia
BS EN 1264
Floor heating - Systems and components
BS 7291
Thermoplastic pipes and associated fittings for hot and cold water for
domestic purposes and heating installations in buildings
3.1
Manufacturers documentation
Manufacturers and suppliers documents relating to work in this section are:
REHAU Piping, Connection and System Guidelines Technical information
REHAU Under Floor Heating/Cooling Technical Information
The above information is available from REHAU:
Web:
www.rehau.com.au
Phone: 1300 768 033 (Australia only) or +61 2 8741 4500
Pipe dimensions
16 x 2.2mm or 20 x 2.8mm
System
RAUFIX
Version: Mar-2012
Page: 13
Double Meander
Single Meander
Pipe spacing
Number of zones
Number of manifolds
Number of circuits
29 C
m3/h
Zone control
RAUMATIC M
Standard
Control
Comfort (optional with floor sensor)
MATERIALS
6.1
6.2
RAUTITAN pink
Colour
Pink
Material
Pressure rating
Design pressure
Continuous operation
70 C at 1,000 kPa
90 C
100 C
50 years
Available sizes in mm
16 x 2.2mm
32 x 4.4mm
50 x 6.9 mm*
20 x 2.8mm
40 x 5.5mm
63 x 8.6 mm*
25 x 3.5mm
* Non-standard item in Australia. Check for availability.
AS/NZS 2492:2007
BRANZ appraisal no. 434
Version: Mar-2012
Page: 14
6.3
6.4
6.5
REHAU manifold
Manifolds shall be installed at a location approved by the Architect. The number of manifold
outlets shall correspond to the number of circuits served by that manifold.
Option 1: Brass
REHAU manifold manufactured from standard (CW508L) brass as a distributor and collector
for the individual heating and cooling circuits. Pre-assembled and mounted on sound-insulated
galvanised steel brackets. Combined flow meter 0-4 l / min and quick stop in the supply
header, thermostat insert with flow rate control in return header. 2 to 12 outlets male thread
Version: Mar-2012
Page: 15
euro-cone. Maximum operational pressure 600kPa (6 bar) at 80C. N.B. 7-port, 9-port and 11port manifolds are non-standard items in Australia and New Zealand, please check with your
local REHAU Sales Office for availability.
Option 2: Polymer
Modular REHAU manifold manufactured from corrosion resistant and thermal resistant
reinforced fibreglass as a distributor and collector for the individual heating and cooling
circuits. Supply modules in red colour with integrated shut-off valve, attachment of actuator
possible. Return modules in blue colour with integrated, adjustable flow meter, lead-sealable
cap. 2 to 17 outlets male thread euro-cone. Operating temperatures from -20 to +90C.
Maximum test pressure 1,000kPa (10 bar), maximum operational pressure 600kPa (6 bar).
6.6
6.7
7
7.1
Page: 16
Co-ordinate with builder at shop drawing stage to identify all construction joints and saw cuts
with concrete floors. Install the manifold straight at the designated position.
Ensure the area for installation remains dry and weathertight by incorporating a dampproof
membrane in the floor slab. Lay insulation to the total area of the installation, with edge
insulation on all internal and external wall lines. If the floor construction is a two part slab with
the walls already in place, edge insulation is required around the walls to prevent heat loss up
the walls and to allow the screed for expansion.
Screed insulation and damp proof membrane not part of REHAU product range and to be
chosen according to separate specification.
Connect RAUFIX rails to form the desired length and lay parallel on the floor with a spacing of
1m. Secure RAUFIX rails with RAUFIX retaining pins with a spacing of 400mm. Connect one
end of the pipe to the manifold and clip the pipe into the moulded connectors of the RAUFIX
rail. Secure the pipe in areas of direction change with additional REHAU Tacker staples or
RAUFIX retaining pins. Mark all heated and non-heated areas and floor joints on the floor
area. Assemble the REHAU expansion joint profile.
Pipework Layout
Pipework fixed onto the insulation board to REHAU's recommendations. Lay pipes in a
continuous length from the manifold in the pre-designed configuration. REHAU fittings can be
embedded into concrete if agreed with designer. Fittings to be wrapped with PVC tape. Pipes
start and finish at the manifold position. Pipes must run to the corresponding port on the
manifold. Do not cross pipes over in the floor. Note the real pipe length of each circuit to adjust
the hydraulic balancing of the manifold. Mark the name of each circuit on the corresponding
manifold outlet.
All coils in floors shall be installed strictly in compliance with the requirements of the structural
engineer and in accordance with the recommendations of REHAU for concrete floor heating
applications. Piping shall be installed completely free of twists, warps or buckles. Screed
height should provide a minimum thickness of 45mm above the crown of the pipework.
Depending on structural loads the screed thickness must eventually be increased.
Conduit Sleeving
Sleeve all flow pipes with REHAU conduit sleeving where the pipe enters and returns from
screed/ concrete for the first metre to REHAU requirements. Sleeve across construction joints
in floor. When installing pipe in door frames or through walls install a section of corrugated
sleeving in this area to allow free movement of the pipe.
Connection to main supply and return lines
Provide total flow rates and head losses for each manifold to the contractor of the main supply
and return lines to enable them to design pump sizes, pipe dimensions and all other
components required to render the system fully operational. The connection of the UFH/C
system to the main supply and return pipes is the duty of the mechanical contractor.
7.2
7.3
Initial Warm-Up
Allow the concrete to dry for 3 weeks. Balance the system via the valves on the manifold to
achieve an even flow and heat up. Start the warm-up procedure according with BS EN 1264
and REHAU requirements. Provide signed and witnessed warm-up protocol.
7.4
Commissioning
Ensure the complete central heating system, including main supply circulation pump and
radiators if present, is working. Based on the real pipe length noted during laying of the
Version: Mar-2012
Page: 17
pipework, adjust each circuit slowly via the valves on the manifold to ensure an even flow and
heat up is achieved (hydraulic balancing). Provide commissioning certificate.
Run the system for at least two weeks before the floor covering is finally laid. For floor
coverings use adhesive suitable for temperatures up to 40C.
8
DOCUMENTATION
8.1
Design Data
Installer to provide pipe layout drawing to main contractor prior to installation.
8.2
8.3
MANUFACTURER WARRANTY
25 years Pipe warranty period from date of completion of system test, based on the Terms and
Conditions of the REHAU RAUTITAN Warranty Certificate in the manufacturers standard form.
Version: Mar-2012
Page: 18
GENERAL
This section relates to REHAU Concrete Core Tempering
(CCT) system.
SYSTEM DESCRIPTION
The REHAU RAUTITAN system for Concrete Core Tempering consists of:
RAUTITAN pink pipe, fittings and accessories
REHAU manifolds
Main supply and return pipes including valves and fittings, main circulation pump, heat source
and all other components required to render the system fully operational are not included in
this section.
REFERENCE DOCUMENTATION
The documents referred to in this section are:
NCC / BCA
Building Code of Australia
BS EN 1264
Floor heating - Systems and components
BS 7291
Thermoplastic pipes and associated fittings for hot and cold water for
domestic purposes and heating installations in buildings
3.1
Manufacturers documentation
Manufacturers and suppliers documents relating to work in this section are:
REHAU Piping, Connection and System Guidelines Technical information
REHAU Under Floor Heating/Cooling Technical Information
The above information is available from REHAU:
Web:
www.rehau.com.au
Phone: 1300 768 033 (Australia only) or +61 2 8741 4500
Pipe dimensions
16 x 2.2mm or 20 x 2.8mm
System
Reverse Spiral
Double Meander
Single Meander
Version: Mar-2012
Page: 19
Pipe spacing
Number of zones
Number of manifolds
Number of circuits
29 C
m3/h
Zone control
MATERIALS
6.1
6.2
6.3
Product
RAUTITAN pink
Colour
Pink
Material
Pressure rating
Design pressure
Continuous operation
70 C at 1,000 kPa
90 C
100 C
50 years
Available sizes in mm
16 x 2.2mm
32 x 4.4mm
50 x 6.9 mm*
20 x 2.8mm
40 x 5.5mm
63 x 8.6 mm*
25 x 3.5mm
* Non-standard item in Australia. Check for availability.
AS/NZS 2492:2007
BRANZ appraisal no. 434
Page: 20
REHAU manifold
Manifolds shall be installed at a location approved by the Architect. The number of manifold
outlets shall correspond to the number of circuits served by that manifold.
Option 1: Brass
REHAU manifold manufactured from standard (CW508L) brass as a distributor and collector
for the individual heating and cooling circuits. Pre-assembled and mounted on sound-insulated
galvanised steel brackets. Combined flow meter 0-4 l / min and quick stop in the supply
header, thermostat insert with flow rate control in return header. 2 to 12 outlets male thread
euro-cone. Maximum operational pressure 600kPa (6 bar) at 80C. N.B. 7-port, 9-port and 11port manifolds are non-standard items in Australia and New Zealand, please check with your
local REHAU Sales Office for availability.
Option 2: Polymer
Modular REHAU manifold manufactured from corrosion resistant and thermal resistant
reinforced fibreglass as a distributor and collector for the individual heating and cooling
circuits. Supply modules in red colour with integrated shut-off valve, attachment of actuator
possible. Return modules in blue colour with integrated, adjustable flow meter, lead-sealable
cap. 2 to 17 outlets male thread euro-cone. Operating temperatures from -20 to +90C.
Maximum test pressure 1,000kPa (10 bar), maximum operational pressure 600kPa (6 bar).
7
7.1
Page: 21
All coils in floors shall be installed strictly in compliance with the requirements of the structural
engineer and in accordance with the recommendations of REHAU for concrete floor heating
applications. Piping shall be installed completely free of twists, warps or buckles.
Conduit Sleeving
Sleeve all flow pipes with REHAU conduit sleeving where the pipe enters and returns from
concrete for the first metre to REHAU requirements. Sleeve across construction joints in floor.
When installing pipe in door frames or through walls install a section of corrugated sleeving in
this area to allow free movement of the pipe.
Connection to main supply and return lines
Provide total flow rates and head losses for each manifold to the contractor of the main supply
and return lines to enable them to design pump sizes, pipe dimensions and all other
components required to render the system fully operational. The connection of the CCT
system to the main supply and return pipes is the duty of the mechanical contractor.
7.2
7.3
Initial Warm-Up
Allow the concrete to dry for 3 weeks. Balance the system via the valves on the manifold to
achieve an even flow and heat up. Start the warm-up procedure according with BS EN 1264
and REHAU requirements. Provide signed and witnessed warm-up protocol.
7.4
Commissioning
Ensure the complete central heating system, including main supply circulation pump and
radiators if present, is working. Based on the real pipe length noted during laying of the
pipework, adjust each circuit slowly via the valves on the manifold to ensure an even flow and
heat up is achieved (hydraulic balancing). Provide commissioning certificate.
Run the system for at least two weeks before the floor covering is finally laid. For floor
coverings use adhesive suitable for temperatures up to 40C.
DOCUMENTATION
8.1
Design Data
Installer to provide pipe layout drawing to main contractor prior to installation.
8.2
8.3
Version: Mar-2012
Page: 22
MANUFACTURER WARRANTY
25 years Pipe warranty period from date of completion of system test, based on the Terms and
Conditions of the REHAU RAUTITAN Warranty Certificate in the manufacturers standard form.
Version: Mar-2012
Page: 23
GENERAL
Please ask your local REHAU sales office for specification texts for this system or call
Phone:
1300 768 033 (Australia only) or +61 2 8741 4500
Version: Mar-2012
Page: 24
GENERAL
Please ask your local REHAU sales office for specification texts for this system or call
Phone:
1300 768 033 (Australia only) or +61 2 8741 4500
Version: Mar-2012
Page: 25