INDEX
DESCRIPTION
PAGE NO.
---01
SECTION 2 INSTALLATION
---10
---20
SECTION 4 COMMISSIONING
---34
---39
---71
---81
---92
---93
---96
---101
---103
SECTION 1
PAGE NO.
GENERAL INTRODUCTION
1) TRANSPORT, PACKING & DESPATCH
a) GENERAL
---2
b) PACKING
---3
c) LIFTING
---4
d) JACKING
---5
e) STORAGE
---5
f) SHIPMENT OF OIL
---6
---6
---7
i) PLACING IN POSITION
---8
GENERAL INTRODUCTION:
Transformer is a static equipment, which converts electrical energy from one voltage to
another. As the system voltage goes up, the techniques to be used for the Design,
Construction, Installation, Operation and Maintenance also become more and more critical.
If proper care is exercised in the installation, operation, maintenance and condition monitoring
of the transformer, it can give the user trouble free service throughout the expected life of
equipment which is of the order of 20~25 years. Hence, it is very essential that the personnel
associated with the installation, operation or maintenance of the transformer are thorough with
the instructions provided by the manufacturer.
This Manual contains general descriptions about Transformers & specific details about the
particular contract against which the Transformer is supplied. Also, it contains instructions
regarding the safety aspects, erection, commissioning, operation, maintenance & trouble
shooting of large capacity Power Transformers.
a) GENERAL
Depending on the restriction imposed by the weight and transport dimensions, the transformer
will be despatched either in oil filled or nitrogen gas filled condition.
In case of transformer despatched without oil, the transformer will be pressurised with dry
nitrogen gas to minimise the likelihood of condensation or moisture entering the tank.
Transformers are supplied, fitted with nitrogen gas cylinder to maintain positive pressure during
transportation and storage before erection.
While transformers are in transit, gas pressure must be checked on daily basis and any loss of
pressure must be made up by feeding gas from the cylinder. For allowable range of pressure at
various ambient temperatures, please refer to Fig. 2.I.
Accessories and cooler are despatched separately. All oil pipes and chambers are despatched in
sealed condition to avoid entry of water during transportation and storage.
b) PACKING
When any internal part like tap changer, CT's etc. are removed from the main body for
transportation, they shall be despatched in tanks filled with oil or dry nitrogen gas or suitable
measures are taken so that they do not absorb moisture.
All fragile parts such as temperature indicators, oil level gauges etc. shall be carefully packed to
avoid breakage in transit.
Air cell type conservator shall be despatched with air cell mounted inside the conservator and
inflated with air at a slightly positive pressure so that it remains fully tight inside the
conservator. This is to avoid relative movement of air cell inside the conservator during transit
and to avoid damages to air cell during handling.
All blanking plates, valves guards etc., which are used exclusively for transportation are painted
with a different colour shade than the transformer (normally post office red) and shall be
preserved for future use.
c) LIFTING
Transformers should be lifted only by using the lifting bollards provided on the main body for
the purpose. All the lifting bollards should be used simultaneously. Care should be taken to use
the correct size of sling for lifting and the lifting angle should not exceed 600.
Safe loads of wire ropes and the multiplying factor to be used corresponding to the lifting
angles are shown in Fig. 2.2
MULTIPLYING
FACTOR FOR
DIFFERENT LIFTING
ANGLES
Lifting Multiplying
Angle
Factor
Lifting Angle
Slinging Angle
0
20
40
60
Fig. 2.2
Correct method of slinging
1.000
1.015
1.065
1.155
6
12
16
20
24
28
32
36
40
44
56
64
70
600
1,300
2,300
3,500
5,000
7,000
9,000
11,000
14,000
17,000
24,500
33,500
40,000
d) JACKING
For the purpose of jacking, only the jacking pads provided on the tank are to be used. Capacity
of Jacks should be at least 1.5 times the weight of transformer. Put sufficient wooden/steel
packing below the jack to support the weight. Do not lift more than 30 mm at a time. Use all
jacks simultaneously. Jacks should not be left in the loaded position for long time. Transformer
should be handled only in the normal upright position.
Rollers should be used for shifting the transformer from one place to other. Roller axles or
radiators should not be slinged for the purpose of towing. Pulling holes provided on the tank for this
purpose should only be used.
Transformers of higher ratings are provided with four jacking pads. Each jacking pad is designed
to take approximately 25% of the total load. Under no circumstances, jacking should be used
anywhere else other than these specially provided pads.
e) STORAGE
On receipt of the Transformer at site, it is desirable to install and commission the transformers
with minimum delay. In case, this is not possible, the silica-gel breather should be fitted. The
breather incorporates an oil sealing device which must be filled with oil to the marked level to be
effective. A periodic watch should be kept on the silica-gel breather to ensure that the gel is blue.
The gel should be replaced or dehydrated immediately on its tunings pink.
It is advisable to check the condition of silica gel during storage at least once a week and Break
down Voltage (BDV) of oil at least once in a month and should be maintained at a level of 50 KV. It
is desirable to keep the transformer energised even at a low voltage so that the oil temperature is
about 10 to 15 C higher than the surrounding ambient temperature.
Accessories like, bushings, buchholz relay, dial type temperature indicator, terminal box,
radiators, all pipe work, should be stored indoors till such time they are not required. It they are
not stored properly, they are likely to be damaged. The conservator pipe work and radiators are
despatched with blanking plates and these are to be stored with their blanking plates, in
position.
It these are stored for a longer period like six months or so, it advisable to flush them with clean
transformer oil before use.
f) SHIPMENT OF OIL
Transformer oil is despatched to site in sealed steel drums or tankers. When oil is filled in
drums, there should be sufficient air space to allow for expansion and contraction of oil due to
variations in temperature. Drums should be stacked only in horizontal position with the oil.This
will avoid collection of water on top of the drum, which may be sucked in by the vacuum
created inside the drum due to the expansion and contraction of oil owing to changes in
ambient temperature.Due to any reason, if the drums are kept in vertical position, drums should
be covered with polythene or tarpaulin sheet to avoid risk of water getting collected on top and
eventually leaking into the drums.
Filter holes and air release holes shall be in one horizontal line. This will avoid breathing in of
moist air. If there is any leakage of oil it can easily be identified.
When oil is transported in tankers, there should be storage tanks of sufficient capacity available
at site. Such tanks should be fitted with dehydrating breathers.
STORAGE OF OIL DRUMS
45
OIL DRUMS
OIL FILTER HOLE
Inspect all packing cases and loose components for damage or missing items.
Check whether the transformer has arrived at site with a positive gas pressure in case of
despatch without oil. In case of despatch of main body in oil filled condition, the oil level should
be checked. One transport oil level gauge is welded near the top of the tank for indicating the
level of oil in the tank.
Should the transformer arrive at site without pressure (owing to gas leakage) it must be
assumed that moisture has entered the tank and that the moisture will have to be driven out.
In such cases the manufacturers advice must be sought.
Confirm that case numbers match with the packing list. Check their contents tally with the
packing list if the packing case is damaged.
IMPORTANT: If any scratches or damage to the paint is noticed on receipt of Main body or
Accessories, touchup painting should be done immediately over the damaged area. For
procedures of touchup painting, refer to Clause 4.22: Touchup Painting at site.
h) UNLOADING OF MAIN UNIT
In cases where the substations are having adequate crane facility; the transformer is unloaded
by crane. Alternatively, mobile cranes are used. Where no crane facility is available a trench is
due to a depth equal to height of the trailer platform and the transformer is slide to position. If
this also is not possible the transformer is unloaded into a sleeper platform and gradually
lowered to plinth level. The sleeper platform level is to be at a slightly higher level to allow for
the increase in height of the trailer while the load is released due to the springs getting relaxed.
Winches are to be used for putting the transformer into position.
Lift the main body of the transformer with a mobile crane and wire ropes. The crane capacity
must be at least 10% higher than the weight of consignment. Lifting angle of ropes should be
limited to 30 deg. to vertical.
Unloading must be done with maximum care, avoiding any jerking movements or dropping.
Use only the lifting bollards/hooks for slinging while lifting.
For lifting with hydraulic jacks, the transformers are provided with jacking pads dimensioned for
lifting the complete transformer filled with oil.
If the foundation of the transformer is not ready and if the transformers are to be unloaded
temporarily, it should be done on levelled hard surface.
Under base of the transformer should not rest on the ground as it will lead to rusting of the
transformer.
i) PLACING IN POSITION
If foundation is ready and if rail link between unloading point/storage place is available, then
the main body of the transformer must be moved on its own rollers to the foundation where the
transformer is to be erected finally.
If the transformer is not provided with rollers and if it is to be erected on its skid base, the
transformer must be slid to its final position using greased steel plates to protect the plinth
surface and make movement easier. The plates should form a continuous surface and it must
clear the final jacking areas.
The transformer must be pulled by using slings and winches as shown in Fig. Use only the
specified haulage lugs for pulling. Pulling capacity of winches should be more than (Main body
weight x 0.15/4) tons. Pulleys should have a capacity of (Main body weight x 0.15/2) tons.
When jacking, position the jacks under specified jacking pads only. When jacking, ensure that
all four jacks are operated simultaneously.
Before lowering, clean all grease dirt etc. from the under base of the transformer.
SECTION 2
PAGE NO.
2) INSTALLATION
a) LOCATION
---11
b) FONDATION
---11
---11
---11
(i)
MAIN TANK
---11
(ii)
BUSHINGS
---11
---11
---14
(v)
BREATHERS
---14
(vi) RADIATORS
---14
---15
---15
e) AIR RELEASE
---15
---16
---17
---18
---19
10
2) INSTALLATION
a) LOCATION
The transformer should be kept in a well ventilated place, free from excessive dust,
corrosive fumes etc. Adequate ventilation is necessary for tank and radiators so that they can
dissipate heat. There should be clear space of about 1.25 m on all sides of the transformers if it
is enclosed in a room.
b) FOUNDATION
Foundation should be firm, horizontal and dry. where rollers are fitted, suitable rails should be
provided.
c) PROVISIONS FOR OIL DRAINING:
Necessary provisions for oil draining; in the event of a fire, should be made by way of Oil
Soak Pits. Fire separation walls should also be provided when necessary.
d) ASSEMBLY OF DISMANTLED COMPONENTS:
Various components dismantled for transportation should be duly assembled.
o
MAIN TANK
Keep the main tank in its permanent position of operation. Lock the rollers to prevent any
accidental movement on rails. Draw an oil sample from the bottom of the tank and test it for
Break-down-Voltage (BDV).
o
BUSHINGS:
Clean the bushings and check that there are no hair-cracks or other damages. Test IR value
of each bushing with a 500V Megger. It should be 100 M ohms or greater. Note details of
Bushings in the "Commissioning Report." Mount all the bushings, Ensure that the test cap is fully
tightened, thus positively grounding the same. Adjust the Arcing Horn Gaps in accordance with
the Insulation Co-ordination.
o
If the M.O.G. is provided with a locking lever, it should be removed. Mount the conservator. When
there is an OLTC, its conservator is sometimes provided separately or by making a partitioned
compartment in the main conservator. OLTC conservator, if separate, should also be mounted.
Mount the conservator as shown in G.A. Drawing.Very often the small conservator for on
load tap changer is attached to the main conservator.
11
Usually the main conservator is provided with Magnetic Oil level Gauge having low oil level
alarm contacts and OLTC conservator is provided with oil sight window.Magnetic oil level gauge
shall be mounted after attaching the float to the gauge. Check and confirm free movement of
float arm and proper locking of float to the float arm.Mount all valves as shown in GA drawing
on the conservator.
Mount the connecting pipe with Buchholz relay from the main tank to the conservator. Ensure
direction of Buchholz Relay by the direction of arrow on Buchholz Relay towards conservator.
Mount breather connecting pipes and silica gel breathers for the main tank and OLTC
conservators.
METHOD OF MOUNTING FLEXI SEPARATOR (AIR CELL) INSIDE THE CONSERVATOR
Set up the air cell in side the conservator. Care should be taken to see that the hooks on
air cell are properly engaged in the brackets provided in side the conservator.
Inflate the air cell at a pressure as shown in the instruction plate (DO NOT APPLY
EXCESS PRESSURE AS IT MAY DAMAGE THE AIR CELL) through the breather connection
pipe. Follow the instructions given in the Instruction Plate fixed on the transformer.
12
The conservator with Air Cell is pressure tested and despatched from the factory at a
slightly positive pressure. Confirm that there is no oil leakage.
Keep air release valves open. Fix air filling adapter on breather pipe and inflate the air
cell at an air pressure indicated on the INSTRUCTION PLATE affixed on the transformer
and hold air pressure.
Open the air release valves and start oil filling from the bottom filter valve of the
transformer.
Observe the air release valves and as soon as oil starts overflowing, close the air release
valves one by one. Stop oil filling when all air release valves are closed.
Continue oil filling and observe the Magnetic Oil Level Gauge (MOLG)
Stop the filling when the needle of MOLG shows the level corresponding to the ambient
temperature at the time of filling.
CAUTION: Do not open any of the air release valves after completion of oil filling. If air release
valve is opened, air will enter and oil level will drop.
The plain oil level gauge on the end cover of the conservator should indicate full oil level
always. If air enters the conservator, it can be seen by a fall in the oil level in plain oil level
gauge.
The plain oil level gauge should be monitored on regular basis.
FILLING PROCEDURE UNDER VACUUM IN CONSERVATOR
The conservator, with its separator, being set up and plugged in above the transformer, is
connected to its oil filling reserve by a pipe in its lower part.
13
Proceed as follows:
Create a vacuum in separator.
With the same source of vacuum, create a vacuum in the conservator.
Open the oil filling valve of the transformer. Because of the vacuum in the conservator,
the oil level rises automatically.
Stop the oil filling once the required volume in the conservator is attained.
While maintaining the conservator under vacuum, allow Dry Air or Nitrogen gas to enter
into the internal part of the separator. Then, the separator inflates by itself, and takes all
the free space due to the fact that the conservator was not completely full. In particular,
during the operation, the oil is going to rise to the top of the conservator.
Inflate the separator at a maximum as shown in the INSTRUCTION PLATE.
Check on the vent-holes, and confirm that there is no more air in the conservator or, if
necessary, adjust the level.
o
BUCHHOLZ RELAY:
Buchholz Relay floats are tied to prevent transit damage. They should be released. Also If 'Test'
lever is provided, it should be in the working position.
o BREATHERS:
"If OLTC is provided, it may have its own separate breather."Check that the colour of Silica Gel in
main breather is Blue. Remove the rubber cap closing the breather pipe and it the breather. Fill
oil in the oil cup and remove the seal which closes the breather opening. Similarly mount the
OLTC breather.
o RADIATORS:
i) Radiators are to be assembled only one at a time. Oil required to fill in the radiators is sent
separately in drums. Test oil sample from each drum for BDV. Ensure it is more than
minimum specified in I.S. 1866 for new Transformer.
ii) Fill the conservator full using an oil filter machine, if available.
iii) Clean one radiator externally. Remove blanking plates and clean the gaskets and radiator
flanges. If gaskets are damaged, use spare gaskets.
14
iv) If blanking plates are not in position and it is suspected that foreign material might have
entered the radiators, clean them internally by flushing fresh and clean transformer oil.
v) Oil might seep through the tank side radiator valves and be retained by the blanking
plates. This oil should be collected in a clean container at the time of removing top and
bottom blanking plates.
vi) Bring the radiator flanges close to the flanges on the tank. Ensure that tank gasket is in
position. Fit by means of bolts, nuts, spring washers etc.
vii) Open the bottom radiator valve using the operating handle. Gradually unscrew the air
release plug on the top of the radiator, until air starts escaping. Air release plug should not be
removed from the engaging threads as it would be difficult to control oil coming out of it.
When oil comes out steadily from the air release plug and no more air comes through, close
the air release plug. Open the top radiator valve. Oil level in the conservator would now
have fallen. Check that there is no oil leakage from the radiator itself and the gasket
joints. Restore the oil level and assemble the next radiator in the same manner.
o
MARSHALLING BOX:
i) Marshalling box should be fitted in Position. Pockets of O.T.I. & W.T.I., should be filled with
transformer oil. Bulbs of O.T.I. & W.T.I. should be fitted in position in their respective pockets.
ii) Set the 'Alarm' & Tip' contacts of O.T.I. & W.T.I., at required values. O.T.I, setting of A=85C
& T=95C W.T.I., setting of A=95C & T=105C are considered good. They can be worked out
to suit local conditions.
o
CABLE BOX
When Cable Boxes are provided they should be mounted and cable terminations done. Oil filled
cable-boxes should be duly filled with oil. In case of "Bus-Duct" connections, transformer is provided
with a flange to receive the bus-duct. Due to connection and fitting should be done to over-head line
by a terminal connector.
e) AIR RELEASE:
Release air by slowly unscrewing Air Release Plugs provided at Bushings, Bushing Pockets, Buchholz
Relay, Main Tank Cover, Oil Surge Relay etc. From plain porcelain bushing of 11, 22 8t 33 KV, air can
be released by loosening the nut pressing the rubber gasket and pressing the metal part down.
15
Table -1
Selection of Samples from drums
No. of Drums in a Batch
2 to 5
6 to 20
21 to 50
61 to 100
101 to 200
10
201 to 400
15
20
Samples should be collected from the bottom of the drums for testing.
If oil is received in containers, oil sample shall be collected through the sampling valve at the
tank outlet or by means of thief dipper as suggested for sampling of oil from drums. The
container should be allowed to stand for atleast one hour before drawing the sample.
Conduct the following tests for ascertaining the quality of oil.
Tan delta
Resistivity
16
If oil does not meet the specified criteria, oil should be filtered and stored in the oil storage tank
before filling in to the transformer.While pumping oil from the barrels, the barrels may be tilted
suitably to ensure that complete oil is taken out from each barrel.
For high voltage jobs of 400 kV and above, dry air having dew point below -400C should
be purged inside the tank during internal assembling work.
Transformer oil should be tested for B.D.V. before filling and it should be more than
55kV at 2.5 mm gap.
Extreme care shall be taken against any foreign objects falling inside the transformer
tank during inside working.
Keep only one man hole open at a time and close it as soon as possible. Avoid inside
working on rainy days.
Earthwork near the transformer should be avoided when internal assembly is in progress
to avoid ingress of dust.
17
Any tools taken inside should be tied by string or cotton tape to the person who is using
the same. No. of tools shall be counted and recorded before and after each days work in
order to ensure that no tools are left inside.
Gaskets used are of synthetic rubber bonded cork material. These are to be compressed
to 50 ~ 60% of its original thickness. Over tightening and under tightening of gaskets
should be avoided as these may cause oil leakage and shortening of gasket life.
Generally for oil forced cooled transformers radiators will be mounted in a separate
cooler bank.
Since cooler headers are provided with butter fly type shut off valve, oil from main body
need not be drained for assembling cooler.
Check and ensure that level of all the foundations for cooler support are in same level as
that of the top surface of rails. Level difference should be compensated by putting shims
if the level is lower and chipping the concrete foundation if the level is higher.
Fix cooler header mounting frames as per dimensions shown in General arrangement
and Foundation Plan drawing.
Mount cooler headers loosely. Final tightening to be done only after proper alignment.
Top and bottom butterfly valves of all radiators should be in the vertical line. This should
be confirmed by a plumb.
Tighten the cooler frame foundation bolt, and clamping bolts of cooler headers and pipe
connections.
While mounting the oil pump and oil flow indicators, care should be taken to ensure the
arrows indicating the oil flow direction are towards the transformer tank.
18
While mounting radiators care should be taken to ensure that the weight is balanced.
In case of separately mounted coolers, the oil pipes are provided with expansion joints.
Tack welded bars on expansion joints should be removed.
Fix the fan mounting frames and fans as indicated in the general arrangement drawing.
19
SECTION 3
PAGE NO.
---21
---21
---21
d) LIFTING LUGS
---22
e) VALVES
---22
f) BUSHINGS
---22
g) CABLE BOXES
---24
h) BUSDUCT
---24
i) MARSHALLING BOX
---24
---25
k) TEMPERATURE INDICATOR
---26
---27
---27
---28
---28
---28
---29
---30
---31
20
THE TRANSFORMERS MUST BE ISOLATED FROM ALL THE LIVE LINES, BEFORE OPERATING THE SWITCH.
Operating the switch when transformer is energised, will damage the switch contacts due to
severe arcing between the contacts and may damage transformer winding. When the switch
handle is provided on the side wall, it is necessary that Switch handle assembly is dismantled
before untanking.
ii) Off-Circuit Ratio Changing links:
Sometimes links are provided inside the transformers tank to obtain required voltage ratio.
Links are required to be loosened and fixed in new required position as given in R & D Plate.
Links are accessible from the inspection cover.
iii) On-Load Tap Changer:
The on-load tap changer is an optional fitting. The on-load tap changers are provided with local
manual control, local electrical control and remote electrical control. The automatic voltage
regulation can also be provided as an optional fitting. The tappings are located on high voltage
winding.
c) EARTHING TERMINALS:
The core laminations assembly is connected to core clamping fame which is in turn connected
21
to the tank. Two earthing terminals are provided on the transformer tank. The earthing
terminals should be connected to the earthing.
d) LIFTING LUGS:
Two/Four lifting lugs of adequate capacity are provided on tank sides/top cover to lift fully
assembled transformer filled with oil. All lugs are designed for simultaneous use and must be used
accordingly. Two/Four lifting lugs are all heavy fittings are also provided with individuals lifting lugs.
e) VALVES:
Every transformer is provided with drain cum filter valve at bottom of the tank, and filter valve at
top of the tank. Valves are fitted with plugs/blanking plates to stop oil coming out.
Mainly two types of valves are provided.
i) Wheel Valves.
ii) Butterfly Valves.
The Wheel Valves are used either with female screw threads or with flanges. These are of
gun-metal/cast iron type.
Generally, one isolating valve also known as shut off valve is provided for transformer up to
2000 KVA between conservator and buchholz relay. The Butterfly type cast-steel valves with the
machined flanges are used at points of connection between tank and detachable radiators.
f) BUSHINGS:
Oil Communicating Type:
Transformers windings are connected to the external circuit through terminal bushings. The
bushings are installed on the cover or, on side walls of the transformer tank. The lower ends of
the bushing protrudes into the tank and at both their ends are provided with suitable fasteners to
connect the line leads inside the transformers an external conductors outside it.
The shape and size of the bushings depend on the voltage class, type of current. Bushings of
1000 Volts are of two piece construction without arcing horns, whereas all other bushings are of
single piece porcelain type. Assembly and dismantling of single piece type bushing is possible
without disturbing the active part. For bushings of two piece constructions, tank cover is
required to be removed for necessary access to the inner (lower) end of the bushings. These
22
Open the bushing case carefully and check it for transit damage and clean the bushing
thoroughly.
(ii)
Remove the locating pin. The cable bolt to be used on the unit is brazed to the end of
the flexible draw through type lead mentioned above.
(iii)
Remove the blanking plate and uncoil the daw through type lead. Tie the Flexible Steel
wire to the head of the bolt fixed temporarily on the top of the cable bolt to facilitate
the threading of the main lead through the bushing tube and at the same time
preventing the lead from falling bank into the tank.
(iv)
Suitably raise the bushing and remove the protective cover at the oil end of the
bushing.
(v)
Check that Oil Level in the bushing is appearing in the Oil Level indicating glass. In
case it is not visible, do not mount that bushing. Also do not attempt to fill oil at site
as such bushing is most likely to fail in service.
(vi)
During the lowering operation, thread the flexible steel wire through the inside tube of
the bushing and pull it. Continue the operation till the bushing rests on its flange
pocket. Bolt the two flanges and remove the slings.
(vii)
Hold the cable bolt in position, remove the flexible wire and insert the locking pin to
hold the cable bolt remove the slings.
(viii)
For removing air from the central tube after oil filling, unscrew the terminal cap and
23
Fix upper and lower arcing horns and adjust the gap setting as per the required
Insulation Co-ordination.
g) CABLE BOXES:
Cable boxes are designed for receiving and protecting cable ends. Insulating paper is most
hygroscopic and all paper insulated cable ends must be protected by suitable insulating
compound. These cable boxes are provided with brass wiping glands and are designed with
clearances inside the box suitable for compound filling. The cable box in such case must be filled
with compound as marked as indicated in the drawling.
Cable boxes for PVC are XLPE cables are designed with air clearances and hence these boxes are
not required to be filled with compound.
Cable boxes of 3.6 KV and above are provided with detachable gland plates. Earthing terminals
are also provided on these cable boxes for earthing the armouring of individual cables.
h) BUSDUCT:
Some users prefer connections to load by means of busduct. Busduct is supplied by some other
agency. However, we provide suitable flanges around transformers bushings for receiving the
busduct.
The level of the busduct flanges from ground/rail level is indicated in the General Arrangement
drawings of the transformer. The complete details of busduct flange is furnished by us giving
complete dimensional details for the matching flanges, bolt spacing, bushing terminal details, etc.
i) MARSHALLING BOX:
The transformer is provided with certain fittings directly mounted on the transformer at various
locations. These fittings are having electrical contacts or terminals which are required to be
connected to the protection schemes to give alarm/annunciation under abnormal conditions and
if further required to disconnect the transformer form mains. In order to facilitate connections
of all such devices to the protective scheme, the cable form all such contacts are wired up to a
weather-proof terminal box, This box called marshalling box, is also used for housing Oil
Temperature Indication (OTI) and winding Temperature Indicator (WTI).
The capillaries from OTI & WIT come out from the bottom of the Marshalling box through suitably
recessed gland plate thus preventing ingress of dust.
24
It has a detachable gland plate with glands through which cables enter and leave. It has a rain
shed provided on top to prevent rain falling directly over it. All these provisions make Marshalling
Box a Weather-Proof enclosure.
Before starting the erection work of Condenser Bushing, lift the Bushing from its crate
and keep it vertical and check the oil level. Confirm that oil level is up to the centre of oil
sight window of Bushing.
If oil is drained from the tank a continuous supply of dry air should be ensured while
removing the blanking plates and fixing the bushing turrets and bushings.Dry air shall
have a dew point of -40OC or better.
Total exposure time should not exceed 8 hrs. At the end of each days work, blank off all
openings and pressurise with dry air.
If weather is bad (rain, snow or fog) the tank should not be opened unless adequate
shelter is provided.
25
For details of connections from winding to the bushing please refer to the specific drawing
and suppliers catalogue given in the instruction manual.
Ensure that a fresh gasket is used while mounting the bushing.Ensure that the air release
pipe connections are oriented towards the correct directions.
Bushing shall be mounted in the order of B, A, C or B, C, A.
While mounting the bushings, ensure that the oil level gauge is oriented away from the
transformer.
While lowering draw lead type condenser bushing the cable shall be held tightly by using
strong steel/plastic rope. Remember that dropping of cable can cause injury to the
personnel and damage to the transformer.
Check and ensure that secondary terminal of turret mounted C.T. if any are connected to
the proper terminals on the terminal board.
Check and ensure that secondary leads of C.T's. mounted inside the transformer are
connected to the proper terminals in the terminal board.
k) TEMPERATURE INDICATORS
Sensing elements of oil and winding temperature indicators are to be fitted on to the
thermometer pockets welded on the top cover of the transformer.
Before mounting the thermal sensing bulbs, inside of the pocket should be cleaned
thoroughly and filled with transformer oil upto a depth of half the pocket.
Care should be taken not to damage the capillary tubing. Capillary tubes should be
clamped properly.
RTD sensor element and heater coil are fitted on the cover.
CT leads shall be connected on one side and sensor leads are taken from the other side.
RTD instruments are mounted on the remote panel in the control room.
26
Gasket materials used are either Synthetic Rubber Bonded Cork (SRBC) sheet or nitrile
rubber.SRBC material conforms to RC-70C of IS : 4253(Part II); thickness used are 6.0
mm and 10.0 mm. Gaskets should be stored in stress free condition and must be
protected from moisture, oil and grease.
27
Synthetic rubber bonded cork sheets once used should not be used again. Gasket seating
surfaces should be smooth and free from scratches, oil, grease, dirt etc.
Gasket should be properly located before tightening. Gasket joints are designed with
40~50% compression.
Over tightening will cause the gasket material to loose its properties and under tightening
maynot prevent oil leakage.
Drain oil & create vacuum of 200 torr inside the tank, close the valve between vacuum
pump and tank and stop the pump and hold the vacuum. There should be no appreciable
loss of vacuum over one minute.
Start the pump and open the valves and continue till a vacuum of 10 torr is achieved.
Close vacuums valve and stop the pump. There should not be an increase of pressure of
more than 1 torr over half an hour.
If results are satisfactory, restart the vacuum pump open the valves and continue
pumping to obtain a vacuum of 1 torr or better and maintain this vacuum for more than
24 hrs. before and during subsequent oil filling operations.
28
After draining the oil completely from the transformer, vacuum should be pulled from the
oil filling hole on main conservator. If the conservator is fitted with air cell, pressure
equalising connection is required to avoid damage to the air cell.
Before starting vacuum, all bolted connections shall be checked. Radiator valves shall be
kept open.
A transparent vinyl hose shall be connected to the bottom sampling valve for indicating
the oil level.
If explosion vent is provided, the pressure shall be equalised on either side of the
diaphragm to avoid damage to the diaphragm.
Vacuum shall be maintained for 6 hours.
Oil may be injected through the bottom filter valve until the level reaches 35OC marking
on the Magnetic Oil Level Gauge of the conservator.
Natural rubber hose shall not be used as sulphur in the rubber may react with oil.
Oil inlet valve shall be closed and after one hour the vacuum shall be broken. Oil level
indicating vinyl hose can be removed by closing the bottom sampling valve.
Vacuum gauges may be detached and breathers assembled in its position.
Pressure equalising connection provided for explosion vent diaphragm and OLTC diverter
chamber shall be removed.
q) TOUCH UP PAINTING AT SITE
Any damage to the painting of the transformer and accessories shall be made good after
erection work is completed.
If a welding has been done on the transformer at site, the paint film burnt by the welding
shall be removed by wire brush or metal spatula. Remove the rust by wire brush and
emery paper #80 / #100.
Wash away the oil, grease, dirt and dust by using suitable solvent and dry it up.
Polish the surface to be painted by using emery paper #80 /#100 and then clean the
surface.
29
After cleaning, stir the ready mixed rust resistant primer paint 'Yellow Zinchromate' or
'Red Oxide' primer paint. Before applying the paint, confirm the correct viscosity.
Apply the paint uniformly by using a brush. drying time for the paint is normally 4 hours.
After the first coat of paint is dried up, mix and stir the finish coat paint to the desired
viscosity and apply by brush uniformly. Drying time of finish coat paint is normally 6
hours.
Inspect the repainted surface and do re-painting if the painting is not uniform and
unpainted surface is visible.
: 50 ~ 55 sec.
: 20 ~ 25 sec.
: 55 ~ 60 psi.
: 24 Hours.
30
31
32
The pump set is a single stage axial flow gland-less type, integral with the drive motor.
It has been specifically designed for forced circulation of oil through the cooling system
of large transformer & allows thermo phonic flow.
It is designed for flange mounting directly to the pipe circuit of transformers in either
horizontal or vertical position.
All the moving parts are completely enclosed and gasket thus permitting open air
installation, without any need for protective cover. It is compact in design.
The Nameplate gives details of pump and motor output along with respective
connecting pipe size.
33
SECTION 4
PAGE NO.
4) COMMISSIONING
a) INSPECTION MAINTENANCE OF LOG SHEET
---35
b) PHYSICAL CHECKS
---35
---36
d) RATION TEST
---36
---37
---37
---37
---37
i) OPERATION CHECK
---38
---38
34
4) COMMISSIONING
35
Check & confirm that the test tap caps of all Condenser type Bushings are tightened.
Remove the cap provided at the bottom of silicagel breather for the transportation
purpose.
Arcing horns if provided are set to the specified gap
All earthing connections are tightened properly.
Anti condensation heaters are functioning correctly.
Rating and connection diagram plates and other marking labels are fitted properly.
All isolating switches are set at ON position.
Cooler control switch is set to AUTO.
All alarm circuits are reset.
OLTC to Transformer equalising pipe shall be removed after oil filling under vacuum and
the opening shall be coverd by blanking plate supplied with the transformer.
c) INSULATION RESISTANCE CHECK
o
Check and record insulation resistance between pair of windings and windings and earth
using 5 kV Motorised megger megger and record the values at 15, 60 & 600 seconds.
Check insulation resistance between core and frame to ground if the earthing connection
is brought out through bushings.
d) RATIO TESTS
Connect 3-phase 415 volts supply between HV terminals and measure the voltage ratios
at all taps and record.
Earth connections from star point shall be removed during measurement and reconnected
after tests.
36
CAUTION: If there is a residual magnetism in the core, it can give erratic readings.
g) SHORT CIRCUIT IMPEDENCE
LV terminals are shorted by using suitable cables.
3 phase 415 volts supply is connected to HV winding and HV exciting current of all the
phases and LV circulating currents of all the phases are measured and recorded.
Percentage impedance = Rated current x Applied voltage x 100
Measured current x Rated voltage
Compare the results with factory test results.
h) WINDING RESISTANCE MEASUREMENT
Note down the oil/winding temperature. If the measurements are done after hot oil
circulation; the oil/winding temperature may be different from the ambient temperature.
Measure the resistance of all windings using a Whetstone Bridge or Kelvin bridge. Convert
the resistances to 75OC.
R (75)= R (measured) x (234.5 + 75)
(234.5 + Oil temperature at the time of measurement)
Compare the values with factory test results.
37
i) OPERATION CHECKS
Check direction of rotation of pumps and fans.
Check and confirm that flow indicators are mounted correctly.
Check signalling circuits for pump fail/fans fail etc., and reset.
Check setting of over load relays and reset.
j) BUCHHOLZ RELAY OPERATION
Check inclination of Buchholz relay pipe. The slope should be in upward direction,
between 3 ~ 9O to horizontal towards the conservator.
Connect a compressed air line (Pressure 4 kg/cm2) or a nitrogen cylinder to the petcock
on top of the Buchholz relay. Open the petcock slowly and allow air to enter into the
Buchholz relay.
Check the continuity of alarm contacts by using a multimeter.
Record the volume of air in the Buchholz Relay at which the alarm switch contact closes.
Close the air supply and release all the air by opening the other petcock on the Buchholz
relay. Open the petcock quickly and allow air full flow with surge. Record the minimum
pressure required to operate the surge contacts.
Release all the air trapped in the Buchholz relay.
38
SECTION 5
PAGE NO.
5) TRANSFORMER ACCESSORIES
a) TEMPERATURE INDICATOR
---40
---43
---46
d) SILICAGEL BREATHER
---55
---57
---61
g) COOLING FANS
---63
---65
39
5) TRANSFORMER ACCESSORIES
a) TEMPERATURE INDICATOR:
APPLICATION
OTI & WTI: Instrument with specified Range, Number of control switches, length of
capillary and sensing bulb.
40
(iii) OPERATION
o
The instrument operates as OTI when its sensing bulb is mounted in an oil filled pocket
located in the hottest oil of an oil immersed transformer.
The instrument operates as WTI when its sensing bulb is exposed to the medium
adjacent to the windings of a dry type transformer.
When a proportionate load current of the transformer is passed through the thermal
image device, the instrument operates as a WTI integrating the simulated temperature
rise of the thermal image device and the top oil temperature measured by the sensing
bulb.
(iv) CONSTRUCTION
o
A second bellows connected with a second capillary running parallel to the first capillary
and terminated at the head of the bulb from the temperature compensating system.
Both the systems are completely filled with the same liquid.
The two bellows are linked to a compensating lever in such a manner that the effect of
ambient temperature changes on the capillary line and measuring bellows is
compensated.
The movement of the measuring bellows is related only to the temperature being
measured by the sensing bulb.
This movement is amplified by the link and lever mechanism, which directly drives the
rotating disc carrying the control switches. The same mechanism moves, through rack
and pinion a separately mounted indicating pointer over a calibrated dial.
Head compensation is provided by sealing both the systems under initial pressure, which
is greater than the possible head pressure due to differences in the elevation between
the bulb and indicator.
41
(v) MAXIMUM POINTER (RED COLOURED): located on the indicator lid, is resettable
from outside the case by a screw driver blade. Unscrew and remove black cap to reach
the screw driver-slot.
CAUTION: Never use the switch testing knob for setting the maximum pointer. If used,
the switch contacts will close and initiate the external control circuits when the
instrument is in operation.
(vi) SWITCH TESTING KNOB: It is fitted on the indicator lid to check mercury switches
setting and potentiometer operation. These knobs when rotated moves the indicating
pointer, switch mechanism and potentiometer wiper together and facilitates testing
these circuits without opening the lid. Rotate the knob slowly and steadily for an
accurate check. Never allow the knob to spring back suddenly or quickly, as this will
cause damage.
(vii) THERMAL IMAGE DEVICE: A heater coil is fitted around the measuring bellow and
supplied from a current transformer in the load circuit of transformer. The heater coil
simulates hot-spot temperature of the winding over top oil temperature for a given load.
The measuring bellows reacts to this simulated temperature rise in addition to the top
oil temperature measured by the sensing bulb and the instrument functions as a WTI
displaying the hottest spot temperature of the winding. An adjustable shunt resistor (17calibrating shunt) is provided for shunting portion of the current through the heater coil
to obtain precise thermal image.
(viii) ELECTRICAL CONNECTION: All internal electrical connection are wired to the
terminal block mounted inside the indicator case. A wiring diagram is fixed inside the
case of each indicator. Switches are identified by markings S1, S2, S3 and S4 on them.
Terminal Nos. wired to each circuit are detailed below.
(ix) GRADIENT ADJUSTMENT: After opening the instrument lid, carefully remove the
dial. Withdraw the calibrating shunt after removing the nut and retaining washer. One
adjustable centre band and two fixed bands at the ends are provided in the shunt. One
supply lead is connected to the centre band and the other lead to the lower band on the
shunt. Slacken the screw in the retaining clip of the centre band. To reduce the
temperature rise, move the centre band nearer to the lower band, to increase the
temperature rise reverse the procedure. Retighten the screw on the centre band after
42
adjustment. Replace the shunt, dial and lid. Repeat the calibration, check after
adjustments until the accuracy limits achieved.
(x) INSTALLATION MOUNTING: Mount the instrument in a vertical position. Otherwise
errors, particularly in the horizontal plane, will upset the zero setting of the mercury
switches. Place a sprit level on the top of the indicator case to ensure correct positioning
and operation of the mercury switches. If vibration exists at the mounting position,
mount the indicator on a non-vibrating structure. Suitable anti-vibration mountings are
supplied. Do not use these mountings during transport.
(xi) CAPILLARY LINE: Do not stretch hard twist or bend the capillary to a radius less
than 75 mm. Continuously support the capillary by suitable clips at intervals of 300 to
450 mm. Allow necessary slack at the bulb and for mounting and removing the bulb
without sharp bend at the joint. Wind in spiral (minimum dia. 150 mm) the possible
excess length of capillary close to the indicator or the bulb.
43
collected in the body of the relay and is used in some way or other to close the alarm or the
tripping circuit
The principle of the Gas and Oil relay was first successfully demonstrated and utilised by
'Buchholz' many years back.
iii) APPLICATIONS
Double element relays can be used in detecting minor faults in a transformer. The alarm
element will operate, after a specified volume of gas has collected to give an alarm indication.
Examples of incipient faults are
o
Shorted laminations
Bad contacts
The alarm element will also operate in the event of oil leakage, or if air gets into the oil system.
The trip element will be operated by an oil surge in the event of more serious fault such as o
Earth faults
Puncture of bushings
44
mally Open
: Norm
R
Contact Rating
Switching
g Current
: 5 A - A.C. or D.C
C. max.
Switching
g Voltage
A
(r.m.s.)) max.
: 300 V D.C. max----240 Volts A.C.
Breakdow
wn voltage
: 650 Volts
V
D.C. min.
m
Initial Co
ontact Resisttance : 70 milli-ohms
m
ma
ax.
Resonantt Frequency
Actuating
g Time
: 2 milli-seconds (T
Typical)
ARRANGEMENT OF TERMINALS
T
S AND ME
EANS OF PROTECTIO
P
ON FOR REED
R
v) A
SW
WITCH CON
NTACT.
45
These instructions are crucial for the proper handling, installation, operation & maintenance of
Oil Impregnated Paper Condenser Bushings and these should be in the possession of
those who are responsible for the above activities.
INSTRUCTIONS FOR INSTALLATION, OPERATION AND MAINTENANCE OF OIP CONDENSER
BUSHINGS
The general constructional details of the bushing, intended for oil-air application are
shown in Fig. 1. The active part of the bushing consists of an Oil Impregnated Paper
46
(OIP) core (1) manufactured from superior grade Kraft insulating paper with condenser
graded layers for field control, wound under tension on central tube / conductor (2).
o
The innermost condenser layer is electrically connected to the central tube / conductor
(2) and the outermost layer is electrically connected to the fixing flange (3) through a
test tap (11). The core is dried under heat and vacuum and then impregnated with
superior grade of insulating oil.
Porcelain insulators (4&5) on the upper and lower sides of the bushing, oil resistant high
quality rubber gaskets & O rings (6) are held together with the central tube by means
of a set of powerful springs (7).
The fixing flange (3) is provided with a test tap (11) for the measurement of
Capacitance and Tan delta, air releasing screw (10) to release the air trapped in the
transformer during topping up of oil or can be connected to Buchholz relay, name plate
giving the product details, handle / eyebolt for lifting and space for ring type CT's on the
oil end of the bushing.
At the oil end, an epoxy coated stress shield or base plate (15) is provided to control the
high stresses in oil inside the transformer. A detachable bottom arc shield is provided for
bushing rated 245 kV and above. The intervening space between the core and the
porcelain insulators is filled with specially treated mineral oil under vacuum.
A Prismatic (up to 300kV) or magnetic (up to 400 kV) Oil sight glass (14) is provided on
the expansion bowl (8). A top terminal (12) is provided to connect to the over head line.
Arcing horns (16, 17) are provided on request. (Ref. Fig. 3). Test Tap: - (Refer Fig. 2)
The test tap (11) is provided for the measurement of Capacitance, Tan delta and
Insulation Resistance (IR) values of the bushing. It is connected with a copper lead to
the last condenser foil of the core directly. During normal service this test tap is
electrically connected to the mounting flange through test tap cover. The threaded test
tap cover must be fixed properly (Fig 2a) before putting into service.
47
To prevent physical damage to the bushings, generally only one bushing is packed in
wooden packing case. At times, more than one bushing is also packed in the case of
bushings of lower voltage rating. The bushing is placed in the packing case at an angle
48
of 6-8 degrees to horizontal. Accessories like arcing horns, terminals etc. are also
packed in the same packing case.
o
This is to ensure the core remains immersed in oil. When the packed bushings are
stored outdoors, they should be kept horizontal and covered with tarpaulin for
protection from rain and other atmospheric contaminants.
The IR values may vary due to the atmospheric condition (humidity), surface cleanliness of the
porcelains, dryness of test tap etc. In such cases, preheating of porcelains, terminals test tap
etc., with hot air is recommended.
However, the healthiness of the bushings can be known only after measurement of Tan
delta & capacitance values.
Capacitance and Tan delta values of the bushing should be measured between the top
terminal and test tap at 2 kV to 10 kV (Maximum). The measurement should be
preferably carried out indoors with RH not exceeding 60% and at ambient temperature,
with the facilities and procedure as described as described below:
Schering Bridge
Place the bushing vertically on suitable stand. Remove the threaded test tap cover. Insert a
plug / clip into the central stud of the test tap and connect to the Schering Bridge through a
screened cable. The flange body should be grounded. Connect the high voltage supply to the
top terminal. Measure the capacitance & tan delta value of bushing up to a maximum of 10 kV.
Note: The voltage applied on the bushing should be limited to 10 kV, when the bottom end is
not immersed in oil. Utmost care should be taken to avoid any contact with the bushing during
testing as this may result in fatal injury to the personnel.
49
The test tap should be dry, free from any moisture condensation and dirt deposition.The
threaded test tap cover should be fixed back to the test tap, immediately after the test.
Factory test values of tan delta and capacitance are indicated in the test report of
individual bushing at working voltages. However, site values may vary, as they do not
resemble factory test conditions.
The site values recorded at the time of commissioning should be taken as the reference
values for comparison with future measurements. The bushing can be commissioned, if
tan delta value measured is less than or equal to 0.007, and capacitance value as per the
factory test value with maximum variation of 10%. If higher values are obtained, please
contact ALSTOM, Customer Service Department giving full details of testing arrangement,
for further advice.
Note: The bushing should be kept vertical or mounted on transformer for a minimum period of
24 hours before application of voltage.
50
51
The bushing is suitable for installation for a maximum angle of 30 degrees from vertical.
During the lowering of the bushing into the transformer, extreme care should be taken
to prevent the lower porcelain hitting the wall of the tank. The bushing should be so
mounted on the transformer that the oil sight glass is visible from the ground level.
Ensure the visibility of the oil level to the naked eye.
Maximum stress experienced by the bushing is at the bottom stress shield during
testing. Hence sufficient care should be taken to avoid any flashover from the stress
shield to the wall of the turret. The flashover voltage depends on the clearance
maintained in oil between the stress shield and turret, oil quality, surface smoothness,
presence of barriers, shape of the stress shield and turret etc. The recommended size of
the turret to be maintained for various voltage class of bushings is given in the
manufacturers booklet / respective drawings.
Each bushing is supplied with a top terminal (12), cable bolt (9), cable bolt pin and a
gasket placed separately in the packing case.
Drills a hole of suitable diameter based on the size of the flexible transformer cable at
the bottom end of the cable bolt and braze the cable into it. Insert an M8 bolt at the
upper end of the cable bolt and tie a wire or a fish cord on to it. Clean the gasket
seating surface on top face of the transformer and place the gasket in position. Lift the
bushing above the transformer turret and clean the bottom end of the bushing.
Lower the bushing slowly into the transformer; simultaneously pull the transformer cable
brazed with cable bolt through the central tube with the help of the fish cord. Secure the
cable bolt to the central tube with the cable bolt pin. Remove the fish cord. Bolt the
bushing into position taking care to correctly position the gasket joint. Tighten the
terminal to the cable bolt ensuring full thread engagement for proper current transfer.
Sometimes the cable bolt is supplied along with the brazed flexible lead up to the flange
seat with a half connector at bottom end. In such cases the flexible lead from the
transformer winding should be brazed to the other half connector and should be
fastened with the draw lead connector of the bushing using bolts and nuts.
52
v)
o
Remove the draw rod through the bushing tube or take it out from the packing case.
Clean the outer surface and braze the transformer cable to the lower half connector.
Clamp the upper and lower half connectors together with bolts and nuts. Follow the
installation instructions as described for draw lead type of bushing.
In solid stem type of bushings, the central conductor forms the current carrying part.
Mount the bushing on the turret and connections should be made to the top and bottom
terminals individually. The transformer cable termination should be connected to the
bottom terminal with bolts & nuts, through the viewing port of the transformer. The top
terminal should be fixed directly to the central conductor.
Ensure the top terminal is fixed tightly with the gasket provided to avoid entry of
moisture in to the transformer.
Measure and record the capacitance and tan delta values of the bushing. Here again the
values may differ from the previous ones.
Note: The threaded test tap cover should be fixed back to the test tap immediately after the
test.The bushing should be kept vertical mounted on the transformer for a minimum of 24
hours before energisation.
CAUTION: THE TEST TAP WILL ALWAYS BE EARTHED AS LONG AS THE THREADED CAP IS
FIXED (Fig. 2a). HENCE THE CAP SHOULD NEVER BE KEPT OPEN.
53
SAFETY:
o
Understanding the procedures and instructions are a must while handling bushings. Also,
all applicable safety procedures such as regional or local safety rules and regulations
must be followed. Safe working practices and good judgement are essential by the
personnel while installing, testing, maintaining or disposing the bushings.
54
d) SILICAGEL BREATHER
SILICAGEL DEHYDRATING BREATHER FOR TRANSFORMER
o
A dehydrating breather is used to dry the air that enters a transformer as the volume of
oil decreases because of fall in temperature.
Air entering the breather is first drawn through an oil seal and passes upwards through
the silicagel crystals to the connecting pipe at the top. During this upward passage of
air, any moisture present is absorbed by the dry silica gel.
The oil seal ensures that the gel absorbs moisture only when the transformer is
breathing.
i) INSTALLATION
The breather is usually detached from the tank and shipped separately; the silica gel charge is
shipped in at the top with a plug. To install, it is necessary to:
1. Remove top cover by unscrewing cap nut and fill with silica gel.
2. Remove the plug.
3. Pipe up to the tank or conservator.
4. Fill the oil cup with transformer oil to the indicated level.
ii) MAINTENANCE
o
When the breather is first installed, the crystals have a blue tint, and after a period of
operation, the colour of the tinted crystals gradually changes to pink; this is an
indication that the silica gel is becoming saturated and losing its absorbent properties.
When there is a preponderance of pink crystals the gel should be changed or
reactivated.
Before filling the container with silica gel, clean and dry all parts of the breather. Verify
that the oil Level in the oil cup is correct when reassembling.
Ensure that the breather is not choked and is free for passage of air.
55
SILICA
AGEL BREA
ATHER TY
YPE 1
SECTIO
ONAL VIEW
W OF BRE ATHER TY
YPE 2
56
e) MA
AGNETIC OIL
O LEVEL GAUGE: (MOLG)
OIL LEV
VEL INDIC
CATOR
SIDE V IEW
FRON
N T VIEW
57
58
MODEL SO-03
MODEL SO-06
MODEL SO-10
i) APPLICATION
This model of indicator is manufactured considering Transformer application. It can also be
used as Content Gauge on other tanks where level of liquid inside the tank is required to be
indicated continuously on a dial.
ii) CONSTRUCTION, WORKING & FEATURES
o
A float is used as sensor of liquid level inside the conservator (tank). Swing of hinged
float due to change in liquid level is utilised to indicate level on a calibrated dial and to
operate a switch for external alarm unit.
Use of magnetic coupling in the indicator achieves complete sealing off of liquid inside
the conservator from surrounding atmosphere. This result in avoiding any leakage of
costly oil and avoiding contamination of insulating oil due to seepage of surrounding air
in the conservator.
The glass mercury switch is nylon encapsulated to avoid breakage and spilling of mercury.
Switch is accessible for servicing while indicator is mounted on the conservator without any
necessity of draining the oil.
iii) CALIBRATION
The standard calibration of dial is Empty, 1/4, 1/2, 3/4, Full. Calibration of marks Empty & Full
is done after leaving 65 mm from bottom and top of conservator to avoid striking of float to
conservator wall. Different calibrations are done to suit customer's needs.
iv) MOUNTING
In fig. 2, indicator is shown mounted by keeping dial and mounting pad in vertical position.
However, indicator can be mounted in titled position towards ground (max 30) for easy
viewing by fixing mounting pad at desired angle. The position of indicator on the conservator
can be selected to suit site condition. Float mechanism passes through the hole in pad.
v) ALARM SWITCH & CONNECTIONS
One mercury switch is provided for Low Level Alarm. The Normally Open switch closes when oil
level drops to 10 mm above Empty level i.e. 75 mm from bottom of conservator. Leads from
59
mercury switch are brought into a terminal box positioned at the bottom of indicator (see Fig.
4B), A two-way terminal strip is provided which is accessible for connection after removing
cover of terminal box. A hole with 3/4 B.S.P. is provided for cable gland. Wiring should be
done as per Fig. 4B.
vi) SPECIFICATIONS
Operating Liquid
Working Temperature
0 to 100 C of Oil
Working Pressure
0 to 4 kg/cm
Environment
Weight
Float Travel
Electrical witch
Contact Rating
Switch Setting
Dial Size
250 mm dia.
Dial Position
Vertical or Inclined
Conservator diameter
60
f) PRES
SSURE RE
ELIEF VALV
VE
o MODEL:M
T-3
3
o MODEL:M
T-5
5
o MODEL:M
T-6
6
i) AP
PPLICATIO
ON:
This PRV
V is designed
d to be used
d on Power Transformer
T
r. When presssure in the tank rises above
a
predeterm
mined safe limit this valvve operates and perform
ms following functions.
o
A
Allows
the pressure
p
to drop by in
nstantaneoussly opening a port of about 150 mm
diameter.
G
Gives
visual indication of valve opera
ation by rising a flag.
O
Operates
a micro
m
switch.
61
This PRV has an integral flange with six holes for mounting. The valve can be mounted
vertically or horizontally on the tank. The PRV has got a port of about 150 mm dia. This
port is sealed by a stainless steel diaphragm.
The diaphragm rests on an 'O' ring and is kept pressed by two heavy-duty springs,
thereby keeping the port closed. The other side of the diaphragm is exposed to tank
pressure. Whenever the pressure in the tank rises due to any reason, the same pressure
acts on the diaphragm from inside. When pressure rises above predetermined safe limit
the diaphragm gets lifted from its seat.
This lifting is instantaneous and allows vapours, gases or liquid to come out of tank
depending upon the position of valve on tank.
The diaphragm restores its position as soon as pressure in the tank drops below set
limit. The lift of the diaphragm is utilised to operate flag and micro switch with the help
of rod. The flag and switch remain operated until they are reset manually.
Remove the cover of switch box. By lifting the operating rod check operations of switch
as stated in Test 4 in test certificate with the help of an AVO meter. After checking,
reset the switch by pressing knob. Replace the cover.
The flag operation should be checked manually by lifting the rod. Reset the flag by
turning it down. Handling of flag should be done very carefully.
The product label indicates the suitability of valve for synthetic liquid or for transformer
oil. A proper valve should be selected. Normally Red product label is used for synthetic
liquid and Black label for transformer oil.
The valve has rugged construction and it is not likely to get damaged easily. However,
the indicating flag is delicate item. Hence if is likely to get damage.
The indicating flag can be replaced by either making similar flag at your end or by
asking for replacement.
You can repair with the help of good instrument mechanic minor faults occurring in
working of switch or flag mechanisms.
62
g) COO
OLING FAN
NS
i) GENERAL
G
Exhaust type
t
cooling
g fans used on
o transform
mers are dessigned to ope
erate outdoo
ors in all weather
condition
ns. Generally
y the followin
ng sizes of fa
ans are used
d.
Sr. No.
Size
Speed
Inputt
(mm)
(r.p.m.))
(watts))
610
700
240
610
900
500
e
Phase
Voltag
ge
ency
Freque
Currrent
(volts))
(Hzz)
(Am
mp)
415
50
0
0.5
415
50
0
0.9
63
iii) IM
MPELLER
The impe
eller is desig
gned to give maximum volume
v
at minimum noisse level with minimum power
p
consump
ption.
For reduccing vibratio
ons, special shoes
s
made of rubber arre provided at fixing points of fan lu
ugs.
iv) MOUNTING
M
The arm is secured by the resilient mounting caps, wh
hich are placced over the
e rubber so
ockets
and secu
ured to the diaphragm with 8 scre
ews, nuts an
nd washers provided. The
T
lock wasshers
should be
e fitted unde
er the headss of the screw
ws.
Rubber sockets
s
fitte
ed to arms. To be fitte
ed so that flat
f
side will come in contact
c
with
h the
diaphragm.
NOTE: Lo
ock washerss are supplied and should
d be fitted.
Setscrew
w in blade sh
hould engag
ge in dimple
e nearest the
e end of the
e shaft. Afte
er blade is fitted,
f
see that split pin 5 iss replaced in end of shafft.
64
i) INTRODUCTION
o
Flexible separator (Air Cell) is provided inside the conservator of power transformers for
avoiding direct contact of air with the transformer oil. Air Cell provides a permanent,
flexible and non porous barrier between the atmosphere and the transformer oil without
affecting the operational function of the system.
The basic construction of the separator is a highly resistant fabric coated externally to
resist transformer oil and internally to Ozone and weather resistant.
Flexible separators offer the following advantages : Avoids contact between air and oil and consequently of condensation or oxidation
inside the transformer.
Protection against water vapour and gases.
Suppression of any gas bubble formation in oil.
Compensation of large volume changes.
65
ii) DESCRIPTION
Flexible separator is fitted inside a cylindrical conservator. Oil being outside, the separator is in
direct contact with atmosphere. This type of mounting makes it possible to compensate for the
oil volume displacements due to temperature variations.
iii) CHARACTERISTICS OF MATERIAL
o
Flexible separators are made from coated fabric consisting of: Textile reinforcement i.e.
highly resistant polyamide fabric.
Coating
Textile reinforcement
Polyamide
66
iv) IN
NSTALLATIION PROCE
EDURE
1 Conne ction to th
he
inside of Air Ce ll
2 Conne ction to th
he
inside of
o
Conservvator
3 Magne tic Oil
Level Gauge
G
D
Details
Of Fixxing Air Cell
O Conserva
On
ator
On Conserrvator And
Handle On
O Air Cell
Fig
g. 2
F
Fig.
3
67
The conservator with Air Cell is pressure tested and despatched from the factory at a
slightly positive pressure. Confirm that there is no oil leakage.
Keep air release valves open. Fix air filling adapter on breather pipe and
cell at an air pressure indicated on the INSTRUCTION PLATE affixed on the transformer
and hold air pressure.
DO NOT APPLY EXCESS AIR PRESSURE AS IT MAY DAMAGE THE AIR CELL.
o
Open air release valves and start oil filling from the bottom of the conservator.
Observe the air release valves and as soon as oil starts overflowing, close the air release
valves one by one. Stop oil filling when all air release valves are closed.
Continue oil filling and observe the Magnetic Oil Level Gauge (MOLG)
68
Stop the filling when the needle of MOLG shows the level corresponding to the ambient
temperature at the time of filling.
Open the oil filling valve of the transformer.Because of the vacuum in the conservator,
the oil level rises automatically.
Stop the oil filling once the required volume in the conservator is attained.
While maintaining the conservator under vacuum, allow Dry Air or Nitrogen gas to enter
into the internal part of the separator. Then, the separator inflates by itself, and takes
all the free space due to the fact that the conservator was not completely full. In
particular, during the operation, the oil is going to rise to the top of the conservator.
Check on the vent-holes, and confirm that there is no more air in the conservator or, if
necessary, adjust the level.
69
70
SECTION 6
PAGE NO.
---72
a) ELECTRICAL SAFETY
---73
b) HAZARDOUS SUBSTANCES
---73
c) ENVIRONMENTAL SUBSTANCES
---74
---74
e) CONTROL OF FIRE
---74
---75
---75
h) TROUBLESHOOTING
---79
71
72
a) ELECTRICAL SAFETY
The following hazards are commonly associated with the installation, operation and
maintenance of electrical equipment
Existence of AC and DC voltage.
Possible existence of toxic hazards associated with material used in the construction of
electronic components, cleaning agent and solvents.
Electric shock due to incorrect earthing, moisture on insulation, bad engineering or
working practices.
Fire or burn out due to incorrect setting or over load or protective devices, incorrect
cables or fuses, insufficient ventilation or incorrect operating voltage.
Short circuit flash over due to dust or moisture on insulation or short circuit on live
conductors.
If the secondary of a current transformer is disconnected, a dangerously high voltage
can be induced in the circuit. If the secondary circuit of a current transformer is to be
disconnected it must be shorted by a link capable of carrying the rated current.
Do not apply any voltage or even high voltage megger when the equipment is under
vacuum.
b) HAZARDOUS SUBSTANCES
TRANSFORMER OIL
o
Oil is a hydrocarbon and will burn. Carbon dioxide, dry chemical, foam or water fog
is the extinguish ants.
MERCURY
O
73
Keep a track of the maintenance schedule of Transformer & ensure that the required
routine & preventive maintenance are done as per the schedule
On noticing any leakages from the Transformer immediately place a tray /container to
collect the spillage and inform the maintenance department for immediate corrective
action (for example replacement of gasket etc.). Oil shall not be allowed to fall on to
ground.
In case any leakage to ground take place, remove the same with cotton/cloth/ saw dust.
In case large scale spillage immediately inform the shift in charge & start collecting the
spilled oil to suitable container and assess the risk of continuous operation of the
Transformer
e) CONTROL OF FIRE
It is necessary to check the healthiness of the Transformer fire protection system regularly so
that the fire risk can be minimized
o
During hot oil circulation in the Transformer keep fire extinguisher ready near the
Transformer, all the combustible materials shall be kept at a safe distance.
Proper Housekeeping near Transformer may help to reduce the risk of fire.
74
Proper fire fighting system as per CBIP recommendation shall be installed near
Transformer. Regular inspection & maintenance to be done on the Fire fighting system.
Welding on oil filled Transformer shall be carried out if unavoidable, as per the
instructions of the Manufacturer.
Hot oil circulation shall be carried out only under the round the clock supervision to
prevent chances of fire on lagging materials etc.
DO'S
Insulating oil and insulation of windings and connections are inflammable. Watch for fire
hazards.
Before entering inside the Transformer, replace Nitrogen gas completely with air if it was
transported with nitrogen gas inside.
Make sure that nothing is kept inside the pockets before one enters inside the main unit.
Also take off the wristwatches and shoes.
List up all the tools and materials to be taken inside and check it after coming out to
make sure that no tools are left inside.
There must be a protective guard for lamp to be taken inside.
Keep inspection covers open for supply of fresh air when someone is working inside.
When one person is working inside, second person must be available outside for
emergency help.
Use rings spanners and tie them to the wrist of the person or somewhere outside the
tank.
Be careful during connections where bolted joints are involved so that nut, washers etc.
are not dropped inside the tank.
De-energise the unit by circuit breakers and line switches while working on energised
unit.
Check the diaphragm of explosion vent and replace it if cracked.
Attach the caution tags "DO NOT OPERATE THE SWITCHES" while working on units,
which are energised.
75
Fire fighting equipment should be checked regularly and should have sufficient quantity
of extinguisher.
Transformer tank, control cabinets etc. as well as oil treatment equipment shall be
connected with permanent earthing system of the station.
Check and thoroughly investigate the transformer whenever any alarm or protective
device is operated.
Check air cell in conservator.
Attend leakage on the bushings.
Examine the bushings for dirt deposits and clean them periodically.
Check the oil in transformer and OLTC for dielectric strength and moisture content and
take suitable action for restoring quality.
Check the oil level in oil cup and ensure air passages are free in breather. If oil is less
make up the oil.
If inspection covers are removed or any gasket joint is to be tightened, then tighten the
bolts evenly to avoid uneven pressure.
Check and clean the relay and alarm contacts. Check also their operation and accuracy
and if required change the setting.
Check the protection circuits periodically.
Check the pointers of all gauges for their free movement.
Clean the oil conservator thoroughly before erecting.
Check the OTI and WTI pockets and replenish the oil if required.
Gas filled storage of transformer at site should be limited to a maximum of 3 months.
Check the door seal of the Marshalling box. Change the rubber lining if required.
Ensure proper tightness of top terminal of condenser bushings to avoid entry of
rainwater.
Check oil level in condenser bushing, any discrepancy should be reported immediately to
the manufacturer.
Do jacking only at jacking pad.
76
DON'TS
Do not take any fibrous material such as cotton waste inside while repairing.
Do not drop any tools / material in side.
Do not stand on leads / cleats.
Do not weld, braze or solder inside the tank.
Do not weld anything to the tank wall from outside.
Do not weld anything to the conservator vessel if Air cell bag is inside.
Do not smoke near the transformer.
Do not use fibrous material for cleaning as it can deteriorate the oil when mixed with it.
Do not energise without thorough investigation of the transformer whenever any alarm
of protection has operated.
Do not re-energise the transformer unless the Buchholz gas is analysed.
Do not re-energise the transformer without conducting all pre-commissioning checks.
The results must be compared with factory test results.
Do not handle the off circuit tap switch when the transformer is energised.
Do not energise the transformer unless the off circuit tap switch handle is in locked
position.
Do not leave off circuit tap switch handle unlocked.
Do not use low capacity lifting jacks / slings on transformer for jacking / slinging.
Do not change the setting of WTI and OTI alarm and trip frequently. Setting should be
done as per manufacturer's instructions.
Do not leave any connection loose.
Do not meddle with the protection circuits.
Do not leave marshalling box doors open, they must be locked.
Do not switch off the heater in marshalling box except to be periodically cleaned.
Do not allow unauthorised entry near the transformer.
Do not close any valve in pump circuit for taking stand by pump and motor into circuit.
Do not allow water pressure to exceed the oil pressure in oil to water heat exchangers.
Do not mix transformer oils of different make/ base, unless oil is new and conforms fully
to IS: 335.
77
Do not continue with pink (wet) silica gel, this should immediately be changed or
reactivated.
Do not store transformer in gas filled condition for more than three months after
reaching site. If storage is required for longer duration, the main body should be filled
up with oil.
Do not leave tertiary terminals unprotected outside the tank.
Do not allow WTI / OTI temperature to exceed 70C during dry out of transformer and filter
machine temperature beyond 75C
Do not parallel transformers, which do not fulfil the conditions for paralleling.
Do not over load the transformers beyond limit specified in IS: 6600.
Do not leave secondary terminals of any CT open.
Do not measure insulation resistance by using megger when the transformer is under
vacuum.
Do not stand on any vessel, which is under vacuum.
78
o TROUBLE SHOOTING
Following table shows some of the symptoms, possible causes and remedies in case of
abnormal situations:
ABNORMAL OPERATING CONDITIONS
TROUBLE
High Winding/ Oil
Temperature
Electrical
Troubles/
Winding
CAUSE
REMEDY
Over voltage
Over current
Insufficient cooling
Deterioration/
Failure
79
SECTION 7
7)
PAGE NO.
---81
---82
b) MAINTENANCE SCHEDULE
---83
c) OIL SAMPLING
---84
---85
---86
---87
g) OIL FILTRATION
---87
---88
---89
---90
80
7) OPERATION
o
After the inspection and pre-commissioning tests are successfully completed the transformer can
be energised at no load.
Oil soaking/ settling duration of 2 days for transformers up to 245 kV class and 3 days for 400 kV
and above class are recommended after completion of hot oil circulation and before energising.
Excessive vibration if any on any part of the transformer shall be located and rectified.
If any gas is collected inside the Buchholz relay, it shall be analysed for its combustibility. If gas
is not combustible, it indicates air trapped inside the transformer.
Check winding temperature and oil temperature readings at least once in every shift.
Check and confirm that tap position indicators is same in local and remote indicators.
Ensure that pumps and fans are running smoothly as temperature dictates. If the temperature is
below the ON setting neither the pump nor fan should be running.
After watching the operation of the transformer at no load for 24 hours and confirming that
everything is normal, the transformer shall be taken on load.
While temperature is rising, confirm that fans and pumps are switched on automatically at the
preset temperatures.
While temperature is falling, observe that the pumps and fans are switched off at preset
temperature.
81
Items to be inspected
Frequency
Load current
Hourly
Terminal Voltage
Hourly
Ambient Temperature
Hourly
Winding Temperature
Hourly
Oil Temperature
Hourly
Tap position
Daily
Daily
Daily
Daily
10
Daily
11
Daily
12
Connections
Monthly
13
Monthly
14
Quarterly
15
Quarterly
16
Half yearly
17
Half yearly
18
Half yearly
19
Half yearly
20
Yearly
21
Yearly
22
Yearly
23
Surface paint
2 ~ 3 Years**
82
Note:
** Duration of surface repainting depends on the level of pollution prevailing at site. If pollution level is
Core and coils are to be inspected only if such an inspection is warranted by test results of dissolved
gas analysis, any abnormality in performance or for suspected internal damages due to external
short circuit.
b) MAINTENANCE SCHEDULE
Periodicity
Preventive Maintenance Procedures
Months
3
Scheduled
12
outage
Oil Sampling
Bushings
OTI/ WTI Tests
Oil Filtration
Surface Painting
83
C) OIL SAMPLING
o
Oil sample should be tested for the following and results recorded:-
If the dielectric strength of oil in transformer is less than 55 kV at 2.5 mm gap, the oil must be
filtered to improve the characteristics.
For line end OLTC diverter chamber, oil filtration is recommended when the BDV is 40 kV at 2.5
mm gap.
For neutral end OLTC diverter chamber, oil filtration is recommended when the BDV is less than
30 kV at 2.5 mm gap.
For transformers of 400 kV and above class, if the moisture content is found to have increased
beyond 20 ppm oil should be filtered.
For transformers of voltage class up to 245 kV, if the moisture content is found to have increased
beyond 25 ppm oil should be filtered.
(iii) ACIDITY
o
It the acidity is increased beyond 0.5 mg KOH/g, than the oil needs filtration.
After draining the oil completely from the transformer, core, winding, insulation and interior of
tank should be washed by hot oil jet. The oil being used for washing of internal body also must
be drained completely.
Special care in oil sampling is required for Delta connected transformer and autotransformers.
Spanner set
Thermometer
Clean cloths
84
(vi) PROCEDURE
o
The sampling bottles shall be labelled and marked with information like source of sample, date
and time & sample temperature.
Clean the silicon rubber tubing thoroughly and fit to sampling point nipple.
Rinse the bottle in oil stream and reduce the rate of oil flow to 1 litre/minute.
Put the end of rubber tubing to sampling bottle and fill the bottle from bottom.
Remove all tools, excess oil container and oil sample from the area.
Multimeter
Clinical thermometer
(ii) PROCEDURES
o
The purpose of this check is to confirm that the winding temperatures Indicators are functioning
accurately.
Rotate the indicator pointers slowly to the alarm set value and confirm from the control room
that the alarm signal has been received.
Rotate the pointer still further and confirm from the control room that trip signal is received.
(iii) CALIBRATION
o
Remove the thermal sensing bulbs from the transformer and insert it into the hot oil bath.
85
Check the winding temperature readings up and down the scale at intervals of 5 C.
Confirm from control room that remote temperature readings are tallying with the local readings.
Connect the secondary injection test set across the heater coil terminals.
Inject current and check the resultant gradient for ONAN rating.
2) OFAF RATING
Inject current in the heater coil and check the gradient for OFAF rating.
Disconnect.
Multimeter
Nitrogen cylinder with regulator and pressure gauge or air supply (4 kg/cm)
Bucket
(ii) PROCEDURE
o
Check and confirm from control room that alarm signal is received.
Close petcock on gas supply side and release all gases trapped in relay casing.
86
Open the test petcock and allow full surge of gas to enter the relay casing.
Check and confirm from control room that trip signal has been received.
If relay has not operated, increase gas pressure and repeat the test.
Open conservator shut off valve and release all gases trapped.
f) TAPCHANGER OPERATION
o
Regular inspection of tap changing equipment is not required because mechanical operation of
tap changer does not involve significant contact wear.
It is sufficient to operate the tap changer through the whole range of tap selector positions twice
a year.
The purpose of this check is to ensure correct mechanical operation of tap changer.
Operate the tap changer through operating handle through entire range of tap positions.
Press RAISE button and release. Check and confirm the tap position indication has changed and
that limit switch stops the tap changing at preset tap.
Repeat.
Press the LOWER button and release. Check and confirm that limit switch has operated and tap
position indication has changed.
Repeat till the tap position has returned to the original value.
g) OIL FILTRATION
o
Purpose of this maintenance is to improve the unsatisfactory condition of oil found during
sampling.
87
Hose adapters to match the flanges of top and bottom filter valves.
Cleaning cloths
(ii) PROCEDURE
o
Remove the blanking plate from filter valves and connect the oil inlet hose to top filter valve and
oil outlet hose to the bottom filter valve.
Open the filter valves and start circulation of hot oil. Oil temperature shall be 55C to 70C.
Cleanliness of gasket surfaces and correct compression (40 % ~ 50% approx.) of gasket must be
ensured during reassembling.
Blanking plates
New gaskets.
(ii) PROCEDURE
o
Remove the drain plug of the pump and drain oil from the pump.
Open air release plug and close when oil starts flowing out.
New gaskets.
(ii) PROCEDURE
o
Close the inlet and outlet valves if radiator is mounted on a separate cooler tank.
Remove the bottom drain plug and drain the oil to oil container under gravity.
Remove radiator.
If the radiator is on a separate cooler bank, oil shall be filled into the radiator bank through the
bottom header valve by using the filter machine. If the radiator is tank mounted, the oil from the
oil tank should be pumped into the tank by using the filter machine.
Close the air release plug on top as soon as oil starts flowing through the air release plug.
89
In case of separate cooler banks, air should be released through the top common header air
release plugs.
(ii) PROCEDURE
o
Set cooler supply isolator to OFF and lock the marshalling box.
Support the weight of fan and motor assembly by using fork lift truck.
Assemble the fan and motor in position and tighten clamping bolts.
90
SECTION 8
PAGE NO.
---92
---93
---96
---101
---103
91
92
: ....
EQUIPMENT DETAILS
: .......
SITE
: ....
STATUS
SR.
NO.
1
O.K.
CHECK POINT
AVAILABILITY OF DOCUMENTATION
Erection drawings including OGA
Erection / Maintenance Manual
Transport packing list
RECEIPT OF TRANSFORMER
Externally inspected damage (if any)
Gas pressure on receipt (Where applicable)
Oil level (in case of oil filled transformer)
Unit correctly positioned
RECEIPT OF ACCESSORIES
All materials stored correctly
Packing Cases inspected, damage if any
Marshalling box inspected, damage if any
Control panels (RTCC)inspected damage if any
Materials received corresponded to Advise note
Any shortages / wrong supply
Materials comply with shipping specification
Remark (if any)
93
NOT O.K.
REMARKS
STATUS
SR.
NO.
4
O.K.
CHECK POINT
ERECTION
Transport rollers mounted
Conservator mounted
Buchholz relay and oil surge relay mounted (arrow
marked should be towards conservator)
Breather mounted and duly charged
HV Bushings mounted
LV Bushing mounted
Tertiary Bushing mounted (if applicable)
HV neutral Bushing mounted
LV Neutral Bushing mounted
Bushing installed at correct angles
Diaphragm checked
MOLG mounted
Radiator mounted
Fans mounted
Pressure Relief valves mounted
Alignment of all pipe work
OLTC Conservator mounted
Heat Exchangers assembled with pipe work
Topping up of transformer oil
Leakage observed after 24 hrs.(if any)
Rating Diagram and identification plate fitted
Control panel (RTCC) aligned
Control panel (OLTC) aligned
94
NOT O.K.
REMARKS
STATUS
SR.
NO.
5
O.K.
CHECK POINT
OIL FILLING
All bushing oil level
Tap changer selector oil level
Diverter switch oil level
Auxiliary unit oil level
Radiator, Headers oil filled
Transformer / OLTC Conservator oil tight
Complete transformer oil tight
All air release plug vented
Valves in service position
All drain / filter valves blanked
MULTICORE CABLE
All tray work adequately secured
All cables adequately tied/clipped back to tray
Cables glaned correctly
BREATHERS
Transformer silica gel breather satisfactory
Tap changer silica gel breather satisfactory
Dry breather correctly installed
FANS
Fans rotate freely & quickly
Pumps installed for correct flow
Flow indication visible
CONTROL PANELS
Cable termination & Glanning
10
95
NOT O.K.
REMARKS
Site: ______________________________
TRANSFORMER
Rating:
Oil Qty:
DETAILS:
Voltage:
Mass of oil:
Year of Manf.:
Wight of C&W:
Sr. No.:
Impedance:
Vector Group:
TR Tag #:
Make:
YOM:
Type:
Sr. No.:
OLTC/OCTC DETAILS:
Tap Position:
GENERAL CHECKS:
SR.
STATUS
NO.
O.K.
CHECK POINTS
Dryness of silica gel, seal removal & oil level in bottom cup
10
11
Overall clearances.
12
13
14
15
96
NOT O.K.
REMARKS
STATUS
NO.
1
O.K.
CHECK POINTS
W.T.I. (Sl. No., Make & Model)
a. Transit lock release.
b. Switch settings & operation.
c. Connections.
d. Ambient reading.
e. Heater shunt shorting link.
f. Matching with repeaters.
g. Power supply & current converter
Timer settings.
97
NOT O.K.
REMARKS
STATUS
NO.
O.K.
CHECK POINTS
NOT O.K.
REMARKS
a. Manual - Local.
b. Manual - Remote
c. Auto & Stand by operation
4
Overload setting
Starting current
Running current
Megger values
STATUS
NO.
O.K
CHECK POINTS
Manual operation.
10
11
12
98
NOT O.K.
REMARKS
SR.
STATUS
NO.
CHECK POINTS
O.K
13
14
Earthing.
15
16
NOT O.K.
REMARKS
Setting of Timers.
W.T.I. Repeater.
O.T.I. Repeater.
10
O.L.T.C. Operations :
a. Individual :
b. As Master :
c. As Follower :
11
Emergency Trip.
12
13
99
STATUS
NO.
OK
CHECK POINTS
Manual operation.
Auto operation.
Overload setting
Starting current
Running current
10
100
NOT OK
REMARKS
2U2V
1V1W
2V2W
2W2U
1V1W
1W1U
2U2V
1W1U
2U2N
2V2N
2W2N
2W2U
2U2N
2V2N
2W2N
3. Magnetizing Current test:- on HV Side (Voltage applied on HV Side, and current measured
on HV Side in Mille Ampere)
Tap No.
1
2
3
4
5
6
7
8
9
1U1V
1V1W
1W1U
1U-ph
1V-ph
1W-ph
101
C)
Sr. No:
Capacity:
60 sec
15 sec
600 sec
PI
(If applicable)
5000
2500
1000
5. Vector Group Test:- (Shorted 1U & 2U terminal and Voltage applied on HV Side i.e. to 1U1V
1V1W 1W1U):- (Before any activity done)
1U1V=
1V1W=
1W1U=
Readings
1V2V=
1W2V=
Remarks:-
Conditions Required:
1W2V>1W2W
1V2V=1V2W
1U2N+1V2N=1U1V
1V2W=
1W2W=
From above it is confirmed that vector group is
1U2N =
1V2N =
6. Oil BDV Test:- measured in Kilo Volt (with 2.5 mm gap & average of 05-strokes)
Tested By:
Before Filtration
KV
KV
Customer Sign:
102
After Filtration
KV
KV
STATUS
NO.
O.K
CHECK POINTS
NOT O.K.
REMARKS
terminals, etc.
4
a.
Buchholz relay
b.
c.
e.
f.
M.O.L.G.
g.
h.
Bushings
b.
Radiators, headers
c.
Buchholz relay
d.
e.
f.
Disconnecting chamber
Transformer is successfully charged on dtd. _________ at __________ Hrs. On tap position no._____ on
no load condition & load is taken on dtd. _________ at ________ Hrs. No abnormality found during
charging and loading condition. Transformer put on _______ Amp. / MVA __________ load on ________
at _______ Hrs and is operating satisfactorily.
Signature: ----------------------------------
----------------------------------------
Name:
---------------------------------------
----------------------------------
(FOR SCHNEIDER)
(FOR CUSTOMER)
103