Installation and Commisioning Manual REC670
Installation and Commisioning Manual REC670
Installation and Commisioning Manual REC670
Innovation
from
ABB
COPYRIGHT
WE RESERVE ALL RIGHTS TO THIS DOCUMENT, EVEN IN THE EVENT
THAT A PATENT IS ISSUED AND A DIFFERENT COMMERCIAL
PROPRIETARY RIGHT IS REGISTERED. IMPROPER USE, IN PARTICULAR
REPRODUCTION AND DISSEMINATION TO THIRD PARTIES, IS NOT
PERMITTED.
THIS DOCUMENT HAS BEEN CAREFULLY CHECKED. HOWEVER, IN
CASE ANY ERRORS ARE DETECTED, THE READER IS KINDLY
REQUESTED TO NOTIFY THE MANUFACTURER AT THE ADDRESS
BELOW.
THE DATA CONTAINED IN THIS MANUAL IS INTENDED SOLELY FOR
THE CONCEPT OR PRODUCT DESCRIPTION AND IS NOT TO BE DEEMED
TO BE A STATEMENT OF GUARANTEED PROPERTIES. IN THE INTEREST
OF OUR CUSTOMERS, WE CONSTANTLY SEEK TO ENSURE THAT OUR
PRODUCTS ARE DEVELOPED TO THE LATEST TECHNOLOGICAL
STANDARDS. AS A RESULT, IT IS POSSIBLE THAT THERE MAY BE SOME
DIFFERENCES BETWEEN THE HW/SW PRODUCT AND THIS
INFORMATION PRODUCT.
Manufacturer:
ABB AB
Substation Automation Products
SE-721 59 Vsters
Sweden
Telephone: +46 (0) 21 34 20 00
Facsimile: +46 (0) 21 14 69 18
www.abb.com/substationautomation
Table of contents
Table of contents
Section 1
Introduction..........................................................................11
Introduction to the installation and commissioning manual....................11
About the complete set of manuals for an IED..................................11
About the installation and commissioning manual.............................12
Intended audience.............................................................................13
Related documents............................................................................13
Revision notes...................................................................................14
Section 2
Safety information...............................................................15
Warning signs.........................................................................................15
Caution signs..........................................................................................16
Note signs...............................................................................................17
Section 3
Overview.............................................................................19
Commissioning and installation overview...............................................19
Section 4
Section 5
Table of contents
Section 6
Table of contents
Section 7
Section 8
Section 9
Table of contents
Table of contents
Table of contents
Table of contents
Table of contents
Table of contents
Section 16 Glossary............................................................................225
Glossary................................................................................................225
10
Section 1
Introduction
Section 1
Introduction
About this chapter
This chapter introduces the user to the manual.
1.1
1.1.1
Technical
reference
manual
Installation and
commissioning
manual
Operators
manual
Engineering
guide
en06000097.vsd
The Application Manual (AM) contains application descriptions, setting guidelines and
setting parameters sorted per function. The application manual should be used to find out
when and for what purpose a typical protection function could be used. The manual should
also be used when calculating settings.
The Technical Reference Manual (TRM) contains application and functionality
descriptions and it lists function blocks, logic diagrams, input and output signals, setting
parameters and technical data sorted per function. The technical reference manual should
be used as a technical reference during the engineering phase, installation and
commissioning phase, and during normal service.
The Installation and Commissioning Manual (ICM) contains instructions on how to
install and commission the protection IED. The manual can also be used as a reference
during periodic testing. The manual covers procedures for mechanical and electrical
installation, energizing and checking of external circuitry, setting and configuration as
well as verifying settings and performing directional tests. The chapters are organized in
11
Section 1
Introduction
1.1.2
12
The chapter Safety information presents warning and note signs, that the user
should pay attention to.
The chapter Overview is a summary of the major tasks faced when installing and
commissioning an IED.
The chapter Unpacking and checking the IED explains how to take delivery of
the IED.
The chapter Installing the IED explains how to install the IED.
The chapter Checking the external optical and electrical connections explains
how to check that the IED is properly connected to the protection system.
The chapter Energizing the IED explains how to start the IED.
The chapter Establishing connection and verifying the SPA/IEC-communication
contains explains how to enter SPA/IEC settings and verifying the SPA/IEC
communication.
The chapter Establishing connection and verifying the LON communication
contains a reference to another document.
The chapter Configuring the IED and changing settings explains how to download
settings and configure the terminal.
The chapter Verifying settings by secondary injection contains instructions on how
to verify that each included function operates correctly according to the set values.
Section 1
Introduction
1.1.3
Intended audience
General
The installation and commissioning manual addresses the personnel responsible for the
installation, commissioning, maintenance and taking the protection in and out of normal
service.
Requirements
The installation and commissioning personnel must have a basic knowledge in handling
electronic equipment. The commissioning and maintenance personnel must be well
experienced in using protection equipment, test equipment, protection functions and the
configured functional logics in the protection.
1.1.4
Related documents
Documents related to REC 670
Identity number
Operators manual
Application manual
Buyers guide
13
Section 1
Introduction
SPA and LON signal list for IED 670, ver. 1.1
IEC 61850 Data objects list for IED 670, ver. 1.1
1KHA001027-UEN
1MRS755552
1.1.5
Revision notes
Revision
A
14
Description
No functionality added. Minor changes made in content due to problem reports.
Section 2
Safety information
Section 2
Safety information
About this chapter
This chapter contains safety information. Warning signs are presented which urge the
user to be careful during certain operations in order to avoid injuries to humans or damage
to equipment.
2.1
Warning signs
Strictly follow the company and country safety regulations. Working in
a high voltage environment requires serious approach to avoid human
injuries and damage to equipment.
Always avoid touching the circuitry when covers are removed. The
product contains electronic circuits which can be damaged if exposed to
static electricity (ESD). Lethal high voltage circuits are also exposed
when covers are removed.
Always use suitable isolated test pins when measuring signals in open
circuitry. Potentially lethal voltages and currents are present.
15
Section 2
Safety information
Never remove any screw from a powered IED or from a IED connected
to powered circuitry. Potentially lethal voltages and currents are present.
Take adequate measures to protect the eyes. Never look into the laser
beam.
2.2
Caution signs
Always transport PCBs (modules) using certified conductive bags.
Always handle modules using a conductive wrist strap connected to
protective ground and on a suitable antistatic surface. Electrostatic
discharge (ESD) may cause damage to the module since electronic
circuits are sensitive to this phenomena.
Do not connect live wires to the IED. Internal circuitry may be damaged
Section 2
Safety information
Changing the active setting group will inevitably change the IEDs
operation. Be careful and check regulations before making the change.
2.3
Note signs
The protection assembly is designed for a maximum continuous current
of four times rated value.
17
18
Section 3
Overview
Section 3
Overview
About this chapter
This chapter outlines the installation and commissioning of the IED.
3.1
19
20
Section 4
Unpacking and checking the IED
Section 4
4.1
5.
21
22
Section 5
Installing the IED
Section 5
5.1
Overview
The mechanical and electrical environmental conditions at the installation site must be
within the limits described in the IED technical data. Dusty, damp places, places
susceptible to rapid temperature variations, powerful vibrations and shocks, surge
voltages of high amplitude and fast rise time, strong induced magnetic fields or similar
extreme conditions should be avoided.
Sufficient space must be available in front of and at the rear of the IED to allow access
for maintenance and future modifications. Flush mounted IEDs should be mounted so
that IED modules can be added and replaced without excessive dismantling.
5.2
Dimensions
5.2.1
23
Section 5
Installing the IED
D
F
Figure 1:
xx04000464.vsd
Figure 2:
Case size
(inches)
G
H
xx04000448.vsd
6U, 1/2 x 19
10.47
8.81
7.92
9.96
8.10
7.50
8.02
7.39
6U, 3/4 x 19
10.47
13.23
7.92
9.96
12.52
7.50
12.44
7.39
6U, 1/1 x 19
10.47
17.65
7.92
9.96
16.94
7.50
16.86
18.31
7.39
19.00
5.2.2
24
Section 5
Installing the IED
K
D
xx05000502.vsd
xx05000501.vsd
Figure 3:
Figure 4:
xx05000503.vsd
Figure 5:
6U, 1/2 x 19
265.9
223.7
242.1
255.8
205.7
190.5
203.7
228.6
6U, 3/4 x 19
265.9
336.0
242.1
255.8
318.0
190.5
316.0
228.6
6U, 1/1 x 19
265.9
448.3
242.1
255.8
430.3
190.5
428.3
465.1
228.6
482.6
25
Section 5
Installing the IED
Case size
(inches)
6U, 1/2 x 19
10.47
8.81
9.53
10.07
8.10
7.50
8.02
9.00
6U, 3/4 x 19
10.47
13.23
9.53
10.07
12.52
7.50
12.4
9.00
6U, 1/1 x 19
10.47
17.65
9.53
10.07
16.86
7.50
16.86
18.31
9.00
19.00
5.2.3
A
B
E
D
xx04000465.vsd
Figure 6:
Case size
Tolerance
Flush mounting
Cut-out dimensions (inches)
A
+/0.04
B
+/0.04
6U, 1/2 x 19
8.27
10.01
0.160.39
0.49
6U, 3/4 x 19
12.69
10.01
0.160.39
0.49
6U, 1/1 x 19
17.11
10.01
0.160.39
0.49
E = 188.6 mm without rear protection cover, 229.6 mm with rear protection cover
26
Section 5
Installing the IED
5.2.4
xx06000182.vsd
Figure 7:
C
xx05000505.vsd
Figure 8:
27
Section 5
Installing the IED
5.2.5
Case size
(inches)
Tolerance
A
0.04
B
0.04
C
0.04
D
0.04
E
0.04
F
0.04
G
0.04
6U, 1/2 x
19
8.42
10.21
9.46
7.50
1.35
0.52
0.25 diam
6U, 3/4 x
19
12.85
10.21
13.89
7.50
1.35
0.52
0.25 diam
6U, 1/1 x
19
17.27
10.21
18.31
7.50
1.35
0.52
0.25 diam
A
B
E
en04000471.vsd
Figure 9:
28
Wall mounting
Section 5
Installing the IED
Case size (inches)
6U, 1/2 x 19
10.50
10.52
10.74
15.36
9.57
6U, 3/4 x 19
15.92
14.94
10.74
15.36
9.57
6U, 1/1 x 19
20.31
19.33
10.74
15.36
9.57
5.3
5.3.1
The same mounting kit is used for side-by-side rack mounting and side-by-side flush
mounting.
The mounting kits must be ordered separately when ordering an IED.
They are available as options on the ordering sheet in Accessories for
IED 670, see section 0.
Generally, all the screws included in delivered mounting kits are of Torx type and a
screwdriver of the same type is needed (Tx10, Tx15, Tx20 and Tx25).
29
Section 5
Installing the IED
Figure 10:
Description
A
Flush mounting
C Wall mounting
D Side-by-side rack or flush mounting
5.3.2
Flush mounting
5.3.2.1
Overview
All IED sizes, 1/2 x 19, 3/4 x 19 and 1/1 x 19 and RHGS6 6U 1/4 x 19, cases, can
be flush mounted. Only a single case can be mounted in each cut-out on the cubicle panel,
for class IP54 protection.
The flush mounting kit are utilized for IEDs of sizes: 1/2 x 19, 3/4 x 19 and 1/1 x 19
and are also suitable for mounting of RHGS6, 6U 1/4 x 19 cases.
Flush mounting cannot be used for side-by-side mounted IEDs when IP54
class must be fulfilled. Only IP20 class can be obtained when mounting
two cases side-by-side in one (1) cut-out.
30
Section 5
Installing the IED
5.3.2.2
2
6
5
3
4
xx06000246.vsd
Figure 11:
PosNo
Description
Quantity
Type
Fastener
Groove
0.11x1.76 inches
Panel
Screw
M5x25
Procedure
1.
REC 670 ANSI
31
Section 5
Installing the IED
2.
3.
4.
5.
5.3.3
5.3.3.1
Overview
All IED sizes can be mounted in a standard 19 cubicle rack by using the for each size
suited mounting kit which consists of two mounting angles and fastening screws for the
angles. The mounting angles are reversible which enables mounting of IED size 1/2 x
19 or 3/4 x 19 either to the left or right side of the cubicle.
Please note that the separately ordered rack mounting kit for side-by-side
mounted IEDs, or IEDs together with RHGS cases, is to be selected so
that the total size equals 19.
When mounting the mounting angles, be sure to use screws that follows
the recommended dimensions. Using screws with other dimensions than
the original may damage the PCBs inside the IED.
32
Section 5
Installing the IED
5.3.3.2
1a
1b
xx04000452.vs d
Figure 12:
PosNo
Description
Quantity
Type
1a, 1b
Screw
M4x6
Procedure
1.
2.
3.
Carefully fasten the mounting angles (1a, 1b) to the sides of the IED.
Use the screws (2) supplied in the mounting kit.
Place the IED assembly in the 19 panel.
Fasten the mounting angles with appropriate screws.
33
Section 5
Installing the IED
5.3.4
Wall mounting
5.3.4.1
Overview
All case sizes, 1/2 x 19, 3/4 x 19 and 1/1 x 19, can be wall mounted. It is also possible
to mount the IED on a panel or in a cubicle.
When mounting the side plates, be sure to use screws that follows the
recommended dimensions. Using screws with other dimensions than the
original may damage the PCBs inside the IED.
If fiber cables are bent too much, the signal can be weakened. Wall
mounting is therefore not recommended for communication modules with
fiber connection; Serial SPA/IEC 60870-5-103 and LON communication
module (SLM), Optical Ethernet module (OEM) and Line data
communication module (LDCM).
5.3.4.2
2
1
5
6
Figure 13:
34
xx04000453.vs d
Section 5
Installing the IED
PosNo
Description
Quantity
Type
Bushing
Screw
M4x10
Screw
M6x12 or corresponding
Mounting bar
Screw
M5x8
Side plate
Procedure
1.
2.
3.
4.
5.3.4.3
35
Section 5
Installing the IED
3.2"
(80 mm)
ANSI_en06000135.vsd
Figure 14:
PosNo
Description
Type
Screw
M4x10
Screw
M5x8
Procedure
1.
2.
3.
Remove the inner screws (1), upper and lower on one side.
Remove all three fixing screws (2), on the opposite side, from wall support.
The IED can now be swung out for access to the connectors, after removing any
rear protection.
5.3.5
5.3.5.1
Overview
IED case sizes, 1/2 x 19 or 3/4 x 19 and RHGS cases, can be mounted side-by-side up
to a maximum size of 19. For side-by-side rack mounting, the side-by-side mounting kit
together with the 19 rack panel mounting kit must be used. The mounting kit has to be
ordered separately.
36
Section 5
Installing the IED
When mounting the plates and the angles on the IED, be sure to use screws
that follows the recommended dimensions. Using screws with other
dimensions than the original may damage the PCBs inside the IED.
5.3.5.2
xx04000456.vsd
Figure 15:
PosNo
Description
Quantity
Type
Mounting plate
2, 3
Screw
16
M4x6
Mounting angle
Procedure
1.
2.
3.
4.
5.
6.
7.
37
Section 5
Installing the IED
5.3.5.3
xx06000180.vsd
Figure 16:
IED 670 (1/2 x 19) mounted with a RHGS6 case containing a test switch
module equipped with only a test switch and a RX2 terminal base.
5.3.6
5.3.6.1
Overview
It is not recommended to flush mount side by side mounted cases if IP54 is required. If
your application demands side-by-side flush mounting, the side-by-side mounting details
kit and the 19 panel rack mounting kit must be used. The mounting kit has to be ordered
separately. The maximum size of the panel cut out is 19.
With side-by-side flush mounting installation, only IP class 20 is
obtained. To reach IP class 54, it is recommended to mount the IEDs
separately. For cut out dimensions of separately mounted IEDs, see
section "Flush mounting".
38
Section 5
Installing the IED
When mounting the plates and the angles on the IED, be sure to use screws
that follows the recommended dimensions. Using screws with other
dimensions than the original may damage the PCBs inside the IED.
Please contact factory for special add on plates for mounting FT switches
on the side (for 1/2 19" case) or bottom of the relay.
5.3.6.2
3
4
xx06000181.vsd
Figure 17:
PosNo
Description
Quantity
Type
Mounting plate
2, 3
Screw
16
M4x6
Mounting angle
Procedure
39
Section 5
Installing the IED
1.
2.
3.
4.
5.
6.
7.
8.
9.
5.4
5.4.1
IED connectors
5.4.1.1
Overview
The quantity and designation of connectors depend upon the type and size of the IED.
The rear cover plates are prepared with space for the maximum of HW options for each
case size and the cut-outs that are not in use are covered with a plate from factory.
Table 1:
Module
Description
40
Section 5
Installing the IED
Module
Description
Table 2:
Module
Description
41
Section 5
Installing the IED
5.4.1.2
Figure 18:
PosNo Description
1
The cable between PC and the IED serial communication port shall be a
crossed-over Ethernet cable with RJ45 connectors. If the connection are
made via a hub or switch, a standard Ethernet cable can be used.
5.4.1.3
42
Section 5
Installing the IED
Table 3:
Module
Rear Positions
PSM
X11
X51, X52
SLM
X301:A, B, C, D
IRIG-B 1)
X302
OEM
X311:A, B, C, D
RS485 or LDCM 2) 3)
X312
LDCM 2)
X313
TRM
X401
43
Section 5
Installing the IED
Table 4:
Module
Rear Positions
PSM
X11
X101, X102
SLM
X301:A, B, C, D
IRIG-B or LDCM 1) 2)
X302
LDCM 2)
X303
OEM
X311:A, B, C, D
RS485 or LDCM 2) 3)
X312
LDCM 2)
X313
TRM
X401
44
Section 5
Installing the IED
Table 5:
Module
Rear Positions
PSM
X11
X71, X72
SLM
X301:A, B, C, D
X302
LDCM 2)
X303
OEM
X311:A, B, C, D
RS485 or LDCM 2) 3)
X312
LDCM 2)
X313
LDCM 2)
X322
LDCM 2)
X323
TRM 1
X401
TRM 2
X411
Table 6:
45
Section 5
Installing the IED
Module
Rear Positions
PSM
X11
X161, X162
SLM
X301:A, B, C, D
IRIG-B or LDCM
1,2)
X302
LDCM 2)
X303
OEM
X311:A, B, C, D
RS485 or LDCM 2)
3)
X312
LDCM 2)
X313
TRM
X401
46
Section 5
Installing the IED
Table 7:
Module
Rear Positions
PSM
X11
X131, X132
SLM
X301:A, B, C, D
IRIG-B or LDCM
1,2)
X302
LDCM 2)
X303
OEM
X311:A, B, C, D
RS485 or LDCM 2)
3)
X312
LDCM 2)
X313
LDCM 2)
X322
LDCM 2)
X323
TRM 1
X401
TRM 2
X411
5.4.1.4
Connection diagrams
47
Section 5
Installing the IED
Figure 19:
48
Transfo
rmer
input
module
(TRM)
Current/voltage
configuration
(50/60 Hz)
AI0
1
AI
02
AI
03
AI
04
AI
05
AI
06
AI07
AI08
AI09
AI10
AI11
AI12
12I (1A)
1A
1A
1A
1A
1A
1A
1A
1A
1A
1A
1A
1A
12I (5A)
5A
5A
5A
5A
5A
5A
5A
5A
5A
5A
5A
5A
9I (1A) and 3V
1A
1A
1A
1A
1A
1A
1A
1A
1A
110-22
0V
110-22
0V
110-22
0V
9I (5A) and 3V
5A
5A
5A
5A
5A
5A
5A
5A
5A
110-22
0V
110-22
0V
110-22
0V
1A
1A
1A
1A
1A
5A
5A
5A
5A
110-22
0V
110-22
0V
110-22
0V
7I (1A) and 5V
1A
1A
1A
1A
1A
1A
1A
110-22
0V
110-22
0V
110-22
0V
110-22
0V
110-22
0V
7I (5A) and 5V
5A
5A
5A
5A
5A
5A
5A
110-22
0V
110-22
0V
110-22
0V
110-22
0V
110-22
0V
6I (1A) and 6V
1A
1A
1A
1A
1A
1A
110-22
0V
110-22
0V
110-22
0V
110-22
0V
110-22
0V
110-22
0V
6I (5A) and 6V
5A
5A
5A
5A
5A
5A
110-22
0V
110-22
0V
110-22
0V
110-22
0V
110-22
0V
110-22
0V
6I (1A)
1A
1A
1A
1A
1A
1A
6I (5A)
5A
5A
5A
5A
5A
5A
Section 5
Installing the IED
Figure 21:
Figure 20:
49
Section 5
Installing the IED
Figure 22:
Note to figure 22
1)
Rear communication port SPA/IEC 61850-5-103, ST-connector for glass alt. HFBR Snap-in connector for plastic as ordered
2)
Rear communication port LON, ST connector for glass alt. HFBR Snap-in connector for plastic as ordered
3)
4)
5)
6)
7)
8)
9)
Rear communication port 15-pole female micro D-sub, 1.27 mm (0.050") pitch
10)
50
Section 5
Installing the IED
Figure 24:
Figure 23:
Figure 25:
Binary output module (BOM). Output contacts named XA corresponds to rear position X31, X41,
etc. and output contacts named XB to rear position X32, X42, etc.
51
Section 5
Installing the IED
Figure 26:
52
Section 5
Installing the IED
Figure 27:
Binary in/out module (IOM). Input contacts named XA corresponds to rear position X31, X41, etc. and
output contacts named XB to rear position X32, X42, etc.
5.4.1.5
Connection examples
WARNING! USE EXTREME CAUTION! Dangerously high voltages
might be present on this equipment, especially on the plate with resistors.
Do any maintenance ONLY if the primary object protected with this
equipment is de-energized. If required by national low/standard enclose
the plate with resistors with a protective cover or in a separate box!
53
Section 5
Installing the IED
L1
(A)
L2
(B)
L3
(C)
7
1
CT 1200/1
Star/Wye
Connected
AI01 (I)
2
3
AI02 (I)
4
5
AI03 (I)
6
7
AI04 (I)
10
AI05 (I)
10
11
AI06 (I)
12
IED 670
Protected Object
N
L3 (C)
L2 (B)
L1 (A)
N
L3 (C)
L2 (B)
CT 1200/1
Star/Wye
Connected
L1 (A)
X1
11
12
13
14
Figure 28:
54
L2
(B)
L3
(C)
1
3
4
R3
1
3
4
R2
1
3
R1
4
2
1
2 U
1
R6
2 U
R5
R4
L1
(A)
2 U
Number 1 shows the scheme earthing point. Note that it is of outmost importance to
insure that only one earthing point exist in such scheme.
Number 2 shows the three-phase plate with setting resistors and metrosils.
Number 3 shows the necessary connection for three-phase metrosil set. Shown
connections are applicable for both types of three-phase plate.
Number 4 shows the position of optional test switch for secondary injection into the
high impedance differential relay.
Number 5 shows the necessary connection for setting resistors. Shown connections
are applicable for both types of three-phase plate.
Number 6 shows that the factory made star point on a three-phase setting resistor set
shall be removed for installations with 670 series. This star point is required for
RADHA schemes only!
Number 7 shows how to connect three individual phase currents for high impedance
scheme to three CT inputs in IED 670.
Number 8 shows a TRM module where these current inputs are located. Note that
the CT ratio for high impedance differential protection application must be set as
one! Thus for main CTs with 1A secondary rating the following setting values shall
be entered: CTprim=1A and CTsec=1A; while for main CTs with 5A secondary
Section 5
Installing the IED
rating the following setting values shall be entered: CTprim=5A and CTsec=5A. The
parameter CTStarPoint shall be always left to the default value ToObject.
Number 9 shows three connections made in Signal Matrix Tool (i.e. SMT) which
connect these three current inputs to first three input channels of the preprocessing
function block (10). For high impedance differential protection preprocessing
function block in 3ms task shall be used.
Number 10 shows the preprocessing block which has a task to digitally filter the
connected analogue inputs. Preprocessing block outputs AI1, AI2 and AI3 shall be
connected to three instances of high impedance differential protection function
blocks (e.g. HZD1, HZD2 and HZD3 function blocks in the configuration tool).
Restricted earth fault (REF) protection is a typical application for one-phase high
impedance differential protection. Typical CT connections for high impedance based
REF protection scheme with 670 series are shown in figure CT connections for Restricted
Earth Fault Protection
L1
(A)
L2
(B)
L3
(C)
7
1
CT 1500/5
Star/Wye
Connected
AI01 (I)
2
3
AI02 (I)
4
5
AI03 (I)
6
7
AI04 (I)
8
9
AI05 (I)
10
11
Protected Object
L1
(A)
L2
(B)
AI06 (I)
12
L3
(C)
IED 670
4
1
CT 1500/5
X1
Figure 29:
3
4
R2
R1
en07000194.vsd
2 U
55
Section 5
Installing the IED
5.4.2
Number 1 shows the scheme earthing point. Note that it is of outmost importance to
insure that only one earthing point exist in such scheme.
Number 2 shows the one-phase plate with setting resistor and metrosil.
Number 3 shows the necessary connection for the metrosil. Shown connections are
applicable for both types of one-phase plate. Number 4 shows the position of
optional test switch for secondary injection into the high impedance differential relay.
Number 4 shows the position of optional test switch for secondary injection into the
high impedance differential relay.
Number 5 shows the necessary connection for setting resistor. Shown connections
are applicable for both types of one-phase plate.
Number 6 shows how to connect the REF high impedance scheme to one CT input
in IED 670.
Number 7 shows a TRM module where this current input is located. Note that the
CT ratio for high impedance differential protection application must be set as one!
Thus for main CTs with 1A secondary rating the following setting values shall be
entered: CTprim=1A and CTsec=1A; while for main CTs with 5A secondary rating
the following setting values shall be entered: CTprim=5A and CTsec=5A. The
parameter CTStarPoint shall be always left to the default value ToObject.
Number 8 shows a connection made in Signal Matrix Tool (i.e. SMT) which connects
this current input to first input channel of the preprocessing function block (10). For
high impedance differential protection preprocessing function block in 3ms task shall
be used.
Number 9 shows the preprocessing block which has a task to digitally filter the
connected analogue inputs. Preprocessing block output AI1 shall be connected to
one instances of high impedance differential protection function block (e.g. HZD1
function block in the configuration tool).
Connecting to protectiveground
Connect the grounding screw (pos 1 in figure 30) on the rear of the IED unit to the closest
possible earthing point in the cubicle. Electrical codes and standards require that
protective ground cables are green/yellow conductors with a cross section area of at least
2.5 mm2 (AWG14). There are several protective grounding screws on an IED. The Power
supply module (PSM), Transformer input modules (TRM) and the enclosure are all
separately grounded, see figure 30 below.
The cubicle must be properly connected to the station earthinggrounding system. Use a
conductor with a core cross section area of at least 4 mm2 (AWG 12).
56
Section 5
Installing the IED
3
1
en05000509.vsd
Figure 30:
PosNo Description
1
2
3
Grounding screw to Transformer input module (TRM). (There is one ground connection per TRM)
Use the main protective ground screw (1) for connection to the stations
grounding system. Grounding screws for PSM module (2) and TRM
module (3) must be fully tightened to secure protective ground connection
of these modules.
5.4.3
5.4.4
57
Section 5
Installing the IED
other for an input of 1A. If the CT rated secondary current does not match the TRM input
current rating adjustments can be made in settings depending on the tolerance of the TRM.
5.4.5
Figure 31:
58
Examples of ringlug
terminals
Figure 32:
Exaples of standard
compression connection
terminals
Section 5
Installing the IED
5.4.6
2.
3.
xx02000742.vsd
Figure 33:
A female connector
59
Section 5
Installing the IED
Figure 34:
1
2
xx06000168.vsd
Figure 35:
Cable connectors
PosNo Description
5.4.7
Is ferrule,
60
Section 5
Installing the IED
3
Lc
Cc
Lc
Rx
Tx
IED
Tx
Rx
Sc
Sc
Figure 36:
External
Equipment
en06000190.vsd
PosNo Description
1
Outer shield
Inner shield
5.5
Optical connections
5.5.1
Optical ports X311: A, B (Tx, Rx) and X311: C, D (Tx, Rx) on the OEM module are
used for IEC 61850 communication. Connectors are of ST type. When the optical
61
Section 5
Installing the IED
ethernet module is used, the protection plate for the galvanic connection must not be
removed.
Optical port X301: A, B (Tx, Rx) on the SLM module is used for SPA or IEC
60870-5-103 communication. Connectors are of ST type (glass) or HFBR Snap in
(plastic).
Optical port X301: C, D (Tx, Rx) on the SLM module is used for LON
communication. Connectors are of ST type (glass) or HFBR Snap in (plastic).
Connectors are generally color coded; connect blue or dark grey cable connectors to blue
or dark grey (receive) back-side connectors. Connect black or grey cable connectors to
black or grey (transmit) back-side connectors.
The fiber optical cables are very sensitive to handling. Do not bend too
sharply. The minimum curvature radius is 15 cm for the plastic fiber
cables and 25 cm for the glass fiber cables. If cable straps are used to fix
the cables, apply with loose fit.
Always hold the connector, never the cable, when connecting or
disconnecting optical fibers. Do not twist, pull or bend the fiber. Invisible
damage may increase fiber attenuation thus making communication
impossible.
Please, strictly follow the instructions from the manufacturer for each type
of optical cables/connectors.
5.5.2
62
Section 5
Installing the IED
5.6
5.6.1
The galvanic X.21 line data communication module uses a ABB specific PC*MIP Type
II format.
en07000196.vsd
Figure 37:
63
Section 5
Installing the IED
en07000195.vsd
Figure 38:
1.
2.
3.
Soft ground
To avoid ground loops when the grounds are connected, a soft ground connection for the
IO-ground can be used. This is handled in the ground selection connector.
Three different kinds of grounding principles can be set:
1.
2.
3.
X.21 connector
Table 8:
Pin number
Signal
Shield (ground)
TXD A
Control A
RXD A
Signal timing A
Ground
TXD B
10
Control B
64
Section 5
Installing the IED
11
RXD B
13
Signal timing B
5,7,12,14,15
Not used
5.7
5.7.1
Screw
terminal
X3
Screw
terminal
X1
1
2
1
2
3
4
5
6
RS485
PWB
Backplate
en07000140.vsd
Figure 39:
Pin
The connection plate to the backplate with connectors and screws. This
figure also shows the pin numbering from the component side
Name 2-wire
Name 4-wire
Description
x3:1
soft ground
x3:2
soft ground
x1:1
RS485 +
TX+
Receive/transmit high or
transmit high
x1:2
RS485
TX-
Receive/transmit low or
transmit low
x1:3
Term
T-Term
x1:4
reserved
R-Term
65
Section 5
Installing the IED
Pin
Name 2-wire
Name 4-wire
Description
x1:5
reserved
RX-
Receive low
x1:6
reserved
RX+
Receive high
2wire:
Termination (2-wire):
Termination (4-wire):
The distance between earth points should be < 1200 m (3000 ft), see figure 40 and 41.
Only the outer shielding is connected to the protective earth at the terminal. The inner
and outer shieldings are connected to the protective earth at the external equipment. Use
insulating tape for the inner shield to prevent contact with the protective earth. Make sure
that the terminals are properly earthed with as short connections as possible from the earth
screw, for example to an earthed frame.
The terminal and the external equipment should preferably be connected to the same
battery.
Cc
1 2 3 4 5 6
Cc
1)
2)
1 2 3 4 5 6
X1
X1
IED
External
Equipment (PC)
IED
PG
PG
PG
PG 1) 3)
Figure 40:
en07000141_ansi.vsd
Where:
66
Section 5
Installing the IED
The inner shields shall be connected together (with an isolated terminal block) and only have one
grounding point in the whole system, preferably at the external equipment (PC).
The outer shield shall be connected to Protective Ground (PG) in every cable end i.e. to PG at all
relay terminals and to PG at External equipment (PC). The first terminal will have only one cable
end but all others of course two.
Connect according to installation instructions for the actual equipment, observe the 120 ohms
termination.
The protective ground should be close to the external equipment (< 2m)
Cc
Communication cable
PE
Cc
Cc
1)
1)
1 2 3 4 5 6
2)
1 2 3 4 5 6
X1
X1
IED
External
Equipment (PC)
IED
PG
PG
PG
PG 1) 3)
Figure 41:
en07000142_ansi.vsd
Where:
The inner shields shall be connected together (with an isolated terminal block) and only have one
grounding point in the whole system, preferably at the external equipment (PC).
The outer shield shall be connected to Protective Ground (PG) in every cable end i.e. to PG at all
relay terminals and to PG at External equipment (PC). The first terminal will have only one cable
end but all others of course two.
Connect according to installation instructions for the actual equipment, observe the 120 ohms
termination.
The protective ground should be close to the external equipment (< 2m)
Cc
Communication cable
67
Section 5
Installing the IED
PG
en03000110.vsd
Figure 42:
Where:
1
is cable
is screw
Pair separator
Pair Shield
Drain wire
Conductor
Overall shield
Separator
Jacket
en07000139.vsd
Figure 43:
The EIA standard RS-485 specifies the RS485 network. An informative excerpt is given
in section "Installing the serial communication cable for RS485 SPA/IEC".
68
Section 5
Installing the IED
5.7.2
Normative references
EIA Standard RS-485 - Electrical Characteristics of Generators and Receivers for Balanced Digital
Multipoint Systems
2
Transmission method
Galvanic isolation
2.3.1
Requirements
a) The RS485 specification requires the Signal A and Signal B wires.
b) Each node also requires (5 V) Excitation of the RS485 termination network.
c) Vim - the common mode voltage between any pair of RS485 chips may not exceed 10 V.
d) A physical ground connection between all RS485 circuits will reduce noise.
2.3.2
The termination network below required at each end of each Bus Ph-segment.
Table continued on next page
69
Section 5
Installing the IED
ExV+
Ru = 390 ohm
1/4 W, 2%
Signal B
Rt = 220 ohm
1/4 W, 2%
Signal A
Rd = 390 ohm
1/4 W, 2%
DGND
ExV is supplied by the Node at end of the Bus Segment
en03000112.vsd
Figure 44:
2.3.3
a) Ru
+ 5 V to Signal B
b) Rt
Signal B to Signal A
c) Rd
Signal A to GND
The end node in each Ph-segment applies 5 V bus excitation power to the Termination network via
the Excitation pair (ExV+ and GND) used in the Type 3 Physical layer specification.
5.7.3
70
Shield:
Length:
Maximum 1200 m (3000 ft) from one system earth to the next system earth (includes
length from platform point to system earth on both sides)
Temp:
According to application
Impedance:
120 W
Capacitance:
Example:
Section 5
Installing the IED
5.8
5.8.1
5.8.1.1
Antenna installation
The antenna is mounted on a console for mounting on a horizontal or vertical flat surface
or on an antenna mast.
2
3
xx05000510.vsd
Figure 45:
PosNO Description
GPS antenna
TNC connector
71
Section 5
Installing the IED
Mount the antenna and console clear of flat surfaces such as buildings walls, roofs and
windows to avoid signal reflections. If necessary, protect the antenna from animals and
birds which can affect signal strength. Also protect the antenna against lightning.
Always position the antenna and its console so that a continuous clear line-of-sight
visibility to all directions is obtained, preferably more than 75%. A minimum of 50%
clear line-of-sight visibility is required for un-interrupted operation.
99001046.vsd
Figure 46:
5.8.1.2
Antenna line-of-sight
Electrical installation
Use a 50 ohm coaxial cable with a male TNC connector on the antenna end and a male
SMA connector on the receiver end to connect the antenna to IED 670. Choose cable type
and length so that the total attenuation is max. 26 dB at 1.6 GHz. A suitable antenna cable
can be supplied with the antenna.
The antenna has a female TNC connector to the antenna cable. For location of GPS
module, refer to section "Rear side connectors". Connection diagram for GPS module is
shown in figure 24.
Make sure that the antenna cable is not charged when connected to the
antenna or to the receiver. Discharge the antenna cable by short-circuiting
the end of the antenna cable with some metal device and then connect it
to the antenna. When the antenna is connected to the cable, connect the
72
Section 5
Installing the IED
cable to the receiver. IED 670 must be switched off when the antenna
cable is connected.
73
74
Section 6
Checking the external optical and electrical connections
Section 6
6.1
Overview
The user must check the installation which includes verifying that the IED is connected
to the other parts of the protection system. This is done with the IED and all connected
circuits de-energized.
6.2
Polarity check.
VT circuit voltage measurement (primary injection test).
Grounding check.
Phase relationship
Insulation resistance check
The polarity check verifies the integrity of circuits and the phase relationships. The check
should be performed as close as possible to the IED.
The primary injection test verifies the VT ratio and the wiring all the way through from
the primary system to the IED. Injection must be performed for each phase-to-neutral
REC 670 ANSI
75
Section 6
Checking the external optical and electrical connections
circuit and each phase-to-phase pair. In each case voltages in all phases and neutral are
measured.
6.3
Check of CT circuits
The CTs must be connected in accordance with the circuit diagram provided with the
IED, both with regards to phases and polarity. The following tests shall be performed on
every primary CT connected to the IED 670:
primary injection test to verify the current ratio of the CT, the correct wiring up to
the protection IED and correct phase sequence connection (i.e. A, B, C)
polarity check to prove that the predicted direction of secondary current flow is
correct for a given direction of primary current flow. This is an essential test for the
proper operation of the differential function.
CT secondary loop resistance measurement in order to confirm that the current
transformer secondary loop dc resistance is within specification and that there are
no high resistance joints in the CT winding or wiring.
CT excitation test in order to confirm that the current transformer is of the correct
accuracy rating and that there are no shorted turns in the current transformer
windings. Manufacturer's design curves should be available for the current
transformer in order to compare the actual results.
check the grounding of the individual CT secondary circuits to verify that each threephase set of main CTs is properly connected to the station ground and only at one
electrical point.
Insulation resistance check.
Phase identification of CT shall be made.
Both primary and secondary sides must be disconnected from the line and
IED when plotting the excitation characteristics.
76
Section 6
Checking the external optical and electrical connections
6.4
6.5
6.5.1
6.5.2
6.6
77
78
Section 7
Energizing the IED
Section 7
7.1
Overview
Before the procedures in this chapter can be carried out the connection to external circuitry
must have been checked which ensures that the installation was made correctly.
The user could also check the software version, the IEDs serial number and the installed
modules and their ordering number to ensure that the IED is according to delivery and
ordering specifications. The user must energize the power supply of the IED to start it
up. This could be done in number of ways, from energizing a whole cubicle to energizing
a single IED. The user should reconfigure the IED to activate the hardware modules in
order to enable the self supervision function to detect possible hardware errors. Then the
IED time must be set. The self supervision function (Diagnostics in HMI) should also be
checked to verify that the IED unit operates properly.
7.2
55
90
t (s)
xx04000310.vsd
Figure 47:
79
Section 7
Energizing the IED
3 The main menu is displayed. A steady green light indicates a successful startup.
If the upper row in the window indicates Fail instead of Ready and the green LED
flashes, an internal failure in the IED has been detected. See section 3.3 "Checking the
self supervision function" in this chapter to investigate the fault.
An example of the local HMI with a small LCD is shown in figure 48.
The different parts of the medium size LHMI is shown in figure 48The LHMI, exists in
an IEC version and in an ANSI version. The difference is on the keypad operation buttons
and the yellow LED designation.
80
Section 7
Energizing the IED
81
Section 7
Energizing the IED
Figure 48:
7.3
7.3.1
7.3.2
1.
2.
3.
82
Section 7
Energizing the IED
7.3.3
7.3.3.1
7.3.4
Indicated result
Possible reason
Proposed action
InternFail OK
No problem detected.
None.
InternFail Fail
InternWarning OK
No problem detected.
None.
InternWarning Warning
NUM-modFail OK
No problem detected.
None.
NUM-modFail Fail
NUM-modWarning OK
No problem detected.
None.
NUM-modWarning
Warning
ADC-module OK
No problem detected.
None.
ADC-module Fail
The AD conversion
module has failed.
RealTimeClock OK
No problem detected.
None.
83
Section 7
Energizing the IED
Indicated result
84
Possible reason
Proposed action
RealTimeClock Warning
TimeSync OK
No problem detected.
None.
TimeSync Warning
No time synchronization.
Section 8
Set up PCM 600 communication link per IED
Section 8
8.1
direct point to point link between PCM 600 and the IED 670
indirect link via a station LAN or from remote via a network
85
Section 8
Set up PCM 600 communication link per IED
in this case get a special null-modem cable (Rx, Tx cross-wired) for the direct
link between PCM 600 and IED 670
PCM600
Tx
Tx
Rx
Rx
en05000810.vsd
Figure 49:
Point to point link between IED 670 and PCM 600 using a null-modem
cable
86
Section 8
Set up PCM 600 communication link per IED
1.
2.
3.
4.
5.
Remark
Administrator rights are requested to change the configuration as described above.
en05000812.vsd
Figure 50:
87
Section 8
Set up PCM 600 communication link per IED
en05000813.vsd
Figure 51:
en05000814.vsd
Figure 52:
88
Section 8
Set up PCM 600 communication link per IED
en05000815.vsd
Figure 53:
via the first window of the wizard by including a new IED 670 in a project
by entering the IP-address of the IED 670 in the Object Properties window
89
Section 8
Set up PCM 600 communication link per IED
en05000643.vsd
Figure 54:
en05000811.vsd
Figure 55:
The used alternative depends very much on the time at which the IP-address is available.
Alternative 2 allows a change of the IP-address at any time.
90
Section 9
Establishing connection and verifying the SPA/IEC- communication
Section 9
9.1
Entering settings
If the IED is connected to a monitoring or control system via the rear SPA/IEC port, the
SPA/IEC port has to be set either for SPA or IEC use.
9.1.1
When using the SPA protocol, the rear SPA/IEC port must be set for SPA use.
Procedure
1.
2.
REC 670 ANSI
91
Section 9
Establishing connection and verifying the SPA/IEC- communication
The slave number and baud rate can be found on the local HMI at:
Settings/General settings/Communication/SLM configuration/Rear optical
SPA/IEC port/SPA
Set the same slave number and baud rate as set in the SMS system for the IED.
9.1.2
Procedure
1.
2.
9.2
9.2.1
92
Section 9
Establishing connection and verifying the SPA/IEC- communication
1.
2.
Use a SPA-emulator and send RF to the IED. The answer from the IED should
be IED 670 .
Generate one binary event by activating a function which is configured to an event
block where the used input is set to generate events on SPA. The configuration must
be made with the PCM 600 software. Verify that the event is presented in the SMS/
SCS system.
During the following tests of the different functions in the IED, verify that the events and
indications in the SMS/SCS system are as expected.
9.2.2
Check that the master system time-out for response from the IED, for example after
a setting change, is > 40 seconds.
Use a protocol analyzer and record the communication between the IED and the
IEC master. Check in the protocol analyzers log that the IED answers the master
messages.
Generate one binary event by activating a function which is configured to an event
block where the used input is set to generate events on IEC. The configuration must
be made with the PCM 600 software. Verify that the event is presented in the IEC
master system.
During the following tests of the different functions in the IED, verify that the events and
indications in the IEC master system are as expected.
9.3
glass
plastic
93
Section 9
Establishing connection and verifying the SPA/IEC- communication
Remote monitoring
system with
PCM600
Local monitoring
system with
PCM600
IED670
Teleph
one
modem
IED670
IED670
Teleph
one
modem
Optical to electrical
converter, e.g. SPA-ZC 22
or Fiberdata modem
Remote monitoring
system with
PCM600
en05000672.vsd
Local monitoring
system with
PCM600
IED670
Telephone
modem
IED670
IED670
Telephone
modem
Optical to
electrical
converter, e.g. SPA-ZC 22
or Fiberdata
modem
Figure 56:
en05000672_ansi.vsd
Where:
1
94
A separate minute pulse synchronization from station clock to obtain 1 ms accuracy for time
tagging within the substation might be required.
Section 9
Establishing connection and verifying the SPA/IEC- communication
9.4
Example
Distance 1 km
Glass
Distance 25 m
Plastic
- 11 dB
- 7 dB
4 dB
4 dB
5 dB
1 dB
1 dB
2 dB
1 dB
11 dB
7 dB
95
96
Section 10
Establishing connection and verifying the LON communication
10.1
10.1.1
LON communication
LON communication is normally used in substation automation systems. Optical fiber is
used within the substation as the physical communication link.
The test can only be carried out when the whole communication system is installed. Thus,
the test is a system test and is not dealt with here.
The communication protocol LON (Local Optical Network) is available for IED 670
products as an option.
97
Section 10
Establishing connection and verifying the LON communication
Control Center
Station HSI
MicroSCADA
Gateway
Star coupler
RER 111
IED670
IED670
IED670
en05000663.vsd
Figure 57:
An optical network can be used within the Substation Automation system. This enables
communication with the IED 670s through the LON bus from the operators workplace,
from the control center and also from other IEDs via bay-to-bay horizontal
communication.
The fiber optic LON bus is implemented using either glass core or plastic core fiber optic
cables.
Table 12:
98
Plastic fiber
Cable connector
ST-connector
snap-in connector
Cable diameter
62.5/125 m
1 mm
1000 m
10 m
Wavelength
820-900 nm
660 nm
Transmitted power
Receiver sensitivity
Section 10
Establishing connection and verifying the LON communication
10.2.1
10.2.2
99
Section 10
Establishing connection and verifying the LON communication
These parameters can only be set with the LNT, LON Network Tool.
Table 13:
Parameter
Range
Default
Unit
Parameter description
DomainID
SubnetID*
0 - 255
Step: 1
NodeID*
0 - 127
Step: 1
These parameters can only be set with the LNT, LON Network Tool.
Table 14:
Parameter
Range
Default
Unit
Parameter description
NeuronID*
0 - 12
Not loaded
Location
0-6
No value
100
Section 10
Establishing connection and verifying the LON communication
Table 15:
Parameter
Range
Default
Unit
Parameter description
SessionTmo
1-60
20
RetryTmo
100-10000
2000
ms
Retransmission timeout.Only to be
changed after recommendation from ABB.
IdleAckCycle
1-30
BusyAckTmo
100-5000
300
ms
ErrNackCycle
100-10000
500
ms
LON commands
Command
Command description
ServicePinMsg
10.2
Command with confirmation. Transfers the node adress to the LON network tool.
Example
Distance 1 km
Glass
Distance10 m
Plastic
-11 dB
- 7 dB
4 dB
3 dB
5 dB
2 dB
1.5 dB
2 dB
0.5 dB
11 dB
7 dB
101
102
Section 11
Configuring the IED and changing settings
11.1
Overview
The customer specific values for each setting parameter and a configuration file have to
be available before the IED can be set and configured, if the IED is not delivered with a
configuration.
Use the PCM 600 configuration tool to verify that the IED has the expected configuration.
A new configuration is done with the CAP tool. The binary outputs can be selected from
a signal list where the signals are grouped under their function names. It is also possible
to specify a user-defined name for each input and output signal.
Each function included in the IED has several setting parameters which have to be set in
order to make the IED behave as intended. A factory default value is provided for each
parameter. A setting file can be prepared using the parameter setting tool (PST), which
is available in the PCM 600 package.
All settings can be:
103
Section 11
Configuring the IED and changing settings
11.2
11.3
11.3.1
CT configuration
Parameter description
Rated CT primary current in A
104
Parameter name
CT Prim Input
Range
from -10000 to +10000
Default
0
Section 11
Configuring the IED and changing settings
This parameter defines the primary rated current of the CT. For two set of CTs with ratio
1000/1 and 1000/5 this parameter is set to the same value of 1000 for both CT inputs.
Negative values (i.e. -1000) can be used in order to reverse the direction of the CT current
by software for the differential function. This might be necessary if two sets of CTs have
different neutral (WYE) point locations in relation to the protected busbar. It is
recommended that this parameter is set to zero, for all unused CT inputs.
For main CTs with 2A rated secondary current, it is recommended to connect the
secondary wiring to the 1A input and to set the rated primary current to one half times its
true value. For example, a CT with a primary secondary current ratio of 1000/2A can be
treated as a 500/1A CT.
Take the rated permissive overload values for the current inputs into
consideration.
11.4
11.4.1
105
106
Section 12
Verifying settings by secondary injection
12.1
Overview
IED test requirements:
Calculated settings
Application configuration diagram
Signal matrix (SMT) configuration
Terminal diagram
Technical reference manual
Three-phase test equipment
PCM 600
The setting and configuration of the IED must be completed before the testing can start.
The terminal diagram, available in the Technical reference manual, is a general diagram
of the IED. but note that the same diagram is not always applicable to each specific
delivery (especially for the configuration of all the binary inputs and outputs). Therefore,
before testing, check that the available terminal diagram corresponds to the IED.
The Technical reference manual contains application and functionality summaries,
function blocks, logic diagrams, input and output signals, setting parameters and technical
data sorted per function.
The test equipment should be able to provide a three-phase supply of voltages and
currents. The magnitude of voltage and current as well as the phase angle between voltage
and current must be variable. The voltages and currents from the test equipment must be
obtained from the same source and they must have minimal harmonic content. If the test
equipment cannot indicate the phase angle, a separate phase-angle measuring instrument
is necessary.
107
Section 12
Verifying settings by secondary injection
Prepare the IED for test before testing a particular function. Consider the logic diagram
of the tested protection function when performing the test. All included functions in the
IED are tested according to the corresponding test instructions in this chapter. The
functions can be tested in any order according to user preferences and the test instructions
are therefore presented in alphabetical order. Only the functions that are used (Operation
is set to On) should be tested.
The response from a test can be viewed in different ways:
Please observe the measuring accuracy of the IED, the test equipment and
the angular accuracy for both of them.
Please consider the configured logic from the function block to the output
contacts when measuring the operate time.
12.2
12.2.1
Overview
This section describes how to prepare the IED to verify settings.
If a test switch is included, start preparation by making the necessary connections to the
test switch. This means connecting the test equipment according to a specific and
designated IED terminal diagram. The IED can then be put into test mode in order to
facilitate the test of individual functions and prevent unwanted operation caused by other
functions. The test switch should then be connected to the IED. The user can also verify
the connection and that the analog input signals are measured and recorded correctly by
injecting currents and voltages required by the specific IED. To make testing even more
effective the Protection and Control IED Manager (PCM 600) should be used. The
108
Section 12
Verifying settings by secondary injection
primary tool at your disposal in the PCM 600 apart from the Parameter Setting Tool (PST)
is the Disturbance Handling Tool (DHT). The content of reports generated by the DHT
can be determined by the user which makes it more efficient. For example, the tool may
be configured to only show time tagged events and to exclude analog information and so
on. The disturbance report settings could be checked to ensure that indications are correct.
Functions to test, signals and parameter names can be found in the technical reference
manual.
12.2.2
109
Section 12
Verifying settings by secondary injection
12.2.3
12.2.4
110
Section 12
Verifying settings by secondary injection
IA
IB
IB
IC
IC
IN
IN (I4,I5)
VA
VA
VB
VB
VC
VC
VN
VN
REx 670
IA
VN (U4,U5)
TRIP A
TRIP B
TRIP C
IEC61850
en05000467_ansi.vsd
Figure 58:
12.2.5
4.
111
Section 12
Verifying settings by secondary injection
5.
6.
12.2.6
Measurements/Monitoring/ServiceValues/SVR
Inject an unsymmetrical three-phase current and voltage at rated value in two
phases.
Compare the injected value with the measured value.
The current phasor menu is located in the local-HMI under:
Measurements/Monitoring/CurrentPhasors/CP
The voltage phasor menu is located in the local HMI under:
Measurements/Monitoring/VoltagePhasors/VP
112
Section 12
Verifying settings by secondary injection
12.2.7
Disturbance report
12.2.7.1
Introduction
The following functions are included in the disturbance report function:
Disturbance recorder
Event list
Event recorder
Fault locator (not included in all products)
Trip value recorder
Indications
If the disturbance report is running, then its sub-function are also running and so it is not
possible to only switch these functions off. The disturbance report function is switched
off from PCM 600 or from the local HMI.
12.2.7.2
12.2.7.3
113
Section 12
Verifying settings by secondary injection
A manual trig can be started at any time. This results in a recording of the actual values
from all recorded channels.
12.2.7.4
12.2.8
12.2.9
12.3
12.3.1
114
Section 12
Verifying settings by secondary injection
12.3.1.1
3.
4.
12.3.1.2
Check the configuration of binary inputs that control the selection of the active
setting group.
Browse the ActiveGroup menu to achieve information about the active setting
group.
The ActiveGroup menu is located in the local HMI under:
Test/Function status/Setting groups
Connect the appropriate dc voltage to the corresponding binary input of the IED
and observe the information presented on the HMI display.
The displayed information must always correspond to the activated input.
Check that the corresponding output indicates the active group.
Operating procedures for the PC aided methods of changing the active setting groups
are described in the corresponding PCM documents and instructions for the
operators within the SCS are included in the SCS documentation.
12.4
Differential protection
12.4.1
12.4.1.1
Connect single phase or three phase test set to inject the operating voltage. The
injection shall be on the primary side of the stabilizing resistor.
Note! As the operating voltage is adjusted on the stabilizing resistor and with the
setting of the resistor value in the function this is essential for the measurement of
115
Section 12
Verifying settings by secondary injection
the expected value. Normally a slightly higher operating value is no problem as the
sensitivity is not influenced much.
2. Connect the trip contact to the test set to stop the test set for measurement of trip
times below.
3. Increase the voltage and make note of the operate value TripPickup. This is done
with manual test and without trip of the test set.
4. Reduce the voltage slowly and make note of the reset value. The reset value must
be high for this function.
5. Check the operating time by injecting a voltage corresponding to 1,2 TripPickup>
level Make note of the measured trip time.
6. If required, verify the trip time at another voltage. Normally 2*TripPickup is
selected.
7. If used measure the alarm level operating value. Increase the voltage and make note
of the operate value AlarmPickup. This is done with manual test and without trip
of the test set.
8. Measure the operating time on the alarm output by connecting the stop of the test
set to an output from tAlarm. Inject a voltage 1,2*AlarmPickup and measure the
alarm time.
9. Check that trip and alarm outputs operates according to the configuration logic.
10. Finally check that pickup and alarm information is stored in the Event menu and if
a serial connection to the SA is available verify that the correct and only the required
signals are presented on the local station HMI and on the SCADA system.
Information on how to use the event menu is found in the IED 670 operator's manual.
12.4.1.2
12.5
Current protection
12.5.1
116
Section 12
Verifying settings by secondary injection
Ensure that the maximum continuous current of the IED does not exceed four times its
rated value.
12.5.1.1
12.5.1.2
Inject a phase current into the IED with an initial value below that of the setting.
Set operation mode to 1 out of 3.
Increase the injected current in the Ln phase until the TR_A (TR_B or TR_C) signal
appears.
Switch the fault current off.
Observe the maximum permitted overloading of the current circuits in the IED
Compare the measured operating current with the set value.
Set operation mode to 2 out of 3 and inject current into one of the phases. Checkno operation.
12.5.2
12.5.2.1
Connect the test set for appropriate current injection to the appropriate IED
terminals.
If there is any configuration logic which is used to enable/block any of 4 available
overcurrent steps, make sure that step under test is enabled (i.e. end fault protection).
If 1 of 3 currents for operation is chosen: Connect the injection current to terminals
A and neutral.
117
Section 12
Verifying settings by secondary injection
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
118
If 2 of 3 currents for operation is chosen: Connect the injection current into terminal
A and out from terminal B.
If 3 of 3 currents for operation is chosen: Connect the symmetrical 3 phase injection
current into terminals A, B and C.
Connect the test set for the appropriate three-phase voltage injection to the IED
terminals A, B and C. The protection shall be fed with a symmetrical three phase
voltage.
Set the injected polarizing voltage slightly larger than the set minimum polarizing
voltage (default is 5% of Vn) and set the injection current to lag the appropriate
voltage by an angle of about 80 if forward directional function is selected.
If 1 of 3 currents for operation is chosen: The voltage angle of phase A is the
reference.
If 2 of 3 currents for operation is chosen: The voltage angle of phase A the voltage
angle of B is the reference.
If 3 of 3 currents for operation is chosen: The voltage angle of phase A is the
reference.
If reverse directional function is selected, set the injection current to lag the
polarizing voltage by an angle equal to 80 + 180.
Increase the injected current and note the operated value of the studied step of the
function.
Decrease the current slowly and note the reset value.
If the test has been performed by injection of current in phase A, repeat the test when
injecting current into terminals B and C with polarizing voltage connected to
terminals B respectively C (1 of 3 currents for operation).
If the test has been performed by injection of current in phases A B, repeat the
test when injecting current into terminals B C and C A with appropriate phase
angle of injected currents.
Block higher set stages when testing lower set stages according to below.
Connect a trip output contact to a timer.
Set the injected current to 200% of the operate level of the tested stage, switch on
the current and check the time delay.
For inverse time curves, check the operate time at a current equal to 110% of the
operate current for tmin.
Check that all trip and pickup contacts operate according to the configuration (signal
matrixes)
Reverse the direction of the injected current and check that the protection does not
operate.
If 2 of 3 or 3 of 3 currents for operation is chosen: Check that the function will not
operate with current in one phase only.
Repeat the above-described tests for the higher set stages.
Finally check that pickup and trip information is stored in the event menu.
Section 12
Verifying settings by secondary injection
12.5.2.2
12.5.3
Ensure that the maximum continuous current of the terminal does not exceed four times
its rated value.
12.5.3.1
12.5.3.2
Inject a phase current into the IED with an initial value below that of the setting.
Increase the injected current in the Ln or in the neutral (summated current input)
phase until the TRIP signal appears.
Switch the fault current off.
Observe the maximum permitted overloading of the current circuits in the IED
Compare the measured operating current with the set value.
119
Section 12
Verifying settings by secondary injection
12.5.4
12.5.4.1
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
12.5.4.2
Connect the test set for single current injection to the appropriate IED terminals.
Connect the injection current to terminals A and neutral, or to terminals N and
neutral.
Set the injected polarizing voltage slightly larger than the set minimum polarizing
voltage (default 5 % of Vn) and set the injection current to lag the voltage by an
angle equal to the set reference characteristic angle (AngleRCA) if the forward
directional function is selected.
If reverse directional function is selected, set the injection current to lag the
polarizing voltage by an angle equal to RCA+ 180.
Increase the injected current and note the value at which the studied step of the
function operates.
Decrease the current slowly and note the reset value.
If the test has been performed by injection of current in phase A, repeat the test when
injecting current into terminals B and C with a polarizing voltage connected to
terminals B respectively C.
Block higher set stages when testing lower set stages according to the instructions
that follow.
Connect a trip output contact to a timer.
Set the injected current to 200 % of the operate level of the tested stage, switch on
the current and check the time delay.
For inverse time curves, check the operate time at a current equal to 110 % of the
operate current for tmin.
Check that all trip and start contacts operate according to the configuration (signal
matrixes)
Reverse the direction of the injected current and check that the protection does not
operate.
Check that the protection does not operate when the polarizing voltage is zero.
Repeat the above-described tests for the higher set stages.
Finally, check that pickup and trip information is stored in the event menu.
120
Section 12
Verifying settings by secondary injection
1.
12.5.4.3
In principle this is done as described above, see section "Four step directional
overcurrent protection", but without applying any polarizing voltage.
12.5.5
IN
V_A
V_B
V_C
V1
V2
V3
V_N
V_N
-3V0
TRIP
en07000094_ansi.vsd
Figure 59:
Values of the logical signals belonging to the sensitive directional residual overcurrent
protection are available under menu tree:
Test/Function status/Current protection/SensDirResOvCurr/SDE
REC 670 ANSI
121
Section 12
Verifying settings by secondary injection
12.5.5.1
3.
4.
5.
6.
7.
8.
122
Set the polarizing voltage to 1.2xVNRel> and the phase angle between voltage and
current to the set characteristic angle (RCADir), the current lagging the voltage.
Take setting RCAComp into consideration if not equal to 0.
Measure that the operate current of the set directional element is equal to the
INcosPhi> setting.
The I Dir (I0 cos(Angle)) function activates the BFI_3P and STDIRIN output.
Measure with angles j = RCADir +/- 45 that the measuring element operates when
I0 cos (RCADir - j) =INcosPhi>.
Compare the result with the set value.
Take the set characteristic into consideration, see figure 60 and figure 61.
Measure the operate time of the timer by injecting a current two times the set
INcosPhi> value and the polarizing voltage 1.2xVNRel>.
Compare the results with the set value tDef.
Set the polarizing voltage to xero and increase until VNREL appears. Compare the
voltage with the set value UVNRel>.
Continue to test another function or complete the test by setting the test mode to
off.
Section 12
Verifying settings by secondary injection
3I0
3I0 cos
Operate area
-3V0=Vref
RCA = 0
ROA
en06000650_ansi.vsd
Figure 60:
123
Section 12
Verifying settings by secondary injection
Operate area
-3V0=Vref
Instrument
transformer
angle error
RCA = 0
RCAcomp
Characteristic after
angle compensation
3I0 (prim)
en06000651_ansi.vsd
Figure 61:
Explanation of RCAcomp.
3.
4.
5.
124
Set the polarizing voltage to 1.2xVNRel> and the phase angle between voltage and
current to the set characteristic angle (RCADir), the current lagging the voltage.
Measure that the operate power is equal to the SN> setting for the set directional
element.
Note that for pick-up, both the injected current and voltage must be greater than the
set values INRel> and VNRel> reespectively.
The function activates the BFI_3P and STDIRIN output.
Measure with angles j = RCADir +/- 45 that the measuring element operates when
3I0 3V0 cos (RCADir - j) = SN>.
Compare the result with the set value tDef.
Measure the operate time of the timer by injecting 1.2xVNRel> and a current to get
two times the set SN> operate value.
Section 12
Verifying settings by secondary injection
6.
7.
(Equation 1)
3.
4.
5.
6.
7.
Set the polarizing voltage to 1.2xVNRel> and the phase angle between voltage and
current to the set characteristic angle (RCADir), the current lagging the voltage.
Measure that the operate power is equal to the INDir> setting for the set directional
element.
Note that for pickup, both the injected current and voltage must be greater than the
set values INRel> and VNRel> respectively.
The function activates the BFI_3P and STDIRIN output.
Measure with angles j around RCADir +/- ROADir.
Compare the result with the set values, refer to figure 62 for example characteristic.
Measure the operate time of the timer by injecting a current to get two times the set
S operate value.
Compare the result with the set value tDef.
Continue to test another function or complete the test by setting the test mode to
off.
125
Section 12
Verifying settings by secondary injection
RCA = 0
ROA = 80
Operate area
3I0
80
-3V0
en06000652_ansi.vsd
Figure 62:
Example characteristic
Section 12
Verifying settings by secondary injection
4.
5.
6.
12.5.5.2
12.5.6
12.5.6.1
Quickly set the measured current (fault current) in one phase to about 300% of
IRef (to minimise the trip time), and switch the current off.
Reset the thermal memory under menu tree:
Reset/Reset temperature/ThermalOverload1TimeConst(PTTR,26)/THL
Switch the fault current on and take note of the temperature:
Test/Current protection/ThermOverLoad1TimeConst(PTTR,26)/THL/
TEMP
Check the Alarm time limit AlarmTemp during injection.
Measure the signal ALARM until it appears on the corresponding binary output or
on the local HMI.
Compare the measured temperature with the setting.
Measure the THL protection trip time.
Use the TRIP signal from the configured binary output to stop the timer.
Take the TEMP readings.
Compare with the setting of TripTemp.
Activate the BLOCK binary input.
The signals ALARM, PICKUP and TRIP should disappear.
127
Section 12
Verifying settings by secondary injection
12.5.6.2
12.5.7
12.5.7.1
4.
5.
6.
7.
8.
9.
128
Section 12
Verifying settings by secondary injection
10. Connect a trip output contact to the timer and monitor the output of contacts
Alarm1 and Alarm2 to digital inputs in test equipment.
Read the heat content in the thermal protection from the local HMI and wait until
the content is zero.
11. Switch on the injection current and check that Alarm1 and Alarm2 contacts operate
at the set percentage level and that the operate time for tripping is in accordance
with the set Time Constant 1 (Tau 1).
With setting Itr = 101% IBase1 and injection current 1.50 x IBase1, the trip time
from zero content in the memory shall be 0.60 x Time Constant 1 (Tau1).
12. Check that all trip and alarm contacts operate according to the configuration logic.
13. Switch off the injection current and check from the service menu readings of thermal
status and LOCKOUT that the lockout resets at the set percentage of heat content.
14. Activate the digital input for cooling input signal to switch over to base current
IBase2.
Wait 5 minutes to empty the thermal memory and set Time Constant 2 (Tau2) in
accordance with the setting plan.
15. Test with injection current 1.50 x IBase2 the thermal alarm level, the operate time
for tripping and the lockout reset in the same way as described for stage IBase1.
16. Finally check that pickup and trip information is stored in the Event menu
Information on how to use the event menu is found in the RET 670 operators manual.
12.5.7.2
12.5.8
129
Section 12
Verifying settings by secondary injection
Calculated settings
Valid configuration diagram for the IED
Valid terminal diagram for the IED
Technical reference manual
Three-phase test equipment
To verify the settings in the most common back-up trip mode 1 out of 3 it is sufficient
to test phase-to-ground faults.
At mode 2 out of 4 the Phase current setting, Pickup_PH can be checked by single
phase injection where the return current is connected to the summated current input. The
value of residual (EF) current IN set lower than Pickup_PH is easiest checked in backup trip mode 1 out of 4.
12.5.8.1
130
Apply the fault condition, including initiation of BFP, with a current below set
Pickup_PH.
Repeat the fault condition and increase the current in steps until a trip occurs.
Compare the result with the set Pickup_PH.
Disconnect AC and initiate input signals.
Note: If No IPickup check or Retrip off is set, only back-up trip can be used to
check set Pickup_PH.
Section 12
Verifying settings by secondary injection
12.5.8.2
Checking the residual (GF) current operate value Pickup_N set below
Pickup_PH
The check of low set Pickup_N current level is best made in FunciontMode= Current
and BuTripMode= 1 out of 4.
Procedure
1.
2.
3.
4.
12.5.8.3
Apply the fault condition, including initiation of BFP, with a current just below set
Pickup_N.
Repeat the fault condition and increase the current in steps until trip appears.
Compare the result with the set Pickup_N.
Disconnect AC and initiate input signals.
3.
12.5.8.4
Apply the fault condition, including initiation of BFP, well above the set current
value. Measure time from Start of BFP.
Check the re-trip t1 and back-up trip times t2 and t3
In applicable cases the back-up trip for multi-phase start t2MPh and back-up trip
2, t2 + t3 can also be checked. For check of t2MPh a two-phase or three-phase
initiation shall be applied.
Disconnect AC and initiate input signals.
131
Section 12
Verifying settings by secondary injection
Checking the re-trip with current check, RetripMode = I>RetripMode =
Current check
Procedure
1.
2.
3.
4.
5.
6.
12.5.8.5
Use the actual tripping modes. The case below applies to re-trip with current check.
Procedure
1.
2.
3.
4.
132
Apply the fault condition, including initiation of BFP, with phase current well above
set value IP
Arrange switching the current off, with a margin before back-up trip time, t2. It may
be made at issue of re-trip command.
Check that re-trip is achieved, if selected, but no back-up trip.
Disconnect AC and initiation input signals.
Section 12
Verifying settings by secondary injection
The normal mode BuTripMode = 1 out of 3 should have been verified in the tests above.
In applicable cases the modes 1 out of 4 and 2 out of 4 can be checked. Choose the
mode below, which corresponds to the actual case.
The EF current setting Pickup_N may be equal to or below phase current setting
Pickup_PH.
Procedure
1.
2.
3.
4.
5.
6.
12.5.8.6
133
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
12.5.8.7
Repeat the check of back-up trip time. Disconnect current and initiation input
signals.
Activate the input 52FAIL. The output CBALARM (CB faulty alarm) should appear
after set time tCBAlarm. Keep the input activated.
Apply the fault condition, including initiation of BFP, with current above set current
value.
Verify that back-up trip is obtained without intentional delay, e.g. within 20 ms from
application of initiation.
Disconnect injected AC and input signals.
12.5.8.8
Checking the case with fault current above set value IP>Pickup_PH
The operation shall be as in FunctionMode = Current.
Procedure
134
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
The case shall simulate a case where the fault current is very low and operation will
depend on CB position signal from CB auxiliary contact. It is suggested that re-trip
without current check is used; setting Retrip = No I>Retrip = No Current check.
Procedure
1.
2.
3.
4.
5.
6.
7.
8.
9.
12.5.8.9
12.5.9
135
Section 12
Verifying settings by secondary injection
12.5.9.1
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
12.5.9.2
Check that the input logical signals BLOCK and ENABLE are logical zero and note
on the local HMI that the TRIP logical signal is equal to the logical 0.
Logical signals for STUB protection are available under menu tree:
Measurements/Current protection/Stub/STB
Activate the ENABLE binary input.
STUB protection settings are available under menu tree:
Settings/Setting group N/Current protection/Stub/STB
Quickly set the measured current (fault current) in one phase to about 110% of the
set operating current, and switch the current off with the switch.
Observe the maximum permitted overloading of the current circuits in the IED.
Switch the fault current on and measure the operating time of the STUB protection.
Use the TRIP signal from the configured binary output to stop the timer. The
operation should be instantaneously.
Activate the BLOCK binary input.
Switch on the fault current (110% of the setting).
No TRIP signal should appear.
Switch off the fault current.
Quickly set the measured current (fault current) in same phase to about 90% of the
set operating current, and switch the current off with the switch.
Switch the fault current on.
No TRIP signal should appear.
Switch the fault current off.
Reset the ENABLE binary input.
Switch the fault current on.
No TRIP signal should appear.
Switch the fault current off.
12.5.10
136
Section 12
Verifying settings by secondary injection
12.5.10.1
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
137
Section 12
Verifying settings by secondary injection
12.5.10.2
12.5.11
12.5.11.1
Connect the test set for injection of voltage and current corresponding to the measure
mode to be used in the application. If a three phase test set is available this could
be used for all the measure modes. If a single phase current/voltage test set is
available the test set should be connected to a selected input for one phase current
and voltage.
Set value: measureMode
A, B, C
S = V A I A* + VB I B* + VC I C *
Arone
S = V AB I A* - VBC IC *
PosSeq
S = 3 VPosSeq I PosSeq*
AB
S = VAB ( I A* - I B* )
Table continued on next page
138
Section 12
Verifying settings by secondary injection
Set value: measureMode
BC
S = VBC ( I B* - IC * )
CA
S = VCA ( I C * - I A* )
A
S = 3 VA I A*
B
S = 3 VB I B*
C
S = 3 VC I C *
2.
3.
4.
5.
6.
7.
12.5.11.2
Adjust the injected current and voltage to the set rated values IBase and VBase
(converted to secondary current and voltage). The angle between the injected current
and voltage shall be set equal to the set direction Angle1 (equal to 0 for low forward
power protection). Check that the monitored active power is equal to 100% of rated
power and that the reactive power is equal to 0% of rated power.
Change the angle between the injected current and voltage to Angle1 + 90. Check
that the monitored active power is equal to 0% of rated power and that the reactive
power is equal to 100% of rated power.
Change the angle between the injected current and voltage back to 0. Decrease the
current slowly until the START1 signal is activated. Check the injected power and
compare to the set value Power1.
Increase the current to IBase.
Switch the current off and measure the lime for activation of TRIP1.
If a second step is used: repeat points 2 6 for the second step.
139
Section 12
Verifying settings by secondary injection
12.5.12
12.5.12.1
Connect the test set for injection of voltage and current corresponding to the measure
mode to be used in the application. If a three phase test set is available this could
be used for all the measure modes. If a single phase current/voltage test set is
available the test set should be connected to a selected input for one phase current
and voltage.
Set value: measureMode
A, B, C
S = V A I A* + VB I B* + VC I C *
Arone
S = V AB I A* - VBC IC *
PosSeq
S = 3 VPosSeq I PosSeq*
AB
S = VAB ( I A* - I B* )
BC
S = VBC ( I B* - IC * )
CA
S = VCA ( I C * - I A* )
Table continued on next page
140
Section 12
Verifying settings by secondary injection
Set value: measureMode
S = 3 VA I A*
B
S = 3 VB I B*
C
S = 3 VC I C *
2.
3.
4.
5.
6.
7.
12.5.12.2
Adjust the injected current and voltage to the set rated values IBase and VBase
(converted to secondary current and voltage). The angle between the injected current
and voltage shall be set equal to the set direction Angle1 (equal to 180 for reverse
power protection). Check that the monitored active power is equal to 100% of rated
power and that the reactive power is equal to 0% of rated power.
Change the angle between the injected current and voltage to Angle1 + 90. Check
that the monitored active power is equal to 0% of rated power and that the reactive
power is equal to 100% of rated power.
Change the angle between the injected current and voltage back to Angle1 value.
Increase the current slowly from 0 until the START1 signal is activated. Check the
injected power and compare to the set value Power1.
Increase the current to IBase and switch the current off.
Switch the current on and measure the lime for activation of TRIP1.
If a second step is used: repeat points 2 6 for the second step.
12.5.13
12.5.13.1
141
Section 12
Verifying settings by secondary injection
1.
Check that the input logical signal BRC-BLOCK is logical zero and note on the
local HMI that the BRC-TRIP logical signal is equal to the logical 0.
Values of the logical output signals belonging to the broken conductor check
function are available under menu tree:
Test/Function Status/Current protection/ Broken Cond Check
2. Set the measured current (fault current) in one phase to about 110% of the set
operating current (IP>).
Observe the maximum permitted overloading of the current circuits in the terminal.
3. Switch on the fault current and measure the operating time of the BRC protection.
Use the BRC--TRIP signal from the configured binary output to stop the timer.
4. Compare the measured time with the set value tOper.
5. Activate the BRC--BLOCK binary input.
6. Switch on the fault current (110% of the setting) and wait longer than the set value
tOper.
No BRC--TRIP signal should appear.
7. Switch off the fault current.
8. Set the measured current (fault current) in same phase to about 90% of the set
operating current. Switch off the current.
9. Switch on the fault current and wait longer than the set value tOper.
No BRC--TRIP signal should appear.
10. Switch off the fault current.
12.5.13.2
12.6
Voltage protection
12.6.1
12.6.1.1
142
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
6.
7.
8.
Make sure that the IED settings are appropriate, especially the Pickup-value, the
definite time delay and the 1 out of 3 operation mode.
Supply the terminal with three-phase voltages at their rated values.
Slowly decrease the voltage in one of the phases, until the PICKUP signal appears.
Note the operate value and compare it with the set value.
Increase the measured voltage to rated load conditions.
Make sure that the PICKUP signal resets.
Instantaneously decrease the voltage in one-phase to a value about 20% lower than
the measured operate value.
Measure the time delay for the TRIP signal, and compare it with the set value.
Extended testing
Procedure
1.
2.
3.
4.
5.
12.6.1.2
12.6.2
12.6.2.1
143
Section 12
Verifying settings by secondary injection
5.
6.
7.
12.6.2.2
Set and apply about 20% higher voltage than the measured operate value for one
phase.
Measure the time delay for the TRST1 signal and compare it with the set value.
Repeat the test for step 2.
12.6.3
12.6.3.1
12.6.3.2
Apply the single phase voltage either to a single phase voltage input or to a residual
voltage input with the pickup value below the set value Pickup1
Slowly increase the value until PU_ST1 appears
Note the operate value and compare it with the set value.
Switch the applied voltage off.
Set and apply about 20% higher voltage than the measured operate value for one
phase.
Measure the time delay for the TRST1 signal and compare it with the set value.
Repeat the test for step 2.
12.6.4
144
Section 12
Verifying settings by secondary injection
12.6.4.1
Check of V1Low
Procedure
Connect voltages to the IED according to valid connection diagram and figure 63.
Apply voltage higher than the highest set value of VDTrip, V1Low and V2Low to
the V1 three phase inputs and to one phase of the V2 inputs according to
figure 63.
The voltage differential PICKUP signal is set.
VA
VA
VB
VB
VC
VC
VN
VN
VA
VB
VC
IED 670
1.
2.
en07000106_ansi.vsd
Figure 63:
Connection of the test set to the IED for test of V1 block level
where:
3.
4.
5.
Decrease slowly the voltage in phase VL1 of the test set until the PICKUP signal
resets.
Check V1 blocking level by comparing the voltage level at reset with the set
undervoltage blocking V1Low.
Repeat steps 2 to 4 to check V1Low for the other phases.
145
Section 12
Verifying settings by secondary injection
Check ofV2Low
Procedure
Connect voltages to the IED according to valid connection diagram and figure 64.
VA
VA
VB
VB
VC
VC
VN
VN
VA
VB
VC
IED 670
1.
en07000107_ansi.vsd
Figure 64:
Connection of the test set to the IED for test of V2 block level
where:
2.
3.
4.
146
Apply voltage higher than the highest set value of VDTrip, V1Low and V2Low to
the V1 three phase inputs and to one phase of the V2 inputs according to
figure 64.
The voltage differential PICKUP signal is set.
Decrease slowly the voltage in phase VL3 of the test set until the PICKUP signal
resets.
Check V2 blocking level by comparing the voltage level at reset with the set
undervoltage blocking V2Low.
Section 12
Verifying settings by secondary injection
12.6.4.2
VA
VA
VB
VB
VC
VC
VN
VN
VA
VB
VC
IED 670
1.
en07000108_ansi.vsd
Figure 65:
Connection of the test set to the IED for test of alarm levels, trip
levels and trip timer
where:
2.
3.
4.
Check the alarm operation level by comparing the differential voltage level at
ALARM with the set alarm level VDAlarm.
147
Section 12
Verifying settings by secondary injection
5.
6.
7.
12.6.4.3
12.6.4.4
Connect voltages to the IED according to valid connection diagram and figure 65.
Set Vn (rated voltage) to the V1 inputs and increase V2 voltage until differential
voltage is 1.5 x operating level (UDTrip).
Switch on the test set. Measure the time from activation of the PICKUP signal until
TRIP signal is activated.
Check the measured time by comparing it to the set trip time tTrip.
Increase the voltage until PICKUP signal resets. Measure the time from reset of
PICKUP signal to reset of TRIP signal.
Check the measured time by comparing it to the set trip reset time tReset.
With the protection in test mode, view the the differential voltage service values in
each phase.
LHMI path to the differential voltage values is:
Test/Function status/Voltage protection/VoltageDiff(PTOV,60)/VDCn
The IED voltage inputs should be connected to the VTs according
to valid connection diagram.
2.
3.
4.
5.
148
Section 12
Verifying settings by secondary injection
12.6.4.5
12.6.5
12.6.5.1
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Check that the input logical signals LOV-BLOCK, LOV-CBOPEN and LOVVTSU are logical zero.
Supply a three phase rated voltage in all three phases and note on the local HMI that
the LOV-TRIP logical signal is equal to the logical 0.
Logical output signals for loss of voltage check protection are available under menu
tree:
Test / Function status/Voltage Protection/ Loss of Voltage
Switch off the voltage in all three phases.
After set ttrip time a LOV-TRIP signal appears on the corresponding binary output
or on the local HMI. Note that LOV--TRIP at this time is a pulse signal, duration
should be according to set tpulse.
Inject the measured voltages to their rated values for at least set tRestore time.
Activate the LOV-CBOPEN binary input.
Simultaneously disconnect all the three phase voltages from the IED.
No LOV-TRIP signal should appear.
Inject the measured voltages to their rated values for at least set tRestore time.
Activate the LOV-VTSU binary input.
Simultaneously disconnect all the three phase voltages from the tRestore.
No LOV-TRIP signal should appear.
Reset the LOV-VTSU binary input.
Inject the measured voltages to their rated values for at least set tRestore time.
Activate the LOV-BLOCK binary input.
Simultaneously disconnect all the three phase voltages from the terminal.
No LOV-TRIP signal should appear.
Reset the LOV-BLOCK binary input.
Continue to test another function or complete the test by setting the test mode to
off.
149
Section 12
Verifying settings by secondary injection
12.6.5.2
12.7
Frequency protection
12.7.1
12.7.1.1
Make sure that the IED settings are appropriate, especially the Pickup-value and the
definite time delay.
Supply the terminal with three-phase voltages at their rated values.
Slowly decrease the frequency of the applied voltage, until the PICKUP signal
appears.
Note the operate value and compare it with the set value.
Increase the frequency until rated operating levels are reached.
Make sure that the PICKUP signal resets.
Instantaneously decrease the frequency of the applied voltage to a value about 20%
lower than the operate value.
Measure the time delay of the TRIP signal, and compare it with the set value.
Extended testing
Procedure
1.
2.
150
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
6.
7.
12.7.1.2
Make sure that the IED settings are appropriate, especially the PickupFrequency,
IntBlkPuVal, and the tTrip.
Supply the terminal with three-phase voltages at rated values.
Slowly decrease the magnitude of the applied voltage, until the BLKDMAGN signal
appears.
Note the voltage magnitude value and compare it with the set value, IntBlkPuVal.
Slowly decrease the frequency of the applied voltage, to a value below
PUFrequency.
Make sure that the PICKUP signal not appears.
Wait for a time corresponding to tTrip, and make sure that the TRIP signal not
appears.
12.7.2
12.7.2.1
Make sure that you have appropriate settings in the terminal, especially the
Pickup-value and the definite time delay.
Supply the terminal with three-phase voltages at their rated values.
Slowly increase the frequency of the applied voltage, until the PICKUP signal
appears.
Note the operate value and compare it with the set value.
Decrease the frequency to rated operating conditions.
Make sure that the PICKUP signal resets.
Instantaneously increase the frequency of the applied voltage to a value about 20%
higher than the operate value.
Measure the time delay for the TRIP signal, and compare it with the set value.
151
Section 12
Verifying settings by secondary injection
Extended testing
Procedure
1.
12.7.2.2
Make sure that you have appropriate settings in the terminal, especially the
PUFrequency, IntBlkPuVal, and the tTrip.
Supply the terminal with three-phase voltages at their rated values.
Slowly decrease the magnitude of the applied voltage, until the BLKDMAGN signal
appears.
Note the voltage magnitude value and compare it with the set value, IntBlkPuVal.
Slowly increase the frequency of the applied voltage, to a value above
PUFrequency.
Make sure that the PICKUP signal not appears.
Wait for a time corresponding to tTrip, and make sure that the TRIP signal does not
appears.
12.7.3
12.7.3.1
152
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
6.
7.
8.
Make sure that you have appropriate settings in the terminal, especially the -value
and the definite time delay. Set PUFreqgrad, to a rather small negative value.
Supply the terminal with three-phase voltages at their rated values.
Slowly decrease the frequency of the applied voltage, with an increasing rate-ofchange that finally exceeds the setting of PUFreqgrad, and check that the
PICKUP signal appears.
Note the operate value and compare it with the set value.
Increase the frequency to rated operating conditions, and zero rate-of-change.
Make sure that the PICKUP signal resets.
Instantaneously decrease the frequency of the applied voltage to a value about 20%
lower than the nominal value.
Measure the time delay for the TRIP signal, and compare it with the set value.
Extended testing
Procedure
1.
2.
3.
12.7.3.2
12.8
Multipurpose protection
12.8.1
153
Section 12
Verifying settings by secondary injection
between maximum and minimum quantities (unbalance) can be derived and then used in
the function.
Due to the versatile possibilities of the GF itself but also the possibilities of logic
combinations in the CAP-configuration of outputs from more then one GF function block
it is hardly possible to define a fully covering general commissioning test.
12.8.1.1
12.8.1.2
154
Section 12
Verifying settings by secondary injection
The current restraining value has also to be measured or calculated and the influence
on the operation has to be calculated when the testing of the operate value is done.
12.8.1.3
3.
4.
12.8.1.4
Connect the test set for injection of 3-phase currents and 3-phase voltages to the
appropriate current and voltage terminals of IED 670.
Inject current(s) and voltage(s) in a way that relevant measured (according to setting
parameter CurrentInput and VoltageInput) currents and voltages are created from
the test set.
Overall check in principal as above (non-directional overcurrent feature)
Operate value measurement
The relevant voltage restraining value (according to setting parameter
VoltageInput) has also to be injected from the test set and the influence on the operate
value has to be calculated when the testing the operate value is done.
Operate time measurement
Definite times may be tested as above (non-directional overcurrent feature). For
inverse time characteristics the pickup value (to which the overcurrent ratio has to
be calculated) is the actual pickup value as got with actual restraining from the
voltage restraining quantity.
Connect the test set for injection of 3-phase currents and 3-phase voltages to the
appropriate current and voltage terminals of IED 670.
Inject current(s) and voltage(s) in a way that relevant measured (according to setting
parameter CurrentInput and VoltageInput) currents and voltages are created from
the test set.
Set the relevant measuring quantity current to lag or lead (lag for negative rca angle
and lead for positive rca angle) the relevant polarizing quantity voltage by an angle
155
Section 12
Verifying settings by secondary injection
4.
5.
6.
12.8.1.5
equal to the set relay characteristic angle (rca-dir) when forward directional feature
is selected and the CTstarpoint configuration parameter is set to ToObject.
If reverse directional feature is selected or CTstarpoint configuration parameter is
set to FromObject the angle between current and polarizing voltage shall be set
equal to rca-dir+180.
Overall check in principal as above (non-directional overcurrent feature)
Reverse the direction of the injection current and check that the protection does not
operate.
Check with low polarization voltage that the feature becomes non-directional,
blocked or with memory according to the setting.
Over/Undervoltage feature
Procedure
1.
2.
3.
12.8.1.6
Connect the test set for injection 3-phase voltages to the appropriate voltage
terminals of IED 670.
Inject voltage(s) in a way that relevant measured (according to setting parameter
VoltageInput) voltages are created from the test set.
Overall check in principal as above (non-directional overcurrent feature) and
correspondingly for the undervoltage feature.
12.9
12.9.1
156
Section 12
Verifying settings by secondary injection
12.9.1.1
12.9.1.2
Check the input circuits and the operate value of the IMinOp current level detector
by injecting current, one phase at a time
Check the phase current blocking function for all three phases by injection current,
one phase at a time. The output signals shall reset with a delay of 1 second when
the current exceeds 1.5*IBase
Inject a current 0.9*IBase to phase A and a current 0.15*IBase to the reference
current input I5
Decrease slowly the current to the reference current input and check that blocking
is obtained when the current is about 0.1*IBase
12.9.2
12.9.2.1
Simulate normal operating conditions with the three-phase currents in phase with
their corresponding phase voltages and with all of them equal to their rated values.
Connect the nominal dc voltage to the 89bS binary input.
157
Section 12
Verifying settings by secondary injection
3.
4.
5.
6.
7.
The BLKV and BLKZ signals should appear without any time delay.
No undervoltage-dependent functions must operate.
There should be no change in the high status of the output signals BLKV and
BLKZ.
The signal 3PH will appear.
8.
12.9.2.2
Simulate normal operating conditions with the three-phase currents in phase with
their corresponding phase voltages and with all of them equal to their rated values.
Slowly decrease the measured voltage in one phase until the BLKV signal appears.
Record the measured voltage and calculate the corresponding negative-sequence
voltage according to the equation.
Observe that the voltages in the equation are phasors:
2
3 V2 = VA + a VB + a VC
(Equation 20)
Where:
V A VB and VC
158
Section 12
Verifying settings by secondary injection
a = 1e
4.
12.9.2.3
2p
j ----------3
3
= 0, 5 + j ------2
Compare the result with the set value (consider that the set value 3V2PU is in
percentage of the base voltage U1b) of the negative-sequence operating voltage.
Simulate normal operating conditions with the three-phase currents in phase with
their corresponding phase voltages and with all of them equal to their rated values.
Slowly decrease the measured voltage in one phase until the BLKV signal appears.
Record the measured voltage and calculate the corresponding zero-sequence voltage
according to the equation.
Observe that the voltages in the equation are phasors.
3 V0 = V A + VB + VC
(Equation 23)
Where:
V A VB and VC
4.
12.9.2.4
Compare the result with the set value (consider that the set value 3V0Pickup is in
percentage of the base voltage of the zero-sequence operating voltage.
Simulate normal operating conditions with the three-phase currents in phase with
their corresponding phase voltages and with all of them equal to their rated values.
Connect the nominal dc voltage to the 52a binary input.
Change the voltages and currents in all three phases simultaneously.
The voltage change should be greater then setDVPU and the current change should
be less than the set DIPU.
159
Section 12
Verifying settings by secondary injection
The BLKV and BLKZ signals appear without any time delay. The BLKZ
signal will be activated , only if the internal deadline detection is not activated
at the same time.
3PH should appear after 5 seconds, if the remaining voltage levels are lower
than the set VDLDPU of the DLD function.
12.9.2.5
12.10
Control
12.10.1
160
AutoEnerg = On/Off/DLLB/DBLL/Both
ManEnerg = Off
Operation = Off, On
Activation of the voltage selection function if applicable
Section 12
Verifying settings by secondary injection
The tests explained in the test procedures below describe the settings, which can be used
as references during testing before the final settings are specified. After testing, restore
the equipment to the normal or desired settings.
A secondary injection test set with the possibility to alter the phase angle by regulation
of the resistive and reactive components is needed. The test set must also be able to
generate different frequencies on different outputs.
The description below applies for a system with a nominal frequency of
60 Hz but can be directly transferred to 50 Hz. The synchronism-check
function can be set to use different phases, phase to earth or phase to phase.
Use the set voltages instead of what is indicated below.
Figure 66 shows the general test connection principle, which can be used during testing.
This description describes the test of the version intended for one bay.
Figure 67 shows the general test connection for a breaker-and-a-half diameter with onephase voltage connected to the line side.
REx670
Test
equipment
V-Bus
V-Bus
VMeasure
Ph/N
Ph/Ph
V-Line
VA
VB
VC
VN
Input Phase
A,B,C
AB,BC,CA
en05000480_ansi.vsd
Figure 66:
161
Section 12
Verifying settings by secondary injection
REx670
Test
equipment
V-Bus1
V3PBB1
V-Bus2
V3PBB2
V-Line2
V3PL2
N
V-Line1
V3PL1
VMeasure
Ph/N
Ph/Ph
en05000481_ansi.vsd
Figure 67:
12.10.1.1
General test connection for a breaker-and-a-half diameter with onephase voltage connected to the line side
V3PBB1
V3PBB2
V3PL2
The settings in table 19 shows typical values. The final settings should be used during
testing.
Table 19:
Parameter
Setting
Operation
Off
VBase
SelPhaseBus1
VB
SelPhaseBus2
VB
162
Section 12
Verifying settings by secondary injection
Parameter
Setting
SelPhaseLine1
VB
SelPhaseLine2
VB
PhaseShift
0 degrees
1.00
CBConfig
SingleBus
AutoEnerg
Off
ManEnerg
Off
ManEnergDBDL
Off
VLiveBusEnerg
80% VBase
VLiveLineEnerg
80% VBase
VDeadLineEnerg
30% VBase
VMaxEnerg
125% VBase
OperationSynch
On
VLiveBusSynch
70% VBase
VLiveLineSynch
70% VBase
VDiffSynch
15%VBase
FreqDiffMin
0.01 Hz
FreqDiffMax
0.22 Hz
tMaxSynch
600 sec
OperationSC
On
PhaseDiffM
35 degrees
PhaseDiffA
35 degrees
FreqDiffM
0.01 Hz
FreqDiffA
0.01 Hz
VDiff
15% VBase
tAutoEnerg
0.1 s
tManEnerg
0.1 s
ShortPulse
Off
tClosePulse
0.20 s
tBreaker
0.08 s
VTConnection
Line
tSyncM
0s
tSyncA
0s
FreqDiffBlock
Off
163
Section 12
Verifying settings by secondary injection
Testing the frequency difference
The frequency difference is in the example set at 0.20 Hz on the local HMI, and the test
should verify that operation is achieved when the FreqDiffSynch frequency difference is
lower than 0.20 Hz. The test procedure below will depend on the settings used.
Procedure
1.
2.
3.
4.
5.
12.10.1.2
Apply voltages V-line = 100% VBase, f-line=60.0 Hz and V-Bus = 100% VBase,
f-bus = 60.2 Hz.
Check that a closing pulse is submitted and at closing angle less than 2 degrees from
phase equality. Modern test sets will evaluate this automatically.
Repeat with V-Bus = 80% VBase, f-bus=60.25 Hz to verify that the function does
not operate when freqency difference is above limit.
Repeat with different frequency differences e.g. 100 mH with f-bus nominal and
line leading and for example 20 mHz (or just above fSynMin) to verify that
independent of frequency difference the closing pulse occurs within 2 degrees.
Verify that the closing command is not issued when the frequency difference is less
than the set value fSynMin.
V-bus
Voltage inputs
SYN2
V-line
VA
Activate SYN1_FD1CLD
VB
Activate SYN1_CB2CLD
V4
V-bus
V5
V-line
UL2
Activate SYN2_FD2CLD
V4
Activate SYN2_CB3CLD
VA
Activate SYN2_FD1CLD
V5
Activate SYN2_CB1CLD
VA
Activate SYN3_CB2CLD
V-bus
SYN3
V-line
164
Section 12
Verifying settings by secondary injection
V-bus
VB
Activate SYN3_FD2CLD
V5
V4
Set the voltage difference at 15% VBase on the HMI, and the test should check that
operation is achieved when the voltage difference VDiff is lower than 15% VBase.
The settings used in the test shall be final settings. The test shall be adapted to site setting
values instead of values in the example below.
Test with no voltage difference between the inputs.
Test with a voltage difference higher than the set VDiffSCV
1.
2.
3.
4.
5.
Apply voltages V-line (e.g.) = 80% VBase and V-Bus = 80% VBase.
Check that the AUTOENOK and MANENOK outputs are activated.
The test can be repeated with different voltage values to verify that the function
operates within the set VDiffvalues. Check with both V1 and V2 respectively lower
than the other.
Increase the V-bus to 110% VBase, and the V-line = 90% VBase and also the
opposite condition.
Check that the two outputs for manual and auto synchronism are not activated.
The phase angle differences PhaseDiffM and PhaseDiffA respectively are set to their final
settings and the test should verify that operation is achieved when the phase angle
difference is lower than this value both leading and lagging.
Test with no voltage difference
1.
2.
Apply voltages V-line (e.g.) = 100% and V-bus = 100% VBase, with a phase
difference equal to 0 degrees and a frequency difference lower than fSynchMax.
Check that the AUTOOK and MANOK outputs are activated.
The test can be repeated with other PhaseDiff values to verify that the function
operates for values lower than the set ones. By changing the phase angle on V1
connected to V-bus, between d degrees. The user can check that the two outputs
are activated for a PhaseDiff lower than the set value. It should not operate for other
values. See figure 68.
165
Section 12
Verifying settings by secondary injection
V-Bus
No operation
+dj
V-Line operation
-dj
V-Bus
en05000551_ansi.vsd
Figure 68:
3.
Change the phase angle between +d and d and verify that the two outputs are
activated for phase differences between these values but not for phase differences
outside, see figure 68.
The frequency difference test should verify that operation is achieved when the
FreqDiff frequency difference is lower than the set value for manual and auto
synchronism check respectively and that operation is blocked when the frequency
difference is bigger.
Test with FreqDiff = 0 mHz
Test with a frequency difference outside the set limits for manual and auto sychronism
check respectively.
1.
2.
3.
4.
Apply voltages V-Line equal to 100% VBase and V-Bus equal to 100%
UBaseVBase, with a frequency difference equal to 0 mHz and a phase difference
lower than the set value.
Check that the AUTOSYOK and MANSYOK outputs are activated.
Apply voltage to the U-line equal to 100% VBase with a frequency equal to 50 Hz
and voltage V-bus equal to 100% VBase, with a frequency outside the set limit.
Check that the two outputs are not activated.
The test can be repeated with different frequency values to verify that the function
operates for values lower than the set ones. If a modern test set is used, the frequency
can be changed continuously.
Section 12
Verifying settings by secondary injection
2.
3.
4.
12.10.1.3
The VDiff between the voltage connected to V-bus and V-line should be 0%, so that
the AUTOOK and MANOK outputs are activated first.
Change the V-Line voltage connection to V-Line2 without changing the setting on
the local HMI.
Check that the two outputs are not activated.
The test can also be repeated by moving the V-line voltage to the V3PL input.
V-bus
General
At test of the energizing check function for the applicable bus, arrangement shall be done
for the energizing check functions. The voltage is selected by activation of different inputs
in the voltage selection logic.
The test shall be performed according to the settings for the station. Test the alternatives
below that are applicable.
The test should verify that the energizing check function operates for a low voltage on
the V-Line and for a high voltage on the V-bus. This corresponds to the energizing of a
dead line to a live bus.
Procedure
1.
2.
3.
Apply a single-phase voltage 100% VBase to the U-bus, and a single-phase voltage
30% VBase to the V-line.
Check that the AUTOENOK and MANENOK outputs are activated.
Increase the V-Line to 60% VBase and V-Bus to be equal to 100% VBase. The
outputs should not be activated.
The test can be repeated with different values on the V-Bus and the V-Line.
The test should verify that the energizing check function operates for a low voltage on
the V-bus and for a high one the V-line. This corresponds to an energizing of a dead bus
from a live line.
Procedure
167
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
The test should verify that the energizing check function operates for a low voltage on
both the U-bus and the U-line, i.e closing of the breaker in a non-energized system. Test
is valid only when this function is used.
Procedure
1.
2.
3.
4.
5.
6.
Verify the local HMI setting AutoEnerg to Off and ManEnerg to DBLL.
Set the parameter ManDBDL to On.
Apply a single-phase voltage of 30% VBase to the U-bus and a single-phase voltage
of 30% VBase to the V-line.
Check that the MANENOK output is activated.
Increase the V-bus to 80% VBase and keep the U-line equal to 30% VBase.
The outputs should not be activated.
Repeat the test with ManEnerg set to DLLB with different values on the V-bus and
the V-line voltage.
12.10.1.4
168
Section 12
Verifying settings by secondary injection
Testing the voltage selection for single CB arrangements
This test should verify that the correct voltage is selected for the measurement in the
energizing check function used in a double-bus arrangement. Apply a single-phase
voltage of 30% VBase to the V-line and a single-phase voltage of 100% VBase to the Vbus.
If the VB1/2OK inputs for the fuse failure are used, they must be activated, during tests
below. Also verify that deactivation prevents operation and gives an alarm.
Procedure
1.
2.
This test should verify that correct voltage is selected for the measurement in the
energizing function used for a diameter in a breaker-and-a-half arrangement. Apply
single-phase voltages to the inputs according to the table 19. H means a voltage of
100% VBase and L means a voltage of 30% VBase. Verify that correct output signals
are generated.
Procedure
1.
2.
3.
12.10.1.5
Connect the analog signals to the voltage inputs, in pair of two for V1 and V2.
(Inputs U3P - BB1, BB2, L1, L2)
Activate the binary signals according to the used alternative. Verify the measuring
voltage on the synchronism check function. Normally it can be good to verify
synchronism check with the same voltages and phase angles on both voltages. The
voltages should be verified to be available when selected and not available when
another input is activated so connect only one voltage transformer reference at each
time.
Record your voltage selection tests in a matrix table showing read values and
AUTOSYOK/MANSYOK signals to document the test performed.
169
Section 12
Verifying settings by secondary injection
12.10.2
170
Section 12
Verifying settings by secondary injection
thus be low at the instant of reclosing. After each Open or Close operation it may need a
recharging period before it goes high again.
In the example of CB simulation arrangement, the CBREADY condition is simulated by
a manual switch, SRY.
Information and material for the verification:
Protection or control unit, Intelligent electronic device (IED), configured and with
settings entered.
Configuration diagram for the IED
Terminal diagram for the IED, or plant circuit diagram including the IED
Technical reference manual for the IED
Relay test set for secondary injection
Means to indicate, measure and record operation and times, e.g. an event recording
facility
A bi-stable relay (BR) or two auxiliary relays to simulate a CB
Two push-buttons (SC, ST) to operate the BR and a change-over switch (SRY) to
simulate CBREADY
Possibly a switch simulation the Synchronism check (SYNC) condition
171
BI
Trip
AR01 - CB 52a
AR01 - CB READY
IED
Section 12
Verifying settings by secondary injection
BI
SRY
ST
SC
To test
set
BR
en04000202_ansi.vsd
Figure 69:
12.10.2.1
172
Section 12
Verifying settings by secondary injection
2.
3.
4.
5.
12.10.2.2
If any timer settings are reduced to speed-up or facilitate the testing, they shall be
set to normal after testing. A temporary label on the unit can be a reminder to restore
normal settings after which a verification test should be performed.
Decide if a synchronism check (SYNC) shall be included in the test.
If SYNC as an internal function or external device is not operated by the injection,
it may be connected as a permanent high signal or controlled by a switch.
Read and make notes of the reclosing operation counters.
Local HMI tree:
Test/Function status/Control/Auto recloser/Autorecloser(RREC,79)
Possibly reset the counters to zero. Counters are reset in the RESET menu.
Make arrangements for the simulation of the CB, e.g. as in figure 69.
Make arrangements for indication, recording and time measurements.
The signals for ,52a, RI, CLOSECMD, READY and other relevant signals should
preferably be arranged for event recording with time tagging. If that is not possible,
other means of time measurement and recording should be arranged.
12.10.2.3
173
Section 12
Verifying settings by secondary injection
5.
6.
7.
12.10.2.4
Inject AC quantities to give a trip, e.g. 1-pole trip, to the BR and to the RI input.
Observe and preferably record the operation. The BR relay shall trip and reclose
(pick-up). After reclosing, the SRY switch can be opened for about 5 s and then
closed again.
The auto-reclosing open time and the sequence should be checked, for example in
the event recording. Check also the operation indications (disturbance report) and
the operation counters.
Test/Function status/Control/Autorecloser(RREC,79)
Should the operation not be as expected, this should be investigated. It could be
caused by an inappropriate setting or missing condition such as CBREADY (or
SYNC at three-phase reclosing).
Repeat the sequence by simulating a permanent fault.
Shortly after the reclosing shot a new fault is applied. If a single-shot reclosing
program is selected, there shall be one reclosing operation and then blocking of the
auto-reclosing function for the set reset time.
Before a new reclosing sequence can be run, the CBREADY and 52a (CB closed)
must be set manually.
Repeat the sequence by simulating a three-phase transient and permanent faults, and
other applicable cases, such as signal to RI_HS and High-speed reclosing.
If just single-phase reclosing is selected, FirstShot=1ph, a check can be run to make
sure that a three-pole trip does not result in any reclosing. Other similar cases can
be checked as required.
Check that the auto-reclosing function is operative, e.g. by making a reclosing shot
without the INHIBIT signal.
Apply a fault and thereby a RI signal. At the same time, or during the open time,
apply a signal to the input INHIBIT.
Check that the reclosing sequence is interrupted and no reclosing takes place.
Check that the reclosing function is operative, e.g. by making a reclosing shot.
Section 12
Verifying settings by secondary injection
2.
3.
4.
Check that the auto-reclosing function is operative, e.g. by making a reclosing shot.
Keep the CB simulator BR closed. Remove the CBREADY signal by opening SRY.
Apply a fault and thereby a IRsignal.
Check that no reclosing takes place.
Check that the auto-reclosing function is operative, e.g. by making a reclosing shot.
Set the auto-reclosing Operation Off, e.g. by external control.
The output READY shall be low, and PREP3P shall be high.
Apply a fault and thereby a RI signal.
Check that no reclosing takes place.
The usual arrangement is to have an auto-reclosing function per circuit-breaker. They can
be in different CB related units (IEDs) or in a common unit. One auto-reclosing function
(Master) is set with Priority=High and the other (Slave) with Priority=Low. An
illustration of typical interconnections is shown in the Application manual, section
Autorecloser/Setting guidelines. The two functions can be checked individually by
carefully applying START, WAIT, and INHIBIT signals.
It is also possible to verify the two functions together by using CB simulating equipment
and two CB circuits. There should be interconnections from the Master to the Slave
175
Section 12
Verifying settings by secondary injection
After the tests, restore the equipment to normal or desired state. Check the following
items in particular:
Procedure
1.
2.
3.
4.
12.10.2.5
12.10.3
12.10.4
Interlocking
Prepare the IED for verification of settings as outlined in section "Overview" and
section "Preparing for test" in this chapter.
The interlocking function consists of a bay-level part and a station-level part. The
interlocking is delivery specific and is realized by bay-to-bay communication over the
station bus. For that reason, test the function in a system, that is, either in a complete
delivery system as an acceptance test (FAT/SAT) or as parts of that system.
176
Section 12
Verifying settings by secondary injection
12.10.5
Increasing or decreasing the injected voltage or current at the analogue inputs of the
IED.
Checking that the corresponding command/s (Lower or Raise) are issued by the
voltage control function.
Setting confirmation is an important step for voltage control in the installation and
commissioning phase to ensure consistency of power systems base quantities, alarm/
blocking conditions and parallel control settings for each transformer control function.
Before starting any test, undertake the following general setting checks in the PCM 600
PST for single or parallel voltage control function:
177
Section 12
Verifying settings by secondary injection
Terminology
The busbar voltage VB is a shorter notation for the measured voltages Va, Vb, Vc or
Vij, where Vij is the phase-to-phase voltage, Vij = Vi -Vj, or Vi, where Vi is one single
phase to ground voltage.
IL is a shorter notation for the measured load current; it is to be used instead of the three
phase quantities Ia, Ib, Ic or the two phase quantities Ii and Ij, or single phase current Ii.
Also note that for simplicity PST menu structures included in the following procedure
are referred to universally as VCP1, for example,
Setting Group Nn/Control/TransformerVoltageControl/VCP1/t1 and t2l
For cases where single mode voltage control is implemented, the PST menu structure will
include VCS1 instead of the parallel designator VCP1
12.10.5.1
Secondary test
The VCTR function performs basic voltage regulation by comparing a calculated load
voltage (VL) against a voltage range defined by PST setting VDeadband (with upper and
178
Section 12
Verifying settings by secondary injection
lower limits V2 and V1 respectively). The calculated load voltage VL represents the
secondary transformer bus voltage VB adjusted for Load Drop Compensation (LDC)
where enabled in PST settings. Note that when LDC is disabled, VB equals VL.
When the load voltage VL stays within the interval between V1 and V2, no action will
be taken.
If VL < V1 or VL > V2, a command timer will start which is constant time or inverse
time defined by PST setting t1 and t1Use. The command timer will operate while the
measured voltage stays outside the inner deadband (defined by PST setting
VDeadBandInner).
If VL remains outside of the voltage range defined by VDeadband and the command
timer expires, the VCTR will execute a Raise or Lower command to the transformer tap
changer. This command sequence will be repeated until VL is brought back within the
inner deadband range.
12.10.5.2
2.
General Settings/Control/TransformerVoltageControl/TCMn/EnabTapCmd
While the test set is connected to the IED but no voltage is applied, the VCTR
function will detect an under voltage condition that may result in an alarm or
blocking of the VCTR operation. These conditions will be shown on the IED built
in HMI.
Apply the corresponding voltage
Confirm the analogue measuring mode prior to undertaking secondary injection
(positive sequence, phase to phase or phase to earth). This measuring mode is
defined in
Setting Group Nn/Control/TransformerVoltageControl/VCP1/General/
MeasMode
179
Section 12
Verifying settings by secondary injection
The application of nominal voltage Vset according to set MeasMode to the relays
should cause the alarm or blocking condition for undervoltage to reset.
12.10.5.3
4.
5.
6.
12.10.5.4
Review the settings for VDeadband (based on percentage of nominal bus voltage)
and calculate the upper (V2) and lower (V1) voltage regulation limits for which a
tap change command will be issued.
Review the expected time for first (t1) and subsequent (t2) tap change commands
from the VCTR function
Setting Group N1/Control/TransformerVoltageControl/VCP1/t1 and t2l
Lower the voltage 1% below V1 and wait for the issue of a Raise command from
the VCTR after the expiry of a constant or inverse time delay set by t1. Detection
of this command will involve locating the allocated binary output for a Raise pulse
command in the PCM 600 Signal Matrix (SMT) and monitoring a positive from this
output.
After the issue of the Raise command, return the applied voltage to Vset (nominal
value).
Raise the voltage 1% above the upper deadband limit V2 and wait for the issue of
a Lower command from the VCTR after the expiry of a constant or inverse time
delay set by t1. Detection of this command will involve locating the allocated binary
output for a Low pulse command in the PCM 600 Signal Matrix (SMT) and
monitoring a positive from this output.
Return the applied voltage to Vset.
2.
3.
180
Section 12
Verifying settings by secondary injection
12.10.5.5
3.
4.
12.10.5.6
Overcurrent blocking
Procedure
1.
2.
3.
12.10.5.7
Single transformer
Load Drop Compensation
Procedure
181
Section 12
Verifying settings by secondary injection
1.
2.
3.
(Equation 25)
where:
VL, IL = Re(IL) + jlm(IL) are complex phase quantities
When all secondary phase-to-ground voltages are available, use the positive
sequence components of voltage and current. By seperation of real and imaginary
parts:
vl , re =vb , re - rline il , re + xline il , im
(Equation 26)
(Equation 27)
where:
vb
il
rline
xline
For comparison with the set point value, the modulus of UL are according to
equation 28.
VL =
4.
5.
6.
7.
182
( vl , re )
+ ( vl , im )
(Equation 28)
Section 12
Verifying settings by secondary injection
8.
With OperationLDC set to Enabled, the voltage regulation algorithm uses the
calculated value for Load Voltage as the regulating quantity to compare against
Vset and the voltage deadband limits VDeadband and VDeadbandinner.
9. While injecting rated current I2Base into the IED, inject a quantity for VB that is
slightly higher then Vset+|(Rline+jXLine)IL|. This will ensure that the regulating
voltage VL is higher than Vset, and hence no tap change command should be issued
from the IED.
10. Reduce the injected voltage for VB slightly below Vset+|(Rline+jXLine)IL| and
confirm that the calculated value for Load Voltage is below Vset and a tap change
command is issued from the IED.
12.10.5.8
For the transformers connected in the parallel group, confirm that OperationPAR
is set to MF.
For parallel operation, it is also recommended that settings be confirmed for parallel
group membership, governed by PST setting TnRXOP
Setting Group Nn/Control/Transformer Voltage Control/VCPn/ParCtrl
Within the PST configuration, the general parallel arrangement of transformers are
defined by settint TnRXOP to Enabled or Disabled. The following rules are
applicable on the function inputs T1RXOP T4RXOP. If terminal T1 and T2 are
connected, T1RXOP shall be set to Enabled in ATC2 and T2RXOP shall be set to
Enabled in ATC3, T2RXOP and T3RXOP to Enabled in ATC1 and so on.
The parameter corresponding to the own terminal must not be set.
T1RXOP should thus not be set in terminal T1, T2RXOPnot in
terminal T2, etc.
3.
4.
5.
6.
The lowest transformer number in the parallel group is by default set as the Master
confirm that this is the case by reviewing the local IED HMI.
Review the settings for VDeadband (based on percentage of nominal bus voltage)
and calculate the upper (V2) and lower (V1) voltage regulation limits for which a
tap change command will be issued from the Master transformer in the group.
Review the expected time for first (t1) and subsequent (t2) tap change commands
from the Master transformer
Setting Group Nn/Control/TransformerVoltageControl/VCP1/t1 and t2l
Apply a voltage 1% below V1 and wait for the issue of a Raise command from the
VCTR after the expiry of a constant or inverse time delay set by t1. Detection of
this command will involve locating the allocated binary output for a Raise command
183
Section 12
Verifying settings by secondary injection
7.
8.
9.
in the PCM 600 Signal Matrix (SMT) and monitoring a positive from this output.
Confirm the timing of this command correlates with the PST setting t1.
After the issue of the Raise command, confirm that all Follower transformers in the
group change tap in accordance with the command issued from the Master
transformer.
Inject a voltage VB for the Master transformer that is 1% above the upper deadband
limit V2 and wait for the issue of a Lower command from the VCTR after the expiry
of a constant or inverse time delay set by t2.
Confirm that all Follower Transformers in the group change tap in accordance with
this command.
This instruction for confirmation of circulating current voltage regulation assumes two
transformers in the parallel group. Setting confirmation through secondary injection
requires calculation of circulating currents for each transformer based on impedance
values and respective compensating factors, and is therefore more complex for greater
than two transformers.
Procedure
1.
2.
Confirm that OperationPAR is set to CC for the transformers in the parallel group.
For parallel operation, it is also recommended that settings be confirmed for parallel
group membership, governed by PST setting TnRXOP
Setting Group Nn/Control/Transformer Voltage Control/VCPn/ParCtrl
Within the PST configuration, the general parallel arrangement of transformers are
defined by setting TnRXOP to Enabled or Disabled. The following rules are
applicable on the function inputs T1RXOP - T4RXOP. If terminal T1 and T2 are
connected, T1RXOP shall be set to Enabled in ATC2 and T2RXOP shall be set to
Enabled in ATC1. If T1 - T3 are available T1RXOP and T2RXOP shall be set to
Enabled in ATC3, T2RXOP and T3RXOP to Enabled in ATC1 and so on.
The parameter corresponding to the own terminal must not be set.
T1RXOP should thus not be set in terminal T1, T2RXOP not in
terminal T2 etc.
3.
4.
5.
6.
184
Review the settings for VDeadband (based on percentage of nominal bus voltage)
and calculate the upper (V2) and lower (V1) voltage regulation limits for which a
tap change command will be issued from the Master transformer in the group.
Review the expected time for first (t1) and subsequent (t2) tap change commands
from the Master transformer
Setting Group Nn/Control/TransformerVoltageControl/VCP1/t1 and t2
Inject a voltage VB equal to Vset for each transformer.
Inject a load current for Transformer 1 that is equal to rated load current I2Base and
a load current for Transformer 2 that is equal to 95% of rated load current I2Base.
Section 12
Verifying settings by secondary injection
7.
8.
This will have the effect of producing a calculated circulating current that flows
from HV to LV side for Transformer 1 and LV to HV side for Transformer 2.
Confirm that a circulating current is measured on the IED local HMI that is equal
in magnitude to 5% of I2Base, with polarity as discussed in step "".
Confirm the PST settings for Ci (Compensation Factor) and Xi (Transformer Short
Circuit Impedance). Using these setting values and the measured quantity of
circulating current from the IED HMI (Icc_i), calculate the value for circulating
current voltage adjustment Vci.
Vdi = Ci Icc _ i Xi
(Equation 29)
The voltage regulation algorithm then increases (for transformer T2) or decreases
(for transformer T1) the measured voltage by Vdi and compares Vi against the
voltage deadband limits V1 and V2 for the purposes of voltage regulation.
Vi = VB + Vdi
9.
(Equation 30)
To cause a tap change, the calculated value for circulating current voltage
adjustment must offset the injected quantity for bus voltage VB so that Vi is outside
the voltage deadband created by setting VDeadBand. Expressed by equation 31 and
equation 32.
Vdi > V 2 - VB
VB = Vset
Therfore:
Icc _ i >
(V 2 - Vset )
( Ci Xi )
(Equation 33)
(Equation 34)
10. Using the PST settings for Vset, VdeadBand, C (Compensating factor) and Xr2
(transformer short circuit impedance) calculate the magnitude of Icc_i necessary to
cause a tap change command.
185
Section 12
Verifying settings by secondary injection
11. Inject current equal to I2base for Transformer 1 and (I2Base - |Icc_i|) for
Transformer 2 so that the magnitude of calculated circulating current will cause a
Raise command to be issued for Transformer 2 and a Lower command for
Transformer 1. Magnitude and direction of circulating currents measured for each
transformer can be observed as service values on the IED local HMI and Raise/
Lower commands detected from the binary output mapped within SMT.
The voltage injection equal to Vset is required for both transformers
during this test.
12. Confirm that a tap change command is issued from the VCTR function to
compensate for the circulating current.
13. Injected currents can be reversed such that the direction of calculated circulating
currents change polarity, which will cause a Lower command for Transformer 2
and a Raise command for Transformer 1.
Confirm that OperationPAR is set to CC for each transformer in the parallel group.
Confirm that OperCCBlock is set to On for each transformer in the parallel group.
Review the setting for CircCurrLimit.
Review the setting for CircCurrBk to confirm whether a circulating current limit
will result in an Alarm state, Total Block or Automatic Block of the VCTR function.
Inject a voltage VB equal to Vset for each transformer.
Inject a load current for Transformer 1 that is equal to rated load current I2Base and
a load current for Transformer 2 that is 1% less than [I2Base (I2Base
CircCurrLimit)]
Confirm that the VCTR function responds in accordance with the setting for
CircCurrBk. Alarm and blocking conditions can be confirmed through interrogation
of the Event or Control menus on the IED local HMI.
186
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
12.10.5.9
Confirm that OperationPAR is set to MF for each transformer in the parallel group.
Review the setting for VTMismatch and tVTMismatch.
Inject a voltage UB equal to Uset for Transformer 1 and a voltage less than [Vsset
(VTMismatch Vset)] for Transformer 2.
This condition should result in a VTMismatch which will mutually block the
operation of VCTR for all transformers connected in the parallel group, which can
be confirmed through interrogation of the local IED HMI.
Confirm that the VCTR function responds in accordance with the setting for
CircCurrBk.
12.11
Scheme communication
12.11.1
12.11.1.1
187
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
6.
7.
12.11.1.2
12.11.1.3
188
Section 12
Verifying settings by secondary injection
6.
7.
8.
9.
12.11.1.4
12.11.1.5
12.11.2
12.11.2.1
189
Section 12
Verifying settings by secondary injection
Checking of current reversal
The reverse zone timer must not operate before the forward zone fault is
applied. The user might need to block the reverse zone timer during testing
of current reversal.
Procedure
1.
2.
3.
4.
5.
12.11.2.2
Check the blocking of the echo with the injection of a CR signal >40 ms after a
reverse fault is applied.
Measure the duration of the echoed signal by applying a CR carrier receive signal.
Check the trip functions and the voltage level for trip by reducing a phase voltage
and applying a CR carrier receive signal.
Testing conditions
Only one type of fault is sufficient, with PSCH function. Apply three faults (one in each
phase), when ZC1P function is used. For phase L1-N fault, set these parameters:
190
Section 12
Verifying settings by secondary injection
Phase
I (Amps)
Phase-angle (Deg)
L1
L2
240
63
240
L3
120
63
120
Change all settings cyclically for other faults (L2-N and L3-N).
Weak end infeed set for trip
Weak end infeed set for echo
1.
2.
3.
4.
5.
6.
7.
8.
12.11.2.3
12.11.3
12.11.3.1
191
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
6.
7.
8.
12.11.3.2
Provide the terminal with conditions equivalent to normal load for at least two
seconds.
Deactivate the conditions for accelerated function.
Apply a phase to ground fault at 100% of line impedance.
Check that the fault is tripped with the second zone time delay.
Provide the terminal with conditions equivalent to normal load for at least two
seconds.
Activate the condition for accelerated function either by the auto-recloser or by the
loss of load.
Apply a phase to ground fault at 100% of line impedance.
Check that the fault is tripped instantaneously.
12.11.4
12.11.4.1
192
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Inject the polarizing voltage 3V0 at 5% ofVBase(directional TGF)and the with the
current lagging the voltage by 65.
Inject current (65 lagging the voltage) in one phase at about 110% of the set
operating current, and switch the current off with the switch.
Switch the fault current on and measure the operating time of the EFC logic.
Use the TRIP signal from the configured binary output to stop the timer.
Compare the measured time with the set value tCoord.
Activate the CR binary input.
Check that the CRL output is activated when the CR input is activated.
Switch the fault current on (110% of the setting) and wait longer than the set value
tCoord.
No TRIP signal should appear.
Switch the fault current off.
Reset the CR binary input.
Activate the BLOCK digital input.
Switch the fault current on (110% of the setting) and wait for a period longer than
the set value tCoord.
No TRIP signal should appear.
Switch the fault current and the polarizing voltage off.
Reset the BLOCK digital input.
Permissive scheme
Procedure
1.
Inject the polarizing voltage 3V0 which is 5% of UBaseVBase (Four step PEFM)
and with the current lagging the voltage by 65.
2. Inject current (65 lagging the voltage) into one phase at about 110% of the set
operating current, and switch the current off with the switch.
3. Switch the fault current on, (110% of the setting) and wait longer than the set value
tCoord.
No TRIP signal should appear, and the CS binary output should be activated.
4. Switch the fault current off.
5. Activate the CR binary input.
6. Switch the fault current on (110% of the setting) and measure the operating time of
the EFC logic.
Use the TRIP signal from the configured binary output to stop the timer.
7. Compare the measured time with the setting for tCoord.
8. Activate the BLOCK digital input.
9. Switch the fault current on (110% of the setting) and wait for a period longer than
the set value tCoord.
No TRIP signal should appear.
10. Switch the fault current and the polarizing voltage off.
11. Reset the CR binary input and the BLOCK digital input.
193
Section 12
Verifying settings by secondary injection
12.11.4.2
12.11.5
12.11.5.1
12.11.5.2
Inject the polarizing voltage 3V0 to 5% of UBase (directional TGF) and the phase
angle between voltage and current to 155, the current leading the voltage.
Inject current (155 leading the voltage) in one phase to about 110% of the setting
operating current (INDir).
Check that the IRVL output is activated after the set time (tPickUp).
Abruptly reverse the current to 65 lagging the voltage, to operate the forward
directional element.
Check that the IRVL output still is activated after the reversal with a time delay that
complies with the setting (tDelay).
Switch off the polarizing voltage and the current.
194
Section 12
Verifying settings by secondary injection
1.
2.
3.
4.
5.
6.
7.
8.
9.
Inject the polarizing voltage 3V0 to 5% ofVBase and the phase angle between
voltage and current to 155, the current leading the voltage.
Inject current (155 leading the voltage) in one phase to about 110% of the setting
operating current (INDir).
Activate the CRL binary input.
No ECHO and CS should appear.
Abruptly reverse the current to 65 lagging the voltage, to operate the forward
directional element.
No ECHO and CS should appear.
Switch off the current and check that the ECHO and CS appears on the
corresponding binary output or on the local HMI unit, about 200 ms after resetting
the directional element.
Switch off the CRL binary input.
Activate the BLOCK binary input.
Activate the CRL binary input.
No ECHO and CS should appear.
Switch off the polarizing voltage and reset the BLOCK and CRL binary input.
If setting WEI=Trip
Procedure
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Inject the polarizing voltage to about 90% of the setting (3V0) operating voltage.
Activate the CRL binary input.
No ECHO, CS and TRWEI outputs should appear.
Increase the injected voltage to about 110% of the setting (3V0) operating voltage.
Activate the CRL binary input.
Check that the ECHO, CS and TRWEI appears on the corresponding binary output
or on the local HMI.
Reset the CRL binary input.
Activate the BLOCK binary input.
Activate the CRL binary input.
No ECHO, CS and TRWEI outputs should appear.
Reset the CRL and BLOCK binary input.
Inject the polarizing voltage 3V0 to about 110% of the setting (3V0) and adjust the
phase angle between the voltage and current to 155, the current leading the voltage.
Inject current (155 leading the voltage) in one phase to about 110% of the setting
operating current (INDir).
Activate the CRL binary input.
No ECHO, CS and TRWEI should appear.
Abruptly reverse the current to 65 lagging the voltage, to operate the forward
directional element.
195
Section 12
Verifying settings by secondary injection
12.11.5.3
12.12
Logic
12.12.1
12.12.1.1
196
Make sure that AutoLock and TripLockout are both set to Off.
Initiate a three-phase fault
An adequate time interval between the faults should be considered, to overcome
areset time caused by the possible activation of the autoreclosing function. The
function must issue a three-pole trip in all cases, when trip is initiated by any
protection or some other built-in or external function. The following functional
Section 12
Verifying settings by secondary injection
output signals must always appear simultaneously: TRIP, TR_A, TR_B. TR_Cand
TR3P.
12.12.1.2
4.
5.
12.12.1.3
Make sure that TripLockout and AutoLock are both set to off.
Initiate different single-phase-to-ground faults one at a time.
Initiate different phase-to-phase and three-phase faults.
Consider using an adequate time interval between faults, to overcome a reset time
which is activated by the autoreclosing function. A three-pole trip should occur for
each separate fault and all of the trips. Functional outputs TRIP, all TR_A, TR_B,
TR_C and TR3P should be active at each fault. No other outputs should be active.
Initiate a single-phase-to-ground fault and switch it off immediately when the trip
signal is issued for the corresponding phase. Initiate the same fault once again within
the reset time of the used autoreclosing function.
Initiate a single-phase-to-ground fault and switch it off immediately when the trip
signal is issued for the corresponding phase. Initiate the second single-phase-toground fault in one of the remaining phases within the time interval, shorter than
tEvolvingFault (default setting 2.0 s) and shorter than the dead-time of the autoreclosing function, when included in the protection scheme.
Check that the second trip is a three-pole trip and that a three phase autoreclosing
attempt is given after the three phase dead time. Functional outputs TRIP, TR_A,
TR_B, TR_C and TR1P should be active during first fault. No other outputs should
be active. Functional outputs TRIP, all TR_A, TR_B, TR_C and TR3P should be
active during second fault.
Make sure that AutoLock and TripLockout both are set to off.
Initiate different single-phase-to-ground faults one at a time.
Take into consideration an adequate time interval between faults, to overcome a
reset time which is activated by the autoreclosing function. Only a single-pole trip
should occur for each separate fault and only one of the trip outputs (TR01-TR_A,
197
Section 12
Verifying settings by secondary injection
3.
4.
5.
6.
7.
12.12.1.4
7.
198
Make sure that AutoLock and TripLockout are both set to Off.
Activate shortly the set lockout (SETLOCKOUT) signal in the IED.
Check that the circuit breaker lockout (CLLKOUT) signal is set.
Activate shortly thereafter, the reset lockout (RSTLKOUT) signal in the IED.
Check that the circuit breaker lockout (CLLKOUT) signal is reset.
Initiate a three-phase fault
A three- trip should occur and all trip outputs ) should be activated. Functional
outputs TRIP and TR3P should be active at each fault. The output CLLKOUT
should not be set.
Activate the automatic lockout function, set AutoLock = On and repeat
Beside the trip outputs, CLLKOUT should be set.
Section 12
Verifying settings by secondary injection
8.
Reset the lockout signal by shortly thereafter activating the reset lockout
(RSTLKOUT) signal.
9. Activate the trip signal lockout function, set TripLockout = On and repeat
All trip outputs (TR_A, TR_B, TR_C) and functional outputs TRIP and TR3P
should be active and stay active after each fault, CLLKOUT should be set.
10. Repeat
All functional outputs should reset.
11. Deactivate the trip signal lockout function, set TripLockout = Off and the automatic
lockout function, set AutoLock = Off.
12.12.1.5
12.13
Monitoring
12.13.1
12.13.2
In Test Mode, individual event blocks can be blocked from the PCM 600.
Individually event blocks can also be blocked from the local HMI under the menu:
REC 670 ANSI
199
Section 12
Verifying settings by secondary injection
12.13.3
Test settings
Parameter:
Condition:
I
Healthy conditions
V = 69.3 V, I = 0 A & ZF = 0
Impedance |Z|
Test point
Note:
Impedance angle ZF
Test angle
12.13.3.1
200
Section 12
Verifying settings by secondary injection
1.
2.
3.
Set the test point (|Z| fault impedance and ZF impedance phase angle ) for a
condition that meets the requirements in table 20.
Subject the IED to healthy normal load conditions for at least two seconds.
Apply a fault condition.
Check that the distance-to-fault value displayed on the HMI complies with the
following equations (the error should be less than five percent):
Z
p = ------x- 100
X1
(Equation 35)
p=
3 Zx
X0 + 2 X1
100
(Equation 36)
(Equation 37)
12.13.3.2
Zx
X0
X1
XM
201
Section 12
Verifying settings by secondary injection
12.14
Metering
12.14.1
12.15
Station communication
12.15.1
12.15.2
12.16
Remote communication
12.16.1
202
Section 12
Verifying settings by secondary injection
To perform a test of the binary signal transfer to remote end the hardware (LDCM) and
binary input and output signals to transfer must be configured as required by the
application.
There are two types of internal self-supervision of the binary signal transfer to remote
end:
Status for inputs and outputs as well as self-supervision status are available from the local
HMI under the menus:
Test correct functionality by simulating different kind of faults. Also check that sent and
received data is correctly transmitted and read.
A test connection is shown in figure 70. A binary input signal (BI) at End1 is configured
to be transferred through the communication link to End2. At End2 the received signal
is configured to control a binary output (BO). Check at End2 that the BI signal is received
and the BO operates.
Repeat the test for all the signals configured to be transmitted over the communication
link.
203
Section 12
Verifying settings by secondary injection
Figure 70:
204
Section 13
Primary injection testing
13.1
13.1.1
13.1.1.1
205
Section 13
Primary injection testing
The load current is fed into the VCTR function where parameters corresponding to the
line data for resistance and inductance are set. The voltage drop calculated by the LDC
will be proportional to the voltage drop in the system up to the load point.
In the IED this voltage will be subtracted from the measured busbar voltage (VB) and
the result, corresponding to the voltage at the load point (UL) will be presented to the
VCTR function for the purposes of voltage regulation. This voltage will be lower (if
resitive or inductive load current is applied) than the Vset voltage and VCTR will increase
the voltage in order to achieve the correct system voltage at the load point.
Procedure
1.
2.
3.
4.
5.
6.
13.1.1.2
206
Section 13
Primary injection testing
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
b) When measuring the current from the L3 phase the main current transformer in
L1 phase must have its secondary winding short-circuited and the cables to the
terminal disconnected
Modify the connections according to a) above.
Increase slightly the setting Uset so that the RAISE output is on the verge of
activation (ie just below the measured value for bus voltage).
Set Rline and Xline to values for the maximum line impedance to the load point.
The RAISE output should activate when either Rline or Xline will be set to the
maximum value. The operation can be checked at the corresponding binary output
and in the Event Report. If the RAISE output does not activate reset both Rline and
Xline to Zero and set Uset to a little lower value until the Lower circuit is on the
verge of operation.
If the LOWER output activates when either Rline or Xline have a high setting the
current circuits of the L1 phase are incorrect and must be reversed. Incorrect current
polarity may be an issue with physical wiring or the current direction convention
selected for the CT analogue input as part of the PST setting. The operation can be
checked at the corresponding binary output and in the Event Report.
Restore the original connections at the CT in phase L1.
Modify the connections according to b).
Increase slightly the setting Uset so that the RAISE output is on the verge of
activation (ie just below the measured value for bus voltage (UB)).
Set Rline and Xline to values for the maximum line impedance to the load point.
The RAISE output should activate when either Rline or Xline will be set to the
maximum value. The operation can be checked at the corresponding binary output
and in the Event Report. If the RAISE output does not activate reset both Rline and
Xline to Zero and set Uset to a little lower value until the Lower circuit is on the
verge of operation.
If the LOWER output activates when either Rline or Xline have a high setting the
current circuits of the L1 phase are incorrect and must be reversed. Incorrect current
polarity may be an issue with physical wiring or the current direction convention
selected for the CT analogue input as part of the PST setting. The operation can be
checked at the corresponding binary output and in the Event Report.
Retain the settings for Rline and Xline to values as the maximum line impedance
to the load point.
Decrease slowly the setting of Vset until the "Lower" circuit is on the verge of
Operation (ie just above the calculated value for load (VL)).
Reduce the setting for XLine to zero so that the "Lower" circuit operates.
If the operation of Raise and Lower is inverted (Lower instead of Raise and Raise
instead Lower) the current connections have to be reversed in the same way as for
the tests of the Raise component of the voltage regulation with LDC.
Modify the CT connections according to (b) and undertake the same test for the
Lower of the tap changer with LDC (repeating steps 11 to 13).
207
Section 13
Primary injection testing
15. Restore settings for Vset, RLine and XLine to normal in service values.
16. Restore the original connections at the CT in phase L3.
17. After these tests the single mode voltage control function in the IED can be taken
in to service.
13.1.1.3
a single IED with CAP531 configuration for the necessary data transfer, for up to
four transformers; or
multiple IEDs (with up to 8 VCTR functions in total) communicating via Goose
messages on station bus IEC61850-8-1
The parallel control functions can be tested directly with operational currents i.e. with
the power transformer in service and loaded.
13.1.1.4
208
Section 13
Primary injection testing
Within the PST configuration, the general parallel arrangement of transformers are
defined by setting TnRXOP to On or Off. The following rules are applicable on the
function inputs T1RXOP - T4RXOP. If terminal T1 and T2 are connected, T1RXOP
shall be set to On in ATC2 and T2RXOP shall be set to On in ATC1. If T1 - T3 are
available T1RXOP and T2RXOP shall be set to On in ATC3, T2RXOP and
T3RXOP to On in ATC1 and so on.
The parameter corresponding to the own terminal must not be set.
T1RXOP should thus not be set in terminal T1, T2RXOP not in
terminal T2 etc.
6.
7.
8.
9.
10.
11.
12.
13.
209
Section 13
Primary injection testing
the sum (with opposite sign) of the current measured at T2 and T3.
The currents measured at T2 and T3 will ideally be about the same
values.
If the voltage is close to the upper limit of the Vdeadband the tap
changer of T1 will try to decrease the controlled voltage, but in the
opposite case, i.e. the voltage is close to the lower limit of
Vdeadband, the tap changer at T1 will not try to decrease the
controlled voltage.
The tap changer for T2 and T3 will not operate due to the fact that
the detected circulating current will be half of the current detected
at T1.
The setting of the parameter Comp then might need to be increased
a little.
At least one Tap Changer step difference between the different
transformers should be allowed in order to avoid the Tap Changers
to operate too often. If the allowed difference is for example two
steps, the Tap Changer shall be stepped up three steps when setting
parameter Comp. This applies to all the VCTR in the same group.
14. The setting of the parameter Comp at T2 and T3 will be carried out in the same
manner as at T1. According to the described procedure when the Tap Changer of
one transformer lies two steps above the others, it shall automatically step down.
When there are only two transformers in the group either shall one step down or the
other step up depending on the voltage level at the VCTR.
15. Before placing the VCTR into service, confirm the correct settings of Uset,
Udeadband, the blocking settings for overcurrent, undervoltage and high circulating
currents, and the compensating parameters Rline and Xline.
Also confirm SMT settings for binary Raise and Lower outputs in conjunction with
the basic CET configuration for Goose messages between parallel transformer
control functions.
16. Ensure that Automatic Control mode is set for each transformer from the IED and
that OperationPAR is set to CC.
13.1.1.5
210
Section 13
Primary injection testing
4.
5.
Confirm the setting of MFMode as Follow Tap or Follow Cmd. If this setting is
Follow Tap, all Follower transformers shall match the actual tap setting of the
Master, while Follow Cmd requires that Follower transformers follow the Raise and
Lower commands executed by the Master.
General Settings/Control/TransformerVoltageControl/VCP1/MFMode
Note that the maximum difference in tap positions for parallel transformers will be
determined by PST setting[Setting Group N1/Control/
TransformerVoltageControl/VCP1/MFPosDiffLim and that tap differences
exceeding that setting can produce system alarms or blocking of the VCTR.
For parallel operation, it is also recommended that settings be confirmed for parallel
group membership, governed by PST setting TnRXOP
Setting Group N1/Control/Transformer Voltage Control/VCP1/ParCtrl
Within the PST configuration, the general parallel arrangement of transformers are
defined by setting TnRXOP to On or Off. The following rules are applicable on the
function inputs T1RXOP - T4RXOP. If terminal T1 and T2 are connected, T1RXOP
shall be set to On in ATC2 and T2RXOP shall be set to On in ATC1. If T1 - T3 are
available T1RXOP and T2RXOP shall be set to On in ATC3, T2RXOP and
T3RXOP to On in ATC1 and so on.
The parameter corresponding to the own terminal must not be set.
T1RXOP should thus not be set in terminal T1, T2RXOP not in
terminal T2 etc.
6.
7.
8.
9.
10.
11.
12.
13.
14.
211
Section 13
Primary injection testing
T1 to Follower and note the Automatic block state on the IED built in HMI for all
parallel transformers.
15. Restore T1 to Master of the parallel transformer group and ensure that control mode
for each transformer is Automatic, OperationPAR is set to MF and settings for
Vset are restored to normal in service values.
13.1.1.6
212
Section 14
Commissioning and maintenance of the fault clearing system
14.1
213
Section 14
Commissioning and maintenance of the fault clearing system
14.2
Commissioning tests
During commissioning all protection functions shall be verified with the setting values
used at each plant. The commissioning tests must include verification of all circuits by
highlighting the circuit diagrams and the configuration diagrams for the used functions.
Further, the settings for protection functions are tested and recorded carefully as outlined
for the future periodic maintenance tests described below.
The final testing will include primary verification of all directional functions where load
currents is checked on the IED through the LHMI or the PCM 600 tool. The
magnitudes and angles of all currents and voltages should be checked and the symmetry
verified.
Directional functions have information about the measured direction and for example
measured impedance. These values must be checked and verified as correct with the
export or import of power available.
Finally final trip tests must be performed. This involves activation of protection functions
or tripping outputs with the circuit breaker closed and the tripping of the breaker verified.
When several breakers are involved each must be checked individually and it must be
verified that the other involved breakers are not tripped at the same time.
14.3
214
Section 14
Commissioning and maintenance of the fault clearing system
Periodic maintenance test for protection relays of objects with redundant protection
system.
First maintenance test should always be carried out after the first half year
of service.
When protection IEDs are combined with built-in control the test interval
can be increased drastically, up to for instance 15 years, because the IED
continuously reads service values, operates the breakers etc.
14.3.1
Visual inspection
Prior to testing, the protection IEDs should be inspected in order to detect any visible
damage that may have occurred (dirt or moisture deposits, overheating, etc.). Should
burned contacts be observed when inspecting the relays, a diamond file or an extremely
fine file can be used to polish the contacts. Emery cloth or similar products must not be
used as insulating grains of abrasive may be deposited on the contact surfaces and cause
failure.
Make sure that all IEDs are equipped with covers.
14.3.2
Maintenance tests
To be made after the first half year of service, then with the cycle as proposed above and
after any suspected maloperation or change of the relay setting.
Testing of protection relays shall preferably be made with the primary circuit deenergized. The relay cannot protect the circuit during testing. Trained personnel may test
one relay at a time on live circuits where redundant protection is installed and deenergization of the primary circuit is not allowed.
215
Section 14
Commissioning and maintenance of the fault clearing system
ABB protection relays are preferably tested by aid of components from the COMBITEST
testing system or FT test systems described in information B03-9510 E. Main components
are RTXP 8/18/24 test switch located to the left in each protection relay and RTXH
8/18/24 test handle which is inserted in test switch at secondary testing. All necessary
operations such as opening of trip circuits, short-circuiting of current circuits and opening
of voltage circuits are automatically performed in the right order to allow for simple and
safe secondary testing even with the object in service.
Important components of FT test system are FT1, FTx, FT19, FT19RS, FR19RX switches
and assemblies as well as FT-1 test plug.
14.3.2.1
Preparation
Before starting maintenance testing the test engineers should scrutinize applicable circuit
diagrams and have the following documentation available: Test instructions for protection
IEDs to be tested. Test records from previous commissioning and maintenance tests. List
of valid settings. Blank test records to fill in measured values.
14.3.2.2
Recording
It is of utmost importance to carefully record the test results. Special test sheets covering
the frequency of test, date of test and achieved test values should be used. Relay setting
list and protocols from previous tests should be available and all results should be
compared for differences. At component failures, spare equipment is used and set to the
requested value. A note of the exchange is made and the new measured values are
recorded. Test records for several years of testing should be stored in a common file for
a station, or a part of a station, to give a simple overview of the period of testing and
achieved test values. These test records are valuable when analysis of service disturbances
shall be done.
14.3.2.3
Secondary injection
The periodic maintenance test is done by secondary injection from a portable test set.
Each protection shall be tested according to the secondary injection test information for
the specific protection IED. Only the setting values adopted shall be checked for each
protection function. If the discrepancy between obtained value and requested set value is
too big the setting should be adjusted, the new value recorded and a note should be made
in the test record.
14.3.2.4
Alarm test
When inserting the test handle of RTXP or using FT plugs, the alarm and event signalling
is normally blocked. This is done in IED 670 by setting the Event reporting to off during
the test. This can be done when the test handle is inserted or the IED is set to test mode
216
Section 14
Commissioning and maintenance of the fault clearing system
from the LHMI. At the end of the secondary injection test it should be checked that the
event and alarm signalling is correct by activating the events and performing some
selected tests.
14.3.2.5
14.3.2.6
14.3.2.7
217
Section 14
Commissioning and maintenance of the fault clearing system
14.3.2.8
Restoring
Maintenance is very important to improve the availability of the protection system by
detecting failures before the protection is required to operate. There is however little point
in testing healthy equipment and then putting it back into service with an open terminal,
with a removed fuse or open miniature circuit breaker with an open connection, wrong
setting etc.
Thus a list should be prepared of all items disturbed during test so that all can be put back
into service quickly and without overlooking something. It should be put back into service
item by item and signed by the responsible engineer.
218
Section 15
Fault tracing and repair
15.1
Fault tracing
15.1.1
Description
INT Fail
OFF / ON
INT Warning
OFF / ON
NUM Fail
OFF / ON
NUM Warning
OFF / ON
219
Section 15
Fault tracing and repair
HMI Signal Name:
Status
Description
ADMnn
READY / FAIL
BIMnn
READY / FAIL
BOMn
READY / FAIL
IOMn
READY / FAIL
MIMn
READY / FAIL
RTC
READY / FAIL
Time Sync
READY / FAIL
Application
READY / FAIL
RTE
READY / FAIL
IEC61850
READY / FAIL
LMD
READY / FAIL
LDCMxxx
READY / FAIL
OEM
READY / FAIL
Also the internal signals, such as INT--FAIL and INT--WARNING can be connected to
binary output contacts for signalling to a control room.
In the IED Status - Information, the present information from the self-supervision function
can be viewed. Indications of failure or warnings for each hardware module are provided,
as well as information about the external time synchronization and the internal clock. All
according to table 21. Loss of time synchronization can be considered as a warning only.
The IED 670 has full functionality without time synchronization.
220
Section 15
Fault tracing and repair
15.1.2
When an internal fault has occurred, you can retrieve extensive information about the
fault from the list of internal events available in the SMS part:
TRM-STAT TermStatus - Internal Events
The list of internal events provides valuable information, which can be used during
commissioning and during fault tracing.
The internal events are time tagged with a resolution of 1 ms and stored in a list. The list
can store up to 40 events. The list is based on the FIFO principle, when it is full, the oldest
event is overwritten. The list cannot be cleared; its content cannot be erased.
The internal events in this list not only refer to faults in the IED, but also to other activities,
such as change of settings, clearing of disturbance reports, and loss of external time
synchronization.
The information can only be retrieved with the aid of the PST software package. The PC
can be connected either to the port at the front or at the rear of the IED.
These events are logged as internal events.
Table 22:
Event message:
INT--FAIL
Description
Off
INT--FAIL
INT--WARNING
Off
Off
Off
INT--NUMWARN
IOn--Error
INT--NUMFAIL
INT--NUMWARN
INT--WARNING
INT--NUMFAIL
Generating signal:
Off
IOn--Error
221
Section 15
Fault tracing and repair
Event message:
Description
ADMn-Error
Off
Off
ADMn-Error
Generating signal:
ADMn-Error (reset event)
ADMn-Error (set event)
MIM1-Error
MIM1-Error
INT--RTC
Off
INT--RTC
INT--TSYNC
Off
INT--TSYNC
INT--SETCHGD
DRPC-CLEARED
The events in the internal event list are time tagged with a resolution of 1 ms.
This means that when using the PC for fault tracing, it provides information on the:
15.2
Repair instruction
Never disconnect the secondary connection of a current transformer
circuit without short-circuiting the transformers secondary winding.
Operating a current transformer with the secondary winding open will
cause a massive potential build up that may damage the transformer and
may cause injuries to humans.
222
Section 15
Fault tracing and repair
An alternative is to open the IED and send only the faulty circuit board to ABB for repair.
When a printed circuit board is sent to ABB, it must always be placed in a metallic, ESDproof, protection bag. The user can also purchase separate replacement modules.
Strictly follow the company and country safety regulations.
Most electronic components are sensitive to electrostatic discharge and latent damage
may occur. Please observe usual procedures for handling electronics and also use an ESD
wrist strap. A semi-conducting layer must be placed on the workbench and connected to
ground.
Disassemble and reassemble the 670 IED accordingly:
1.
2.
3.
4.
5.
6.
7.
8.
9.
15.3
Repair support
If a IED 670 needs to be repaired, the whole IED must be removed and sent to an ABB
Logistic Center. Please get in touch with your local ABB representative to get more
details.
223
Section 15
Fault tracing and repair
15.4
Maintenance
The IED 670 is self-supervised. No special maintenance is required.
Instructions from the power network company and other maintenance directives valid for
maintenance of the power system must be followed.
224
Section 16
Glossary
Section 16 Glossary
About this chapter
This chapter contains a glossary with terms, acronyms and abbreviations used in ABB
technical documentation.
16.1
Glossary
AC
Alternating current
A/D converter
ADBS
ADM
ANSI
AR
Autoreclosing
AngNegRes
Setting parameter/ZD/
ArgDirAngDir
Setting parameter/ZD/
ASCT
ASD
AWG
BBP
Busbar protection
BFP
BIM
BOM
BR
BS
British standard
BSR
BST
C37.94
225
Section 16
Glossary
226
CAN
CAP 531
CB
Circuit breaker
CBM
CCITT
CCM
CCVT
Class C
CMPPS
CO cycle
Close-open cycle
Co-directional
COMTRADE
Contra-directional
CPU
CR
Carrier receive
CRC
CS
Carrier send
CT
Current transformer
CVT or CCVT
DAR
Delayed auto-reclosing
DARPA
DBDL
DBLL
DC
Direct current
DFT
Section 16
Glossary
DIP-switch
DLLB
DNP
DR
Disturbance recorder
DRAM
DRH
DSP
DTT
EHV network
EIA
EMC
EMF
EMI
EnFP
ESD
Electrostatic discharge
FOX 20
FOX 512/515
Access multiplexer
FOX 6Plus
G.703
GCM
GI
GIS
GOOSE
GPS
GSM
HDLC protocol
HFBR connector
type
227
Section 16
Glossary
228
HMI
HSAR
HV
High voltage
HVDC
IDBS
IEC
IEC 60044-6
IEC 60870-5-103
IEC 61850
IEEE
IEEE 802.12
IEEE P1386.1
IED
I-GIS
IOM
Instance
IP
IP 20
Section 16
Glossary
IP 40
Ingression protection, according to IEC standard, level IP40Protected against solid foreign objects of 1mm diameter and
greater.
IP 54
IRF
IRIG-B:
ITU
LAN
LIB 520
LCD
LDCM
LDD
LED
LNT
LON
MCB
MCM
MIM
Milli-ampere module
MPM
MVB
NCC
NUM
Numerical module
OCO cycle
Open-close-open cycle
OCP
Overcurrent protection
OEM
OLTC
OV
Over voltage
Overreach
229
Section 16
Glossary
reach. The relay sees the fault but perhaps it should not have
seen it.
PCI
PCM
PCM 600
PC-MIP
PISA
PMC
POTT
Process bus
Bus or LAN used at the process level, that is, in near proximity
to the measured and/or controlled components
PSM
PST
PT ratio
PUTT
RASC
RCA
REVAL
Evaluation software
RFPP
230
RISC
RMS value
RS422
RS485
RTC
RTU
SA
Substation Automation
SC
SCS
SCT
SLM
Section 16
Glossary
SMA connector
SMS
SNTP
SPA
SRY
ST
Starpoint
SVC
TC
Trip coil
TCS
TCP
TCP/IP
TEF
TNC connector
Underreach
231
Section 16
Glossary
U/I-PISA
UTC
UV
Undervoltage
WEI
VT
Voltage transformer
X.21
3IO
232