Excavation Method
Excavation Method
Excavation Method
Title
Doc. No
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Page 1
Doc. Title
Doc. No
CM MS BW - 008
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
CONTENT
1.
Purpose
Page 3
2.
Scope of Work
Page 3
3.
Page 4
Reference Drawings
Page 4
Excavation Procedures
Page 5
Quantity Control
Page 8
Safety Control
Page 8
Appendix 1
Page 10
Page 2
Doc. Title
Doc. No
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
1. PURPOSE
This Method Statement is prepared to ensure that construction of buildings for the project shall
comply on plans specifications and all relevant standard and code requirements in the execution
of different work activities to be performed in the construction of buildings and other relevant
structures associated with the project in general. In addition, this will serve as a tool to guide all
technical personnel and layman execute proper construction procedures complied with the
quality and safety plans for the project.
2. SCOPE OF WORK
The scope of work for the construction of all Building and its utilities:
Expansion excavation:
No.
Building name
Storey
Structure
Security Office
RC Structure
Amenity Block
RC Structure
1+M
Container Gate
RC Structure
Operation Building
RC Structure
Maintenance Shop
1+M
Sub Station
Reefer Rack
10
Miscellaneous structures
Page 3
RC & Steel
Structure
RC & Steel
Structure
RC & Steel
Structure
RC Structure
RC & Steel
Structure
R C & Steel
Structure
Doc. Title
Doc. No
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Building name
Storey
Structure
Septic tank
RC Structure
Fuel Station
RC Structure
4. REFERENCE DRAWINGS
Refer to attachment of Excavation Shop Drawing and Excavation Sequence Drawing.
Page 4
Doc. Title
Doc. No
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
5. EXCAVATION PROCEDURE
5.1
Flowchart
Completion of pile
Foundation works
Sand backfilling
Finish works
Page 5
Doc. Title
Doc. No
CM MS BW - 008
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
5.2
Description
Quantity
Engineer
Surveyor
Foremen
Worker
30
Safety officer
Remarks
Table 1
- Equipments to be used for the work in accordance with table 2
No
Description
Quantity
Backhoe
02
Dump Truck
03
Level Machine
02
Water Pump
05
Remarks
Table 2
- Certificate of operator and equipment shall be submitted by separated document to the
Engineer for review and approval.
5.3
Detail Procedure
Page 6
Doc. Title
Doc. No
CM MS BW - 008
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
- During excavation, it is necessary to make drainage ditch slope to sump pit as precaution in
case raining and ground water occurs during construction.
- Ground water will be drained by water pump with hose line is allocated to sump pit then
discharge to the river. Contractor shall monitor ground water level and continuously run the
dewatering pumps to maintain dry working platform when ground water is encountered.
Additional pumps will be added if the pumping capacity is insufficient.
- Excavated soil to be loaded to dump truck and transported to the stockpile. Unsuitable material
and waste material shall be removed from site to the waste yard in accordance with the
specification requirements.
5.3.3 Excavation up to design level
Mat
pm3
Page 7
Doc. Title
Doc. No
CM MS BW - 008
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Sprinkle water to the earth fill in compliance with the allowable moisture contents specified
before start compaction.
5.4
Termite work
Material
- Termite material shall be submitted by the separated document to the Engineer for approval
before start work.
Application
- Application procedure shall be submitted by the separated document to Engineer for approval
before start the work.
6. QUALITY CONTROL
Compaction of Backfilling
- After excavation, the bottom surface of pit shall be compacted to not less than 95% of
maximum dry density by vibratory plate compactor and the slope shall be trimmed off to avoid
collapse of pit wall.
- The fill material shall be checked and accepted by the Engineer before carrying out the work.
Survey of excavated area
- After completion of excavation, dimensions shall be checked and recorded as attachment 1.
Tolerance of bottom elevation is 10mm
7. SAFETY CONTROL
Fundamental Policy
Key Activities
Page 8
Doc. Title
Doc. No
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
- Pick up hazardous factors of each work activity and always reflect them at the safety meetings.
Point out them every day at the meetings in order to let individual worker to renovate his safety
consciousness.
- Prevention of Heavy Machinery Accidents
- Be consistent with inspection at beginning of works (including working ground), regular
maintenance of machineries, designation of working area and provision of a proper signalman.
Others.
- Safety signboards and barricades shall be installed around excavated area. Security guard
should observe all passengers around the site.
Page 9
Doc. Title
Doc. No
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix 1
Excavation Shop Drawing
Sequence Drawing
Page 10
Doc. Title
Doc. No
Rev. No.
Date
Nov, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Page 11