Building Work Method Statement
Building Work Method Statement
Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Page 1
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
TABLE OF CONTENS
1.
Purpose
Page 3
2.
Work Scope
Page 3
3.
Page 3
4.
Reference Drawings
Page 5
5.
Construction Work
Page 6
5.1
Page 6
5.2
Construction Procedure
Page 7
5.2.1 Preparation
Page 7
Page 7
Page 9
Page 16
5.2.5 Formwork
Page 17
Page 19
Page 22
5.2.8
Page 23
5.2.9
Finishing Work
Page 25
Page 26
Page 28
6.
Construction Schedule
Page 28
7.
Organizational Chart
Page 29
8.
Page 30
9.
Safety Control
Page 30
10.
Environmental Control
11.
12.
Page 31
Appendix
Page 2
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
1. PURPOSE
This Method Statement is prepared to ensure that construction of buildings for the project shall
comply on plans specifications and all
Building name
Storey
Structure
R C Structure
Security Office
R C Structure
Operation Building
R C Structure
Amenity Block
R C Structure
1+M
Maintenance Shop
1+M
Container Gate
Substation
R C Structure
Fuel Station
10
Pump Station
R C Structure
11
Miscellaneous structures
Page 3
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
4. REFERENCE DRAWINGS.
Preparation
Earth Work
Piling Work
Finishing Work
Completion
Page 4
M & E Work
( HVAC ) (Plumbing)
(Electrical)
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
5.2
CONSTRUCTION PROCEDUCE
PREPARATION
Temporary yard such as stockpile and fabrication yard for building work shall be prepared
within the site after soil improvement. Location and plan shall be considered to avoid traffic
and congestions during mobilization of materials, machines and obstruction to construction
during the course of different activities in the site.
It is necessary to set up a fabrication yard in order to carry out the fabrication of
Reinforcing bars, form work, steel frames and so on. And also, those fabricated ,cast,
assembled products will be temporarily stocked at the Stock yard. The yards will be graded
flat at the designated area and with adequate drainage.
Joint survey with the Engineers representative shall be carried out to establish control
points and confirm the coordinates and elevation prior to the commencement of the
construction works.
After confirming the coordinates and elevations of all the building location, survey location
for piling and excavation shall be carried out each stage of the works.
5.2.2
EARTH WORK
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
After excavation, the bottom surface of pit shall be compacted to not less than 95% of
maximum dry density by vibratory plate compactor and the slope shall be trimmed off to
avoid collapse of pit wall.
5.2.2.2 Backfilling work
Approved suitable material should be used for backfilling. Compaction standard shall be
employed in the execution of this work. Fill materials shall be distributed evenly to the
backfill area to a specified thickness of compaction = 150 mm thick and compacted by
portable compactor to a specified compaction factor. Sprinkle water to the earth fill in
compliance with the allowable moisture contents specified before start compaction. Every
layer shall be tested for compaction to assure that this particular work is checked and
complied with the governing specification.
5.2.3
PILING WORK
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Pile Material
- Pile Material :
PHC Spun Pile 600mm dia.
PHC Spun Pile 500mm dia.
RC Square Pile 400mm x 400mm
Piles will be plant fabricated and transported to the site by Barge and trailer truck. They will
be supported by bedding timbers placed directly under the positions of lifting hoops.
Piles will be stored carefully on flat ground within the temporary yard. Piles will be stacked
on top of one another to a maximum of three layer.
Material delivery dockets, receipts and inspection shall be conducted to every pile delivery
at site. Result of the inspection and delivery documents shall be submitted to the Engineer.
TIMBER
RC PILE
Storage of RC Pile
Page 7
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
TRUCK CRANE
RC PILE
TRAILER
Transportation of RC pile
- Piling Equipment :
The following equipment shall be used for the Piling work.
Hammer : Diesel Hammer 4.5 7 tons class, (KOBELKO K45/KB60)
Base Machine : HITACHI PD9 or equivalent
Service Crane : 35 ton class, crane truck
Others : Semi-automatic welding machine / Oxy Acetylene cutting outfit
2. Piling by diesel hammer : ( Refer attached drawing below )
The pile will be driven by diesel hammer and driving shall stop when the bearing capacity is
already reached and confirmed. All piles shall be driven to their specified bearing capacity
and location complying with technical specification and design drawings.
Page 8
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
DIESEL HAMMER
PILE DRIVER
DI
REC
T IO
TRANSIT/PLUMB BOB
SURVEYER
TRANSIT/PLUMB BOB
SURVEYER
Pile Driving
Page 9
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
DIESEL HAMMER
HELMET
UPPER PILE
LOWER PILE
PILE DRIVER
3) SPLICING
4) RESUMING OF DRIVING
FOR AREAS REQUIRING MORE THAN 1 PILE LENGTH TO OBTAIN DESIGN BEARING CAPACITY
Driving will be stopped when bearing capacity is already achieved, through the application
of Hiley s formula in calculating the bearing capacity. See PDA Test calculation .
If it is found that the bearing capacity is insufficient against design after the rebound
record, the pile will be extended and re-driven until the bearing capacity is attained.
Ru
9.81 (Ef.MR.H)
x MR + e2.MP
S+0.5(C1+C2+C3)
MR + MP
In which:
Ru : Ultimate Resistance, KN
MR : Weight of ram, Kg
H : Drop height of hammer, mm
Ef
: Coefficient of restitution
Page 10
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
REINFORCEMENT WORK
Manufacturer of reinforcing bar shall be proposed to the Engineer for accreditation and
approval. No deliveries shall be accepted for use without decision by the engineer.
Page 12
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Every delivery of reinforcing bar supply for construction, the quantity and physical
properties shall be checked by the Contractor. The quality shall be confirmed by checking
mill certificate issued by the manufacturer through the comparison of the laboratory test
result of specimen taken from the different kinds of diameter in the delivered product.
5.2.4.1 Material
Round bar & deformed bar shall be 2100 Kg/cm- ( Yield strength ) .
5.2.4.2 Reinforcement storage before fabrication
Reinforcement will be stored in a warehouse area at site with adequate protection from
getting rusty, or protected from any element that would affect its quality condition as
specified.
Storing will be organized by category, type, grade and diameter. As a rule, the end of
each bar had been painted to differentiate the different grades.
Reinforcing steel that are rejected have to be stored in a separate place away from where
it was accepted, before sending back to the supplier.
5.2.4.3 Reinforcement fabrication process
1. Reinforcement fabrication and storage.
Workers will fabricate the bar according to the information mentioned on the label, and
fabricated bars will be stored systematically according to their structural usage per work
unit mentioned on their label (Work Unit, structure, drawing, category, type, diameter,
grade).
All precautions will be taken to avoid damage and bending the steel bars during storage,
loading and transportation to the site. The bars should be protected from the rust by
storage on wooden platform, crates or elevated trestles.
2. Installation at site.
The reinforcement installation will be in accordance with the drawings, the General
Technical Specifications, and the Owner requirements (cover, spacer blocks,
reinforcement continuity and tolerances).
Before any pouring, all the reinforcement shall be inspected and accepted by the
Engineer or the owners representative.
Page 13
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
The foreman on site will correct any deviation out of tolerances immediately upon notice
before filling the inspection request.
5.2.5 FORMWORK
5.2.5.1 Formwork Set-Up :
Blinding concrete shall be installed prior to placing formwork.
Form made of plywood or steel shall be cleaned on all its surfaces in contact with concrete
shall be treated or painted with oil prior to the installation. Installation shall be made
precisely on the lines and grades using string, spirit level, survey instrument etc.
Forms shall be kept firmly in position by putting tie rods or external support. Tie rods
support shall be so arranged and distributed and strong enough to withstand the pressure
during casting concrete.
5.2.5.2 Construction method
Foundations shall be constructed first and then columns to the tripod beam bottom
level. In the Workshop building, sub-columns and sub-beams system on wall, beam
surface form will be done after the installation of steel framework.
Establish accurate centerline axis and level for the layout of foundations, columns,
beams, and floors, before installing forms.
Check the alignment of formwork by stretching a cord along edges of installed forms
For additional supports, Iron and tension cable can be used as supports in the
installation of forms of column footings. Check the establish centerline for accuracy
to avoid deviations.
Staging and scaffolding support system is to be utilized for beams and slab forms, and
they are installed at the same time. During installation regular checking of lines and
grades shall be made to ensure the evenness and straightness of slabs and beams
during construction .
Page 14
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
position Steel and wood joist supports and bracings is utilized for forms of concrete
structures. Jacks are installed at top and base of supports for adjusting height or length, all bases of
support should be propped by a piece of wooden material to prevent settlement.
All supporting columns and bracings should be anchored, hold and connect together to
CONCRETE WORK
5.2.6.1 Material
- The class of concrete for each section of the works shall comply with Specification, JIS and
ASTM Standards.
PROPERTY
1. Concrete Class
2. Application
3. Cement Type-1
4. Water Cement Ratio
5. Minimum Cement
Content (kg/m3)
6. Max Aggregate Size
7. Concrete Cylinder
Strength at 28 days
Fc (Mpa)
CONCRETE TYPE
E
Over 2 Story
Buildings
1 Story Buildings
Lean
Concrete
PCB40
0.475
PCB40
0.5
PCB40
.76
350
330
220
19
19
38
30Mpa
25Mpa
14Mpa
Design mix shall be submitted and approved by the engineer and trial mix shall be conducted to
confirm the compression strength and satisfy the specification.
In general, concrete must be casted within 60 minutes from mixing to placing. The concrete
temperature shall be below 35C as specified at the point of pouring. Other measures to keep the
concrete temperature low is to keep the aggregates and water cool, or arrange early morning
pouring to avoid casting daytime which has high humidity condition.
5.2.6.2
Construction method :
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Page 16
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
P U M P
C A R
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Work preparation:
After removing formwork of slab, floor cleaning shall be done for marking.
Survey group shall re-establish center line, ink marks shall be applied to a re-located
margin lines of brick walls on columns and slabs.
Brick work shall be constructed from bottom to top process, main walls shall be laid
first followed by partition walls.
5.2.7.3 Checking:
Check regularly the verticality and straightness during brick laying by ruler and
plumb.
Stretched cord to both ends to ensure brick laying course are in straight line.
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
inspected and checked by the recipient. Delivery dockets, mill certificates , quantity and
physical property checking of the material shall be performed before unloading. Inferior
and sub standard materials are rejected and prevented from unloading. The material
technical datas from the mill certificate shall be confirmed by conducting laboratory test
on sample taken from the delivered materials. Usage of the material depends on the test
result for the specified stress requirements.
2. Shop Fabrication
Prior to fabrication, shop drawings shall be submitted to the engineer for approval.
Bended steel members shall conform to the approved shop drawing. In order to maintain
quality and minimise the installation and assembly period, painting must be done in the
fabrication yard.
3. Erection work
Detailed erection sequence for each structure approved by the Engineer shall be
acquired prior to erection. Mobile cranes will be used for the erection. Temporary
bracings shall be prepared before column erection in order to maintain the verticality and
alignment. After checking proper alignment, fasten these steel members by connectors of
high strength bolt and tighten it according to its specified torque moment requirement by
using torque wrench or special tightening hand tool. Touch up paint will be applied to all
scratched surfaces to restore its required texture surfaces.
Page 19
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Page 20
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Ensure all vehicles and equipment is safe and fully efficient, guarded and equipped with
safety devices and has been subjected to necessary test.
Make sure that operators, drivers and attendants will only concern themselves on the
equipment for which they have been thoroughly trained. Check working efficiency of
equipment for its intended purpose, and its valid registration and calibration certificates.
Safety lifelines shall be provided to all elevated work areas to enhance connection point
safety harness or belts used by workers, especially to a location where scaffolding
impossible. All workers working higher than 1.5 meters must wear a safety harness or belt.
The safety line manufacturer's recommendations for use shall be strictly followed.
5.2.9 FINISHING WORK
5.2.9.1 Door & Window works
Doors, louvers and windows shall be of the approved ones and in compliance with the
specification. Installations shall be made in accordance with the schedule to keep finishing
work in sequence and to avoid lapping of activities that cause delay or damage impact to
other finishing work. Installed doors, louvers and windows shall be keep protected to avoid
damages caused by other ongoing finishing works and other parties.
5.2.9.1 Plastering
The thickness and mix proportion of mortar for plastering or rendering shall be in accordance
with the specification and the mixing and kneading process is to be done manually or by
portable mixer. Cement shall be of the standard ordinary Portland cement and sand, sourced
out from land or river and shall be approved by the Engineer.
5.2.9.2 Tiling
Tile material and shop drawing for tile layout or arrangement shall be submitted to engineer
for approval. Prior to tile laying concrete surface where tile is laid shall be cleaned, free from
dust, oil, grease and other elements that would affect quality of tile bed mortar. Bed mortar of
specified mix proportion (1:3) is placed and spread evenly with a minimum thickness of
10mm over the area to be tiled. Tiles are then laid over the evenly applied bed mortar until it
adhere firmly inplace.Tile gaps shall be filled up with grout of approved type or as specified
in the plan. After grouting tiled area shall be cleaned from excess grout to keep the work
clean as specified.
5.2.9.3 Painting
Page 21
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Paint material shall be of the approved one in accordance with specification. Surface
preparation before painting shall conform to the manufacturers instruction to each kind of
paint material. Number of coat, dry film thickness shall comply with the approved paint
schedule. Where required, final coat shall be carried out, after or almost all of the work
nearby is completed to minimize damage.
5.2.9.4 Ceiling Work
The material for ceiling shall be submitted to the engineer for approval. Shop drawing for
ceiling
layout and arrangement plan shall be approved by the Engineer. And proper
coordination to M/E works shall be made to avoid lapping of works that cause delay in
executing the work.
Hangers shall be installed, fastened and fixed properly under the concrete slab or steel
structural members. Then thin gauge and light steel frame is installed to enhance level
adjustments required. M&E works above ceiling shall be completed before installing the
ceiling frame.
Deflections or damage on the T-runner frame shall be repaired prior to installation of the
gypsum board.
5.2.10 MECHANICAL & ELECTRICAL WORK
5.2.10.1 Air Conditioning and Ventilation Work
Manufacturer and Equipment of Air Conditioning and Ventilation system including shop
drawing plans and all schematic layouts for these works shall be submitted to the Engineer
for approval. All slots in exterior walls intended for pipe crossing shall be made impervious.
Shop drawings of ceilings and walls shall reflect location of air conditioner, ventilator and
ducts, to account for the balance distribution of other equipment. Installation of air
conditioner, ventilator, air inlet and outlet, including pipes, ducts and other related fittings
shall conform as indicated in the shop drawings. Exhaust pipe/duct shall sloped downward
from inside to outside.
5.2.10.2 Plumbing Work
Material and equipment for Plumbing work and shop drawings shall be submitted to the
engineer for approval.
Excavation and trenching of soil, preparation of sleeves on floor, wall and beam where there
are necessary in structures shall be well considered.
Before being installed, all pipes shall be thoroughly cleaned, free from any scales, burrs,
rusts and obstructions.
Page 22
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Prefabrication, installation and jointing of pipes (including fittings) with adhesive for PVC
material, including valves, strainers, and flexible joints shall be done carefully.
Adequate pipe supports, hanging steel bars and anchorage shall be provided.
Sealing of pipe sleeves shall be done properly.
Pressure test for water supply pipes and flushing test for drainage pipes shall be performed.
Back-fill and compaction of soil for underground piping shall be done carefully.
5.2.10.3 Electrical Work
Material and equipment for Electrical work and shop drawings shall be submitted to the
Engineer for approval.
Preparation for efficient wire or cable laying such as confirmation of the exact locations
where they are to be laid, cleaning the trenches or ducts, scraping/brushing inside of the
duct bank, pipes or conduits and so on shall be done.
All cable connections shall be made inside distribution board; pull box and outlet box etc.
and the connection shall never be exposed or inside of conduits.
Cable alignment, binding, fixing, wall penetration sealing, cable marking, cable penetration
into conduits between cable trays, ducts and Job-site junction boxes and similar shall be
made properly.
Adequate press-save coupling, wire connector or press combine terminal etc. will be used as
a principle for the connection of wires and/or cables.
In the case of line pipe exceeding 30m for one section or where leading in is difficult, pull
box shall be used.
Fixing method of distribution boards etc. shall be specified on the construction drawing, and
shall be fixed accordingly.
The position of lighting apparatus shall be indicated on ceiling allotted sketch in advance,
taking balance with other facilities apparatus.
Fixing height of switch and socket outlet shall be shown on the shop drawing securing the
approval of the consultant and shall be fixed accordingly.
5.2.11 TESTING AND TRIAL RUN
After installation of Mechanical and Electrical equipment, test and inspection including
their record reports will be done. Trial operation shall be proceeded to adjust and check the
function of equipment.
Page 23
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
6. CONSTRUCTION SCHEDULE :
See Attach- Appendix-3
7. ORGANIZATIONAL CHART
Page 24
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
TTJV
Project Manager
Mr. Fukushima
Construction
Manager
Mr. Asai
Safety/Environment
Manager
Mr. Quan
Survey
Engineer
Site
Building Chief
(Mr. Tien Mr.Jun)
Site
Engineer
Page 25
Sub- Contractor
Site
Engineer
QA/QC
Chief
Mr. Rolly
Site
Engineer
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Page 26
Doc. Title
Doc. No
CM MS BW - 001
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Environmental Management Plan will incorporate work method statements, inspections, test
plans , and check sheets are developed to cover the particular requirements of this project.
This Plan is established based on the Environmental Management Manual of TTJV.
11.Appendix :
1. Applicable Codes and Standards
2. Drawing List for Building
3. - Building Construction Schedule
4. Inspection and Test Plan
Page 27
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix - 1
Applicable Codes and Standards
Page 28
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix - 2
Drawing List for Building
Page 29
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix - 3
Building Construction Schedule
Page 30
Doc. Title
Doc. No
Rev. No.
Date
July, 2010
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix - 4
Inspection and Test Plan
Page 31