Rajasthan Solar Parks
Rajasthan Solar Parks
Rajasthan Solar Parks
Concept and
Implementation
A Presentation
by
Rajasthan Renewable Energy Corporation Ltd.
Index
Solar Power Potential in Rajasthan
Solar park concept
CCI technical assistance
ADB technical assistance
Solar parks in Rajasthan
Bhadla Solar park
Development of phase I of Bhadla Solar park
Development of phase II of Bhadla Solar park
Major implementation issues
Rajasthan solar policy 2014
Future solar parks in Rajasthan
DNI
!
"
. /
"#
!
$ %
$$ &
$$$ '
)
+$
*
+$$
''0 /
2% /
- 1
- 1
!!
'&
Development of Phase I of
Bhadla Solar Park
The DPR of Bhadla Solar Park Phase I has been prepared. The total
estimated cost is Rs. 74.86 Crores. The works undertaken are:
Topographical survey and geo-technical test of the identified land.
Solar Park layout, survey & demarcation of the plots.
Construction of Road & Road lighting.
Connectivity & Power Evacuation Infrastructure
Development Charges @ Rs. 6 lacs/hectare has been levied on the
Solar Power Developers and O&M Charges levied are @ Rs. 30,000 /
annum / hectare with escalation of 10% every year.
Seven Solar Power Developers were selected through a competitive
bidding process for establishment of 75 MW PV plants (@Rs. 6.45/kWh).
Two projects of 25 MW (20+5) capacity have been commissioned and
others are likely to be commissioned before 31.03.15.
Development of Phase II of
Bhadla Solar Park
A Draft Report for Phase II has been prepared by ADB consultant. The
preliminary estimated cost for sub-phase 1 is Rs. 450 Cr.
Phase I
Phase II
&
Roads
A road from Kanasar / Nure Ki Burj to Bhadla of about 21 Km has been
constructed.
A 4 Km long 10 m wide main road is under construction in Phase I. Road
Lighting work is also in progress.
Power Evacuation
RVPNL is developing strong power evacuation system comprising of
following:
One 400/220/132/33 kV GSS initially charged on 220kV.
Two 132 kV possible to be upgraded to 220 kV GSS with associated 220
kV lines
Two 220 kV GSS with associated lines.
Land for all GSS has been identified
Water
Water pipeline is under planning
16
" #
"
$ %
&'
(
'