Method Statement
Method Statement
TABLE OF CONTENTS
DESCRIPTION PAGE
1. INTRODUCTION 2
2. ASSUMPTIONS 3
3. REFERENCE 4
4. SCOPE 5
5. MATERIALS 6
6. ELEVATED STRUCTURE 7
7. CONSTRUCTION METHODOLOGY 8
8. CURING 18
9. CONCLUSION 19
1. INTRODUCTION
This method statement describes in brief the broad sequence and method of
construction of six lane elevated structure of length 3.6 km covering central
built up Panipat Section including Gohana road crossing, Sanauli road
crossing, bus stand and skylark tourist complex on BOT basis.
2. ASSUMPTIONS
Following assumptions have been made to arriving at this methodology:
3. REFERENCES
Following document has been referred for the preparation of this method
statement:
4. SCOPE
5. MATERIALS
5.1. Concrete: Concrete for the entire works will be supplied from captive
batching plants strategically located. Alternatively concrete will be
sourced from approved RMC plants. Materials used in the concrete will
be tested to check their conformity to project specification / standards.
Concrete will be transported from plant to the work place in transit
mixtures. Admixtures will be used with the prior approval of the engineer.
Temperature of the concrete will be maintained as per the specifications
/ standards.
6. ELEVATED STRUCTURE
General and Structural Arrangement:
The deck of the structure is designed to cater for three lanes of traffic in each
direction with two separate decks. The carriageways are separated by
median of 1.2m in the elevated structure. The elevated structure comprises
multispan deck slab on precast pretensioned girders (span varies 27m to
31m) supported on single rectangular / square type piers and abutment twin
columns resting on pile foundations.
7. CONSTRUCTION METHODOLOGY
The survey works for approaches will start with setting out of grids and
marking the existing ground features for the entire stretch of elevated
structure. Pier locations and bench marks for the regular survey will be fixed,
and the benchmarks will be cross-checked by closing the traverse and
ascertain the accuracy of bench marks. The survey pillars will be established
at convinent locations.
The method of advancement and diameter of the bore will be such that the
boring will be completed and logged to the scheduled depth, and samples of
the specified materials will be obtained, in situ testing will be carried out as
required. In locations where water table is penetrated and disturbance of soil
is likely, positive hydraulic head will be maintained in the bore.
While the bore progresses, the sampling frequency and the type of samples
will be obtained as per the requirements. While drilling in the bore hole is in
progress the change in soil strata, colour of water, rate of penetration of the
drilling rod, starting and completion of each run, any water loss, side
collapsing etc. will be recorded and details furnished. All samples will contain
the full details of the location of bore, depth at which recovered etc. The
samples of soil collected from the bore hole will be packed in sealed packets
and sent to soil laboratory for tests.
The site infrastructure will consist of project site offices and infrastructure
facilities for Precast I Girder casting, reinforcement yard and stacking. This
will contain temporary offices for the project managerial personnel, stores
and cement godown, work shop and generator shed etc. For layout of
casting yard and site facilities refer our drawing no O5086-Q-BR-CM-GA-
0008.
Casting Yard: The various components involved in the casting yard are listed
below:
Moulds for casting I-girders: - The I-girder mould will be fabricated out of
structural steel plates with sufficient stiffeners to resist the concrete pressure.
It is planned to deploy four bottom and two side shutters. The gantry
available in the yard can handle the side shutter from one mould to another.
The PSC Girders will be cast in respective beds and once the casting is
completed, the strands will be distressed and the girders will be shifted to
stacking yard. The stacking of girders will be done in two tyres as shown in
our drawing O5086-Q-BR-CM-GA-0044.
The I-Girders from the stacking yard will be shifted to erection location by
long bedded trailers.
All piling works for the foundation will comply with the requirement as per the
specifications for piling.
The pile points will be marked at specified locations, the hydraulic rotary
drilling rig (or) RTC rig is aligned to the exact location and the verticality of
the Kelly is checked. The temporary casing if required is driven along with
the advancement of pile boring. No permanent casing is envisaged. The
verticality of the temporary casing is then checked by spirit level while
lowering of bore and is recorded. The process of lowering the casing and
boring by auger is continued till the temporary liner reaches required level.
The verticality and the lateral shift of the pile are checked at regular intervals.
When the bore is intercepted with soft rock in the process of boring, the tool
bit will be changed from soil auger to rock auger/barrel for further boring
through soft rock. Once pile reaches the level as specified in drawing, the
boring is stopped and the bore is cleaned by bucket and sounding is
checked.
The pre-fabricated reinforcement cages in standard lengths will be cut for the
required length taking into account the bore depth, cut-off level, lap length
etc. Reinforcement cages are then welded together into the bore. Cover
blocks of suitable size will be tied to the reinforcement and lowered. Before
lowering the reinforcement cage the lap length and welds will be checked
and recorded.
overflow to at least 1m above the cut off level. The tremmie pipes and
temporary casing will be removed in stages as the concrete builds up in the
pile. The tremmie will be inside concrete by minimum 1.5m at all the times till
end of concrete.
The pile load test will be carried out at location specified by client.
Once all the piles at a pier location are completed, the reconnaissance
survey with the Engineer will be done and the pile cap layout will be
marked on the ground to commence the excavation work for pile caps.
Open excavation of slope 1:1 with a bottom working space of 0.6 m
maximum is considered. The excavation will be done using excavator up
to 100 mm above the binding concrete level. The dressing will be done
manually and the loose patches will be removed and compacted using a
hand hammer. The sides of the excavated pits will be protected using
shoring wherever required so as to prevent collapse and also to allow for
the movement of traffic in the adjoining area.
The pile heads will be chipped to the required level i.e. to the soffit level
of the pile cap and the blinding concrete will be placed. Reinforcement
from the pile will be bent to the required shape and the pile cap
reinforcement will be placed and tied along with starter bars for the pier.
The side forms / block work with solid blocks for the pile cap will be fixed
and checked for the edge co-ordinates and levels. After approval of the
engineer, concrete will be placed in position. In the mean time the starter
concrete for the pier will be cast on the top of the pile cap, which will be
used for casting the piers. The pile cap will be cured for 14 days. Back
filling of the pile cap will be done in layers and compacted using
excavated materials/ fill material as required in specification.
7.6. Pier
Fixing of Formwork : The shutters for the pier will be fixed & aligned
depending on the height of pier. Inside surfaces of the forms will be coated
with approved release agent. The form work consists of shutters made of
steel plates and supported by
horizontal and vertical steel
walers. The vertical walers are
supported by inclined props for
alignment control and in turn
fixed to the anchor bolts
embedded in the pile cap.
Necessary working platform
and access ladders will also be provided. Refer our drawing ‘’ Pier Formwork
– General Arrangement‘’ (Drg. No. O5086-Q-BR-CM-GA-0054).
After completing the erection of girders in one span the formwork and
reinforcement for diaphragm will be placed and concreted. Precast planks
between the girders for deck slab will be placed. Reinforcement for deck will
be tied and concrete for slab will be placed by placer boom. For cantilever
deck, steel brackets will be fixed from the end-precast girders for supporting
the formwork and the concrete.
8. CURING
9. CONCLUSION