Penstock Taquesi
Penstock Taquesi
Penstock Taquesi
General Index:
a) Fabrication & Installation Procedure
1.0
2.0
3.0
4.0
Pag.
20
Pag.
36
d) Painting Procedure
1.0
2.0
3.0
4.0
Pag.
b) Welding Procedure
1.0
2.0
3.0
4.0
5.0
6.0
Pag.
Pag. 1
Pag. 2
No.14
No.2
No. 1
No. 3
No. 8
No. 1
No. 1
No. 1
No. 2
No. 2
No. 2
No. 1
No. 2
and inside joints in a fixed position, with pipe over Motorized Tube Rollers. (Normally the
circumferential inside joints would be welded with a manipulator)
ESAB DC 400 Amps Welding Machine for manual welding.
ESAB DC 600 Amps Welding Machine for manual welding and for Arc Air Torch.
ESAB DC 400 Amps Gas Semi-Automatic Welding Machine
High Frequency Generator with four (4) Inlet each for Grinding Machines
High Frequency Angular Grinding Machine
Directional x-ray Apparatus - 200 kW for Quality Control
Ultrasonic Apparatus for Quality Control
Alternative Motorized Saw
Heating and Treatment Ovens for Submerged Arc Welding Flux Electrical Type
Vertical Heating and Treatment Ovens for Welding electrodes Electrical Type - Around 1200
Electrodes capacity
Electrical Motorized Air Compressors for Arc Air Torches
Diesel Motor Welding Machine - 600 Amps
Pick-up or Shop service.
The shop is complete with all the electrical and distribution panels, lighting system, air distribution
system and all necessary hand tools such as hydraulic and mechanical jacks, tir-4, lift pulleys, lifting
cables, individual tools and all the protective clothing required. Also incorporated in the shop will be
tools spare parts and consumable materials store. Store for welding materials, first aid infirmary,
workshop office, x-ray laboratory and permanent material store.
For the Taquesi project the shop will also be provided with the following:
No. 1
No. 2
No. 1
No. 2
Marking plates;
Roll bending with machine for plates 830 mm thick. Use jig to control radius;
Assembling of pipes;
Pag. 4
3.1
Construction characteristics
Materials:
The steel utilized for manufacturing the Penstock is ASTM A537 CL. 1 - produced in Italy and all
other welding materials according to WPS (Welding Procedure Specifications).
Material characteristics
a)
b)
c)
d)
e)
f)
1.
2.
e)
f)
g)
h)
i)
j)
The metal plates for the manufacturing the Penstock shall be ASTM A537 CL. 1 produced in Italy shall be produced in compliance with applicable specifications;
All welding materials shall be in compliance with WPS and applicable specifications;
The steel used in the construction of the other parts such as Bends, Manifolds, Flanges and
Expansion Joints shall also be ASTM A537 CL. 1;
Anchor rings for pipes AP11AP17 will be manufactured and welded to the pipes in the
shop;
Manholes will be placed according to shop drawings and will be manufactured in the shop;
Expansion joints will be manufactured in the shop. Assembling of expansion joints will be
made accordance with specifications, pipes will be cut according to a thermal expansion
charts, depending on the temperature and length in which the expansion joint is installed;
Saddle supports steel plate, 8 mm thick, shall have a half moon of 120 form, and shall be
welded to anchor hooks for second stage concrete;
Pipes shall be completely painted in the shop, except for 20 cm. at both ends that shall be
painted on the job site, after erection and inspections.
The flange and coupling tie rod, bolt and nut dimension after machining shall not be
inferior to nominal values.
The average internal diameter of every pipe or element, established by the measure of the
external development at the two ends and of the thickness, shall not be different from the
theoretic diameter more than 0.3% plus or minus with a maximum of 5 mm.
The ovalization of every pipe or segment, determined by the maximum length difference of
almost two diameters perpendicular between them, can not be greater than 0.01D, D been
the theoretic internal diameter.
Anchor rings shall be fabricated and welded to the pipes in the workshop according to
approved shop drawings.
Mechanical expansion joints shall be manufactured in the workshop according to approved
shop drawings.
The theoretic mass of every pipe or element appear on the single mass list an the shop
drawings on the basis of the final project for the piping, a variation less than 5% is
Pag. 5
accepted. The theoretic mass shall be calculated on the basis of the nominal dimensions
and mass volume of 7.85 kg/dm3.
3.2 Welding
Materials used in the construction of welded parts shall comply with the requirements for materials
given an shall be proven of weldable quality.
a)
b)
c)
d)
e)
f)
Records of the names of the welders who make each weld shall be maintained. Welders and
welding operators shall be qualified and qualification records shall be available for audit.
Two sample test will made, for tensile test and for bend test as per attached sheet. These
tests will be certified by a qualified firm.
Welding of the pipes in the workshop will be by automatic welding machines. Welds will
be butt welds from inside and outside. In tunnel sections welding will be from inside only
against external counter bars.
The edge to be butt welded shall be completely free from exfoliation, cracks or incision,
rust, calamine, humidity and shall be, therefore, submitted to the checks and adequately
protected.
When the temperature of the elements to be welded is lower than +5C, and anyhow when
the room temperature is lower than 5C or there is excessive ventilation (with influence
on the protection of the arc), the welding operations shall be made with appropriate
methods so that the cooling, after the welding, is sufficiently slow to guarantee from
cracking risk.
The removal of alignment jacks, tack welds and/or other possible appendixes shall be done
by grinding and subsequent visual examination of the grinded areas .
Pag. 6
The pipe sections located in anchor points AP17 to AP11 will be positioned first, leveled according to plan.
The pipe will be welded to the anchor stay rods prepared during 1 phase concrete. After 2 phase concrete
of the block, the erection of pipe sections will follow from one AP point to the other AP point and so forth
up to Yanacachi tunnel Portal.
The procedure for Penstock installation on job site is as follows:
-
The pipes will be transported from the pipe factory to the erection site on a truck with special
supporting saddles;
Set up equipment, tools, temporary support shall be ready on the erection site including ventilation
for the steel lined sections;
Pipes will be unloaded with a cable way (Blondins) Lifting Capacity 5 Tons;
When working on slope and elevation areas, internal and external scaffold will be prepared and
erected.
The pipes will be lifted brought to position with the Blondins, a 60 cm alignment slide will be
welded and the joint spaced with a 2-3 mm spacer;
If necessary an aux. support will be welded on the front part to maintain the pipe in position;
The pipe will be aligned and edges tack welded;
The inside welding shall be carried out first;
The exterior will be cleaned with arc-air and welded from the exterior;
Ultrasonic and radiographic tests will be made and eventual repairs will be carried-out;
The welded part will be painted and the painting will be checked;
Anchor rings for pipes AP11AP17 will be manufactured and welded to the pipes in the shop.
Manholes will be placed according to approved shop drawings and will be manufactured in the shop.
Expansion joints will be manufactured in the shop. Assembling of expansion joints will be made in
accordance with specifications. Slip pipes will be cut according to a thermal expansion charts,
depending on the temperature and length in which the expansion joint is installed;
Saddle supports steel plate, 8 mm thick, shall have a half moon of 120 form, and shall be welded to
anchor stay hooks.
Welding will proceed in accordance with WPS here after specified. For security reasons during night
shifts, the interior of pipe will be welded and during day shifts the exterior will be welded;
Painting and controls will follow;
For erection of steel lined tunnel sections, a trolley mounted on rails will be used to transport the
pipes, auxiliary foot supports welded to the pipe ends will be left to concrete. Welding will be from
inside only against external counter bars ;
Visual inspection will be carried-out in the interior of the piping;
Covers of the manholes will be placed, o-rings checked;
Expansion joints will be tightened to torque;
Finally the piping will be filled with water and leak tested ;
Infiltration and leak inspections and controls will be carried-out;
A hydropressure test will be carried out to underground piping prior to covering. Hollow blind
flanges with adequate safety valves and manometers will be welded at the 2 ends of the piping. The
piping will be filled with water; pressure will be gradually brought to 1-1/2 times the design
pressure of the piping and maintained for 30 minutes; after a visual control of the piping the
pressure will be lowered to the design pressure and maintained at this pressure for the time required
to permit inspection of the piping. If during test defects appear, the defectous element will be
repaired in accordance to specifications and the hydrostatic test will be repeated. The blind flanges
will be removed, and the erection will proceed.
Pag. 7
Pag. 8
WELDING PROCEDURE
Index:
1.0 Cutting, Fitting and alignment...............................................................................................Pag. 10
2.0 Cleaning of surface to be welded...........................................................................................Pag. 10
2.1 Preparation of base metal.............................................................................................Pag. 10
3.0 Preheating treatment..............................................................................................................Pag. 11
3.1 Weather condition for welding.....................................................................................Pag. 11
3.2 Preheat and interpass temperature................................................................................Pag. 11
4.0 Welding process specifications..............................................................................................Pag. 11
4.1 General welding procedure specifications for shielded metal arc process....................Pag.
4.2 Control of parameters..................................................................................................Pag.
4.3 Technique.....................................................................................................................Pag.
4.4 General welding procedure specifications for submerged arc welding process............Pag.
4.5 Filler metal...................................................................................................................Pag.
4.6 Control of parameters..................................................................................................Pag.
4.7 Technique.....................................................................................................................Pag.
11
13
13
14
15
15
16
17
17
17
17
Pag. 9
Pag. 10
Reference
ASME Boiler and Pressure Vessel Code, Section IX. Welding Qualifications, Edition and Addenda as shown
on the specific WPS.
Procedure qualifications
WPS for the project have been supplied by the welding materials supplier ESAB.
Preparation on base metal
The edges or surfaces of the pieces to be joined by welding shall be prepared by flame cutting, plasma arc
cutting, arc gouging, machining, shearing, grinding, or chipping and shall be cleaned of detrimental oil,
grease, scale and rust. The edges of the pieces may have a protective coating applied to them which need not
be removed before they are welded unless specifically prohibited by the specific WPS.
4.1.1 Weather conditions for welding
Welding shall not be performed when the surfaces in the welding area (within 6" (15.2cm) of the arc)
are wet; nor in periods of high winds unless the welder and the pieces to be welded are properly
protected.
4.1.2 Joints (QW-402)
4.1.2.1
Root Opening
Normal root opening shall be 0-1 1/4" (0 m-m - 6.4 mm). See contract drawings for the
specific joint detail. Spacer bar joints are considered 0" gap.
4.1.2.2
Wide Gaps
The following technique shall be used for welding joints with wide gaps which exceed
twice that specified on the applicable contract drawing. When zero gap is specified on the
contract drawings, gaps exceeding 3/16 (4.8 mm) shall be reduced as outlined below to a
3/16" (4.8 mm) or smaller gap. Maximum weld build-up shall be T (where T is the
thickness of the plate) for each plate edge or 1/2" (12.7 mm) whichever is smaller.
Method:
Plate edge build-up shall be done with a welding, procedure approved for contract use.
Weld passes shall be deposited utilizing a stringer bead technique to restore the plate edges
to the gap and approximate joint configuration as shown on the contract drawing.
On single or square butt joints a temporary back-up bar of compatible material may be
used. The edges should be built-up using stringer beads to restore the joint to the gap and
approximate joint configuration as shown on contract drawings, before tying the edges
together.
The temporary back-up bar shall be removed by gouging, chipping or grinding to clean,
sound-metal the second side.
4.1.2.3
Narrow Gaps
The following technique shall be used for correcting joints with gaps less than specified on
the applicable contract drawing which are not sufficiently wide to allow free manipulation
of the electrode in the joint.
Pag. 12
Method:
The plate edges of the joint shall be prepared by flame cutting, plasma arc cutting, grinding
arc gouging or chopping to restore the joint to the gap and approximate joint configuration
shown on the contract drawings. Gouging dross, burning dross, or reside shall be removed
by brushing or grinding before welding commences.
4.1.2.4
Retainers
Nonmetallic retainers or non-fusing metal retainers may only be used when they are
specified on the specific WPS.
4.1.2.5
Backing
Double welded groove welds are considered welding with backing.
For single welded groove welds, the backing shall be as specified in the specific WPS.
Root Opening
Normal root opening shall be 0- 1/4" (0 mm-6.4 mm). Spacer bar joints are considered 0"
gap.
Wide Gaps
The following technique shall be used for welding joints with wide gaps which exceed
twice that specified on the applicable contract drawing. When zero gap is specified on the
contract drawing, gaps exceeding 3/16" (4.8 mm) shall be reduced as outlined below to a
3/16" (4.8 mm) or smaller gap. Maximum weld build-up shall be T (where T is the
thickness of the plate) for each plate edge or (12.7 mm) whichever is smaller.
Pag. 14
Method:
Plate edge build-up shall be done with a welding procedure approved for contract use.
Weld passes shall be deposited utilizing a stringer bead technique to restore the plate edges
to the gap and approximate joint configuration as shown on the contract drawings.
On single or square butt joints, a temporary back-up bar of compatible material may be
used. The edges should be built-up using stringer beads to restore the joint to the gap and
approximate joint configuration as shown on contract drawings, before tying the edges
together.
The temporary back-up bar shall be removed by gouging, chipping or grinding to clean,
sound-metal before welding the second side.
4.4.2.3
Narrow Gaps
The following technique shall be used for correcting joints with gaps less than specified on
the applicable contract drawing which are not sufficiently wide to allow free manipulation
of the electrode in the joint.
Method:
The plate edges of the joint shall be prepared by flame cutting, plasma arc cutting, arc
gouging, or chipping to restore the joint to the gap and approximate joint configuration
shown on the contract drawings. Gouging dross, burning dross, or residue shall be removed
by brushing or grinding before welding commences.
4.4.2.4
Retainers
Nonmetallic retainers or non-fusing metal retainers may only be used when they are
specified on the specific WPS.
4.4.2.5
Backing
Double welded groove welds are considered welding, with backing,
For single welded groove welds, the backing shall be as specified in the specific WPS.
Pag. 15
When an imperfection is repaired by chipping or grinding and subsequent repair by welding is non
required, the excavated area shall be blended into the surrounding surface so as to avoid sharp
notches, crevices or corners.
When an imperfection is to be repaired by welding, after the imperfection is thought to have been
removed and prior to making weld repairs, the area shall be examined by the applicable steps in the
Procedure section of the Technique Procedure to ensure it has been removed or reduced to an
acceptably sized imperfection.
Pag. 17
20
20
24
25
25
26
27
28
29
Pag. 18
The Manufacturer shall certify that the welding on a vessel has been done only by welders and
welding operators who have been qualified under the requirements of Section IX and the Inspector
shall assure himself that only qualified welders and welding operators have been used.
The Manufacturer shall make available to the Inspector a certified copy of the record of the
qualification tests of each welder and welding operator. The Inspector shall have the right at any time
to call for a witness tests of the welding procedure or of' the ability of any welder and welding
operator.
Pag. 19
Imperfections which produce a response greater than 20% of the reference level shall be investigated to the
extent that the operator can determine the shape, identity, and location of all such imperfections and evaluate
them in terms of the acceptance standards given in (a) and (b) below.
a)
b)
Report of examination
The Manufacturer shall prepare a report of the ultrasonic examination and a copy of this report shall he
retained by the Manufacturer until the Manufacturer's Data Report has been signed by the inspector. The
report shall contain the information required by Section V. In addition, a record of repaired areas shall he
noted as well as the results of the reexamination of the repaired areas. The Manufacturer shall also maintain a
record of all reflections from uncorrected areas having responses that exceed 50% of the reference level. This
record shall locate each area, the response level, the dimensions, the depth below the surface, and the
classification.
All welded joints to be radiographed shall be examined in accordance as per attached specifications
1)
2)
b)
Indications shown on the radiographs of welds and characterized as imperfections are unacceptable
under the following conditions and shall be repaired, and the repair radiographed, ultrasonically
examined in accordance with the method and the standards specified, provided the defect has been
confirmed by the ultrasonic examination to the satisfaction of the Authorized Inspector prior to
making the repair. For material thickness in excess of 1 in., the concurrence of the user shall be
obtained. This ultrasonic examination shall be noted under remarks on the Manufacturer's Data
Report Form:
1)
2)
full penetration weld includes a fillet weld, the thickness of the throat of the fillet shall be
included in t.
c)
3)
any group of aligned indications that have an aggregate length greater than t in a length of 12t,
except when the distance between the successive imperfections exceeds 6L where L is the length
of the longest imperfection in the group;
4)
All welded joints to be examined by Real Time Radioscopic Examination shall be examined in
accordance with Specifications.
1)
2)
3)
A complete set of records shall be evaluated by the Manufacturer prior to being presented to the
Inspector. Imperfections shall be repaired and the repair reexamined by either film or Real Time
Radioscopic Examination. Records shall be retained until the Data Report has been signed by the
Inspector.
Provisions for training, experience, qualification and certification of personnel responsible for
equipment setup, calibration, operation, and evaluation of examination data shall be described in
the Manufacturer's Quality Control System.
The use of Real Time Radioscopic Examination shall be noted under remarks on the
Manufacturer's Data Report.
When the weld metal is of an alloy group or grade which has a radiation attenuation that
differs from the base material, the penetrameter material selection shall be based on the
weld metal or shall be from an alloy material group or grade with less radiation absorption
than the material being radiographed. As an example, for Inconel weld metal use of a
carbon steel or stainless steel IQI is acceptable
When density limits can not be met with one penetrameter and the exceptional density
area(s) is at the interface of the weld meta1 and the base material, the materia1 se1ection
for the additional penetrameter(s) shall be based on the base material.
IQI Placement
-
For single or double wall exposures for single wall viewing, place a source side
penetrameter on the side nearest the radiation source. Where inaccessibility prevents this,
place a film side penetrameter in contact with the object being examined. Place a lead letter
F" adjacent to or on the penetrameter (s) , but it sha11 not mask the essential hole or
designated wire.
For double wall exposures for double wall viewing, place a source side penetrameter on the
side nearest the radiation source.
When using hole type penetrameters, place then adjacent to or on the weld. If the filler
metal is not radiographically similar to the base material (as categories in SE1025), place
the hole type penetrameter on the weld. When using wire type penetrameters, place them
on the weld with the wires perpendicular to the length of the weld. The lead identification
numbers for either type penetrameter shall not appear in the area of interest
Lead identification numbers and lead letter F when used, may appear in the area of
interest; if geometric configuration makes it impractical to place the penetrameter.
For cylindrical components where the source is placed on the axis of the component for a single
exposure, at least three penetrameters, spaced approximately 120 deg. Apart, are required under
the following conditions:
a) when the complete circumference is radiographed using one or more film holders, or;
b) when a section or sections of the circumference, where the length between the ends of the
outermost sections span 240 or more deg., is radiographed using one or more film holders.
Additional film locations may be required to obtain necessary penetrameter spacing.
For cylindrical components where the source is placed on the axis of the component for a single
exposure, at least three penetrameters, with one placed at each end of the span of the
circumference radiographed and one in the approximate center of the span, are required under
the following conditions:
a) when a section of the circumference, the length of which is greater than 120 deg. And less
than 240 deg., is radiographed using just one film holder, or;
Pag. 22
b)
when a section or sections of the circumference, where the length between the ends of the
outermost sections span less than 240 deg., is radiographed using more than one film
holder.
In (1) and (2) above, where sections of longitudinal welds adjoining the circumferential weld are
radiographed simultaneously with the cricumferential weld, an additional penetrameter shall be
placed on each longitudinal weld at the end of the section most remote from the junction with the
circumferential weld being radiographed.
For spherical components where the source is placed at the center of the component for a single
exposure, at least three penetrameters, spaced approximately 120 dec. Apart, are required under
the following conditions:
a) when a complete circumference is radiographed using one or more film holders, or;
b) when a section or sections of a circumference, where the length between the ends of the
outermost sections span 240 or more deg., is radiographed using one or more film holders.
Additional film locations may be required to obtain necessary penetrameter spacing.
For spherical components where the source is placed at the center of the component for a single
exposure, at least three penetrameter, with one placed at each end of the radiographed span of the
circumference radiographed and one in the approximate center of the span, are required under
the following conditions:
a) when a section of a circumference, the length of which is greater than 120 deg. And less than
240 deg., is radiographed using just one film holder, or;
b) when a section or sections of a circumference, where the length between the ends of the
outermost sections span less than 240 deg., is radiographed using more than one film
holder.
In (4) and (5) above, where other welds are radiographed simultaneously with the
circumferential weld, one additional penetrameter shall be placed on each other weld.
When an array of components in a circle is radiographed, at least one penetrameter shall show on
each component image
In order to maintain the continu8iti of records involving subsequent exposure, all radiographs
exhibiting penetrameters which qualify the techniques permitted in accordance with (1) through
(6) above shall be retained.
insufficient and the radiograph shall be considered unacceptable. A dark image of the B on a
lighter background is not cause for rejection.
4.1.7 Length of Film
For 100% radiographic examination, the length of film used will be determined by the job
conditions. However, film length shall be at least 1 inch (25 mm) greater than the interval spacing to
ensure adequate overlap at each end.
For spot radiographic examination, the minimum length of film shall be 7 inches (178 mm).
4.1.8 Shape of film
Shape of the film to the contour of the object and place it as close as possible to the surface of the
weld during exposure.
4.1.9 Number of Exposures
4.1.9.1
The number of spot radiographs and their locations shall be in accordance with drawings
and instructions.
4.1.9.2
For the Single Wall Technique, when the source is located on the inside or outside of the
vessel or pipe, an adequate number of exposures shall be made to demonstrate coverage.
4.1.9.3
For the Double Wall Technique for Single Wall Viewing, a minimum of three (3) exposures
separated by 120 is required.
4.1.9.4 For the Double Wall Technique for Double Wall Viewing, (3 inch (89 mm) O.D. pipe or
less), the following applies:
1)
A minimum of two (2) exposures are required, taken at 90 to each other, when the
radiation beam is offset from the plane of the weld centerline at an angle sufficient to
separate the images of the weld so there is no overlap of areas to be interpreted. See
Figure C.
2)
A minimum of three (3) exposures are required, taken at 60 to 120 to each other,
when the radiation beam is positioned so the images of both walls are superimposed.
The minimum thickness of steel or nickel for which radioactive Iridium 192 may be used
shall be 0.75 inches (19 mm) and for Cobalt 60 shall be 1.50 inches (38 mm) except al
provided in 6.3
4.2.2.2. Radioactive isotopes shall not be used on aluminum with a minimum thickness less than
2.50 inches (63.5 mm)
Pag. 24
4.2.3
The maximum thickness for the use of radioactive isotopes is primarily dictated by exposure time;
therefore, upper limits are not shown. The minimum recommended thickness limitation may be
reduced when the radiographic techniques used demonstrate that the required radiographic sensitivity
has been obtained.
4.3 Geometrical unsharpened limitation guidelines
The following geometrical unsharpened values shall be used as a guide for determining minimum source to
weld or object distant (D). Final acceptance of radiographs shall be based on the ability to see the prescribed
penetrameter image and specified hole or the designated wire of a wire penetramenter.
Material
Thickness, inches (mm)
Ug
Maximum inches (mm)
Under 2 (51)
2 (51) through 3 (75)
Over 3 (76) through 3 (102)
Greater than 4 (102)
0.020
0.030
0.040
0.070
(0..5)
(0.76)
(1.0)
(1.8)
Geometrical unsharpened (Ug), equals effective source size (F): the maximum projected dimension of the
radiating source in the plane perpendicular to the distance D from the weld or object being radiographed,
times the distance (d) from source side of weld or object being radiographed to the film, over distance (D)
form source of radiation to weld or object being radiographed.
UG = Fd/D
4.4.2
The film density through the image of the body of a hole type penetrameter or adjacent to the
designated wire of a wire type penetrameter and the area of interest for single film viewing
shall be 1.8 minimum for radiographs made with an X-ray source and 2.0 minimum for
radiographs made with a gamma ray source. For composite viewing of multiple film
exposures, each film of the composite set shall have a minimum density of 1.3. The
Pag. 25
maximum density shall be 4.0 for viewing. A tolerance of 0.05 in density is allowed for
variations between densitometer readings.
4.4.3
4.4.4
If the requirements are met by using two Penetrameters, one shall be representative of the
lightest area of interest and the other the darkest are of interest, and the intervening densities
on the radiograph shall be considered as having acceptable density.
4.4.5
All radiographs shall be free from mechanical, chemical or other processing defects that
could interfere with proper interpretation of the radiograph.
4.5 Documentation
Record radiographs, with their grading, on a Report of Radiography Examination
4.5.1.1 Record spot radiography and 100% radiography on separate report forms.
4.5.1.2 Acceptable radiographs may be combined on one line of the report, provided the interval
numbers are consecutive.
4.5.1.3 List tracers separately in sequence and mark them T1, T2, etc.
4.5.1.4 List repairs separately in sequence and mark them R1, R2, etc.
4.5.1.5 List reshots, taken for reason other than either of the above, separately from the original film
and mark them RS.
4.5.1.6 When inaccessibility or other limitations prevent the location of markers, a dimensioned
sketch of the geometric arrangement including marker locations shall be documented on
the back of the Report of Radiography Examination form.
4.5.2
4.5.2.1 In-Process Radiographs taken for information only on an area of a joint not fully welded
regardless of whether or not they are used for making repairs.
4.5.2.2 Technique radiographs showing no rejectable indications taken to establish parameters that
produce radiographs that meet the film quality requirements of this procedure.
4.5.2.3 Radiographs showing no rejectable indications, but unacceptable from standpoint of film
quality requirements due to defective film, improper processing, physical damage, or
improper technique.
4.5.2.4 Radiographs that can not be identified as to location (i.e. vessel, joint number, film number)
4.5.2.5 Record on the Record Drawing or Checklist the film interval or identification numbers and
the sequential direction of the numbers for each weld joint as follows:
4.5.2.6 For 100% or Random Radiography, record the first and last interval number
4.5.2.7 For Spot Radiography, record all the film identification numbers.
4.5.2.8 Record joint identification number
4.5.2.9 Record welders or operators identification for all butt welded joints.
Pag. 26
4.6 Radiographic requirements for ASME Section VIII Code Division 1 e 2 pressure vessels
Scope
This procedure contains the ASME Section VIII Code radiographic acceptance criteria requirements and is to
be used with the applicable standard or contract X or N general Radiographic Examination Technique
Procedure RT5 or RTDF.
Reference
1992 ASME Section VIII Code or with any of the following Addenda: 92, 93, 94
1995 ASME Section VIII Code or with any of the following Addenda: 95, 96
Personnel
Personnel performing this examination shall be qualified in accordance with a Nondestructive Examination
Personnel Training, Qualification and certification Program which is in accordance with the guidelines of the
Code referenced edition of SNT-TC-1A. Level I, II or III personnel may perform radiography and level II or
III personnel shall evaluate.
Reinforcement
Reinforcement on each side of all butt welded joints shall not exceed the following thickness:
Nominal Wall
Thickness (T), In. (mm)
(2.4)
(2.4 to 4.8) incl.
(4.8 to 12.7), incl.
(12.7 to 25.4) incl.
(25.4 to 51) incl.
(51 to 75) incl.
(76 to 102) incl.
(102 to 127) incl.
(127)
(2.4)
(3.2)
(4.0)
(3.0)
(3.0)
(6.4)
(6.4)
(6.4)
(7.9)
3/32
3/32
1/8
5/32
5/32
5/32
5/32
1/4
5/16
(2.4)
(2.4)
(3.2)
(4.0)
(4.0)
(4.0)
(4.0)
(6.4)
(7.9)
Other
Welds
Div. 1 & 2
1/32
1/16
3/32
3/32
1/8
5/32
7/32
1/4
5/15
(0.8)
(1.6)
(2.4)
(2.4)
(3.2)
(4.0)
(5.6)
(6.4)
(7.9)
Pag. 27
Acceptance criteria for 100% radiography of division 1 vessels and all radiography (100% and spot) of
division 2 vessels
Sections of welds that are shown by radiography to have any of the following types of discontinuities are
unacceptable. The weld shall be repaired and re-radiographed in accordance with this procedure.
- Any indication characterized as a crack or zone of incomplete fusion or penetration.
- Any other elongated indication which has a length greater then:
1/4 in. (6.3 mm) for T up to 3/4 in. (19 mm)
1/3 T for T from 3/4 in. (19 mm) to 2-1/4 in. (57 mm)
3/4 in. (19 mm) for T over 2-1/4 in. (57 mm)
T = the thickness of the weld excluding any allowable reinforcement. For a butt weld
joining two members having different thickness at the weld, T is the thinner of these two
thickness. If a full penetration weld includes a fillet weld, the thickness of the throat of the
fillet shall be included in T.
- Any group of aligned indications that have an aggregate length greater than T in a length of 12 T,
except where the distance between successive imperfections exceeds 6L, where L is the length of
the longest imperfections in the group.
- Rounded indications in excess of that shown as acceptable in Appendix 4 of Division 1 or in
Appendix 8 of Division 2 of the ASME Section VIII Code.
4.7 Acceptance criteria for spot radiography of Division 1 vessels only
4.7.1
4.7.2
4.7.3
Welds in which the radiography shows any of the following types of discontinuities are unacceptable
until repaired and re-radiographed per this procedure:
4.7.1.1 Any indication characterized as a crack or zone of incomplete fusion or penetration.
4.7.1.2 Indications characterized as slag inclusions or cavities which have a length greater than 2/3T
where T is the thickness of the weld excluding any allowable reinforcement. For a butt weld
joining two members having different thickness at the weld, T is the thinner of these two
thickness. If a full penetration weld includes a fillet weld, the thickness of the throat of the
fillet shall be included in T. Maximum length of any such indication shall be inch (19
mm). Any such indication shorter than inch (6 mm) shall be acceptable for any plate
thickness.
If several indications within the above limitations exist in line, the weld shall be acceptable if the
sum of the longest dimensions of all such indications is no more than T in a length of 6T (or
proportionately for radiographs shorter than 6T) and if the longest indications considered are
separated by at least 3L of acceptable weld metal, where L is the length of the longest indication.
Rounded indications are not a factor in the acceptability of welds required to be spot radiographed.
When a spot radiograph is graded acceptable the entire length of weld represented by this radiograph
is acceptable.
4.8.2
When a spot radiograph discloses welding which does not comply with the minimum requirements
two additional radiographs (tracers) shall be taken in the same weld unit at locations away from the
original spot.
Pag. 28
4.8.2.1
If the two additional radiographs (tracers) show welding which meets the minimum quality
requirements the entire weld unit represented by the three radiographs is acceptable. The
unacceptable welding disclosed by the first of the three radiographs shall be removed and
the area repaired and re-radiographed.
4.8.2.2 If either of the two additional radiographs (tracers) shows unacceptable welding, the entire
unit of weld represented shall be rejected. At the option of the Manufacturer:
EITHER
The entire unit of rejected weld shall be removed, the joint rewelded and spot radiographed
in accordance with this procedure.
OR
The entire unit of rejected weld shall be 100% radiographed and only unacceptable welding
need be repaired and spot radiographed in accordance with this procedure.
As necessary, clean welds of dirt, oil, grease or other substances that might interfere with the
examination using a cleaning agent.
While performing the inspection, natural or artificial lighting shall be adequate to illuminate the
surface being examined to a minimum of fifty (50) foot cans. Illumination form any one of the
following light sources or a brighter light source is adequate:
Light Source
Maximum Source to Object
Distance in inches (mm)
2D Cell
Flashlight
60 Watt
Bulb
75 Watt
Bulb
100 Watt
Bulb
10 (254)
10 (254)
13 (381)
18 (457)
If possible, the surface being inspected shall be viewed without visual aids. However, visual aids
such as mirrors, magnifying lenses, etc. may be used if access to the surface being examined is not
easily achieved.
Personnel performing direct visual inspections shall have access sufficient to place the eye within 24
inches (610 mm) of the surface to be inspected and at an angle not less than 30 degrees to the surface
to be inspected. If the use of visual aids is required, the resolution capability shall be at least
equivalent to that obtainable by direct visual observation.
This may be demonstrated by the inspector being able to see a fine line, 1/32 inch (.8 mm) wide or
less, or other artificial flaw on the surface (or a surface similar to that being examined) in the least
discernible (viewable) location of the area being examined).
If required by the applicable Code or Standard, inspect joints after fit-up, but before welding, for
correct weld edge prep, gap and alignment.
After welding, inspect welds for surface indications and appearance and measure at representative
locations for adequacy of size, concavity, convexity (if applicable), reinforcement and length using
gauges and measuring tapes.
Where readily accessible for viewing without visual aids, inspect the root surface of single sided
welds to determine the amount of penetration (protusion) or concavity (suck up).
5.2 Visual inspection requirements for ASME Section VIII Code division 1 & 2 pressure vessels
Scope
This procedure contains the ASME Section VIII Code visual inspection acceptance criteria requirements for
complete welds and is to be used with the applicable standard or contract X or N general Visual
Inspection Technique Procedure VI5.
Reference
1992 ASME Section VIII Code or with any of the following Addenda: 92, 93, 94
1995 ASME Section VIII Code or with any of the following Addenda: 95, 96
Acceptance Criteria
As welded surfaces are permitted, provided the surface of welds are sufficiently free from coarse
ripples, grooves, overlaps, and abrupt ridges and valleys.
The surface condition of the finished weld shall be suitable for proper interpretation of radiographic
and other required nondestructive examinations when these examinations are required by contract
drawings.
Undercut shall not exceed 1/32 inch (0.8 mm) or 10% of the nominal thickness of the adjoining
surface, whichever is less.
The surface of butt welded joints may be flush with the base material or may have uniform crowns.
The height of reinforcement for each weld surface shall not exceed the following:
Pag. 30
Nominal Wall
Thickness (T), In. (mm)
(2.4)
(2.4 to 4.8) incl.
(4.8 to 12.7), incl.
(12.7 to 25.4) incl.
(25.4 to 51) incl.
(51 to 75) incl.
(76 to 102) incl.
(102 to 127) incl.
(127)
3/32
1/8
5/32
1/8
1/8
1/4
1/4
1/4
5/16
(2.4)
(3.2)
(4.0)
(3.0)
(3.0)
(6.4)
(6.4)
(6.4)
(7.9)
3/32
3/32
1/8
5/32
5/32
5/32
5/32
1/4
5/16
(2.4)
(2.4)
(3.2)
(4.0)
(4.0)
(4.0)
(4.0)
(6.4)
(7.9)
Other
Welds
Div. 1 & 2
1/32
1/16
3/32
3/32
1/8
5/32
7/32
1/4
5/15
(0.8)
(1.6)
(2.4)
(2.4)
(3.2)
(4.0)
(5.6)
(6.4)
(7.9)
Concavity on the root side of a single side welded circumferential butt weld is permitted when the
resulting thickness of the weld is at least equal to the thickness of the thinner member of the two (2)
sections being joined and the contour of the concavity is smooth.
Offset of final butt welded joints shall not be greater than that shown in the following Table
NOTE: t is the nominal thickness of the thinner section of the joint.
Section Thickness, in. (mm)
A
Up to 1/2 (12.7), incl.
Over to (12.7 to 19), incl.
Over to 1-1/2 (19 to 38), incl.
Over 1-1/2 to 2 (38 to 51)
Over 2 (51)
Joint Categories
B,C, & D
1/4 t
1/8 in. (3.2)
1/8 in. (3.2)
1/8 in. (3.2)
Lesser of
1/16t or 3/8 in. (9.5)
1/4 t
t
3/16 in. (4.8)
1/8 t
Lesser of
1/8t or in. (19)
Any offset within the allowable tolerance of the Table shall be faired at a three to one taper over the
width of the finished weld, or if necessary, by adding additional weld metal beyond what would
otherwise be the edge of the weld.
Fillet Welds
Fillet welds may vary from convex to concave
The size of the fillet weld shall be determined as follows:
Cracks or other linear indications in welds are unacceptable.
Pag. 31
6.2 Placement of location markers (film interval numbers or identification numbers) and film
identification
Place location markers, which are to appear as images on the film, on the surface near the weld ate the film
intervals for multiple exposures or the approximate center point of the film location for single exposures. The
location of the markers shall be marked permanently on the surface of the part when permitted (shall be with
a low stress centerpunch) or on a record drawing. In this manner, the area of interest on a radiograph may be
accurately traceable to its location on the surface of the part. It also provides evidence on the radiograph that
the area being examined has been obtained, When permanent marking is not allowed, use temporary marking
such as a paint stick or equal.
6.2.1
Lead number location markers (film interval numbers or identification numbers), which are
to appear as images on the film, shall be placed on the material adjacent to the weld at the
marks located in 5.1 and as follows:
6.2.2
Location markers shall be placed on the source side when radiographing joints in:
- Flat components or longitudinal joints in cylindrical or conical components;
- Curved or spherical components whose concave side is toward the source and when the
source to material distance is less than the inside radius of the component;
- Curved or spherical components whose convex side is toward the source.
6.2.3
Location markers shall be placed on the film side when radiographing joints in curved or
spherical components whose concave side is toward the source and when the source to
material distance is greater than the inside radius.
6.2.4
Location markers may be placed on either the source side or film side when radiographing
joints in curved or spherical components whose concave side is toward the source and the
source to material distance equal the inside radius of the component.
6.2.5
As an alternative to source side placement, location markers may be placed on the film side
when the radiograph shows coverage beyond the location markers to the extent
demonstrated as follows:
6.2.6
6.2.7
For single wall viewing, circumferential number tapes shall be used. The 0 numbers shall be
placed on the 0 point on the pipe and the remaining numbers located clockwise (or counterclockwise) around the outside of the pipe. A minimum number of markers shall be used to
provide evidence that the required coverage has been obtained.
6.2.8
For double wall viewing, at least one location marker shall be placed on the source side
surface adjacent to the weld for each exposure.
6.2.9
7.1.2
7.1.3
For the pipes, the pressure shall first be gradually brought to the testing value, later shall be
lowered to the calculated value and maintained for the time needed to allow, where possible,
visual control of the welding; shall then be brought to test value and maintained with this
value for at least 10 minutes, and anyhow for the time needed in order to make a careful
exam of all the welded joints and expansion joints that may need tightened.
If the hydraulic test reveals unacceptable local deformation or transuding for lack of
penetration, scoring, cracks, porosity or other, the faulty element shall be repaired and reexamined.
The pressure, during the hydraulic test shall be recorded continually with a manometer.
7.2.1.3
7.2.1.4
7.2.1.5
7.2.1.6
After the completion of erection, and an accurate internal control of the piping in order to
ensure that no extraneous materials remained inside, the pipes shall be submitted, before
starting, to the static tests of hydraulic pressure.
For the tests execution, the downstream cut-off may be carried out with the machine valves
when the seal is already checked and the relative base foundations verified also for the
loads resulting from the tests; when these conditions are not respected, flanged bottoms
shall be used, the piping shall be filled with water through the bottoms with pump
connections, the air discharge and the manometer. Safety valves shall be gagged,
provisions shall be made to limit maximum pressure applied during test.
The piping shall be filled with water and maintained for the required length of time to permit
in services leak testing. All bolts of the expansion joints shall be adjusted.
If during tests appear seal defects, the defectous elements, if possible, shall be repaired in
accordance to the specifications or a replace may be requested. The hydraulic test of the
piping section where the defectous element was found shall be repeated.
The pressure shall be gradually brought to test value and so maintained for 30 minutes; then
lowered to the value corresponding to maximum static level in the load chamber or in the
piezometer well; at this pressure through visual control the junctions carried out during the
site assembly shall be checked; at last the pressure shall be brought back to test value and
maintained for the required time to carry out the piping inspection.
If during test appear resistance or seal defects, the defectous element, if possible, shall be
repaired in accordance to the specification of paragraph 7.4 or a replacement may be
requested.
The hydraulic test of the piping section where the defectous element was found shall be
repeated.
Pag. 33
PAINTING PROCEDURE
Index:
1.0 Field blasting & painting procedure.......................................................................................Pag. 35
1.1 Scope...........................................................................................................................Pag. 35
1.2 Surface preparation......................................................................................................Pag 35
1.3 Painting........................................................................................................................Pag. 35
Technical Data: Navitar AS...............................................................................................Pag. 36
Technical Data: Jotabar ZEP..............................................................................................Pag. 39
Technical Data: Primastic Universal..................................................................................Pag. 42
2.0 Field Touch-Up Requirements...............................................................................................Pag. 45
3.0 Inspection Requirements........................................................................................................Pag. 45
4.0 General Painting requirements...............................................................................................Pag. 45
4.1 Paint buckets...................................................................................................................Pag. 46
Pag. 34
two (2) coats of Epoxy coal-tar NAVITAR AS for a total thickness of dry film of 400
micros.
External surface: one (1) coat of Zinc-rich epoxy primer JOTABAR ZEP for a total thickness of dry film of
50 microns;
two (2) coats of high solids modified epoxy PRIMASTIC UNIVERSAL for a total
thickness of dry film of 90 microns.
The total external surface will have a total dry film thickness of 140 microns.
Pag. 35
NAVITAR AS
PRODUCT:
Navitar AS
DESCRIPTION:
RECOMMENDED USE:
TECHNICAL INFORMATION:
Colour
Solids (% by volume):
Flash point
Flexibility
Gloss
Water resistance
Chemical resistance
Solvent resistance
Abrasion resistance
:
:
:
:
:
:
:
:
:
Dark Brown/Black
90 2
75 C 2 (Setaflash)
Good
Semi-flat
Excellent
Good
Good (discoloration)
Good
Film thickness per coat
in microns
Dry
Wet
200 400
300
225 445
330
4.5 2.3
3.0
APPLICATION DATA:
Application methods
Miring ratio
(by volume)
Pot life (23 C)
Thinner/Cleaner
Guiding data airless spray
Pressure at nozzle
Nozzle tip
Spray angle
Filter
:
:
:
:
:
:
:
:
:
Pag. 36
NAVITAR AS (cont.)
SURFACE
PREPARATION:
CONDITION DURING
APPLICATION:
DRYING/
CURING TIME:
Substrate
temperature
10 C
23C
35 C
1.
2.
3.
4.
Surface
Dry
24 h
12 h
4h
The drying times are measured according to BS 3900 Part C2 and BS 3900
Part C3.
Drying times are generally related to air circulation, temperature, film thickness
and number of coats, and will be affected correspondingly. The figures given in
the table are typical with:
* Good ventilation
* Recommended film thickness
* One coat on top of inert substrate
1
Hard
Dry
Cured
48 h
24 h
6h
14 d
7d
3d
Dry to recoat3
Minimum
48 h
24 h
6h
Maximum 4
Interior
Exterior
7d
7d
4d
The given data must be considered as guidelines only. The actual drying time/times before recoating
may be shorter or longer, depending on existing coating, generic type, film thickness, system chosen,
no. of coats, ventilation, temperature, requirement for early handling and mechanical strength etc. A
complete system can be described on a system sheet, where all parameters and special conditions could
be included.
TYPICAL RECOMMENDED
PAINT SYSTEM:
Navitar AS (diluted 25%)
Stripe coat
Navitar AS
Thickness)
Pag. 37
NAVITAR AS (cont.)
PACKING CONTENT:
HEALTH AND SAFETY:
DISCLAIMER:
The information in this data sheet is given to the best of our knowledge based on laboratory
testing and practical experience. However, as the product is often used under conditions beyond
our control, we can not guarantee anything but the quality of the product itself. We reserve the
right to change the given data without notice.
VERSION 1/97. ISSUED SEPTEMBER 1997, JOTUN FAINTS NORWAY
THIS DATA SUPERSEDES THOSE PREVIOUSLY ISSUES
Pag. 38
JOTABAR ZEP
PRODUCT:
JOTABAR ZEP
DESCRIPTION:
RECOMMENDED USE:
TECHNICAL INFORMATION:
Colour
Solids (% by volume):
Flash point
Flexibility
Gloss
Water resistance
Chemical resistance
Solvent resistance
Abrasion resistance
:
:
:
:
:
:
:
:
:
Grey
43 2
25 C 2 (Setaflash)
Good
Flat
Excellent
Fair
Fair
Good
Film thickness per coat
in microns
Dry
Wet
25 75
50
60 175
115
17.2 5.7
8.6
APPLICATION DATA:
Application methods
Miring ratio
(by volume)
Pot life (23 C)
Thinner/Cleaner
Guiding data airless spray
Pressure at nozzle
Nozzle tip
Spray angle
Filter
SURFACE
PREPARATION:
:
:
:
:
:
:
:
:
:
Pag. 39
JOTABAR ZEP
CONDITION DURING
APPLICATION:
DRYING/
CURING TIME:
The drying times are measured according to BS 3900 Part C2 and BS 3900
Part C3.
Drying times are generally related to air circulation, temperature, film thickness
and number of coats, and will be affected correspondingly. The figures given in
the table are typical with:
* Good ventilation (outdoor exposure or free circulation air)
* Recommended film thickness
* One coat on top of inert substrate
1
Substrate
temperature
Surface
Dry
5 C
10 C
23C
35 C
50 min
20 min
10 min
5 min
1.
2.
3.
4.
Hard
Dry
Cured
Dry to recoat3
Minimum
3h
2h
1.5 h
1h
10 d
7d
5d
3d
3h
2h
1.5 h
1h
Maximum 4
-
The given data must be considered as guidelines only. The actual drying time/times before recoating
may be shorter or longer, depending on existing coating, generic type, film thickness, system chosen,
no. of coats, ventilation, temperature, requirement for early handling and mechanical strength etc. A
complete system can be described on a system sheet, where all parameters and special conditions could
be included.
TYPICAL RECOMMENDED
PAINT SYSTEM:
HANDLING:
PACKING CONTENT:
Jotabar ZEP
Topcoat:
Pag. 40
JOTABAR ZEP
DISCLAIMER:
The information in this data sheet is given to the best of our knowledge based on laboratory
testing and practical experience. However, as the product is often used under conditions beyond
our control, we can not guarantee anything but the quality of the product itself. We reserve the
right to change the given data without notice.
VERSION 1/97. ISSUED JUNE 1997, JOTUN FAINTS NORWAY
THIS DATA SUPERSEDES
Pag. 41
PRIMASTIC UNIVERSAL
PRODUCT:
DESCRIPTION:
PRIMASTC UNIVERSAL
Primastic Universal is a two-pack, high solids modified epoxy coating.
RECOMMENDED USE:
Anticorrosive primer for steel structures above and below water, also on
steel where blast cleaning may not be possible.
TECHNICAL INFORMATION:
Colour
Solids (% by volume):
Flash point
Flexibility
Gloss
Gloss retention
Water resistance
Chemical resistance
Solvent resistance
Abrasion resistance
:
:
:
:
:
:
:
:
:
:
135 335
170
7.5 3.0
6.0
APPLICATION DATA:
Application methods
Miring ratio
(by volume)
Pot life (23 C)
Thinner/Cleaner
Guiding data airless spray
Pressure at nozzle
Nozzle tip
Spray angle
Filter
:
:
:
:
:
Airless spray,
5 parts Comp. A (base) to be mixed thoroughly with
1 part Comp. B (curing agent)
10 minutes
Jotun Thinner No. 17
:
:
:
:
Pag. 42
PRIMASTC UNIVERSAL
SURFACE
PREPARATION:
Power tool cleaning to St. 2, mill scale free (ISO 8501-1:1988/SS 05 59 00).
Improved surface pretreatment will improve the performance. When used over
old coating systems, the surface must be clean and dry.
CONDITION DURING
APPLICATION:
DRYING/
CURING TIME:
Part C3.
The drying times are measured according to BS 3900 Part C2 and BS 3900
Drying times are generally related to air circulation, temperature, film thickness
and number of coats, and will be affected correspondingly. The figures given in
the table are typical with:
* Good ventilation (outdoor exposure or free circulation of
air)
* Recommended film thickness
* One coat on top of inert substrate
Substrate
temperature
10 C
23 C
35 C
1.
2.
3.
4.
Surface
Dry
8h
4h
2h
Hard
Dry
Cured
Dry to recoat3
Minimum
24 h
10 h
5h
14 d
7d
3d
24 h
10 h
5h
Maximum 4
Interior
-
PRIMASTC UNIVERSAL
DRYING /
CURING TIME: (cont.)
The given data must be considered as guidelines only. The actual drying time/times befog recoating
may be shorter or longer, depending on existing coating, generic type, film thickness, system chosen,
no. of coats, ventilation, temperature, requirement for early handling and mechanical strength etc. A
complete system can be described on a system sheet, where all parameters and special conditions could
be included.
TYPICAL RECOMMENDED
PAINT SYSTEM
ABOVE WATER:
Thickness)
Primastic Universal
TYPICAL RECOMMENDED
PAINT SYSTEM
Primastic Universal
UNDER WATER:
STORAGE AND PACKING:
STORAGE:
PACKING CONTENT:
HEALTH AND SAFETY:
DISCLAIMER:
The information in this data sheet is given to the best of our knowledge based on laboratory
testing and practical experience. However, as the product is often used under conditions beyond
our control, we can not guarantee anything but the quality of the product itself. We reserve the
right to change the given data without notice.
Pag. 44
When the surface temperature is above 40C or below 10C, or per the paint manufacturer's
requirements for specific paints.
b)
When the relative humidity in the work area is greater than 85% or per the paint manufacturer's
recommendation for specific paints.
c)
The surface temperature is less than 3C (5F) above the dew point of the air in the work area.
d)
Pag. 45
Pag. 46