P Stock
P Stock
P Stock
Astaldi-CBI prepared an area for the penstock fabrication, quality control, sand
blasting and painting shops. These facilities are located in the Unduavi Valley, in a
suitable area in Sacahuaya close to the Yanacachi Penstock and Powerhouse. Nearby a
camp facilities are also constructed for personnel working in the Penstock
Manufacture and Erection activities.
The shop is complete with all the electrical and distribution panels, lighting system, air
distribution system and all necessary hand tools such as hydraulic and mechanical jacks,
tir-4, lift pulleys, lifting cables, individual tools and all the protective clothing required.
Also incorporated in the shop will be tools spare parts and consumable materials
store. Store for welding materials, first aid infirmary, workshop office, x-ray laboratory
and permanent material store.
For the Taquesi project the shop will also be provided with the
following:
Materials:
The steel utilized for manufacturing the Penstock is ASTM A537 CL. 1 - produced
in Italy and all other welding materials according to WPS (Welding Procedure
Specifications).
Material characteristics
a. The metal plates for the manufacturing the Penstock shall be ASTM A537 CL. 1 -
produced in Italy shall be produced in compliance with applicable
specifications;
b. All welding materials shall be in compliance with WPS and applicable
specifications;
c. The steel used in the construction of the other parts such as Bends, Manifolds,
Flanges and Expansion Joints shall also be ASTM A537 CL. 1;
d. Anchor rings for pipes AP11AP17 will be manufactured and welded to the
pipes in the shop;
e. Manholes will be placed according to shop drawings and will be manufactured in
the shop;
f. Expansion joints will be manufactured in the shop. Assembling of expansion
joints will be made accordance with specifications, pipes will be cut
according to a thermal expansion charts, depending on the temperature and
length in which the expansion joint is installed;
1. Saddle supports steel plate, 8 mm thick, shall have a half moon of 120º
form, and shall be welded to anchor hooks for second stage concrete;
2. Pipes shall be completely painted in the shop, except for 20 cm. at both
ends that shall be painted on the job site, after erection and inspections.
g. The flange and coupling – tie rod, bolt and nut dimension after machining shall not
be inferior to nominal values.
h. The average internal diameter of every pipe or element, established by the
measure of the external development at the two ends and of the thickness, shall
not be different from the theoretic diameter more than 0.3% plus or minus with
a maximum of 5 mm.
i. The ovalization of every pipe or segment, determined by the maximum length
difference of almost two diameters perpendicular between them, cannot be
greater than 0.01D, D been the theoretic internal diameter.
j. Anchor rings shall be fabricated and welded to the pipes in the workshop
according to approved shop drawings.
k. Mechanical expansion joints shall be manufactured in the workshop according
to approved shop drawings.
l. The theoretic mass of every pipe or element appear on the single mass list an
the shop drawings on the basis of the final project for the piping, a variation less
than 5% is accepted. The theoretic mass shall be calculated on the basis of the
nominal dimensions and mass volume of 7.85 kg/dm³
3.2 Welding
Materials used in the construction of welded parts shall comply with the requirements
for materials given and shall be proven of weldable quality.
a. Records of the names of the welders who make each weld shall be maintained.
Welders and welding operators shall be qualified and qualification records
shall be available for audit.
b. Two sample tests will made, for tensile test and for bend test as per attached
sheet. These tests will be certified by a qualified firm.
c. Welding of the pipes in the workshop will be by automatic welding machines.
Welds will be butt welds from inside and outside. In tunnel sections welding will
be from inside only against external counter bars.
d. The edge to be butt welded shall be completely free from exfoliation, cracks or
incision, rust, calamine, humidity and shall be, therefore, submitted to the checks
and adequately protected.
e. When the temperature of the elements to be welded is lower than +5°C, and
anyhow when the room temperature is lower than –5°C or there is excessive
ventilation (with influence on the protection of the arc), the welding operations
shall be made with appropriate methods so that the cooling, after the welding,
is sufficiently slow to guarantee from cracking risk.
f. The removal of alignment jacks, tack welds and/or other possible appendixes
shall be done by grinding and subsequent visual examination of the grinded areas .
The pipes will be transported from the pipe factory to the erection site on a
truck with special supporting saddles;
Set up equipment, tools, temporary support shall be ready on the erection site
including ventilation for the steel lined sections;
Pipes will be unloaded with a cable way (Blondins) Lifting Capacity 5 Tons;
When working on slope and elevation areas, internal and external scaffold will be
prepared and erected.
The pipes will be lifted brought to position with the Blondins, a 60 cm alignment
slide will be welded and the joint spaced with a 2- 3 mm spacer ;
If necessary an aux. support will be welded on the front part to maintain the pipe
in position;
The pipe will be aligned and edges tack welded;
The inside welding shall be carried out first;
The exterior will be cleaned with arc-air and welded from the exterior;
Ultrasonic and radiographic tests will be made and eventual repairs will be carried-
out;
The welded part will be painted and the painting will be checked;
Anchor rings for pipes AP11AP17 will be manufactured and welded to the pipes
in the shop.
Manholes will be placed according to approved shop drawings and will be
manufactured in the shop.
Expansion joints will be manufactured in the shop. Assembling of expansion
joints will be made in accordance with specifications. Slip pipes will be cut
according to a thermal expansion charts, depending on the temperature and
length in which the expansion joint is installed ;
Saddle supports steel plate, 8 mm thick, shall have a half moon of 120 form, and
shall be welded to anchor stay hooks.
Welding will proceed in accordance with WPS here after specified. For security
reasons during night shifts, the interior of pipe will be welded and during day shifts
the exterior will be welded;
Painting and controls will follow;
For erection of steel lined tunnel sections, a trolley mounted on rails will be used
to transport the pipes, auxiliary foot supports welded to the pipe ends will be left
to concrete. Welding will befrom inside only against external counter bars ;
Visual inspection will be carried-out in the interior of the piping;
Covers of the manholes will be placed, o-rings checked;
Expansion joints will be tightened to torque;
Finally the piping will be filled with water and leak tested ;
Infiltration and leak inspections and controls will be carried-out;
A hydropressure test will be carried out to underground piping prior to
covering. Hollow blind flanges with adequate safety valves and manometers will
be welded at the 2 ends of the piping. The piping will be filled with water;
pressure will be gradually brought to 1-1/2 times the design pressure of the
piping and maintained for 30 minutes; after a visual control of the piping the
pressure will be lowered to the design pressure and maintained at this pressure
for the time required to permit inspection of the piping. If during test defects
appear, the defectous element will be repaired in accordance to specifications
and the hydrostatic test will be repeated. The blind flanges will be removed, and
the erection will proceed.
WELDING PROCEDURE
Scope
This is a general Welding Procedure Specification to be used with a specific
Welding Procedure Specification (WPS) when referred on the WPS. In case of
conflict between these documents and the specific WPS, the specific WPS shall
govern.
Reference
ASME Boiler and Pressure Vessel Code, Section IX. Welding Qualifications, Edition
and Addenda as shown on the specific WPS. Procedure qualifications WPS for the
project have been supplied by the welding materials supplier ESAB.
4.4 General welding procedure specifications for submerged arc welding
process (SAW)
Scope
This is a general Welding Procedure Specification to be used with a specific
Welding Procedure Specification (WPS) when referenced on the WPS. In cases
of conflict between this document and the specific WPS, the specific WPS shall
govern.
Reference
ASME Boiler and Pressure Vessel Code, Section IX, Welding Qualifications, Edition
and Addenda as shown on the specific WPS. Procedure qualifications WPS for the
project have been supplied by the welding materials supplier ESAB.