Accounting in The Modern World
Accounting in The Modern World
Accounting in The Modern World
Section:___________________
Final Exam
BA 301
Fall 2002
S.K. Norman
Version 1
Final Exam
Fall 2002
3 Points each
1.
We strive to lead in the creation, development, and manufacture of the most advanced
information technologies. This is an excerpt from IBMs _________.
a. total quality management plan
b. mission statement
c. competitive advantage
d. strategies
Final Exam
Fall 2002
8. An ambulance firm in a large metropolitan area is concerned with its response time. For
the last 20 days, they have randomly sampled 4 ambulance calls and measured the
response time for each. The firm has decided to implement statistical process control to
monitor average response time. What is the most appropriate chart(s)?
a. c-chart
b. p-chart
c. x -chart and R chart
d. z-chart
9. What is an advantage of outsourcing?
a. Allows firms to focus on core competition
b. Can be more cost effective
c. Adds capacity without additional fixed costs and overhead
d. All of the above
10. Which of the following is not part of the inventory cost structure?
a. Ordering cost
b. Setup cost
c. Variable cost
d. Holding cost
11. The R chart does which of the following:
a. Calculates intervals of data
b. Collects, organizes, and interprets data
c. Shows sample ranges and monitors variability
d. None of the above
12. The process of identifying other organizations that are best at some facet of your
operations and then modeling them is:
a. Copying
b. Benchmarking
c. Copycatting
d. Continuous improvement
13. The EOQ model reflects the trade-off between
a. Carrying costs and setup/ordering costs
b. Stockout costs and carrying costs
c. Penalty costs and ordering cost
d. Quantity discounts and setup costs
14. An airline ticket counter, with several agents for one line of customers is an example of a
a. single channel, single phase system
b. single channel, multi-phase system
c. multi-channel, single phase system
d. multi-channel, multi-phase system
Final Exam
Fall 2002
15. What combination of x and y will yield the optimum for this problem? NOTE: You do
not need to use the graphical method to answer this question.
Maximize
subject to
a.
b.
c.
d.
$3x + $15y
2x + 4y < 12
5x + 2y < 10
x 0, y 0
x = 2, y = 0
x = 0, y = 3
x = 1, y = 1
x = 1, y = 5
Final Exam
Fall 2002
Final Exam
Fall 2002
Final Exam
Fall 2002
Final Exam
Fall 2002
deliveries. The trucks arrive at random times throughout the day at the stores
dock to be loaded with new deliveries or to have incoming shipments from the
regional warehouse unloaded. The mean arrival rate per truck is 0.25 trucks per
hour. The mean service rate is 4 trucks per hour. Use the Excel OM output
below, to determine the hourly cost of operations if the cost is $50/hour for
waiting trucks and $30/hour for the dock.
Waiting Lines
Data
Arrival rate ()
Service rate ()
a.
b.
c.
d.
0.0625
0.0042
0.0667
0.0167
0.2667
0.9375
$30.21
$30.89
$33.33
$43.33
8
Final Exam
Fall 2002
Mark Koslow is the operations manager for the New England Shirt Company. In this capacity he
is required to develop an aggregate plan for the next six months with the goal of meeting
demand during this period. He has gathered the following data to determine the costs of the
plan.
Jan
Feb
Mar
Apr
May
Jun
Demand
2400
1200
2800
3600
3200
3600
Final Exam
Fall 2002
The Outdoor Furniture Company manufactures two products, benches and picnic tables. The
firm has two main resources: its carpenters (labor force) and a supply of redwood. During the
next production cycle, 1,200 hours of labor are available under a union agreement. The firm also
has a stock of 3,500 board feet of quality redwood. Each bench requires 4 labor-hours and 10
board-feet of redwood; each picnic table takes 6 labor-hours and 35 board-feet. Completed
benches will yield a profit of $9 each, and tables will result in a profit of $20 each. Formulate an
LP to determine the number of tables and benches to produce in order to optimize profit. Answer
the following questions regarding the LP formulation. Let B represent the number of benches and
T represent the number of tables.
Adjustable Cells
Cell
Name
$B$7 Number to build Bench
$C$7 Number to build Table
Constraints
Cell
Name
$D$2 Labor
$D$3 Redwood
Using the above description and the Solver Sensitivity Report, answer the next three questions.
52. The manager has additional budget to invest in additional Labor (overtime) or additional
redwood. How should this budget be used in order to optimize profits?
a. Invest in additional labor.
b. Invest in additional redwood.
c. Invest in both labor and redwood.
d. Cannot be determined.
53. The additional redwood is available as a special order. It would cost $0.35 per board-foot
to acquire this redwood. What is your recommendation to the manager regarding this
purchase?
a. Purchase up to 3493.3 board-feet with an additional profit of $20 per board-foot.
b. Do not purchase the redwood. The additional profit per board-foot is only
$0.325.
c. Purchase up to 3493.3 board-feet with an additional profit of $0.325 per boardfoot.
d. Cannot be determined.
54. What is the optimal solution?
a. B = 1198, T = 3495
b. B = 9, T = 20
c. B = 1.4375, T = 0.325
d. B = 262, T = 25
10
Final Exam
Fall 2002
Use the bill-of-materials for Product J (given below) to answer the next 3 questions.
J
LT = 2
K (2)
LT = 1
N (2)
LT = 2
L (4)
LT = 2
M (1)
LT = 1
O (1)
LT = 1
55. If a time-phased structure is drawn, how many weeks are required to produce Product J?
a. 3
b. 4
c. 5
d. 9
56. If 50 units of Product J have been ordered, how many units of N are required to fill the
order?
a. 2
b. 4
c. 100
d. 200
57. Using the gross requirements plan below, determine which week to release the order for
N.
Gross Requirements Plan
1
J
K
L
M
N
Required Date
Order release data
Required Date
Order release data
Required Date
Order release data
Required Date
Order release data
Required Date
Week
4 5 6
8
50
a.
b.
c.
d.
Week 2
Week 3
Week 4
Week 5
11
Final Exam
Fall 2002
Below is an unfinished net requirements plan for Product X. EOQ = 120 is the lot-sizing
technique used. Answer the next 2 questions using this information.
Net Requirements Plan
1
Gross requirements
Scheduled receipts
Lead Time
Projected on-hand | 60
= 2 weeks Planned order receipts
Planned order releases
Product X
3
100
Week
5
6
100
9
100
10
50
58. Using the EOQ = 120 lot-sizing technique, what is the amount of the planned order
release in Week 4?
a. 0
b. 70
c. 100
d. 120
59. Using the EOQ = 120 lot-sizing technique, what is the projected on-hand inventory in
Week 10?
a. 0
b. 10
c. 30
d. 50
60. A crew of mechanics at the Highway Department garage repair vehicles that break down
at an average of = 8 vehicles per day (approximately Poisson in nature). The
mechanic crew can service an average of = 10 vehicles per day with a repair time
distribution that approximates an exponential distribution. What is the average time
before the facility can return a breakdown to service?
a. 0.40 hours
b. 0.40 days
c. 0.50 hours
d. 0.50 days
12
Final Exam
Fall 2002
Below is the output from Excel OM for a project consisting of 10 activities and the completion
time in days. Answer the next 2 questions using this information.
Data
Time
A
B
C
D
E
F
G
H
I
J
Precedence 1Precedence 2
3
5A
10
3B
C
5B
C
10E
8C
3G
2D
H
3F
I
Results
Task
A
B
C
D
E
F
G
H
I
J
Late
Early StartEarly Finish Late Start
Finish
0
3
2
3
8
5
0
10
0
10
13
20
10
15
10
15
25
15
10
18
12
18
21
20
21
23
23
25
28
25
Project
28
Slack
5
10
10
23
15
25
20
23
25
28
2
2
0
10
0
0
2
2
2
0
61. Activity A takes 1 day more than expected. What affect does this have on the length of
the entire project?
a. The entire project takes 1 more day.
b. The entire project takes 2 more days.
c. No effect on the length of the entire project.
d. Cannot be determined.
62. Determine the critical path.
a. A-B-D-G-H-I-J
b. A-B-C-D-E-F-G-H-I-J
c. C-E-F-J
d. A-C-E-F-J
HAPPY HOLIDAYS!
13
Final Exam
Fall 2002
Formula Sheet
M/M/1
Ls
Lq
Ws
Wq
P0 1
Pn k
k 1
TC = CwLs + Csk
14