Solar Project
Solar Project
Solar Project
SOLAR PV TECHNOLOGY
This section discusses Pv applications, module technologies, mounting systems,
inverters, monitoring and forecasting techniques. It provides an overview of current
commercially available technologies used in utility scale solar Pv projects. The
purpose is to provide a framework of understanding for developers and investors
before they commit to a specific technology.
Applications of Solar PV
There are four primary applications for Pv power systems:
Off-grid domestic - Providing electricity to households and villages that are not
current (AC) for connection to the utility grid. Many modules in series strings and
parallel strings are connected to the inverters.
further step-up in voltage to reach the AC grid voltage level. The step- up transformer
takes the output from the inverters to the required grid voltage (for example 25 kv, 33
kv, 38 kv, 110 kv depending on the grid connection point and requirements).
The grid connection interface - This is where the electricity is exported into the
grid network. The substation will also have the required grid interface switchgear such
as circuit breakers and disconnects for protection and isolation of the Pv power plant
as well as generation and supply metering equipment. The substation and metering
point are often externalto the Pv power plant boundary and are typically located on the
network operators property.
SITE SELECTION
Selecting a suitable site is a crucial component of developing a viable solar Pv project.
There are no clear cut rules for site selection. viable projects have been developed in
locations that may seem unlikely on first look, such as on high gradient mountain
slopes, within wind farms and on waste disposal sites. In general, the process of site
selection must consider the constraints and the impact they will have on the cost of the
electricity generated. The main constraints that need to be assessed include:
Solar resource.
Local climate.
Available area.
Land use.
Topography.
Geotechnical.
Geopolitical.
Accessibility.
Grid connection.
Module soiling.
Water availability.
Financial incentives.
Showstoppers for developing a utility scale Pv power plant in a specific location
may include constraints due to a low solar resource, low grid capacity or insufficient
area. However, a low solar resource could be offset by high local financial incentives,
making a project viable. A similar balancing act applies to the other constraints. These
are discussed further below.
Area
The area required per kWp of installed power varies with the technology chosen. The
distance between rows of modules (the pitch) required to avoid significant inter-row
shading varies with the site latitude. Sites should be chosen with sufficient area to
allow the required power to be installed without having to reduce the pitch to levels
that cause unacceptable yield loss.depending on the site location (latitude) and the
type of Pv module selected (efficiency), a well-designed Pv power plant with a
capacity of 1 MWp developed in India is estimated to require between one and two
hectares (10,000 to 20,000 m2) of land. A plant using lower efficiency CdTe thin film
modules may require approximately 40 to 50% more space than a plant using polycrystalline modules. Figure 15 shows a large ground mounted plant.
Climate
In addition to a good solar resource, the local climate should not suffer from extremes
of weather that will increase the risk of damage or downtime. Weather events that may
need consideration include:
Flooding - May increase the risk of erosion of support structure and foundations,
Snow - Snow settling on modules can significantly reduce annual energy yield if
mitigating measures are not taken. If the site is prone to snow, then one has to consider
factors such as extra burden on the mounting structures, the loss in energy production
and the additional cost of higher specification
Topography
modules or support structures. The cost of removing the snow needs to be weighed
against the loss in production and the likelihood of further snowfall. The effects of
snow can be mitigated by a design with a high tilt angle and frameless modules. The
design should also ensure that the bottom edge of the module is fixed higher than the
average snow level for the area. A site that has regular coverings of snow for a long
period of time may not be suitable for developing a solar Pv plant.
modifications required to adjust for undulations in the ground. With additional cost
and complexity of installation, mounting structures can be designed for most
locations. In general, the cost of land must be weighed against the cost of designing a
mounting structure and installation time.
Geotechnical
A geotechnical survey of the site is recommended prior to final selection. The purpose
is to assess the ground conditions in order to take the correct design approach, and to
ensure that the mounting structures will have adequate foundations. The level of the
geotechnical survey required will depend on the foundation design that is envisaged.
The soil pH and chemical constituents in order to assess the degree of corrosion
Access
The site should allow access for trucks to deliver plant and construction materials.
This may require upgrading existing roads or building new ones. At a minimum,
access roads should be constructed with a gravel chip finish or similar.
The closer the site is to a main access road, the lower the cost of adding this
infrastructure. Safe packaging of the modules and their susceptibility to damage in
transport must also be carefully considered.
The site should be in a secure location where there is little risk of damage from either
people or wildlife. It should ideally be in a location where security and maintenance
personnel can respond quickly to any issue and this requirement should be stipulated
in the maintenance contract.
Grid Connection
A grid connection of sufficient capacity is required to enable the export of power. The
viability of grid connection will depend on three main factors: capacity, availability
and proximity. These factors should be considered thoroughly at an early stage of a
project; otherwise, the costs could become prohibitive if the site is later found to be in
an unfavourable area for grid connection.
Capacity - The capacity for the grid to accept exported power from a solar plant
will depend on the existing network infrastructure and current use of the system. The
rating of overhead lines, cables and transformers will be an important factor in
assessing the connection capacity available. Switchgear fault levels and protection
settings may also be affected by the connection of a generation plant. In cases where a
network does not have the existing capacity to allow connection, there are two options
available:
1) to reduce peak power export to the allowable limits of the network.
2) to upgrade the network toallow the desired export capacity. network upgrade
requirements will be advised by the network operator. But some aspects of that
upgrade can be carried out by contractors other than the network operator. Initial
investigation into network connection point capacitycan often be carried out by
reviewing published data.
However, discussion with the network operator will berequired to fully establish the
scope of work associated with any capacity upgrades.
Proximity - A major influence on the cost of connecting to the grid will be the
distance from the site to the grid connection point. Sites should be at locations where
the cost of grid connection does not adversely affect project economics. Besides, a
higher connection voltage will entail increased cost of electrical equipment such as
switchgear and transformers, as well as a higher conductor specification. A higher
voltage is also likely to increase the time taken to provide the connection resulting in a
longer development period.
Availability - The grid availability describes the percentage of time that the
network is able to export power from the solar Pv plant. The annual energy yield from
a plant may be significantly reduced if the grid has significant downtime. This may
have adverse effects on the economics of the project.
Availability statistics should be requested from the network operator to establish the
expected downtime of the network. In developed areas, the availability of the grid is
usually very high.
Land Use
Solar Pv power plants will ideally be built on low value land. If the land is not already
owned by the developer, then the cost of purchase or lease needs to be considered. The
developer must purchase the land or rights for the duration of the project. Besides
access to the site, provision of water, electricity supplies and the rights to upgrade
access roads must be considered along with relevant land taxes. Since government
permission will be required to build a solar plant, it is necessary to assess the site in
line with the local conditions imposed by the relevant regulatory bodies. If the land is
currently used for agricultural purposes, then it may need to be re-classified for
industrial use with cost and time implicationsand the possibility of outright
rejection. The future land use of the area must also be taken into account. It is likely
that the plant will be in operation for at least 25 years. As such, extraneous factors
need to be considered to assess the likelihood of their impact on energy yield. For
example, the dust associated with building projects could have significant impact on
the energy yield of the plant. Locating the plant in an environmentally sensitive area
should be avoided. Government stipulated environmental impact assessments or
plant/wildlife studies will slow down and potentially stop the development of a
project.
Any trees on the project site and surrounding land may need to be felled and removed,
with associated cost.
Clearances from the military may be required if the site is in or near a militarysensitive area. Glare from solar modules can affect some military activities.
Module Soiling
If the modules are soiled by particulates, then the efficiency of the solar plant could be
significantly reduced. It is, therefore, important to take into account local weather,
environmental, human and wildlife factors while determining the suitability of a site
for a solar Pv plant. The criteria should include:
dust particles from traffic, building activity, agricultural activity or dust storms.
Module soiling from bird excreta. Areas close to nature reserves, bird breeding
areas and lakes should be carefully assessed. Soiling of modules may require an
appropriate maintenance and cleaning plan at the site location.
Water Availability
Clean, low mineral content water is preferred for cleaning modules. A mains water
supply, ground water, stored water or access to a mobile water tank may be required;
the cost of the various options will have an impact on the project economics. The
degree to which water availability is an issue will depend upon the expected level of
module-soiling, the extent of natural cleaning due to rainfall and the required cleaning
frequency.
Financial Incentives
Financial incentives (such as feed-in tariffs or tax breaks) in different countries, or
regions within countries, have a strong bearing on the financial viability of a project.
Such incentives could outweigh the costs associated with one or more of the site
selection constraints.
3. Modelling the performance of the plant with respect to varying irradiance and
temperature to calculate the energy yield prediction in each time step.
4.
characteristics, the site layout, DC and AC wiring, module degradation, downtime and
soiling characteristics.
5. Applying statistical analysis of resource data and assessing the uncertainty in input
values to derive appropriate levels of uncertainty in the final energy yield prediction.
These steps are described in more detail in the following sections.
Performance Modelling
Sophisticated simulation software is used to predict the performance of a Pv power
plant in time steps for a set of conditions encountered in a typical year. This allows a
detailed simulation of the efficiency with which the plant converts solar irradiance
into AC power and the losses associated with the conversion. Some of these losses
may be calculated within the simulation software, others are based on extrapolations
of data from similar Pv plants and analysis of the site conditions.depending on specific
site characteristics and plant design, losses may be caused by any of the factors
described. Energy yield prediction reports should consider and (ideally) quantify each
of these losses. In individual cases, some of the losses may be negated or considered
in logical groupings.
resource data depending on the quality of the satellite or the distance from a well
maintained MET station. In general, resource data,.
PLANT DESIGN
Designing a megawatt-scale Pv power plant is a complex process that requires
considerable technical experience and knowledge. There are many compromises that
need to be made in order to achieve the optimum balance between performance and
cost. This section highlights some of the key issues that need to be considered when
designing a Pv plant.
Technology Selection
Modules
While certification of a module to IEC/CE/UL standards (as described in Section
2.3.6) is important, it says very little about the performance of the module under field
conditions of varying irradiance and temperature. It is also relatively difficult to find
comprehensive and independent module performance comparisons. In addition,
modules tested under a specific
set of conditions of irradiance, temperature and voltage, with a specific inverter, may
perform very differently under alternative conditions with a different inverter. This
makes choosing a module a more difficult process than it may first appear. Many
developers employ the services of an independent consultant for this reason. When
choosing modules, the following key aspects should be considered:
The aim is to keep the levelised cost of electricity (LCoE) at a minimum. When
choosing between high efficiency-high cost modules and low efficiency- low cost
modules, the cost and availability of land and plant components will have an impact.
High efficiency modules require significantly less land, cabling and support structures
per MWp installed than low efficiency modules.
multi crystalline silicon and The cost per kWh of electricity generated that takes into
account the time value of money thin film amorphous silicon, it should be realised that
each technology has examples of high quality and low quality products from different
manufacturers.
suited for use in certain locations, depending on the local light conditions.
than crystalline silicon modules. Many of them show a better response in low light
levels.
The nominal power of a module is given with a tolerance. Some modules may
be rated with a 5% tolerance while others are given with a 3% tolerance. Some
manufacturers routinely provide modules at the lower end of the tolerance, while
others provide modules that achieve their nominal power or above (positive
tolerance).
modules but care should be taken with the power warranty. Some manufacturers offer
as guarantee of performance the percentage of the peak power for a given duration;
others give it as a percentage of the minimum peak power (that is, the peak power
minus the tolerance).
Frameless modules may be more suitable for locations that experience snow, as
Quality Benchmarks
product guarantee ensuring that modules will be fully functional for a minimum of 2
years. Some companies guarantee a longer period, with 5-6 years being the usual
duration.
grant nominal power guarantees. These vary between manufacturers but a typical
power guarantee stipulates that the modules will deliver 90% of the original nominal
power after 10 years and 80% after 25 years. So far no module manufacturer has
offered a power output guarantee beyond 25 years. The conditions listed in both the
power guarantee and product guarantee are
important, and vary between manufacturers.
Lifetime - Good quality modules with the appropriate IEC certification have a
Manufacturer Xxxx
Module Model
Xxxx
Power tolerance
210 Wp
3%
operating temperature
-40C to +85C
dimensions 148099050 mm
Weight
18 kg
Maximum load
5400 Pa
Product warranty
5 years
Performance guarantee
Inverters
No single inverter concept is best for all situations. In practice, the local conditions
and the system components have to be taken into account to tailor the system for the
specific application. different solar Pv module technologies and layouts may suit
different inverter types. So care needs to be taken in the integration of modules and
inverters to ensure optimum performance and lifetime. Among the major selection
criteria for inverters, the
efficiency are major inverter selection criteria, directly affecting the annual revenue of
the solar Pv plant. It is also important to bear in mind that efficiency varies according
to a number of factors. of them, dC input voltage and percentage load are the two
dominant factors. Several other factors should inform inverter selection, including site
temperature, product reliability, maintainability, serviceability and total cost of
ownership. A thorough financial analysis is required to determine the most costeffective inverter option. Many of the inverter selection criteria listed in Table may
feed into this analysis.
Table Criterion Description
Incentive scheme
Banding of financial incentive mechanisms may have an
influence on the choice of inverter. For example, feed-in tariff
(FiT) schemes might be tiered for different plant sizes which
may, in turn, influence the inverter size.
Project size
Size influences the inverter connection concept. Central
inverters are commonly used in large solar PV plants.
Performance
High efficiency inverters should be sought. The additional
yield usually more than compensates for the higher
initial cost. The way the efficiency has been defined should be
carefully considered.
Consideration must also be given to the fact that efficiency
changes with DC input voltage, percentage of load, and several
other factors.
MPP range A wide MPP range allows flexibility and facilitates design.
3-phase or single phase output
National electrical regulations might set limits on the
maximum power difference between the phases in the case of
an asymmetrical load. For example, this limit is 4.6 kVA in the
German regulations.
Module technology
The compatibility of thin-film modules with transformer-less
inverters should be confirmed with manufacturers.
General Layout
Minimising cable runs and associated electrical losses may suggest positioning an
Lv/Mv station centrally within the plant. If this option is chosen, then adequate space
should be allocated to avoid the possibility of the station shading modules behind it.
The layout should allow adequate distance from the perimeter fence to prevent
shading. It should also incorporate access routes for maintenance staff and vehicles at
appropriate intervals.
Tilt Angle
Every location will have an optimal tilt angle that maximises the total annual
irradiation (averaged over the whole year) on the plane of the collector. For fixed tilt
grid connected power plants, the theoretical optimum tilt angle may be calculated
from the latitude of the site. However, adjustments may need to be made to account
for:
Soiling - Higher tilt angles have lower soiling losses.The natural flow of rainwater
cleans such modules more effectively and snow slides off more easily at higher
angles.
Shading - More highly tilted modules provide more shading on modules behind
them. As shading impacts energy yield much more than may be expected simply by
calculating the proportion of the module shaded, a good option (other than spacing the
rows more widely apart) is to reduce the tilt angle. It is usually better to use a lesser
tilt angle as a trade-off for loss in energy yield due to inter-row shading.
Inter-Row Spacing
The choice of row spacing is a compromise chosen to reduce inter-row shading while
keeping the area of the PV plant within reasonable limits, reducing cable runs and
keeping ohmic losses within acceptable limits. Inter-row shading can never be reduced
to zero: at the beginning and end of the day the shadow lengths are extremely long.
Figure 18 illustrates the angles that must be considered in the design process.
PV Array Design
The
design
of
Pv
array
will
depend
on
the
inverter
specifications and the chosen system architecture besides the specific context and
conditions of use. Using many modules in series in high voltage arrays minimises
ohmic losses. However, safety requirements, inverter voltage limits and national
regulations also need to be considered.
Maximum number of modules in a string -The maximum number of modules in a
string is defined by the maximum dC input voltage of theinverter to which the string
will be connected to (vMax
(Inv, dC)
exceeded. Crossing the limit can decrease the inverters operational lifetime or render
the device inoperable. The highest module voltage that can occur in operation is the
open-circuit voltage in the coldest daytime temperatures at the site location. design
rules of thumb for Europe use - 10C as the minimum design temperature, but this
may vary according to location. The maximum number of modules in a string (n Max)
may therefore be calculated using the formula: VOC(Module)@Coldest Module Operating TemperatureNMax
<VMax(Inv, DC)
governed by the requirement to keep the system voltage within the MPPT range of the
inverter. If the string voltage drops below the minimum MPP inverter voltage, then the
system will underperform. In the worst case, the inverter may shut down. The lowest
expected module voltage occurs during the highest operating temperature conditions.
design rules of thumb for Europe use 70C as the design benchmark, but this may
vary according to site conditions. The minimum number of modules in a string (n Min)
may therefore be calculated using the formula:
voltage, it is preferable to optimise the design by matching the array perating voltage
and inverter optimum voltage as closely as possible. This will require voltage
dependency
graphs
in
19).
Figure
inverter
of
If
inverter
such
efficiency
graphs
manufacturers,
they
are
(see
not
may
example
provided
be
by
obtained
from independent sources. Substantial increases in the plant yield can be achieved by
successfully matching the operating voltages of the Pv array with the inverter.
Number of strings - The maximum number of strings permitted in a Pv array is a
function of the maximum allowable Pv array current and the maximum inverter
current. In general, this limit should not be exceeded as it leads to premature inverter
ageing and yield loss.
Inverter Sizing
It
is
strategy
not
possible
that
applies
to
formulate
in
all
an
cases.
optimal
Project
inverter
specifics
sizing
such
as
the
solar resource and module tilt angle play a very important role when choosing a
design.
been
to
this
is
option
to
While
use
not
always
might
lead
curtail
(based
an
on
compliance
power
the
rule
of
inverter-to-array
the
to
best
a
spikes
one
hour
data).
in
cases
where
power
design
situation
not
thumb
ratio
approach.
where
anticipated
or, it
could
reactive
fail
power
the
by
to
has
less
For
than
unity,
example,
this
inverter
manages
irradiance
profiles
achieve
injection
to
grid
code
the
grid
is required.
The optimal sizing is, therefore, dependent on the specifics of the plant design. Most
plants will have an inverter sizing range within the limits defined by:
0.8<Power ratio<1.2
Where:
PInverter DC rated
Guidance on inverter and PV array sizing can be obtained
from the inverter manufacturers, who offer system sizing software. Such tools also
provide an indication of the total number of inverters required.
A number of factors and guidelines must be assessed when sizing an inverter:
The maximum voC in the coldest daytime Temperature must be less than the
The inverter must be able to safely withstand the maximum array current.
The minimum voC in the hottest daytime temperature must be greater than the
dC Turn-off
).
The maximum inverter dC current must be greater than the Pv array(s) current.
The inverter MPP range must include Pv array MPP points at different
temperatures.
When installed, some thin film modules produce a voltage greater than the
nominal voltage. This happens for a period of time until initial degradation has
occurred, and must be taken into account to prevent the inverter from being damaged.
PV Peak
Pinverter AC rated
n100%
that
the
inverter
efficiency
is
dependent
on
voltage.
Specification sheets and voltage dependency graphs are required for efficient voltagematching.
The
selection
should
and
take
sizing
for
Pv
plants
and
regulations
each
country.
Cables
specifically
designed
for
(solar
cables)
are
available
and
general,
three
installations
used.
In
codes
solar
national
solar
be
cables
account
to
should
dC
into
applicable
Pv
of
criteria
readily
must
be
observed
services
and/or
harmonic
Infrastructures
A utility scale Pv power plant requires infrastructure appropriate to the specifics of the
design chosen. Locations should be selected in places where buildings will not cast
unnecessary shading on the Pv module. It may be possible to locate buildings on the
northern edge of the plant to reduce shading, or to locate them centrally if appropriate
buffer
zones are allowed for. depending on the size of the plant, infrastructure requirements
may include:
Office - A portable office and sanitary room with communication devices. This
must be watertight and prevent entry to insects. It should be located to allow easy
vehicular access.
LV/MV station - Inverters may either be placed amongst the module support
Communications - The plant monitoring system and the security system will
require a
communications medium with remote access for visibility and control of the plant.
There can also be a requirement from the grid network operator for specific telephone
landlines for the grid connection. often, an Internet broadband (dSL) or satellite
communications system is used for remote access. A GSM (Global System for Mobile
Communications) connection or standard telephone line with modems is an alternative
though it has a lower data transfer rate.
other issues to consider when designing and specifying a transformer may also
include:
Tap setting requirements.
Cooling medium.
Earthing.
Winding connections.
number of windings.
requirement for redundancy/spare transformer. Losses.
Bushings for connection of cabling and overhead lines.
Transformer trip and warning alarms.
Choosing a reputable manufacturer to carry out the detailed design and manufacture
should ensure that the transformer provided is of the required standard. There are, of
course,
many other parameters and design considerations that could be specified.
Losses
Transformers
can
lose
energy
through
magnetising current in the core, known as iron losses and copper losses in the
windings. Minimising the losses in a transformer is a key requirement as this will
increase the energy supplied to the grid and, as a result, enhance the revenue of a solar
power plant.
Test Requirements - Transformers should be subject to a number of routine and type
tests performed on each model manufactured; these tests are set out in IEC 60076. The
Manufacturer also can be requested to undertake special tests mentioned in IEC
60076.
Forecasting Technology
dispatchable
power
forecast
the
to
plants
network
typically
operator.
need
This
to
helps
provide
to
fix
a
plant
algorithms
regional
typically
forecasts
and
take
break
three-hour
them
down
to
national
30
and/or
minute
local
forecast
production
power
and
production.
actual
weather
Comparison
can
also
of
historical
allow
learning
products
available
in
the
market
today.
But
Conclusions
The performance of a Pv power plant may be optimised by reducing the system losses.
reducing the total loss increases the annual energy yield and hence the revenue,
though in some cases it may increase the cost of the plant. In addition, efforts to
reduce one type of loss may conflict with efforts to reduce losses of a different type. It
is the skill of the plant designer to make compromises that result in a plant with a high
performance at a reasonable cost. For plant design, there are some general rules of
thumb. But specifics of project locationssuch as irradiation conditions, temperature,
sun angles and shadingshould be taken into account in order to achieve the
optimum balance between annual energy yield and economic return.
The solar PV modules are typically the most valuable and portable components of a
Pv power plant. Safety
Precautions may include anti-theft bolts, anti-theft synthetic resins, CCTv cameras
with alarms and security fencing.
The risk of technical performance issues may be mitigated by carrying out a thorough
technical due diligence exercise in which the final design documentation from the
EPC contractor is scrutinized
PHOTOS